COLLEGE OF THE REDWOODS WATER TANKS AND TRANSMISSION MAIN BENEFITS

advertisement
COLLEGE OF THE REDWOODS
WATER TANKS AND TRANSMISSION MAIN
Utility Infrastructure Replacement / Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Improved water system reliability
•
Reduced tank maintenance
•
Designed to modern seismic standards
•
Improved system monitoring and operations capabilities
•
New more robust transmission main to campus
PROJECT DESCRIPTION
The project proposes to replace the two aging unrestrained redwood water tanks with two new steel water
tanks of similar total size. The new water tanks will be built to modern seismic standards including the
foundation and tank anchorage systems. The existing water transmission main between the water tanks and
the campus water distribution system will also be replaced to improve reliability of the transmission main
supplying campus. The monitoring and control system will be upgraded to provide greater operational
capabilities.
SCHEDULING
Academic Calei
Proposed Construction I
ACADEMIC IMPACTS
Classrooms
None anticipated
Traffic
Traffic control and detours will be required on campus and along Tompkins Hill Road
between the North Entrance and the Applied Technology building
Parking
Parking availability will be reduced in some areas during traffic detours
COLLEGE OF THE REDWOODS
WASTEWATER TREATMENT AND DISPOSAL SYSTEM
UtHity Infrastructure Replacement I Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Reduced permitting requirements and permit compliance costs
•
Reduced operations and maintenance costs
•
Greater robustness and ability to handle flow and load variations
•
Reduced system complexity and less mechanical equipment
Reduced electricity consumption
•
Designed to modern seismic standards
PROJECT DESCRIPTION
The project proposes to replace the existing wastewater treatment plant and method of effluent disposal. The
existing complex mechanical treatment plant currently discharges treated effluent to a creek that drains to
Humboldt Bay and is subject to stringent regulatory requirements. The proposed new treatment plant will
include an effluent pipeline along Tompkins Hill Road, a large enclosed settling and treatment tank,
recirculating gravel filters, a pump station, and a new subsurface leach field located behind the stadium.
SCHEDULING
ACADEMIC IMPACTS
Class rooms
None anticipated
Traffic
Traffic control will be required along Tompkins Hill Road
Parking
None anticipated
COLLEGE OF THE REDWOODS
BUILDING INFRASTRUCTURE AND SITE UTILITIES
Utility Infrastructure Replacement I Seismic Strengthening Project
BENEFITS
•
•
•
•
•
•
•
•
•
Improved water system reliability through development of a robust pipe network with additional
transmission mains and isolation valves
Improved natural gas system reliability through replacement of aging campus distribution lines
Improved conduit routing for telecommunications upgrades providing flexibility and capacity for current and
future improvements
New main electrical switchgear building providing greater reliability and capacity
Reduced maintenance costs associated with repairs for water and sewer systems
Reduced stormwater inflow and infiltration to sewer system
Reduced flooding during storm events at campus entrances
Improved reliability & maintainability of campus power distribution system
Components designed to modern seismic standards and considering known geologic hazards
PROJECT DESCRIPTION
The project proposes to replace and/or improve selected “wet” and “dry” utilities throughout campus. The
“wet” utility replacement plan includes portions of the aging water distribution system, sanitary sewer system,
and the natural gas distribution system. In addition, minor stormwater drainage improvements will be made at
key locations of campus. The proposed “dry” utility plan includes replacement of the 1 2-ky electrical
switchgear, various substation transformers and legacy cabling throughout the campus. The replacements will
consider known geologic hazards to reduce system vulnerabilities.
SCHEDULING
2016
-~
L~
~
a
2017
>c
-~
bOQ4~
~
•
Q
._~_>.
Z
O
.!~
~
2018
C
.~
.~
.~
3~ ~
z
Academic Calendar
Proposed Construction
o ~o~)
_________
ACADEMIC IMPACTS
Classrooms
Coordination required for connections of new utilities to existing buildings.
