B-8 GAZ MÉTRO RESPONSE TO IR NO. 1 FROM ACIG/IGUA (Gas Métro -1 documents 1.13 - 13.6 Gax Métro -2 document 1.1-1.2) (English translation) Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Connection Model Reference: (i) Gaz Métro 1, document 1, p.11, Graph 1 Preamble: In graph 1, Gaz Métro indicates that the TCPL/TQM [TransCanada PipeLines Limited/ Trans Québec & Maritimes Pipelines Inc.] network can be used for the transmission of natural gas between the consumption areas. Question: 1.1 Do the existing installations of the distribution network allow routing the gas from the consumption areas to the TQM network? If negative, how does Gaz Métro intend to recover the costs related to such investments, if applicable? Answer: Generally, Gaz Métro’s consumption areas are connected to TQM and therefore route the excess gas to TQM. Each situation is different, therefore it is not possible to generalize whether or not specific installations are required in order to route the natural gas to the TQM network. However, as mentioned in the response to request for information 11.1 of the Régie Gaz Métro-1, Document 1.11), if investments were necessary to improve Gaz Métro’s network in order to route natural gas from the consumption areas to the TQM network, producers would be entirely responsible for the charges. Question: 1.2 Do the existing TQM installations allow to reverse the flowing direction of the gas on certain segments (i.e. between the adjacent consumption areas) as a temporary measure (e.g. flow towards east during winter and west during summer)? Answer: Yes. Up to certain volume limits that should be indicated by TQM. Original: 2010.09.14 Gaz Métro – 1, Document 1.13 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Category “A” Costs References: (i) (ii) Gaz Métro 1, Document 1, page 14, Line 15 Gaz Métro 1, Document 1, page 15, Line 11 Preamble: At point (i), Gaz Métro specifies: “Moreover, if new investments in the existing distribution network (i.e. downstream the interconnection point) are required only for the need of the producers, the costs related to these investments will be borne by the producers.” At point (ii), Gaz Métro states: “This agreement will describe the circumstances and the conditions leading to the reimbursement of incurred costs.” Question: 2.1 Please describe the nature and the scope of the investments which may be necessary downstream from the interconnection point. Answer: Investments would be mainly for compression and possibly an increase in capacity. The scope of these investments is unknown for the moment and will depend mainly on the volume injected into the gas network. Question: 2.2 What are, according to Gaz Métro, the circumstances that should not lead to the reimbursement of the incurred expenses? Original: 2010.09.14 Gaz Métro – 1, Document 1.14 Page 1 of 2 Answer: There are no circumstances that should not lead to reimbursement of incurred charges. Use of the conditional has no other goal than to refer to a situation that has not yet occurred. At reference (i), the sentence could therefore read: “In addition, when new investments [...] are required for only the needs of producers, producers will also be responsible for the costs related to these investments.” At reference (ii), the sentence could read: “This agreement will describe the circumstances and conditions which lead to a reimbursement of incurred costs.” Original: 2010.09.14 Gaz Métro – 1, Document 1.14 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Category “B” Costs References: (i) Gaz Métro 1, Document 1, page 15, Line 27 Preamble: At point (i), Gaz Métro specifies: “There is a distinction made within the same gas network, that is the distribution network and the transmission network of Gaz Métro.” Question: 3.1 Please indicate whether Gaz Métro has already established a distinction between the transmission and distribution functions of the distribution network and provide appropriate references. Answer: Currently there is a distinction between the functionalities of the various pipelines in the service cost allocation study (R-3720-2010, Gaz Métro-13, Document 14, Page 5, Factor “CONPRIN”). The allocation of carrier pipelines (which in fact includes the allocation of carrier and supply pipelines) is done for the capacity component only, whereas the allocation of distribution pipelines is done for the access and capacity components. 3.2 Please draw the lists including the types of pipeline according to their level of pressure and indicate which of them are associated with the transmission function. For each of these types of pipelines please indicate the number of existing clients who are connected to them and the tariff class they belong to. Answer: See answer to question 5.1 of the Régie in the document Gaz Métro-1, Document 1.5 for the type of pipeline. [See table in corresponding .pdf file] Original: 2010.09.14 Gaz Métro – 1, Document 1.15 Page 1 of 2 3.3 Please indicate whether there are clients who are served by high-pressure pipelines; if affirmative, how many. Answer: Yes, see answer to question 3.2. 3.4 Please indicate whether the gas transmission in the distribution network requires compression. If affirmative, Please indicate whether it is provided that a part of these costs are allocated to producers. Answer: Routing natural gas through the distribution network generally does not require compression. The only compression in operation today is found in Saint-Maurice, at the junction between Gaz Métro’s network and TQM’s network. The gas is compressed upon exiting TQM’s network and routed to Saguenay, and upon exiting the LSR plant for injection into the network. However, if there were compression costs to disperse the natural gas injected by producers from the connection network to the existing network (compression at interconnection points), these costs would be charged to producers and priced at receiving points. Original: 2010.09.14 Gaz Métro – 1, Document 1.15 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Category “D” Costs References: (i) Gaz Métro 1, Document 1, page 17, Line 16 Preamble: At point (i), Gaz Métro specifies: “…if the additional costs for the use of the network were incurred, these costs would be paid by the producers.” Question: 4.1 Please identify exhaustively the situations where the additional costs for the use of the TCPL/TQM network will be incurred. Answer: Each time the gas must be routed via TCPL/TQM’s carrier network, costs will be incurred because Gaz Métro must contract carrier services from carrier companies. Besides the additional costs for using TCPL/TQM’s network, Gaz Métro could also incur costs for modifying their network, such as modifications to measuring and ranging equipment at receiving points, etc. At this time, Gaz Métro does not believe that it is possible to exhaustively identify the occurrence of additional costs for using TCPL/TQM’s network. When an investment is required, Gaz Métro will analyze the reasons for this investment and will allocate this cost to the type of client involved. Question: 4.2 For each of the situations identified above, Please indicate whether there are contract obligations binding Gaz Métro to TCPL/TQM or any other obligations not allowing Gaz Métro to substitute the gas from outside the franchise with the gas from the reception point without generating additional expenses for TCPL/TQM. Original: 2010.09.14 Gaz Métro – 1, Document 1.16 Page 1 of 2 Answer: The contract held by Gaz Métro with TQM refers specifically to the transportation of gas from storage sites located in Quebec and include two specific receiving points. The transportation contracts held by Gaz Métro with TCPL refer to the transportation of gas between Empress, Dawn or Parkway in accordance with the contract and the delivery points located in Gaz Métro’s territory. These contracts strongly do not allow the receiving of gas at other delivery points. TCPL’s pricing does not allow Gaz Métro to segment these transportation contracts to transport gas over different segments within the same contract. Gaz Métro can therefore not transport natural gas from one consumption area to another without incurring costs. However, Gaz Métro is free to change its existing portfolio with TCPL in order to supply itself with locally produced natural gas instead of natural gas from the West. Gaz Métro would, however, have to end its transportation contracts originating from the West and enter into new transportation contracts that allow them to route natural gas from one consumption area to another. The applicable rates for the various contracted services will be different due to less distance travelled. Original: 2010.09.14 Gaz Métro – 1, Document 