Hydro- Québec Distribution R-3677-2008 Application MECHANISM FOR THE RECOVERY OF OPERATING COSTS ASSOCIATED WITH MAJOR OUTAGES Original : 2008-08-01 HQD-4, Document 4 Page 1 of 19 Hydro- Québec Distribution Original : 2008-08-01 R-3677-2008 Application HQD-4, Document 4 Page 2 of 19 Hydro- Québec Distribution R-3677-2008 Application TABLE OF CONTENTS 1. CONTEXT.........................................................................................................5 2. STEPS TAKEN BY THE DISTRIBUTOR ........................................................7 2. STEPS TAKEN BY THE DISTRIBUTOR ........................................................7 2.1 COMPARABLE SITUATIONS IN THE INDUSTRY....................................................8 2.1.1 Canadian Industry.................................................................................8 - B.C. Hydro ...................................................................................................8 - Ontario.........................................................................................................9 2.1.2 American Industry .................................................................................9 2.2 THE DISTRIBUTOR’S TREATMENT OF MAJOR OUTAGES ..................................10 2.2.1 Definition of Major Outage ..................................................................10 2.2.2 Accounting for Costs Associated with Major Outages ........................11 3. RECOVERY MECHANISMS ANALYSED......................................................12 3.1 AMOUNTS BUDGETED IN THE AFFECTED COST CATEGORIES ...........................12 3.2 PROVISION ..................................................................................................13 3.3 DEFERRAL ACCOUNT ...................................................................................13 4. SELECTING A MECHANISM – THE DISTRIBUTOR’S PROPOSAL............14 4.1 PROVISION FOR MAJOR OUTAGES ................................................................14 4.2 MECHANISM FOR EXCEPTIONAL COSTS .........................................................16 4.3 DEMONSTRATING THE “HYBRID” APPROACH PROPOSED BY THE DISTRIBUTOR 17 5. REQUEST FOR A REGULATORY PRINCIPLE ............................................18 Original : 2008-08-01 HQD-4, Document 4 Page 3 of 19 Original : 2006-07-06 HQT-12, Document 1 Page 4 of 19 Hydro- Québec Distribution R-3677-2008 Application 1. CONTEXT In the budgetary process to set its rates, the Distributor has included, to this day, a separate amount in its revenue requirement for a set of provisions as a whole that were aimed at guarding against operating cost variances. These annual provisions have generally but not specifically sought to account for uncertainties related to activities or events like taking charge of a new distribution network, new human resource plans (e.g. contingency plans for retirements), the bankruptcy of Large Power customers and major outages. In fact, the occurrence of major outages, for which no amount was specifically budgeted in revenue requirements given the sporadic nature and variable degree of such events, also fell within the perimeter of these provisions. In decisions D-2005-34 and D-2006-34, the Régie recognized the need for such provisions to ensure that the Distributor was able to guard against multiple variances that can occur throughout the year.1 According to the Régie, this practice was consistent with prudent budgetary management. Over the period 2005 to 2008, the provisions for operating cost variances totalled amounts that ranged between $5.6 million and $8.6 million. During the hearings held during the months of December 2006 and 2007 respectively, the Distributor highlighted the importance of including major outages in operating cost variances for 2006 and 2007.2 In decision D-2007-12, the Régie questioned the appropriateness of setting such provisions, generic in nature, on the basis of specific events. Moreover, in the same hearings held in December 2006 and 2007, the Régie expressed its concerns regarding the follow-up on the use of these provisions. In actual fact, and as the Distributor mentioned in the evidence for each of the rate applications, the costs associated with operating cost variances were directly 1 D-2005-34, R-3541-2004, page 74 and D-2006-34, R-3579-2005, page 44. R-3610-2006, transcriptions for December 1, 2006, pages 269 to 275. R-3644-2007, transcriptions for December 5, 2007, pages 189 and 190. 2 Original : 2008-08-01 HQD-4, Document 4 Page 5 of 19 Hydro- Québec Distribution R-3677-2008 Application recorded, depending on their nature, in the different cost categories identified, based on their nature. There is no denying the difficulty the Distributor encountered to provide precise budgetary reports that make it possible to establish a link between forecasts and actual costs. The Distributor nonetheless stated that it was able to produce a follow-up based on the actual occurrence of elements or events covered by the provisions. With that aim, the Distributor pointed to major outages as key elements that justified the use of provisions in 2005 and 2006.3 The Distributor also noted, by this very fact, that the other elements or events had not significantly required the financial resources that had been set aside for them. In decision D-2008-024, the Régie formally ordered the Distributor to provide details on the actual use of the provision for operating cost variances in its annual report. In addition, in its 2007 annual report the Distributor stated that it intended, in the course of 2008, to find a solution to its incapacity to provide the required follow-up regarding the use of these provisions. With that aim, the proposal outlined in section 4 of this document makes it possible to comply with the Régie’s order. 