UFC 3-701-01 March 2011 ED UNIFIED FACILITIES CRITERIA (UFC) C AN C EL L DoD FACILITIES PRICING GUIDE FOR FY 2011 APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED UFC 3-701-01 March 2011 UNIFIED FACILITIES CRITERIA (UFC) DoD FACILITIES PRICING GUIDE FOR FY 2011 ED Any copyrighted material included in this UFC is identified at its point of use. Use of the copyrighted material apart from this UFC must have the permission of the copyright holder. U.S. ARMY CORPS OF ENGINEERS NAVAL FACILITIES ENGINEERING COMMAND (Preparing Activity) AIR FORCE CIVIL ENGINEER SUPPORT AGENCY EL L OFFICE OF THE DEPUTY UNDER SECRETARY OF DEFENSE FOR INSTALLATIONS AND ENVIRONMENT Record of Changes (changes are indicated by \1\ ... /1/) Date Location C AN C Change No. This UFC supersedes UFC 3-701-01, dated June 2010. 2 UFC 3-701-01 March 2011 FOREWORD ED The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD(AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of the United States is also governed by Status of Forces Agreements (SOFA), Host Nation Funded Construction Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA.) Therefore, the acquisition team must ensure compliance with the more stringent of the UFC, the SOFA, the HNFA, and the BIA, as applicable. EL L UFC are living documents and will be periodically reviewed, updated, and made available to users as part of the Services’ responsibility for providing technical criteria for military construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities Engineering Command (NAVFAC), and Air Force Center for Engineering and the Environment (AFCEE) are responsible for administration of the UFC system. Defense agencies should contact the preparing service for document interpretation and improvements. Technical content of UFC is the responsibility of the cognizant DoD working group. Recommended changes with supporting rationale should be sent to the respective service proponent office by the following electronic form: Criteria Change Request (CCR). The form is also accessible from the Internet sites listed below. UFC are effective upon issuance and are distributed only in electronic media from the following source: • Whole Building Design Guide web site http://dod.wbdg.org/. AN C Hard copies of UFC printed from electronic media should be checked against the current electronic version prior to use to ensure that they are current. JAMES C. DALTON, P.E. C Chief, Engineering and Construction U.S. Army Corps of Engineers TERRY G. EDWARDS, P.E. Director, Air Force Center for Engineering and the Environment Department of the Air Force JOSEPH E. GOTT, P.E. Chief Engineer Naval Facilities Engineering Command MICHAEL McANDREW Director, Facility Investment and Management Office of the Deputy Under Secretary of Defense (Installations and Environment) 3 UFC 3-701-01 March 2011 UNIFIED FACILITIES CRITERIA (UFC) REVISION SUMMARY SHEET Subject: Cancels: UFC 3-701-01 UFC 3-701-01, dated June 2010 Description of revision: This revision: ED Updates all UFC tables (listed below) for FY 2011 using pricing data available in January 2011. C AN C EL L Table 2: Facility Unit Costs for Military Construction ...................................................... 3 Table 3: Unit Costs for DoD Facility Cost Models ........................................................ 12 Table 4-1: Area Cost Factors ....................................................................................... 32 Table 4-2: Military Construction Escalation Rates ........................................................ 46 Table 4-3: PRV Escalation Rates ................................................................................. 47 Table 4-4: Operation and Maintenance Escalation Rates ............................................ 48 i UFC 3-701-01 March 2011 TABLE OF CONTENTS CHAPTER 1 INTRODUCTION........................................................................................ 1 1-1 SCOPE .................................................................................................................. 1 1-1.1 Chapter 2: Unit Costs for Military Construction Projects ............................ 1 1-1.2 Chapter 3: Unit Costs for DoD Facilities Cost Models ................................. 1 1-1.3 Chapter 4: Cost Adjustment Factors ............................................................. 