1.16 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Receiving Point Pricing References: (i) Gaz Métro 1, Document 1, page 21, Line 16 Preamble: At point (i), Gaz Métro specifies: “A progressive increase of the [CMC] is allowed in the 16 cases of progressive start-up of certain production sites.” Question: 5.1 Please indicate whether the application of a progressive CMC will affect the level of the tariff, the recovery profile of costs in time and the yield of the project. Answer: Receiving point pricing is established in order to recover costs over the amortization period of investments. The rates established at receiving points will vary depending on the characteristics specific to each project and each proposal must be reviewed by the Régie when investments are required. The possibility of a progressive CMC form a part of the characteristics specific to the project. In order to not create cross-subsidization between producers, the progressivity of the CMC will be taken into account in the establishment of receiving point rates. The profitability of the project will not be affected as Gaz Métro will always target an IRR equal to the cost of weighted capital and as a result, a rate break-even point equal to the amortization period. The rate level will be slightly higher than if the CMC had not been progressively established in order to make up for the lack of revenue vs. service costs that do not change. Lastly, the cost recovery profile will also be slightly affected. Indeed, rate revenues for years where the CMC is progressing will be lower than the rate revenues if the rate was fixed with a continuous CMC. However, for the entire amortization period, the rate revenue is strictly equal to the service cost in the two cases. Original: 2010.09.14 Gaz Métro – 1, Document 1.17 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) (i) Gaz Métro 1, Document 1, Page 27 Gaz Métro 1, Document 1, Page 29, Table 2 Preamble: At point (i), Gaz Métro draws the following list of exploitation expenses related to the supply of the producers: “Administration expenses Services to clients Contracts, calling clients and orders Invoicing the subscribers Credit and recovery Provisions for bad debts Other expenses – Accounting subscribers” At point (ii), Gaz Métro allocates $107,787,000 of the exploitation expenses to the “Producer” budget in the total exploitation expenses of $156,096,000. Thus, 48.3 million dollars are not allocated to the “Producer” budget. Question: 6.1 Please distribute by budget heading the 48.3 million dollars of exploitation expenses that were not allocated to the “Producer” budget (column 2 of table 2). Please justify for each of the headings the option not to allocate the cost to the “Producer” budget. Original: 2010.09.14 Gaz Métro – 1, Document 1.18 Page 1 of 3 Answer: Details of Operating Expenses Gas lost in the network Main pipelines Connections and detours Counters and regulators Administration expenses Electricity transmission Mercaptan and other Amortization of deferred charges Biogas compression Customer service Contracts, client calls and orders Subscriber billing Credit and collection Provisions – bad debt Other charges – subscriber account Sales and representation charges Advertising expenses TOTAL OPERATING EXPENSES 2008-2009 BUDGET 7,190,000 13,820,000 5,206,000 3,364,000 81,122,000 1,666,000 300,000 1,300,000 1,040,000 12,155,000 4,796,000 4,125,000 2,830,000 1,010,000 1,749,000 10,581,000 3,842,000 156,096,000 2008/2009 BUDGET TO SHARE 0 0 0 0 81,122,000 0 0 0 0 12,155,000 4,796,000 4,125,000 2,830,000 1,010,000 1,749,000 0 0 107,787,000 ALLOCATION FACTORS FB01D CONDPRIN FS21 FS22 EXPLOITD FB01D FB01D FB07D Biogaz FB08 FS23 FS25 FS29 FS26 CDA FS27 FS28 • Gas lost in the network: This cost is included in Category B. • Main pipelines: This cost is included in Category B. • Connections and detours: Current connections and detours consist of distribution function costs and will continue to be assumed by consumer clients. See Section 2.2.2 of the document Gaz Métro-1, Document 1. • Counters and regulators: Current connections and detours consist of distribution function costs and will continue to be assumed by consumer clients. See Section 2.2.2 of the document Gaz Métro-1, Document 1. • Electricity transmission: This cost is included in Category B. • Mercaptan and other: Gas injected into the network does not include Mercaptan. • Amortization of deferred charges: For the moment, these are past deferred charges. If new deferred charges are added in the future, one part must be assumed by the producers. • Biogas compression: Biogas costs will continue to be allocated to level M10 only, where the current biogas client is found. • Sales and representation charges: For the moment, it is not expected that the current sales force will be involved with producer clients. It will be directly via Operations. • Advertising expenses: For the moment, it is not expected that advertising will be done for producer clients. This will be done directly via Operations. No advertising will be done for this group of clients. Original: 2010.09.14 Gaz Métro – 1, Document 1.18 Page 2 of 3 Question: 6.2 Please add to table 2 a specific line for the provisions of bad debts. Answer: Distribution Costs Provisions – Bad Debt OPERATING EXPENSES GLOBAL ENERGY EFFICIENCY PLAN ENERGY EFFICIENCY FUND 2008/2009 BUDGET 2008/2009 BUDGET (1) 1,010,000 156,096,000 TO SHARE (2) 1,010,000 107,787,000 14,282,000 0 Number of clients function Volume function (3) (4) Income function Other 138 0 (5) 91,656 91,656 0 0 0 Total (6) 822,773 (7) 91,656 914,566 0 0 1,892,000 0 0 0 0 0 0 GREEN FUND 37,957,000 0 0 0 0 0 0 AMORTIZATION EXPENSES 86,248,000 19,911,000 0 0 0 234,729 234,729 AMORTIZATION OF DEFERRED COSTS 57,697,000 15,466,000 0 62,072 62,072 156,529 280,672 TAXES AND FEES 25,057,000 1,876,263 0 0 0 21,770 21,770 INCOME TAX 32,398,000 2,831,238 0 0 256,929 0 256,929 1,062,000 0 0 0 0 0 0 124,318,000 12,830,777 0 0 0 141,362 141,362 537,007,000 160,702,278 138 62,072 410,656 1,377,163 1,638,631,000 169,122,000 CONSUMPTION REBATE AND OTHER RATE BASE RETURN TOTAL DISTRIBUTION COSTS RATE BASE 1,850,028 45,792,000 Question: 6.3 Does Gaz Métro intend to make provisions for bad debts concerning the producers? Answer: Yes. Original: 2010.09.14 Gaz Métro – 1, Document 1.18 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) (ii) (iii) (iv) Gaz Métro 1, Document 1, Page 29, Table 2 R-3662-2008, Gaz Métro-9, Document 18 (dated November 20, 2008) R-3662-2008, Gaz Métro-9, Document 20 (dated November 20, 2008) R-3662-2008, Gaz Métro-9, Document 21 (dated November 20, 2008) Question: 7.1 Please reconcile the budget amounts for the amortization expense (total budget and “Producer” budget) with the values presented at point (ii). Answer: The costs in Column 1, Table 2 result from the 2008/2009 cost allocation study and represent distribution costs only. The document Gaz Métro-9, Document 18 provides all projected amortization expenses. Some costs in this document are functionalized in the balancing service for the service cost study. These costs are the overall costs related to the LSR plant totalling $1,201,000. For the budgeted amount to producers in the amortization costs, only costs related to general installations were taken into account in Category C, being $19,911,000. Question: 7.2 Please reconcile the amounts allocated for the amortization expense of the reported expenses (total budget and “Producer” budget) with the values presented at point (iii). Answer: The breakdown of total budgeted amounts for amortization expenses of deferred fees is found in the document Gaz Métro-12, Document 12, lines 315 to 337 and corresponds to Column 5 of the document Gaz Métro-9, Document 20. For the budgeted amount to producers in the amortization expenses of deferred fees, only costs related to self-insurance provisions, computer development, start-up benefit and stakeholder expenses were taken into account in Category C, being $15,466,000. Original: 2010.09.14 Gaz Métro – 1, Document 1.19 Page 1 of 3 Question: 7.3 Please justify why the amortization of the reported expense account “leveling lost gas” and “patents” in the “Producer” budget. Answer: Gaz Métro considers that patents do not target producer clients, but consumer clients. Producer clients are not to assume these costs for now. Costs related to lost gas were taken into account in Category C and not in Category B. Question: 7.4 Please confirm that the reported expense account “integrated management system” is included in the “Producer” budget. If negative, please explain why it was not included. Answer: Gaz Métro confirms that this cost is integrated into Category C