Yonge Subway Extension – Finch Station to Richmond Hill Centre

advertisement
Yonge Subway Extension – Finch Station to Richmond Hill Centre
Transit Project Assessment
Environmental Project Report
Summary of Changes
Page
Section
Original EPR Text
Environmental Project Report
104
4.1.4.4
This entrance would require the full
acquisition of the existing strip mall,
allowing for the entrance and the
required substation to be integrated
into the redevelopment of the site.
107
Exhibit 4-12
N/A
110
Exhibit 4-14
Revised EPR Text
Only partial acquisition of the property
has been identified at this time for the
entrance and the required substation to
be integrated into the redevelopment of
the site.
Revised by adding the following
notation:
The proponents will continue to work
with all affected stakeholders during
detail design to refine the northern limit
of the station box and location of station
facilities.
Revised by adding the following
notation:
N/A
135
5.2.1.7
The corridor is mostly urbanized and
there are generally limited
opportunities to provide storm water
management for runoff associated
with the Transit Project.
143
5.2.2.1.4
Exhibit 5-6
144
5.2.2.1.6
Physical Address: 8100 Yonge Street
Full Taking: Entrance / Substation
Partial Taking: N/A
The Ladies’ Golf Club will be
provided with a permanent access of
similar characteristics to the existing
access approximately 20 metres south
of the proposed East Don River
bridge.
May 1, 2009
The proponents will continue to work
with all affected stakeholders during
detail design to refine the northern limit
of the station box and location of station
facilities.
The corridor is mostly urbanized and
there are generally limited opportunities
to provide storm water management for
runoff associated with the Transit
Project. It may not be possible to meet
level 1 quality treatment as defined in
MOE’s Stormwater Management
Planning and Design Manual at all
locations (i.e. station locations) although
MOE has indicated it believes that the
implementing the best measures that are
feasible in such locations is satisfactory.
Physical Address: 8100 Yonge Street
Full Taking: N/A
Partial Taking: Entrance / Substation
The Ladies’ Golf Club will be provided
with a permanent access of similar
characteristics to the existing access
approximately 20 metres south of the
proposed East Don River Bridge.
Furthermore, it is anticipated that the
proposed East Don River crossing will
affect an existing pedestrian access to
Cricklewood Park off the east side of
Yonge Street. The park is situated north
of the Toronto Ladies’s Golf Club
fronting Yonge Street. To mitigate the
effect, the bridge will be designed such
that pedestrian access to the park off
Yonge Street will be provided.
Page 1
Yonge Subway Extension – Finch Station to Richmond Hill Centre
Transit Project Assessment
Page
148
Section
5.2.3.1
Original EPR Text
Under Royal Orchard Station (first
three bullets):
•
159
5.3.1.2
…the need for this will be
determined during detailed
design, based on the specific
impact and in consultation with
the City of Vaughan
Under Mitigation Measures (8th
bullet):
Environmental Project Report
Revised EPR Text
Under Royal Orchard Station (first three
bullets):
…the need for this will be
determined during detailed design,
based on the specific impact and in
consultation with the City of
Vaughan, their respective
municipal heritage committee, the
OHT, ORC and the Ministry of
Culture.
Under Mitigation Measures (8th bullet):
•
…only native species
representative of the local area and
valley habitats will be used and
measures necessary to address
invasive species both during and
after construction will be
implemented.
Permit to Take Water from the Ministry
of the Environment is required if
dewatering or diversion of flow from
any of the watercourses by means of
active pumping in exceedance of 50,000
litres per day will result from
construction activities;
Add the following bullet (Bullet #10):
•
•
…only native species
representative of the local area
and valley habitats will be used.
199
6.1 (3)
Permit to Take Water from the
Ministry of the Environment if
dewatering exceeds 50,000 litres per
day.
203
6.11
N/A
Carrying out a HIA for 7780 Yonge
Street (Robert West House) early in
the Detail Design process to
mitigate the potential indirect
impacts associated with the Transit
Project;
York Region, TTC and City of Toronto
will conduct a noise and vibration study,
in accordance with the MOE / TTC
Protocol For Noise and Vibration
Assessment For the Proposed YongeSpadina Subway Loop, June 16, 1993.
•
204
6.13
Appendix A
Figures 11, 12,
19, and 20
York Region, TTC and City of
Toronto will conduct a noise and
vibration study, in accordance with
the protocols established with the
Ministry of the Environment
N/A
Revised by adding the following
notation:
The proponents will continue to work
with all affected stakeholders during
detail design to refine the northern limit
of the station box and location of station
facilities.
Appendix C
7
4
The vertical profile of the bridge
indicated in Figure 4-1 will be
illustrated in more detail once
conceptual design principles have
May 1, 2009
The bridge crossing, as proposed, meets
the Toronto and Region Conservation
Authority’s hydraulic, terrestrial, and
fluvial design requirements. The
Page 2
Yonge Subway Extension – Finch Station to Richmond Hill Centre
Transit Project Assessment
Environmental Project Report
Page
Section
Original EPR Text
been developed for this potentially
significant community feature.
