CITY COLLEGE Facilities Master Planning and Oversight Committee Project Submittal: Physical Plant and Tennis Courts L O S AN G EL E S CO M M UN IT Y CO LL EG E D I S T RICT DEPARTMENT OF FACILITIES PLANNING AND DEVELOPMENT SUSTAINABLE BUILDING PROGRAM CAPITAL CONSTRUCTION COMMITTEE (CCC) MEETING LEED PROJECT EXECUTIVE SUMMARY College Name: LACCD Project Name: LACCD Project Number: College Project Manager: Design Build Team: Los Angeles City College LACC Physical Plant (M&O) and Tennis Courts 01C-146 & 01C-152 Serafin Fernandez Pankow Builders / IBI Group Project Description: PLANT FACILITIES BUILDING The Project will provide new centralized facilities for the college Maintenance and Operations Department. The new facilities consist of a single story, 13,000 square foot, industrial type space to accommodate shops for painting and signage, carpentry, metalwork, auto/HVAC, plumbing, electrical and electronics and locksmith. There will also be an additional 6,700 square feet of covered storage area for vehicles, material, trash and recyclables. The building will be a concrete masonry unit structure with steel frame and metal deck roof structure with roof mounted photovoltaic panels which will produce 40,516 AC kWh per year. TENNIS COURTS This portion of the project consists of six new tennis courts for athletics, instruction and recreation. The courts will be constructed to include an asphalt paving section with an acrylic court surfacing system, mesh-covered perimeter fencing and be lighted for evening play. Restrooms with exterior access and a secure storage area for tennis equipment will be included in the facility. Relevant Statistics: The current college M&O operations are spread throughout the campus and the various outdated shops are not functionally sufficient to support the college’s growing needs. This project will provide new centralized facilities for the college Maintenance and Operations Department. Tennis is a part of the college wellness program by Department of Kinesiology, Health and Dance. Currently, campus leases tennis courts at Griffith Park for teaching purpose. The design-build contract is $6,799,908 and funded by Measure J. Schedule: Expected Design Phase Completion: Expected Construction Phase Completion: Expected Close-Out Phase Completion: 1/2014 9/2014 10/2014 Sustainable Features: The project is expected to achieve (27) LEED™ points for a LEED™ Certified rating. Some of the sustainable features include: • • • • • • Exterior canopy to shade south exposure glazing Glazed overhead doors in all shops to provide views for occupants Water efficient and waterless restroom fixtures Heat reflective roofing material Energy efficient light fixtures Majority of construction materials includes high level of recycled content Form DES-015-A Page 1 of 1 Rev.04.25.2011 Campus Map HELIOTROPE DRIVE HELIOTROPE DRIVE 2. CESAR CHAVEZ ADMINISTRATION 16. 9. HEALTH FITNESS AND PE SOUTH GYM 22. LIFE SCIENCES 1. ATHLETIC FIELD / PARKING STRUCTURE A03-107029 3. STUDENT SERVICES 10. THEATER ARTS 11. RAD TECH 21. 379' - 0" CHEMISTRY 4. HOLMES HALL VEHICLE STOR. 17. WORKSHOPS COVERED STOR. FUTURE MAIN OFFICE LOCATION 12. 8. JEFFERSON HALL STUDENT UNION BUILDING A03-113143 13. CENTRAL PLANT 1 5. DA VINCI HALL 20. MLK LIBRARY NEW HAMPSHIRE AVENUE NEW HAMPSHIRE AVE Proposed LACC Physical Plant (M&O) and Tennis Courts Project Site MONROE STREET MONROE STREET 23. BRAILLE INSTITUTE 14. CENTRAL PLANT 2 6. LEARNING SUPPORT CENTER 7. CLAUSEN HALL 18. CDC 19. 15. FRANKLIN HALL SCIENCE AND TECHNOLOGY BUILDING VERMONT AVENUE VERMONT AVE N 1. Athletic Field / Parking Structure 2. Cesar Chavez Administration 3. Student Services 4. Holmes Hall 5. Da Vinci Hall 6. Learning Support Center 7. Clausen Hall 8. Student Union 9. South Gym 10. Theater Arts 11. Rad Tech 12. Jefferson Hall 13. Central Plant I 14. Central Plant II 15. Franklin Hall 16. Health Fitness and PE 17. Communications 18. CDC 19. Science and Technology 20. MLK Library 21. Chemistry 22. Life Sciences 23. Braille Institute WILLOW BROOK AVE WILLOW BROOK AVENUE COMMUNICATIONS VALLEY COLLEGE Facilities Master Planning and Oversight Committee Project Submittal: Community Workforce Development Center/Administration – part 2 L O S AN G EL E S CO M M UN IT Y CO LL EG E D I S T RICT DEPARTMENT OF FACILITIES PLANNING AND DEVELOPMENT SUSTAINABLE BUILDING PROGRAM CAPITAL CONSTRUCTION COMMITTEE (CCC) MEETING LEED PROJECT EXECUTIVE SUMMARY College Name: LACCD Project Name: Los Angeles Valley College Community Workforce Development Center (Valley Glen Gateway Building-Administration Center and Omega Data Center) – Part 2 LACCD Project Number: 38V.5836.02 College Project Manager: Design Build Team: Eloy Retamal, Yang Management, Inc. Pankow / Quatro Design Group Project Description: This 35.7 Million Dollars Design Build project funded by Measure J, consists of three distinct, but interrelated parts: Valley Glen Gateway (VGG): A new 70,310 gross square feet, two-story structure will house college administration, community and workforce development programs as well as instructional and conference facilities. Most of these departments are operating in an outdated 1960’s era structure on the same site that will be razed to make way for this new building. In addition to providing facilities that better serve the current and future needs of the campus community, this building will provide and identifiable and welcoming gateway to the college along Fulton Avenue. Part 2 to be approved by CCC on 08/21/2013. Omega Data Center (ODC): The current administration building houses a data center essential to the operation of the campus IT network. So, as part of this project a new free-standing Omega Data Center will be built on a separate site and will be fully operational prior to initiating to demolition of the administration building. In addition to serving LAVC needs, this new data center will also house some LACCD IT infrastructure. Part 1 was approved by CCC on 5/15/2013. Swing Space: During the course of construction, interim facilities will be needed to house the departments that will be displaced. As part of this project, a combination of existing permanent and relocatable buildings throughout campus will be utilized with a minimum of alteration. Part 1 was approved by CCC on 5/15/2013. Part 2 Scope of Work: The new, 70,310 gross square feet, Valley Glen Gateway Building will include offices and spaces for instruction and meeting facilities for the College and its community. The scope of work also includes demolition of the existing Administration building; and construction of the Valley Glen Gateway Building and all associated signage, site preparation, and improvements. The new building will be constructed as a steel brace frame structure with curtain wall at the exterior building envelope utilizing glazing, plaster, and metal panels as finish materials. The office and educational program functions are arranged on either side of the main circulation spine or “Avenue” that provides efficient access to the various office suites as well as bringing ample natural light into the heart of the building. The building entrances are located at each end of this “Avenue” and are accentuated with double height glass entrance volumes. At the center of the building is a central stair and seating court with a large skylight above that serves as a gathering space. Also within the gallery is an “Art Wall” that celebrates the history of Los Angeles Valley College. Form DES-015-A Page 1 of 2 Rev.04.25.2011 L O S AN G EL E S CO M M UN IT Y CO LL EG E D I S T RICT DEPARTMENT OF FACILITIES PLANNING AND DEVELOPMENT SUSTAINABLE BUILDING PROGRAM The Valley Glen Gateway Building consists of three functional zones: • • • Instructional Zone is comprised of lecture rooms and a computer lab Conference Zone is comprised of meeting rooms and a catering kitchen Office Zone is comprised of 14 departments, with varying hours of operation Relevant Statistics: The existing Los Angeles Valley College Administration Building, which was originally constructed around 1960’s has become outdated in its ability to facilitate the functioning of the College Departments that it holds. The existing facility will be demolished and replaced by the new Valley Glen Gateway Building. The goal is to bring many community and workforce development programs together under one roof, along with the College Administrative Center. The awarded Design Build contract for the entire project is $35.7M, funded by Measure J. The Part 2 contract is $25.6 million. Schedule: Works related to Part 2: Expected Design Phase Completion: Expected Construction Phase Completion: Expected Close-Out Phase Completion: April 2014 October 2015 December 2015 Sustainable Features: The project is expected