1 Seminar at Case Western Reserve University, September 29, 2014 SSmartt Distribution Di t ib ti Systems: S t State‐of‐the‐Art and the Future Chen‐Ching Liu Boeing Distinguished Professor Washington State University (Also Professor, Professor University College Dublin) Research Sponsored by PNNL and Dept of Energy 2 Smart Grid Source: http://energy.gov/sites/prod/files/oeprod/DocumentsandMedia/Arshad_Mansoor.pdf 3 US Smart Grid Investment Grants (SGIGs) Federal SGIG Expenditures versus Plan • • • Total SGIG Expenditures by Type of Project Including the investments made by the recipients, the combined level of federal and recipient investment totals about $4 $4.6 6 billion billion, through March 31 31, 2012 ETS projects have installed more than 287 networked PMUs and a total of at least 800 networked PMUs will be installed at completion. AMI projects installed 10.8 million smart meters now and it will install up to 65 million smart meters by b 2015. Source: http://energy.gov/sites/prod/files/Smart%20Grid%20Investment%20Grant%20Program%20-%20Progress%20Report%20July%202012.pdf 4 Benefits of SGIGs Highlights • • • Electric Power Board of Chattanooga (EPB) is installing 1,500 automated circuit switches and sensors on 164 circuits. When 9 tornados ripped through communities in April of 2011, early in the project’s installation schedule, EPB used 123 smart switches that were in service to re‐route power, avoiding 250 truck rolls and saving customers thousands of hours of outage time. Talquin Electric Cooperative (TEC) in northern Florida deployed smart meters that have already produced annual savings of more than $500,000 by avoiding more than 13,000 truck rolls for service connections and disconnections and non‐payment problems. The system also improves outage management and enables TEC to send repair crews to the precise locations where faults occurred. Western Electricity Coordinating Council (WECC) synchrophasor project involves 18 transmission owners in 14 states and is installing 341 PMUs and 62 phasor data concentrators (PDC). WECC estimates that the application of these devices will enable ~100 100 MWs additional capacity on the California‐Oregon intertie. Source: http://energy.gov/sites/prod/files/Smart%20Grid%20Investment%20Grant%20Program%20-%20Progress%20Report%20July%202012.pdf 5 SGIGs on Distribution Automation • EDS involves deployment of technologies and systems for improving distribution system operations, including: (1) outage management with devices such as automated circuit switches and reclosers, and (2) voltage/volt‐ampere reactive (VAR) control with field devices such as automated capacitors, voltage regulators, and voltage sensors. Installed SGIG Automated Switches Avista Utilities, Utilities WA Spokane and Pullman ((WSU)) Smart Circuit Installed SGIG Automated Capacitors Project Cost: $40M Fed Funding: $20M Source: http://energy.gov/sites/prod/files/Smart%20Grid%20Investment%20Grant%20Program%20-%20Progress%20Report%20July%202012.pdf 6 SGIG Advanced Metering Infrastructure • AMI involves deployment of smart meters; communications networks to transmit data from the meters at 15, 30, or 60 minute intervals; and meter data management systems to receive,, store,, and process p data from the meters. These projects p j use smart meters to collect interval load data, while some projects also use smart meters to collect data on voltages and