Revised EPR Text
vertical profile of the bridge indicated in
Figure 4-1 will be illustrated in more
detail once conceptual design principles
have been developed for this potentially
significant community feature.
Appendix E
Appendix A
Criteria ‘D1’
N/A
Adding the following noise and
vibration indicator in Header D of the
table titled ‘Analysis and Evaluation of
Steeles Station Options’, in Appendix A
of Appendix E – Station Layout
Concepts:
Appendix B
Appendix B
Title of the table in Appendix B of
Appendix E – Station Layout
Concepts:
Criteria ‘D1’
Appendix B
Appendix G
7
6.1
‘Analysis and Evaluation of Steeles
Station Options.’
N/A
Indicator: D 1.2) Noise and Vibration
Effects
Measure: Opportunity to minimize
noise and vibration effects
Option 1: ‘Least’
Option 2: ‘Least’
Option 3a: ‘Most’
Option 3b: ‘Most’
Option 4: ‘Medium’
Revised by re-titling the table in
Appendix B of Appendix E – Station
Layout Concepts:
‘Analysis and Evaluation of Richmond
Hill Centre Station Options.’
Adding the following noise and
vibration indicator in Header D of the
table titled ‘Analysis and Evaluation of
Richmond Hill Centre Station Options’,
in Appendix A of Appendix E – Station
Layout Concepts:
Headings in the analysis and
evaluation ‘Summary’ table:
Indicator: D 1.2) Noise and Vibration
Effects
Measure: Opportunity to minimize
noise and vibration effects
Option 1: ‘All alternatives yield similar
results’
Option 2: ‘All alternatives yield similar
results’
Headings in the analysis and evaluation
‘Summary’ table:
Option 3 – Surface Alignment C
Option 4 – Stacked Alignment C
Option 1 – Surface Alignment C
Option 2 – Stacked Alignment C
It should be noted that the Yonge
Street corridor is mostly urbanized
and there are generally limited
opportunities to provide storm water
management for the Yonge
Street/subway runoff. In addition,
only a small section of the overall
It should be noted that the Yonge Street
Corridor is mostly urbanized and there
are generally limited opportunities to
provide storm water management for the
Yonge Street/subway runoff so the
proposed Stormwater Management Plan
may not achieve level 1 quality
May 1, 2009
Page 3
Yonge Subway Extension – Finch Station to Richmond Hill Centre
Transit Project Assessment
Environmental Project Report
Page
Section
Original EPR Text
corridor currently outlets to a storm
water management facility.
8
6.2.1, 6.2.2
8
6.2.3
The road way drains from north to
south and the area is completely
urbanized. There are no opportunities
for grassed swales or wet ponds
within or adjacent to the right-of-way.
There are three low spots within this
stretch of Yonge Street and the
Yonge Street storm sewers connect to
sewers on the cross roads. The area is
completely urbanized and there are no
opportunities for grassed swales or
wet ponds within or adjacent to the
right-of-way.
Revised EPR Text
treatment as defined in MOE’s
Stormwater Management Planning and
Design Manual at all locations (i.e.
station locations) although MOE has
indicated it believes that the
implementing the best measures that are
feasible in such locations is satisfactory.
In addition, only a small section of the
overall corridor currently outlets to a
storm water management facility.
The road way drains from north to south
and the area is completely urbanized.
There are no opportunities for grassed
swales or wet ponds within or adjacent
to the right-of-way.
There are three low spots within this
stretch of Yonge Street and the Yonge
Street storm sewers connect to sewers
on the cross roads. The area is
completely urbanized and there are no
opportunities for grassed swales or wet
ponds within or adjacent to the right-ofway.
R3, R3, R2
Paragraph below Table F on Page 170
of Appendix K:
R34, R35, R20
Paragraph below Table F on Page 170 of
Appendix K:
These levels are higher than the
MOE/TTC Protocol criteria and are
expected to be noticeably higher than
traffic noise on Yonge Street
especially for the golf course as
traffic noise on Yonge Street will be
lower due to its lower grade
elevations. At night, public
perception is also expected to be
significant when vehicular traffic
noise is reduced.
The above listed sound levels are higher
than the MOE/TTC Protocol criteria
(with the exception of the Totally
Enclosed Viaduct option where
compliance is predicted within the
applicable criteria) and are expected to
be noticeably higher than traffic noise
on Yonge Street especially for the golf
course as traffic noise on Yonge Street
will be lower due to its lower grade
elevations. At night, public perception is
also expected to be significant when
vehicular traffic noise is reduced.
Last sentence on Page 171:
Appendix K
Figure 5.4
170
171
Figures
Impact
Assessment
Impact
Assessment
Last sentence on Page 171:
Based on the findings of this study, it
is recommended that the necessary
noise/vibration control measures be
considered, the details of which
should be evaluated during the detail
design stage.
May 1, 2009
Based on the findings of this study, the
necessary noise/vibration control
measures that are technologically,
economically and administratively
feasible will be implemented so that
noise and vibration will satisfy the
MOE/TTC Protocol for Noise and
Vibration Assessment for the Proposed
Yonge –Spadina Subway Loop, June 16,
1993, the details of which would be
evaluated at the detail design stage and
submitted to MOE for review.
Page 4
Download