to achieve (54) LEED Some of the sustainable features include: TM points for a LEED TM Silver rating. For Part Two: 1. Reuse of existing urban site 2. Durable materials (Plaster, Glass, & Metal) 3. Large glazing surfaces and skylights to maximize natural day lighting 4. Cool Roof (White PVC) 5. No VOC paint, sealant and caulking 6. Smart bathroom plumbing fixtures 7. Dual Flush Toilets 8. Occupancy Light Sensors 9. Temperature control (thermostat) 10. Landscape Bio-swales to mitigate storm water run-off 11. Drought-tolerant planting 12. Trees and light colored paving to minimize heat island affect Form DES-015-A Page 2 of 2 Rev.04.25.2011 LEED 2009 for New Construction and Major Renovations Los Angeles Valley College - Valley Glen Gateway Building Project Checklist 17 8 Y ? 1 Y 1 5 1 6 Prereq 1 Credit 1 Credit 2 Credit 3 Credit 4.1 1 3 2 1 1 1 Credit 4.4 Credit 5.1 Credit 5.2 Credit 6.1 Credit 6.2 Credit 7.1 Credit 7.2 Credit 8 1 Y 2 3 4 2 2 1 Credit 1 Credit 2 Credit 3 Prereq 2 Prereq 3 3 11 7 Credit 1 Credit 2 Credit 3 Credit 4 Credit 5 2 3 Credit 6 6 Y 3 1 2 Credit 1.1 Credit 1.2 Credit 2 2 Credit 3 Possible Points: Possible Points: Storage and Collection of Recyclables Building Reuse—Maintain Existing Walls, Floors, and Roof Building Reuse—Maintain 50% of Interior Non-Structural Elements Construction Waste Management Materials Reuse Materials and Resources, Continued 26 1 5 1 6 1 3 2 1 1 1 1 1 1 1 10 2 to 4 2 2 to 4 Fundamental Commissioning of Building Energy Systems Minimum Energy Performance Fundamental Refrigerant Management Optimize Energy Performance On-Site Renewable Energy Enhanced Commissioning Enhanced Refrigerant Management Measurement and Verification Green Power Materials and Resources Prereq 1 Possible Points: Water Use Reduction—20% Reduction Water Efficient Landscaping Innovative Wastewater Technologies Water Use Reduction Energy and Atmosphere Prereq 1 2 2 3 5 Possible Points: Construction Activity Pollution Prevention Site Selection Development Density and Community Connectivity Brownfield Redevelopment Alternative Transportation—Public Transportation Access Alternative Transportation—Bicycle Storage and Changing Rooms Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles Alternative Transportation—Parking Capacity Site Development—Protect or Restore Habitat Site Development—Maximize Open Space Stormwater Design—Quantity Control Stormwater Design—Quality Control Heat Island Effect—Non-roof Heat Island Effect—Roof Light Pollution Reduction Water Efficiency Prereq 1 12 5 18 Y Y Y 5 Credit 4.2 Credit 4.3 1 1 1 1 5 Sustainable Sites N Y ? 1 1 1 1 1 Credit 5 Credit 6 Credit 7 10 3 2 Y Y 1 Prereq 2 Credit 1 1 1 1 1 1 Credit 3.2 Credit 4.1 Credit 4.2 Credit 4.3 Credit 4.4 1 1 Credit 5 Credit 6.1 1 1 1 Credit 7.2 2 Credit 8.1 Credit 8.2 1 1 1 Credit 1.2 1 1 1 Credit 1.3 Credit 1.4 Credit 1.5 1 Credit 2 1 1 1 Possible Points: Minimum Indoor Air Quality Performance Environmental Tobacco Smoke (ETS) Control Outdoor Air Delivery Monitoring Increased Ventilation Construction IAQ Management Plan—During Construction Construction IAQ Management Plan—Before Occupancy Low-Emitting Materials—Adhesives and Sealants Low-Emitting Materials—Paints and Coatings Low-Emitting Materials—Flooring Systems Low-Emitting Materials—Composite Wood and Agrifiber Products Indoor Chemical and Pollutant Source Control Controllability of Systems—Lighting Controllability of Systems—Thermal Comfort Thermal Comfort—Design Thermal Comfort—Verification Daylight and Views—Daylight Daylight and Views—Views Possible Points: Innovation in Design: Green Cleaning Program Innovation in Design: Green Education Program Innovation in Design: Process Water Use Reduction Innovation in Design: 95% Construction Waste Diversion Innovation in Design: Life Cycle Assessment of Bldg. Assemblies LEED Accredited Professional Regional Priority Credits Credit 1.1 Credit 1.2 1 1 to 2 1 to 2 1 1 Innovation and Design Process Credit 1.1 1 1 to 3 1 1 to 2 1 to 2 Credit 6.2 Credit 7.1 1 1 2 Credit 2 Credit 3.1 1 Recycled Content Regional Materials Rapidly Renewable Materials Certified Wood Indoor Environmental Quality Prereq 1 1 3 14 Credit 4 1 35 1 to 19 1 to 7 2 2 3 2 N Credit 1.3 1 Credit 1.4 54 23 33 Total Regional Regional Regional Regional 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6 1 1 1 1 1 1 Possible Points: 4 Priority: Site Development, Maximixe