costs. Question: 7.5 Please reconcile the amounts allocated for the tax and royalty expense (total budget and “Producer” budget) with the values available at point (iv). Please identify the items of this document that are included in the “Producers” budget. Answer: The same costs are taken into account in the two documents. The $484,000 spread between the two totals ($25,538,000 – $25,057,000 = $484,000$) is due to the fact that in table 2, only distribution costs are taken into account, whereas in reference IV, the tax on capital includes all services. Question: 7.6 Please detail the calculation of the amounts related to the income tax and the yield based on the pricing for the “Producer” budget. Original: 2010.09.14 Gaz Métro – 1, Document 1.19 Page 2 of 3 Answer: The applicable ratio on income tax and the base is 10%. This ratio was calculated as follows: DISTRIBUTION RATE BASE Self-insurance provision Computer system development Start-up benefit Stakeholder fees Régie fees TOTAL NON AMORTIZED COSTS General installations Land, structure and improvement Various equipment and materials Mobile materials and machinery TOTAL CAPITAL PROPERTY Rate base taken into account in Category C TOTAL DISTRIBUTION RATE BASE RATIO (328,000) 44,597,000 3,254,000 684,000 607,000 48,814,000 55,181,000 30,910,000 34,217,000 120,308,000 169,122,000 1,638,631,000 10.321% The obtained ratio is multiplied by the total 2008/2009 budget to estimate the portion of costs that must be shared between producer clients and consumer clients. Original: 2010.09.14 Gaz Métro – 1, Document 1.19 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) Gaz Métro 1, Document 1, Page 29, Table 2 Question: 8.1 Please distribute the “others” category (column 6) of table 2. Original: 2010.09.14 Gaz Métro – 1, Document 1.20 Page 1 of 3 Answer: FUNCTIONALIZATION AND CLASSIFICATION TABLE – 2008/2009 BUDGET 2008-2009 BUDGET 2008/2009 BUDGET TO SHARE Gas lost in the network Main pipelines Connections and detours Counters and regulators Administration expenses Electricity transmission Mercaptan and other Amortization of deferred charges Biogas compression Customer service Contracts, client calls and orders Subscriber billing Credit and collection Provisions – bad debt Other charges – subscriber account Sales and representation charges Advertising expenses TOTAL OPERATING EXPENSES 7,190,000 13,820,000 5,206,000 3,364,000 81,122,000 1,666,000 300,000 1,300,000 1,040,000 12,155,000 4,796,000 4,125,000 2,830,000 1,010,000 1,749,000 10,581,000 3,842,000 156,096,000 0 0 0 0 81,122,000 0 0 0 0 12,155,000 4,796,000 4,125,000 2,830,000 1,010,000 1,749,000 0 0 107,787,000 FB01D CONDPRIN FS21 FS22 EXPLOITD FB01D FB01D FB07D Biogaz FB08 FS23 FS25 FS29 FS26 CDA FS27 FS28 GLOBAL ENERGY EFFICIENCY PLAN 14,282,000 0 PGEE Distribution Costs ENERGY EFFICIENCY FUND ALLOCATION FACTORS 1,892,000 0 FEE 0 FB01FV Contributions Main pipelines Land and easements Civil part of stations Delivery and holding stations (regulation equip.) Connections and detours Counters and regulators General installations Biogas TOTAL AMORTIZATION EXPENSES (16,358,000) 45,709,000 684,000 530,000 3,626,000 25,315,000 6,559,000 19,911,000 272,000 86,248,000 0 0 0 0 0 0 0 19,911,000 0 19,911,000 CONDPRIN CONDPRIN CONDPRIN CONDPRIN CONDPRIN FS21-A FS22-A IMMOBILD Biogaz Self-insurance provision Computer development – amortization Stabilization account recovery CTGN patent Income tax assessment Subsidy – P.R.C. Subsidy – P.A.I.R.E. Global energy efficiency plan 1st establishment fees Start-up benefit Stakeholder fees Régie fees 2003 overpayment Operating expense relief Green fund TOTAL DEFERRED EXPENSE AMORTIZATION (656,000) 13,192,000 13,350,000 13,000 (860,000) 18,802,000 5,000 2,773,000 113,000 1,562,000 1,368,000 1,214,000 (8,006,000) 1,556,000 13,271,000 57,697,000 (656,000) 13,192,000 0 0 0 0 0 0 0 1,562,000 1,368,000 0 0 0 0 15,466,000 BASETARD BASETARD TEMPER-A BASETARD REVBRUTD PRCA PAIRE PGEE IMMOBILD IMMOBILD FS31 FB01D REVREQ EXPLOITD FB01FV Tax on network Tax on capital Tax on capital – Green Fund Transmission network Places of business Régie du bâtiment/de l’énergie fees TOTAL TAXES AND FEES 11,851,000 4,382,000 15,000 2,448,000 1,424,000 4,937,000 25,057,000 0 452,263 0 0 1,424,000 0 1,876,263 REVBRUTD BASETARD BASETARD BASETARD IMMOBILD FB01D Income tax Income tax – Green Fund Tax related to productivity gain sharing TOTAL INCOME TAX RELATED TO RETURN 27,432,000 97,000 562,000 28,091,000 2,831,238 0 0 2,831,238 REVNETD REVNETD REVNETD Tax on temporary spreads and other TOTAL INCOME TAX UNRELATED TO RETURN 4,307,000 4,307,000 0 0 IMMOBILD More pollutant energy substitution assistance account Consumption rebate TOTAL CONSUMPTION REBATE AND OTHER 1,000,000 62,000 1,062,000 0 0 0 CASEP PRC SUB-TOTAL OF DISTRIBUTION COSTS 412,689,000 147,871,501 RATE BASE RETURN 124,318,000 12,830,777 TOTAL DISTRIBUTION COSTS 537,007,000 160,702,278 Original: 2010.09.14 821,713 1,060 822,773 37,957,000 GREEN FUND OTHER 234,729 234,729 -7,227 145,342 18,414 156,529 4,983 16,787 21,770 0 0 1,235,801 BASETARD 141,362 1,377,163 Gaz Métro – 1, Document 1.20 Page 2 of 3 Question: 8.2 Please indicate the methods used to allocate the costs to producers based on the incomes, knowing that the allocation period of the costs is prior to the establishment of the tariff and thus the incomes of the producers. Answer: Gaz Métro issued the hypothesis that the income is proportional to volume. Question: 8.3 Please detail the allocation calculation of the underlying costs in table 2 including for each of the items subject to allocation: the allocation factor used, the percentage allocated to producers, the data allowing to establish this percentage, the hypotheses sustaining these data, and any other information necessary to reproduce the calculations. Answer: In order to evaluate the distribution costs unrelated to the gas network of a producer client, Gaz Métro simulated costs from the allocation study. For the details of costs that must be shared among producers and consumer clients, as well as the corresponding factor, see the response to the request for information 8.1. For cost sharing in columns (3), (4) and (5), the concept of marginal cost was used. Each cost was prorated depending on the number of clients, volume or income. Gaz Métro hypothesized that the income was proportional to volume. For example, in order to obtain the amount of $256,929 in column (5) for costs related to income tax, the reasoning is as follows: 516,475,000 m³ (expected volume of a typical case) / (5,174,833,000 m³ (2008-2009 budget total expected volume) + 516,745,000 m³ (expected volume of a typical case)* $2,831,238. For costs where the allocation factor is not a basic factor function (volume, number of clients and income), the portion of costs assumed by clients at a rate of 4.09 (for each factor) was applied to each cost. Following are the results obtained from the allocation of costs: CDA: EXPLOITD: BASETARD: IMMOBILD: REVNETD: REVBRUTD: FS26: Original: 2010.09.14 0.000606129 0.010129351 0.01101741 0.011788902 0.023976551 0.018407594 0.006374122 Gaz Métro – 1, Document 1.20 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) (ii) Gaz Métro 1, Document 1, Page 29, Table 2 La Presse, August 18, 2010, Page A2 (copy attached) Preamble: At point (i), Gaz Métro writes: “For this purpose, Gaz Métro drew up several hypothetical scenarios regarding the level of the volumes injected in the network as well as the investments made by Gaz Métro to supply the new clients. Consequently, a ratio has been calculated dividing the distribution costs allocated to the producers (different from the 28 royalties) by the investments based on the hypotheses of different scenarios. The ratios vary from 2.8% to 5.6%.” Point (ii) indicates: “This is our first project of gas line for the gas production, states Marie-Noelle Cano, Gaz Metro spokeswoman. The producers authorized us to suggest a route. Our role is to extend our network towards the production sites. We plan the start-up for the middle of 2011.” Question: 9.1 For each of the scenarios analyzed, please: 9.1.1. present and explain all the hypotheses used; 9.1.2. prove the economic feasibility of the scenarios; 9.1.3. distribute the investment between the different components (connection pipelines, measuring installations, chromatographic installations,…); 9.1.4. indicate the length and the diameter of the connection pipeline as well as the associated capacity to each of the diameters; 9.1.5. present the equivalent of table 2. Original: 2010.09.14 Gaz Métro – 1, Document 1.21 Page 1 of 3 Answer: For sub-question 9.1.1, see answer to request for information 9.5 of the Régie (Gaz Métro-1, Document 1.9). For