Traffic
Traffic control and detours will be required throughout campus as construction progresses.
Parking
Parking areas will be temporarily modified to accommodate construction.
COLLEGE OF THE REDWOODS
CAMPUS M[RO~G~T’ MANAGEMENT SYSTEM
Utility Infrastructure Replacement / Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Improve maintenance staff efficiency
•
Reduce overall HVAC maintenance costs
•
Reduce HVAC energy usage at the Administrative of Justice (AJ) building
Improve HVAC operations at the AJ building
PROJECT DESCRIPTION
The project proposes to provide a new campus energy management system (EMS) server, connect existing
building EMS main control panels to the new server, and provide a new EMS in the AJ building. The existing
building EMS main control panels are located in the Creative Arts (boiler system only), Waste Water Treatment
Plant, Pump House, Science, Learning Resource Center, Student Services/Administration, Boiler/Chiller Utility,
and the Child Development Center buildings. Communication will be via the campus Ethernet.
SCHEDULING
2016
C
-~
.~
~
~
a
2017
—
~
.~
.~
°-
<
t ~
z
0
~
~
-~
~-
~
a
<
~
~
2018
~
~
Academic Calendar
Proposed Construction
ACADEMIC IMPACTS
Classrooms
Minor disruption in the AJ building.
Traffic
None anticipated.
Parking
Minor reduction due to construction workers present.
zC
C
-~
~~
a
~- .~
C
~
—
-~
<
~.
U
Q
- Z
>
0
COLLEGE OF THE REDWOODS
IT SERVER ROOM
Utility Infrastructure Replacement I Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Generator backup power for the campus main server room
•
Addition of power panel in the campus main server room to facilitate additional server and telecom rack
equipment.
•
Reduced chance of accidental sprinkler system discharge in the campus main server room
PROJECT DESCRIPTION
This project proposes to install a standby generator system to provide backup power to the campus main
server room located in the Learning Resource Center (LRC). In addition, the existing fire sprinkler system in
the main server room will be retrofitted with a pre-action fire suppression system to reduce the chance of an
accidental sprinkler discharge which would damage IT equipment.
SCHEDULING
2016
I
JS~
-~
L~
~~
-~
.~
2017
DO a.
>
Dw000)
<
0 Z 0
-~
-o
L~
~
~
c
-~
-~
2018
<
>
0
~
0 Z
0~-~
~
~
-~
—
-~
DO
<
>
‘) Z
0
0
Academic Calendar
Proposed Construction
ACADEMIC IMPACTS
Classrooms
None anticipated
Traffic
None anticipated
Parking
Parking availability to the North-East of the Learning Resources Center will be impacted
during a portion of the construction period.
ç~ I
a1
COLLEGE OF THE REDWOODS
CAMPUS FIRE ALARM SYSTEM
Utility Infrastructure Replacement I Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Replaces obsolete fire alarm equipment with a new Code compliant system.
•
Improved audible\visual alarm signaling capabilities including ADA mandated visual notification coverage
for hearing impaired.
•
Allows for comprehensive central monitoring and control of fire alarm system detection and alarm devices
throughout the campus. The central monitoring station (command post) can be relocated anywhere on the
fire alarm network as desired.
•
Allows consolidation of multiple accounts to the outside monitoring service company, thereby reducing
annual costs.
PROJECT DESCRIPTION
Provide new networked Fire Alarm Control Panels and initiation and annunciation devices throughout at AJ,
AT, DH & MH Dorms, PE & FH, MN & WH, and SU Buildings. Extend and complete the central fire alarm
system network throughout the campus using the existing underground conduit system where possible and
augment with new underground conduit where necessary.
SCHEDULING
2016
~
.D
I_:~ ~
~
~
2017
D.
>
(.~J
~ ~
~
~
~
2018
tC~
,_>.
,~
>
L)
—
.~
.~
,~
<
0
.~
~
—
~
.~
.~
D
<
~
—
U
0
o
>
Academic Calendar
Proposed Construction
ACADEMIC IMPACTS
Classrooms
Installation of conduit and fire alarm devices may result in disruption to some classrooms
during non-class scheduled hours.