Open Space Priority: Water Use Reduction (40%) Priority: On-Site Renewable Energy Priority: Daylight and Views Certified 40 to 49 points 15 1 1 1 1 Possible Points: 110 Silver 50 to 59 points Gold 60 to 79 points Platinum 80 to 110 Los Angeles Harbor College First Amendment to the 2010 Master Plan Facilities Master Planning and Oversight Committee August 21, 2013 Context • Demolition of General Classroom Building • Rename “Job Placement/ Data Center” to “Old Administration” • New site for SPS & Health – pending funding 2010 Master Plan Changes • Demolition of General Classroom Building • Re-siting of SPS & Health • Rename Job Placement/ Data Center to Old Administration Approved July 23, 2013 at the LAHC Shared Governance Meeting First Amendment to 2010 Master Plan • Demolition of General Classroom (14,336 sf) would result in minor air and noise impacts Negligible impacts off site • Building is less than 50 years old (constructed in 1969) and does not have exceptional significance • Ineligible for National Register or California Register of Historic Places • Project is eligible for a Class 1 CEQA Categorical Exemption • Exemption is appropriate because project involves minor alterations to campus with negligible or no expansion of existing uses (building would be replaced by an open quad) CEQA Notice of Exemption Los Angeles Harbor College EAST LOS ANGELES COLLEGE FACILITIES MASTER PLAN Dr. Ryan M. Cornner Dean of institutional Effectiveness ELAC PLANNING IN SUMMARY College Mission Strategic Plan Educational Master Plan Facilities Master Technology Plan Master Plan ELAC PLANNING IN SUMMARY • 2011 – Strategic Plan is approved by the Board of Trustees • November 2012 – College Master Plans are presented to the Board Institutional Effectiveness Committee • January 2013 – Educational Master Plan approved by the Board of Trustees • Facilities and Technology Master Plans are pulled for CEQA review A NEW MASTER PLAN • All currently planned buildings carried over • Recognizing the value of the facilities already available • • • • Plans for maximizing facilities usage Improving safety and emergency planning Improving the aesthetics of the campus Greater engagement with the community SUMMARY OF CHANGES • The 2012 Update does not propose any additional construction or demolition beyond that which has already been proposed and analyzed. Also, the 2012 Update does not propose to accommodate any additional student enrollment, or faculty or staff and as such would not result in increased vehicle trips or parking need. No new or substantially greater significant impacts would result. • Required Finding: No substantial changes are proposed for the project that require major revisions of the previous EIR due to the involvement of new, significant environmental effects or a substantial increase in the severity of previously identified significant effects. TECHNOLOGY MASTER PLAN • The 2009 SEIR and this 2012 Update continue to include the facilities required to implement the 2012-2018 Technology Master Plan and its prior iterations. • The 2012-2018 Technology Master Plan provides for maintaining and expanding wireless and other online and technology features, such as online portal systems and increased speeds and mobile efficiency, which do not require physical facilities and are supported by the facilities contained in the Facilities Master Plan as a whole. COLLEGE MISSION East Los Angeles College empowers students to achieve their educational goals to expand their individual potential, and to successfully pursue their aspirations for a better future for themselves, their community and the world. In order to fulfill this College Mission, the college has developed four goals. These goals serve as the broad planning objectives through which all other college planning documents and departmental plans will be based. Together these goals provide a foundation for building a true agenda of student success. Goal 1: Increasing student success and academic excellence through student-centered instruction, student-centered support services, and dynamic technologies. Goal 2: Increasing equity in successful outcomes by analyzing gaps in student achievement and using this to identify and implement effective models and programming to remedy these gaps. Goal 3: Sustaining community-centered access, participation, and preparation that improves the college's