RÉGIE DE L’ÉNERGIE HYDRO-QUÉBEC DISTRIBUTION’S APPLICATION FOR APPROVAL OF TARIFFS EFFECTIVE 2004-2005 PHASE 1: REGULATORY PRINCIPLES AND COST OF SERVICE FILE R-3492-2002 EVIDENCE OF WILLIAM HARPER ECONALYSIS CONSULTING SERVICES ON BEHALF OF: OPTION CONSOMMATEURS JANUARY 8, 2003 Table of Contents 1.0 Background ……………………………………………………………. 1 2.0 Purpose of Evidence …………………………………………………. 3 3.0 Purpose of a Cost Allocation Study ……………………………….. 4 4.0 Hydro Quebec Distribution’s Proposed Cost 5.0 Allocation Methodology ……………………………………………… 6 4.1 Overview…………………………………………………………. 6 4.2 Functionalization ………………………………………………. 8 4.3 Classification and Allocation ………………………………….. 25 Overall Conclusions …………………………………………………. 42 Schedule 1 Demand Allocator Adjustment Based on Minimum System Load Carrying Capability …………………………….. 51 Appendix A – Qualifications and Experience for William Harper Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1.0 Background 2 3 On July 8th, 2002, Hydro-Québec Distribution (HQD) filed its first Application with 4 the Régie de l’énergie (the Régie) regarding approval of its distribution rates. 5 This Application arises as a result of recent changes in both the organizational 6 structure of Hydro-Québec as well as the legislative and regulatory framework in 7 which it operates. 8 9 On June 2nd, 1997, the Act respecting the Régie de l’énergie, which was adopted 10 on December 19th, 1996 by the National Assembly of Québec, came into force. 11 The Régie de l’énergie replaced the former regulatory body, the Régie du gaz 12 naturel, whose jurisdiction was limited to the natural gas sector. The new Régie’s 13 jurisdiction was extended to cover two additional sectors of the energy industry: 14 gasoline retailing and electricity (Hydro-Québec1). 15 16 On June 16th, 2000, the Act respecting the Régie de l’énergie was amended by 17 Bill 116. The effect of Bill 116 was, among other things, to exclude from the 18 Régie’s regulatory oversight the generation function of Hydro-Québec and to 19 create the Heritage Pool for electricity, whereby Hydro-Québec – Production 20 (HQP), the generation arm of Hydro-Québec, assures HQD access to 165 TWh 21 of electricity supply (plus transmission and distribution losses) at an average unit 22 cost of 2.79¢ per kWh. In addition, Appendix I to the 2000 amended Act 23 provided for the unit allocators that were to be used to allocate the Heritage Pool 24 electricity costs to the rate classes for the year 2000. This cost allocation was 25 then to be reviewed and approved by the Régie de l’énergie for the determination 26 of future years’ rates. Consistent with the regulatory changes introduced by Bill 1 At that time the Régie’s jurisdiction covered the generation, transmission and distribution functions of Hydro-Québec. The rates of the Utility were to be cost-based, and approved by the Régie after public hearings such as those that had been standard practice in the natural gas sector for many decades. 1 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 116, in June 2001 Hydro-Québec completed the functional separation of its 2 Production, Transmission and Distribution activities2. 3 4 On April 30th, 2002, the Régie released the decision D-2002-95 in the first 5 transmission tariff application ever filed by Hydro-Québec – TransÉnergie (HQT) 6 (reference R-3401-98). In this decision, the Régie ruled that the transmission 7 cost of service was to be allocated to the Native Load customers (i.e. HQD and 8 its customers) and to the Point-to-Point customers (the largest of which is HQP in 9 its export activities) on the basis of the annual coincident peak demand (1 CP). 10 This decision was on an interim basis, and the Régie directed HQT to come forth 11 in its next tariff application with further studies on a cost allocation model by 12 function. 13 14 On October 21st, 2002, the Régie released decision D-2002-221 in HQD’s 15 Application to determine the allocation of the Heritage Pool costs to the rate 16 classes for the years 2001 and 2002 (reference R-3477-2001). In this decision, 17 the Régie approved the Heritage Pool cost allocation model proposed by HQD. 18 It is understood that this same cost allocation model will be used to allocate the 19 cost of non-Heritage Pool costs to the rate classes when incremental supplies 20 come online as a result of the calls for tenders launched in 2002 going forward. 21 The Régie’s decision D-2002-221 is currently under appeal. 22 23 HQD’s July 8th, 2002 Application represents its first distribution rate application to 24 the Régie, incorporating both the charges it will incur for electricity commodity 25 and transmission service purchases from other business units of Hydro-Québec 26 and its own internal costs. The Application addresses the need for rates 27 approved by the Régie as of 2004-2005, when the current rate freeze expires3. 2 HQD-1, Document 1, page 3. Note : Hydro-Québec had previously unbundled its Transmission activities in 1997. 3 See: DEMANDE RELATIVE À LA DÉTERMINATION DU COÛT DE SERVICE DU DISTRIBUTEUR ET À LA MODIFICATION DES TARIFS D’ÉLECTRICITÉ (PHASE 1), July 5, 2002, page 3, § 9-10. 2 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 2.0 Purpose of Evidence 2 3 In its Application, Hydro-Québec Distribution (HQD) proposed that the Régie 4 undertake its review in two Phases and requested that in Phase 1 the Régie 5 among other things: 6 1. Adopt its proposals with respect to the determination of HQD’s revenue requirement based on a forward test year, 7 8 2. Approve its proposed deemed capital structure, 9 3. Approve its proposed return on equity and overall return on capital, 10 4. Approve its proposed revenue requirement for the 2002-2003 rate year, and 11 12 5. Approve its proposed cost allocation methodology for allocating the revenue requirement to be recovered from rates to customer classes. 13 14 In Phase 2, HQD would present an Application for rates effective April 1, 2004, 15 based on the results of Phase 1. 16 17 On October 9, 2002, the Régie issued an Order (D-2002-208 with respect to R- 18 3492-2002) outlining the schedule for the planned proceeding and identifying the 19 following issues for Phase 1: 20 • General presentation of the case and regulatory principles, 21 • Capital structure and capital cost, 22 • Accounting principles, cost of service and revenue requirement, and 23 • Cost allocation and cross-subsidization between the rate classes. 24 25 After reviewing HQD’s Application and the Procedural Order issued by the Régie, 26 Option Consommateurs (OC) retained Econalysis Consulting Services (ECS), a 27 Canadian consulting firm offering regulatory services to clients in the electricity, 28 natural gas and telecommunications sectors, to provide evidence that would 3 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 assist the Régie in evaluating the issues associated with HQD’s proposed cost 2 allocation methodology. 3 4 The Evidence was prepared by Bill Harper who, prior to joining ECS in July 2001, 5 worked for over 25 years in the energy sector in Ontario, first with the Ontario 6 Ministry of Energy and then, with Ontario Hydro and its successor company 7 Hydro One. Mr. Harper’s areas of expertise and experience include cost 8 allocation/rate design, the regulation of electric distribution utilities and 9 management of utility involvement in regulatory proceedings. He has served as 10 an expert witness in public hearings before the Manitoba Public Utilities Board, 11 the Ontario Energy Board, the Ontario Environmental Assessment Board and a 12 Select Committee of the Ontario Legislature on matters dealing with rates, 13 regulation and demand/supply planning. Mr. Harper also provided comment and 14 expert evidence in the Régie’s proceeding dealing with HQD’s 2002-2011 supply 15 plan4. A full copy of Mr. Harper’s CV is attached in Appendix A. 16 17 The Evidence starts by discussing the purpose of cost of service (or cost 18 allocation) studies, the key steps involved and the principles. This is followed by 19 a review of the cost allocation methodology proposed by HQD. Overall, HQD’s 20 cost allocation methodology is generally consistent with accepted electricity 21 industry practices. However, there are some exceptions and also areas where 22 more documentation and/or analysis are required. These are noted throughout 23 the text and summarized in section 5.0. 24 25 3.0 Purpose of a Cost Allocation Study 26 27 As a guide for determining the appropriate rates to be charged to each class of 28 customers, gas and electric utilities generally perform a cost of service or cost 29 allocation study. A cost allocation study analyzes the components of the 30 Company’s costs and assigns or directly allocates plant investments and other 4 File R-3470-2001 4 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 assets as well as operating expenses among the various customer classes 2 receiving service and, in some instances, among different services offered by the 3 utility. The purpose of the study is to determine both the total and the unit costs 4 of providing service to various customer classes. The results are then used to 5 provide guidance in establishing the rate levels and designing the rate structures 6 for each customer class so as to fairly apportion the total costs between 7 customer classes and provide proper price signals. A cost allocation study can 8 also assist in identifying the costs of providing individual services in those 9 jurisdictions where rates are to be unbundled. 10 11 12 Cost allocation studies generally employ a three-step process of cost analysis: 1) Functionalization of assets and annual expenses (including the cost of 13 capital) according to the services (or functions) the utility provides such as 14 production, transmission, distribution and customer service. However, 15 these functions are frequently broken down further to capture specific 16 activities. 17 2) Classification of each function’s costs according to the system design or 18 operating characteristics that caused those costs to be incurred. In the 19 case of electric utilities, costs are generally classified as one of three 20 types: demand costs incurred to meet a customer’s maximum 21 instantaneous power requirements (i.e., demand or capacity); energy 22 costs incurred to provide customers with electricity over a period of time; 23 and, customer costs incurred to carry customers on the system. 24 3) Allocation of each functionalized and classified cost component to specific 25 customer classes based on each class’ contribution to the specific cost 26 driver selected. 27 28 While the process appears straightforward and logical, the nature of utility 29 operations is characterized by the existence of common or joint use facilities (and 30 activities) that are used to support the provision of more than one product/service 31 and/or serve more than one customer class. As a result, while cost analysts may 5 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 strive to identify and isolate plant and expenses incurred exclusively to serve a 2 specific customer class or group of customers, it is unrealistic to assume that 3 large portions of a utility’s plant investment and expenses can be directly 4 assigned. In addition, there are practical constraints (e.g. time and budgets) that 5 will limit the extent to which costs can be directly tracked and assigned. 