Schedule “B” HQCMÉ’s Registration Information and Applicable Standards for RTA Standards Included Title BAL-005-0b Automatic Generation Control Applicable to RTA as: GOP-2 Requirements R1.1. Each Generator Operator with generation facilities operating in an Interconnection1 shall ensure that those generation facilities are included within the metered boundaries of a Balancing Authority Area2. Brief description Making sure all generation (energy injected or withdrawn from the BA area is included within the metered boundaries of a Balancing Authority area. That is metered by HQCMÉ as BA. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Bulk While, RTA’s generation resources are primarily for its own load displacement needs, it does enter into commercial agreements from time to time, for the purposes of providing HQ net energy sales that are in excess of its own needs. Requirement ought to apply, as per existing agreements and current installations, in order to have metering at the interconnections with HQT for monitoring and billing net energy exchanges for use in HQCMÉ’s resource adequacy analysis for Québec load and net energy injections required to service RTA’s load and those of HQ interconnected to RTA’s Installations. NA for each GO unit/plant. CIP-001-1 Sabotage Reporting GOP2 R1. Each [...], Generator Operator [...], shall have procedures for the recognition of and for making their operating personnel aware of sabotage events on its facilities and multi-site sabotage affecting larger portions of the Interconnection. R2. Each [...], Generator Operator [...], shall have procedures 2 Each responsible entity must have documented sabotage reporting procedures and communication protocols in place for communicating such events to the appropriate internal staff, other Non Bulk See NERC Glossary of terms; Interconnection means; when capitalized, any one of the three major electric system networks in North America: Eastern, Western, and ERCOT (Authors note: now includes Québec). See NERC Glossary of terms; Balancing Authority Area means; the collection of generation, transmission, and loads within the metered boundaries of the Balancing Authority. The Balancing Authority maintains load-resource balance within this area. #1732371 Page 1 Standards Included Title Applicable to RTA as: Requirements for the communication of information concerning sabotage events to appropriate parties in the Interconnection. Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process entities and authorities, including the RC. R3. Each [...], Generator Operator [...], shall provide its operating personnel with sabotage response guidelines, including personnel to contact, for reporting disturbances due to sabotage events. R4. Each [...], Generator Operator [...], shall establish communications contacts, as applicable, with local Federal Bureau of Investigation (FBI) or Royal Canadian Mounted Police (RCMP) officials and develop reporting procedures as appropriate to their circumstances. COM-002-2 EOP-004-1 Communication and Coordination GOP-2 Disturbance Reporting GOP-2 R1. Each GOP shall have communications (voice and data links) with appropriate Reliability Coordinators, Balancing Authorities, and Transmission Operators. Such communications shall be staffed and available for addressing a real-time emergency condition. Having the capability and staff to communicate with HQCMÉ for emergency situations. R2.Each GOP shall promptly analyze Bulk Electric System disturbances on its system or facilities. Analysis and report of disturbances affecting the responsible entity’s facilities. R3. Each GOP experiencing a reportable incident shall provide a preliminary written report to its Regional Reliability Organization and NERC. (Per Requirement R3.1, R3.2 and R.3.3). R3.4. If, in the judgment of the Regional Reliability Organization, after consultation with the Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Operator, or Load Serving Entity in which a disturbance occurred, a final report is required, the affected Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Operator, or Load Serving Entity shall prepare this report within 60 days. As a minimum, the final report shall have a discussion of the events and its cause, the conclusions reached, and recommendations to prevent recurrence of this type of event. The report shall be subject to Regional Reliability Organization approval. #1732371 Non Bulk RTA has existing processes, procedures and communication facilities in place with HQT and HQCMÉ for its interconnection with HQT. Non Bulk RTA has existing processes and procedures with HQT allowing appropriate assessment of incidents in order to enable HQT and HQCMÉ to meet their disturbance reporting obligations to NERC and NPCC, if such disturbance is reportable. RTA reporting (verbal and written) should remain to HQCMÉ, in its capacity as the RC, per existing protocols, not directly to NPCC and NERC. Incident investigation / followups are best coordinated exclusively by one entity, the RC. Page 2 Standards Included FAC-001-0 Title Facility Connection Requirements Applicable to RTA as: TO-3 Requirements Brief description R1. The Transmission Owner shall document, maintain, and publish facility connection requirements to ensure compliance with NERC Reliability Standards and applicable Regional Reliability Organization, subregional, Power Pool, and individual Transmission Owner planning criteria and facility connection requirements. The Transmission Owner’s facility connection requirements shall address connection requirements for: i) generation, ii) transmission and iii) end-user facilities Note: This standard is typically for transmission owners like HQT, Hydro One, etc. It is not normally intended for generator owners that have their own transmission “distribution” assets used for interconnecting their own facilities and legacy local loads. R2. The Transmission Owner’s facility connection requirements shall address, but are not limited to, the following items: (all listed sub items). Coordination of Plans For New Generation, Transmission, and End-User TO3, GO-2 R1. The.