power quality. SGIG Smart Meter Deployment SGIG AMI Project Expenditures on Technologies and Systems Source: http://energy.gov/sites/prod/files/Smart%20Grid%20Investment%20Grant%20Program%20-%20Progress%20Report%20July%202012.pdf 7 Reliability Improvements • • 48 SGIGs are applying DA technologies to improve reliability: 42 deploying automated feeder switches (1 to > 1000’s of switches) – • System integration schemes (AMI/OMS/DMS/SCADA/GIS) – – – • Enables fault location,, isolation and service restoration functions 26 projects are applying distribution management systems 36 implementing AMI outage notification 22 deploying equipment health sensors Initial results from 4 Projects (1,250 feeders) ‐ April 1, 2011 through March 31, 2012 Source: http://tcipg.org/sites/tcipg.org/files/slides/2013_02-01_Arnold.pdf 8 Distribution System Restoration (DSR) • A smart grid application and an important objective of distribution automation. automation • Restore critical load during extreme events. • A typical multi‐objective, combinatorial problem with constraints, including topological and electrical constraints. Restore R t loads l d in i a secure andd efficient manner Selecting and sequencing a set of switching operations ti Reduce the duration of outages and improve reliability Distribution System Restoration 9 Basic DSR Strategies Strategies* Single Single & level‐2 Double Triple Double & level‐2 Self *KEPCO: Intelligent DA System 10 DSR Algorithm: Spanning Tree Search* Search • Restore maximum amount of load with the minimum number of switching operation. * J. Li, X.-Y. Ma, C.-C. Liu, and K. P. Schneider, "Distribution system restoration with microgrids using spanning tree search," IEEE Trans. Power Syst., Available online: http://ieeexplore.ieee.org/stamp/stamp.jsp?arnumber=06781027 11 Example – PNNL Test System Z15 Z28 Z25 Z29 Z31 F-a Z1 Z24 Z22 Z4 Z17 Z35 Z30 Z8 Z18 Z5 Z23 Z20 Z39 Z6 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z40 Z33 Z12 Z3 Z10 Z13 Z26 Z27 Z66 Z67 • FB-a Z34 Z21 Z32 Z36 Z11 T1 Z41 Z64 Z62 Z44 Z65 Z69 Z71 F-b Z55 Z68 Z37 Z57 Z75 Z48 Z70 Z58 T2 Z45 Z63 Z60 Z79 Z46 Z47 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 SubTransmission Node F-c Z81 Z104 Z102 Z84 Z116 Z115 Z110 Z88 Z98 Z97 Z85 T6 Z113 Z105 Z109 Z111 Z95 Z108 Z77 S Z103 Z100 Z119 Z86 Z87 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 Z90 Z92 Z112 Z101 Z89 Z106 Z107 • • Taxonomy “R3-12.47-2” is a prototypical unbalanced distribution feeder model for moderate urban areas, which is developed by Pacific Northwest National Laboratory (PNNL).* A fault occurs at zone Z110. Triple grouping restoration Z91 Z120 Z117 Fd F-d Z121 Z144 Z142 Z135 Z148 T4 Z149 Z145 T5 Z151 Z156 Z137 Z140 Z159 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z141 Z155 Z152 Z153 Z123 Z158 Z122 Z134 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Z160 Z132 Z131 Z133 Z157 Voltage Regulator * F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch Restoration Scheme •Open: 90-92, 90-92 96-89 •Close: 88-156(T4), 136120(T5), 45-90(T3) K. P. Schneider, Y. Chen, D. Engle, and D. Chassin, "A Taxonomy of North American Radial Distribution Feeders,“ Proc. IEEE PES Gen. Meet., 2009, pp. 1-6. 