6 7 In evaluating any cost allocation study primary consideration should be given to 8 the need to reflect cost causality to the extent possible. In this regard, while 9 industry standards and precedents have been established which can assist cost 10 analysts in performing cost of service studies, recognition must also be given to 11 the specific utility’s circumstances (e.g., its operating characteristics and design). 12 Other considerations include equity, efficiency, stability of results over time, 13 transparency, logical consistency and practical limits of implementation. 14 15 4.0 Hydro-Québec Distribution’s Proposed Cost Allocation Methodology 16 17 4.1 Overview 18 19 HQD’s cost allocation methodology follows the standard three-step process of 20 functionalization, classification and allocation of costs to customer classes. This 21 methodology is applied to both the specific cost components of the annual 22 revenue requirement as well as the rate base, which is used in turn to allocate 23 the proposed cost of capital to customer classes. 24 25 For the 2002-2003 rate year, HQD’s proposed revenue requirement to be 26 recovered from rates is $8,747.0 M and is made up of the following costs5: 27 • Electricity Purchases: $4,229.0 M 28 • Cost of Fuel for Electricity Generation: $ 29 • Transmission Services: $2,312.6 M 24.9 M 5 See HQD-5, Document 1, pages 3-5 and HQD-9, Doc 1, Table 3 (Note: Where differences exist between the two sources due to rounding the values from Table 3 are reported) 6 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 • Gross OM&A6: $ 773.0 M 2 • Capitalized OM&A: $ (250.3) M 3 • Cost of Shared (HQ) Services: $ 415.8 M7 4 • Depreciation and Amortization: $ 416.5 M 5 • Taxes: $ 106.0 M 6 • Corporate (HQ) Overheads: $ 37.5 M8 7 • Services to Other HQ Units: $ (50.2) M9 8 • Other Revenues: $ (63.1) M10 9 • Ice Storm Reimbursement: $ (4.5) M 10 The revenue requirement also includes cost of capital charges of $ 799.7 M11. 11 12 The rate base proposed by HQD for 2002-2003 is $8,063.6 M12 and consists of: • • • 13 14 15 16 • Fixed assets with a net book value of $7,624.2 M, Unamortized expense with a value of $ 100.7 M, Working capital valued at $ 234.0 M, and Inventories valued at $ 104.6 M. 6 Operating, Maintenance and Administration Expense Includes $18.2 M of billings between HQD business units. See HQD-10, Document 8, page 22, Question 15.2. 8 The Corporate overheads included here are for services not directly billed to HQD, but rather allocated. Directly billed services ($42.5 M) are included in the $415.8 M cost of shared services. See HQD-10, Document 8, page 24, Question 19.1. 9 Includes $18.2 M of billings between HQD business units. See HQD-10, Document 8, page 22, Question 15.2. 10 Only includes other non-rate revenues from customers and from third parties (e.g. pole rentals). Other non-rate revenues (e.g. customer contributions) are treated as a cost offset. See HQD-10, Document 8, pages 19-20, Question 14.1. 11 HQD-9, Document 1, page 28, Table 1. 12 HQD-9, Document 1, page 29, Table 2. 7 7 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 4.2 Functionalization 2 3 Functions Employed 4 5 HQD uses the standard Production, Transmission, Distribution and Customer 6 Service functions13 employed by electric utilities. The Distribution and Customer 7 Service functions are then broken down further into a number of sub-functions as 8 follows14: • 9 Distribution: 10 o Distribution Stations and Operating Centres 11 o Medium Voltage Lines 12 o Low Voltage Lines 13 o Connections 14 o Streetlights/Sentinel Lighting • 15 Customer Service: 16 o Customer Care and Accounting 17 o Metering 18 o Sales and Marketing 19 o Other 20 A separate function (and set of similar sub-functions) is used to capture the costs 21 associated with serving Remote Communities. 22 23 Functionalization of HQD’s Revenue Requirement 24 25 o Electricity Purchases, Transmission Services and Fuel for Generation 26 27 The costs of electricity purchases ($4,229.0 M) and transmission services 28 ($2,312.6 M) are functionalized to the Production and Transmission sub- 13 14 HQD-9, Document 1, pages 7-8 HQD-9, Document 1, pages 8-10 8 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 functions respectively15. The cost of fuel for electricity generation ($ 24.9 M) is all 2 associated with the operation of the remote communities and is assigned to the 3 Remote Communities - Production function16. 4 5 o OM&A and Shared Services 6 7 HQD has organized its internal activities and cost reporting such that costs are 8 separated based on the following cost centres17: • 9 Networks – which captures activities associated with managing and 10 maintaining HQD’s distribution assets (including production, transmission 11 and distribution of power in Remote Communities), • 12 Customer Service – which includes activities associated with customer 13 meter reading, billing and accounting as well as customer care (e.g., the 14 call centre) and marketing & sales activities for small and medium power 15 customers, • 16 Large Customer Marketing & Sales – which includes marketing programs and other support activities for large power customers, and 17 • 18 Various HQD Corporate activities including: a) Executive, b) Electricity 19 Supply, c) Regulation and Tariffs, d) Human Resources, and e) 20 International Projects (Note: The costs associated with International 21 projects are not included in the Revenue Requirement). 22 23 Based on this cost centre structure, HQD can directly assign most18 of its OM&A 24 costs (net of capitalized OM&A) to the Distribution and Customer Service 25 functions. Within the Distribution Function, OM&A costs are separated between 26 Remotes and Grid-connected distribution and then the costs are assigned to the 15 See HQD-9, Document 1, Table 3. See HQD-9, Document 1, Table 12. 17 HQD-4, Documents 5 and 5.1 through 5.3. 18 The costs associated with HQD’s Executive and other corporate groups are assigned to the Customer Service-Other sub-function. See HQD-10, Document 8, pages 74-75, Question 32.1. 16 9 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 sub-functions based on the net book value of the assets in each sub-function19. 2 In the case of the Customer Service, HQD indicates that the definitions of the 3 cost centres allow OM&A costs to be directly assigned to the appropriate sub- 4 functions20. 5 6 The cost of shared services (including “billings” between business units of HQD) 7 are assigned to the Distribution and Customer Service functions based on the 8 shared services costs attributable to the cost centres associated with each of the 9 two functions. Within Distribution, the costs of shared services are assigned to 10 the individual sub-functions on the basis of net book value. Within the Customer 11 Service function, the costs of shared services can be directly assigned to the 12 sub-functions, based on usage. As a result, the assignment of shared services 13 costs generally follows the same approach as used for OM&A costs. 14 15 Comments 16 17 HQD’s evidence is that its OM&A costs and costs for shared services can 18 be directly assigned to the relevant functions and, in the case of Customer 19 Service, the relevant sub- functions. However, the cost centre structure 20 for the Customer Service group presented in HQD-4, document 5.2 21 includes a number of cost centres that do not appear to be directly 22 attributable to either the Customer Care & Accounting, Metering or Sales 23 & Marketing sub-functions. Examples of this include: 24 • Bur. dir. Princ. SALC, 25 • Dir. Expertise et support SALC, 26 • Dir. Développement et projets, 27 • Dir. Planification et contrôle, 28 • Dir. Projets Systemes d’inform. Clientèle, and 19 HQD-9, Document 1, page 36, classification factor FC17, column 3 and HQD-10, Document 1, page 122, FC17 20 HQD-10, Document 1, page 122, FC17 10 Evidence of William Harper 1 • Hydro-Québec Distribution Régie File R-3492-2002 Phase I Gestion des actifs. 2 3 To date, there is insufficient documentation on the record to indicate 4 precisely how the OM&A and shared services costs for these activities are 5 allocated. What is required from HQD is a more complete explanation as 6 to: 7 • proposed cost allocation methodology, and 8 9 How the costs of these business units were functionalized in the • What the activities associated with these business units entail and 10 whether any of the costs can be directly assigned to the sub- 11 functions. 12 As they are similar in nature to overhead costs, it is highly likely that some, 13 if not all, of the costs associated with these business units should be 14 allocated across all three sub-functions. 15 16 Another aspect of the allocation of OM&A costs requiring clarification is 17 the determination of the Distribution function costs associated with 18 Remote Communities. It not clear from the documentation provided 19 whether all of the OM&A and shared services costs for the Remote 20 Communities – Distribution function can be directly assigned based on the 21 definitions of the cost centres involved or whether some of the costs have 22 to be “allocated”. Similarly, it is not clear whether the Customer Service – 23 Customer Care and Accounting sub-function costs attributed to Remote 24 Communities were the result of a direct assignment (based on cost 25 centres) or an allocation. 11 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Depreciation and Amortization Expenses 2 3 HQD’s cost of service includes both depreciation expense for assets in-service 4 ($ 409.9 M) and the amortization of costs associated with commercial programs 5 ($ 6.7 M)21. Depreciation expenses are assigned to the Distribution (including 6 Remotes) and Customer Service functions based on the assets associated with 7 the cost centres for each. Within Distribution, depreciation expenses are 8 assigned to the individual sub-functions on the basis of net book value. For 9 Customer Service, the depreciation expense for each of the cost centres is 10 directly assigned to the associated sub-function. The amortization costs 11 associated with commercial programs are assigned directly to the Customer 12 Service-Sales & Marketing sub-function. 13 14 Comments 15 16 The earlier comments regarding the assignment of OM&A and shared 17 services costs associated with various customer service-related cost 18 centres that are not readily attributable to a specific cost allocation sub- 19 function, also apply for any depreciation expense associated with the 20 same cost centres. Again, there is insufficient information on the record to 21 determine if there are any depreciation expenses associated with these 22 cost centres22 and, if so, how they were allocated to the various Customer 23 Service sub-functions. 