RÉGIE DE L’ÉNERGIE HYDRO-QUÉBEC DISTRIBUTION’S APPLICATON FOR APPROVAL OF THE PROPOSED 2005-2014 SUPPLY PLAN FILE R-3550-2004 EVIDENCE OF WILLIAM HARPER ECONALYSIS CONSULTING SERVICES ON BEHALF OF: OPTION CONSOMMATEURS MAY 25, 2005 Table of Contents 1 Background ...........................................................................................................................1 2 Purpose of Evidence............................................................................................................4 3 HQD’s Load Forecast ..........................................................................................................6 4 3.1 HQD’s Expected Sales Forecast ...............................................................................6 3.2 HQD’s Expected Energy Requirements .................................................................12 3.3 HQD’s Expected Power Requirements...................................................................14 3.4 Load Forecast Sensitivity..........................................................................................15 3.5 Conclusions .................................................................................................................18 HQD’s Supply Requirements ...........................................................................................20 4.1 4.1.1 Energy Requirements ........................................................................................20 4.1.2 Capacity Requirements .....................................................................................23 4.2 Heritage Pool S upply .................................................................................................26 4.2.1 Total Supply Available .......................................................................................26 4.2.2 Heritage Pool Dispatch......................................................................................27 4.3 Needs in Excess of the Heritage Pool ....................................................................33 4.4 Post Heritage Pool Supplies Currently Under Contract/Planned .......................36 4.4.1 Existing Contracts ..............................................................................................36 4.4.2 Planned Contracts..............................................................................................37 4.5 Additional Supplies Required ...................................................................................40 4.5.1 Energy and Capacity .........................................................................................40 4.5.2 Types of Capacity Required .............................................................................42 4.6 5 Total Supply Requirements ......................................................................................20 Conclusions .................................................................................................................44 HQD’s 2005-2014 Supply Strategy and Plans ..............................................................47 5.1 Near Term (2005-2008).............................................................................................47 5.1.1 Inter-Tie Capability .............................................................................................48 5.1.2 Mix of Market Purchases...................................................................................52 5.1.3 Conclusions .........................................................................................................53 5.2 Longer Term (2009-2014) .........................................................................................55 6 5.2.1 Available Supply Options ..................................................................................55 5.2.2 HQD’s Long Term Supply Strategy .................................................................61 5.2.3 Conclusions .........................................................................................................71 Issues From Previous Régie Decisions ..........................................................................74 6.1 Evaluation of Transmission Costs for Small Scale Plants ...................................74 6.2 Evaluation of Transmission Costs ...........................................................................75 6.3 Contract Term .............................................................................................................76 Appendix A: CV for ECS Consultant………………………………………………………..77 Evidence of William Harper 1 1 Hydro-Québec Distribution Régie File R-3550-2004 Background 2 3 On November 1, 2004, Hydro-Québec Distribution (HQD) filed an application with the 4 Régie de l’énergie (the Régie) requesting approval of its 2005-2014 Electricity Supply 5 Plan. This is the second such plan HQD has submitted to the Régie since the 6 restructuring of Hydro-Québec, the establishment of the Heritage Pool and the 7 amendments to the Loi sur la Régie de l’énergie. As a result of these changes, HQD is 8 required to submit a Supply Plan every three years for full review by the Régie and an 9 annual update in each of the intervening years. 10 11 HQD’s first supply plan (the 2002 Plan) was submitted to the Régie in October 2001. 12 Following a two -phased hearing process, the Régie eventually approved 1 HQD’s plan 13 which called for the acquisition of 600 MW/4.1 TWh of baseload capacity and 400 MW 14 of modulable supply commencing in 2006-2007. In addition, the Régie approved the 15 acquisition of an additional 600 MW of supply to meet the loads of the Alouette 16 aluminium plant expansion with deliveries commencing in 2005. HQD’s 2002 Plan also 17 called for: a) the use of short-term contracts to address any supply shortfalls prior to the 18 in-service of the new capacity and to address fluctuations in load d ue to normal weather 19 variations and b) an agreement with Hydro-Québec Production (HQP) to manage 20 extreme, short-term load variations due to abnormal weather conditions or supply failure 21 and involuntary overages due to the dispatch of the Heritage Pool without going through 22 a formal tendering process 2. Following the development of the 2002-2011 Supply Plan 23 and its approval by the Régie, HQD received further advice and direction from both the 24 Régie and the Québec government concerning the acquisition of future supplies: • 25 In March 2003, the government directed HQD to solicit 1000 MW of new supplies from wind power and an additional 100 MW of new supply from biomass 3. 26 • 27 In December 2003, the government directed HQD to acquire 800 MW of supply via cogeneration4. 28 1 2 3 D-2002-17, Phase 1 and D-2002-169, Phase 2 R-3470-2001, HQD-2, Document 3, page 33 HQD-1, Document 2, page 6 1 Evidence of William Harper • 1 Hydro-Québec Distribution Régie File R-3550-2004 Following the Régie’s June 2004 report5 to Québec government regarding 2 Québec’s Electricity Energy Security and the Suroît project, HQD cancelled 6, at 3 the direction on the provincial government, its plans to construct the Suroît 4 project (an 836 MW gas-fired combined cycle plant). 5 Consistent with its 2002-2011 Supply Plan and subsequent approvals/directions, HQD 6 has initiated the following supply-related activities over the past three years: • 7 In February 2002, HQD initiated a call for tender (A/O 2002-01) for 600 MW of 8 supply for delivery starting in 2006. This eventually led to HQD entering into 9 three contracts for a total of 1107 MW and 8.2 TWh per annum 7, with deliveries 10 starting in 2006 and 2007. • 11 In April 2003, HQD initiated a call for tender (A/O 2003-01) for 100 MW of supply 12 from biomass. This eventually led to HQD entering into two contracts for a total 13 of 39.4 MW of supply8 with deliveries starting in 2006. • 14 In May 2003, HQD initiated a call for tender (A/O 2003-02) for 1,000 MW of 15 supply from wind energy. This eventually led to HQD entering into 9 contracts for 16 a total of 990 MW of wind power supply9 with deliveries starting in 2006. • 17 In April 2004, HQD initiated a call for tender (A/O 2004-01) for 250 MW for the 18 period January 1 to December 31, 2005. The successful contractor – the 19 Constellation Group – was announced in May 2004 10. • 20 In October 2004, HQD initiated a call for tender (A/O 2004-02) for 350 MW of 21 supply from cogeneration11. The associated energy supply would be 2.8 TWh 22 per annum 12 and deliveries are assumed to start in 2008. • 23 In October 2004, HQD initiated a call for tender (A/O 2004-03) for 100-400 MW 24 of short-term supply for 2005. In November 2004, HQD entered into contracts for 25 the supply of 800 GWh over the period January to April 2005 13. 4 HQD-1, Document 2, page 7 A-2004-01 6 Press Release, Ministère des Ressources naturelles, Québec, November 17, 2004 7 HQD-1, Document 2, page 7 8 HQD-1, Document 2, pages 7-8 9 HQD-1, Document 2, pages 9-10 10 HQD-5, Document 6, page 3, Response 2.1 11 HQD-1, Document 2, page 10 12 HQD-3, Document 3, page 5 5 2 Evidence of William Harper • 1 Hydro-Québec Distribution Régie File R-3550-2004 In November 2004, HQD initiated another call for tender (A/O 2004-04) for 900 GWh of short term firm supply for 2005 14. 2 3 4 The current 2005-2014 Supply Plan proposed by HQD foresees the need for additional 5 energy supplies over and above those currently contracted for or being acquired for the 6 years 2006-2014 inclusive and, similarly, additional power supply requirements for 7 2005-2006 and beyond 15. The Plan calls for the needs through 2008 to be met primarily 8 by short-term purchases. For the period 2009-2014, the Plan calls for the additional 9 supplies to come from a second call for tender (CFT) for wind energy; a CFT for 10 modulable supply; followed by a another CFT for supply from cogeneration; with any 11 remaining balance to be made up through short-term purchases 16. 12 13 On November 11, 2004 the Régie issued a procedural order (D-2004-240/R-3550-2004) 14 to initiate a public review of HQD’s Application for approval of the 2005-2014 Supply 15 Plan. 13 14 15 16 HQD-1, Document 2, page 10 and HQD-5, Document 6, page 4, Response 3.1 R-3558-2005, HQD-1, Document 1, page 13 HQD-3, Document 3, pages 5-6. HQD-1, Document 1, pages 5-6. 3 Evidence of William Harper 1 2 Hydro-Québec Distribution Régie File R-3550-2004 Purpose of Evidence 2 3 After reviewing HQD’s Application and the Procedural Order issued by the Régie, 4 Option consommateurs (OC) retained Econalysis Consulting Services (ECS), a 5 Canadian consulting firm offering regulatory services to clients o n the electricity and 6 natural gas matters, to provide evidence that would assist the Régie in evaluating the 7 issues associated with HQD’s new Supply Plan. 8 9 The Evidence was prepared by Bill Harper who, prior to joining ECS in July 2000, 10 worked for over 25 years in the energy sector in Ontario, first with the Ontario Ministry of 11 Energy and then, with Ontario Hydro and its successor company Hydro One. Since 12 joining ECS, he has assisted various clients participating in regulatory proceedings on 13 issues related to electricity and natural gas utility revenue requirements, cost 14 allocation/rate design a nd supply planning. Mr. Harper has served as an expert witness 15 in public hearings before the Manitoba Public Utilities Board, the Manitoba Clean 16 Environment Commission, the Régie, the Ontario Energy Board, the Ontario 17 Environmental Assessment Board and a Select Committee of the Ontario Legislature on 18 matters dealing with electricity regulation, rates and supply planning. His most recent 19 experience with supply planning matters includes: • 20 The preparation of comments/evidence and appearance as an expert witness on 21 behalf of OC in the Régie proceeding (R-3470-2001) dealing with HQD’s 2002- 22 2011 Supply P lan. • 23 The preparation of evidence 17 and appearance as a n expert witness before the 24 Manitoba Clean Environment Commission with respect to its review of the Need 25 for and Alternatives to the Wuskwatim Hydro Generation/Transmission project 26 proposed by Manitoba Hydro. Mr. Harper’s responsibilities included review and 27 comment on: a) Manitoba Hydro’s supply/demand outlook and the need for the 28 additional supply, b) Manitoba Hydro’s levelized costing methodology used for 29 screening alternatives to Wuskwatim, c) the methodology used by Manitoba 17 The evidence was jointly prepared by Mr. Harper and Dr. Higgin. 4 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Hydro to evaluate the economics and benefits of the Wuskwatim project and d) 2 the economic, financial and operational risks associated with the project.; 3 • 4 Providing expert advice and support to clients in British Columbia participating in the BCUC proceedings dealing with: 5 o The electricity demand/supply outlook for Vancouver Island and the 6 proposed Electricity Purchase Agreement between BC Hydro and Duke 7 Point Power, 8 o The natural gas demand/supply outlook for Vancouver Island and the 9 Terasen Gas (Vancouver Island) application for Liquified Natural Gas 10 Storage Facilities to increase peak supply capability to the Island , and 11 o BC Hydro’s proposed 2005 Resource Expenditure and Acquisition Plan 12 (i.e., BC Hydro’s proposed 2005 Electricity Supply Plan). 13 14 A full copy of Mr. Harper’s CV is attached in Appendix A. 15 16 The evidence generally follows the structure of HQD’s Application and, in turn, 17 considers HQD’s load forecast; overall needs (allowing for reliability and reserve 18 considerations ); existing (and currently planned) supplies; the strategy for acquisition of 19 additional supply requirements and issues arising from previous Régie decisions. In 20 doing so the evidence attempts to build on the findings of previous Régie proceedings 21 by looking at changes from both: 22 • 23 24 The 2002-2011 Supply Plan and the resulting Régie decision (D-2002-17 and D2002-169) and • The 2003 Plan Update which was the basis for the Régie’s report (A-2004-01) to 25 the Minister of Natural Resources on Québec’s energy security and the Suroît 26 project. 5 Evidence of William Harper 1 3 Hydro-Québec Distribution Régie File R-3550-2004 HQD’s Load Forecast 2 3 3.1 HQD’s Expected Sales Forecast 4 5 Based on the most likely economic and demographic outlook and currently planned 6 energy efficiency initiatives, HQD’s load forecast18 calls for electricity energy sales to 7 customers to increase from 165.7 TWh in 2003 to 184.8 TWh in 201419. 8 9 In its Decision regarding HQD’s first Supply Plan, the Régie indicated that it generally 10 accepted HQD’s medium (or expected) load forecast for planning purposes 20. However, 11 in its 2004 report to the Minister of Natural Resources (A-2004-01), the Régie 12 recommended that a medium -high growth scenario be used for planning purposes. 13 14 Table 1 contrasts HQD’s current load forecast with the load forecasts underpinning its 15 2002-2011 Supply Plan, its 2003 Supply Plan Update and the medium-high growth 16 scenario recommended by the Régie in A-2004-01. Table 1 Comparison of Load Forecasts (Sales to Customers in TWh) 2001 2002 2003 2004 2005 2006 2007 2006 2009 2010 2011 2012 2013 2014 Source: - 2005-2014 Plan 154.5 159.2 165.7 164 169.3 173.1 175.3 177.7 178.8 180.1 181.2 182.9 183.6 184.8 - 2002-2011 Plan Difference 154.6 -0.1 156.7 2.5 160.2 5.5 163.8 0.2 165.5 3.8 167.2 5.9 168.8 6.5 170.8 6.9 171.7 7.1 173.2 6.9 174.6 6.6 n/a n/a n/a - 2003 Plan Update Difference 154.5 0 159.2 0 164.2 1.5 166.4 -2.4 169.7 -0.4 173.8 -0.7 175.4 -0.1 177.5 0.2 179.5 -0.7 182.1 -2 184.4 -3.2 n/a n/a n/a 164.3 1.4 167.1 -3.1 169.7 -0.4 173.8 -0.7 175.4 -0.1 177.5 0.2 179.5 -0.7 182.1 -2 184.4 -3.2 n/a n/a 168.8 -4.8 172.7 -3.4 177.5 -4.4 180.2 -4.9 183 -5.3 185.3 -6.5 187.9 -7.8 190.5 -9.3 n/a n/a - A-2004-01 HQD's Medium Scenario Difference n/a - A-2004-01 Regie's Medium-High Scenario Difference 17 18 Source: n/a HQD-2, Document 1, pages 20, 26 and 31 A-2004-01, pages 37 and 55 18 Reflects HQD’s medium load forecast scenario based on the most probable values for the various underlying economic and demographic factors (HQD-2, Document 1, page 16) 19 HQD-2, Document 1, pages 20 and 26 Tables 2.3 and 2.5 20 D-2002-169, page 22 6 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments re: Variances from the 2002-2011 Plan 2 3 The current load forecast is considerably higher than that underpinning the 2002-2011 4 Supply Plan. There are a number of reasons for this: 5 6 • First, actual sales through to 2004 have been significantly higher than projected in 7 2001 when the first Supply Plan was prepared – particularly when allowance is 8 made for the strike in 2004 at the ABI aluminium facility. This is primarily due to 9 exceptional electricity sales growth in both the Residential and Agriculture sector as 10 well as in the General and Institutional sector21. Table 2 contrasts the previously 11 forecast values with the actual values for the main economic and demographic 12 factors underlying the electricity sales in these two sectors 22 and substantiates 13 HQD’s comments attributing the growth to residential construction and strong 14 commercial growth23. 21 22 23 HQD-5, Document 1.1, page 15, Response 3.1 The factors shown are those identified in HQD-5, Document 1.1, page 3, Response 1.1 HQD-5, Document 1.1, page 17, Response 3.1 7 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 2 Demographic and Economic Factors - Forecast vs. Actual Results 2002 2003 2004 7,432 7,446 7,458 7,492 7,483 7,530 Tertiary GDP (Annual Growth Rate) - 2002-2011 Plan 2.40% 1 - Actual 4.80% 2.70% 2.50% 2.40% 2.70% 24.8 45.0 30.4 46.0 2.30% 0.90% 2.40% 2.10% 5.5 6.85 5.25 7.01 Population (millions) 1 - 2002-2011 Plan 2 - Actual Household Formation (Thousands) - 2002-2011 Plan 3 - Actual 26.8 40.0 Disposable Income (Annual Growth) - 2002-2011 Plan 2.20% - Actual 3.60% 3 Natural Gas Prices ($/m ) - 2002-2011 Plan - Actual Notes: 1) 2002/2011 Plan Values as per R-3470-2011, HQD-2, Doc 1, page 5 2) Actual values are as per HQD-5, Document 1.1, page 30 Acutal values shown for 2004 are the current forecast values per HQD-2, Document 1, page 13. 