12 Distribution Automation (DA) • Distribution Management System (DMS) provides SCADA functions and other distribution system applications such as feeder restoration. Functions • Fault detection • Trouble call analysis • Network reconfiguration and restoration • Alarm processing • Voltage / VAR Control • Remote monitoring and control User Interface Mi i M Mini-Map M i i & Control Monitoring C l Alarm Operation p historyy Equipment Information GIS Map Switch & Line Symbol y This MMI software was developed by and used in KEPCO (Korean power utility) Feeder RTU LBS FRTU Feeder RTU RTU Controller Modem Space p Battery (24V) Transformer Power / Control Receptacle p This feeder RTU is manufactured by pnctech http://www.pnctech.co.kr 16 Service Restoration with DA (1) (1)* 1. Fault occurs 2. Open CB 3. Find fault 4. Isolation *KEPCO: Intelligent DA System 17 Service Restoration with DA (2) (2)* 5. Transfer outage area 6. Execute restoration plan 7. Field crew *KEPCO: Intelligent DA System 18 Self‐Healing Self Healing Technology Conventional Restoration Self-Healing Restoration F3 F5 F3 F5 F6 F6 F9 Peer to peer communication F2 Fault Current F2 Fault Current F10 DMS Control Center F7 F8 F9 F10 DMS Control Center F7 F4 F8 F4 • Fault isolation: Manual switching • Fault isolation: Automatic switching • Restoration time: Minutes to hours • Restoration time: Seconds to minutes • Outage duration: Long • Outage duration: Short • Customer costs: High • Customer costs: Low 19 Restoration Fault detection MAS based Service Restoration Lim, I.-H.; Sidhu, T.S.; Choi, M.-S.; Lee, S.-J.; Hong, S.; Lim, S.-I.; Lee, S.-W., "Design and Implementation of Multiagent-Based Distributed Restoration System in DAS," Power Delivery, IEEE Transactions on , vol.28, no.2, pp.585,593, April 2013 20 Resilience • Resilience: “..ability to prepare for and adapt to changing conditions diti and d withstand ith t d and d recover rapidly idl from f di disruptions..”* ti ”* • For distribution systems, resilience means the ability to withstand Blackout in Manhattan caused by Sandy major j disturbances. – Natural disasters: Earthquake, tsunami, hurricane, flood, forest fire ice storm fire, storm, etc. etc – Major events: • Superstorm Sandy, US, 2012 • East Japan earthquake, March 11, 2011 • Ice storm in Québec, Canada, 1998 * Source: Beth Buczynski, “What Hurricane Sandy Taught Us About America's Crumbling Infrastructure”, http://inhabitat.com/whathurricane-sandy-taught-us-about-americas-crumbling-infrastructure/ Presidential id i l Policy li Directive i i 21 – Critical i i l Infrastructure Security i andd Resilience ili [Online]. li Available: il bl http://www.whitehouse.gov/theh // hi h /h press-office/2013/02/12/presidential-policy-directive-critical-infrastructure-security-and-resil 21 Enhancing resilience in Distribution Systems • Nearly 90% of power outages occur in distribution systems.* • Natural disasters cause large‐area large area and extended outages for electricity services, resulting in huge losses. Downed utility poles and wires after hurricane Source: Rebecca Smith, “Getting 'Smart' on Outages”, http://online.wsj.com/news/articles/SB100014240529702047554045781 01591971017814 * Power poles pulled down by ice storms Source: “Thousands in the dark after ice storms cut power lines in US, Canada”, http://eyebuster.com/thousands-in-the-dark-after-ice-storms-cut-power-lines-inus-canada/ H. Farhangi, “The path of the smart grid,” IEEE Power & Energy Magazine, vol. 8, no. 1, pp. 18-28, Jan. 2010. 