sub-question 9.1.2, projects are always oriented toward being profitable, therefore sustainable on an economic point of view, for the distributor and their current clients, when subject to the receiving rate, as it is adjusted in such a way that projects would defer costs over the lifetime of the assets. The economic sustainability of projects on the producers’ point of view is not evaluated by Gaz Métro. For sub-question 9.1.3: • • • • • • Permits, land and engineering: Approximately 12% Materials: Approximately 17% Management and inspection: Approximately 5% Construction: Approximately 3% Pipeline: Approximately 54% Contingency: Approximately 9% For sub-questions 9.1.3 to 9.1.5: Scenario 1: Approximately 50 km, the majority 273 mm CL-3950 pipelines, with a capacity of more than 70,000 m3/h Scenario 2: Approximately 60 km, the majority 273 mm CL-3950 pipelines, with a capacity of more than 60,000 m3/h Scenario 3: Approximately 80 km, the majority 273 mm CL-3950 pipelines, with a capacity of more than 90,000 m3/h Gaz Métro cannot accurately respond to these questions as the scenarios result from actual discussions with producers and are therefore governed by confidentiality agreements. For sub-question 9.1.5, see answer to request for information 9.3 of the APGQ. Question: 9.2 Referring to point (ii), please indicate the level of the investment, the length and the diameter of the anticipated connection pipelines, as well as the volumes for all the projects currently subject to a claim to Gaz Métro. Answer: See answer to request for information 9.1 of the APGQ. Original: 2010.09.14 Gaz Métro – 1, Document 1.21 Page 2 of 3 Question: 9.3 Please present the equivalent of table 2 for each of the projects. Answer: See answer to request for information 9.1 of the Régie (Gaz Métro-1, Document 1.9). Question: 9.4 Please explain the proposition of Gaz Métro to calculate the costs based on the investment value and not on other criteria (e.g. incomes, volume). Answer: See answer to request for information 9.6 of the Régie (Gaz Métro-1, Document 1.9). Question: 9.5 Based on the example in table 2, please identify the category “C” costs that vary based on the investment level related to the reception point and sum it up. Answer: Table 2 refers to Category “B” costs and not Category “C” costs. See answer to request for information 4.1 of TCE (Gaz Métro-1, Document 1.40). Original: 2010.09.14 Gaz Métro – 1, Document 1.21 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) (ii) Gaz Métro 1, Document 1, Page 31, Table 3 Gaz Métro 1, Document 1, Page 32, Table 4 Question: 10.1 Please provide the analyses obtained or made by Gaz Métro and any other data available for Gaz Métro and that sustain the hypothesis of a useful life of 20 years for the connection pipelines and related installations. Answer: See answers to requests for information 6.1 and 6.2 of the Régie (Gaz Métro-1, Document 1.6). Question: 10.2 Which is the inflation rate used in the example presented in table 3 and 4? Answer: In the example presented in Tables 3 and 4, inflation rates were not incorporated. Question: 10.3 Please explain why inflation is not applied on the distribution costs not related to the gas network available in table 4. Answer: These costs were established based on the allocation of costs. Gaz Métro did not foresee the evolution of costs attributed to producers. Inflation could justify, on one hand, the increase of these costs in future years, and on the other hand, the increase in Original: 2010.09.14 Gaz Métro – 1, Document 1.22 Page 1 of 3 volume of producers in future years could justify a decrease in these costs via scale savings. Question: 10.4 Please explain why inflation is not applied on the royalty cost available in table 4. Answer: Gaz Métro does not foresee the inflation of fees. In fact, if volumes produced for a specific project decrease over the years, fee costs may decrease. Question: 10.5 Gaz Métro suggests using as measure of the capital cost the capital cost approved by the Régie for all the franchise. Can one draw the conclusion that Gaz Métro considers that the business risk associated to the producers is similar to that associated to consumers? Answer: No. Gaz Métro cannot conclude anything on this subject. Each market to be developed or each client has its own risk. Question: 10.6 Please provide the underlying calculation file in table 4 including the 20 years of calculation. If this file is not submitted, please provide all necessary data to reproduce the calculations including the source data as well as the applied formulae. Answer: See attached file named Tableaux III et IV. Original: 2010.09.14 Gaz Métro – 1, Document 1.22 Page 2 of 3 Question: 10.7 Which is the discount rate used by Gaz Métro and which is the source? Answer: The refresh rate is the weighted rate of the capital, being 7.67%. Project Hypothesis 3 Annual volume (m ) Total capital investment ($) Distribution costs unrelated to gas network (4.0% of investment) ($) Regulated Parameters Useful lifetime of assets (years) 3 3 Régie de l’énergie fee rate ($/10 m ) 3 3 Régie du bâtiment fee rate ($/10 m ) Utility tax rate Income tax Debt rate (weighted cost) Equity rate (weighted cost of equity of ordinary and privileged shareholders) Percentage of debt Percentage of equity of shareholders (ordinary and privileged) Weighted rate of capital Rate break-even point (years) 500,000,000 45,000,000 1,800,000 20 0.311486 0.411000 1.50% 26.90% 6.91% 8.55% 54% 46% 7.67% 20 [Refer to corresponding .pdf file to view second table] Original: 2010.09.14 Gaz Métro – 1, Document 1.22 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) Gaz Métro 1, Document 1, Page 23, Line 4 Preamble: At point (i), Gaz Métro states: “In the example given, the incomes necessary are of $7,525,000 and divided by the volumes injected of 500 Mm3/year the result is a rate of 1.50 ¢/ m3.” Question: 11.1 Is it possible that Gaz Métro will receive a request for a connection of 500 Mm3 per year, but it chooses to install a more important pipeline which would be necessary in the future? If affirmative, how will the price at the reception point be established? Answer: No. Given that rates are established in order to recover all project costs, Gaz Métro will build according to these needs. In the case where the capacity of a receiving point becomes insufficient following an increase in demand for natural gas injection at a receiving point, Gaz Métro should evaluate the investments required in order to increase the receiving capacity. On this last point, please refer to the answer to question 55 of the APGQ in document Gaz-Métro-1, Document 2.51. Question: 11.2 Does Gaz Métro intend to maintain the same price at the reception point for the 21st year as that for year 1 to 20 following the connection of a production site? If negative, please specify how the tariff will be calculated as of the 21st year. Answer: No. Theoretically, once the initial investments are completely amortized, the applicable receiving point rate should be adjusted at the decline to allow the recovery of distribution costs unrelated to the gas network. Original: 2010.09.14 Gaz Métro – 1, Document 1.23 Page 1 of 2 However, the reality will likely be different. In effect, the initial amortization rates of pipelines will probably be readjusted in transit following changes to the useful lifetime of the pipelines. For example, if there are five years remaining on the amortization duration, but the client signs a new contract and wishes to inject gas on the 15th and 25th year, Gaz Métro will review the amortization period of the asset, as well as the applicable receiving rate. In addition, new investments may be required along the way in order to maintain the receiving point injection. In this case, there may be non amortized investments after the 20th year. The receiving point rate starting on the 21st year will then take into account these changes and/or investments. Question: 11.3 If the two reception points are located at the middle (reception point 1) and respectively at the extremity (reception point 2) of the same connection pipeline, how will the costs be distributed between the two reception points and how will the prices be established? Answer: Take a simple case where two producers (at receiving points 1 and 2) have a CMC of 50,000 m³/day. The part of the connection pipeline that connects receiving point 1 at the interconnection point to the existing network must have a capacity of 100,000 m³/day. The cost of the portion of the pipeline between receiving point 1 and the interconnection point will be equally assumed between the two producers. The rate at receiving point 1 will take into account these