3) Actual household formation values are calculated from above referenced sources 1 2 3 5.5 4.23 • Second, the growth rates for the demographic and economic factors underpinning 4 the forecast beyond 2004 are higher in the 2005-2014 Plan than they were in the 5 2002-2011 Plan, as demonstrated in Table 3 below. While differing from that used 6 in the previous plan, HQD’s current economic forecast is in line with those recently 7 prepared by other parties 24. 24 HQD-5, Document 1.1, pages 5-11 8 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 3 Comparison of Economic and Demographic Forecast Assumptions Population ('000's) - 2005/14 Plan - 2002/11 Plan Difference 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 7530 7483 0.63% 7566 7507 0.79% 7597 7529 0.90% 7628 7551 1.02% 7657 7571 1.14% 7685 7590 1.25% 7713 7608 1.38% 7738 7624 1.50% 7763 n/a 7786 n/a 7808 n/a 5.4 5.1 5.88% 8.2 7.7 6.49% 10.9 10.2 6.86% 13.6 12.7 7.09% 16.4 15.3 7.19% 19.3 17.9 7.82% 22.3 20.7 7.73% 25.0 n/a 27.8 n/a 30.6 n/a 7.16 5.00 43.20% 6.82 5.00 36.40% 6.45 5.05 27.72% 6.24 4.90 27.35% 5.86 5.15 13.79% 5.59 5.40 3.52% 5.55 5.60 -0.89% 5.49 n/a 5.54 n/a 5.79 n/a GDP (% Cumulative growth) - 2005/14 3.0 - 2002/11 2.5 Difference 20.00% 3 Natural Gas Prices ($/m ) - 2005/14 7.01 - 2002/11 5.25 Difference 33.52% Notes: 1) Source for 2005/2014 data: HQD-2, Document 1, page 13 2) Source for 2002/2011 data: R-3470-2001, HQD-2, Document 1, page 5 1 2 3 • Third, the expansion of the Alouette plant leading to increased sales of 4.3 TWh by 200625. 4 5 However, offsetting these factors are the higher energy efficiency reductions 6 incorporated in the current 2005-2014 Plan. These reductions are the result of including 7 the anticipated impacts of HQD’s 2005-2010 PGEÉ and allowances for natural energy 8 efficiency improvements in the industrial sector 26. The difference in energy efficiency 9 savings assumed for the two plans are summarized in Table 4. 25 26 HQD-5, Document 1.1, page 18. HQD-5, Document 6, pages 20-21, Response 22.1 9 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 4 Energy Efficiency Assumptions (TWh) 2004 Domestic & Agriculture 2005-2014 Plan 0.9 2002-2011 Plan 1.1 Difference -18.2% 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 1.4 1.3 7.7% 1.7 1.3 30.8% 2.2 1.5 46.7% 2.7 1.7 58.8% 3 1.8 66.7% 3.5 2 75.0% 3.9 2.2 77.3% 4 n/a 4.2 n/a 4.4 n/a G&I 2005-2014 Plan 2002-2011 Plan Difference 0.5 0.7 -28.6% 0.7 0.8 -12.5% 0.8 0.8 0.0% 1 0.9 11.1% 1.1 0.9 22.2% 1.4 1 40.0% 1.6 1.1 45.5% 1.9 1.2 58.3% 2 n/a 2.1 n/a 2.2 n/a Industrial 2005-2014 Plan 2002-2011 Plan Difference 1.6 1.1 45.5% 2 1.1 81.8% 2.4 1.1 118.2% 2.8 1.1 154.5% 3.3 1.1 200.0% 3.6 1.1 227.3% 4.1 1.1 272.7% 4.4 1.1 300.0% 4.7 n/a 5 n/a 5.3 n/a Other 2005-2014 Plan 2002-2011 Plan Difference 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 0.2 0.0% 0.2 n/a 0.2 n/a 0.2 n/a Unallocated 2005-2014 Plan 2002-2011 Plan Difference 0 0.1 -100.0% 0 0.2 -100.0% 0 0.4 -100.0% 0 0.4 -100.0% 0 0.4 -100.0% 0 0.4 -100.0% 0 0.4 -100.0% 0 0.4 -100.0% 0 n/a 0 n/a 0 n/a Total 2005-2014 Plan 2002-2011 Plan Difference 3.2 3.2 0.00 4.3 3.6 0.70 5.1 3.8 1.30 6.2 4.1 2.10 7.3 4.3 3.00 8.2 4.5 3.70 9.4 4.8 4.60 10.4 5.1 5.30 10.9 n/a 11.5 n/a 12.1 n/a Source: HQD-5, Document 6, pages 20-21, Response 22.1. Totals may differ from reference due to rounding. 1 2 3 Comments re: Variances from the 2003 Update 4 5 Over the period 2005-2011, the electricity sales forecast underpinning the current Plan 6 is less than that associated with the 2003 Plan Update. HQD suggests that the reasons 7 for this are both the lower economic and demographic assumptions and greater energy 8 efficiency savings27 associated with the 2005-2014 Plan. 9 10 Table 5 compares the basic demographic and economic assumptions underlying the 11 two sale forecasts and does not appear to substantiate HQD’s claim that the lower sales 12 forecast in the 2005-2014 Plan is, in part, due to changes in the demographic and 27 HQD-5, Document 6, page 11, Response 12.1 10 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 economic assumptions. Indeed, the current assumptions for core variables such as 2 GDP growth, population growth and household formation all appear to be the same or 3 higher than those used in the 2003 Plan Update. 4 Table 5 Comparison of Economic and Demographic Forecast Assumptions 2004 2005 2006 2007 2008 2009 2010 2011 7,530 7,521 0.1% 7,566 7,546 0.3% 7,597 7,572 0.3% 7,628 7,597 0.4% 7,657 7,621 0.5% 7,685 7,643 0.5% 7,713 7,664 0.6% 7,738 7,684 0.7% Household Formation (#) 2005-2014 Plan 46.00 2003 Plan Update 35.50 Difference 29.6% 39.00 31.50 23.8% 36.00 31.40 14.6% 34.00 30.50 11.5% 32.00 28.50 12.3% 30.00 27.50 9.1% 30.00 26.50 13.2% 28.00 25.80 8.5% GDP (% Cumulative growth) 2005-2014 Plan 3 2003 Plan Update 3.2 Difference -6.3% 5.4 5.5 -1.8% 8.2 8.2 0.0% 10.9 10.9 0.0% 13.6 13.6 0.0% 16.4 16.3 0.6% 19.3 19.1 1.0% 22.3 22 1.4% Natural Gas Prices ($/m3) 2005-2014 Plan 7.01 2003 Plan Update 5.94 Difference 18.0% 7.16 5.58 28.3% 6.82 4.96 37.5% 6.45 5.05 27.7% 6.24 4.94 26.3% 5.86 5.02 16.7% 5.59 5.17 8.1% 5.55 5.36 3.5% Population ('000's) 2005-2014 Plan 2003 Plan Update Difference Notes: 1) Source for 2005-2014 Plan data: HQD-2, Document 1, page 13 2) Source for 2003 Plan Update data: A-2004-01, page 40 5 6 7 However, there a couple of other key reasons why the current sales forecast is likely 8 lower: 9 • First, HQD has captured in the current load forecast the impact of the Régie’s recent 10 decision to abrogate the BT rate and the resulting loss of load is expected to be 11 about 1.3 TWh by 201128. 12 • 13 Second, the current forecast captures 29 the recent cancellation of various expansion projects in the aluminium sector, notably the Alcoa plant at Baie-Comeau. 28 HQD-2, Document 1, page 25 11 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 In the case of energy efficiency savings, Table 6 does support the premise that the 2 savings in the current 2005-2014 Supply Plan exceed those underpinning the 2003 Plan 3 Update. Table 6 Comparison of Energy Efficiency Savings (TWh) - 2005-2014 Plan - 2003 Plan Update Difference 2004 2005 2006 2007 2008 2009 2010 2011 3.2 3.4 4.1 4.1 5.1 4.9 6.1 5.7 7.2 6.5 8.3 7.3 9.4 8 10.3 8.6 -0.2 0 0.2 0.4 0.7 1 1.4 1.7 Source: 2005-2014 Plan: HQD-2, Document 1, page 37 2003 Plan Update: A-2004-01, page 39 4 5 6 Furthermore, the difference in energy efficiency savings accounts for a substantial 7 portion of the overall variance between the two sales forecasts. 8 9 3.2 HQD’s Expected Energy Requirements 10 11 A number of adjustments are required in order to translate HQD’s electricity sales 12 forecast into a forecast of electricity energy needs for supply planning purposes 13 including: 14 • 15 The exclusion of sales to non-grid connected communities (i.e., remote communities), 16 • The inclusion of consumption for internal use, and 17 • An allowance for losses. 18 Table 7 sets out the calculation of the electricity needs for supply planning purposes 19 associated with the 2005-2014 Supply Plan and contrasts each of the adjustments with 20 the values used in the 2002-2011 S upply Plan. 29 HQD-2, Document 1, page 24 12 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 7 Determination of Energy Requirements for Supply Planning (TWh) 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Customer Sales Forecast - 2005-2014 Plan 164 - 2002-2011 Plan 163.8 Difference 0.2 169.3 165.5 3.8 173.1 167.2 5.9 175.3 168.8 6.5 177.7 170.8 6.9 178.8 171.7 7.1 180.1 173.2 6.9 181.2 174.6 6.6 182.9 n/a 183.6 n/a 184.8 n/a Less Sales to Remote Communities - 2005-2014 Plan - 2002-2011 Plan Difference 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 0.3 0 0.3 n/a 0.3 n/a 0.3 n/a Plus Internal Use - 2005-2014 Plan - 2002-2011 Plan Difference 0.5 0.4 0.1 0.5 0.4 0.1 0.5 0.4 0.1 0.5 0.4 0.1 0.4 0.4 0 0.5 0.4 0.1 0.4 0.4 0 0.4 0.4 0 0.4 n/a 0.3 n/a 0.3 n/a Plus Losses - 2005-2014 Plan - 2002-2011 Plan Difference 12.5 13.5 -1 12.7 13.7 -1 13 14 -1 13.1 14.2 -1.1 13.3 14.4 -1.1 13.4 14.6 -1.2 13.4 14.8 -1.4 13.5 15 -1.5 13.7 n/a 13.7 n/a 13.8 n/a 182.2 179.3 2.9 186.3 181.3 5 188.5 183.0 5.5 191.1 185.3 5.8 192.3 186.3 6 193.7 188.0 5.7 194.7 189.7 5 196.6 n/a 197.3 n/a 198.6 n/a Plannning Energy Needs - 2005-2014 Plan 176.6 - 2002-2011 Plan 177.4 Difference -0.8 1 2 3 Source: 2005-2014 Plan: HQD-2, Document 1, page 20 2002-2011 Plan: R-3470-2001, HQD-2, Document 1,page 21 and HQD-2, Document 3, page 2 Comments 4 5 From a materiality perspective , the only major change is the allowance for transmission 6 and distribution losses. For the current plan a loss factor of 7.5% was assumed for the 7 entire 2005-2014 period, in contrast to the 2002-2011 Supply Plan which assumed loss 8 factors in excess of 8%. HQD indicates 30 that the 7.5% is based on the experience of 9 the last three years. HQD has indicated 31 in its response to OC’s information requests 10 that “internal use” now captures construction site consumptions whereas formerly it did 11 not. However, the impact of this change is only in the order of 0.1 TWh per annum. 12 30 31 HQD-2, Document 1, page 27 HQD-5, Document 6, pages 15-16, Response 16.2 13 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Overall total expected energy requirements are projected to increase from 178.2 TWh in 2 200332 to 198.6 TWh in 2014 – which represents an average annual growth rate of just 3 under 1.0% 33. 4 5 3.3 HQD’s Expected Power Requirements 6 7 In terms of power requirements, HQD’s peak demand is projected to increase from 8 34,450 MW in 2003-2004 to 37,365 MW in 2013-2014 – which represents an average 9 annual growth rate of just over 0.8% 34. The power requirements forecast is derived35 10 from the expected energy requirements forecast and assumptions regarding the 11 characteristics of the energy use (e.g., space heating, water heating, etc.). Shifts in 12 energy by sector or end use application can lead to differences in growth rates as 13 between energy and power requirements. 14 15 Comments 16 17 Table 8 contrasts the expected power and energy requirements for 2010-2011 under 18 the current plan with those associated with the 2002-2011 Supply Plan and the 2003 19 Plan Update. The currently anticipated power requirements for 2010-2011 exceed 20 those of the original 2002-2011 Plan but are slightly less than those of the 2003 Plan 21 Update, thereby maintaining the same relative relationships as discussed previously 22 regarding the energy requirements for 2011. 32 HQD-5, Document 1.1, page 31, Table R6.1d 2003 was used as the base year for the calculation due to the impact the strike at ABI has on 2004 usage 34 HQD-2, Document 1, pages 21 and 24 35 HQD-2, Document 1, pages 20-21 33 14 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 8 Comparison of Power and Energy Requirements 2005-2014 Plan 2002-2011 Plan 2003 Update 194.7 189.7 198.7 0 -2.57% 2.05% 2010-2011 Req. 36,700 35,680 37,240 Var. from 2005-2014 Plan 0 -2.78% 1.47% Energy (TWh) 2011 Req. Var from 2005-2014 Plan Power (MW) Source: HQD-2, Document 1, Tables 2.6, 2.7, 2.9 and 2.10 1 2 3.4 Load Forecast Sensitivity 3 4 Similar to the 2002-2011 Plan, HQD has described the potential sensitivity of the 5 expected energy and power requirements to both the underlying economic and 6 demographic assumptions as well as to variations in weather. 7 8 For the future energy requirements, the sensitivity (based on one standard deviation36) 9 to annual variations in weather is approximately 1.8 TWh and this value is virtually 10 constant throughout the forecast period 37 such that it actually declines as a percentage 11 of total energy requirements. However, the sensitivity (again at one standard deviation) 12 of future requirement to economic and demographic factors increases from 4.6 TWh in 13 2005 to 15.2 TWh in 2014 – which represents an increase both in absolute terms and 36 Assuming a “Normal” probability distribution, there is roughly a 16% probability that the expected value will be exceeded by more than one standard deviation. 37 HQD-2, Document 1, page 46 and HQD-5, Document 6, page 22, Response 25.1 15 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 as a percentage of total energy requirements 38. Since the two sources of variation are 2 independent of each other, their combined impact on the sensitivity of future energy 3 requirements is less than the sum of two factors and, based on one standard deviation, 4 ranges from 5 TWh in 2005 to 15.3 TWh in 2014. This can be seen from Table 9 which 5 summarizes the sensitivity of the two sources of variation both independently and 6 together. 7 Table 9 Sensitivity Range - One Standard Deviation 2005 2006 2007 2008 2009 2010 2011 1012 2013 2014 4.6 2.5 5.0 2.7 6.2 3.3 7.6 4.0 8.7 4.5 9.7 5.0 11.0 5.7 12.2 6.2 13.7 6.9 15.2 7.7 1.8 1.0 1.8 1.0 1.8 1.0 1.8 0.9 1.8 0.9 1.8 0.9 1.8 0.9 1.8 0.9 1.8 0.9 1.8 0.9 5.0 2.7 5.3 2.8 6.4 3.4 7.8 4.1 8.9 4.6 9.9 5.1 11.2 5.7 12.4 6.3 13.8 7.0 15.3 7.7 Factor Econ&Demographic - TWh -% Weather - TWh -% Total - TWh -% Source: HQD-2, Document 1, pages 43, 46 and 50 8 9 10 For future power requirements, the sensitivity to economic and demographic factors is 11 roughly the same/perhaps slightly less (in % terms) than for energy. However, as one 12 would expect, the sensitivity of power requirements to variations in weather is greater 13 (in percentage terms) than for energy requirements. Overall the sensitivity (based on 14 one standard deviation) of both factors increases from 4.3% of expected power 15 requirements in 2004-05 to 8.2% of power requirements in 2013-14 39. 38 39 HQD-2, Document 1, page 43 HQD-2, Document 1, page 50 16 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments re: Changes from the 2002-2011 Supply Plan 2 3 HQD’s 2002-2011 Supply Plan also included sensitivity analyses with respect to 4 economic and demographic assumptions as well as weather. Table 10 sets out the 5 “coefficients of variation” associated with one-standard deviation attributable to 6 economic and demographic factors in both Plans. 7 Table 10 Energy Coefficient of Variation for Economic and Demographic Factors Horizon 2002-2011Plan 2005-2014 Plan 3 Years 4 Years 5 Years 6 Years 7 Years 8 Years 9 Years 10 Years 3.4% 3.3% 4.1% 4.0% 4.9% 4.5% 5.5% 5.0% 6.1% 5.7% 6.8% 6.2% 7.4% 6.9% 8.1% 7.7% Source: HQD-2, Document 1, page 43 R-3470-2001 Phase II, HQD-6, Document 1, page 13 8 9 10 The sensitivity of the current (2005-2014) Plan is deemed to be slightly less than that of 11 the 2002/11 Plan with respect to these factors. 12 13 In the case of weather, the sensitivity of the 2005-2014 Plan is roughly the same as the 14 previous plan. The 2002-2011 Plan’s sensitivity to weather was 1.9 TWh40 – based on 15 one standard deviation (as compared to 1.8 TWh in the current 2005-2014 Plan). 16 17 Comments re: Régie A-2004-01 Findings 18 19 In its June 2004 Report to the Minister, the Régie concluded41 that sales growth was 20 most likely to fall between the results of sales forecasts based on the medium and the 21 strong economic/demographic growth scenarios. The reasons for this included: 40 41 R-3470-2001, HQD-2, Document 1, page 26 A-2004-01, pages 33-34. 17 Evidence of William Harper • 1 2 Hydro-Québec Distribution Régie File R-3550-2004 The recently observed strong growth in the residential due to significant increases in construction starts. 3 • A competitive position of electricity better than forecast for 2004-2005. 4 • Forecast increases in consumption for the industrial sector over the period, 5 coupled with uncertainty regarding the future industrial expansion, particularly in 6 the aluminium sector. 7 8 Many of these same factors are still present and creating uncertainty with respect to the 9 current sales/requirements forecast: • 10 Continued strong growth through 2004, this time in the General and Institutional sectors 42. 11 • 12 13 The Régie just recently approved 43 a distribution rate increase of 1.2% for 2005, as opposed to the 2.7% originally requested. • 14 The inclusion of fairly conservative assumptions about future industrial expansions in the 2005-2014 Plan44. 15 16 As a result, the circumstances continue to exist to support the logic used by the Régie 17 when it adopted a higher than medium sales forecast for planning purposes. 18 19 3.5 Conclusions 20 21 Current Load Forecast 22 23 Overall, HQD’s load forecast appears to be reasonable when considered in terms of the 24 changes observed from both the 2002-2011 Plan and the 2003 Update. However, the 25 same issues the Régie raised in its A-2004-01 Report to the Minister regarding the 26 (upside) uncertainty associated with the load forecast still exist. Therefore, it would be 27 prudent for HQD to either: 42 43 44 HQD-5, Document 1.1, page 17, Response 3.1 D-2005-34 HQD-5, Document 1.1, pages 20-21, Response 3.1 18 Evidence of William Harper • 1 2 Hydro-Québec Distribution Régie File R-3550-2004 Adopt a higher load forecast (e.g., a medium-high forecast such as adopted by the Régie in A-2004-01) for planning purposes, or • 3 4 Ensure that the supply plan developed based on the medium load forecast is sufficiently flexible to meet higher growth scenarios. 