22 Damages to Distribution Grids by Superstorm Sandy Downed power lines and other debris litter the streets of Seaside Heights, N.J., on 31 October 2012, two days after Superstorm Sandy made landfall in the US.* The storm surge that accompanied Superstorm Sandy sent water rushing through the streets near a substation in Brooklyn, N.Y. Restoring a flooded substation takes much longer than restoring a downed power line because of the large amounts of water, rust, and mud left trapped in the structure.* * Source: Nicholas C. Abi-Samra, “One Year Later: Superstorm Sandy Underscores Need for a Resilient Grid”, IEEE Spectrum, http://spectrum.ieee.org/energy/the-smarter-grid/one-year-later-superstorm-sandy-underscores-need-for-a-resilient-grid 23 Differences Between Typical Outages and Catastrophic Outages Due to Extreme Events Typical Outages Catastrophic Outages • Single fault: In most cases, there is only • Multiple faults: Multiple electrical one faulted component. facilities are damaged. • Small amount of load and a small number of customers are involved. • Large amount of load and a large number of customers are out of services. • Power is available: Most power • Lack of power: Power sources can not sources are working and stay connected. access the load or are out of service. • T&D network remains intact: Outage loads are easily connected to sources. • T&D network damaged: Overhead lines, transformers, substations are damaged. • Easy to repair and restore • Difficult to repair and restore 24 Approaches to Resilient Distribution Systems* Systems • Construction – Improving design and construction standards, overhead distribution reinforcement, undergrounding, etc. • Maintenance – Online temperature monitoring, power system assessment, thermal imaging, vegetation management, etc. • Design and Operation – Smart Grid Techniques – – – – – – FFault l LLocation, i IIsolation, l i and d Service S i Restoration R i (FLISR) Integrated Distribution Management System (IDMS) Advanced Metering Infrastructure (AMI) Advanced Control and Communication System Distribution Operation Training Simulator Microgrids * G. Davis, A. F. Snyder, and J. Mader, "The future of Distribution System Resiliency," 2014 Clemson University Power Systems Conference (PSC), pp. 1-8, Mar. 2014. 25 Smart Grid Technique (3) Microgrids • Consisting of DERs, storage, and controllable load • Grid‐connected and islanded modes • Microgrids Mi id enhance h resilience ili off di distribution t ib ti systems t i two in t ways: – Providing reliable electricity supply for critical loads within microgrids.* – Supporting outage load recovery of distribution systems.** * C. Abbey, D. Cornforth, N. Hatziargyriou, K. Hirose, A. Kwasinski, E. Kyriakides, G. Platt, L. Reyes, and S. Suryanarayanan, “Powering through the storm,” IEEE Power & Energy Magazine, vol. 12, no. 3, pp. 67-76, May 2014. ** J. Li, X.-Y. Ma, C.-C. Liu, and K. P. Schneider, "Distribution system restoration with microgrids using spanning tree search," IEEE Trans. Power Syst., Available online: http://ieeexplore.ieee.org/stamp/stamp.jsp?arnumber=06781027. 