costs. The rate at receiving point 2 will be established by taking into account the share of costs of the portion of the connection pipeline that connects receiving point 1 at the interconnection point to the existing network over and above 100 % of the costs of the portion of the connection pipeline that connects receiving point 2 to receiving point 1 at a capacity of 50,000 m³/day. Question: 11.4 How does Gaz Métro intend to establish the reception price if the consumers are connected starting at the connection pipeline of a production site. Answer: The receiving point rate will be established in accordance with the Régie’s proposed methodology by taking into account that only the producer uses the new pipeline. If consumer clients were possibly connected to this pipeline, the decline of the applicable receiving point rate would be reviewed. The cost allocation method among producers and consumer clients will be presented to the Régie upon request. Original: 2010.09.14 Gaz Métro – 1, Document 1.23 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Applicable Receiving Point Rates References: (i) (ii) Gaz Métro 1, Document 1, Page 23, Line 6 Gaz Métro 1, Document 1, Page 20, Line 19 Preamble: At point (i), Gaz Métro writes: “If another producer wishes to inject the same level of volume (i.e. additional 500 Mm3) and does not require additional assets, the necessary income will also be $7,525,000 per year divided by the new volumes of 1,000 M m3/year and this will be equal from now on to a rate of 0.75¢/m3. Gaz Métro will revise the rates at the reception points concerned at the time of the subsequent tariff cause to the investment request.” At point (ii), Gaz Métro writes: “This option will allow to reduce the risk of inaccurate real costs and thus the rates at the reception points and to ensure thus the stability of these rates for the producers.” (emphasis supplied) Question: 12.1 What treatment will Gaz Métro apply if a producer who shares a reception point with one or more producers shuts down? Does the reverse situation apply (i.e. proportional increase of the rate)? Answer: In the case of the closure of a producer client who shares a receiving point with one or more other producer clients prior to the maturity of the first contract, the producer must continue to pay the fixed fees up to the maturity of this contract and the rates paid by other producers will not be subject to any adjustment. On the other hand, as mentioned in Article 3.5.3 of the document Gaz Métro-1, Document 1, producers who do not renew their contract while the break-even point has not yet been reached must pay an allowance. In this case, other producer clients will not be subject to an increase. Original: 2010.09.14 Gaz Métro – 1, Document 1.24 Page 1 of 2 However, in the case where a new producer adds a receiving point and that the receiving capacity is sufficient, applicable rates must be newly calculated in order to share the costs of connection pipelines among all user producers and these pipelines. However, if new investments were required in order to increase the receiving capacity, the new producer would be responsible for the charges. Question: 12.2 Please comment on the stability of the rates referred to at point (ii) if the answer is affirmative at point (i) and considering the answer to the previous question. Answer: Rates would remain effectively stable in the case of a closure of a producer client, but may be called to be lowered in the case where a new producer is added to a receiving point. Original: 2010.09.14 Gaz Métro – 1, Document 1.24 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Unit Rate to Volume Delivered Outside the Franchise References: (i) (ii) Gaz Métro 1, Document 1, Page 37, Line 1 Gaz Métro 1, Document 1, Page 37, Line 18 Preamble: At point (i), Gaz Métro states: “The application of this allocation factor as part of the allocation study of the costs for year 2008/2009 allowed identifying that 32% of the gas network pipelines are transmission pipelines.” At point (ii), Gaz Métro specifies regarding the allocated costs according to the derived factors: “For all these costs, the segment allocated to the transmission function is 16%.” Question: 13.1 Please show in detail how the application of the CONDPRIN factor allows identifying that 32% of the gas network pipelines are transmission pipelines? Answer: The breakdown of main pipelines in the allocation of costs is done via a method called CAU. It allows for making a distinction between the pipelines according to their purpose. • • Carrier pipelines feed the various distribution networks; Distribution pipelines allow for the connection to service lines. The breakdown of costs for carrier and distribution pipelines that cannot be directly attributed to each rate class requires the application of certain hypotheses. Two important functions can be perceived for distribution pipelines: • • An “access” component; A “capacity” component; Carrier pipelines are a function of the capacity component only. Original: 2010.09.14 Gaz Métro – 1, Document 1.25 Page 1 of 3 In order to allow the breakdown of pipeline costs between the distribution and carrier pipelines, two pieces of information are required: 1. A unit cost ($/metre) for each type of pipeline, and the length (metre) of the pipelines. 2. The lengths are categorized per pipe capacity: • Distribution: 0 to 999 kpa • Carrier: 1000 kpa or more. Unit costs are multiplied by the lengths of each category. This provides a proportion of costs for each category. These same proportions are then applied to the capital property value. The 32% is obtained by the ratio between the carrier pipeline value and the total value of the pipelines. Question: 13.2 Please explain in detail the calculations allowing concluding that 16% of the associated costs to the derived factors must be allocated to the transmission function. Answer: See answer to request for information 12.1 of the Régie (Gaz Métro-1, Document 1.12). Question: 13.3 Please present the calculations allowing concluding that 16% of the costs associated to the “REVBRUTD” factor must be allocated to the transmission function. Answer: See answer to request for information 12.1 of the Régie (Gaz Métro-1, Document 1.12). Question: 13.4 Please present the calculations allowing concluding that 16% of the associated costs to the “BASETARD” factor must be allocated to the transmission function. Answer: See answer to request for information 12.1 of the Régie (Gaz Métro-1, Document 1.12). Original: 2010.09.14 Gaz Métro – 1, Document 1.25 Page 2 of 3 Question: 13.5 Please present the calculations allowing concluding that 16% of the associated costs of the “REVNETD” must be allocated to the transmission function. Answer: See answer to request for information 12.1 of the Régie (Gaz Métro-1, Document 1.12). Original: 2010.09.14 Gaz Métro – 1, Document 1.25 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Unit Rate to Volume Delivered Outside the Franchise References: (i) (ii) Gaz Métro 1, Document 1, Page 38, Table 5 Gaz Métro 1, Document 1, Page 39, Line 21 Preamble: At point (i), Gaz Métro allocates $5,193,557 of the contributions to the “Producer” budget. At point (ii), Gaz Métro writes: “The transmission costs allocated to D4 price (excluding the 4.10 section) are of $11,112,086 and the volume of 1,582,973 103m3. The resulting unit cost is thus of 0.70 ¢/m³ and this is the rate applicable to producers for this new price.” Question: 14.1 Please indicate whether it is planned that the producers pay the contributions to fund the investments for the main pipelines. If not, please explain the allocation of the contribution to the “Producer” budget. Answer: No. With respect to the allocation of contributions to the “Producer” budget, given that these stem from government subsidies, Gaz Métro deems it reasonable that producer clients reap the benefits. Original: 2010.09.14 Gaz Métro – 1, Document 1.26 Page 1 of 2 Question: 14.2 Referring to point (ii), please indicate the transmission costs allocated to D4 tariff excluding the allocation contributions. Please calculate the resulting unit cost. Answer: 2008/2009 Budget 2008/2009 BUDGET Carrier BUDGET ALLOCATION FACTORS D4.6 D4.7 D4.8 D4.9 D4.10 ANNUAL DISTRIBUTION VOLUME (000 m3) Gas lost in network Main pipelines Electricity transmission Other TOTAL OPERATING EXPENSES GLOBAL ENERGY EFFICIENCY PLAN ENERGY EFFICIENCY FUND GREEN FUND Contributions Main pipelines Land and easements Civil part of stations Delivery and holding stations (regulation equip.) Other TOTAL AMORTIZATION EXPENSES TOTAL AMORTIZATION EXP. OF DEFERRED FEES Tax on network Tax on capital Transmission network Other TOTAL TAXES AND FEES Income tax