[...] Generator Owner, Transmission Owner, Distribution Provider, and Load-Serving Entity seeking to integrate generation facilities, transmission facilities, and electricity end-user facilities shall each coordinate and cooperate on its assessments with its Transmission Planner and Planning Authority. The assessment shall include: R1.1 to R1.5 Transmission Vegetation TO-3 R1. The Transmission Owner shall prepare, and keep current, a formal transmission vegetation management program Although RTA’s Installations do interconnect HQ load transfer customers3 per existing transmission service agreements, its facilities are designed for its own use, and are not intended for use by HQ customers. Connection requirements for connecting HQ local loads to RTA' s Installations are documented in the transmission service provider’s agreement with HQT. Coordinating new connections, or facilities with TP4 and PC5 Non Bulk For facilities that potentially affect the local area, requires RTA to follow HQT connection and approval processes. To that end, RTA has set up a committee with HQT to address additions and/or modifications to RTA’s Installations or changes to HQT’s network that may impact the local area. R2. The Transmission Owner shall retain its documentation (of its evaluation of the reliability impact of the new facilities and their connections on the interconnected transmission systems) for three years and shall provide the documentation to the Regional Reliability Organization(s) and NERC on request (within 30 calendar days). FAC-003-1 NA Therefore, a connection requirement document is not warranted. R3. The Transmission Owner shall maintain and update its facility connection requirements as required. The Transmission Owner shall make documentation of these requirements available to the users of the transmission system, the Regional Reliability Organization, and NERC on request (five business days). FAC-002 -0 “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Maintaining vegetation under and along transmission right-of-way Non Bulk RTA currently has a vegetation 3 Load transfer customer refers to situations where one distributor’s/transmission system transfers energy or provides transmission service to another entities load over its system. TP means “Transmission Planner”. 5 PC means “Planning Coordinator”. #1732371 4 Page 3 Standards Included Title Applicable to RTA as: Management Program Requirements (TVMP). The TVMP shall include the Transmission Owner’s objectives, practices, approved procedures, and work specifications. R1.1 to R1.5 Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process (ROW) for transmission lines 200 kV and above and those the RRO6 (RC in Québec’s case) deems critical. management program in place on all transmission lines, with current reporting to HQCMÉ. R2. The Transmission Owner shall create and implement an annual plan for vegetation management work to ensure the reliability of the system. The plan shall describe the methods used, such as manual clearing, mechanical clearing, herbicide treatment, or other actions. The plan should be flexible enough to adjust to changing conditions, taking into consideration anticipated growth of vegetation and all other environmental factors that may have an impact on the reliability of the transmission systems. Adjustments to the plan shall be documented as they occur. The plan should take into consideration the time required to obtain permissions or permits from landowners or regulatory authorities. Each Transmission Owner shall have systems and procedures for documenting and tracking the planned vegetation management work and ensuring that the vegetation management work was completed according to work specifications. Application of the requirement for “Non Bulk” lines of 200 kV and above to be based on what HQT proposes for its own “Non Bulk” transmission lines for consistency in application. R3. The Transmission Owner shall report quarterly to its RRO, or the RRO’s designee, sustained transmission line outages determined by the Transmission Owner to have been caused by vegetation. R3.1 to R3.4 FAC-008-1 Facility Ratings Methodology TO-3, GO-2 R1. The Transmission Owner and Generator Owner shall each document its current methodology used for developing Facility Ratings (Facility Ratings Methodology) of its solely and jointly owned Facilities. The methodology shall include all of the following: R1.1 to R1.3.5. R2. The Transmission Owner and Generator Owner shall each make its Facility Ratings Methodology available for inspection and technical review by those Reliability Coordinators, Transmission Operators, Transmission Planners, and Planning Authorities that have responsibility for the area in which the associated Facilities are located, within 15 business days of receipt of a request. Facility owners are responsible for documents relating to methodologies used in developing facility and equipment ratings. The facility ratings methodology used could include nameplate ratings, engineering analysis, IEEE standards, standards developed following accredited procedures of the Canadian Standards Association (CSA), etc. Non Bulk The primary focus of these reliability requirements should be the transmission facilities interconnecting with HQT. The facility ratings and the capabilities of the generation units have commercial implications only rather than reliability (security) implications for HQT or HQCMÉ. 