5 6 Load Forecast Uncertainty 7 8 Relative to the first (2002-2011) Plan, HQD’s evidence regarding load forecast 9 uncertainty is much better presented, particularly in that it clearly demonstrates the 10 combined effects of both weather and demographic/economic factors. This serves to 11 address the related issues raised45 in the Comments/Evidence prepared by ECS with 12 respect to the 2002-2011 Plan. 45 R-3470-2001 – ECS Comments, December 14, 2001, page 20 and ECS Evidence, March 19, 2002, page 8. 19 Evidence of William Harper 1 4 Hydro-Québec Distribution Régie File R-3550-2004 HQD’s Supply Requirements 2 3 4.1 Total Supply Requirements 4 5 4.1.1 Energy Requirements 6 7 Total energy requirements for purposes of supply planning are based on the energy 8 requirements discussed earlier (see Table 7) plus an allowance to manage the Heritage 9 Pool supplies in real time 46. These later requirements are discussed in more detail in 10 Section 4.2 below. 11 12 HQD has also established 47 a longer term energy reliability criterion which calls for HQD 13 to have sufficient energy supply capability in place such that its dependence on short- 14 term markets beyond a four year horizon is less than 5 TWh per annum under a higher 15 load growth scenario 48. For purposes of this long-term criterion, high load growth is 16 defined as the medium growth scenario plus 7.8 TWh, which is based on one standard 17 deviation for four years forward (currently 2008) 49. 18 19 The 5 TWh is based on the current interconnection capacity that HQD expects to be 20 able to rely on after allowing for both technical and market constraints and also allowing 21 for HQP’s potential need to access the interconnected markets to guarantee the 22 Heritage Pool supplies50. 46 47 48 49 50 HQD-3, HQD-3, HQD-3, HQD-5, HQD-3, Document 3, page 5 Document 1, page 6 Document 3, page 15, lines 18-20 Document 6, page 48, Response 61.1 Document 1, page 14. See also Section 5.1.1 below. 20 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments 2 3 In its decision regarding HQD’s first Supply Plan, the Régie accepted the energy 4 reliability criteria proposed by HQD which was that HQD demonstrate the ability to meet 5 a strong growth scenario over the entire planning horizon. At the same time, the Régie 6 also directed HQD to propose alternative criteria in conjunction with its next Supply 7 Plan51. The now proposed energy reliability criteria call for HQD to be able to meet – 8 with four years’ notice - the expected load forecast plus one standard deviation. 9 Furthermore, the standard deviation used is that associated with the fourth year of the 10 forecast on the basis that greater uncertainty beyond that year can be addressed in 11 future plans. 12 13 HQD’s currently proposed approach of “fixing” the standard deviation used in the 14 analysis, based on the timeframe required to place new resources in service, appears 15 reasonable. However, it is questionable as to whether the four-year time horizon used 16 in the current Plan is sufficient. First, the four -year time horizon includes the current 17 year (in this case 2005) during which the plan is under review and approval for the 18 request for additional CFTs still subject to approval by the Régie. Since the 4 to 5 ½ 19 year time horizon for new supply contracts starts with the issuing of CFTs 52, the current 20 year should not be “counted” as one of the four lead years. Assuming the a new CFT 21 was issued in the second half of 2005, shortly after a decision by the Régie on the 22 currently proposed plan; the four -year lead time would suggest an in-service date of late 23 2009. Indeed, HQD has acknowledged this additional time requirement and noted that 24 additional modulable capacity required to reduce dependence on short-term markets 25 would not be available until the end of 2009 53. 26 27 Also, the criterion needs to recognize the lag that will exist if commitments are not made 28 based on the current plan. For example, if the need for new supply is not identified until 51 52 53 D-2002-169, pages 46-47 HQD-3, Document 3, pages 15 and 39 HQD-5, Document 6, page 39, Response 50.1.2 and pages 46-47, Responses 59.1 and 60.1 21 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 the next annual update (the end of 2005) and Régie approval for a new CFT is obtained 2 in 2006, the earliest additional capacity could be in-service would likely be 2010. Given 3 these two considerations, HQD should adopt the one standard deviation value 4 associated with a six year lead time. Based on Table 9 (above) the revised value for 5 the long-term energy reliability criterion would be 9.9 TWh. 6 7 Also, unlike the 2002 Plan’s criteria, the current energy planning criteria do not address 8 the potential for variations in requirements in the short-term (i.e., the next 4-5 years). 9 As demonstrated in Table 11, energy requirements over the short-term can vary from 10 those forecasted due to weather or economic influences. In its first Supply Plan, HQD’s 11 planning criteria also called for it to be able to meet a “strong growth” scenario during 12 the initial years of plan. In the initial years of the current plan the strong growth scenario 13 is similar to the expected load forecast plus one standard deviation. HQD should also 14 adopt a short-term energy reliability criteria which requires it to demonstrate an ability to 15 meet the medium load forecast plus at least one standard deviation while limiting 16 reliance on the inter-ties to 5 TWh per annum. 17 Table 11 Additional Energy Capability Required (TWh) Probability Usage Exceeded 2005 2006 2007 2008 2009 2010 5.00 5.30 6.40 7.80 8.90 9.90 10% 6.90 7.31 8.83 10.76 12.28 13.66 5% 8.25 8.75 10.56 12.87 14.69 16.34 2% 10.28 10.89 13.15 16.03 18.29 20.34 One Standard Deviation (~16%) Source: 1) One standard deviation: HQD-3, Document 3, page 38 2) 10%, 5% and 2% calculated assuming a Normal probability distribution 18 22 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Finally, the use of one standard deviation to the medium load forecast in setting the 2 energy reliability criteria means that the “limit” is likely to be exceeded more than 15% of 3 the time 54. Based on the current load forecast, one standard deviation represents 5 4 TWh in 2005 – increasing to 9.9 TWh in 201055. Table 11 also sets out both the 5 additional energy usage associated with the one standard deviation requirement and 6 also the additional usage associated with reducing the uncertainty to 10%, 5% and 2% 7 respectively. 8 9 4.1.2 Capacity Requirements 10 11 For planning purposes, capacity requirements include an allowance for reserves 12 consistent with the NPCC (Northeast Power Coordinating Council) resource adequacy 13 criterion which requires that the probability of disconnecting a non-interruptible customer 14 due to resource inadequacies will be no more than once in ten years or 2.4 hours per 15 annum 56. In the 2002-2011 Supply Plan, HQD indicated that this translated into an 16 overall reserve margin of 11-13% 57. Based on more recent studies, Hydro-Québec is 17 now of the view58 that the reserve requirements to meet the NPCC criteria are 18 somewhat less: 19 • 8.8% for the first planning year (i.e., 2004-2005) 20 • 9.2% fore the next year (2005-2006) 21 • 9.5% for the third year of the Plan (2006-2007) and 22 • 10.1% for the fourth and subsequent years of the Plan. 23 However, HQD noted in its Application, that these values would be updated, if 24 necessary. 25 Table 12 sets out the annual capacity requirements for HQD overall based on these 26 reserve margins. 54 HQD-3, Document 1, page 6. Also, based on a Normal probability distribution, the probability of exceeding the “mean” by more than one standard deviation is 15.87%. 55 HQD-2, Document 1, page 50, Table 2.17 56 HQD-3, Document 1, page 7 57 R-3470-2001, HQD-2, Document 3, Annexe 3D, page 2 58 HQD-3, Document 1, page 9, Table 2.2 23 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Table 12 HQD's Total Capacity Requirements (MWs) 20042005 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 Peak Demand 34,184 35,412 35,674 36,011 36,282 36,532 36,699 36,909 37,144 37,365 Reserve Margin 3,008 3,258 3,389 3,637 3,664 3,690 3,707 3,728 3,752 3,774 Total Capacity Req. 37,192 38,670 39,063 39,648 39,946 40,222 40,406 40,637 40,896 41,139 2 3 Source: HQD-3, Document 3, page 6 4 Comments 5 6 Hydro-Québec’s Annual Interim (Reliability) Assessment59 was recently made public by 7 the NPCC. In it, Hydro-Québec indicates that the required reserves (consistent with the 8 NPCC’s planning criteria) are 9.6%, 9.7% and 10.3% for 2004-2005, 2005-2006 and 9 2006-2007 respectively. These reserve margin requirements are higher than those 10 presented by HQD in its Application. However, most of the variance appears to be due 11 to the treatment of interruptible power contracts. In the Annual Interim Assessment, 12 interruptible power contracts are treated as a supply resource and inc luded based on 13 their gross value of 800 MW 60. In contrast, the 2005 Supply Plan also treats 14 interruptible power contracts as a supply resource but includes the net value of the 15 contracts (560 MW) in its supply/demand balance calculations 61. The 240 MW 16 difference represents roughly 0.7% of the capacity requirements during the three year 17 period62 concerned and accounts for most of the variance in each year. 18 19 Also, HQD assumes that the capacity reserve margin is constant beyond 2006-2007 at 20 the 2007-2008 value. HQD indicates that the rationale for this is the fact that it could 59 The document is titled “Québec Control Area Interim Review of Resource Adequacy” and dated December 2004. 60 HQD-5, Document 10 (Revised), pages 29-30, Response 16.2 61 HQD-3, Document 3, page 26 62 HQD-3, Document 3, page 26 indicates that the annual peak demand during this period is between 34,184 MW and 35,674 MW 24 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 make additions to peak capacity at 36 month out 63. However, this statement is at odds 2 with the balance of HQD’s evidence which suggests a timeline of four years or more is 3 required for a ll resources except wind power 64. Furthermore, given the annual planning 4 review cycle used by HQD and discussed in the previous Section, once the current Plan 5 has been adopted new supplies will not be available until the winter of 2010-2011. As a 6 result, it would be prudent for HQD to project its reserve margin requirements out to the 7 winter of 2009-2010 and use the reserve margin as determined for that year to project 8 reserve requirements for subsequent years. 9 10 There is no information available as to the reserve margins required beyond 2007-2008 11 in order to maintain the NPCC reliability criteria However, given that the load forecast 12 uncertainty increases over the planning horizon65, one would expect the reserve margin 13 requirements for the period 2008-2009 through 2013-2014 to be higher. Indeed, simply 14 increasing the reserve requirements in line with the annual increase in load forecast 15 uncertainty would add 0.5 percentage points for each year. 16 17 The capacity planning reserve margins used by Manitoba Hydro 66 and BC Hydro 67, two 18 other provincial utilities with predominantly hydraulic resources, are12% and 14% 19 respectively. The electrical systems for both of these provinces are admittedly different 20 and the reserve requirements will not be the same as those for Hydro-Québec. 21 However, after revising the long-term planning reserve requirements to reflect the 22 reserve requirements for 2009-2010 (as opposed to 2007-2008), HQD’s long-term 23 capacity planning reserve requirements are likely to be closer to these values. 24 63 HQD-3, Document 1, page 9 HQD-5, Document 6, page 39, Response 50.1.2 and page 8, Response 9.2. Also, HQD-3, Document 3, pages 19 and 39 65 HQD-2, Document 1, page 45 66 Manitoba Hydro’s April 2003 NFAAT Application, Chapter 5, pages 12-13. 67 BC Hydro, 2004 Integrated Electricity Plan, Section 2, page 32 64 25 Evidence of William Harper 1 4.2 Hydro-Québec Distribution Régie File R-3550-2004 Heritage Pool Supply 2 3 4.2.1 Total Supply Available 4 5 Under the terms of the Heritage Pool68, HQP is required to provide HQD with 179.52 69 6 TWh (includes transmission and distribution losses as well as internal uses and plant 7 consumption by HQD, HQP and HQT). After allowing for internal use by Hydro- 8 Québec, the Heritage Pool energy resources available to meet forecast customer 9 requirements are 178.9 TWh70. Furthermore the hourly load profile of the Heritage Pool 10 energy has been set by Regulation and ranges from a maximum of 34,342 MW to 11 11,420 MW 71. 12 13 The same Statute and Regulations require that HQP also provide the services and 14 reserves necessary to guarantee the availability of the specified Heritage Pool supplies 15 to HQD 72. As a result, HQP is required to provide some of the reserves necessary to 16 meet the overall NPCC resource adequacy requirements. Specifically, it is currently 17 estimated that the reserves associated with ensuring sufficient supply is in place to 18 meet the 34,342 MW associated with the Heritage Pool are 3,100 MW (or roughly 9%). 19 This number is substantially less than the 3,600 MW used in the 2003 Plan Update 73. 20 21 Comments 22 23 There is an inconsistency between the reserve margin requirements associated with 24 total load in the original Application and those associated with the Heritage Pool supply. 25 Total reserve margin requirements are meant to address both load forecast uncertainty 68 69 70 71 72 73 As specified in la Loi sur Hydro-Québec and associated Orders in Council HQD-5, Document 10, page 36, Responses 22.1-22.2 HQD-5, Document 10, page 36, Response 22.2 HQD-3, Document 2, page 5 and R-3470-2001, HQD-2, Document 2, Annexe 2A HQD-3, Document 2, pages 5 and 6 HQD-3, Document 1, page 8 26 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 as well as uncertainty with respect to availability of generation. In contrast, HQP’s 2 responsibility for reserves with respect to the Heritage Pool extends only to generation 3 (supply) availability. HQD is responsible for load forecast uncertainty. As a result, one 4 would expect HQP’s reserve margin requirements for the Heritage Pool to be less (in 5 percentage terms) than the total reserve margin requirements for the system overall. 6 For 2004-2005, when load forecast uncertainty is likely to be fairly small, the two 7 reserve margins should be fairly close but the total reserve margin should still be higher. 8 This is not the case in the 2005-2014 Plan where, for 2004-2005, the total reserve 9 margin is 8.8% which is less than the 9% attributed to the Heritage Pool supply 10 capability. 11 12 However, with the revised system reserve margin requirements filed by HQD 74 this 13 inconsistency no lo nger appears to exist as the total system reserve requirements for 14 period 2004-2005 through 2006-2007 range from 9.6% to 10.3%. 15 16 4.2.2 Heritage Pool Dispatch 17 18 As indicated in Section 4.1.1, HQD forecasts that additional energy will be needed in 19 each year due to the need to manage the Heritage Pool in real time. This need arises 20 due to the protocols that have been established between HQD and TransÉnergie, the 21 entity responsible for the management of Québec’s electricity system in real time. 22 Essentially, HQD must provide advance notice to TransÉnergie as to how much 23 electricity is to be dispatched from: • 24 25 HQD’s long-term supplies acquired through CFTs – based on the contract terms and HQD’s direction to the suppliers themselves, • 26 27 Heritage Pool supplies – based HQD’s selection from the remaining hourly supply options available for the year concerned, and 74 Québec Control Area 2004 Interim Review of Resource Adequacy, December 2004 27 Evidence of William Harper • 1 Hydro-Québec Distribution Régie File R-3550-2004 Short-term purchases, up to and including real time purchases – based on the 2 supply available from short-term contracts and planned real-time spot market 3 purchases. 4 However, to the extent HQD’s actual supply requirements 75 in an hour differ from those 5 forecast by HQD and used to determine the resources it has dispatched, the differences 6 will be made up by HQP 76. 7 8 If the difference is positive, that is more energy is required than has been dispatched by 9 HQD, then HQP will be deemed to have sold the difference to HQD. The framework 10 agreement which HQD and HQP have negotiated sets the “price” that will be associated 11 with such purchases 77. If the difference is negative, that is HQD has dispatched too 12 much energy, then the excess is assumed to be unutilized Heritage Pool supply and 13 there no compensation provided to HQD 78. 14 15 In order to minimize the amount of unutilized Heritage Pool supply, a reconciliation is 16 undertaken at year end 79. Once all the hourly HQD requirements and hourly dispatches 17 of non-Heritage Pool supplies are known, the hourly differences are compared and 18 matched with the hourly supplies available from the Heritage Pool. However, there is 19 unlikely to be a perfect match. Indeed, HQD has modelled this process and estimates 20 that the discrepancy will be in the order to 0.5 TWh in the short-term, decreasing to 0.3 21 TWh in the longer term80. 