24 25 While the initial evidence indicated that the amortization charges included 26 in the 2002-2003 cost of service were $6.7 M, the subsequent responses 27 to the information requests indicate that the amortization expense for 21 HQD-5, Document 10, pages 3-4. Again, these cost centres include: a) the Bur. dir. Princ. SALC, b) Dir. Expertise et support SALC, c) Dir. Développement et projets, d) Dir. Planification et contrôle, e) Dir. Projets Systemes d’inform. Clientèle, and f) Gestion des actifs 22 12 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 commercial programs is $ 8.8 M23 and that this expense was allocated to 2 Customer Service-Sales & Marketing ($ 7.8 M) and Production-Remotes 3 ($ 1.0 M). 4 5 o Taxes 6 7 Taxes included in the 2002-2003 cost of service consist of capital taxes ($ 53.3 8 M), gross revenue taxes ($ 39.6 M), municipal and school taxes ($ 13.3 M) and a 9 municipal tax refund ($ 0.2 M) for a total cost of $ 106.0 M24. Capital and 10 revenue taxes are both allocated between Distribution (including Remotes) and 11 Customer Service on the basis of the net book value of the assets associated 12 with each function. The main difference being that the allocation base for capital 13 taxes includes plant under construction, whereas the allocation base for revenue 14 taxes includes only assets in-service25. Within the Distribution function, HQD’s 15 response to OC interrogatory 32.9 indicates that these two tax expenses are 16 allocated between Remote Communities and the grid-connected Distribution 17 Network based on the relative number of cost centres associated with each26. 18 19 For Remote Communities, HQD’s response to OC interrogatory 32.9 indicates 20 that the costs are further split equally among Production, Transmission and 21 Distribution, and then further allocated to sub-functions based on net book 22 value27. The portion of the two taxes attributed to grid-connected distribution is 23 also allocated to individual sub-functions based on net book value. 24 25 In response to OC interrogatory 32.9, HQD does not specify how the allocation of 26 municipal and school taxes between the Distribution and Customer Service 27 functions was established. However, it appears to have been done based on the 23 HQD-10, Document 8, page 35, Table R22.2. HQD-5, Document 11, pages 3-4 and HQD-10, Document 8, page 36, Question 23.2. 25 HQD-5, Document 11, page 3 and HQD-10, Document 8, page 82-83, Question 32.9. 26 HQD-10, Document 8, pages 82-83. 27 HQD-10, Document 8, page 83. 24 13 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 number of cost centres responsible for the expense. The costs attributed to 2 Distribution are allocated between the grid-connected distribution network and 3 Remote Communities based on the number of buildings associated with each, 4 resulting in virtually 100% of the costs being assigned to the grid-connected 5 distribution network28. The costs were then allocated to sub-functions based on 6 net book value29. Municipal and school taxes attributed to customer service cost 7 centres were allocated to the individual Customer Service sub-functions based 8 on the salaries associated with each30. 9 10 Comment 11 12 The functionalization of taxes should reflect the way they are calculated 13 for Hydro-Québec and HQD overall. HQD’s portion of the total capital 14 taxes paid by the integrated Hydro-Québec utility is based on the net book 15 value of all assets, including assets under construction. This allocation 16 base is consistent with the basis on which the overall capital taxes for the 17 utility are determined, which is based on the value of all outstanding debt 18 and equity (including that used to finance assets under construction)31. As 19 a result, allocating between Distribution and Customer Service on the 20 basis of net book value (including assets under construction) is 21 reasonable. 22 23 However, the apparent subsequent split of capital taxes between Remote 24 Communities and the grid-connected distribution network based on 25 relative number of cost centres is not appropriate and leads to a 26 significantly different result than if the allocation was done on the basis of 27 net book value. The HQD approach allocates 13.7%32 of the total capital 28 taxes associated with Distribution to Remote Communities, whereas using 28 HQD-10, Document 8, page 83 and 86, Question 32.9. HQD-10, Document 8, page 83, Question 32.9. 30 HQD-9, Document 1, page 36, FC20 and HQD-10, Document 8, page 83. 31 HQD-10, Document 1, page 73, Question 44.2. 32 HQD-10, Document 8, page 84, Table R32.9-A, column 8. 29 14 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 net book value would allocate roughly 7% of the associated capital taxes 2 to Remotes33. 3 4 There is a further issue with the way in which capital taxes attributed to 5 Remote Communities are allocated to Production, Transmission and 6 Distribution. While over 70% of the net book value of the assets 7 associated with Remote Communities are Production related34, the “equal” 8 allocation to all three functions results in Production attracting only 1/3 of 9 the costs35. 10 11 Net book value (and preferably NBV including assets under construction) 12 should be used to allocate capital taxes between the grid-connected 13 distribution network and Remote Communities and, also, be used 14 subsequently to allocate capital taxes to the various Remote Communities’ 15 sub-functions. 16 17 There is also an issue with the overall approach HQD uses to allocate 18 gross revenue taxes. Gross revenue taxes for Hydro-Québec (overall) are 19 calculated as 3% of total Hydro-Québec revenues (less a small 20 adjustment for revenues paid to other producers in the province)36. As a 21 result, one would expect revenue taxes to be allocated based on each 22 customer class’ contribution to HQD’s distribution revenues. 23 24 However, Hydro-Québec actually allocates gross revenue taxes between 25 its subsidiaries on the basis of net book value, excluding plant under 26 construction37. HQD contends that this is the appropriate way for the 27 costs to be allocated because the gross revenue tax is a tax in-lieu of 33 See HQD-9, document 1, page 29. Remotes NBV/Total NBV = 518.5/7624.2 = 6.8%. The relative NBVs, including assets under construction are not reported. 34 HQD-9, Document 1, page 38, Table 11, row 9. 35 See HQD-10, Document 8, page 87. 36 HQD-10, Document 1, page 58 37 HQD-5, Document 11, page 3 15 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 municipal taxes. Hence, HQD argues that the gross revenue taxes should 2 be allocated the way municipal taxes would have been calculated and 3 allocated38. 4 5 Gross revenue taxes may be levied in-lieu of municipal taxes, however, 6 they should be allocated in a manner that reflects the basis on which they 7 were actually incurred. From a cost-causality perspective, if the key driver 8 or determinant for gross revenue taxes is “revenues” then this is the basis 9 on which they should be allocated to customers. 10 11 Hydro-Québec should be encouraged to alter the way it allocates revenue 12 taxes across its main lines of business so as to reflect the actual basis on 13 which the taxes are calculated. In the meantime, HQD should change its 14 basis for allocating gross revenue taxes such that it reflects the revenues 15 generated by each customer class, net of the cost of electricity supply and 16 transmission services. 17 18 This change would also address the current issues (similar to those that 19 were discussed previously for capital taxes) in the way revenue taxes are 20 allocated between Remote Communities and grid-connected distribution 21 and, then, within Remote Communities between Production, Transmission 22 and Distribution. 23 24 With respect to municipal and school taxes, there is a need for HQD to 25 clarify how the tax expense is allocated between the Distribution and 26 Customer Service functions39. Similarly, the allocation of 100% of the 27 Distribution function’s expense to grid-connected facilities requires further 28 explanation. 38 HQD-10, Document 8, page 93, Question 36.3 and HQD-10, Document 1, page 58, Question 34.2 39 See HQD-10, Document 8, page 86, Table R32.9C. 16 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Corporate Overheads 2 3 The Hydro-Québec corporate overheads allocated to HQD ($ 37.5 M) include a 4 share of the costs of activities for the CEO/Board of Directors, the Auditor 5 General, Research and Strategic Planning, Corporate Affairs, Human Resources, 6 Finance and the Office of the Secretary General40. With the exception of Human 7 Resources, these corporate overheads are allocated to Distribution and 8 Customer Service functions and, subsequently, to the various Customer Service 9 sub-functions on the basis of the total cost of service associated with each 10 function (and sub-function) excluding the costs of electricity and fuel purchases 11 and transmission services. The corporate overhead costs allocated to 12 Distribution are subsequently allocated to the individual sub-functions on the 13 basis of net book value. Corporate costs for human resources are allocated 14 based on the salary costs assigned to each function and sub-function41. This 15 approach mirrors the methodology HQD proposes to use to allocate corporate 16 overheads between Hydro Quebec’s major business units42. 17 18 o Other Revenues 19 20 Revenues received for shared services provided to other Hydro-Québec 21 business units (e.g. TransÉnergie and Hydro-Québec Production) and to other 22 business units within HQD are allocated to Distribution and Customer Service 23 based on the organizational units (cost centres) providing the services43. Within 24 Distribution, the revenues are allocated to individual sub-functions on the basis of 25 net book value. Within the Customer Service function, the revenues are 26 assigned to the various sub-functions based on the cost centres that generated 27 the revenue44. 40 HQD-4, Document 7, page 8 HQD-9, Document 1, page 17 and page 36, Table 9, FC21. 42 HQD-4, Document 7. 43 HQD-10, Document 1, page 122, FC17 and HQD-10, Document 8, page 81-82. 44 HQD-10, Document 8, page 93, Question 36.1. 41 17 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 External revenues received from customers in the form of administration fees 2 and account-opening fees are assigned to the Customer Service - Other sub- 3 function. Other sources of external revenues are functionalized as follows: • 4 Revenues received from third parties for pole rentals are allocated to the 5 Distribution sub-functions associated with medium and low voltage lines 6 on the basis on net book value of overhead line assets45, • 7 Revenues from service agreements with other distributors are allocated to the Distribution sub-functions on the basis of net book value46, and 8 • 9 Connection fees are assigned directly to the Distribution - Connections sub-function47. 