presence in the community, maximizes access to higher education and provides outlets for artistic, civic, cultural, scientific and social expression as well as environmental awareness. Goal 4: Ensuring institutional effectiveness and accountability through data-driven decisionmaking as well as evaluation and improvement of all college programs and governance structures. VISION Through our emerging focus on student‐centered instruction, student‐ centered services, and integrated learning, East Los Angeles College will be an exemplary model for student academic achievement, skill development, and artistic expression. Approved by the LACCD Board of Trustees August 10, 2011 1 | P a g e 2 | P a g e Goal 1: Increasing student success and academic excellence through student-centered instruction, studentcentered support services, and dynamic technologies. Educational Master Plan Technology Master Plan Facilities Master Plan Ensure on-campus student Support students, faculty, and staff Identify and assess existing green engagement to increase academic in the use of technology. areas on campus that facilitate achievement. learning and informal gatherings Complete the Health Careers Ensure adequate student support Provide high-performing, flexible, Center project to increase student services through the development reliable, and secure IT success for students progressing and implementation of studentinfrastructure to improve the through their health careers centered interventions. effectiveness of teaching and education. operational functions Enhance student employability by Increase student success through Complete the Science Career & expanding interdisciplinary smart and flexible classroom Mathematics Building project to opportunities on campus and designs that enable collaboration increase student success through strengthening campus career and incorporate a variety of the STEM fields and progression services. learning styles. through the math sequence from basic skills to transfer. Complete the Student Success and Provide a comprehensive first-year Ensure faculty greater access to Retention Center (SSRC) project course-related materials through experience that promotes and to increase student success through innovative technology. enhances student completion. the English sequence from basic skills to transfer; increase student success for noncredit students progressing through to credit courses; and increase student success by utilizing the planned lab space. Provide sustained professional Facilitate student-centered Ensure permanent classroom space development training for faculty instruction through multiple to meet enrollment demand for all information systems and platforms. academic programs. Strengthen college response to Facilitate student-centered Complete the South Gate Satellite struggling students. instruction through multiple Campus in order to increase information systems and platforms. student achievement. Develop and implement automated Complete the Campus Student technology to improve studentCenter/Bookstore Complex project centered support services. to increase student achievement. Provide appropriate study space Enhance institutional effectiveness that is conducive to student and promote student success success. through flexible access to technology. Complete the Public Service Careers Building project to increase student success through the career-technical programs. 3 | P a g e Goal 2: Increasing equity in successful outcomes by analyzing gaps in student achievement and using this, to identify and implement effective models and programming to remedy these gaps. Educational Master Plan Technology Master Plan Facilities Master Plan Increase the proportion of students Ensure all students have equitable Provide adequate access to who progress through the access to digital technologies facilities for disabled students, developmental math and English through ADA compliance of faculty, staff and guest. sequences. {ATD} software and technologies for disabled students, faculty, staff and guests. Create strategies to recruit and support underrepresented groups and to eliminate the achievement gap. Improve the transfer rate for underrepresented groups. 