3 R-3610-2006, HQD-19, document 11, response to Undertaking #11. R-3644-2007, transcriptions for December 5, 2007, page 190. Original : 2008-08-01 HQD-4, Document 4 Page 6 of 19 Hydro- Québec Distribution R-3677-2008 Application 2. STEPS TAKEN BY THE DISTRIBUTOR Considering: The variable frequency and degree of climate events that have lead to outages on the system over the past few years; The Distributor’s exposure to the monetary impacts associated with major outages; The absence of a specific budget for anticipated costs caused by major outages; The doubt expressed by the Régie regarding the validity of setting provisions, generic in nature, related to operating cost variances which are, in actual fact, based on specific events; That the importance of variances associated with certain elements covered by the provisions is lesser than expected;4 The reporting requirements regarding the use of provisions, the Distributor has taken steps to reposition its needs in terms of the budgetary provisions that are integrated in the revenue requirement in order to face these variances. These steps have led the Distributor to give priority to the recovery of costs associated with the re-establishment of service on the system as a result of a major outage. To do so, the Distributor began by looking into existing practices in the industry. 4 R-3610-2006, HQD-19, Document 11, response to Undertaking #11. Original : 2008-08-01 HQD-4, Document 4 Page 7 of 19 Hydro- Québec Distribution R-3677-2008 Application 2.1 COMPARABLE SITUATIONS IN THE INDUSTRY 2.1.1 Canadian Industry - B.C. Hydro On July 6, 2007, BC Hydro received the approval of the British Columbia Utilities Commission (BCUC) to create an account for regulatory assets to recover costs exceeding $30 million associated with restoration work that took place following major storms between October 2006 and January 2007. In that account, the costs of major outages are associated with major weather events that are characterised by one or several of the following criteria: More than 100 000 customers are affected at once; A large geographic area, if not the entire province, is affected; A period to re-establish service that exceeds two days or the need to resort to resources that are external to the affected region; The costs of re-establishing supply to customers exceed $1 million. The terms for cost-recovery associated with this account were proposed by BC Hydro in its 2009/2010 rate application and are currently being examined by the BCUC.5 5 See chapter 6 on page 13 of BC Hydro’s rate application at the following address: http://www.bchydro.com/rx_files/info/info55162.pdf Original : 2008-08-01 HQD-4, Document 4 Page 8 of 19 Hydro- Québec Distribution R-3677-2008 Application - Ontario On July 31 2007, four distributors in Ontario (Canadian Niagara Power Inc.-Fort Erie, Canadian Niagara Power Inc.-Port Colborne, Peterborough Distribution Inc. and Lakeland Power Distribution Ltd.) obtained authorisation from the Ontario Energy Board to recover costs incurred to repair damages caused by major storms. The costs incurred were respectively $1.7 million, $0.3 million, $0.4 million and $0.2 million. The criteria used to define major weather events are: Costs must be directly related to the event and must be incremental to the costs used for the establishment of rates. The materiality of costs. In other words, expenses must total at least 0.2% of total distribution expenses before taxes and investments must represent at least 0.2% of net fixed assets. The reasonabless of the amounts claimed relative to other options for the re-establishment of service, with the aim of efficiency. The requests of these distributors were carried out within the framework of incentive regulation. Cost-recovery will take place via the implementation of a rider applied over a 12 month period (24 months in the case of Fort Erie). 2.1.2 American Industry In the midst of natural disasters that have afflicted the United States, several companies have requested the recovery of costs generated by major storms. Different cost recovery mechanisms as regards provisions for outages and deferral accounts were authorized and put in place depending on each of their needs. A survey conducted by Edison lists the mechanisms applied by different companies. The results of the survey can be accessed on the Internet at the following address: Original : 2008-08-01 HQD-4, Document 4 Page 9 of 19 Hydro- Québec Distribution R-3677-2008 Application http://www.eei.org/industry_issues/reliability/nonav_reliability/Utility_Restoration_ Cost_Recovery.pdf 2.2 THE DISTRIBUTOR’S TREATMENT OF MAJOR OUTAGES As a second step, the Distributor examined its treatment of major outages, in terms of identification and accounting, so that it could then develop a mechanism for the recovery of related costs. 