10 11 12 Revenue received from the Quebec government as compensation for the 1998 13 ice storm ($ 4.5 M) is allocated to the Distribution sub-functions associated with 14 the affected grid-connected assets on the basis of net book value48. 15 16 o Cost of Capital 17 18 HQD’s cost of capital is allocated to customers by applying the proposed rate of 19 return (9.917%) to the rate base allocated to each customer class49. 20 21 Functionalization of HQD’s Rate Base 22 23 o Fixed Assets 24 25 The bulk of HQD’s fixed assets consist of facilities and equipment that can be 26 directly assigned to the Distribution or Customer Service functions. Assets that 45 HQD-10, Document 1, pages 123-124, FC22. HQD-10, Document 1, pages 123-124, FC 22. 47 HQD-10, Document 1, page 123, FC22 and HQD-10, Document 8, pages 75-76, Question 32.2. 48 HQD-10, Document 8, page 122, FC17. 49 HQD-9, Document 1, page 28, Table 1, column 3. 46 18 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 fall into this category include meters, distribution stations, operating centres, 2 overhead lines, underground lines, transformers, street lighting facilities and 3 remote community facilities. 4 5 The main issues associated with the functionalization of fixed assets are: a) The allocation of the fixed assets associated with Distribution to the 6 7 individual sub-functions – as HQD’s accounts are not maintained in a form 8 (i.e. by voltage) that allows the costs to be directly assigned50, and b) The allocation of general plant (“Actifs de soutien”) to functions and sub- 9 functions. 10 11 12 HQD uses the results of its minimum system analysis51 to determine the net book 13 value of the distribution assets associated with the Medium Voltage, Low Voltage 14 and Connections (“Branchements”) sub-functions. 15 16 In the case of general plant, HQD functionally separated the related assets 17 associated with the major cost centres, i.e., Networks, Customer Service and 18 Large Customer Marketing & Sales as part of the overall business unit separation 19 undertaken by Hydro Quebec in 199852. In the case of Networks-related General 20 Plant, a further separation is available as to the plant associated with Remote 21 Communities and that associated with the grid-connected network. The costs 22 associated with the grid-connected Distribution function are then allocated to the 23 sub-functions based on net book value. The costs associated with Remote 24 Communities and the Customer Service cost centres are allocated to sub- 25 functions based on an analysis of assets as of December 31, 200153. Finally, the 50 HQD-10, Document 8, pages 15-16,Question 10.3, Note 1. HQD-9, Document 1, pages 43-58. 52 HQD-10, Document 8, pages 120-121, FC12 and HQD-10, Document 8, Question 26.1, pages 48-56. 53 HQD-10, Document 8, pages 49-54. 51 19 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 assets associated with Large Customer Marketing & Sales are allocated directly 2 to the Sales & Marketing sub-function54. Comments 3 4 5 The minimum system analysis calculates customer-related costs for poles 6 lines and transformers associated with the Medium Voltage, Low Voltage 7 and Customer Connection sub-functions. These results are then used to 8 estimate the total costs associated with the three functions. In doing so, it 9 is assumed that: 10 • Connections sub-function costs are all customer-related55, and 11 • The facilities in both the Medium and Low Voltage sub-functions 12 have the same percentage split between customer-related and 13 demand-related costs56. 14 15 In response to OC interrogatory 43.1, HQD indicates that it assumed the 16 low-voltage and medium-voltage splits are the same as between 17 customer-related and demand-related costs because its accounting books 18 do not provide the level of information required to accurately track the 19 costs associated with low voltage and medium voltage lines. The 20 implications of this approach are discussed in the next section that deals 21 specifically with the classification of costs. 22 23 In any event, HQD should be encouraged to track more accurately the 24 cost of low voltage versus medium voltage facilities so to not have to rely 25 on its minimum system analysis to separate the costs of the two 26 Distribution sub-functions in its costs allocation study. 27 54 HQD-10, Document 8, pages 43-56. HQD-10, Document 8, page 113, Question 44.1. 56 HQD-10, Document 8, page 112, Question 43.1. 55 20 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 Again, it is not readily apparent how the general plant associated with 2 those customer service cost centres57 that are not readily attributable to a 3 specific Customer Service sub-function were assigned. As discussed 4 previously, the most appropriate treatment for any such assets would 5 likely be to allocate them to all of the Customer Service sub-functions as 6 an “overhead” based on some general allocator. 7 8 o Unamortized Expenses 9 10 The following unamortized charges and credits are also included in the rate base 11 calculation: 12 • Pension Benefits, 13 • Other Post-Employment Benefits, 14 • Staff Reduction Costs, 15 • Regulatory Assets (Deferred Commercial Program costs), and 16 • Government Reimbursement re: Ice Storm. 17 18 The first three items are related to the cost of employees and, as such, allocated 19 to the Distribution and Customer Service functions based on the salaries 20 associated with the cost centres attributable to each. Within the Distribution 21 function, the costs associated with Remotes are also determined based on its pro 22 rata share of total salaries. However, for the grid-connected Distribution sub- 23 functions, the costs of these items are allocated to sub-functions based on net 24 book value. In the case of Customer Service, the costs for these three 25 unamortized charges are also allocated to sub-functions based on the salaries 26 associated with each58. 57 Again, these cost centres include: a) the Bur. dir. Princ. SALC, b) Dir. Expertise et support SALC, c) Dir. Développement et projets, d) Dir. Planification et contrôle, e) Dir. Projets Systemes d’inform. Clientèle, and f) Gestion des actifs 58 HQD-10, Document 8, page 62-68, Question 31.1 21 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 The unamortized costs associated with past commercial programs are allocated 2 directly to the Customer Service - Sales & Marketing sub-function59. 3 4 Finally, the unamortized funds received from the Quebec government to offset 5 the cost of the ice storm are allocated to the grid-connected Distribution sub- 6 functions associated with lines on the basis of net book value60. 7 8 o Working Capital 9 10 Working capital requirements include both the cost of inventories and an 11 allowance for working funds. The total cost of inventories is based on the 13- 12 month average for the 2002-2003 period61. Inventories related to meters are 13 directly allocated to the Customer Service - Metering sub-function62. The 14 balance of the inventories, which are all related to Distribution activities, are 15 allocated between the Distribution sub-functions associated with grid-connected 16 facilities and Remotes based on an inventory analysis as of April 30, 200263. For 17 the grid-connected facilities, the value of inventories is allocated to individual 18 sub-functions on the basis of net book value of the associated fixed assets64. 19 20 The allowance for working funds covers cash requirements for a number of 21 items: • 22 O&M Expenses 23 o Labour costs 24 o Labour-related deductions (payable to government) 25 o Other O&M expenses • 26 Taxes o Capital taxes 27 59 HQD-10, Document 8, page 67. HQD-10, Document 8, pages 67-68. 61 HQD-6, Document 1, page 4, row « Matériaux, combustibles et fournitures ». 62 HQD-10, Document 8, page 96, Question 36.8. 63 HQD-10, Document 8, page 71, Question 31.3. 64 HQD-9, Document 1, page 36, FC16 60 22 Evidence of William Harper 1 o Gross revenue taxes 2 o Municipal/School taxes 3 • Electricity Commodity purchases 4 • Transmission service purchases 5 • Sales tax allowance 6 • Bad debt allowance Hydro-Québec Distribution Régie File R-3492-2002 Phase I 7 8 HQD indicates that allowances for working funds are directly calculated for the 9 major cost centres: Networks, Customer Service and Large Customer Sales & 10 Marketing65. The costs attributed to Networks are then allocated between the 11 Remote Communities and the grid-connected distribution network on the basis of 12 to the direct OM&A costs (excluding capitalized OM&A), taxes and fuel 13 purchases associated with each and then further allocated to individual sub- 14 functions on the basis of NBV66. 15 16 In the case of Customer Service the working cash requirements associated with 17 Customer Care are allocated to sub-functions on the basis of direct OM&A costs 18 (excluding capitalized OM&A), taxes and fuel purchases associated with each 19 sub-function67. The working cash requirements associated with Large Customer 20 Sales & Marketing are directly assigned to the Customer Service – Sales and 21 Marketing sub-function. 22 Comments 23 24 25 In its information request responses, HQD has indicated how the working 26 funds requirements associated with O&M expenses and Taxes (including 27 sales taxes) are calculated in sufficient detail to determine the allocation to 28 the Networks, Customer Service and Large Customer Sales & Marketing 65 HQD-10, Document 1, page 121, FC 15 and HQD-10, Document 8, pages 68-69, Question 31.2. 66 HQD-10, Document 8, pages 69-70, Question 31.6 67 HQD-10, Document 8, page 69, Question 31.6 23 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 cost centres68. However, for the other items (i.e. electricity commodity and 2 transmission service purchases) there is insufficient detail to determine 3 how the allocation was performed. 4 5 This is particularly critical since, when it comes to the working fund 6 requirements, those associated with electricity commodity and 7 transmission service purchases are by far the largest contributors to the 8 total working funds requirement69. Ideally the working fund requirements 9 for these two items would be calculated separately for small/medium and 10 large volume customer classes based on the electricity commodity and 11 transmission service costs attributable to each and recognizing any 12 differences in billing cycles. In the alternative, if this cannot practically be 13 done, the working capital requirements associated with electricity 14 commodity and transmission purchases should be functionalized as 15 production and transmission costs respectively and, subsequently, 16 allocated to customers on the same basis as the revenue requirement 17 assigned to these two functions. 18 19 In addition it is not clear why the working fund requirements associated 20 with O&M and Taxes are allocated as a single cost item. It would be more 21 appropriate to: § 22 Allocate the working funds associated with labour expenses to the 23 Distribution and Customer Service functions (and within Customer 24 Service to the individual sub-functions) on the basis of overall 25 labour costs by function (and sub-function), § 26 Allocate the working funds associated with other O&M expenses on the same basis as the underlying costs, and 27 68 69 HQD-10, Document 8, pages 36-41, Questions 23.3 & 23.4. HQD-6, Document 6, page 3. 