75 Adjusted for any interruptible power load reductions HQD-5, Document 1.1, Annexe 2, Slides 17-19; HQD-5, Document 1.1, page 57, Response 22.1 and HQD-5, Document 4.1, page 4, Response 2.6 and page 6, Response 3.4 77 HQD-5, Document 4.1, page 3, Response 1.1 and page 4, Response 2.4. The price associated with involuntary energy is proposed in HQD filing R-3568-2005 dealing with the Framework Agreement and currently before the Régie. HQD-15, Document 10, page 37, Response 22.3 78 HQD-5, Document 4.1, page 4, Response 1.2 79 HQD-5, Document 2, page 3, Response 1 80 HQD-5, Document 1.1, page 57, Response 22.1 and Document 6, pages 31-33, Responses 40.2 and 41.1 76 28 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments 2 3 Recognition by HQD that management of the Heritage Pool in real time will be less than 4 optimal is consistent with concerns expressed in the ECS evidence filed for Phase II of 5 R-3470-200181. However, there are four issues/concerns with these “additional 6 requirements” and the determination of involuntary purchases from HQP as specified by 7 HQD in the current Plan. 8 9 • Possibility of Unutilized Heritage Pool Capacity 10 11 First, HQD claims that, while management of the Heritage Pool in real time increases 12 overall energy requirements, it does not have any impact on capacity requirements 82. 13 However, if the protocols for real time dispatch of the Heritage Pool can lead to 14 unutilized Heritage Pool energy due to an imperfect matching of Heritage Pool supply 15 with actual loads on an hourly basis, then there is no reason to believe that these same 16 protocols couldn’t lead to mismatches in and around either the time of overall HQD 17 system peak or in and around the time of the peak demand associated with post- 18 Heritage Pool requirements. Indeed, as indicated in response to OC information 19 request 40.2 83, unutilized energy can arise during all months of the year and during the 20 critical winter months (December-February) averages just over 40 MW per hour. 21 22 • Treatment of Unutilized Heritage Pool Energy 23 24 The second concern is with respect to the disposition of unutilized Heritage Pool 25 energy. HQD’s interpretation of the Regulations governing the Heritage Pool is that it 26 can not make “claim” to unutilized Heritage Pool energy84. HQD notes that this 27 interpretation is consistent with how it has managed Heritage Pool electricity since the 28 introduction of the Regulation. 81 82 83 84 Evidence of William Harper, March 2002, pages 12-13. HQD-5, Document 6, pages 10-11, Responses 12.1 and 12.2 HQD-5, Document 6, page 32 HQD-5, Document 2, page 3, Response 1.1 29 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 2 It is not the purpose of this evidence to provide a legal interpretation of the Regulation. 3 However, based on simple reading of the Regulation, there is no reference in it to 4 unutilized Heritage Pool energy. The Regulation just lays out what the Heritage Pool 5 supply was to provide for including losses and internal use by HQP. There is no 6 specific reference in the Regulation about real time management of Heritage Pool. 7 Indeed, the existence of unutilized energy is, in itself, simply the result of the protocols 8 established between HQD and TransÉnergie regarding the dispatch of HQD’s 9 resources. Over the longer-term, if spot market purchases (and the re-sale of energy 10 acquired from other contracted resources) were used in real time to balance HQD’s 11 demand and supply requirements then there would be no unutilized Heritage Pool 12 energy. 13 14 HQD also contends that practice to-date, whereby HQD only took possession of 15 Heritage Pool energy required to meet its domestic requirements and never claimed 16 rights to Heritage Pool energy in order to sell it on external markets, is consistent with 17 the proposed unutilized energy construct. However, the Regulation appears to make 18 special provision for those years when HQD’s total annual requirements did not exceed 19 the Heritage Pool supply85. Also, in its most recent rate application, when HQD’s supply 20 requirements were forecasted to e xceed Heritage Pool supplies for 2005, the Heritage 21 Pool energy sold to HQD was determined by comparing HQD’s total requirements with 22 the Heritage Pool supply86. In fact, no reference was made to either hourly load 23 profiles, additional energy requirements to manage supply in real time or unutilized 24 Heritage Pool energy until the cross-examination phase of the proceeding. 25 26 In contrast, the 2005-2014 Supply Plan determines Heritage Pool energy used as the 27 difference between the hourly profile of the supply not provided through HQD-sourced 28 contracts (i.e., Heritage Pool and involuntary sales by HQP) and the hourly profile of the 85 86 See Article 7 of Decree 1277-2001, October 24, 2001 R-3541-2004, HQD-15, Document 2.2, page 11 30 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Heritage Pool supply as specified by Regulation87. This leads to unutilized Heritage 2 Pool energy both in the short-term and even in the longer term after the hour ly load 3 profile for HQD’s total requirements exceeds the Heritage Pool’s specified load profile in 4 each and every hour of the year. 5 6 However, once total requirements (for all hours of the year) exceed the Heritage Pool 7 load profile then it is not necessarily Heritage Pool energy that is unutilized in serving 8 domestic load in those circumstances where planned supply exceeded actual 9 requirements in real time. One could equally view the excess as being sourced out of 10 the other resources HQD has contracted for, which are available for HQD to resell. 11 Furthermore, to the extent the excess (or unutilized energy) is sold on the export market 12 or allows HQP to replenish its reservoirs, such excess supply has a real value. Such a 13 perspective does not eliminate the fact that the energy contracted for by HQD will need 14 to exceed the forecasted post-Heritage Pool requirements, but it does mean that such 15 unutilized energy should not be considered valueless. 16 17 Indeed, one possible perspective would be to view the involuntary energy provided by 18 HQP as being similar to the E nergy Imbalance service provided by Hydro-Québec 19 under its Open Access Transmission Tariff88. Under the current Tariff, a Transmission 20 customer compensates the Transmission Provider (TransÉnergie) for additional energy 21 delivered at a rate of 10.41 cents / kWh and is compensated for additional energy 22 supplied at a rate of 1.28 cents / kWh. In other jurisdictions, proposals for pricing 23 energy imbalance services are directly linked to opportunity costs. For example, BC 24 Hydro’s recent proposal89 for Interconnection Operations Services called for the selling 25 price to be based on market prices, differentiated between high load and low load 26 hours. The purchase price was linked to market prices in the low load hours only in 27 order to recognize that, with BC Hydro’s available hydro reservoirs, involuntary on-peak 87 88 89 HQD-5, Document 2, pages 3-4, Response 1.1 See page 126 of Hydro-Québec’s Open Access Transmission Tariff. BC Hydro Application to BCUC, August 3, 2004, page 6 31 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 purchases by BC Hydro were really only displacing off-peak imports. A similar 2 approach could be considered by Hydro-Québec. 3 4 • Quantity of Unutilized Heritage Pool Energy 5 6 Third, it is not clear why the energy required to manage the Heritage Pool in real time is 7 initially set at 500 GWh per annum but assumed to decline to 300 GWh per annum in 8 the later years of the Plan. HQD suggests that, as the total difference between the 9 Heritage Pool supply and HQD’s to tal requirements increases, the additional energy 10 needed to manage the Heritage Pool in real time will decrease90. 11 12 However, unutilized Heritage Pool energy results from negative differences between: a) 13 Total actual hourly requirements less the quantities contracted for by HQD (including 14 real-time purchase directions to TransÉnergie) based on forecasted requirements and 15 b) Heritage Pool energy. Since the amount of supply contracted by HQD will generally 16 be set so as to balance total available supply (including Heritage Pool energy) and total 17 forecasted requirements, unutilized energy is largely the result of errors in short-term 18 load forecasting due to weather variations and other factors that give rise to day to day 19 and hour to hour uncertainty with respect to anticipated loads. Unless these errors and 20 uncertainties are reduced by experience, there is no reason to believe that the absolute 21 quantity of energy required to manage the Heritage Pool in real time will decrease over 22 the time-frame of the Plan. 23 24 • Treatment of Interruptible Power 25 26 Finally, it is not clear from the material provided when and how interruptible power is 27 incorporated into the system dispatch. Materials provided during the January 14, 2005 28 Technical Conference suggest that interruptible power is called upon last – after 29 consideration of involuntary purchases from HQP 91. However, responses to various 90 91 HQD-5, Document 1.1, Response 22.1 HQD-5, Document 1.1, Annexe 2, Slides 17 and 18. 32 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 information requests 92 during the current proceeding suggest that involuntary purchases 2 from HQP are used as a “last resort” after all other source of supply (including 3 interruptible power) have been “dispatched”. Given the pricing associated with 4 interruptible power (i.e., the greater of 30 cents / kWh or the DAM supply cost less Rate 5 L93) and the fact that it involves disrupting supply to customers, it should be considered 6 as a last resort and dispatched only if there are insufficient supplies available from HQP, 7 including potential real time purchases over the inter-ties. Indeed, the pressure from 8 interruptible customers for high prices reflects not only their interests in being 9 compensated for the interruption they experience but also their interests in ensuring the 10 “high cost” means that they are interrupted only when it is absolutely necessary. 11 12 4.3 Needs in Excess of the Heritage Pool 13 14 For planning purposes, the energy requirements in excess of the He ritage Pool are 15 determined as the difference between the total energy supply needs and the 178.9 TWh 16 of Heritage Pool supply, plus an allowance for the additional energy required to manage 17 the Heritage Pool in real time. These requirements are summarized in HQD-3, 18 Document 3, Table 1.1 94. The capacity requirements to be provided by HQD (as 19 opposed to HQP in support of the Heritage Pool) are similarly calculated as the 20 difference between total power requirements plus total reserve requirements less both 21 the maximum demand to be met by the Heritage Pool and the reserve margin to be 22 provided by HQP in support to the Heritage Pool supply. These requirements are 23 summarized in HQD-3, Document 3, Table 1.2 95. For reference purposes both are set 24 out in Table 13 below. 92 93 94 95 HQD-5, Document 4.1, page 6, Response 3.4 and Document 10, page 38, Response 22.3 c). D-2004-213, page 4 page 5 page 6 33 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 13 Requirements in Excess of Heritage Pool Energy Addition Req. (TWh) 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 3.8 7.9 10.1 12.7 13.7 15.1 16.1 18 18.7 20 20042005 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 -250 1228 1621 2206 2504 2780 2964 3195 3454 3697 Capacity Additional Req. (MW) Source: - HQD-3, Document 3, Tables 1.1 and 1.2 1 2 3 The load duration curves HQD has provided for the post Heritage Pool supply needs 4 suggest that additional baseload requirements of roughly 800 MW in 2006 increasing to 5 2100 MW in 201496. 6 7 Comments 8 9 The load profile associated with the requirements in excess of the Heritage Pool is a 10 key factor in determining the types generation/supply options that are best used (from 11 both a technical and cost-effectiveness perspective) to meet these incremental 12 requirements. While HQD has provided information on the load profiles associated with 13 the post-Heritage Pool requirements 97, it has not clearly demonstrated how these load 14 profiles translate into the requirements for different types of capacity – similar to what 15 was done in the 2002-2011 Plan98. Table 14 provides an estimate of HQD’s baseload 16 generation requirements derived from the evidence provided to date. 96 HQD-3, Document 3, page 8, Figure 1.2 HQD-3, Document 3, page 8 and HQD-5, Document 10, page 19, Response 11.1 98 R-3470-2001, HQD-2, Document 3, pages 27-28 and HQD-5, Document 6, page 35, Responses 43.1 and 44.1 97 34 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 14 Characteristics of Post HP Requirements 2008 2010 2014 Total Energy (1) (TWh) 12.7 15.1 20 Maximum Demand(2) (MW) 1698 2039 2826 Baseload Demand(3) (MW) 1250 1600 2100 20072008 20092010 20132014 2206 2780 3697 Capacity Required (4) (MW) Source: 1) Total Energy - HQD-3, Document 3, Table 1.1 2) Maximum Demand - HQD-3, Document 3, page 9 3) Baseload Demand - Estimated based on HQD-5, Document 10, page 19, Response 11.1 4) Capacity Required - HQD-3, Document 3, Table 1.2 1 2 Adoption of a higher capacity reserve margin, as discussed in Section 4.1.2, would 3 further increase the additional capacity requirements after 2007-2008. There is 4 insufficient information to determine the reserve margin requirements to meet the NPCC 5 requirements for this period. For illustrative purposes the reserve margin is assumed to 6 increase by roughly 0.5 percentage points in each of the next two years, reaching 11% 7 for 2009-1010. After 2009-2010, the reserve margin is held constant – consistent with 8 the comments in Section 4.1.2.Table 15 sets out the additional capacity requirements 9 associated with the updated reserve margins for the period 2004-2005 through 2006- 10 2007. The implications of this higher reserve margin are set out in Table 15. 11 35 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 15 Revised Capacity Requirements in Excess of Heritage Pool 20042005 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 Peak Demand (MW) 34,184 35,412 35,674 36,011 36,282 36,532 36,699 36,909 37,144 37,365 Reserve Margin (%) 8.8% 9.2% 9.5% 10.1% 10.5% 11.0% 11.0% 11.0% 11.0% 11.0% 37,192 38,670 39,063 39,648 40,092 40,551 40,736 40,969 41,230 41,475 34,342 34,342 34,342 34,342 34,342 34,342 34,342 34,342 34,342 34,342 3,100 3,100 3,100 3,100 3,100 3,100 3,100 3,100 3,100 3,100 -250 1,228 1,621 2,206 2,650 3,109 3,294 3,527 3,788 4,033 Total Capacity Req. (MW) Heritage Pool Supply (MW) Heritage Pool Reserves (MW) Additional Capacity Required (MW) Source: - HQD 2005 Plan: HQD-3, Document 3, Table 1.2 1 2 3 It should be noted that use of the revised reserve margins will not increase the need for 4 baseload capacity but will increase the need for modulable and peaking capacity in 5 excess of the Heritage Pool supply for the years 2008-2009 and beyond. 6 7 4.4 Post Heritage Pool Supplies Currently Under Contract/Planned 8 4.4.1 Existing Contracts 9 10 As discussed above (see Section 1), HQD has already completed five calls for tender 99 11 the results of which are summarized in Table 16 100. Also included in Table 16 are the 12 demand reductions available from the new interruptible rate option that HQD introduced. 99 The table excludes the results of A/O 2004-04, which was initiated after the preparation of HQD’s Application. 100 In some cases, such as the wind contracts, the contracts have been “signed” but final approval by the Régie is still outstanding. 36 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 16 Supply Associated with Completed HQD CFTs Energy (TWh) 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 0 0 0 1.4 0 0 4.1 2.6 0.9 4.1 3.1 1.1 4.1 3.1 1.1 4.1 3.1 1.1 3.9 3.1 1.1 3.7 3.1 1.1 4.1 3.1 1.1 4.1 3.1 1.1 0 0.1 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0 0.1 0.7 1.2 1.5 1.9 2.3 2.8 3.2 3.2 1.3 0 0 0 0 0 0 0 0 0 0.8 0 0 0 0 0 0 0 0 0 2.1 1.6 8.6 9.8 10.1 10.5 10.7 11 11.8 11.8 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 0 0 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 0 20 36 36 36 36 36 36 36 0 77 131 171 208 263 321 361 361 0 0 0 0 0 0 0 0 0 Interrputible Power 560 560 560 560 560 560 560 560 560 Total Capacity Supply 560 1804 1874 1914 1951 2006 2064 2104 2104 A/O 2002-1 - TCE - HQP - Base - HQP - Cyclable A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-1 - Short-Term Supply A/O 2004-3 - Short-Term Supply Total Energy Supply Capacity A/O 2002-1 - TCE - HQP - Base - HQP - Cyclable A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-1 - Short-Term Supply 1 Source: HQD-3, Document 2, page 12 and HQD-5, Document 6, page 4, Response 3.1 2 3 4.4.2 Planned Contracts 4 5 As well as the completed CFTs discussed above, HQD is also in the process of making 6 the following supply arrangements: • 7 Call for tender A/O 2004-02 for 350 MW (2.8 TWh) of supply from cogeneration, with deliveries anticipated to start in 2008 101. 8 101 HQD-3, Document 2, page 10 37 Evidence of William Harper • 1 Hydro-Québec Distribution Régie File R-3550-2004 A framework agreement with HQP to meet very short-term needs due to weather 2 variations or momentary unavailability of other suppliers 102. The proposed 3 agreement has recently been submitted 103 to the Régie for approval and a 4 procedural order has been issued establishing the regulatory review process 104. • 5 Call for tender A/O 2004-04 to address the balance of the anticipated energy requirements for 2005 105. 6 7 Table 17 sets out the combined effect of these initiatives along with those already 8 completed. 