1 1-2 DATA TABLES ..................................................................................................... 1 1-3 PROPONENT........................................................................................................ 1 2-1 2-2 ED CHAPTER 2 UNIT COSTS FOR MILITARY CONSTRUCTION PROJECTS.................. 2 OVERVIEW ........................................................................................................... 2 FACILITY UNIT COST TABLE ............................................................................. 2 CHAPTER 3 UNIT COSTS FOR DOD FACILITIES COST MODELS ............................. 7 C EL L OVERVIEW ........................................................................................................... 7 REPLACEMENT UNIT COSTS ............................................................................ 7 Definition........................................................................................................... 7 Use of Replacement Unit Costs ...................................................................... 7 SUSTAINMENT UNIT COSTS .............................................................................. 8 Definition........................................................................................................... 8 Use of Sustainment Unit Costs ....................................................................... 9 MODERNIZATION FACTORS .............................................................................. 9 Definitions......................................................................................................... 9 Use of Modernization Factors ......................................................................... 9 OPERATION UNIT COSTS .................................................................................. 9 Definition........................................................................................................... 9 Use of Operation Unit Costs ......................................................................... 10 UNIT COST HEIRARCHY ................................................................................... 10 REVISING UNIT COSTS..................................................................................... 10 AN 3-1 3-2 3-2.1 3-2.2 3-3 3-3.1 3-3.2 3-4 3-4.1 3-4.2 3-5 3-5.1 3-5.2 3-6 3-7 CHAPTER 4 COST ADJUSTMENT FACTORS ............................................................ 30 C 4-1 LOCATION ADJUSTMENTS .............................................................................. 30 4-1.1 Area Cost Factors .......................................................................................... 32 4-2 ESCALATION ..................................................................................................... 45 4-2.1 Military Construction ..................................................................................... 45 4-2.2 Plant Replacement Value Escalation Rates ................................................. 46 4-2.3 Facilities Sustainment and Operation .......................................................... 47 TABLES Table 2: Facility Unit Costs for Military Construction ...................................................... 3 Table 3: Unit Costs for DoD Facility Cost Models ........................................................ 12 Table 4-1: Area Cost Factors ....................................................................................... 32 Table 4-2: Military Construction Escalation Rates ........................................................ 46 Table 4-3: PRV Escalation Rates ................................................................................. 47 Table 4-4: Operation and Maintenance Escalation Rates ............................................ 