2.2.1 Definition of Major Outage To identify the days in which major events occurred, the Distributor bases itself on its normalization methodology for the continuity of service index (CI).6 This statistical methodology makes it possible to set a threshold based on gross daily continuity indexes (CI) for the overall medium voltage network of the five preceding years (excluding catastrophic events such as the 1998 ice storm). This threshold, set at 2.5 typical logarithmic variances (2,5,ß), is based on observations made by several companies that have joined the IEEE (Institute of Electrical and Electronics Engineers, Inc.). Beyond this level distributors resort to more major means for the re-establishment of service. When the service interruptions within a day exceed the 2,5,ß threshold they are considered major whereas interruptions below the 2,5,ß threshold are considered normal and are included in the normalized CI. 6 See R-3677-2008, HQD-03, Document 1, Appendix D, page 49. Original : 2008-08-01 HQD-4, Document 4 Page 10 of 19 Hydro- Québec Distribution R-3677-2008 Application 2.2.2 Accounting for Costs Associated with Major Outages A major outage on the system triggers an emergency plan for the reestablishment of service, thereby activating a management process of human and financial resources. Two different cost centers (internal orders) are then created so as to assign, respectively, the charges and investments pertaining to the re-establishment of service. As previously mentioned, the revenue requirements for given test years did not include any specific amount to cover the eventual costs of major outages. Also, cost recovery remains uncertain because its only vehicle is the provision for operating cost variances, which is shared with other variances and which amounts do not necessarily reflect the cost of these outages. The portion of these costs that is associated with required investments is less problematic. In fact, the investments incurred are included in the rate base once the corresponding assets are put into use. They will therefore be included in rates because the actual rate base is used as a starting point to establish the projected rate base of a subsequent test year, and they will be integrated into the revenue requirement via depreciation costs. Also, the Distributor reduces the scope of its approach to cost recovery for major outages in the operating costs component. To this effect, some mechanisms were considered. These are presented in the following section Original : 2008-08-01 HQD-4, Document 4 Page 11 of 19 Hydro- Québec Distribution R-3677-2008 Application 3. RECOVERY MECHANISMS ANALYSED 3.1 AMOUNTS BUDGETED IN THE AFFECTED COST CATEGORIES For this option, the different cost line-items of which the revenue requirement is comprised are forecast by including estimated costs that will eventually result from major outages. This process thereby consists of integrating the amounts associated with major outages in the normal budgetary process. Under this option, the cost recovery associated with outages is limited to the amounts budgeted based on the nature of the costs and it can lead to overearnings or shortfalls. During exceptional years, shortfalls can be significant. This option also ascribes to intergenerational equity and it has the advantage of allocating the costs to customers that benefit from the services up to the budgeted amounts while minimizing the financial costs that would be associated with cost deferral. Nonetheless, the Distributor rejects this option for the following reasons: The difficulty of forecasting costs associated with major outages; Spreading out the forecast costs of outages in different line-items (working benefits, labour expenditures, bonuses, contractors’ fees, fees for services rendered by public utilities) makes it impossible to include the total budget associated with major outages as a separate item in the revenue requirement. In actual fact, a cost center gathers all of the costs associated with these outages. Therefore, the Distributor considers it preferable to integrate in the regulatory framework the overall costs associated with major outages as a separate item taken as a whole. Original : 2008-08-01 HQD-4, Document 4 Page 12 of 19 Hydro- Québec Distribution R-3677-2008 Application 3.2 PROVISION As an option that follows a similar principle to the previous one, the provision for major outages would consist of including a separate line-item in the revenue requirement in which the overall budgeted costs for major outages are assigned. This option would facilitate a better match between the forecast and actual costs in a separate cost center (see paragraph 2.2.2). As with the previous option, a provision for major outages makes it possible to allocate the costs to customers that benefit from