6 RRC means “Regional Reliability Organization”. #1732371 Page 4 Standards Included Title Applicable to RTA as: Requirements Brief description R3. If a Reliability Coordinator, Transmission Operator, Transmission Planner, or Planning Authority provides written comments on its technical review of a Transmission Owner’s or Generator Owner’s Facility Ratings Methodology, the Transmission Owner or Generator Owner shall provide a written response to that commenting entity within 45 calendar days of receipt of those comments. The response shall indicate whether a change will be made to the Facility Ratings Methodology and, if no change will be made to that Facility Ratings Methodology, the reason why. FAC-009-1 Establish and Communicate Facility Ratings TO-3, GO-2 R1. The Transmission Owner and Generator Owner shall each establish Facility Ratings for its solely and jointly owned Facilities that are consistent with the associated Facility Ratings Methodology. R2. The Transmission Owner and Generator Owner shall each provide Facility Ratings for its solely and jointly owned Facilities that are existing Facilities, new Facilities, modifications to existing Facilities and re-ratings of existing Facilities to its associated Reliability Coordinator(s), Planning Authority(ies), Transmission Planner(s), and Transmission Operator(s) as scheduled by such requesting entities. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Commercial arrangements entered into with RTA for HQCMÉ’s resource adequacy relates to the provision of “net” energy available in excess of RTA’s needs at the interconnection with HQT and is unrelated to the capability of any specific generating unit or their interconnected facilities. As such, the methodology used to establish each unit’s capability or their interconnecting facilities is unwarranted. Requires establishment and communication of the facility ratings or changes to ratings established in accordance with methodologies established under FAC-008, to its TOP, TP, PC and RC. Non Bulk While HQT, in its role as the TOP, the PC and the TP, requires RTA’s facility rating information for its interconnection with HQT for purposes of its (HQCMÉ’s and HQT’s) models to meet the transmission planning standards and for calculating SOLs, this is a local area impact issue for the HQT interconnection and should remain a local area reliability related issue and be managed accordingly per HQCMÉ’s and HQT’s model needs. Commercial arrangements entered into with RTA for HQCMÉ’s resource adequacy relates to the provision of “net” energy available in excess of RTA’s needs at the interconnection with HQT and is unrelated to the capability of specific generating units unit or their interconnected facilities. #1732371 Page 5 Standards Included Title Applicable to RTA as: Requirements Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process As such, the provision of individual unit capability or their interconnecting facilities’ ratings to others is unwarranted. IRO-001-1 Reliability Coordination — Responsibilities and Authorities TSP-3, GOP-2 R8. The Generator Operators and Transmission Service Providers, shall comply with Reliability Coordinator directives unless such actions would violate safety, equipment, or regulatory or statutory requirements. Under these circumstances, the Transmission Operator, Balancing Authority, Generator Operator, Transmission Service Provider, Load-Serving Entity, or Purchasing-Selling Entity shall immediately inform the Reliability Coordinator of the inability to perform the directive so that the Reliability Coordinator may implement alternate remedial actions. The standard establishes the accountabilities and authorities of the RC. R8.: Requires the listed responsible entities to take action as directed by the RC (HQCMÉ) for “real-time” day to day operations. These actions typically concern the to maintaining of system operating limits (SOL), which is a local area issue, and related to the interconnections with HQT. Non Bulk For the interconnections with HQT, pursuant to the directive of the RC, this standard is related to SOL7 limits, which is a local area reliability related issue only. With respect to any “net” energy injections at these interconnects per commercial agreements, the standard is applicable when SOLs or IROLs are impacted by these energy injections. The TSP function is only applicable to RTA if HQP uses point to point service and the associated required e-tags (INT standards) or arranged for transmission service to service their loads via RTA’s Installations. IRO-004-1 Reliability Coordination Operations Planning TSP-3 R1. Each Transmission Operator, Balancing Authority, and Transmission Service Provider shall comply with the directives of its Reliability Coordinator based on the next day assessments in the same manner in which it would comply during real time operating events. R1. TSP must follow the direction of the RC for security (SOL and IROL) assessment that the RC has made for next day operations, similar to those required to follow for real time (IRO-005). Typically, this regards interconnections between jurisdictions, e.g. Québec - New York, and