Worksheet 6 – Calculate maximum flow rate based on plant design and surface loading Complete the following details: Name Name of Instructor Instructions To record your answers for the activities and tasks, you will need to: 1) click in the text boxes 2) type your response When you close the document you will be prompted to save your changes. Save the document to your computer hard drive or a removable storage device such as a USB drive. When finished, print it and keep it with the other forms and records. You may be required to submit this document as part of your evidence of learning for this task. Please check with your instructor or team leader. 1. Calculate the maximum flow rate of a rectangular sedimentation tank (30m long x 10m wide x 4m deep) designed with a maximum surface loading of 50kL per day per m2. 2. Calculate the maximum flow rate of the tank in Question 1 if the design surface loading is only 25kL per day per m2. 3. Calculate the maximum flow rate of a treatment plant with four rectangular sedimentation tanks (30m long x 10m wide x 4m deep) if the design surface loading is 50kL per day per m2, for each tank: a. in kL per day b. in mL per day c. in m3 per second Worksheet 7 – Calculate maximum flow rate based on plant design and surface loading Page 1 of 2 Answers 1. 15,000kL per day (15 mL per day) 2. 7,500kL per day (7.5mL per day) 3. a. 15,000kL per day x 4 = 60,000 kL per day b. 60mL per day c. 0.694m3 per second Worksheet 7 – Calculate maximum flow rate based on plant design and surface loading Page 2 of 2