102 103 104 105 HQD-3, Document 2, page 11 R-3568-2005 Procedural Order D-2005-91, May 2005 HQD-5, Document 6, page 7, Response 8.2 38 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 17 Supply Associated with Completed & Planned HQD CFTs Energy (TWh) A/O 2002-1 - TCE - HQP - Base - HQP - Cyclable A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-1 - Short-Term Supply A/O 2004-3 - Short-Term Supply A/O 2004-4 - Short Term Supply A/O 2004-2 - Cogen Total Energy Supply 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 0 0 0 1.4 0 0 4.1 2.6 0.9 4.1 3.1 1.1 4.1 3.1 1.1 4.1 3.1 1.1 3.9 3.1 1.1 3.7 3.1 1.1 4.1 3.1 1.1 4.1 3.1 1.1 0 0.1 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0 0.1 0.7 1.2 1.5 1.9 2.3 2.8 3.2 3.2 1.3 0 0 0 0 0 0 0 0 0 0.8 0 0 0 0 0 0 0 0 0 0.9 0 0 0 0 0 0 0 0 0 0 0 0 0.1 1.7 2.8 2.8 2.8 2.8 2.8 3 1.5 8.5 9.8 11.7 13.1 13.4 13.7 14.4 14.4 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 0 0 0 547 0 0 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 547 350 250 0 20 36 36 36 36 36 36 36 0 77 131 171 208 263 321 361 361 0 560 0 560 0 560 0 560 0 560 0 560 0 560 0 560 0 560 0 0 0 200 350 350 350 350 350 560 1204 1874 2114 2301 2356 2414 2454 2454 Capacity A/O 2002-1 - TCE - HQP - Base - HQP - Cyclable A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-1 - Short-Term Supply Interrputible Power A/O 2004-2 - Cogen Total Capacity Supply Source: HQD-3, Document 2, page 12 and HQD-5, Document 6, page 4, Response 3.1 1 2 3 Comments 4 5 As well as these arrangements, HQD also plans to enter into agreements for the supply 6 of load balancing services to “firm” up its supply from wind power and allow it to be 7 treated as a firm source of supply106. Indeed, due to the intermittent nature of wind 106 HQD-3, Document 3, page 13 and Document 6, pages 8 and 9, Responses 11.1 and 11.2 39 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 energy, without a complementary load balancing service to firm and shape the supply 2 this source of power can not be relied upon to meet capacity requirements as presented 3 in the proposed 2005 Plan. However, to this date, no discussions have taken place with 4 potential suppliers of load balancing services 107. Furthermore, the potential number of 5 suppliers of such services appears to be limited108. Given the contractual commitments 6 that HQD is in the process of concluding and the pending Government regulation calling 7 for the acquisition of more wind power-based resources, the identification of sufficient 8 suitable and cost-effective load balancing resources needs to be a high priority for HQD. 9 10 4.5 Additional Supplies Required 11 12 4.5.1 Energy and Capacity 13 14 Table 18 summarizes the additional energy and capacity requirements that HQD has 15 identified as still needing to be addressed over the coming 10-year planning horizon 16 2005-2014. 107 108 HQD-5, Document 6, page 9, Response 11.2 HQD-5, Document 6, page 17, Response 17.1 and R-3526-2004, HQ-3, Document OC, Response 2.3 40 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 18 New Supplies Required Energy (TWh) 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Addition Req. over HP 3.8 7.9 10.1 12.7 13.7 15.1 16.1 18 18.7 20 Supplies Contracted/ Planned For 3 1.5 8.5 9.8 11.7 13.1 13.4 13.7 14.4 14.4 0.8 6.4 1.6 2.9 2.0 1.9 2.7 4.3 4.3 5.6 20042005 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 Additional Req. over HP -250 1,228 1,621 2,206 2,504 2,780 2,964 3,195 3,454 3,697 Supplies Contracted/ Planned for 560 560 1,204 1,874 2,114 2,301 2,356 2,414 2,454 2,454 New Supply Req. -810 668 417 332 390 479 608 781 1,000 1,243 New Supply Req. Capacity (MW) 1 2 3 Source: - HQD-3, Document 3, Tables 1.1 and 1.2 Comments 4 5 Based on the earlier comments in Sections 4.1.2, 4.2.2 and 4.4.1, it would appear that 6 HQD has underestimated the new capacity supplies that will be needed to reliably meet 7 customers’ requirements through to 2013-2014 as follows: 8 • 9 10 The required reserve margins need to be increased in light of the more recent 2004 Interim Review of Resourced Adequacy completed by Hydro-Québec. • Higher (capacity) reserve margins should have been used in the period beyond 11 2007-2008 to reflect the lead time required to bring new supply into service in the 12 context of HQD’s overall planning cycle. 13 • 14 There are likely to be addition capacity (as well as energy) requirements associated with the management of the Heritage Pool supply. 15 There is insufficient information available to determine by how much the requirement for 16 new capacity supplies is underestimated but Table 19 provides an estimate based on a 17 long-term capacity planning reserve of 11% 109 as opposed to 10.1%. 109 See Section 4.3’s comments for the rationale underlying the 11% 41 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 19 New Supplies Required Based on Revised Reserve Marging Requirements Capacity (MW) 1 2 3 20042005 20052006 20062007 20072008 20082009 20092010 20102011 20112012 20122013 20132014 Additional Capacity Required (MW) -250 1,228 1,621 2,206 2,650 3,109 3,294 3,527 3,788 4,033 Supplies Contracted/ Planned for 560 560 1,204 1,874 2,114 2,301 2,356 2,414 2,454 2,454 New Supply Req. -810 668 417 332 536 808 938 1,113 1,334 1,579 Source: - HQD-3, Document 3, Table 1.2 - Tables 15 and 17 4.5.2 Types of Capacity Required 4 5 The capacity that HQD has already contracted for and/or has plans to contract for is a 6 mix of baseload, modulable/cyclable and peaking supply as demonstrated in Table 20. 42 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 20 Capacity Mix of Current/Planned Contracts 20072008 20092010 20132014 500 350 500 350 500 350 36 36 36 Baseload A/O 2002-1 - TCE - HQP - Base A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-2 - Cogen Total Baseload 131 208 361 0 1017 350 1444 350 1597 Modulable/Cyclable A/O 2002-1 - HQP - Cyclable Total Modulable/Cyclable 250 250 250 250 250 250 560 560 560 47 607 47 607 47 607 1874 2301 2454 Peaking Interrputible Power A/O 2002-1 - TCE Total Peaking Total 1 2 3 Comments 4 5 Comparing the values in Tables 14 and 20 suggests 110 that the requirement for 6 additional baseload capacity is in the order of 200 MW in both 2007-2008 and 2009- 7 2010 and, then increases to roughly 500 MW by 2013-2014. At the same time, total 8 additional capacity requirements as set out in HQD’s Application increase from roughly 9 330 MW in 2007-2008 to 480 MW in 2009-2010 to 1240 MW in 2013-2014. As a result, 10 while over half of the new requirements are for baseload capacity in 2007/08, 110 The baseload requirements indicated here are only rough estimates. More precise values would require analyses by HQD 43 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 incremental baseload needs represent only 40% of the total new requirement for 2013- 2 2014. 3 4 4.6 Conclusions 5 6 Methodology 7 8 HQD’s explanation as to how the load forecast is translated into additional (post- 9 Heritage Pool) supply requirements has generally improved relative to the material 10 presented in support of the 2002-2011 Supply Plan. The one major exception is the 11 lack of details in the current Application regarding the types of capacity (e.g., baseload 12 versus modulable, etc.) needed to meet the identified gap between the load forecast 13 and the supplies currently under contract/planned for. 14 15 Capacity Planning Criteria 16 17 While the current Application more clearly lays out HQD’s planning reliability criteria and 18 how they are translated into the need for additional supplies, there are some issues 19 regarding the actual planning criteria used. The capacity planning criteria and, in 20 particular, the 10.1% reserve margin used to determine capacity requirements over the 21 longer term needs to be revised for a couple of reasons: 22 • The value needs to be updated (and increased) in order to be consistent with the 23 more recent 2004 Interim Review of Resource Adequacy filed with the NPCC. 24 Howvever, the revision required as a result of this updated information is likely to be 25 minor. 26 • The use of 2007-2008 as the reference year going forward is inconsistent with the 27 four year lead time required for major new supply and HQD’s planning cycle. %. 28 Although further analysis by HQD (and HQP) is required in order to determine the 29 actual value. The appropriate long-term capacity planning reserve margin is likely in 30 the order of 11%. 44 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Energy Planning Criteria 2 3 The use of one standard deviation from the medium load forecast as the basis for the 4 long-term energy planning criterion means there is a material probability (over 15%) that 5 the limit will be exceeded. When coupled with the earlier concerns regarding the 6 uncertainty associated with the load forecast, use of one standard deviation leads to 7 considerable risk that the limits may be exceeded. Consideration should be given to 8 adopting a more conservative limit (e.g., 10% probability of exceeding). 9 10 In addition, based on the same rationale used to support a longer timeframe for the 11 capacity planning criterion, the 4-year time horizon used to establish the variance 12 associated with the long-term energy-related criterion should be extended to 6 years. 13 14 Also, for this 6 year period, HQD should adopt a short-term energy planning criterion 15 that acknowledges the potential for variations in future energy requirements and the 16 limited capability of the inter-ties to support such variations. Adoption of a short-term 17 energy criterion of this form would be consistent with past findings of the Régie111. 18 19 Load Balancing Services 20 21 Given HQD’s current commitment to wind generation and its future plans to procure 22 additional wind-based supplies, high priority should be given to securing the necessary 23 contracts for “balancing resources” that will permit wind power to be considered a firm 24 resource for planning purposes. Indeed, the lack of any progress to date in this area is 25 concerning and the Régie should direct HQD to, at minimum, complete agreements for 26 sufficient balancing resources to support the 990MW of wind generation already under 27 contract before approval is given to proceed with new CFT for additional wind -based 28 generation. 111 D-2002-169, page 47 45 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Heritage Pool Management 2 3 A number of concerns have been identified regarding the management of the Heritage 4 Pool. While their resolution is unlikely to have a material impact on the overall 5 additional supply requirements, they have been ongoing matters of concern since the 6 first Supply Plan was filed with the Régie and need to be resolved as they will have 7 impact on the overall cost of supply for HQD’s customers. 8 46 Evidence of William Harper 1 5 Hydro-Québec Distribution Régie File R-3550-2004 HQD’s 2005-2014 Supply Strategy and Plans 2 3 5.1 Near Term (2005-2008) 4 5 HQD has indicated that due to the lead times required to obtain new long-term supply 6 sources, the additional power and energy needs set out in Table 18 (above), for the 7 period up to a nd including the winter of 2008-2009 will be met by short-term market 8 purchases 112 with contract periods of one-year or less 113. These short-term market 9 purchases could be sourced from Hydro Quebec and neighbouring grids (i.e., in the 10 United States). However, HQD can not assume the Quebec producers (including HQP) 11 will have surplus energy available since they all rely on hydro-based resources and are 12 subject to supply variances 114. This means that the inter-ties may have to be relied on 13 to meet any short-term shortfall in projected supply and also to meet any increases in 14 load over and above the forecast used to determine the new supply requirements 15 associated with the medium load forecast115. Table 21 below summarizes the HQD’s 16 anticipated reliance on the inter-ties assuming all new supplies needed are acquired 17 through short-term markets. For purposes of preparing the table, the anticipated new 18 wind supplies116 from HQD’s proposed CFTs have been included and reduce the 19 reliance on the inter-ties. 112 HQD-5, Document 6, page 8, Responses 9.1 and 9.2 HQD-5, Document 6, page 34, Response 41.2 114 HQD-5, Document 1.1 page 50, Response 17.1 115 In its current plan HQD is forecasting small amounts of energy to also be available in 2007 and 2008 from a future CFT for wind power. There is also the possibility that output from already in-service modulable/cyclable capacity could be increased to meet higher than currently anticipated energy requirements. 116 Wind energy is the only source of new supply with a lead time of less than four years – see HQD-3, Document 3, Annexe 3A 113 47 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 21 Short Term Energy Requirements Energy (TWh) 2005 2006 2007 2008 2009 2010 - New Supply Req. 0.8 (Table 18) - Existing ST 3 Commitments (Table 17) - Planned Supply 0 from New Sources (HQD-3,Doc 3, page 25) -Total ST Req. 3.8 (Based on Medium Load Forecast) 6.4 1.6 2.9 2.0 1.9 0 0 0 0 0 0 -0.1 -0.7 -1.3 -1.9 6.4 1.5 2.2 0.7 0 -One-Standard Deviation (Table 11) 5 5.3 6.4 7.8 8.9 9.9 8.8 11.7 7.9 10 9.6 9.9 20042005 20052006 20062007 20072008 20082009 20092010 -810 668 417 332 390 479 Total ST Req. (Based on 85% Confidence) Capacity (MW) - New ST Req. (Table 18) 1 2 3 5.1.1 Inter-Tie Capability 4 5 HQD has updated 117 the information it provided in R-3470-2001 regarding the import 6 capability of the inter-ties and its ability to rely on imports: • 7 The amount of power that can be imported annually based on technical and 8 physical limits is 24.1 TWh – 10.2 TWh in the peak period and 13.9 TWh in the 9 off-peak period. The comparable value in R-3470-2001 was 34.7 TWh. 117 HQD-5, Document 1, pages 6 & 7, Response 3 48 Evidence of William Harper • 1 Hydro-Québec Distribution Régie File R-3550-2004 The amount of power that can be imported after taking into account “market 2 constraints” is 16.2 TWh – 4.5 TWh in the peak period and 11.6 TWh in the off- 3 peak period. The comparable value in R-3470-2001 was 20 TWh. 4 5 Comments 6 7 For planning purposes, HQD has set118 a strategic limit of 5 TWh annually as the 8 amount it should rely on the inter-ties for planning purposes. This limit recognizes that a 9 significant amount of the 16.2 TWh is in the off-peak period and may not be of value to 10 HQD. It also recognizes the HQP may also need to access the inter-ties to meet its 11 Heritage Pool commitments 119. 12 13 The strategy underlying HQD’s 2002-2011 Plan called for relying on energy supplies 14 from the short-term markets (e.g., the inter-ties) and interruptible power during the initial 15 years of the Plan only to meet uncertainties in future demands 120. However, the 16 situation has fundamentally changed for the 2005 Plan in that the short-term markets 17 are being heavily relied upon over the next 4 years (or more) to meet the expected load 18 forecast. Indeed, based on the expected load forecast, HQD will only be able to stay 19 within the 5 TWh limit in three out of the next fo ur years – with 2006 being the year the 20 limit is exceeded (i.e., requirements are 6.4 TWh vs. 5 TWh) . However, HQD has 21 confirmed with HQP that its (i.e., HQD’s) reliance on the inter-ties for 6.4 TWh will not 22 jeopardize HQP’s ability to meet its supply obligations 121 over the next few years given 23 the current status of its hydro reservoirs. 24 25 Given these circumstances, the question arises as to where the incremental energy 26 supplies would come from in the short-term if energy needs were to exceed the current 27 load forecast due to either stronger economic growth or weather variations. As 118 HQD-3, Document 1, page 14 HQD-5, Document 6, pages 35-36, Response 45.1 120 R-3470-2001, HQD-2, Document 3, page 21 121 HQD-5, Document 6, page 45, Responses 57.3 and 57.4. Annexe 3B suggests that HQP’s reliance on interconnections under low water conditions would be 3 TWh or less per annum. 119 49 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 illustrated in Table 21 (above), if energy requirements were to exceed the medium 2 forecast by one standard deviation then HQD’s reliance on the inter-ties would exceed 3 the 5 TWh limit in all four years and, indeed, even exceed the 10 TWh limit established 4 for the inter ties overall in one out of the four years concerned (i.e., 2006). 5 6 Under normal water flows, there may be additional resources available from HQP 122 to 7 meet HQD’s increased requirements. However, if HQP were to experience low water 8 flows at the same time and require 2 TWh of inter-tie capability each year to meet its 9 obligations, the 10 TWh limit would be exceeded in 3 out of the 4 years. Thus, while the 10 conclusions in Section 4.1 suggested adopting a more conservative limit for HQD’s 11 energy reliability criterion, HQD could be pressed simply to meet a short-term criterion 12 based on one standard deviation if hydraulic conditions in the province were to 13 deteriorate. 14 15 There is additional import capability available in the off-peak period. However, it is 16 unlikely that HQD would be able to utilize it without access to storage whereby the 17 energy would be purchased in the off-peak, stored overnight or longer and re- 18 dispatched in a higher load period (i.e. something akin to the load balancing service 19 required for wind energy). A n issue therefore arises as to what arrangements might be 20 made, in the event of higher load growth, between HQD and HQP that would see HQP 21 importing energy in the off-peak, effectively storing some or all of it in its hydro 22 reservoirs and then re-selling the energy to HQD in the peak period. 23 24 Going forward, HQD’s supply mix would typically include modulable and cyclable 25 sources of supply whose energy o utput could be increased in the event of a higher than 26 expected loads. However, HQD’s first cyclable post-Heritage Pool resources are not 27 scheduled to come on line until 2007 123. This resource could help address additional 122 123 HQD-3, Document 3, page 36 This would be the 250 MW of supply contracted for with HQP as a result of A/O 2002-1. 