the transfer capabilities of those ties lines, for next day operations, unless point to point Non Bulk For RTA’s Installations, based on HQCMÉ studies, this is limited to the interconnection with HQT for local area SOL limits and “net” energy injections, per existing commercial agreements, which is the limit of HQCMÉ’s purview as the RC for RTA’s Installations with respect to managing facilities within their 7 SOL means “System Operating Limit”. #1732371 Page 6 Standards Included Title Applicable to RTA as: Requirements Brief description transmission service is also used. ratings. The standard places the obligation on RTA as a TSP to follow the direction of the RC for day ahead SOL limits (local area limits) related to physical transmission service it has provided to PSEs (e.g. HQP) for arranged commercial energy transactions. RTA’s explicit TSP reliability obligations under this standard for actions related to provision of point to point transmission service to HQ loads or otherwise need to be clarified by HQCMÉ. For a TSP, this is the same as Requirement R8 in IRO-001, but for next day’s operations. IRO-005-2 Reliability Coordination Current Day Operations TSP-3, GOP-2 R13. Each Reliability Coordinator shall ensure that all Transmission Operators, Balancing Authorities, Generator Operators, Transmission Service Providers, Load-Serving Entities, and Purchasing-Selling Entities operate to prevent the likelihood that a disturbance, action, or non-action in its Reliability Coordinator Area will result in a SOL or IROL violation in another area of the Interconnection. In instances where there is a difference in derived limits, the Reliability Coordinator and its Transmission Operators, Balancing Authorities, Generator Operators, Transmission Service Providers, Load-Serving Entities, and Purchasing-Selling Entities shall always operate the Bulk Electric System to the most limiting parameter. R14. Each Reliability Coordinator shall make known to Transmission Service Providers within its Reliability Coordinator Area, SOLs or IROLs within its wide-area view. The Transmission Service Providers shall respect these SOLs or IROLs in accordance with filed tariffs and regional Total Transfer Calculation and Available Transfer Calculation processes. 8 “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process With the exception of R14, which requires the TSP to take action, these are obligations for the RC. It must coordinate actions to ensure that GOPs and the TSP (and others), as required, are aware of, and that the RC takes actions to mitigate, potential and actual SOL or IROL in another area of the Interconnection8 (jurisdiction). Typically this is with respect to interconnections, between jurisdictions e.g. Québec - New York and the transfer capabilities of those ties lines for real time operations unless point to point transmission service is also. R13. require all entities to use the most limiting parameter if there is Note: version 2 of the standard is in effect now rather than the version 1 HQCMÉ submitted and is now only applicable to BAs, TOPs and TSPs to follow the direction of RC. This latest version eliminates duplications of requirements that exist in other standards. Non Bulk For RTA’s Installations, based on HQCMÉ studies, this is limited to the interconnection with HQT for local area SOL limits and “net” energy injections, per existing commercial agreements, which is the limit of HQCMÉ’s purview as the RC for RTA’s Installations with respect to managing facilities within their ratings. Responsibility to manage RTA’s other facilities, within their respective facility ratings lies within RTA’s purview. RTA’s explicit TSP reliability obligations under this standard for actions related to provision See NERC Glossary of terms; Interconnection means: When capitalized, any one of the three major electric system networks in North America: Eastern, Western, and ERCOT (also includes Québec now). #1732371 Page 7 Standards Included Title Applicable to RTA as: Requirements R17. When an IROL or SOL is exceeded, the Reliability Coordinator shall evaluate the local and wide-area impacts, both real-time and post-contingency, and determine if the actions being taken are appropriate and sufficient to return the system to within IROL in thirty minutes. If the actions being taken are not appropriate or sufficient, the Reliability Coordinator shall direct the Transmission Operator, Balancing Authority, Generator Operator, or Load-Serving Entity to return the system to within IROL or SOL. MOD-010-0 Steady-State Data for Transmission System Modeling and Simulation TO-3, GO-2 R1. The Transmission Owners and Generator Owners, (specified in the data requirements and reporting procedures of MOD-011-0_R1) shall provide appropriate equipment characteristics, system data, and existing and future Interchange Schedules in compliance with its respective Interconnection Regional steady-state modeling and simulation data requirements and reporting procedures as defined in Reliability Standard MOD-011-0_R 1. Brief description disagreement on limit values. The Measures of the standard with the exception of M14 and to some degree M12, all relate to the RC’s obligations to show it did what was required. The requirement of entities to follow the RC directives is covered elsewhere (see IRO-001, IRO-004 and TOP-001). This standard requires submissions of steady data for its facilities to the NERC and the RE (NPCC) typically via the RC. R2. The Transmission Owners and Generator Owners (specified in the data requirements and reporting