the services, up to the budgeted amounts, while minimizing the financial costs associated to the delay between the time the costs are incurred to the time those costs are recovered through rates. However, this mechanism has the same disadvantages as the preceding option, which are the risks of overearnings or shortfalls in cost recovery and the difficulty of forecasting costs given that major outages remain very variable in frequency and degree over time. 3.3 DEFERRAL ACCOUNT A deferral account makes it possible to recover the costs incurred a posteriori. Under this option, the actual costs associated with the restoration of the system following a major outage are accumulated in an account so that they may subsequently be recovered through rates. This option is removed from the budgetary process and from the principle of a revenue requirement that is based on projected costs. However, this departure is justified by the variable frequency and degree of outages. Moreover, the deferral Original : 2008-08-01 HQD-4, Document 4 Page 13 of 19 Hydro- Québec Distribution R-3677-2008 Application account has the advantage recovering all but no more than the actual costs incurred and it facilitates the task of budgetary follow-up. Nonetheless, the deferral account option does not respect the principle of intergenerational equity and it generates financial costs associated with cost deferral. These costs remain subject to the terms that are agreed upon. 4. SELECTING A MECHANISM – THE DISTRIBUTOR’S PROPOSAL Following the analysis of the three options, which were examined by considering the advantages and disadvantages in a regulatory context, and given the context described in section 1 of this document, the Distributor proposes a “hybrid” approach that links two regulatory mechanisms in order to recover the operating costs associated with major outages. Therefore it proposes, first, to replace the provisions for operating cost variances with a provision reserved for major outages. Moreover, because the frequency of major outages can be very variable as can be the degree of resulting damages, costs generated in this way can reach exceptional proportions. As a complementary measure, the Distributor also proposes the creation of a deferral account which would make it possible to recover costs that are considered exceptional. The following paragraphs explain the Distributor’s dual proposal in greater detail. 4.1 PROVISION FOR MAJOR OUTAGES Considering the variable frequency and degree of major outages, the Distributor considers it relevant to apply an objective method to set the amount of its provision for major outages that differs from an approach based on a percentage of operating costs. To support this argument, in decision D-2007-12, the Régie disapproved of that approach in these terms: “the threshold of 1.5% of operating Original : 2008-08-01 HQD-4, Document 4 Page 14 of 19 Hydro- Québec Distribution R-3677-2008 Application costs used to limit the amount of provisions is based more on an empirical approach than on a systematic evaluation”.7 The Distributor proposes instead to establish the amount of the provision for major outages on the basis of actual average costs incurred in previous historic years. This method has the following advantages: It minimizes the risk of overearnings or shortfalls over a period of a few years since it is based on an average of actual costs; It consists of an objective method; It makes it possible to avoid significant annual fluctuations of the provision since it is based on an average. Table 1 below shows the annual costs that resulted from major outages over the period 2001-2007. Table 1 Historic Costs Resulting from Major Outages Charges ($M) Days of major events 2001 10.8 2002 5.6 2003 4.8 2004 1.2 2005 7.6 2006 34.1 2007 9.6 9 9 7 3 8 17 7 Reference 7.7 8 1 Average data between 2001 and 2007 excluding 2004 and 2006, which were exceptional years, the first of them due to the low number of major outages, the other due to its high number. By excluding 2004 and 2006, so as to establish an average that is more representative of the annual costs incurred over this period, the average over the period examined is almost $8 million. Therefore, the Distributor proposes to maintain a yearly provision of $8 million for major outages, which could be revised as required. 7 D-2007-12, R-3610-2006, page 45. Original : 2008-08-01 HQD-4, Document 4 Page 15 of 19 1 Hydro- Québec Distribution R-3677-2008 Application This method, which is based on a cost average, makes it possible to anticipate that, statistically, over a sufficiently long period of time, the Distributor will recover its costs without overearnings or shortfalls. 