4 | P a g e Goal 3: Sustaining community-centered access, participation, and preparation that improves the college's presence in the community, maximizes access to higher education and provides outlets for artistic, civic, cultural, scientific and social expression as well as environmental awareness. Educational Master Plan Technology Master Plan Facilities Master Plan Develop opportunities for students Expand access to higher education Provide adequate open spaces, to expand their educational through a “greater and more userincluding a large open space and experience at ELAC through nonfriendly” Internet presence that additional green areas (for classroom activities such as provides up-to-date information on beautification, circulation and scientific lectures, demonstrations, college resources. outdoor activities) to promote civic and cultural events. and cultural activities necessary for improving the college’s presence in the community Create programs to prevent “cold Provide adequate parking and assessment” and prepare students promote public transportation to take placement exams. {ATD options to improve access to the college while mitigating impact on the community Enhance the Transfer Culture on Develop a plan, with input from campus. students and the community, to create visually appealing campus environments that establish ELAC as a community-centered venue. Utilize the college’s online Restore recreational areas offerings and existing learning accessible to the community management systems to enhance student access for non-traditional students and accelerate progress for on-campus students. Obtain recognition for ELAC as a cultural center. 5 | P a g e Goal 4: Ensuring institutional effectiveness and accountability through data-driven decision-making as well as evaluation and improvement of all college programs and governance structures. Educational Master Plan Technology Master Plan Facilities Master Plan Identify and implement successful Evaluate emerging technologies to Enhance efficient use of all sites elements within special programs provide solutions that maximize and buildings. (Honors, Adelante, Athletics, access to higher education, improve Distance Education, etc.) into other the college’s operational scalable campus programs. efficiencies and provide effective modes of communication. Enhance facilities’ emergency Implement an online planning and Develop a method to evaluate the safety measures and planning. Program Review interface to effectiveness and classroom support the continual self-review application of student-centered and refinement of all college instruction strategies offered through Professional Development. programs. Develop methods to promote the During emergencies, ensure the Ensure adequate interior and use of data at the departmental ability to quickly and accurately exterior lighting. level to enhance decision-making. notify all personnel of threats, provide them instructions and assess their status in real-time. Deter illicit activity and protect Ensure that the campus is well Develop and revise curriculum to maintained. demonstrate that disciplines are up- campus assets. to-date and to expand articulation to more in-state/out-of state/private four-year colleges/universities Create a college consensus Use information technology and Provide adequate office space for defining “completion.” learning analytics to assess college fulltime and part-time faculty. accountability measures, including student learning and Program Learning Outcomes. Expand campus dialog on student Ensure that critical technical outcomes services have zero downtime. 6 | P a g e FacilitiesMasterPlanUpdateSummary Project 1998 Facilities Master Parking Structure 3 1,350-car, four level (one level below ground) parking structure with tennis courts located on the roof and campus police facilities Swim Stadium renovation and modernization Swim Stadium and Fitness Center, D5 Parking Structure 4 1,000-car, five level (one below ground) parking structure Student Services (F5) and Administration Building (E1) In construction Renovation and addition to the Student Services and Administration buildings Student Center, G1 Remodel of existing building Humanities Center, E3 and E5 New Humanities building, existing Music buildings proposed to be demolished to accommodate new facility Performing and Fine Arts Complex and Gallery, S1, S2 and P2 Plant Facility P a g e |1 2004 Facilities Master Plan Update 1,900-car, six level parking structure 2009 Facilities Master Plan Update Swim Stadium renovation not proposed, Fitness Center modernization to occur at Men’s Gymnasium 1,600-car, four level parking structure with expanded footprint Fitness Center complete Project Completed on 1/26/09 A reduction of 155 parking spaces. 