procedures of MOD-011-0_R1) shall provide this steady-state modeling and simulation data to the Regional Reliability Organizations, NERC, and those entities specified within Reliability Standard MOD-011-0_R 1. If no schedule exists, then these entities shall provide the data on request (30 calendar days). MOD-012-0 Dynamics Data for Modeling and Simulation of the Interconnected Transmission System TO-3, GO-2 R1. The Transmission Owners, Transmission Planners, Generator Owners, and Resource Planners (specified in the data requirements and reporting procedures of MOD-013-0_R1) shall provide appropriate equipment characteristics and system data in compliance with the respective Interconnection-wide Regional dynamics system modeling and simulation data requirements and reporting procedures as defined in Reliability Standard MOD-013-0_R1. R2. The Transmission Owners, Transmission Planners, Generator Owners, and Resource Planners (specified in the data requirements and reporting procedures of MOD-013-0_R4) shall provide dynamics system modeling and simulation data to its Regional Reliability Organization(s), NERC, and those entities specified within the applicable #1732371 “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process of point to point transmission service to HQ loads or otherwise need to be clarified by HQCMÉ. Note: version 2 of the standard is in effect and should be applicable now not version 1 HQCMÉ has listed. Non Bulk The extent to which modeling data is required by HQCMÉ as the RC and HQT as the PC and TP to maintain its models current need to be established jointly and the standard applicability applied accordingly. Processes currently in place have met HQCMÉ’s and HQT’s requirements to-date. Those deemed for “Bulk” needs, will be managed accordingly under the proposed QCMEP. This standard requires submissions of Dynamic data for its facilities to the NERC and the RE (NPCC) typically via the RC. Non Bulk The extent to which modeling data is required by HQCMÉ as RC and HQT as the PC and TP to maintain its models current need to be established jointly and the standard applicability applied accordingly. Processes currently in place have met HQCMÉ’s and HQT’s requirements to-date. Those deemed for “Bulk” needs, will be managed Page 8 Standards Included Title Applicable to RTA as: Requirements Brief description reporting procedures identified in Reliability Standard MOD013-0_R 1. If no schedule exists, then these entities shall provide data on request (30 calendar days). PRC-001-1 System Protection Coordination GOP-2 R1. Each Transmission Operator, Balancing Authority, and Generator Operator shall be familiar with the purpose and limitations of protection system schemes applied in its area. R2. Each Generator Operator and Transmission Operator shall notify reliability entities of relay or equipment failures as follows: R2.1. If a protective relay or equipment failure reduces system reliability, the Generator Operator shall notify its Transmission Operator and Host Balancing Authority. The Generator Operator shall take corrective action as soon as possible. R3. A Generator Operator or Transmission Operator shall coordinate new protective systems and changes as follows. R3.1. Each Generator Operator shall coordinate all new protective systems and all protective system changes with its Transmission Operator and Host Balancing. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process accordingly under the proposed QCMEP. Each facility owner is required to be familiar with its facility protection systems and the implications when such protection systems fail for notifying the RC. Non Bulk See detailed Response 6.5. Further is required to coordinate applicable protection systems with its TOP. For RTA’s Installations this should at the interconnections with HQT. In a broader sense, RTA needs to ensure coordination internally with respect to its generation, loads and transmission elements for its own system reliability. R5. A Generator Operator or Transmission Operator shall coordinate changes in generation, transmission, load or operating conditions that could require changes in the protection systems of others: (Include sub-Requirement R5.1). PRC-004-1 Analysis and Mitigation of Transmission and Generation Protection System Mis-operations TO-3, GO-2 R1. The Transmission Owner and any Distribution Provider that owns a transmission Protection System shall each analyze its transmission Protection System Misoperations and shall develop and implement a Corrective Action Plan to avoid future Misoperations of a similar nature according to the Regional Reliability Organization’s procedures developed for Reliability Standard PRC-003 Requirement 1. R2. The Generator Owner and Transmission Owner shall analyze its generator Protection System Misoperations, and shall develop and implement a Corrective Action Plan to avoid future Misoperations of a similar nature according to the Regional Reliability Organization’s procedures developed for PRC-003 R1. Investigation and reporting protection misoperations. Non Bulk RTA has its own process and a committee to discuss these analysis with HQT and implement mitigating actions, as required, based on the findings to prevent reoccurrences. R3. The Transmission Owner, any Distribution Provider that owns a transmission Protection System, and the Generator Owner shall each provide to its Regional Reliability Organization, documentation of its Misoperations analyses and #1732371 Page 9 Standards Included Title Applicable to RTA as: Requirements Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Corrective