24 Evidence of William Harper § 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I Allocate the working funds associated with each of the tax 2 expenses on the same basis as the tax expenses themselves were 3 allocated. 4 Finally, it is clear from the information request responses that the analysis 5 of working fund requirements performed in support of the functionalization 6 of the rate base needs to be revised to reflect updated values for the 7 various working capital components, particularly those associated with 8 taxes70. The working capital requirements included in the rate base 9 calculation are currently overstated in light of the revised information71. 10 11 4.3 Classification and Allocation 12 13 HQD classifies the costs in each function (and sub-function) in order to determine 14 whether they are to be allocated to customer classes based on demand, energy, 15 customer count, or more specifically assigned. Then, in each case an 16 appropriate measure of demand, energy use, customer count is then used to 17 allocate the costs to the various customer classes72. 18 19 Classification and Allocation of HQD’s Revenue Requirement 20 21 o Production Function (Electricity Commodity and Fuel Purchases) 22 23 The allocation of HQD’s electricity commodity purchase costs were the subject of 24 an earlier proceeding73 and HQD has specifically assigned the proposed 25 commodity costs for customers served from Distribution Networks to customer 70 HQD-10, document 8, page 36, Questions 23.1 and 23.2. While the total tax expense remains unchanged at $106.0 M – the expense associated with municipal and school taxes has gone down significantly – from $31.8 M to $13.3 M. Since this is the tax item with the largest net lead/lag value the requirement for working capital should decrease. 72 Since the allocation of costs is closely linked to their classification, both steps will be addressed at the same time. 73 File R-3477-2001. 71 25 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 classes based on the Régie’s decision74. In the case of Remote Communities, 2 the costs associated with the production of electricity have been allocated to the 3 customers served employing the same methodology as approved by the Régie 4 for the Heritage Pool electricity costs75. 5 Comment 6 7 8 The method approved by the Régie for allocating electricity commodity 9 cost to grid-connected customers is driven to a large extent by statutory 10 requirements that define the Heritage Pool, establish an average cost for 11 the associated electricity and provide direction as to how these costs are 12 to be allocated to customer classes76. It is understood that these statutory 13 requirements do not extend to the Remote Communities. As a result, 14 there is no reason to adopt the same methodology unless it is consistent 15 with the overall objectives of cost allocation. 16 17 There is no definitively correct way to allocate generation costs and 18 indeed different methodologies have been and are applied in various 19 jurisdictions. The methodology employed by HQD yields the appropriate 20 “relative” results for the various customer classes in that the lower a class’ 21 load factor the higher its average cost (consistent with the need to recover 22 the cost of the generating facilities required to serve these customers over 23 fewer kWh). The approach may warrant further study in the future when 24 revenue to cost ratios are closer to unity but it is likely satisfactory for now. 74 D-2002-221. HQD-9, Document 1, page 18, lines 18-20 and HQD-10, Document 1, page 139-141 76 Section 52.2 of the Act respecting the Régie de l’énergie. 75 26 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Transmission Function 2 3 The cost of transmission services are classified as 100% demand related and 4 allocated to the various grid-connected customer classes on the basis of each 5 class’ contribution to the annual system peak (i.e. 1 CP)77. This approach mirrors 6 the basis on which HQD is billed by TransÉnergie for transmission services. 7 8 o Distribution-Distribution Stations/Operating Centres 9 10 Within the Distribution function, the costs associated with the Distribution 11 Stations & Operating Centres sub-function are classified as 100% demand- 12 related. The costs are allocated to the individual customer classes on the basis 13 of each class’ annual non-coincident peak (1 NCP). Classification of distribution 14 stations as 100% demand-related is consistent with practice elsewhere as is the 15 use of non-coincident peak (NCP) loads to allocate costs. However, the actual 16 non-coincident peak measure used varies by utility78. 17 18 o Medium Voltage, Low Voltage and Customer Connection Facilities § 19 Classification 20 21 The costs in these sub-functions are classified between demand and customer- 22 related using the minimum system method. Under the minimum system method, 23 HQD identifies the costs of replacing the existing medium voltage facilities (lines 24 and poles), low voltage facilities (lines, poles and transformers) and connection 25 facilities (lines) with those required to provide a minimum level of service. The 26 costs associated with these facilities are deemed to be customer-related costs 27 and the balance of the costs associated with the facilities are deemed to be 28 demand-related. The results are then used to classify various miscellaneous 77 D-2002-95 For example, Hydro One Networks uses 12 NCP to allocate distribution station costs to customer classes. 78 27 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 assets included in the sub-function such as land and land rights, regulators and 2 condensers, circuit breakers and switchgear79. The method is applied separately 3 for overhead and underground facilities. 4 Since HQD’s accounting records do not track the costs of lines or poles by 5 voltage a number of assumptions had to be made in the analysis: 6 i. related. 7 8 ii. The split between customer-related and demand-related costs is the same for medium and low voltage system poles. 9 10 The costs allocated to the Connections sub-function are 100% customer- iii. The split between customer-related and demand-related costs is the same for medium and low voltage lines. 11 12 In fact, as noted in the previous section, it is these assumptions that allow HQD 13 to determine the total costs (i.e. NBV) associated with the medium voltage, low 14 voltage and customer connection sub-functions80. 15 16 Furthermore, since the costs for the minimum system are based on current 17 replacement costs and the values for poles, lines and transformers recorded on 18 HQD’s books are historical costs there was a need to discount the replacement 19 costs in order to account for inflation. This was done by calculating the average 20 age of each type of asset (i.e. poles, transformers, etc.) and then applying the 21 Handy-Whitman Index of Public Utility Construction Costs to adjust the current 22 value replacement costs for the time difference81. Overall the analysis results in 23 32% of the Medium Voltage sub-function’s costs and 39% of the Low Voltage 24 sub-function’s costs being classified as customer-related82. 79 HQD-9, Document 1, page 57, Table 4. Please refer to the discussion on page 19. 81 HQD-9, Document 1, pages 49-50, Section 2.4 and HQD-10, Document 8, pages 103-106, Question 40. 82 HQD-9, Document 1, page 31, Table 4. 80 28 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I Comments 1 2 3 HQD indicates that the average age of the equipment associated with 4 overhead facilities is 12-13 years and for underground facilities it is slightly 5 less at 10-11 years83. In making its inflation adjustment for each type of 6 asset, HQD assumes all the facilities are of the same age (i.e. built in the 7 same year – somewhere between 1989 and 1992 depending upon the 8 assets concerned) and applies the change in the Handy-Whitman index 9 for the intervening period. Implicit in this calculation is the assumption that 10 the rate of inflation for the years before the period 1989-1992 has been 11 roughly the same as for the years after 1989-1992. HQD has not 12 provided the annual values for the Handy-Whitman index, as requested in 13 OC interrogatory 40. However a review of the CPI index for Canada 14 indicates that the average rate of inflation between 1990 and 2002 was 15 2.1%, whereas the average rate between 1980 and 2002 was 3.7%84. 16 There is a need for HQD to review the history of the Handy-Whitman index 17 to determine if a similar trend exists. If such is the case, then HQD’s 18 methodology will understate the magnitude of the adjustment that must be 19 made to account for inflation and, thereby, overstate the value of the 20 customer-related costs associated with each function. 21 22 Minimum system methodologies vary across jurisdictions in terms of how 23 the minimum sized poles, conductors, transformers, etc. are determined 24 and how the assets are grouped for reporting purposes. However, it is 25 possible to make some comparisons. At an overall level, HQD’s analysis 26 results in roughly 38%85 of distribution poles, lines, transformers and 27 related equipment being classified as customer-related – a percentage 28 which is comparable to that for studies done by other Canadian utilities. 83 HQD-9, document 1, page 54 The values are based on Bank of Canada data found at: http://www.bankofcanada.ca/en/inflation_calc.htm 85 See HQD-9, Document 1, page 31. 84 29 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 2 The assumption that customer connections are 100% customer related is 3 a common, but not universal practice. In some jurisdictions, a standard 4 demand/customer split is derived for all lines (i.e., medium voltage, low 5 voltage and connections)86; while for others a portion of connections is 6 specifically classified as demand-related. As noted earlier, HQD’s 7 methodology first calculates customer-related costs and then treats the 8 balance of the capital costs associated with distribution poles, lines and 9 transformers as demand-related. As a result, classifying a portion of 10 connection costs as demand-related will not increase the overall 11 proportion of costs considered to be demand-related, but rather increase 12 the total costs associated with connections and thereby reduce the 13 demand-related costs (and thereby the total costs) attributable to medium 14 and low voltage lines. 15 16 Similarly, changes to the assumption that the split between customer and 17 demand costs is the same for medium and low voltage lines and for 18 medium and low voltage poles would not impact on total customer or total 19 demand costs. Rather, changes to this assumption would impact on the 20 total costs (and the total demand costs) attributed to low voltage versus 21 medium voltage assets. 