4.2 MECHANISM FOR EXCEPTIONAL COSTS When the extreme values over the period 2001-2007 are considered, it becomes evident that costs can at times reach exceptional proportions. The costs incurred as a result of major outages in 2006 are a good example of this reality. In a case such as that one, the provision would be insufficient to recover the costs associated with the re-establishment of service on the system following a major outage. In fact, the methodology used to set a provision that is based on an average, as described above, shows that a provision set at $8 million would lead to a statistic variation in costs that ranges between 0 and $16 million, as a normal rule. Above that threshold, in principle, the costs would not be recovered. It is for this reason that the Distributor proposes a mechanism that is complementary to the provision, which seeks to recover the portion of the costs associated with major outages that are considered exceptional, given their magnitude. To this effect, the Distributor proposes to set a threshold of $16 million beyond which the costs associated to major outages would be included in a deferral account so that they may subsequently be recovered through rates. Eventually, the cost recovery mechanism that is complementary to the provision could be based on a technical characterization criterion associated to major outages. The Distributor is pursuing its analyses to this effect. The costs included in the deferral account would bear interest at the weighted average cost of capital until they are recovered through rates. The terms to dispose of the deferral account remain to be determined. Moreover, these could be determined on a case by case basis, based on the level of the deferred charges. Original : 2008-08-01 HQD-4, Document 4 Page 16 of 19 Hydro- Québec Distribution R-3677-2008 Application 4.3 DEMONSTRATING THE “HYBRID” APPROACH PROPOSED BY THE DISTRIBUTOR Table 2 provides an example which seeks to show the complete cost recovery based on different levels of costs, applying a provision set at $8 million and a threshold of $16 million beyond which costs would be included in a deferral account for major outages. The Provision component is recovered in the projected test year while the Deferral Account component would be integrated in rates according to the terms that will be determined. Table 2 Example of Cost-Recovery Based on Level of Costs incurred Recovery Cost of outages $0 M $3 M $8 M $12 M $16 M $17 M $20 M $35 M Provision Deferral Account Total Recovery Overearnings Shortfall $8 M $8 M $8 M $8 M $8 M $8 M $8 M $8 M $0 M $0 M $0 M $0 M $0 M $1 M $4 M $19 M $8 M $8 M $8 M $8 M $8 M $9 M $12 M $27 M $8 M $5 M - $4 M $8 M $8 M $8 M $8 M This example shows that, as soon as costs for a given year exceed the level of the provision, the Distributor is subject to shortfalls which are limited by the level of the provision. Conversely, a cost level that is below the threshold for the provision generates surpluses that are capped to the amount of the provision. The Distributor’s proposal generates a symmetrical risk of overearnings and shortfalls by which the limit for overearnings is equal to the limit for shortfalls. Table 3 illustrates the cost recovery that would have taken place under the new proposal on the basis of historical data from 2001 to 2007. Original : 2008-08-01 HQD-4, Document 4 Page 17 of 19 Hydro- Québec Distribution R-3677-2008 Application Table 3 Demonstration of the Cost-Recovery Based on 2001 to 2007 Data ($M) Recovery Years 2001 2002 2003 2004 2005 2006 2007 Total (7 years) Cost of major outages Provision 10.8 5.6 4.8 1.2 7.6 34.1 9.6 73.7 8.0 8.0 8.0 8.0 8.0 8.0 8.0 56.0 Impact DCA(threshold $16M) 0 0 0 0 0 18.1 0 18.1 Total 8.0 8.0 8.0 8.0 8.0 26.1 8.0 74.1 Overearnings 2.4 3.2 6.8 0.4 - shortfall 2.8 8.0 1.6 +0.4 This last example shows the neutrality of the hybrid approach proposed by the Distributor over a relatively long period of time. Therefore, over the seven year period examined, that is to say between 2001 and 2007, the overearnings and shortfalls tend to cancel each other out so as to result in a consolidated overall impact of $0.4 million in overearnings. 5. REQUEST FOR A REGULATORY PRINCIPLE Considering the preceding proposals and their supporting arguments, the Distributor asks the Régie to recognize the principle for the recovery of costs associated with major outages in compliance with the following joint mechanisms: Creation of a provision for major outages for an amount of $8 million, which is set on the basis of the average historical average between 2001 and 2007, excluding the two extreme values. This provision replaces the provision for operating cost variances which, as a result, is not renewed. Creation of a deferral account to record the costs associated with major outages that exceed a threshold of $16 million. The terms associated to this deferral account will be determined based on the level of the costs Original : 2008-08-01 HQD-4, Document 4 Page 18 of 19 Hydro- Québec Distribution R-3677-2008 Application incurred. This account will bear interest at the average weighted cost of capital. The Distributor considers this an optimal proposal because it allows for a fair trade-off between different principles. It thereby favours the principle of intergenerational equity and the smoothing out of costs while limiting the risks of overearnings or shortfalls and minimizing financial costs. As per the Régie’s request, The Distributor will provide a yearly account of the provision for major outages in its annual report. Original : 2008-08-01 HQD-4, Document 4 Page 19 of 19