48 ii UFC 3-701-01 March 2011 CHAPTER 1 INTRODUCTION 1-1 SCOPE The DoD Facilities Pricing Guide supports a spectrum of facility planning, investment, and analysis needs. This version of the Guide reflects updated cost and pricing data for FY 2011 intended to support preparation of the DoD budget for FY 2013. It includes reference information organized into three chapters: 1-1.1 Chapter 2: Unit Costs for Military Construction Projects Chapter 3: Unit Costs for DoD Facilities Cost Models EL L 1-1.2 ED Chapter 2 provides facility unit cost data for selected DoD facility types in support of preparing Military Construction (MILCON) project documentation (DD Forms 1391) and other project-level estimates in accordance with UFC 3-700-01A, “Programming Cost Estimates for Military Construction” (as may be superseded). Chapter 3 provides unit costs in support of DoD facilities cost models. These unit costs are based upon the reported average DoD facility size or an established benchmark size, as annotated for each Facility Analysis Category (FAC) in the DoD Real Property Classification System (published separately). These unit costs are intended for macrolevel analysis and planning rather than individual facilities or projects. 1-1.3 Chapter 4: Cost Adjustment Factors DATA TABLES AN 1-2 C Chapter 4 provides cost adjustment factors for location and future price escalation that are applicable to the base unit costs in both chapters 2 and 3. For the convenience of UFC users, all data tables in this UFC are available as part of the supporting documentation download file accompanying this UFC on the Whole Building Design Guide web site: http://www.wbdg.org/ccb/DOD/UFC/ARCHIVES/ufc_3_701_01_FY11supplement.zip. PROPONENT C 1-3 The Office of the Deputy Under Secretary of Defense for Installations and Environment is the proponent for the Facilities Pricing Guide. Recommendations from users toward improving the usefulness of this reference are welcome. 1 UFC 3-701-01 March 2011 CHAPTER 2 UNIT COSTS FOR MILITARY CONSTRUCTION PROJECTS 2-1 OVERVIEW 2-2 FACILITY UNIT COST TABLE ED The facility unit costs in this chapter apply to preparation of programming-level cost estimates for constructing military facilities in accordance with the methodology described in UFC 3-700-01A. As explained in UFC 3-700-01A, these unit costs are not to limit more detailed cost estimates. For the convenience of UFC users, all data tables in this UFC are available as part of the supporting documentation download file accompanying this UFC on the Whole Building Design Guide web site: http://www.wbdg.org/ccb/DOD/UFC/ARCHIVES/ufc_3_701_01_FY11supplement.zip. EL L Table 2 provides facility unit costs for various DoD facility types in dollars per square meter ($/m2) and equivalent English unit cost data in dollars per square foot ($/SF) as of October 2010. The listed facility types represent those facilities most frequently constructed by the Military Services. The unit costs in Table 2 are average unit costs from actual project awards since September 2007 for Army, Navy, Air Force, and (for medical projects) TRICARE Management Activity from the HII unit cost database. The database includes new construction projects in the U.S.; it does not include renovation or add/alter projects, or projects outside of the U.S. (other than Family Housing). minimum antiterrorism design features (reference UFC 4-010-01, “DoD Minimum Antiterrorism Standards for Buildings”) meeting Table B-1 standoff distance requirements AN • C The unit costs include the following: • an average sales tax • Sustainable Design features for criteria in effect from September, 2007 thru September, 2009. C The unit costs do not include the following: • gross receipt taxes or gross excise taxes. (Arizona, Mississippi, Washington, New Mexico, Delaware, Hawaii, Illinois, Ohio, Pennsylvania, Texas, Michigan, Kentucky, and the District of Columbia have varying amounts of gross receipt taxes in lieu of a sales tax.)“Acts of God” or unusual market conditions Applicable adjustments for gross receipt or excise taxes, Acts of God, and unusual market conditions shall be documented and added to the cost estimate. Various qualifications and restrictions apply to the unit costs in Table 2. These are specified in the leading notes. 