26 Example – Microgrid Provides Reliable Electrical Supply to Critical Loads • A microgrid installed in Sendai, Japan* Japan • • • • East Japan earthquake, March 11, 2011 Accident at the Fukushima #1 nuclear power plant Power generators used to power university hospitals and welfare facilities. The supply of high-quality power such as dc and uninterruptible ac to load continued without interruption even immediately after power was lost to the rest of Sendai. Source: Marianne Lavelle, “Japan Battles to Avert Nuclear Power Plant Disaster”, http://news.nationalgeographic.com /news/energy/2011/03/110314j japan-nuclear-power-plant-disaster/ l l t di t / * C. Abbey, D. Cornforth, N. Hatziargyriou, K. Hirose, A. Kwasinski, E. Kyriakides, G. Platt, L. Reyes, and S. Suryanarayanan, “Powering through the storm,” IEEE Power & Energy Magazine, vol. 12, no. 3, pp. 67-76, May 2014. 27 Example (2) – Microgrid Supports Fast Recovery of Distribution Systems • One‐line diagram of Pullman‐WSU System 29 13 1 4 SPU121 48 34 37 (Root) 7 35 30 41 32 12 39 49 14 City Hall & Police Station 43 21 22 15 16 23 24 27 25 26 SPU122 5 40 SPU123 Hospital 3 18 31 36 42 SPU124 6 8 10 51 11 SPU125 52 G3 2.1 MW G2 1.1 MW 38 50 9 17 20 19 G1 1.1 MW 2 SPU Substation 46 45 33 44 47 28 WSU Microgrid Load Sections Normally Closed Switch Normally Open Switch 28 Example (2) – Microgrid Supports Fast Recovery of Distribution Systems (Conti.) • Scenario Description – A severe event happened in the South Pullman 115kV Substation. Substation – As a result, all 5 feeders served by the substation are out of service. • Feeders: SPU121, SPU122, SPU123, SPU124, SPU125 • Critical loads: Hospital, City Hall, Courthouse and Police Station – No source in the Avista system can be used for restoration. restoration – WSU generators will be used to restore critical loads. 29 Example (2) – Microgrid Supports Fast Recovery of Distribution Systems (Conti.) • Spanning Tree Search algorithm is applied to find the restoration paths from DERs to critical loads. 29 SPU121 13 48 34 37 35 30 41 32 39 SPU122 SPU123 14 49 10 22 15 16 17 36 23 24 27 25 26 G3 2.1 MW G2 1.1 MW 38 50 51 21 18 31 Hospital SPU124 City Hall & Police Station 43 40 9 Critical Load 42 Critical Load 20 19 G1 1.1 1 1 MW Source SPU125 11 52 46 45 33 44 47 28 WSU Mi Microgrid id 30 Example (2) – Microgrid Supports Fast Recovery of Distribution Systems (Conti.) • Restoration Path: G3 17 19 20 34 37 41 32 39 42 36 38 40 City Hall, Courthouse, Police Station 29 SPU121 13 48 34 37 35 30 41 32 39 SPU122 SPU123 14 49 43 40 9 SPU125 10 51 11 52 22 15 16 17 18 31 36 45 33 24 27 G3, a diesel ggenerator, is used to pick up critical loads, i.e., City Hall, Courthouse, Police Station and Hospital. G3 2.1 MW 42 20 46 23 G2 1.1 MW 38 50 Hospital SPU124 City Hall, Courthouse & Police Station 21 44 47 19 G1 1.1 MW 28 Hospital 25 26 WSU Microgrid 31 Example (2) – Microgrid Supports Fast Recovery of Distribution Systems (Conti.) • Validation by GridLAB‐D GridLAB D Power Flow G3 17 19 20 34 37 41 32 39 42 36 38 40 City Hall, Courthouse, Police Station Hospital 32 Microgrids Enhance Restoration Capability • Generation resources and control capabilities of microgrids enhance fast recovery of distribution systems. • Grid‐connected mode and i l d mode. isolated d • When a blackout occurs, Mi Microgrid id microgrids i id can be b controlled t ll d to provide an efficient DSR strategy to reduce the restoration time of the Restoration schemes considering distribution system. DERs and Microgrids g 33 Integrate Microgrids into DSR Algorithm • Microgrids are modeled as virtual feeders • Generation limits of DERs are formulated as electrical constraints of the distribution feeders. • The island configuration Microgrid Virtual Feeder 9 14 15 16 17 18 7 F2 8 F3 of the microgrid g can be 13 19 modeled as a supplemental 1 2 6 23 20 F4 5 21 topology constraint of the 12 22 4 F5 d distribution b system. 