50 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 energy needs in the latter part of that year and 2008124 – but not in 2006 which is the 2 most critical period. The circumstances HQD faces for 2005 through 2008 highlight the 3 need for HQD to put in place adequate modulable/cyclable resources as part of their 4 overall post Heritage Pool supply mix125. 5 6 Also, in assessing the short-term energy supply situation, HQD has assumed that the 7 deliveries from the second wind energy CFT will commence in 2007 and ramp up there 8 after. However, given that the earliest the second wind CFT could be initiated is in the 9 latter half of 2005, the assumption that deliveries will start as early as 2007 seems 10 overly optimistic. HQD has indicated that for wind power the time required from 11 initiating the CFT to in-service date is roughly 40 months 126. This time frame is 12 consistent with timing assumed for the first wind power CFT which was launched in May 13 2003 with deliveries to start in December 2006127. Similar timelines for the second CFT 14 would mean first deliveries could be expected at the very end of 2008 and, more likely, 15 starting in 2009. 16 17 Finally, the revised reserve margins discussed earlier 128, will increase the capacity 18 requirements that must be met through the short-term markets after 2007-2008. 19 However, HQD’s Application indicates a winter capability of roughly 1900 MW (after 20 allowances for technical constraints 129) which should be sufficient to provide for even 21 the higher requirements now expected. 124 The current supply plan assumes this resource operates at 50% capacity factor and produces roughly 1 TWh per annum – see HQD 3, Document 3, page 25. See also HQD-5, Document 6, pages 39-40, Response 50.1.3 125 This is consistent with and supports HQD’s long-term strategy (HQD-3, Document 3, page 15, lines 18-20) 126 HQD-3, Document 3, page 41 127 HQD-3, Document 2, page 10 128 Sections 4.1.2 and 4.6 129 HQD-3, Document 1, page 12 51 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 5.1.2 Mix of Market Purchases 2 3 Market purchases of short-term (one-year or less) energy supplies can be made well in 4 advance of the time frame they are required or they can be made closer to the date 5 concerned right up to either the day ahead or in “real time” 130. For 2005, HQD plans to 6 enter contracts in advance (i.e., 3 months or more prior to delivery) for 3 TWh of supply 7 and then obtain the remaining 0.8 TWh it anticipates it will require on a very short-term 8 basis131. 9 10 For 2006, HQD plans to reassess, during 2005, exactly how much energy is likely to be 11 required and then issue calls for tender for supply in the spring and fa ll of this year 132. 12 Exactly how much of the total supply will be arranged in advance as opposed to left to 13 very short-term purchases will also be determined during 2005133. Then for 2007, given 14 the relatively smaller amount of energy required, HQD anticipates 134 issuing just one 15 call for tender in 2006. However, again, the requirements will be reassessed after the 16 next demand review. Similarly, the requirements for 2008 will also be re-evaluated as 17 new load forecasts become available. 18 19 Comments 20 21 Purchasing market-based requirements in advance (as HQD recently did with the 22 Constellation Group) allows a utility to lock in (or hedge) prices based on “normal or 23 expected” market conditions; whereas with very short-term purchases the utility and its 24 customers are exposed to more potential price volatility. Indeed, conditions such as 25 colder weather or economic upswings that lead to higher than expected electrical 26 energy requirements are also likely to trigger increases in market prices if demand 27 increases in general across the north-eastern USA. The down-side of advance 130 131 132 133 134 HQD-5, HQD-3, HQD-3, HQD-5, HQD-3, Document 1, pages 8 & 9, Response 4.1 & 4.2 Document 3, page 27 Document 3, page 28 Document 6, Response 57.1 Document 3, pages 30-31 52 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 purchases is that if loads are lower than forecast, the utility may have excess supply 2 and resale price may well be less than the initial purchase price. As result, a balance is 3 required between adva nce purchases and reliance on very short-term purchases and it 4 is reasonable for a utility such as HQD to rely on both market sources. 5 6 HQD’s current strategy135 is to use short-term CFTs to meet the remaining 7 base/intermediate load requirements (i.e., requirements with a high load factor). Then 8 very low load factor/volatile requirements are met through the very short-term supply 9 options such as the day-ahead market. HQD does not appear to have undertaken any 10 detailed economic analyses of the tradeoffs involved between the two to help better 11 define the optimum reliance on very short-term supplies. However, it is early days in 12 terms of HQD’s involvement as a “purchaser” in electricity markets and the terms of the 13 framework agreement with HQP will be a critical element of any hedging strategy. 14 15 5.1.3 Conclusions 16 17 Short Term Supply Situation 18 19 The main conclusion to be taken from the preceding comments is that HQD’s energy 20 supply options are limited in the short term – particularly for the 2005-2008 period when 21 it has only a small amount of modulable /cyclable supply under contract – and the inter- 22 ties may have to be relied on more so than good planning would call for. HQD is 23 fortunate that currently HQP’s hydro reservoirs are in reasonably good supply and, as a 24 result, HQP will not have rely significantly on the inter-ties to meet its supply obligations 25 – even if water conditions are low in the future. 26 27 HQD has indicated that the contribution of the cyclable product (i.e., the 250 MW under 28 contract with HQP) could be increased136. However, the increase is likely to only be in 135 136 HQD-5, Document 1, page 8, Responses 4.1 and 4.2 HQD-5, Document 6, page 40, Response 50.1.3 53 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 the order of 1.0 TWh137. HQD has indicated the re is the possibility of purchasing 2 surplus energy from other current suppliers. However, it has also acknowledged that it 3 has no knowledge of any such excesses existing 138. Furthermore, HQD’s plans to rely 4 on nominal deliveries of wind energy starting in 2007 appear optimistic. 5 6 As a result, a combination of events such as higher load growth and low water 7 conditions could lead to a situation where the 10 TWh limit on the inter-ties would be 8 exceeded. While there appears to be very little more that HQD can do to address the 9 current short-term supply situation, there may be some opportunity for HQD make 10 additional off-peak purchases in the short-term market if suitable storage arrangements 11 could be negotiated with HQP. 12 13 Also, the current situation does highlight the need for the inclusion of more 14 modulable/cyclable capacity in HQD’s future supply mix. 15 16 Mix of Market Purchases 17 18 While it may be currently be premature, for the next Supply Plan HQD should be 19 prepare an economic assessment of the appropriate mix of short-term versus very 20 short-market purchases. 137 138 R-3515-2003, HQD-1, Document 2, page 9 HQD-5, Document 6, page 40, Response 50.1.3 54 Evidence of William Harper 1 5.2 Hydro-Québec Distribution Régie File R-3550-2004 Longer Term (2009-2014) 2 3 Over the longer term period (i.e., 2009 and beyond), HQD plans to meet its additional 4 supply requirements through the acquisition of new resources as well as through the 5 short-term markets. However, in doing so, HQD must take into account not only its 6 actual supply requirements but also directives from the Québec government (and the 7 Régie) regarding the types of resources to be acquired. In this regard, there are 8 currently two directives that will influence HQD’s future acquisition strategies: • 9 In 2003, the Provincial Government issued a regulation calling for HQD to adopt, 10 as an objective, the acquisition of 800 MW of supply based on cogeneration139 11 (current calls for tender have addressed 350 MW of this) and • 12 13 Government regulations are expected shortly140 regarding the acquisition of addition supply based on wind energy. 14 15 5.2.1 Available Supply Options 16 17 A number of potential sources of new generation are identified in HQD’s Application. 18 19 Hydraulic 20 21 There are a number of remaining hydro-electric sites in Quebec and HQP’s current 22 plans 141 call for it to develop over 2600 MW of additiona l capacity by 2011-2012. As a 23 result, hydraulic resources could contribute significantly to HQD’s future supply 24 requirements. 139 140 141 HQD-3, Document 3, page 13 HQD-3, Document 3, page 13 See A-2004-01, page 72 55 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Biomass 2 3 Given the limited response to A-2003-01 and the number of MW of generation from 4 biomass eventually contracted for, HQD suggests that there is unlikely to be additional 5 new supply available at a reasonable cost 142 from this resource. Also, an issue arose 6 during the call for tender regarding the availability of biomass resources 143 which is 7 likely to limit the potential for additional new resources from this source. 8 9 Cogeneration 10 11 The 547 MW TCE project that HQD has contracted for at Bécancour is a cogeneration 12 facility144 with an anticipated levelized ($2007) cost of supply of $60/MWh145. The 13 Régie, in its 2004 Report to the Minister, concluded that the cogeneration potential in 14 Québec (with no efficiency constraints) is in the order of 1,000 to 2,000 MW 146. 15 16 HQD is in the process of completing its first call for tender for supply from cogeneration. 17 The results of this process will provide an indication as to the overall potential for 18 cogeneration in Québec. The preliminary list of bids accepted totalled 591.8 MW from 19 10 bidders for December 2009 in-service147. The supply sources included natural gas, 20 heavy fuel oil, wood residue and biogas. 21 22 Wind Energy 23 24 HQD recently completed its first call for tender for wind-based generation. Overall 32 25 offers from nine different bidders were received with a total capacity of 4,000 MW 148. In 26 February of this year, HQD signed nine contracts for a total of 990 MW of wind powered 142 143 144 145 146 147 148 HQD-3, Document 3, page 12 R-3533, HQD-2, Document 6, Merrimack Report, page 11 A-2004-01, pages 112 and 115 D-2003-159, page 17 A-2004-01, page 112 http://www.hydroquebec.com/distribution/en/marchequebecois/ HQD-1, Document 2, page 8 and HQD-5, Document 6. page 50, Response 64.4 56 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 generation. The contracts have recently been submitted to the Régie for approval149. 2 Documentation provided in support of that Application indicates that the average 3 levelized cost ($2007) of the selected bids is $78/MWh ($65/MWh for the electricity plus 4 $13/MWh for transmission and losses) 150. 5 6 Due to the intermittent nature of wind as a resource, HQD has indicated that it will also 7 be necessary to contract for a load balancing service before wind can be considered a 8 resource for purposes of energy planning 151. HQD has also indicated that while hydro- 9 based facilities with storage (i.e., reservoirs) are a potential source of balancing service, 10 it has not yet entered into discussions with potential suppliers152. 11 12 Combined Cycle Gas Turbines (CCGTs) 13 14 CCGTs are one of the more versatile forms of generation as they are based on proven 15 technology; aren’t as geographically dependent as wind or hydro; and can be used to 16 meet baseload, cyclable or modulable requirements. HQD is of the view that CCGTs 17 have a role in meeting future supply requirements. However, there has been 18 considerable public opposition to specific proposals to locate a CCGT in Quebec153. 19 Analyses undertaken by Merrimack Energy in support of HQD’s applications to the 20 Régie for contract approval indicates that the levelized cost ($2007) of production from 21 new combined cycle plants located in neighbouring jurisdictions would cost roughly $65 22 - $70/MWh (prior to the inclusion of transmission costs for delivery to the Québec 23 border) 154. This is similar to $66/MWh ($2008) cost of production attributed to the 24 proposed Suroît plant 155. 149 150 151 152 153 154 155 Demande R-3569-2005 HQD-2, Document 4, page 6 HQD-3, Document 3, page 13 HQD-5, Document 1.1, page 59, Response 24.1 and HQD-3, Document 6, page 17, Response 17.4 HQD-3, Document 2, page 14 R-3515-2003. HQD-2, Document 4, pages 8-13 A-2004-01, pages 121 and 122 57 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments 2 3 The primary sources of new long -term supply for HQD are likely to be hydro resources, 4 cogeneration projects, wind energy and combined cycle (gas-fired) generation. The 5 hydro resources would be developed by HQP while the other resources would be 6 developed by private parties. 7 8 Table 22 sets out the available information regarding the levelized cost of these various 9 supply sources. 10 Table 22 Cost of New Supply Resources Resource Cost Source Wind $78/MWh ($2007) Results of A/O 2003-02 Hydraulic - Base - Cyclable $55/MWh ($2007) $74/MWh ($2007) Results of A/O 2002-01 Results of A/O 2002-01 CoGeneration - TCE $60/MWh ($2007) Results of A/O 2002-01 Biomass $67/MWh ($2007) Results of A/O 2003-01 Combined Cycle - Suroit $66/MWh ($2008) A-2004-01 - NE USA * - NE USA* $66.2-$74.6/MWh R-3533-2004 Merrimack Energy (Expressed in $2008) $67-$72/MWh R-3515-2003 Merrimack Energy (Expressed in $2007) Note: The Combined Cycle costs for NE USA include transportation to the Quebec border. 11 12 13 However, when comparing the various sources it is important to note that: 14 • 15 Of the four potential sources only combined cycle generation and hydro resources would be capable of meeting HQD’s modulable, cyclable or peaking capacity 58 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 requirements and, in the case of hydro resources, this would be dependent upon the 2 specifics of the site under development. Furthermore, only the combined cycle 3 facilities are likely to have the flexibility to actually increase production in the event of 4 higher loads. 5 • The cost of hydro facilities is likely to be “site specific” such that the costs attributed 6 to the current HQP contracts may not be representative of the cost of future hydro- 7 based resources. Also, one of the key reasons for the difference between the 8 baseload and cyclable hydro-based contracts is that the former is assumed to 9 operate at 94% capacity factor while the capacity factor of the latter is only 50%. 10 • The cost attributable to wind energy does not include any costs for the balancing 11 supply that will be necessary to “firm up” the supply from wind generation and allow 12 it to be included for energy planning 156. 13 14 With respect to the last point, HQD has not had any discussions with potential suppliers 15 of balancing services and, as a result, the associated costs and availability are 16 unknown. In addition, HQD has indicated that there are limits on the amount of load 17 balancing capacity that would be available from hydro resources 157. HQD has 18 suggested the possibility of launching a CFT to obtain the necessary service158 and/or 19 integrating the future needs for both cyclable and load balancing resources159. 20 21 As noted earlier, there is an urgent need for HQD to pursue the availability and cost of 22 load balancing services. HQD has already made a significant commitment to wind 23 energy and this commitment will likely double over the coming years if the anticipated 24 government direction regarding future wind acquisition becomes a reality. It is critical 25 that HQD confirm that sufficient load balancing resources are available at a reasonable 26 cost to support this anticipated commitment to wind power. 156 157 158 159 HQD-3, HQD-3, HQD-5, HQD-5, Document 3, page 13 and HQD-5, Document 6, pages 8-9, Response 11.1 Document 3, page 13 and HQD-5, Document 1.1, page 58, Responses 23.1 and 23.2. Document 1.1, page 59, Response 24.1 Document 6, page 41, Responses 52.1 and pages 42-43, Responses 54.1 and 54.2 59 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Table 21 also includes estimates as to the cost of delivering production from combined 2 cycle generation located in neighbouring jurisdictions to the Québec border. The values 3 were developed as benchmarks to demonstrate the reasonableness of the contract 4 prices associated with Québec based resources selected through HQD’s CFT 5 processes. HQD has expressed concerns 160 about the potential impact that entering 6 into long-term contracts for supply with generation sources outside Québec could have 7 on its short-term import capabilities and its ability to fairly permit such generation 8 sources to participate in its CFT process. The later concern relates to difficulties HQD 9 perceives in creating clear CFT criteria that will protect ST market capabilities over the 10 next 20 years. 