Action Plans according to the Regional Reliability Organization’s procedures developed for PRC-003 R1. PRC-018-1 Disturbance Monitoring Equipment Installation and Data Reporting TO-3, GO-2 R1. Each Transmission Owner and Generator Owner required to install DMEs by its Regional Reliability Organization (reliability standard PRC-002 Requirements 1-3) shall have DMEs installed that meet the following requirements: R1.1. Internal Clocks in DME devices shall be synchronized to within 2 milliseconds or less of Universal Coordinated Time scale (UTC). R1.2. Recorded data from each Disturbance shall be retrievable for ten calendar days. R2. The Transmission Owner and Generator Owner shall each install DMEs in accordance with its Regional Reliability Organization’s installation requirements (reliability standard PRC-002 Requirements 1 through 3). R3. The Transmission Owner and Generator Owner shall each maintain, and report to its Regional Reliability Organization on request, the following data on the DMEs installed to meet that region’s installation requirements (reliability standard PRC-002 Requirements1.1, 2.1 and 3.1): Owners required to install DMEs by their Regional Reliability Organization (reliability standard PRC-002 Requirements 1-3) shall have DMEs installed that meet specific requirements: these need to be or should be at the interconnection with HQT and could be an obligation on either party. Entities may wish to have their own DME installations for their own purposes, which can be used during incident investigation, even where they are not required to meet the specific requirements of this standard. NA DME installations, if required by HQCMÉ, for local area incident reviews, need to be at the interconnections with HQT and owned by HQT. While RTA does have, for its own purposes, its own DME installations that can also be used to facilitate incident investigations, if required, they should not be required to meet the specific requirements of the standard. R4. The Transmission Owner and Generator Owner shall each provide Disturbance data (recorded by DMEs) in accordance with its Regional Reliability Organization’s requirements (reliability standard PRC-002 Requirement 4). R5. The Transmission Owner and Generator Owner shall each archive all data recorded by DMEs for Regional Reliability Organization-identified events for at least three years. R6. Each Transmission Owner and Generator Owner that is required by its Regional Reliability Organization to have DMEs shall have a maintenance and testing program for those DMEs that includes: R6.1 and R6.2. TOP-001-1 #1732371 Reliability Responsibilities and Authorities GOP-2 R3. Each TOP, BA, and Generator Operator shall comply with reliability directives issued by the Reliability Coordinator, and each Balancing Authority and Generator Operator shall comply with reliability directives issued by the Transmission Operator, unless such actions would violate safety, equipment, regulatory or statutory requirements. Under these circumstances the Transmission Operator, Balancing Authority or Generator Operator shall immediately inform the Reliability R3. Follow the “directives” of the RC and the TOP. R6. Help out to extent possible in case of an emergency. Non Bulk R7. Removal of RTA’s Installations from service should be limited to those that impact “net energy” exchanges with HQ above a set threshold or impact the commercial Page 10 Standards Included Title Applicable to RTA as: Requirements Coordinator or Transmission Operator of the inability to perform the directive so that the Reliability Coordinator or Transmission Operator can implement alternate remedial actions. R6. Each TOP, BA, and Generator Operator shall render all available emergency assistance to others as requested, provided that the requesting entity has implemented its comparable emergency procedures, unless such actions would violate safety, equipment, or regulatory or statutory requirements. Brief description R7. Not remove BES equipment from service if such removal will impact the BES. A GOP is required to notify the TOP if it does so. R7. Each TOP and Generator Operator shall not remove Bulk Electric System facilities from service if removing those facilities would burden neighbouring systems unless: “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process transaction in place and not on a unit basis, as well as those that impact SOLs and those for contingency limit planning. The specific RTA’s Installations are identified through the existing agreements. These again impact local area operations only (see worst case contingency in Response 6.7). R7.1. For a generator outage, the Generator Operator shall notify and coordinate with the Transmission Operator. The Transmission Operator shall notify the Reliability Coordinator and other affected Transmission Operators, and coordinate the impact of removing the Bulk Electric System facility. R7.3. When time does not permit such notifications and coordination, or when immediate action is required to prevent a hazard to the public, lengthy customer service interruption, or damage to facilities, the Generator Operator shall notify the Transmission Operator, and the Transmission Operator shall notify its Reliability Coordinator and adjacent Transmission Operators, at the earliest possible time. TOP-002-2 Normal Operations Planning TSP-3, GOP-2 R3. Each Generator Operator shall coordinate (where confidentiality agreements allow) its current-day, next-day, and seasonal operations with its Host Balancing Authority