1,445-car parking structure, 5 levels (approx 52’) Revised in 2009 Facilities Master Plan Update in next row Project Completed on 6/12/12 In Construction Project Completed On 7/6/10 Project Completed On 7/1/11 (E3 AND E5 demolition occurred as part of the Student Success and Retention Center Student Services renovation and addition as planned. Administration building renovation and addition as planned No Change Complete 2012 Facilities Master Plan Update Project Completed on 4/1/09 Project completed On 2/3/11 Humanities building (Multi-Media Classroom Building) in construction: Buildings E3 and E5 to be demolished upon completion of construction Two new buildings to house the Art, Dance, Theater Arts and Music Departments Relocation of Humanities building, existing E3 and E5 buildings proposed to be demolished to accommodate new facility; Music building would remain Site reconfigured to accommodate three new buildings In construction Project Completed On 3/11/11 New Plant/Storage facility No Change Complete Project Completed On 9/14/07 FacilitiesMasterPlanUpdateSummary Project 1998 Facilities Master Technology Center, E7 New Technology Building Women’s Gymnasium Clock Tower P a g e |2 2004 Facilities Master Plan Update No Change 2009 Facilities Master Plan Update 2012 Facilities Master Plan Update Project completed in late 2004 Project completed Project completed Project completed On 11/30/10 Complete Rehabilitation of existing building Not Proposed No Change Complete 70’ clock tower In construction Central Plant N/A N/A Dr. Helen Miller Bailey Library, F3 Expansion and Modernization Eastern Boundary Surface Lot Pool Parking Structure/ Pool Lot, existing D7 and D7a Stadium Lot Not Proposed Not Proposed 3,520 gsf, 1-2 level approx. 21’) building that will house heating, cooling and electricity generating equipment for the campus Proposed in prior EIR update; Bid / Award 407-car surface lot Not Proposed Not Proposed Not Proposed 300-car 4 level (one below ground) parking structure Proposed as planned Not Proposed Not Proposed Not Proposed Not Proposed Not Proposed Football and Soccer Fields 2,200-car, three level (one below ground) parking structure with plant facility office and shops One full-sized field (for football or soccer) Not Proposed Proposed as planned in 2009 Women’s Athletic Field New women’s athletic field Not Proposed One full-sized field (for football or soccer), the B2 Bungalow complex will be removed to accommodate the new athletic facilities. Athletic field for multipurpose sports activities proposed east of the Women’s Softball Field, the F9 Bungalow complex will be removed to accommodate this new athletic field Project completed On 8/24/12 Proposed as planned in 2009 FacilitiesMasterPlanUpdateSummary Project 1998 Facilities Master Tennis Courts Proposed on rooftop of Parking Structure 3 Baseball Field Reorientation of baseball field to restore full outfield Reorientation no longer proposed, new lockers, dugouts and fence are proposed Campus Student Center/Bookstore Complex, existing F5 (formerly referred to as Student Services) design, consolidating Student Center and Bookstore operations Language Arts Building and Health Care Careers Building, G9 2004 Facilities Master Plan Update Not Proposed New lockers, dugouts and fencing project complete; New artificial turf playing surface and miscellaneous improvements P a g e |3 2009 Facilities Master Plan Update Tennis courts proposed east of the proposed football and soccer field in DSA Review Remodel of existing building Proposed as planned Revised plan proposes the demolition of the Existing Student Services F5 and the construction of a new 55,000 gsf, 3-level building (approx 50’) with LEED Expansion of existing Nursing building into Health Care Careers building, new Language Arts building, existing Facilities buildings to be demolished to accommodate new building Health Care Careers to be accommodated in the Math Science Complex (see below); Language Arts building not proposed, Existing Plant Facilities to remain with improvements Health Care Careers accommodated at a satellite location, separate environmental review prepared; Language Arts