22 23 In both cases, since demand costs associated with the low voltage sub- 24 function are allocated to a different set of customer classes than those 25 associated with the medium voltage sub-function these assumptions have 26 a direct impact on the total costs allocated to each customer class. HQD 27 should be directed to investigate further these two assumptions, 28 particularly the use of a common customer/demand split for both the low 29 voltage and medium voltage sub-functions. 86 This approach is taken in situations where the accounting records do not allow for connection (or secondary) service lines to be identified separately. 30 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Medium Voltage, Low Voltage and Customer Connection Facilities § 2 Allocation 3 4 The demand-related costs in the Medium and Low Voltage sub-functions are 5 allocated to customer classes on the basis of each class’ non-coincident peak (1 6 NCP). Customer-related costs are allocated to the various customer classes 7 based on the number of customers in each class87. For Medium Voltage and 8 Customer Connections the demand and customer allocators are based on the 9 total customers in each class; while for Low Voltage facilities the allocators reflect 10 the number of customers in each class served at low voltage and their 11 associated 1 NCP. 12 13 Comments 14 15 The customer load characteristics used to allocate the demand-related 16 portions of Distribution function will depend upon the load diversity that is 17 present in the distribution system at the point where the equipment whose 18 costs are being allocated is located. The distribution stations included in 19 the Stations and Operating Centres sub-function transform power between 20 various medium voltage levels (e.g. 25 kV and 12 kV) and, as a result, the 21 load diversity at HQD’s distribution stations will be fairly high. The same is 22 true for the loads actually carried by the medium voltage lines. In such 23 circumstances common utility practice is to allocate the associated 24 demand-related distribution costs to customer classes based on their 25 individual class peaks (i.e., NCP) and HQD follows this practice. 26 However, HQD has not been able to provide sufficient information to 27 determine whether the use of 1 NCP is appropriate or whether the use of 28 customer class peaks over a number of months would be more 29 appropriate88. 87 88 See HQD-10, Document 1, pages 126-132 for data regarding the allocators. See HQD-10, Document 8, page 57, Question 28.2. 31 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 For facilities closer to the customer, such as secondary feeders and line 2 transformers, the load diversity will be much lower. As a result, in these 3 situations, the demand-related costs of the facilities are often89 allocated 4 to customer classes based on the sum of the individual customer’s 5 maximum demands. HQD’s proposed cost allocation methodology does 6 not make this distinction. 7 8 Also, customer connection costs are frequently allocated to customer 9 classes based on a weighted as opposed to strict numerical customer 10 count. The weighting factor reflects the cost differential in servicing 11 different classes of customers (i.e., the higher service costs typically 12 associated with larger power customers). 13 14 Finally, there is a load carrying capability associated with the minimum 15 system. HQD has indicated that it is in the order of 1-2 kVA (or 1-2 kWs) 16 per connection90. Since the costs associated with this minimum load are 17 allocated to customer classes as a customer-related cost it is necessary to 18 adjust the 1 NCP values used to allocate demand related costs in order to 19 avoid double counting. This is generally done by reducing the 1 NCP 20 value for each customer class by the product of the per customer load 21 carrying capability of the minimum system and the number of customers 22 served. However, HQD has not done so. Furthermore, making this 23 adjustment would have a material impact on the relative 1 NCP values 24 used for each customer class (e.g. using a 2 kW/customer load carrying 25 capability reduces the overall percentage of costs allocated to the 26 Domestic customer classes by roughly 10 percentage points when applied 27 to the Medium Voltage sub-function – see Schedule 1). 28 89 As indicated earlier, in some circumstances utilities do not separate the minimum system costs of secondary and primary feeders and, in these circumstances NCP is used to allocate the costs of both. 90 HQD-10, document 1, pages 144-145. 32 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Distribution - Streetlights/Sentinel Lighting 2 3 The costs associated with Streetlights/Sentinel Lighting are allocated specifically 4 to that customer class91. 5 6 o Customer Service-Customer Care & Accounting 7 8 In the case of the Customer Care & Accounting, the costs for the small/medium 9 power customers92 and the large volume customers are segregated ($346.9 M 10 and $ 1.2 M respectively) and each is classified as customer-related. The costs 11 are then allocated based on the number of customers by customer class93. 12 Comments 13 14 15 Customer Care & Accounting costs include significant costs associated 16 with meter reading and billing94. However, as indicated in response to OC 17 interrogatories 32.5 and 32.695, not all small/medium power customers 18 have either their meters read or bills issued with the same frequency. 19 Furthermore, the billing process for medium power customers is typically 20 more costly as it involves both demand and energy charges. Generally, 21 utilities separate out the costs associated with meter reading and billing 22 and use an allocation factor that weights the number of customers in each 23 class by a factor that reflects the relative meter reading and billing costs 24 per customer across the various customer classes. HQD has not done 25 this, but rather has allocated all costs associated with meter reading and 91 HQD-9, Document 1, pages 33-34, Table 6, column 8 for rate base and Table 7, column 10 for annual revenue requirement. 92 Note : The customer care & accounting costs associated with Remotes are also identified separately and also allocated based on number of customers. 93 See HQD-10, Document 1, page 127. 94 See HQD-9, Document 1, page 9, lines 3-6 and HQD-10, document 1, page 104. 95 HQD-10, Document 8, pages 78-70. 33 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 billing for small/medium power customers strictly on the basis of customer 2 count. 3 4 Also, it is not transparent how the $1.2 M in Customer Care & Accounting 5 costs associated with large volume customers was determined. However, 6 the value is directionally correct on a per customer basis (i.e., on a per 7 customer basis it is significantly higher; as one would expect, than that 8 associated with small/medium volume customers. 9 10 Overall, the process used to split the costs assigned to this function 11 between small/medium power customers and large volume customers 12 could be more clearly documented. For example, it would be useful if 13 HQD were to indicate how the cost centres described in HQD-4 14 (Documents 5.2 & 5.3) are: § 15 Assigned to the Customer Care and Accounting, Metering, and Marketing and Sales sub-functions, and 16 § 17 Attributed to small/medium power versus large volume customers, in the case of the Customer Care and Accounting sub-function. 18 19 20 o Customer Service - Meters 21 22 In the case of Meters, the costs are also classified as customer-related. 23 However, in this instance, HQD does use a weighted customer allocation factor 24 to reflect the difference in the cost of meter used by customer class96. 25 26 o Customer Service - Sales & Marketing 27 28 The costs associated with the Customer Service – Sales & Marketing sub- 29 function are first split between those incurred for small/medium power customers 96 HQD-10, Document 1, pages 128-129. 34 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 ($ 82.0 M) and large power customers ($ 23.7 M). For small/medium power 2 customers the costs are further segmented into those incurred in support of 3 marketing programs (“Commercialisation”) and those incurred to support sales & 4 after sales service (“Ventes en territoires”) to commercial, institutional and 5 industrial customers (i.e., non-domestic customers). Similarly, for large volume 6 customers, the costs are segmented into those incurred for sales promotion 7 programs and other customer service related costs. The costs of sales 8 promotion programs for small/medium and large volume customers are each 9 classified as energy-related and allocated to individual customer classes based 10 on the kWh sales by class. The balance of the costs attributed to small/medium 11 power customers (i.e., those for “Ventes en territoires”) are allocated to the 12 small/medium power non-domestic customer classes on the basis of energy use. 13 The balance of the Sales and Marketing costs associated with large power 14 customers are allocated to the large power rate classes on the basis of customer 15 count97. 16 Comments 17 18 19 The process used to split the costs assigned to this function between 20 small/medium power customers and large volume customers could be more 21 clearly documented, as could the determination of the costs associated with 22 marketing programs versus other sales support activities. For example, it 23 would be useful if HQD were to indicate how the cost centres described in 24 HQD-4 (Documents 5.2 & 5.3) are: § 25 Assigned to the Customer Care and Accounting, Metering, and Marketing and Sales sub-functions, 26 § 27 Attributed to small/medium power versus large volume customers, in the case of the Marketing and Sales sub-function, and 28 § 29 97 Associated with marketing programs versus other sales activities. HQD-10, document 1, page 131, Table 76.1F. 35 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 Also, it is not clear how the amortization of the costs associated with various 2 commercial programs was allocated to customer classes. While the costs 3 can be clearly associated with particular customer classes98, they appear to 4 have been allocated (along with the other costs in this sub-function) to various 5 customer classes. 6 7 o Customer Service - Other 8 9 In the case of the Customer Service - Other sub-function, revenues received 10 from customers, the internal costs of the electricity supply business unit and the 11 balance of the costs are each treated differently. 12 13 Non-rate customer revenues (e.g. late payment fees) derived from large power 14 customers are classified as customer-related and specifically allocated to the 15 large volume customer classes on that basis. Customer revenues from 16 small/medium power customers are allocated to customer classes based on the 17 relative non-rate revenues received from each of the small and medium power 18 customer classes in 2001. 19 20 The internal costs of the electricity supply business unit are allocated to customer 21 classes based on their electricity commodity costs. 