2 UFC 3-701-01 March 2011 Table 2: Facility Unit Costs for Military Construction General: Facility unit costs include installed (built-in) building equipment and furnishings normally funded with MILCON funds. Unit costs are for primary facilities only and do not include the following: supporting facility costs • equipment acquired with other fund sources, including pre-wired workstations or furnishing systems, intrusion detection systems • sustainable design and construction features mandated since September, 2009; these will be estimated separately in accordance with component guidelines and documented on DD form 1391 per DoD Instruction 4170.11, Installation Energy Management, and applicable component guidance • state imposed gross receipts taxes and general excise taxes • special foundations, evidence-based design, intrusion detection system installation, base exterior architectural preservation guidelines • enhanced Anti-Terrorism (AT) standards (exceeding the minimum in UFC 401-01, or when minimum standoff distances [Table B-1] are not achieved) • Progressive Collapse premiums, except for the following specific facility types: Inpatient Hospital/MED Center, Primary Care Clinic (Attached), Major Command Headquarters Building, Barracks/Dormitory, and Recruit Open Bay (Barracks). • construction contingency allowances • supervision, inspection, and overhead (SIOH) • design costs (design-build contracts) • construction cost growth resulting from user changes, unforeseen site conditions, or contract document errors and omissions, unusual market conditions (for example material shortages, labor shortages, or Acts of God) AN C EL L ED • C Medical facilities: Unit costs include category A and category B equipment, but do not include category E and category F equipment costs. Barracks and Unaccompanied Officers Quarters: Unit costs do not include freestanding kitchen equipment. In addition to using the size adjustment factors, use the project size adjustment factors in UFC 3-700-01A. Child Development Centers: Unit costs do not include free-standing food service equipment or playground area and equipment. Family housing: Unit costs are based upon gross area and include sprinkler systems or fire-rated construction. Unit costs include post-award design costs. 3 UFC 3-701-01 March 2011 Reserve facilities other than reserve centers: Use the unit cost of the appropriate facility type. Costs are independent of the acquisition strategy and are not specific to any single construction type. FACILITY TYPE Oct 2010 unit cost (GUC) (gross m2) ($/m2) Reference size (gross SF) Oct 2010 unit cost ($/SF) AN C Std. Dev / GUC (Pct) N (Number of Projects) 6,220 2,881 23,000 46,000 578 268 113 91 20% 34% 3 7 VM* 2,690 *** 121,830 3,004 VF** 29,000 *** 37,134 279 12,588 83 34% 30% 1 7 5 2,320 3,340 1,970 2,314 35,000 36,000 183 215 49 52 27% 24% 120 34 2,970 6,500 2,276 2,065 32,000 70,000 211 192 18 26 9% 14% 60 21 4,460 1,907 48,000 177 49 28% 91 7,430 5,580 3,250 2,360 2,543 3,007 80,000 60,000 35,000 219 236 279 68 75 45 31% 32% 16% 17 5 3 2,790 2,140 1,860 740 1,860 2,092 1,851 1,755 2,156 2,466 30,000 23,000 20,000 8,000 24,000 194 172 163 200 229 43 49 37 50 35 22% 29% 23% 25% 15% 98 15 5 5 5 2,790 *** *** 1,121 30,000 *** *** 104 31 30% 26 13,940 917 150,000 85 36 42% 7 370 3,005 4,000 279 84 30% 4 740 650 2,616 2,016 8,000 7,000 243 187 53 72 22% 38% 6 18 NA 4,499 NA 418 73 17% 4 C OPERATIONS BUILDINGS: GENERAL PURPOSE SQUADRON / BATTALION APPLIED INSTRUCTION BUILDINGS: GENERAL INSTRUCTION HIGH TECH/SIMULATION TRAINING (High Bay) RESERVE CENTER (see note above) HANGARS: MAINTENANCE / GENERAL PURPOSE HIGH BAY MAINTENANCE CORROSION CONTROL SHOPS: VEHICLE MAINTENANCE AIRCRAFT AVIONICS INSTALLATION MAINTENANCE PARACHUTE AND DINGHY AIRCRAFT MACHINE SHOP STORAGE FACILITIES: COLD STORAGE PROCESSING COLD STORAGE WAREHOUSE GENERAL PURPOSE WAREHOUSE – LOW BAY GENERAL PURPOSE WAREHOUSE – HIGH BAY GENERAL PURPOSE MAGAZINE W/O CRANE HIGH EXPLOSIVE MAGAZINE ARMORY MEDICAL FACILITIES (see note above): INPATIENT HOSPITAL / MED CENTER Standard Deviation $/SF 2,140 4,270 EL L COMMUNICATIONS BUILDINGS: SATELLITE COMMUNICATIONS CENTER INTELLIGENCE COMMUNICATION CENTER AIRCRAFT OPERATIONS BUILDINGS: WITHOUT TOWER CONTROL TOWER (STAND-ALONE) AIRFIELD FIRE AND RESCUE STATION (does not include central alarm system) Reference size ED Unit Costs for Military Construction 4 UFC 3-701-01 March 2011 Unit Costs for Military Construction FACILITY TYPE Oct 2010 unit cost (GUC) (gross m2) ($/m2) Std. Dev / GUC (Pct) N (Number of Projects) 55 19% 11 4,047 3,455 15,000 160,000 376 321 78 50 21% 16% 7 7 13,010 2,648 140,000 246 25 10% 3 4,920 1,950 2,095 3,658 53,000 23,000 195 340 42 91 22% 27% 45 6 3,720 2,504 26,000 233 49 21% 6 31,590 2,552 340,000 237 71 30% 10 DENTAL CLINIC MEDICAL CLINIC (attached to HOSPITAL / MED CENTER) 1,390 13,940 MEDICAL CLINIC (LARGE, FREE