to be integrated into new Student Success and Retention Center Building (see below); Plant Facilities improvements complete 2012 Facilities Master Plan Update Not Proposed The new lockers, dugout and fencing were completed in September 2006. The new artificial turf, light poles and retaining wall will be completed in April 2013. Proposed as planned in 2009 The demolition of F5 will begin in mid-March 2013. Proposed completion is November 2014. Proposed as planned in 2009 Proposed as planned in 2009 FacilitiesMasterPlanUpdateSummary Project 1998 Facilities Master Vocational / N/A General Classroom Building, existing G9 Public Services Building 2004 Facilities Master Plan Update N/A Math and Science Complex, G5, G6, H5, H6, H7, G8 and H8 Classrooms G8 and H8 Modernization Consolidation of math and science facilities, seven building to be demolished to accommodate facility Proposed to be demolished as part of the Math and Sciences Complex Health Care Careers building part of plan Math and Science Complex, existing G5, G6, H5, H6, H7 Consolidation of math and science facilities, seven buildings to be demolished to accommodate the 140,000-gsf facility Proposed revision would include Health Care Careers building as part of this complex Transit Center Not Proposed Transportation center/bus terminal with six bus bays and a park-and ride facility Proposed to be demolished as part of the Math and Sciences Complex P a g e |4 2009 Facilities Master Plan Update 60,000 gsf, 3-level (approx. 50’) building with LEED design; the existing Nursing Building (G9) would be demolished to accommodate this new facility Revised in 2009 Facilities Master Plan Update (see below) Modernization to bring existing building up to current code and life safety standards. This 24,349 GSF modernization part of Math and Science Complex Revised plan proposes the demolition of 5 existing buildings and a reduction in gsf to 93,000 GSF (not including the renovation of G8 and H8. Health Care Careers Building accommodated at satellite location. Bid / Award 2012 Facilities Master Plan Update Proposed as planned in 2009 Revised to project below Proposed as planned in 2009; In construction, Proposed completion April 2016 Proposed as planned in 2009; In construction, proposed completion April 2016 Proposed as planned in 2009; in construction FacilitiesMasterPlanUpdateSummary P a g e |5 Project 1998 Facilities Master Language Arts Building/ Student Success and Retention Center, existing E3 and E5 N/A 2004 Facilities Master Plan Update N/A 2009 Facilities Master Plan Update Campus Marquees N/A N/A Weingart Stadium Increase seating capacity from 20,400 to 30,000, proposed at east and west ends of playing field Electrical and data systems upgrades Recommendations for improvements of electrical systems, which include power distribution, branch circuit panels, devices, lighting, communication/television, fire alarm and data systems (Section 9, p21) In construction Seating capacity revised to 20,000 to accommodate Americans with Disabilities Act (ADA) compliance standards. No new seating proposed Proposed as Academic Products planned Services Delivery Network Project (APSDN) 136,600 gsf, 5-level (approx. 74’) building with LEED that includes an open courtyard. The existing Business (E3), Classrooms (E5) and E6 Bungalows would be demolished to accommodate this new facility (3) campus electronic digital message information signs with 22- to -30-foot by 12-foot LightEmitting Diode (LED) display boards 2012 Facilities Master Plan Update Proposed as planned in 2009; in construction, proposed completion October 2014 Proposed as planned in 2009; in construction, proposed completion in June 2013. In construction Proceed as planned with electrical backup generators at E7 MDF, Student Success Datacenter, and Central Plant. FacilitiesMasterPlanUpdateSummary Project 1998 Facilities Master Landscape Frontage Road Revitalize the campus appearance by providing consistent and well maintained landscape entry along Avenida Cesar Chavez 2004 Facilities Master Plan Update P a g e |6 2009 Facilities Master Plan Update This project will provide a formal entry to the campus. The 120,000 square foot plaza will provide a gathering space for students outside of the new Student Services building and will provide a more accessible entry for disabled/handicapped students. 2012 Facilities Master Plan Update