and Transmission Service Provider. Each Balancing Authority and Transmission Service Provider shall coordinate its current-day, next-day, and seasonal operations with its Transmission Operator. R12. The Transmission Service Provider shall include known SOLs or IROLs within its area and neighbouring areas in the determination of transfer capabilities, in accordance with filed tariffs and/or regional Total Transfer Capability and Available Transfer Capability calculation processes R13. At the request of the Balancing Authority or Transmission Operator, a Generator Operator shall perform generating real and reactive capability verification that shall #1732371 Coordinating generation operation with the BA and TSP through day ahead planning. Non Bulk with respect to the GOP function R3, R13, R14 and R15. The need for generator coordination, capability verifications and forecasting should be limited to the generators which are under the direct control of the RC and explicitly available to the BA for management of its load / generation balance, for the “area” within its purview. For a load customer with load displacement generation, such Page 11 Standards Included Title Applicable to RTA as: Requirements include, among other variables, weather, ambient air and water conditions, and fuel quality and quantity, and provide the results to the Balancing Authority or Transmission Operator operating personnel as requested. R14. Generator Operators shall, without any intentional time delay, notify their Balancing Authority and Transmission Operator of changes in capabilities and characteristics including but not limited to: R14.1. Changes in real output capabilities. (Effective August 1, 2007) R15. Generation Operators shall, at the request of the Balancing Authority or Transmission Operator, provide a forecast of expected real power output to assist in operations planning (e.g., a seven-day forecast of real output). R.18. Neighbouring Balancing Authorities, Transmission Operators, Generator Operators, Transmission Service Providers, and Load-Serving Entities shall use uniform line identifiers when referring to transmission facilities of an interconnected network. Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process as RTA, these requirements should be limited to the provision of forecasts for load requirements and the forecasts of excess “net” generation availability. While there is a need for load customers, including those with load displacement, to provide the BAs and TOPs with reasonable forecast of load requirements and changes to load needs, there is no need to validate each load displacement generation unit. R13. NA Should not apply to load displacement generators, as they serve their own loads only. R18. NA for the GOP The TSP requirements are also Non Bulk for interconnections with HQT or the transmission service RTA provides to service HQ’s Load. #1732371 Page 12 Standards Included TOP-003-0 (1a) Title Planned Outage Coordination Applicable to RTA as: GOP-2 Requirements Brief description R1. Generator Operators and Transmission Operators shall provide planned outage information. R1. Plan outages that impact the BES. R1.1. Each Generator Operator shall provide outage information daily to its Transmission Operator for scheduled generator outages planned for the next day (any foreseen outage of a generator greater than 50 MW). The Transmission Operator shall establish the outage reporting requirements. R.1.1. Notify TOP if “net”generation output deviates more than 50 MV from planned production. R1.3. Such information shall be available by 1200 Central Standard Time for the Eastern Interconnection and 1200 Pacific Standard Time for the Western Interconnection. R2. Each TOP, BA, and Generator Operator shall plan and coordinate scheduled outages of system voltage regulating equipment, such as automatic voltage regulators on generators, supplementary excitation control, synchronous condensers, shunt and series capacitors, reactors, etc., among affected Balancing Authorities and Transmission Operators as required. R3. Each TOP, BA, and Generator Operator shall plan and coordinate scheduled outages of telemetering and control equipment and associated communication channels between the affected areas. R2. Plan with and notify TOP if AVR9 or stabiliser equipments are to be removed from service. R3. Plan with and notify TOP if telemetering or control equipment that affects the BES is to be removed from service. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Non Bulk R1. Should be applicable from a “net energy” availability perspective only (see comments for TOP-002 above). RTA transmission line outages between the stations only need to be identified for HQT/HQCMÉ local area security analysis. R2. Applicable as Non Bulk and from the “net” reactive power (VAR) capability perspective to meet RTA’s own VAR requirements and to maintain voltage limits at unity power factor at the interconnections with HQT. It should not be viewed from the individual generation unit AVR outage coordination perspective. Provision of reactive support over and above these requirements should be through commercial arrangements. Bulk. With respect to stabilizer outage reporting, only if stabilizer “in-service” statuses affect HQT’s / HQCMÉ’s established IROLs. Otherwise, “Non Bulk” if only affects SOLs; would be determined through discussions with HQCMÉ. R3. Would continue to apply for local area requirements per current outage reporting practices. #1732371 Page 13 Standards Included TOP-006 Title Monitoring System Conditions Applicable to RTA as: GOP-2 Requirements R1.1. Each Generator Operator shall inform its Host Balancing Authority and the Transmission Operator of all generation resources available for use. Brief description Required for BA to conduct appropriate resource adequacy analysis and be aware when resources designated to meet the BA’s area load requirements become unavailable and enables the TOP to conduct security analysis for SOL. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process NA from a generating unit specific perspective. Bulk from a “net” energy availability forecast perspective per existing agreements for HQCMÉ resource adequacy and security (reliability) analysis. The need to inform the host BA (HQCMÉ) and the TOP (HQT) of generator availability should be limited to those generators that are under the direct control of the RC and TOP and explicitly available to the BA for purposes of management of load/generation balance, for the “area” within its purview (Québec Load), if used for that purpose and for local area security analysis. For a load customer with load displacement generation, such as RTA, this requirement should be limited to the provision of forecasts of excess “net” generation availability per its commercial agreements with HQP and used for the purposes of HQCMÉ’s reliability analysis. VAR-002-1a Generator Operation for Maintaining Network Voltage Schedules GOP-2, GO-2 R1. The Generator Operator shall operate each generator connected to the interconnected transmission system in the automatic voltage control mode (automatic voltage regulator in service and controlling voltage) unless the Generator Operator has notified the Transmission Operator. (Sub- Requirements R2.1 and R2.2) R2. Unless exempted by the Transmission Operator, each Generator Operator shall maintain the generator voltage or Reactive Power output (within applicable Facility Ratings10) as #1732371 GOP must operate each generator connected to the interconnected transmission system in the automatic voltage control mode (automatic voltage regulator in service and controlling voltage) unless the Generator GOP has notified the TOP otherwise. Non Bulk In the absence of commercial arrangements to do otherwise , applicability of this standard should be limited to assuring the availability of sufficient reactive power (VAR) to meet RTA’s own requirements and assure HQT interconnection Page 14 Standards Included Title Applicable to RTA as: Requirements directed by the Transmission Operator. R3. Each Generator Operator shall notify its associated Transmission Operator as soon as practical, but within 30 minutes of any of the following: (Sub- Requirements R3.1 and R3.2) R4. The Generator Owner shall provide the following to its associated Transmission Operator and Transmission Planner within 30 calendar days of a request. (Sub- Requirements R4.1) Brief description “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process voltage limits, which have local area reliability implications, within the objective of maintaining unity power factor, in accordance with existing agreements with HQT though not within the standards prescribed AVR control mode11 on a unit by unit basis. R5. After consultation with the Transmission Operator regarding necessary step-up transformer tap changes, the Generator Owner shall ensure that transformer tap positions are changed according to the specifications provided by the Transmission Operator, unless such action would violate safety, an equipment rating, a regulatory requirement, or a statutory requirement. ( Sub- Requirements R5.1) #1732371 Page 15 A number of standards were excluded in HQCMÉ’s application. Of the standards excluded, PRC-005 is required for local area reliability. PRC-015, PRC-016 and PRC-017 do not apply since there is no special protection scheme (SPS) in place. Otherwise, they would be required for local area reliability, unless designated as a class 1 SPS, in which case it becomes a “Bulk” system requirement. Another standard that was not included by HQCMÉ is the Cyber Standard, which requires internal assessment by HQCMÉ. Standard not Included PRC-005 Title Transmission and Generation Protection System Maintenance and Testing Applicable to RTA as: GO-2 TO-3 Requirements R1. System and each Generator Owner that owns a generation Protection System shall have a Protection System maintenance and testing program for Protection Systems that affect the reliability of the BES. The program shall include: R1.1. Maintenance and testing intervals and their basis. R1.2. Summary of maintenance and testing procedures. Brief description Protection system maintenance programs in place. “Bulk”, “Non Bulk” or NA (not applicable) in the context of the proposed two-tier approach process Non Bulk There is no U/F relays in place on the generators and transmission classed as “Non Bulk”. Required for local area reliability only and ensures incidents only remove facilities required to clear the fault. R2. Each Transmission Owner and any Distribution Provider that owns a transmission Protection System and each Generator Owner that owns a generation Protection System shall provide documentation of its Protection System maintenance and testing program and the implementation of that program to its Regional Reliability Organization on request (within 30 calendar days). The documentation of the program implementation shall include: R2.1. Evidence Protection System devices were maintained and tested within the defined intervals. R2.2. Date each Protection System device was last tested/maintained. #1732371 Page 16