STANDING>60,000 GSF) EL L MAJOR COMMAND HEADQUARTERS BUILDING UNACCOMPANIED HOUSING: BARRACKS / DORMITORY (does not include kitchenette equipment) Standard Deviation $/SF 286 3,079 INSTALLATION/REGIONAL COMMAND HEADQUARTERS BUILDING (gross SF) Oct 2010 unit cost ($/SF) 30,000 2,790 ADMINISTRATIVE FACILITIES: MULTI-PURPOSE ADMIN DATA PROCESSING AREA FACILITY (includes admin and storage) Reference size ED MEDICAL CLINIC (SMALL, FREE STANDING<60,000 GSF) Reference size 9,570 2,166 103,000 201 59 29% 94 RECRUIT OPEN BAY OFFICERS QUARTERS (does not include kitchenette equipment) 7,990 7,060 1,785 2,349 86,000 76,000 166 218 35 8 21% 4% 8 3 DINING FACILITY (includes kitchen equipment and installation) 2,000 3,167 30,000 294 83 28% 38 5,480 1,948 59,000 181 29 16% 4 NA NA 1,138 1,685 NA NA 106 157 34 27 32% 17% 28 6 2,320 2,575 25,000 239 62 26% 43 1,860 3,070 1,950 2,532 2,333 2,402 *** 21,000 33,000 21,000 235 217 223 *** 71 63 41 30% 29% 18% 23 4 3 1,300 2,600 2,580 2,741 *** 14,000 28,000 240 255 *** 33 36 14% 14% 12 6 5,200 8,920 2,151 1,512 *** *** *** 1,360 56,000 96,000 200 140 *** *** *** 126 44 30 22% 21% 14 3 56 44% 3 C AN C TEMPORARY LODGING FACILITY FAMILY HOUSING (see note above): CONUS FAMILY HOUSING OCONUS FAMILY HOUSING FAMILY SUPPORT FACILITIES: CHILD DEVELOPMENT CTR (under 6 years old) CHILD DEVELOPMENT CTR (school age) EDUCATION CENTER YOUTH CENTER FAMILY SERVICE CENTER COMMUNITY SUPPORT FACILITIES: FIRE STATION, COMMUNITY CHAPEL CENTER COMMISSARY (sales store w/ operational equipment) PHYSICAL FITNESS TRAINING CENTER MAIN EXCHANGE (w/ mall service shops) SERVICE CLUB LIBRARY RECREATION CENTER MWR VEHICLE MAINTENANCE FACILITY (Auto Hobby Shop) 930 5 10,000 UFC 3-701-01 March 2011 FACILITY TYPE Reference size Oct 2010 unit cost (GUC) (gross m2) ($/m2) BOWLING CENTER (8 lanes w/ pin-spotting and automatic scoring equipment) DEPENDENT SCHOOLS: ELEMENTARY SCHOOL JUNIOR HIGH / MIDDLE SCHOOL HIGH SCHOOL PARKING GARAGE / BUILDING (450 SF/vehicle includes turning space and ramps) BRIG/STOCKADE (Level 2 Confinement) INDOOR FIRING RANGE *** NA 25,640 1,895 *** *** 548 7,430 2,140 2,547 2,071 * Unit cost per vertical meter (gross SF) Oct 2010 unit cost ($/SF) NA 276,000 80,000 23,000 EL L ** Unit cost per vertical foot Reference size Standard Deviation $/SF C AN C N (Number of Projects) *** 176 *** *** 51 19 11 3 14 27% 11 237 192 97 35 41% 18% 5 9 *** Insufficient pricing data in the Historical Analysis Generator (HII) at www.hnd.usace.army.mil/HII 6 Std. Dev / GUC (Pct) ED Unit Costs for Military Construction UFC 3-701-01 March 2011 CHAPTER 3 UNIT COSTS FOR DOD FACILITIES COST MODELS 3-1 OVERVIEW This chapter describes the unit costs and related factors used in support of DoD facilities cost models. These are intended for macro-level analysis and planning and should not be used for individual facilities or project estimates. ED Unit costs and related factors are associated with Facility Analysis Categories (FACs) represented by a 4-digit code in the DoD Real Property Classification System (RPCS), a hierarchical scheme of real property types and functions that serves as the framework for identifying, categorizing, and modeling the department’s inventory of land and facilities. FACs are common across the department and suitable for department-wide applications. For each FAC, Table 3 identifies the associated unit cost or factor to be used in DoD facilities cost models and metrics. EL L Whenever possible, unit costs and factors have been based upon commercial benchmarks. Detailed supporting data for unit costs is available as part of the supporting documentation download file accompanying this UFC on the Whole Building Design Guide web site: http://www.wbdg.org/ccb/DOD/UFC/ARCHIVES/ufc_3_701_01_FY11supplement.zip. 3-2 REPLACEMENT UNIT COSTS 3-2.1 Definition C AN C Replacement provides a complete and useable facility capable of serving the purpose of the original facility. Replacement costs include construction of standard foundations, all interior and exterior walls and doors, the roof, utilities out to the 5-foot line, all built-in plumbing and lighting fixtures, security and fire protection systems, electrical distribution, wall and floor coverings, heating and air conditioning systems, and elevators. Not included are project costs such as design, supporting facility costs, special foundations, equipment acquired with other funding sources (e.g. missionfunded range targets), contingency costs, and supervision, inspection, and overhead (SIOH). Also not included are items generally considered personal property such as computer systems, telephone instruments, and furniture. 