11 12 This issue was discussed during the review of the first Supply Plan and addressed in 13 the ECS evidence at that time 161. The point made then and still valid today is that the 14 inter-tie limits identified by HQD (i.e., the 15 TWh162) and used to establish the amount 15 for which HQD can rely on the inter-ties for short-term purchases include considerations 16 of regarding the likely availability of power in neighbouring jurisdictions at the time HQD 17 requires it. Prior to these considerations, the import capability of the inter-ties is roughly 18 24 TWh163. As discussed in the original evidence, this would suggest that there is some 19 opportunity (roughly 9 TWh) to use the inter-ties to import power under lo ng term 20 contracts and still rely on the inter-ties as planned to meet short-term needs. 21 22 HQD can not guarantee itself continued access to 5 TWh of inter-tie capacity over the 23 next 20 years unless it formally reserves the capacity under TransÉnergie’s open 24 access tariff. Rather the 5 TWh limit set by HQD is an assessment of what’s expected 25 to be available based on current transmission facilities and contracts. For purposes of 26 its CFT process, HQD should require parties outside Québec to be responsible for 27 arranging the transmission rights required to deliver the power to Québec and any 160 161 162 163 HQD-3, Document 3, pages 16-17 R-3470-2001, ECS Evidence, March 2002, page 14 HQD-3, Document 3, page 14 HQD-5, Document 1, pages 6-7, Response 3 60 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 submitted tender should confirm this. HQD should then assess whether the proposed 2 firm import would impact on transmission capabilities as they currently exist. 3 4 5.2.2 HQD’s Long Term Supply Strategy 5 6 HQD’s long-term supply strategy involves 164: • 7 8 Meeting the longer term (i.e., 48 to 66 months out) needs associated with the medium load forecast through calls for tender. • 9 Acquiring additional modulable generation such that HQD can meet higher load 10 growth while relying on short-term markets for no more than 5 TWh of supply / 11 annum. • 12 13 Maintaining sufficient flexibility in the terms of the actual contracts themselves to meet higher or lower demand forecasts. 14 15 According to HQD’s Application, the additional energy and capacity requirements that 16 must be provided for in order to satisfy this strategy are set out in Table 23. 164 HQD-3, Document 1, page 15 61 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Table 23 Additional Long-Term Supply Requirements Energy (TWh) Additional Req. - Medium Forecast(1) - One Stanard Dev(2) Total 2009 2010 2011 2012 2013 2014 2 7.8 9.8 1.9 7.8 9.7 2.7 7.8 10.5 4.3 7.8 12.1 4.3 7.8 12.1 5.6 7.8 13.4 20092010 20102011 20112012 20122013 20132014 479 608 781 1000 1243 Capacity (MW) Additional Req. - Medium Forecast (3) plus Reserves Source: 1) Table 18 2) HQD-3, Document 3, page 38 3) Table 18 2 3 4 In order to meet these additional requirements, HQD plans to: 5 • first starting to come on line in 2007 165. 6 7 Launch a second CFT in 2005 for 1,000 MW of wind-based generation, with supply • After the completion of the Parliamentary Commission’s work, launch a CFT open to 8 all generation sources designed to obtain 400 MW of modulable resources with in- 9 service dates starting in 2009. HQD indicates that the most likely sources for such a resource would be hydro or thermal (principally combined cycle) generation166, and 10 11 • At some future date, launch a CFT to acquire more supply based on cogeneration with a target in-service date of 2011 167. 12 165 166 167 HQD-3, Document 3, pages 21 and 25 HQD-3, Document 3, pages 23-24 HQD-3, Document 3, page 22, lines 16-20 62 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 Tables 24 and 25 set out how HQD sees these additional resources contributing to its 2 identified long-term capacity and energy requirements based on the medium load 3 forecast. 4 Table 24 Long Term Capacity Balance (MW) Additional Req. - Medium Forecast plus Reserves(1) Planned Acquisitions (2) - 2nd Wind CFT - CFT for Modulable Capacity - CFT for CoGen Capacity Total Supply Surplus/(Deficit) Source: 5 20092010 20102011 20112012 20122013 20132014 479 608 781 1000 1243 210 400 250 400 350 400 350 400 350 400 0 0 100 100 250 610 650 850 850 1000 131 42 69 -150 -243 1) Table 22 2) HQD-3, Document 3, page 26 63 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 25 Long Term Energy Balance Based on Medium Load Forecast (TWh) Additional Req. (1) - Medium Forecast Planned Acquisitions - 2nd Wind CFT - CFT for Modulable Capacity - CFT for Cogen Capacity Total Supply Surplus/ (Deficit) Source: 2009 2010 2011 2012 2013 2014 2 1.9 2.7 4.3 4.3 5.6 1.3 - 1.9 - 2.5 - 3.1 - 3.1 - 3.1 - 0 0 0.1 0.8 0.9 2 1.3 1.9 2.6 3.9 4 5.1 -0.7 0 -0.1 -0.4 -0.3 -0.5 (2) 1) Table 19 2) HQD-3, Document 3, page 25. 1 2 In its Application HQD also suggests the need for additional cyclable resources starting 3 in 2010-2011 based on the need for load following capabilities and balancing services 4 for wind generation168. However, the proposed Plan does not include additional 5 cyclable capacity. Rather, HQD is considering adapting its load balancing service so 6 that it can meet its cyclable requirements as well 169. HQD plans to specify its needs in 7 this regard during 2005. 8 9 Table 26 sets out how HQD’s 2005 Plan meets its longer term energy reliability criterion 10 – i.e., respond to the higher requirements associated with the medium load forecast 11 plus 7.8 TWh without relying on short-term purchases for more than 5 TWh per annum. 168 169 HQD-3, Document 3, page 24 HQD-5, Document 6, page 42, Response 54.1 64 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 26 Long Term Energy Balance Based on Medium Load Forecast Plus One Standard Deviation (TWh) 2009 2010 2011 2012 2013 2014 2 7.8 9.8 1.9 7.8 9.7 2.7 7.8 10.5 4.3 7.8 12.1 4.3 7.8 12.1 5.6 7.8 13.4 1.3 0.3 1.9 3.2 2.5 3.2 3.1 3.2 3.1 3.2 3.1 3.2 0.5 2.1 3.6 3.6 3.6 1.6 5.6 7.8 9.9 9.9 9.9 -8.2 -4.1 -2.7 -2.2 -2.2 -3.5 Additional Req. (1) - Medium Forecast - One Stanard Dev Total Planned Acquisitions - 2nd Wind CFT - CFT for Modulable Capacity - CFT for Cogen (3) Capacity Total (2) Supply Surplus/ (Deficit) Source: 1 2 1) Table 22 2) HQD-3, Document 3, page 38 3) Assumes a one-year advancement of the CFT for Cogen Resources and an increase in the total cogen resources called for. 3 As illustrated in Table 26, in order to meet the energy requirements of a higher growth 4 scenario, HQD indicates that it would advance the initiation of calls for tender for 5 additional cogeneration and increase the planned increment in capacity to 450 MW 6 (versus the 250 MW originally planned)170. This will enable HQD to limit its reliance on 7 short-term purchases after 2009 to less than 5 TWh / annum consistent with its long- 8 term energy reliability criterion171. HQD notes that while the reliance on short-term 9 markets would be high in 2008 and 2009, this should not result in undue risk given the 10 additional capacity that is being installed in Québec through the same period172. 170 171 172 HQD-3, Document 3, page 35 HQD-3, Document 3, page 37 HQD-3, Document 3, page 36 65 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Comments 2 3 • Capacity Mix 4 5 HQD’s proposed Supply Plan calls for its long-term supply needs to be met by a 6 combination of modulable/cyclable and baseload resources. Table 27 sets out the 7 capacity mix resulting from the proposed Supply Plan. As noted earlier, HQD has not 8 provided a definitive breakdown of its required capacity mix over the planning period173. 9 However, for purposes of this evidence an estimate has been developed and included 10 previously in Table 14. Contrasting the acquisition mix in Table 27 with the 11 requirements set out in Table 14 indicates that, while there are years where there is a 12 capacity shortfall relative to the distributor’s expected requirements, the baseload 13 resources contracted for generally meet (and sometimes exceed) HQD’s baseload 14 demand. This observation is consistent with HQD’s own comments 174 that additional 15 cyclable resources are needed towards the end of the planning period. 16 17 However, the fact that HQD has already contracted for sufficient baseload capacity and, 18 if anything, requires more modulable or cyclable capacity raises the question as to 19 whether simply advancing the timing and increasing the quantities associated with the 20 planned CFT for cogeneration (which is also a baseload resource) would be the 21 appropriate response to a higher load forecast. Ideally, given the capacity mix 22 associated with the Plan, the response would also include acquisition of additional 23 modulable and/or cyclable resources. 24 25 As an alternative to contracting for additional modulable/cyclable capacity, HQD could 26 contract for additional baseload generation and resell any excess not required to meet 27 domestic needs. S uch an arrangement is likely to be more costly and expose 28 consumers to the risks associated with short-term energy market prices175. However, it 173 174 175 HQD-5, Document 6, page 41, Responses 52.1 and 52.2 HQD-3, Document 3, page 24 HQD-5, Document 4, pages 18-19, Response 17.1 66 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 could open up the opportunity to provide modulable/cyclable capacity to wind power and 2 cogeneration projects and should be explored further by HQD. 3 Table 27 Capacity Mix of Proposed Supply Plan 20072008 20092010 20112012 20132014 500 350 500 350 500 350 500 350 36 36 36 36 131 208 321 361 0 70 0 350 210 0 350 350 100 350 350 250 Total Baseload 1087 1654 2007 2197 Modulable/Cyclable A/O 2002-1 - HQP - Cyclable CFT for Modulable Total Modulable/Cyclable 250 0 250 250 400 650 250 400 650 250 400 650 560 560 560 560 47 607 47 607 47 607 47 607 1944 2911 3264 3454 Baseload A/O 2002-1 - TCE - HQP - Base A/O 2003-1 - Biomass A/O 2003-2 - Wind A/O 2004-2 - Cogen Second Wind CFT Second Cogen CFT Peaking Interrputible Power A/O 2002-1 - TCE Total Peaking Total 4 5 6 • Load Balancing and Cyclable Resources 7 8 HQD has indicated that it could be advantageous to adapt the load balancing service 9 required for wind to meet cyclable requirements 176 and that it will further analyze the 176 HQD-5, Document 6, page 41, Response 52.1 67 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 issue during 2005. This would represent a totally different approach to load balancing 2 services than that envisioned in the proposed Supply Plan. The load balancing services 3 currently envisioned by the Plan do not generate any incremental energy or capacity 4 requirements 177 for HQD but rather just “firm-up” the wind resources contracted for so 5 that they can be considered a firm baseload resource for planning purposes. Under 6 such service arrangements, it would be the responsibility of the load balancing service 7 supplier to have: • 8 9 The ability to accept (i.e., through the use of storage, ability to use or resell) excess wind production as required by HQD, and • 10 The ability to deliver any shortfall in energy experienced by HQD between the 11 firm hourly energy attributed to the wind contracts and actual deliveries received 12 (either from hydro storage or other production sources) up to the level of firm 13 power MWs attributed to the wind contracts (e.g., 351 MW for the first CFT). 14 However, the supplier would also have an expectation that the receipts and deliveries 15 to HQD would balance out over pre-determined time frame such as one year. The cost 16 of such load balancing services would likely reflect the value of the capacity that has 17 effectively been reserved for HQD along with any differences in what would be consider 18 the opportunity value associated with receipts of any excess wind production versus the 19 opportunity costs associated with the delivery of energy to make up any shortfalls in 20 wind energy production178. 21 22 While there is “capacity” associated with such a load balancing service, it must be 23 “reserved” for those instances when there is insufficient wind to produce the MWs of 24 power that the Supply Plan is attributing to the wind contracts. The same capacity can 25 not also be contracted for as a cyclable resource which theoretically could be called 26 upon at the same time. Similarly, the load balancing service envisioned in the current 27 Plan does not increase the total energy available to HQD over a year, as a cyclable 28 resource should be capable of doing. While it may be possible to combine a contract 177 HQD-5, Document 6, page 17, Responses 18.1 and 18.2 These opportunity costs are likely to be similar to those associated with the HQP framework agreement as discussed in Section 4.2.2 178 68 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 for load balancing services with a contract for cyclable resources such a contract would 2 require the supplier to commit additional capacity to HQD and would – if the cyclable 3 terms of the arrangement were activated – involve net energy deliveries from the 4 supplier to HQD. Both of these requirements would increase the overall costs of the 5 service. 6 7 The alternative would be for HQD to contract with a cyclable resource solely for the 8 purpose of back stopping the wind contracts. In such an event, the cyclable resource 9 would serve to meet HQD’s firm capacity requirement and supplement the energy 10 production available from the wind generators as required. However, under such an 11 approach, HQD would also have to make arrangements to dispose (sell) of any excess 12 wind generation. This would require a different framework agreement with HQP, i.e., 13 one where excess production is not deemed to be from the Heritage Pool and is subject 14 to resale. Another way for HQD to manage excess wind power production would be to 15 increase the flexibility in its contracts with other suppliers such that their deliveries could 16 be varied more over time and reduced on short notice. 17 18 • Revised Capacity Requirements 19 20 The revised capacity reserve margin requirements mean that more capacity will be 21 required over the long term (i.e., 2009-2010 through 2013-2014) than identified in 22 HQD’s Application. Table 28 illustrates the potential shortfall assuming a reserve 23 margin of 11% for 2009-2010 and beyond. 69 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 28 Long Term Capacity Balance (Based on Revised Reserve Requirements) (MW) Additional Req. - Medium Forecast plus Revised Reserves(1) Planned Acquisitions (2) - 2nd Wind CFT - CFT for Modulable Capacity - CFT for CoGen Capacity Total Supply Surplus/(Deficit) Source: 1 2 20092010 20102011 20112012 20122013 20132014 808 938 1,113 1,334 1,579 210 400 250 400 350 400 350 400 350 400 0 0 100 100 250 610 650 850 850 1000 -198 -288 -263 -484 -579 1) Table 19 2) HQD-3, Document 3, page 26 3 Furthermore, given the earlier comments regarding supply mix, the additional capacity 4 requirements would be for dispatchable as opposed to baseload resources. 5 6 • Revised Energy Criteria 7 8 Earlier comments 179 also suggested increasing the timeframe used to establish the 9 standard deviation for the long -term energy reliability criteria from 4 to 6 years. Table 10 28 sets out the extent to which HQD’s proposed 2005 Plan meets this more 11 conservative criterion. 179 See Sections 4.1.1 and 4.6 70 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 Table 29 Long Term Energy Balance Based on Medium Load Forecast Plus Revised Reliability Margin (TWh) Additional Req. (1) - Medium Forecast - One Stanard Dev Total Planned Acquistions (2) - 2nd Wind CFT - CFT for Modulable Capacity - CFT for Cogen (3) Capacity Total Supply Surplus/ (Deficit) Source: 2009 2010 2011 2012 2013 2014 2 8.9 10.9 1.9 9.9 11.8 2.7 9.9 12.6 4.3 9.9 14.2 4.3 9.9 14.2 5.6 9.9 15.5 1.3 0.3 1.9 3.2 2.5 3.2 3.1 3.2 3.1 3.2 3.1 3.2 0 0.5 2.1 3.6 3.6 3.6 1.6 5.6 7.8 9.9 9.9 9.9 -9.3 -6.2 -4.8 -4.3 -4.3 -5.6 1) Table 22 2) HQD-3, Document 3, page 38 3) Assumes a one-year advancement of the CFT for Cogen Resources and an increase in the total cogen resources called for. 1 2 3 Advancing and increasing the capacity for new cogeneration resources as provided for 4 in HQD’s 2005 Plan does not satisfy the 5 TWh long-term limit in all years. However, 5 addressing the additional capacity requirements arising from the revised capacity 6 reserve margin could provide sufficient dispatchable capacity to allow the energy 7 reliability criterion to also be satisfied. 8 9 5.2.3 Conclusions 10 11 Supply Resource Options 12 13 HQD’s primary long-term supply options are hydro, cogeneration, wind energy and 14 combined cycle generation. Of the four sources, hydro, cogeneration and combined 71 Evidence of William Harper Hydro-Québec Distribution Régie File R-3550-2004 1 cycle are reasonably comparable in terms of cost; while wind energy is more 2 expensive 180. However, out of the three cost competitive options only combined cycle 3 and hydro offer the flexibility of being able to operate in a modulable/cyclable, as well as 4 a baseload mode. While increased reliance on wind energy has environmental benefits, 5 it is likely to lead to increases in the costs of electricity to consumers and over-reliance 6 could reduce the flexibility of HQD’s resource base to respond to changes in energy 7 requirements. 8 9 Reliance on Generation External to Québec 10 11 There appears to be some 9 TWh of inter-tie capability181 that could be used to import 12 resources acquired under long -term contracts from sources external to Québec; while 13 still leaving the 15 TWh of capacity that the proposed 2005-2014 Plan relies on for 14 short-term purchases by HQD and HQP. 15 16 Long-Term Capacity Requirements 17 18 Based on the revised reserve margins presented in Section 4.6, HQD’s proposed 2005 19 Plan results in a capacity deficit of roughly 200 to 260 MW for the period 2009-2010 20 through 2011-2012. Assuming a four year lead time for additional long-term resources, 21 CFTs to address the bulk of this deficit would have to be initiated later this year. 22 23 Long-Term Energy Reliability 24 25 HQD’s proposed Supply Plan falls short of meeting the revised long-term energy 26 reliability criteria presented in Section 4.6 in a couple years following 2009-2010. 