New Reference Trajectory and Upcoming Events C. J. Hansen 12 July 2006 Tour Status • We just passed the 2-year halfway point of the tour • S21 Sequence is executing, Rev 25 (39.2 d equatorial orbit) • The s/c is starting the series of 180 transfer orbits – 22 July 2006 to 30 June 2007 – Rev 26 to Rev 47 • DSS 63 is down for the remainder of the year due to elevation bearing failure – Expect sequence rework 180 Transfer Orbits Reference Trajectory Changes Titan Flybys in Remainder of 2006 T16 22 July 950 km Radar, UVIS stellar occ T17 7 Sept. 1000 ORS, INMS T18 23 Sept. 960 INMS T19 9 Oct. 980 Radar T20 25 Oct. 1030 Selected to be VIMS T21 12 Dec. 1000 UVIS, INMS, Radar T22 28 Dec. 1000 RSS Gravity Upcoming Icy Satellite Flybys Rev 28 9 Sept. Enceladus 40,092 km Rev 32 9 Nov. Enceladus 94,658 km Rev 33 21 Nov. Dione 72,853 km