Traffic
None Anticipated
Parking
None Anticipated
COLLEGE OF THE REDWOODS
APPLIED TECHNOLOGY BUILDING RETROFIT
Utility Infrastructure Replacement I Seismic Strengthening Project
BENEFITS
The benefits of this project include:
ADA improvements throughout the building including restroom fixtures and door hardware
•
Improve efficiency and reliability of HVAC equipment
•
Seismic upgrades to meet current seismic design standards
•
Repair and replacement of roofing where needed
•
Improve data network speed and reliability throughout the building
•
Updated fire alarm panel and devices
PROJECT DESCRIPTION
The project proposes to upgrade several major building systems within the Applied Technology building.
Seismic upgrades will maintain the overall architectural character of the building. HVAC upgrades include new
heating and ventilation equipment on the roof (including ductwork), a new boiler system, new building heating
hot water distribution, and a new energy management system (EMS). The new EMS will connect to the
campus central EMS server. Electrical upgrades include new data cabling and equipment throughout the
building to replace legacy equipment and infrastructure. Fire alarm system upgrades include a new
addressable fire alarm panel and new notification devices throughout the building.
SCHEDULING
2016
~D
£g
2017
~
~
~
.~
.~
<
o z
~
a
>
~
2018
~
-~
~ ~
~
z
>
.~
<
~
.~
-~
<
oU z0
Academic Calendar
Proposed Construction
ACADEMIC IMPACTS
Class rooms
Classes in the Applied Technology building may be relocated during construction
Traffic
Traffic control and retours will be required between the North Entrance and the Applied
Technology building
Parking
Parking availability will be reduced between the North Entrance and the Applied
Technology building
COLLEGE OF THE REDWOODS
STUDENT UNION BUILDING RETROFIT
Utility Infrastructure Replacement / Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Improve efficiency and reliability of HVAC equipment
•
Seismic upgrades to meet current seismic design standards
•
Updated fire alarm panel and devices
PROJECT DESCRIPTION
The project proposes to upgrade several major building systems within the Student Union building. Seismic
upgrades will maintain the overall architectural character of the building. HVAC upgrades include new heating
and ventilation equipment on the roof (including ductwork) and a new energy management system (EMS). The
new EMS will connect to the campus central EMS server. Fire alarm system upgrades include a new
addressable fire alarm panel and new notification devices throughout the building.
SCHEDULING
IC.D
l~
2016
~ ~
~
Academic Calendar
Proposed Construction
-~
-,
0
Ol~
2017
~
~
.~
2018
~ >
DWUOW
<
~
0
~
D
1-)
>
0
0 Z
__________
~I
_________
ACADEMIC IMPACTS
Class rooms
Classes in the Student Union building may be relocated during construction
Traffic
Traffic control and retours will be required between the North Entrance and the Student
Union building
Parking
Parking availability will be reduced between the North Entrance and the Student Union
building
COLLEGE OF THE REDWOODS
CAMPUS CABLING
Utility Infrastructure Replacement / Seismic Strengthening Project
BENEFITS
The benefits of this project include:
•
Improved reliability and speed for network connections across the campus
•
Upgraded LAN connections at AT, AJ, CA, DH & MH Dorms, and SU Buildings
PROJECT DESCRIPTION
This project proposes to replace legacy campus telecommunication cabling with new copper and fiber optic
cabling to every building on campus.
SCHEDULING
2016
~
~
>
2017
>
‘-‘
.~
,
>
2018
0.
>
‘-‘
>~
0.
>
w
Academic Calendar
Proposed Construction
ACADEMIC IMPACTS
Classrooms
Installation of conduit and data cabling may result in disruption to some classrooms during
non-class scheduled hours.
Traffic
Traffic control and detours will be required throughout campus
Minor delays are anticipated
Parking
Parking availability may be affected during traffic detours
Download