11 10 3 F1 Load Node Closed Switch (branch) Open Switch (branch) 34 PNNL Test System With Microgrids Z15 Z28 Z31 F-aa F Z1 Z24 Z22 Z4 Z30 Z8 Z18 Z40 Z33 Z12 Z3 M Z17 Z35 Microgrid 1 Z25 Z29 Z20 Z5 Z23 Z6 Z39 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z13 Z10 Z26 Z27 FB-a Z34 Z21 Z32 Z36 Z11 T1 Z71 F-b Z41 Z64 Z62 Z55 Z68 Z37 Z75 Z44 Z70 Z48 Z58 Z69 Z65 Z57 Z60 Z45 Z63 Z46 M Z79 Z47 Microgrid 2 T2 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 Z66 Z67 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 S SubTransmission Node Z81 Z104 Z102 Z116 Z115 Z111 F-c Z95 Z108 Z77 Z110 Z84 Z88 Z98 Z97 Z100 Z119 Z86 Z87 Z85 T6 M Z103 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 Z89 Z92 Z112 Z101 Microgrid 3 Z113 Z109 Z105 Z90 Z106 Z107 Z91 Z120 Z117 Z151 F-d Z121 Z144 Z142 Z135 Z148 T4 Z156 Z149 Z145 Z137 Z140 Z124 Z150 Z128 Z138 Z125 Z143 Z141 Z155 Z152 Z126 T5 Z159 Z127 Z139 Z153 Z123 Z158 Z122 Z134 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Microgrid 4 M Z160 Z132 Z131 Z133 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch M Microgrid 35 Example • A fault occurs at zone Z43 Z15 Z28 Z29 Z31 F-a Z1 Z24 Z22 Z4 Z30 Z8 Z18 Z40 Z33 Z12 Z3 M Z17 Z35 Microgrid 1 Z25 Z20 Z5 Z23 Z6 Z39 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z13 Z10 Z26 Z27 FB-a Z34 Z21 Z32 Z36 Z11 T1 Z71 F-b Z41 Z64 Z62 Z55 Z68 Z37 Z75 Z44 Z70 Z48 Z58 Z69 Z65 Z57 Z60 Z79 Z46 Z47 Z45 Z63 Microgrid 2 T2 M Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 Z66 Restoration Scheme •Close: 73-Microgrid 2 Z67 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 SubTransmission Node Z95 Z108 Z77 S T6 Microgrid 3 Z113 Z109 Z105 Z97 Z100 Z119 Z86 Z87 M Z111 F-c Z81 Z104 Z102 Z116 Z115 Z110 Z84 Z88 Z98 Z85 Z103 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 Z92 Z112 Z101 Z89 Z90 Z106 Z107 Z91 Z120 Z117 T4 Z149 F-d Z121 Z144 Z142 Z135 Z148 T5 Z145 Z151 Z156 Z137 Z140 Z159 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z141 Z155 Z152 Z153 Z123 Z158 Z122 Z134 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Microgrid 4 M Z160 Z132 Z131 Z133 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch M Microgrid • Without Microgrid 2, zone Z73 cannot be restored! 36 Restoration with/without Microgrids • Microgrid Enhance Restoration Capability – Using the capability of microgrids to pick up more interrupted load (Scenario 1 & 2) – Microgrids reduce the number of switching operations during restoration (Scenario 3) Scenario # Fault Location Switching Operations without Microgrids Switching Operations with Microgrids 1 Zone Z43 ‐‐‐ Close: 73‐Microgrid2 2 Zone Z139 Open: 46‐47, 96‐89 Close: 136‐120, 53‐96, 45‐90 Partial Restoration, 315.04 kVA load should be shed at F‐b Open:50‐43, 90‐92 Close: 45‐90, 73‐Microgrid2, 136‐120 3 Zone Z23 Open: 49‐50, 90‐92 Close: 78‐9, 53‐96, 136‐120 Close: 39‐Microgrid1 37 Improvement in Reliability • SAIDI, SAIDI SAIFI and Outage Cost are calculated. calculated * Index Without Microgrids With Microgrids Improvement SAIDI (minute/year) 196.54 182.64 7.07% SAIFI (/year) 0.7800 0.7800 0 % ** Outage Cost (k$/year) 3729.8 3426.5 8.13% * Assume that the permanent failure rate for each zone is 0 0.02, 02 the mean time to operate a (manual) switch is 90 minutes, and the cost for outage load is $1 per kW per minute, respectively. ** In order to improve SAIFI, remote-controlled ability should be added. 