22 23 Finally, the remaining costs in the sub-function (i.e., HQD overheads) are 24 allocated to customer classes based on the total costs allocated to each class 25 (excluding electricity commodity purchase costs and transmission service costs). 26 27 Comments 28 29 It was not readily transparent, until the responses to the Information 30 Requests had been received, that the internal costs incurred by HQD to 98 See HQD-10, Document 8, page 35, Question 22.2. 36 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 obtain electricity commodity supply are actually allocated to each 2 customer class based on their commodity cost of electricity. For purposes 3 of transparency, it would be preferable if the costs for HQD’s electricity 4 supply business unit were functionalized as “Production” costs. 5 6 The allocation base for HQD’s overhead costs is based on the total costs 7 allocated to each customer class, excluding electricity commodity and 8 transmission service costs but including the fuel purchase costs for 9 Remote Communities. In contrast the allocation base used for Hydro- 10 Québec’s corporate overheads is based on all the costs allocated to each 11 function, excluding electricity commodity purchases, transmission service 12 costs and fuel purchase costs99. There is no apparent rationale for the 13 different treatment of the two types of “overhead” costs. Indeed, given 14 that the allocation of the Hydro-Québec corporate overheads is based on 15 the proposed methodology for the allocation of such costs between 16 business units, it would be appropriate to allocate the HQD overheads on 17 a similar basis. 18 19 Classification and Allocation of HQD’s Rate Base 20 21 o Distribution Sub-Functions 22 23 The costs assigned to the various Distribution sub-functions of HQD’s rate base 24 are classified and allocated to customer classes generally in the same manner as 25 was used for the revenue requirement: 26 • The rate base costs in the Distribution - Distribution Stations & Operating 27 Centres sub-function are classified as demand related and allocated to 28 customer classes based on 1 NCP. 99 See HQD-10, Document 1, page 138, Question 76.2 and HQD-9, Document 1, page 17, lines 9-12. 37 Evidence of William Harper 1 • Hydro-Québec Distribution Régie File R-3492-2002 Phase I The rate base costs in the Distribution sub-functions associated with Medium 2 Voltage, Low Voltage and Customer Connections are classified as customer- 3 related and demand-related using the minimum system method. The 4 demand-related rate base costs associated with the Medium Voltage and Low 5 Voltage sub-functions are then allocated to customer classes based on the 1 6 NCP for each class100. Customer-related costs for each of the three sub- 7 functions are allocated to customer classes based on the number of 8 customers in each class that utilize the facilities. 9 • The rate base costs associated with Streetlights/Sentinel Lighting are allocated specifically to the Street Lighting customer class. 10 11 Comments 12 13 14 The same comments that were made with respect to the minimum system 15 methodology – as used to classify and allocate the revenue requirement – 16 also apply for the classification and allocation of the rate base. 17 Specifically, the methodology as applied: § 18 Potentially overstates customer-related rate base costs – due to the way the inflation adjustment is made to replacement costs, 19 § 20 Arbitrarily establishes the demand-related cost, and hence the total 21 costs, associated with the Medium Voltage, Low Voltage and 22 Customer Connection sub-functions, and § 23 Fails to recognize the load carrying capability inherent in the 24 customer-related facilities, in the allocation of demand-related 25 costs. 100 The 1 NCP values for Medium and Low Voltage differ, as the former includes all customers in each rate class, while the later only includes those customers served at low voltage. See HQD10, document 1, page 126. 38 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Customer Service - Customer Care & Accounting 2 3 The rate base costs associated with the Customer Service - Customer Care & 4 Accounting sub-function are allocated to customer classes in the same 5 proportion as the revenue requirement costs associated with the sub-function 6 were101. 7 Comments 8 9 10 Any change in the allocation of the revenue requirement costs associated 11 with this function to customers would also impact on the allocation of the 12 rate base. In particular, while the allocation factors as currently derived 13 recognize the higher cost customer for billing large power customers, they 14 do not capture the typically higher costs associated with billing medium 15 power versus small power customers. The rate base items associated 16 with customer meter reading, accounting and billing should be separated, 17 to the extent possible, and allocated to customer classes using a weighted 18 customer allocation factor that reflects the relative costs of service to the 19 various customer classes. 20 21 o Customer Service - Meters 22 23 The rate base costs associated with Customer Service - Meters are classified as 24 customer-related and allocated to customer classes using the same weighted 25 customer allocation factors as were developed for purposes of allocating the 26 revenue requirement costs associated with the function102. 101 See HQD-9, Document 1, page 33, Table 6, column 10 and HQD-10, Document 1, page 127, Question 76.1, columns 14-15. 102 See HQD-9, Document 1, page 33, Table 6, column 11 and HQD-10, Document 1, pages 128129, Question 76.1. 39 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I o Customer Service - Sales & Marketing 2 3 The rate base costs associated with the Customer Service – Sales & Marketing 4 sub-function are first split into those associated with serving small/medium power 5 customers, those associated with large volume customers and those related to 6 energy efficiency103. 7 8 For small/medium power customers, the costs are then further segregated into 9 those incurred for sales promotion programs and customer sales & after sales 10 support costs (“Ventes en territoires”). The costs of sales promotion programs 11 are allocated to the individual customer classes based on kWh sales by class. 12 The other customer sales/marketing costs are associated with sales support for 13 non-residential customer classes and are allocated specifically to these classes 14 on the basis of kWh sales. 15 16 For large volume customer, the costs are also segmented into those incurred for 17 sales promotion programs and other customer sales support costs. The costs of 18 sales promotion programs are (again) allocated to the individual customer 19 classes based on kWh sales by class. However, the other customer sales 20 support costs are allocated to the individual large power customer classes based 21 on the number of customers by customer class. 22 23 Rate base costs associated with encouraging the effective use of energy are 24 allocated to all customer classes based on the energy sales (kWh) by customer 25 class104. 103 104 HQD-10, Document 1, page 130, Table R76.1-E. HQD-10, Document 1, page 130, Table R76.1E, columns 16-18. 40 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I Comments 1 2 3 The derivation of the breakdown between “sales promotion programs”, 4 other customer sales & marketing costs and the costs associated with 5 encouraging the effective use of energy is not well documented. It would 6 be useful if HQD were to indicate how the cost centres described in HQD- 7 4 (Documents 5.2 & 5.3) are: 8 § Assigned to the Marketing and Sales sub-function, 9 § Associated with sales promotion programs versus other sales 10 support activities in the case of the Large Customer Marketing & 11 Sales related cost centres, and § 12 Associated with sales promotion programs versus sales & after 13 sales support programs in the case of the Customer Service related 14 cost centres. 15 16 Also, it is not clear how the unamortized costs associated with various 17 commercial programs were allocated to customer classes. While the 18 costs can be clearly associated with particular customer classes105, they 19 appear to have been allocated (along with the other costs in this sub- 20 function) to various customer classes. 21 22 o Customer Service-Other 23 24 The functionalized rate base provided in HQD’s Application did not have any 25 costs associated with this sub-function. However, in response to an information 26 request, HQD has indicated that there is $2.5 M currently included in the rate 27 base for the Customer Service – Sales & Marketing sub-function106 which will be 28 re-functionalized to Customer Service - Other. 105 106 HQD-6, Document 5, page 2. HQD-10, Document 8, page 89, Question 32.11. 41 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 5.0 Overall Conclusions 2 3 HQD’s proposed cost allocation methodology generally follows accepted industry 4 practices. However, as identified in the preceding discussion there are specific 5 areas where: 6 • considerations of cost causality, 7 8 • 11 Clarification and further documentation is required as to how the proposed methodology works, and 9 10 Changes are required to the methodology in order to more accurately reflect • Further analysis/work is required to confirm the appropriateness of the proposed methodology. 12 13 The requirements are summarized below and the Régie should direct HQD to 14 undertake the recommended changes, documentation and analyses and 15 incorporate the results into their Phase II filing for 2004-2005 rates. 16 17 1.0 Recommended Changes to HQD’s Cost Allocation Methodology 18 19 Functionalization of the Revenue Requirement 20 21 1.1 Capital Taxes 22 23 In order to more closely reflect the basis on which capital taxes are actually 24 incurred, their allocation to Remote Communities (versus grid-connected 25 distribution network facilities) and the subsequent allocation to individual Remote 26 Community sub-functions should be changed and performed on the basis of net 27 book value (preferably including assets under construction). 42 Evidence of William Harper 1 1.2 Hydro-Québec Distribution Régie File R-3492-2002 Phase I Gross Revenue Taxes 2 3 Similarly, to more closely reflect the basis on which Hydro Quebec’s gross 4 revenue taxes are actually calculated, their allocation to customer classes should 5 be based on distribution revenues or total allocated costs – excluding the cost of 6 electricity commodity purchases and transmission services. 7 8 1.3 Electricity Supply Procurement Costs 9 10 In order to improve the transparency of the proposed cost allocation 11 methodology, the internal costs incurred by HQD for procuring electricity supply 12 (i.e. the costs associated with the electricity supply cost centre107 - including 13 shared services costs and allocated overheads) should be functionalized as 14 Production. 