Other TOTAL INCOME TAX RELATED TO RETURN TOTAL INCOME TAX UNRELATED TO RETURN TOTAL CONSUMPTION REBATE AND OTHER RETURN ON RATE BASE TOTAL DISTRIBUTION COSTS Unit cost would be 0.78 ¢/m3. Question: 14.3 If it collects contributions from the clients, does Gaz Métro make a distinction between the contribution allocated to the main pipelines and the contributions allocated to other assets? If affirmative, please provide the contributions per type of pipelines. Answer: Information on client contributions is not broken down by type of pipeline. Original: 2010.09.14 Gaz Métro – 1, Document 1.26 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Unit Rate to Volume Delivered Outside the Franchise References: (i) Gaz Métro 1, Document 1, Page 36, Section 3.4.2.2 Question: 15.1 Please indicate whether there are contract obligations binding Gaz Métro to TCPL-TQM or any other obligations not allowing Gaz Métro to exchange gas with the producers delivering gas outside the franchise. Answer: There are no contractual constraints that prevent Gaz Métro from proceeding with exchanges. The possibility of exchanges with producers will be evaluated on an individual case basis depending on Gaz Métro’s operational needs and the anticipated gas flow upon request from a producer. Original: 2010.09.14 Gaz Métro – 1, Document 1.27 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Other Provisions References: (i) Gaz Métro 1, Document 1, Page 43, Line 7 Preamble: At point (i), Gaz Métro writes: “Gaz Métro requests the approval of the Régie regarding the methods used to establish the applicable rates to the daily and cumulative disproportions as well as to set these rates based on the TCPL tariffs in force when the decision is made.” Question: 16.1 Gaz Métro requests the approval of the method used to establish the applicable rates to the daily disproportions. However, it dose not provide the result of this method. Please explain in detail the full method of calculations generating the results available in table 6 and 7. Answer: Gaz Métro simply requests that the same penalties be applied as those that will be applied by the transportation company due to a daily or cumulative spread. Fees payable by TCPL are indicated in Section XXII of TCPL’s “General Terms and Conditions”. Fees are expressed in percentage of the “long distance” transportation rate from the East. Currently, the rate of the applicable area is $1.6381/GJ. Gaz Métro simply multiplied the percentage indicated in TCPL’s rate by the rate currently in effect in order to obtain the rates in $/GJ for each level of imbalance. These rates were then converted to ¢/m³ in order to comply with Gaz Métro’s overall pricing. TCPL’s rate can be consulted on their website (www.transcanada.com). Original: 2010.09.14 Gaz Métro – 1, Document 1.28 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Other Provisions References: (i) (i) Gaz Métro 1, Document 1, Page 43, Line 11 Gaz Métro 1, Document 1, Page 43, Line 16 Preamble: At point (i), Gaz Métro writes: “Gaz Métro will request that the initial contracts be concluded for at least 10 years for the clients subject to the reception tariff.” At point (ii), Gaz Métro writes: “This indemnity would be equal to the book value of the assets at this moment plus the opportunity cost that the producer will pay if it is bound by a contract until the break-even point is reached, which must correspond, in the majority of situations, to the duration of the amortization, i.e. 20 years.” break-even point is reached, which must correspond, in the majority of situations, to the duration of the amortization, i.e. 20 years.” Question: 17.1 Please explain the 10 years requested for the initial validity of the contract given the fact that the useful life of the assets is 20 years. Answer: It is current practice to request rate contracts that are shorter than the useful lifetime of the assets. The case of TCE, discussed at length with the Régie, is a good example. Question: 17.2 What will be the minimum contract validity once the initial contract of 10 years is terminated? Original: 2010.09.14 Gaz Métro – 1, Document 1.29 Page 1 of 4 Answer: The minimum duration of the contract, once the initial contract has expired, is one year, but the start-up benefit would still apply for dedicated assets. Question: 17.3 Please indicate whether the tax for the future public services will be considered when calculating the indemnity. Answer: No. Since this cost will not be incurred for years following the benefit. Question: 17.4 At point (ii), Gaz Métro uses the conditional “would” when referring to the value of the indemnity. Please confirm that the sentence refers to the fact that this amount is not conditional and it would be equal to the book value of the assets at this moment plus the opportunity cost that the producer will pay if it is bound by a contract until the break-even point is reached. If negative, please explain the circumstances based on which the indemnity would be different. Answer: Gaz Métro confirms that the conditional has no other goal than to refer to a situation that has not yet occurred (see answer to request for information 2.2 of ACIG; Gaz-Métro-1, Document 1.14). At reference (ii), the sentence could therefore read: “This benefit would equal the book value [...].” Question: 17.5 If a producer decides to end its operations when the 10-year initial agreement expires or at any other moment before the end of the useful life of the equipment and if this client becomes insolvent (i.e. it is impossible to pay the indemnity provided), how does Gaz Métro intend to recover the category “A” costs that could not be recovered from the producer if: 17.5.1. the client is the only one connected at the reception point? 17.5.2. the client shares the reception point with other producers? Answer: In the two figure cases, if a producer goes bankrupt during the year, the shortage to be gained will be shared between clients (consumer and producer clients) and Gaz Métro in accordance with the prescribed regime in effect. For the following year, Gaz Métro expects to recover the costs from all consumer and producer clients. Original: 2010.09.14 Gaz Métro – 1, Document 1.29 Page 2 of 4 Question: 17.6 If the costs are not paid by the producers (e.g. a bankrupt and insolvent client unable to pay the category “A” costs), does the suggestion made by Gaz Métro imply that the “failed” cost would be totally paid by the consumers? If affirmative, why these “failed” costs are not incurred: 17.6.1. only by the producers? 17.6.2. only by the Gaz Métro shareholder? 17.6.3. by the producers and the Gaz Métro shareholder? Answer: As is explained in answers 10.3 and 10.4 to the Régie’s questions in the document Gaz Métro-1, Document 1.10, the risk of “bankruptcy” is as much a residual risk for Gaz Métro as it is for existing clients and other producers under rate contract at the time of the bad debt. The requested rate principles limit the risk over the lifetime of the dedicated assets upon receipt with the proposal of the benefit, but the potential for sharing current costs and gains among everyone (existing clients, producer clients, Gaz Métro shareholders) is also very important with the contribution of the unit rate to volumes outside the territory. Question: 17.7 Or a reception point with two producers (A and B). The two clients are connected at the same time concluding 10-year contracts with CMC of 20,000 m3 each. After 10 years, the client A does not renew its contract. The other renews it for one year for 20,000 m3. 17.7.1 What will happen with the rate of the reception price in the 11th year? 17.7.2 If client B interrupts its operations after the eleventh year, who is responsible to pay the indemnity, and what are the proportions? 