38 Enhance Restoration Capability by Adding Remote Control Functions • A remote‐controlled switch (RCS) can be operated by a distribution system operator. A manual switch is operated by the field crew crew. • Installing RCSs enhances restoration capability of a distribution system. 39 Restoration Scheme Without RCSs • A fault occurs at zone Z99 • Mean time to operate a manual switch is assumed to be 60 minutes Z15 Z28 Z25 Z29 Z31 F-a Z1 Z24 Z22 Z4 Z17 Z35 Z30 Z8 Z18 Z5 Z23 Z20 Z39 Z6 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z40 Z33 Z12 Z3 Z10 Z13 Z26 Z27 Z66 Z67 FB-a Z34 Z21 Z32 Z36 Z11 T1 Z41 Z64 Z62 Z44 Z70 Z65 Z69 Z57 Z75 Z71 F-b Z55 Z68 Z37 Z48 Z58 T2 Z45 Z63 Z60 Z79 Z46 Z47 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 Z77 S SubTransmission Node Z111 F-c Z81 Z104 Z102 Z84 Z95 Z108 Z116 Z115 Z110 Z88 Z98 Z109 Z105 Z97 Z100 Z85 Z103 Z86 T6 Z113 Z119 Z87 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 CL1 F-d Z121 Z144 Z112 Z101 Z142 Z117 Z135 Z148 T4 Z149 Z145 Z89 Z92 CL3 Z156 Z137 Z140 Z159 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z141 Z155 Z152 Z106 Z107 Z91 Z134 CL2 Z123 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Z160 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Critical Load Outage Time (min) CL1 180 CL2 300 CL3 360 Z153 Z158 Z122 Z90 Z120 T5 Z151 Recovery Process • Open “87-99” and “99-82” to isolate Z99; • Reclose Re l e “FB-c” “FB ” to t restore et e loads upstream Z99; • Open “90-92” and close “T3” and “T5” to restore loads downstream Z99 in two groups. Tie Switch Z132 Z131 Z133 40 Restoration Scheme With RCSs • A fault occurs at zone Z99 • Mean time to operate a manual switch is assumed to be 60 minutes • Mean time to operate a RCS is assumed to be 1 minute Z31 Z25 F-a Z1 Z24 Z22 Z4 Z17 Z35 Z30 Z18 Z8 Z5 Z23 Recovery Process Z15 Z28 Z29 Z20 Z39 Z6 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z40 Z33 Z12 Z3 Z10 Z13 Z26 Z27 Z66 Z67 FB-a Z34 Z21 Z32 Z36 Z11 T1 Z71 F-b Z41 Z64 Z62 Z44 Z55 Z68 Z37 Z75 Z70 Z48 Z58 Z69 Z65 Z57 Z60 Z45 Z63 T2 Z46 Z79 Z47 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 Z77 S SubTransmission Node F-c Z81 Z104 Z102 Z84 Z116 Z115 Z110 Z88 Z98 Z97 Z85 T6 Z113 Z105 Z109 Z111 Z95 Z108 Z103 Z100 Z119 Z86 Z87 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 CL1 Z117 Z151 F-d Z121 Z144 Z112 Z101 Z142 Z156 Z135 Z148 T4 Z149 Z145 Z137 Z140 Z124 Z150 Z128 Z138 Z125 Z143 Z141 Z155 Z152 Z126 Z89 Z92 CL3 Z127 Z139 Z91 Z134 CL2 Z153 Z123 Z158 Z122 Z106 Z107 Z120 T5 Z159 Z90 Z136 Z129 Z130 Z160 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie Switch Critical Load Outage Time (min) CL1 3 CL2 5 CL3 6 Z146 Z147 FB-d Z154 • Open “110-88” and “89-90” to separate critical loads from faulted zone; • Reclose “FB-c” to restore CL1; • Open “90-92” and close “T3” and “T5” to restore CL2 and CL3; • Open “87-99” and “99-82” and close “110-88” and “89-90” to restore other loads. Z132 Z131 Z133 41 DA: Adding Remote Remote‐Controlled Controlled Ability Z15 Z28 Z29 Z31 F-a Z1 Z24 Z22 Z4 Z30 Z8 Z18 Z40 Z33 Z12 Z3 M Z17 Z35 Microgrid 1 Z25 Z20 Z5 Z23 Z6 Z39 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z13 Z10 Z26 Z27 FB-a Z34 Z21 Z32 Z36 Z11 T1 Z71 Fb F-b Z41 41 Z64 64 Z62 62 Z55 Z68 Z37 Z75 Z44 Z70 Z48 Z58 Z69 Z65 Z57 Z60 Z45 Z63 Z46 M Z79 Z47 4 Microgrid 