15 16 Functionalization of the Rate Base 17 18 1.4 Working Fund Requirements 19 20 Again, in order to improve the transparency of the proposed cost allocation 21 methodology, the working fund requirements associated with the electricity 22 commodity purchases and transmission services should be assigned to the 23 Production and Transmission functions respectively. 24 25 In order to more closely reflect cost causality, the working fund requirements 26 associated with labour expenses, other O&M expenses, capital taxes, gross 27 revenue taxes, and municipal and school taxes should each be allocated 28 separately to functions. In each case, the functionalization of the working fund 107 See HQD-4, Document 5. 43 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 requirements should be based on the same methodology as was used to allocate 2 the associated revenue requirement component. 3 4 In addition, there is a need to update the calculation of the working fund 5 requirements included in the Application in order to reflect the actual expense 6 levels included in the revenue requirement. 7 8 Classification and Allocation of Revenue Requirement 9 10 1.5 Medium Voltage and Low Voltage Sub-Functions 11 12 The 1 NCP customer class values used to allocate the demand-related costs for 13 the Medium Voltage and Low Voltage sub-functions need to be adjusted to 14 reflect the load carrying capability of the minimum system. This can be done by 15 reducing the 1 NCP value for each customer class by the load carrying capability 16 included in the customer-related costs for each customer class (which is 17 determined as the product of the number of customers in the class and the per 18 customer load carrying capability of the minimum system). 19 20 1.6 Customer Care & Accounting Sub-Function 21 22 The costs associated with customer meter reading, billing and accounting should 23 be separately identified and allocated to customers based on a weighted 24 customer count allocation factor that captures the relative cost of these activities 25 for the various customer classes. 26 27 1.7 HQD Overhead Costs 28 29 The allocation of HQD overheads to customer classes should be changed so it is 30 consistent with the allocation base used to allocate Hydro-Québec’s corporate 31 overheads (i.e., exclude purchased fuel costs for Remote Communities). 44 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I Classification and Allocation of the Rate Base 2 3 1.8 Medium and Low Voltage Distribution Sub-Functions 4 5 The 1 NCP customer class values used to allocate the demand-related rate base 6 costs for the Medium Voltage and Low Voltage sub-functions also need to be 7 adjusted to reflect the load carrying capability of the minimum system. This can 8 be done by reducing the 1 NCP value for each customer class by the load 9 carrying capability included in the customer-related costs for each customer class 10 (which is determined as the product of the number of customers in the class and 11 the per customer load carrying capability of the minimum system). 12 13 1.9 Customer Care & Accounting Sub-Function 14 15 The rate base costs associated with customer meter reading, billing and 16 accounting should also be separately identified and allocated to customers based 17 on a weighted customer count allocation factor that captures the relative cost of 18 there activities for the various customer classes. 19 20 2.0 Aspects of the Proposed Cost Allocation Methodology Requiring 21 Further Documentation 22 23 Functionalization of the Revenue Requirement 24 25 2.1 Treatment of Cost Centres 26 27 There is a need for HQD to more clearly document how the costs (i.e., OM&A, 28 depreciation, shared services, internal revenues, other revenues) attributed to its 29 various cost centres (as described in HQD-4, Document 5 and Documents 5.1- 30 5.3) are functionalized. More specifically, for those cost centres associated with 31 Networks: which ones are assigned directly to the grid-connected Distribution 45 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 sub-functions; which ones are assigned directly to Remote Communities sub- 2 functions; and, whether there was a need to allocate the costs included in any of 3 the cost centres either between grid-connected Distribution and Remote 4 Communities or among the Remote Communities’ sub-functions. 5 6 Similarly, for the Customer Service and Large Customer Marketing & Sales cost 7 centres, which ones are directly assigned to a Customer Service sub-function (or 8 Remote Communities) and whether there was any need to allocate the costs 9 included in any of these cost centres across sub-functions. With respect to the 10 later issue, there is a specific need to clarify the treatment of the following cost 11 centres: a) the Bur. dir. Princ. SALC, b) Dir. Expertise et support SALC, c) Dir. 12 Développement et projets, d) Dir. Planification et contrôle, e) Dir. Projets 13 Systemes d’inform. Clientèle, and f) Gestion des actifs. 14 15 2.2 Municipal and School Taxes 16 17 There is a need for HQD to clarify how municipal and school taxes were 18 assigned to the Distribution and Customer service functions and, then, within the 19 Distribution function, between grid-connected sub-functions and Remote 20 Communities. 21 22 Functionalization of the Rate Base 23 24 2.3 Treatment of Cost Centres 25 26 Similar to the issue raised in 5.2.1, there is a need for HQD to more clearly 27 document how the rate base costs (i.e., specific fixed assets and general plant) 28 attributed to its various cost centres (as described in HQD-4, Document 5 and 29 Documents 5.1-5.3) are functionalized. More specifically, for the Customer 30 Service and Large Customer Marketing & Sales related cost centres which ones 31 are directly assigned to a Customer Service sub-function (or Remote 46 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 Communities) and whether there was any need to allocate the assets associated 2 with any of these cost centres across sub-functions. With respect to the later 3 issue, there is specific need to clarify the treatment of the following cost centres: 4 a) the Bur. dir. Princ. SALC, b) Dir. Expertise et support SALC, c) Dir. 5 Développement et projets, d) Dir. Planification et contrôle, e) Dir. Projets 6 Systemes d’inform. Clientèle, and f) Gestion des actifs. 7 8 2.4 Working Fund Requirements 9 10 It is not clear how the working fund requirements associated with electricity 11 commodity and transmission service purchases were assigned to the various 12 functions. As noted in 5.1.4, these costs should be treated as Production and 13 Transmission function costs respectively. 14 15 Classification and Allocation of the Revenue Requirement 16 17 2.5 Customer Care & Accounting Sub-Function 18 19 Consistent with the recommendations set out in 5.2.1, it would be useful if HQD 20 more clearly documented the process used to split the costs assigned to this 21 function between small/medium power customers and large volume customers. 22 For example, HQD should indicate how the cost centres described in HQD-4 23 (Documents 5.2 & 5.3) are: 24 § Assigned to the Customer Care and Accounting sub-function, and 25 § Attributed to small/medium power versus large volume customers. 26 27 2.6 Sales & Marketing Sub-Function 28 29 Consistent with the recommendations in 5.2.1, it would be useful if HQD more 30 clearly documented the process used to split the costs assigned to this function 31 between small/medium power customers and large volume customers and also 47 Evidence of William Harper Hydro-Québec Distribution Régie File R-3492-2002 Phase I 1 how the costs associated with marketing programs versus other sales support 2 activities were determined. For example, it would be useful if HQD were to 3 indicate how the cost centres described in HQD-4 (Documents 5.2 & 5.3) are: 4 § Assigned to the Marketing and Sales sub-function, 5 § Attributed to small/medium power versus large volume customers, and 6 § 7 Associated with marketing programs versus other sales activities. 8 9 Also, HQD should more clearly explain how the amortization of the costs 10 associated with various commercial programs was allocated to customer classes 11 and why they were not directly assigned. 12 13 Classification and Allocation of the Rate Base 14 15 2.7 Sales & Marketing Sub-Function 16 17 It would be useful if HQD were to indicate how the cost centres described in 18 HQD-4 (Documents 5.2 & 5.3) are: 19 § Assigned to the Marketing and Sales sub-function, 20 § Associated with sales promotion programs versus other sales support 21 activities in the case of the Large Customer Marketing & Sales related 22 cost centres, and 23 § Associated with sales promotion programs versus sales & after sales 24 support programs in the case of the Customer Service related cost 25 centres. 26 27 Also, HQD should more clearly explain how the unamortized costs associated 28 with various commercial programs were allocated to customer classes and why 29 they were not directly assigned. 48 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 3.0 Issues Requiring Further Study/Analyses 2 3 Functionalization 4 5 6 3.1 Identification of Low Voltage, Medium Voltage and Connections SubFunction Assets 7 8 HQD should be encouraged to review its accounting records and determine 9 whether the cost of medium voltage, low voltage and customer connections can 10 be separately established and tracked. 11 12 Classification and Allocation 13 14 3.2 Minimum System Calculations 15 16 HQD should be directed to undertake an analysis of the Handy-Whitman Index’s 17 historical values to determine if there is any difference between the pre and post 18 1989-1992 values and, if so, what impact the difference would have on the 19 determination of customer-related costs. 20 21 HQD should also be directed to undertake further analysis to substantiate its 22 assumptions that: 23 o Customer Connection costs are 100% demand-related, and 24 o The demand/customer cost split is the same for Medium and Low Voltage 25 facilities (i.e., poles and lines). 49 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3492-2002 Phase I 3.3 Determination of NCP Allocators 2 3 HQD should be directed to compile the necessary system loading data (e.g., 4 monthly peak loads by delivery point) in order to establish that1 NCP is the 5 appropriate allocation factor for the Distribution sub-functions’ demand-related 6 costs. 50 SCHEDULE 1 (1) Rate Class D DH DT TOTAL DEMAND ALLOCATOR ADJUSTMENT BASED ON MINIMUM SYSTEM LOAD CARRYING CAPABILITY ( 2 KW PER CUSTOMER) (2) (3) (4) MT % MT 1 NCP # Cust 14891 58.08% 2942066 2 0.01% 198 646 2.52% 117418 15538 60.61% 3059682 (5) (6) MT % Adj 1 NCP 9007 47.58% 2 0.01% 411 2.17% 9419 49.75% G G9 M LIGT BT TOTAL 3097 371 4708 136 398 8710 12.08% 1.45% 18.36% 0.53% 1.55% 33.97% 269396 3507 11095 5833 3048 292879 2558 364 4686 124 392 8124 13.51% 1.92% 24.75% 0.66% 2.07% 42.92% L H LD SPEC TOTAL 1383 5 0 0 1388 5.39% 0.02% 0.00% 0.00% 5.41% 142 1 0 0 143 1383 5 0 0 1388 7.30% 0.03% 0.00% 0.00% 7.33% GRAND TOTAL 25637 3352704 18931 Notes: (1) Source: HQD-10, document 1, page 126, Table R76.1A (3) Source: HQD-10, document 1, page 126, Table R76.1A (5) Based on Column (2) - 2 kW*Column (4) 51