17.7.3 If client B interrupts its operations because of bankruptcy, who is responsible to pay the indemnity, and what are the proportions? Would Gaz Métro recover the entire indemnity? Answer: In the eleventh year, client A, who does not renew his contract, would be billed for the benefit covering his share of costs, being 50% in this example. Thus, the applicable receiving point rate should not be allocated and client B would not be affected. If client B also ceases operation after the 11th year, he would be billed for the benefit covering the other share of costs, being the other 50%. Original: 2010.09.14 Gaz Métro – 1, Document 1.29 Page 3 of 4 If client B ceases operation due to bankruptcy and it is not possible for Gaz Métro to recover the benefit, please refer to answers to questions 17.5 and 17.6. Original: 2010.09.14 Gaz Métro – 1, Document 1.29 Page 4 of 4 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Other Provisions References: (i) Gaz Métro 1, Document 1, Page 44, Line 12 Preamble: At point (i), Gaz Métro writes: “If the gas received is not compliant, Gaz Métro will notify the client and can immediately suspend the reception of the noncompliant gas until the corrective measures are taken or can continue to accept the noncompliant natural gas.” Question: 18.1 If Gaz Métro accepts noncompliant gas (e.g. low calorific content), how does it intend to compensate the consumers in the consumption area affected? Answer: Gaz Métro would only accept non compliant gas from a producer if it had no great impact on the quality of natural gas delivered to consumer clients and that the gas be compliant (significant dilution effect). Original: 2010.09.14 Gaz Métro – 1, Document 1.30 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Gaz Métro Business Risk Question: 19.1 According to Gaz Métro, does contracting of new clients lead to the increase or decrease of the business risk of Gaz Métro or will it be the same? Please explain. Answer: It is impossible to speculate on this question without knowing the rate principles that will inevitably be adopted and without having a bit of development history for this category of clientele. For the moment, on a strictly economic angle, Gaz Métro is of the opinion that the demand of this new rate, with all associated applicable terms and conditions, equally and fairly shares the risks of gains or losses among current clients, producer clients and Gaz Métro shareholders. Question: 19.2 Supposing that the analysis presented by Gaz Métro is based on the hypothesis that the new producers will not affect the business risk of Gaz Métro, please indicate whether a change in this hypothesis (e.g. contracting of new clients will lead an increase in the business risk of Gaz Métro), would impact the offer of Gaz Métro. Answer: See answer to question 19.1. Question: 19.3 Does Gaz Métro intend to subscribe provisions for bad debts regarding the producers? If yes, what would be the range of this provision according to the scenarios analyzed and referred to on page 28 in the GM-1 document, document 1. Original: 2010.09.14 Gaz Métro – 1, Document 1.31 Page 1 of 3 Answer: For the first part of the question, please refer to the answer to question 6.3 of the ACIG. Parameters for quantifying the provision specifically for new producer clients have not yet been established to date. However, Gaz Métro considers that this cost is a category C cost, being distribution costs unrelated to the gas network. This cost is therefore covered by the applicable 4% on investments upon the establishment of receiving point rates. Question: 19.4 If Gaz Métro decides to set up a new company, Gaz Métro 2, and if the latter has the purpose to connect the producers to the Gaz Métro network. Would Gaz Métro accept to offer the same tariffs as those in this file, as well as the same yield? Please explain any difference referring to these two subjects (tariff and yield). Answer: This is a speculative question on which Gaz Métro cannot lean toward with respect to this case. See answer to question 19.1. Question: 19.5 As part of the pricing offered, please confirm that adding a producer will lead to an increase in pricing the first years for all existing clients. If this is not the case, please explain who will pay the difference between the costs and incomes for these clients during the first years. Answer: This affirmation would be true if the receiving rate consisted only of a pricing element at receiving points. However, the rate also includes a pricing element at delivery points. This delivery point pricing anticipates that additional income (0.70¢/m3) will be added to receiving point income in the case where natural gas is delivered outside the territory. This additional income would increase project profitability as there would be a contribution to existing carrier network fees and, thus, a rate decrease for consumer clients. In addition, if a rate increase results in the addition of a new client, this increase would be entirely compensated in the future by more decreases than increases, so that other clients remain unaffected in present value. For additional information, see answer to question 6.3 of the Régie (Gaz Métro-1, Document 1.6). Original: 2010.09.14 Gaz Métro – 1, Document 1.31 Page 2 of 3 Question: 19.6 Has Gaz Métro assessed the impact on pricing that the existing clients may incur depending on whether one or several producers are connected the following years? If affirmative, please present the scenarios analyzed. If negative, please present the impact on pricing for the existing clients if: 19.6.1. there would be one connection in 2011; 19.6.2. there would be 5 connections in 2011; 19.6.3. there would be one connection per year, from 2011 to 2020. As part of this exercise, you can use the data of the mean of the estimated connections to make the other calculations presented in the file with the associated volumes (table 3 of the Gaz Métro provision). Answer: No. Gaz Métro did not evaluate the rate impact that may support existing clients if there were one or more producer client connections in the following years. The following table lists the requested analyses. Gaz Métro used the same hypotheses as those in table 3 and the results from table 4 for service costs, rate income and the difference between costs and income. In order to calculate the rate impact for current consumer clients, Gaz Métro used the distribution income from the 2011 Rate Cause budget, including GAC and Green Fund income. [Refer to corresponding .pdf file to view table] Original: 2010.09.14 Gaz Métro – 1, Document 1.31 Page 3 of 3 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Service Conditions References: (i) Gaz Métro 1, Document 1, Page 43, Line 11 Question: 20.1 How does Gaz Métro intend to make a distinction among the volumes delivered by the two producers by using the same reception point? Answer: Producers should route natural gas from the wells to receiving points via collection networks. If two producers route natural gas via two separate pipelines, Gaz Métro will install two counters and each producer will have a contract with Gaz Métro and will be priced separately. In the event that two producers route natural gas to the same receiving point via one pipeline (collection network), one counter will be installed and billing will be established as if there was only one producer client. Original: 2010.09.14 Gaz Métro – 1, Document 1.32 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Impact on Other Services References: (i) Gaz Métro 1, Document 1, Page 55, Line 22 Preamble: At point (i), Gaz Métro writes: “The supply that Gaz Métro would purchase from the producers would be distributed among the supply services, compressure gas, transmission and balancing based on the same principles as those currently applied for the purchases made at Dawn.” Question: 21.1 Please explain the proposition to distribute the supply costs based on the same principles as those currently applied for the purchases made at Dawn. Answer: Gaz Métro’s grouped pricing ensures that clients are billed independently for supply, compression, transportation and balancing services. The purchase of a molecule at a geographical point other than the borders of Alberta necessarily imply a reallocation of acquisition costs for the various services that will be billed to clients. This is what is done in the case of a purchase in Dawn and it is what Gaz Métro proposes to do for purchases that will be done directly within their territory. Question: 21.2 Does Gaz Métro request the approval for this distribution in this claim. Answer: No. This case targets the creation of a receiving rate and not the purchase of locally produced gas by Gaz Métro. Original: 2010.09.14 Gaz Métro – 1, Document 1.33 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Impact on Other Services References: (i) (i) Gaz Métro 1, Document 1, Page 57, Line 24 Gaz Métro 1, Document 1, Section 3.5.2.2 Preamble: At point (i), Gaz Métro states: “The differences between the “nominations” and the volumes actually injected of the 24 producers are covered by a specific method of the latter and this method as well as the related expenses have been described in section 3.5.2.2.” At point (ii), Gaz Métro describes the application of a penalty in case of disproportion between the nominations and the injected volumes. However this section does not include the operational impacts on the nomination disproportions. Question: 22.1 Please prove that the nomination disproportions would not need additional balancing. If negative, please prove that the costs generated by these additional needs are entirely