27 However, this shortfall would likely be resolved by the new resource additions required 28 to address capacity reliability. 180 This conclusion with respect to wind energy is based on the cost of the selected offers from A/O 200302 and the fact that the quoted costs do not include any costs for load balancing. 181 See Section 5.2.1’s Comments 72 Evidence of William Harper 1 Hydro-Québec Distribution Régie File R-3550-2004 Supply Mix 2 3 The planned CFT for 400 MW of modulable capacity is critical to maintaining the 4 appropriate balance in HQD’s supply mix. Furthermore, given that the level of baseload 5 generation currently planned for appears to be sufficient, any additional resources 6 acquired to address the capacity shortfall discussed above will also need to be provide 7 for the HQD’s modulable /cyclable capacity requirements. 8 9 Similarly, HQD’s plans for responding to higher-than-forecast load growth should 10 consider the acquisition of additional modulable /cyclable generation. This strategy 11 would be preferable to the one currently proposed in the Plan, which consists of merely 12 advancing the in-service date and increasing the capacity associated with the planned 13 CFT for (baseload) cogeneration. 14 15 In the interest of maintain flexibility in terms of its supply options, HQD should 16 investigate further the implications of contracting for reselling excess baseload capacity. 17 18 Load Balancing Service for Wind Energy 19 20 It is imperative that HQD determine the approach it will be taking with regard to load 21 balancing services and establish the necessary contracts to support its wind energy 22 acquisitions as soon as possible for a number of reasons: 23 • 24 25 Such contracts are required to allow the currently acquired wind energy generation to be “counted on” for reliability and planning purposes; • The approach that HQD decides to take with respect to load balancing services 26 could impact on the evolution of both HQD’s overall supply mix, as well as its 27 capacity requirements, and 28 29 • The true cost of wind e nergy can only be known after the cost the load balancing services are known. 73 Evidence of William Harper 1 6 Hydro-Québec Distribution Régie File R-3550-2004 Issues From Previous Régie Decisions 2 3 In the last chapter of its Application182, HQD provided follow-up to various issues 4 identified by the Régie in earlier decisions. 5 6 6.1 Evaluation of Transmission Costs for Small Scale Plants 7 8 In Decision-2004-115, the Régie raised an issue with respect to the impact of 9 transmission-related costs (for connection, etc.) on the overall project costs for small- 10 scale plants, and requested that HQD present alternatives in its next Plan. HQD 11 acknowledges this impact but notes that it arises due to the inclusion of connection 12 costs in the evaluation. However, to exclude the cost of such equipment from the 13 evaluation would result in projects being evaluated at less than their real costs. The 14 only other alternative offered by HQD was to initiate a CFT that would be restricted to 15 small scale plants. But, HQD notes that to do so would require direction from the 16 provincial government183. 17 18 Comment 19 20 Arbitrarily e xcluding certain cost elements from the evaluation of the offers received 21 through a CFT would create an unlevel playing field for the various bidders and could 22 also (inadvertently) lead to the selection of a more costly option for electricity 23 consumers. In contrast, while the current CFT evaluation process (as described in 24 HQD-3, Document 4, page 19) includes considerations other than least-cost, these 25 considerations along with their respective weight are explicitly set out in the selection 26 criteria. As result, HQD’s conclusions regarding this issue are reasonable. 182 183 HQD-3, Document 5 HQD-3, Document 5, pages 5- 6 74 Evidence of William Harper 1 6.2 Hydro-Québec Distribution Régie File R-3550-2004 Evaluation of Transmission Costs 2 3 In D-2002-117, the Régie raised certain issues regarding the methodology used to 4 evaluate transmission costs and, specifically, the treatment of current plants and the 5 loss of transmission capacity margins. HQD notes that while its original proposal had 6 been to impute to existing plants a cost equivalent to the loss of TransÉnergie’s 7 revenues, this was not done in the A/O 2002-01 CFT184. With respect to the issue of 8 transmission capacity margins, HQD’s position is that the imputation of capacity margin 9 costs to a proposed generation plant responding to a CFT would be inconsistent with its 10 mandate to select proposals based on lowest cost 185. 11 12 Comments 13 14 Presumably any transmission revenues arising from the current use of TransÉnergie’s 15 system by existing generating stations are based on contracts for point to point service 16 as per Hydro-Québec’s Transmission Tariff. Provided the existing generators meet their 17 current contractual obligations, HQD’s current practice of not imputing any opportunity 18 costs to the future lost revenues appears reasonable. 19 20 With respect to the issue of transmission capacity margins, HQD’s proposed approach 21 is reasonable as long as: 22 • 23 24 the transmission costs included in the evaluation represent all of the incremental costs that TransÉnergie will incur over its long-term planning horizon, and • 25 the determination of the incremental network facilities that could be required is made after an allowance for HQD’s expected load growth. 184 185 HQD-3, Document 5, page 7 HQD-3, Document 5, pages 7-8 75 Evidence of William Harper 1 6.3 Hydro-Québec Distribution Régie File R-3550-2004 Contract Term 2 3 In D-2002-117, the Régie requested HQD to allow supply contracts of a duration of 15 4 to 25 years with an option for renewal at the discretion of the supplier in order to allow 5 the greatest number of suppliers to respond to the CFT. In the current Application, 6 HQD expresses the opinion that the contract terms should be reduced to 15-20 years. 7 HQD notes that it is difficult to predict the prices of electricity or the state of the 8 supplier’s equipment into the distant future and that allowing renewal at the discretion of 9 the supplier would be disadvantageous to HQD’s customers 186. 10 11 Comments 12 13 HQD’s request to reduce the duration of the contracts to 15-20 years is reasonable. 14 Long-term electricity prices are difficult to forecast and even tying the prices to indices 15 for natural gas prices or electricity prices in adjacent markets may lead to difficulties in 16 the very long term as technology and markets evolve. Similarly, uncertainty with 17 respect to the performance of the resources providing the contracted supply will 18 increase over the longer term as the associated facilities age. Long-term contracts 19 typically include guarantees with respect to the minimum deliveries that the buyer will 20 receive 187. However, this essentially just transfers the risk to the supplier who, 21 presumably, will reflect it in the proposed contract price. 22 23 HQD concerns about granting suppliers the option to renew at their discretion are also 24 valid. 186 187 HQD-3, Document 5, pages 8 - 9. HQD-3, Document 4, page 6. 76 APPENDIX A CV FOR ECS CONSULTANT 77 ECONALYSIS CONSULTING SERVICES William O. Harper Mr. Harper has over 20 year experience in the design of rates and the regulation of electricity utilities. He has testified as an expert witness on rates before the Ontario Energy Board from 1988 to 1995, and before the Ontario Environmental Assessment Board. He was responsible for the regulatory policy framework for Ontario municipal electric utilities and for the regulatory review of utility submissions from1989 to 1995. Mr. Harper coordinated the participation of Ontario Hydro (and its successor company Ontario Hydro Services Company) in major public reviews involving Committees of the Ontario Legislature, the Ontario Energy Board and the Macdonald Committee. He has served as a speaker on rate and regulatory issues for seminars sponsored by the APPA, MEA, EPRI, CEA, AMPCO and the Society of Management Accountants of Ontario. Since joining ECS, Mr. Harper has provided consulting support for client interventions on energy and telecommunications issues before the Ontario Energy Board, Manitoba Public Utilities Board, Québec’s Régie de l’énergie, British Columbia Utilities Commission, and CRTC. He has also appeared before the Manitoba’s Public Utilities Board, the Manitoba Clean Environment Commission and Quebec’s Régie de l’énergie. Bill is currently a member of the Ontario Independent Electricity System Operator’s Technical Panel. EXPERIENCE Econalysis Consulting Services- Senior Consultant 2000 to present • Responsible for supporting client interventions in regulatory proceedings, including issues analyses & strategic direction, preparation of interrogatories, participation in settlement conferences, preparation of evidence and appearance as expert witness (where indicated by an asterix). 78 • Electricity o IMO 2000 Fees (OEB) o Hydro One Remote Communities Rate Application 2002-2004 o OEB - Transmission System Code Review (2003) o OEB - Distribution Service Area Amendments (2003) o OEB – Regulated Asset Recovery (2004) o OEB – Regulated Price Plan (2004/05) o OEB – Framework for 2006 Electricity Distribution Rates* o BC Hydro IPP By-Pass Rates o WKP Generation Asset Sale o FortisBC – 2005 Revenue Requirement Application o BC Hydro Heritage Contract Proposals o BC Hydro’s 2004/05 and 2005/06 Revenue Requirement Application o BC Transmission Corporation – Open Access Transmission Tariff Application -2004 o BC Hydro’s CFT for Vancouver Island Generation – 2004 o BC Transmission Corporation – 2005/06 Revenue Requirement Application o BC Hydro’s 2005 Resource Expenditure and Acquisition Plan o Hydro Québec-Distribution’s 2002-2011 Supply Plan* o Hydro Quebec-Distribution’s 2002-2003 Cost of Service and Cost Allocation Methodology* o Hydro Québec-Distribution’s 2004-2005 Tariffs* o Hydro Québec – Distribution’s 2005/2006 Tariff Application* o Manitoba Hydro’s Status Update Re: Acquisition of Centra Gas Manitoba Inc.* o Manitoba Hydro’s Diesel 2003/04 Rate Application* o Manitoba Hydro’s 2004/05 and 2005/06 Rate Application* o Manitoba Hydro/NCN NFAAT Submission re: Wuskwatim* o Manitoba Hydro – Confirmation of April 2005 Conditional Rate Increase • Natural Gas Distribution o Enbridge Consumers Gas 2001 Rates o BC Centra Gas Rate Design and Proposed 2003-2005 Revenue Requirement o Rate of Return on Common Equity (BCUC-2001) o Terasen Gas (Vancouver Island) LNG Storage Project (2004) • Telecommunications Sector o Access to In-Building Wire (CRTC) o Extended Area Service (CRTC) o Regulatory Framework for Small Telecos (CRTC) 79 • Other o Acted as Case Manager in the preparation of Hydro One Networks’ 20012003 Distribution Rate Application o Supported the implementation of OPG’s Transition Rate Option program prior to Open Access in Ontario o Participated in arbitration proceedings providing expert evidence on behalf of Clients o Prepared Client Studies on various issues including: § The implications of the 2000/2001 natural gas price changes on natural gas use forecasting methodologies. § The separation of electricity transmission and distribution businesses in Ontario. § The business requirements for Ontario transmission owners/operators. § Various issues associated with electricity supply/distribution in remote communities Hydro One Networks Manager - Regulatory Integration, Regulatory and Stakeholder Affairs (April 1999 to June 2000) • • • Supervised professional and administrative staff with responsibility for: o providing regulatory research and advice in support of regulatory applications and business initiatives; o monitoring and intervening in other regulatory proceedings; o ensuring regulatory requirements and strategies are integrated into business planning and other Corporate processes; o providing case management services in support of specific regulatory applications. Acting Manager, Distribution Regulation since September 1999 with responsibility for: o coordinating the preparation of applications for OEB approval of changes to existing rate orders; sales of assets and the acquisition of other distribution utilities; o providing input to the Ontario Energy Board’s emerging proposals with respect to the licences, codes and rate setting practices setting the regulatory framework for Ontario’s electricity distribution utilities; o acting as liaison with Board staff on regulatory issues and provide regulatory input on business decisions affecting Hydro One Networks’ distribution business. Supported the preparation and review before the OEB of Hydro One Networks’ Application for 1999-2000 transmission and distribution rates. 80 Ontario Hydro Team Leader, Public Hearings, Executive Services (April 1995 TO April 1999) • • Supervised professional and admin staff responsible for managing Ontario Hydro’s participation in specific public hearings and review processes. Directly involved in the coordination of Ontario Hydro’s rate submissions to the Ontario Energy Board in 1995 and 1996, as well as Ontario Hydro’s input to the Macdonald Committee on Electric Industry Restructuring and the Corporation’s appearance before Committees of the Ontario Legislature dealing with Industry Restructuring and Nuclear Performance. Manager – Rates, Energy Services and Environment (June 1993 to April 95) Manager – Rate Structures Department, Programs and Support Division (February 1989 to June 1993) • • • • Supervised a professional staff with responsibility for: o Developing Corporate rate setting policies; o Designing rates structures for application by retail customers of Ontario Hydro and the municipal utilities; o Developing rates for distributors and for the sale of power to Hydro’s direct industrial customers and supporting their review before the Ontario Energy Board; o Maintaining a policy framework for the execution of Hydro’s regulation of municipal electric utilities; o Reviewing and recommending for approval, as appropriate, municipal electric utility submissions regarding rates and other financial matters; o Collecting and reporting on the annual financial and operating results of municipal electric utilities. Responsible for the development and implementation of Surplus Power, Real Time Pricing, and Back Up Power pricing options for large industrial customers. Appeared as an expert witness on rates before the Ontario Energy Board and other regulatory tribunals. Participated in a tariff study for the Ghana Power Sector, which involved the development of long run marginal cost-based tariffs, together with an implementation plan. Section Head – Rate Structures, Rates Department November 1987 to February 1989 • With a professional staff of eight responsibilities included: o Developing rate setting policies and designing rate structures for application to retail customers of municipal electric utilities and Ontario Hydro; o Designing rates for municipal utilities and direct industrial customers and supporting their review before the Ontario Energy Board. 81 • • Participated in the implementation of time of use rates, including the development of retail rate setting guidelines for utilities; training sessions for Hydro staff and customers presentations. Testified before the OEB on rate-related matters. Superintendent – Rate Economics, Rates and Strategic Conservation Department February 1986 to November 1987 • Supervised a Section of professional staff with responsibility for: o Developing rate concepts for application to Ontario Hydro’s customers, including incentive and time of use rates; o Maintaining the Branch’s Net Revenue analysis capability then used for screening marketing initiati ves; o Providing support and guidance in the application of Hydro’s existing rate structures and supporting Hydro’s annual rate hearing. Power Costing/Senior Power Costing Analyst, Financial Policy Department April 1980 to February 1986 • • Duties included: ? o Conducting studies on various cost allocation issues and preparing recommendations on revisions to cost of power policies and procedures; o Providing advice and guidance to Ontario Hydro personnel and external groups on the interpretation and application of cost of power policies; o Preparing reports for senior management and presentation to the Ontario Energy Board. Participated in the development of a new costing and pricing system for Ontario Hydro. Main area of work included policies for the time differentiation of rates. Ontario Ministry of Energy Economist, Strategic Planning and Analysis Group April 1975 to April 1980 • • • ? articipated in the development of energy demand forecasting models for the P province of Ontario, particularly industrial energy demand and Ontario Hydro’s demand for primary fuels. Assisted in the preparation of Ministry publications and presentations on Ontario’s energy supply/demand outlook. Acted as an economic and financial advisor in support of Ministry programs, particularly those concerning Ontario Hydro. 82 EDUCATION Master of Applied Science – Management Science • • • University of Waterloo, 1975 Major in Applied Economics with a minor in Operations Research Ontario Graduate Scholarship, 1974 Honours Bachelor of Science • • • University of Toronto, 1973 Major in Mathematics and Economics Alumni Scholarship in Economics, 1972 83