2 T2 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 Z66 Z67 FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 Z77 S SubT Transmission i i Node Z111 F-c Z81 Z104 Z102 Z95 Z108 Z116 Z115 Z110 Z84 Z88 Z98 Z105 Z97 Z100 Z119 Z86 Z87 Z85 T6 M Z103 Z83 Z93 Z118 Z99 Z82 Z94 Z96 FB-c Z114 Z89 Z92 Z112 Z101 Microgrid 3 Z113 Z109 Z90 Z106 Z107 Z91 Z120 Z117 F-d Z121 Z144 Z142 Z135 Z148 T4 Z149 Z145 T5 Z151 Z156 Z137 Z140 Z159 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z141 Z155 Z152 Z153 Z123 Z158 Z122 Z134 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Microgrid 4 M Z160 Z132 Z131 Z133 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch M Microgrid Remote-Controlled Switches (RCSs) •44 ffeeder d bbreakers k •5 normally closed sectionalizing switches •3 normally closed tie switches it h •3 microgrid switches •Marked in red color. 42 Example – PNNL Test System with RCSs Z15 Z28 Z25 Z29 Z31 F-a Z1 Z24 Z22 Z4 Z17 Z35 Z30 Z8 Z18 Z20 Z5 Z23 Z6 Z39 Z7 Z38 Z19 Z2 Z14 Z16 Z9 Z40 Z33 Z12 Z3 Z10 • Z13 Z26 Z27 FB-a Z34 Z21 Z32 Z36 Z71 F-b Z41 Z64 Z62 Z44 Z55 Z68 Z37 T1 Z75 Z70 Z48 Z58 • Z11 Z69 Z65 Z57 Z60 Z45 Z63 T2 Z46 Z79 Z47 Z78 Z59 Z42 Z54 Z49 Z56 Z80 Z73 Z52 Z43 Z50 Z66 Z67 • FB-b Z74 Z61 T3 Z72 Z76 Z51 Z53 T7 S S b SubTransmission Node Z111 Z81 Z104 Z102 Z84 Z116 Z115 Z110 Z88 Z98 Z97 Z85 T6 Z113 Z105 Z109 F-c Z95 Z108 Z77 Z103 Z100 Z119 Z86 Z87 Z82 Z94 Z96 FB-c Z114 CL1 F-d Z121 Z144 Z112 Z101 Z142 Z117 Z135 Z148 T4 Z149 Z145 Z89 Z92 CL3 Z156 Z137 Z140 Z159 Z124 Z150 Z128 Z138 Z125 Z143 Z126 Z127 Z139 Z141 Z155 Z152 Z106 Z107 Z91 Z134 CL2 • Z153 Z123 Z158 Z122 Z90 Z120 T5 Z151 • Z83 Z93 Z118 Z99 Z136 Z129 Z130 Z146 Z147 FB-d Z154 Z160 Z132 Z131 Z133 Z157 Voltage Regulator F-a Feeder Id Load Zone Feeder Breaker Sectionalizing Switch Tie/Microgrid Switch 4 out of 4 feeder b k are RCS breakers RCSs 12 out of 156 normally closed sectionalizing switches i h are RCSs RCS 7 out of 7 normally closed tie switches are RCSs. RCS are marked RCSs k d in i red color. • 3 critical loads ((CLs)) in Feeder F-c. CLs are marked in green color. 43 Improvement in Reliability by DA • SAIDI, SAIDI SAIFI and Outage Cost are calculated. calculated * Index Without RCSs With RCSs Improvement SAIDI (minute/year) 182.64 73.74 59.63% SAIFI (/year) 0.7800 0.7081 9.22% Outage Cost (k$/year) 3426.5 1230.6 64.09% * Assume that the permanent failure rate for each zone is 0 0.02, 02 the mean time to operate a manual/remote-controlled switch is 90/1 minutes, and the cost for outage load is $1 per kW per minute, respectively. 44 R&D Need: Microgrids Increase Resilience • Smart grid applications enhance resilience of distribution systems – DG/DER DG/DER, Microgrid resources survivability must be high – Access through DERs to critical loads must be maintained Mi Microgrid id Source: Jesse Jenkins, “The Smart Grid and Natural Disasters”, http://theenergycollective.com/dickdeblasio/155946/smart-grid-andnatural-disasters Restoration schemes considering DERs and Microgrids 45 Future Needs • Simulation tools: Simulate response of distribution systems during extreme events • Restoration strategy gy in extreme events – Multiple faults, large amount of outage load, lack of power sources, T&D network damaged • DA: Optimal placement of AMIs and RCSs – Consider both functional requirements and cost‐benefits. • DERs/Microgrids supporting distribution Restoration during extreme events.