borne by the producers. Answer: Gaz Métro still doesn’t know the delivery profile of gas producers as well as their ability to precisely anticipate the daily production of their wells. In light of discussions that Gaz Métro held with some producers, they seem confident in their ability to adequately predict the production of their wells and therefore to precisely nominate. Gaz Métro does not foresee contracting balancing tools to producers or reserving them a portion of existing balancing tools. There are therefore no resulting additional costs for producer needs. In the event that producer nomination imbalances produce additional costs for Gaz Métro with TCPL, the necessary fees by Gaz Métro being based on payable fees by TCPL, the remainder of the clientele should be indemnified. Original: 2010.09.14 Gaz Métro – 1, Document 1.34 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Pricing Text References: (i) (ii) (ii) Gaz Métro-2, Document 1, Page 7 Gaz Métro-2, Document 1, Page 15, Section 4.1 Gaz Métro-2, Document 1, Page 13, Section 3.1 Preamble: Point (i) shall be interpreted as follows: “NATURAL GAS SERVICE One or more services of the distributor among the following: natural gas supply, compressure gas service, transmission, and balancing, and distribution.” Point (ii) shall be interpreted as follows: “4.1. NATURAL GAS SERVICE REQUEST 4.1.1. SERVICE REQUEST PROCEDURE 4.1.1.1. Address related to the distribution network The service request can be made by phone, mail, email, fax or on the website of the distributor. If the distributor requests so, this request must be drawn up when the claimant does not understand to occupy the address concerned. The service request of a client subject to an reception tariff must be made in writing.” (emphasis supplied) Reference (iii) shall be interpreted as follows: “3.1. NATURAL GAS SERVICES The distribution service is offered exclusively by the distributor on its territory, as provided by the Law on the Régie de l’énergie. Except for the clients subject to the reception tariff, the following services can be obtained from the distributor, if the client chooses so, subject to Tariff, assumed by the client from one or more suppliers: Original: 2010.09.14 Gaz Métro – 2, Document 1.1 Page 1 of 2 1 the supply service, including the dilution gas; 2 compressure gas service; 3 transmission service; 4 balancing service. The distributor supplies these services by default, according to the Tariff, unless the client expresses the intention to contract one or more services.” (emphasis supplied) Question: 23.1 The natural gas service excludes the reception of gas according to the definitions of the text regarding the service and pricing conditions. However, subsection 4.1.1.1. stipulates the service request methods for the reception service even if section 4.1. refers specifically to the natural gas supply. Does Gaz Métro not see a contradiction here? Should gas service definition include the gas reception? Alternatively, should section 4.1. be called “REQUEST FOR NATURAL GAS SERVICE AND NATURAL GAS RECEPTION?”? Answer: Natural gas service does not exclude the receipt of natural gas. In effect, the introduction of Article 4.2 in the document Gaz Métro-1, Document 1, page 54 justifies that the new natural gas receiving rate will be a part of the distribution service and that the general provisions for the distribution service will apply to both distribution rates and receiving rates. The definition of natural gas service therefore includes the receipt of natural gas and thus no changes to the above references are required according to Gaz Métro. Question: 23.2 In the same manner, in section 3.1, is it necessary to exclude explicitly the clients subject to the reception tariff, knowing that this section specifically refers to the natural gas service? Answer: Since section 3.1 deals with natural gas services that include the receipt of natural gas (see answer to request for information 23.1), it is necessary to explicitly exclude clients subject to the receiving rate. Original: 2010.09.14 Gaz Métro – 2, Document 1.1 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Pricing Text References: (i) Gaz Métro-2, Document 1, Page 73, Section 16.6.3 Preamble: The last paragraph at point (i) shall be interpreted as follows: “If another client wishing to inject natural gas in the network of the distributor requests to access, during the period covered by the indemnity, all or a part of the CMC supplied by the client who paid the indemnity, the latter can be partially reimbursed by the distributor, as agreed on by the parties.” Question: 24.1 Please indicate whether the new reimbursement level is subject to certain formulas or obligations. Would Gaz Métro be free to accept any reimbursement level deemed acceptable. Answer: At this time, Gaz Métro has not yet established a formula for determining the reimbursement level of the allowance. Gaz Métro notes that two conditions are required before such a reimbursement can occur. Firstly, the 10 first years of the producer’s contract must have lapsed. Secondly, a scenario where another producer wishes to detain the released capacity at the same receipt point must occur. Until then, Gaz Métro is open to analyze and eventually propose rules for determining the calculation of the reimbursement in a next rate case. Question: 24.2 Please indicate the principles that Gaz Métro intends to follow to determine if reimbursement is necessary and to establish the amount. Original: 2010.09.14 Gaz Métro – 2, Document 1.2 Page 1 of 2 Answer: See answer to request for information 24.1 of the ACIG. Original: 2010.09.14 Gaz Métro – 2, Document 1.2 Page 2 of 2 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Comparables Question: 25.1 Does Gaz Métro know if there are other gas suppliers in North America who have an reception tariff? If affirmative, please name them and summarize the different pricing structures used by them. Answer: To our knowledge, the only gas distributor in Canada that has a receiving rate is Union Gas. This is a locally produced gas receiving rate, the rate being “M13 Rate Schedule Transportation of Locally Produced Gas”. See the following website for more information: www.uniongas.com/storagetransportation/services/transportation/m13transport.asp Gaz Métro did not find any information from the United States. Original: 2010.09.14 Gaz Métro – 2, Document 1.35 Page 1 of 1 Gaz Métro Limited Partnership Creation of a Natural Gas Receiving Rate, R-3732-2010 GAZ MÉTRO’S RESPONSE TO A REQUEST FOR INFORMATION Origin: Request for information #1 dated August 19th, 2010 Applicant: Industrial Gas Users Association Invoicing Question: 26.1 Please indicate which of the following invoices will be included on the invoices of the producers: 26.1.1. Reception 26.1.2. Delivery in franchise 26.1.3. Delivery outside franchise 26.1.4. Distribution 26.1.5. Balancing 26.1.6. Transmission 26.1.7. Inventories 26.1.8. Supply Answer: As mentioned in the response to request for information 23.1 of the ACIG (Gaz Métro-2, Document 1.1), the receipt of natural gas belongs to the distribution service. It is only this service – distribution – that will appear on producer client invoices. Question: 26.2 Are there other services or expenses that might be invoiced to the producers? Answer: Fees for the daily overrun of the maximum contractual capacity may be billed (Article 3.5.2.1 of Gaz Métro-1, Document 1). However, these are not “additional” fees but fees that are an integral part of the distribution service. With respect to spreads between “nominated” volumes and injected volumes, fees are required when the daily spread between “nominated” volumes and injected or withdrawn volumes is greater than 2% of the total “nominated” volume at this receiving point (Article 3.5.2.2 of Gaz Métro-1, Document 1). Fees are also payable when the daily balance of Original: 2010.09.14 Gaz Métro – 2, Document 1.36 Page 1 of 2 the cumulative spread account is greater than 4% of the greater of the “nominated” volumes or the average of “nominated” volumes over the past 30 days. On the other hand, an allowance can be billed in the event that the producer decides to not renew their contract and that the rate break-even point has not been reached (Article 3.5.3 of Gaz Métro-1, Document 1). In the case where a producer chooses a reading method other than the one chosen by the distributor, actual fees related to the requested reading method may be billed (Gaz Métro-2, Document 1, Article 5.3.1). Lastly, certain other applicable fees (Chapter 17 of Gaz Métro-2, Document 1) may also be billed to producers when applicable. Original: 2010.09.14 Gaz Métro – 2, Document 1.36 Page 2 of 2