3-2.2 Use of Replacement Unit Costs Replacement unit costs form the basis of calculating plant replacement value in a consistent manner across DoD. Plant replacement value represents the cost to design and construct a notional facility to current standards to replace an existing facility at the same location. The standard DoD formula for calculating plant replacement value is: 7 UFC 3-701-01 March 2011 Plant Replacement Value = 1 Facility Quantity x Replacement Unit Cost x Area Cost Factor x 2 3 Historical Records Adjustment x Planning and Design Factor x 4 Supervision Inspection and Overhead Factor x Contingency 5 factor Replacement unit costs can also support large-scale program-level estimates for restationing plans with the addition of allowance for site preparation, earthwork, landscaping, and related factors. Replacement unit costs should not be used for individual project estimates. SUSTAINMENT UNIT COSTS 3-3.1 Definition ED 3-3 Sustainment provides for maintenance and repair activities necessary to keep a typical inventory of facilities in good working order over their expected service life. It includes: regularly scheduled adjustments and inspections, including maintenance inspections (fire sprinkler heads, HVAC systems) and regulatory inspections (elevators, bridges) • preventive maintenance tasks • emergency response and service calls for minor repairs • major repair or replacement of facility components (usually accomplished by contract) that are expected to occur periodically throughout the facility service life C EL L • C AN Sustainment includes regular roof replacement, refinishing wall surfaces, repairing and replacing electrical, heating, and cooling systems, replacing tile and carpeting, and similar types of work. 6 It does not include repairing or replacing non-attached equipment or furniture, or bldg components that typically last more than 50 years (such as foundations and structural members). Sustainment does not include restoration, modernization, environmental compliance, specialized historical preservation, 7 general facility condition inspections and assessments, planning and design (other than shop drawings), or costs related to acts of God, which are funded elsewhere. Other tasks associated with facilities operations (such as custodial services, grass cutting, landscaping, waste disposal, and the provision of central utilities) are also not included. 8 1 A geographic location adjustment for costs of labor, material, and equipment, published in Chapter 4 for vertical construction. An adjustment to account for increased costs for replacement of historical facilities or for construction in a historic district; the current value of the factor is 1.05. 3 A factor to account for the planning and design of a facility; the current value of this factor is 1.09 for all but medical facilities and 1.13 for medical facilities. 4 A factor to account for the supervision, inspection, and overhead activities associated with the management of a construction project; the current value of the factor is 1.057 for facilities in the continental US (CONUS), and 1.065 (USACE) or 1.062 (NAVFAC) for facilities outside of the continental US (OCONUS). 5 A factor to account for construction contingencies; the current value of the factor is 1.05. 6 Facilities Sustainment also generally allows for overhead costs, which include architectural and engineering services. 7 Specialized historical preservation costs are those for customized components or materials that are no longer readily available. 8 Facilities Sustainment Program Element (PE) definition. 2 8 UFC 3-701-01 March 2011 3-3.2 Use of Sustainment Unit Costs Sustainment unit costs represent the annual average sustainment cost for each FAC, and serve as the basis for calculating annual facilities sustainment requirements for DoD using the following formula: 9 Sustainment requirement = Facility Quantity x Sustainment Unit Cost x Area Cost Factor x Inflation Factor MODERNIZATION FACTORS 3-4.1 Definitions ED 3-4 3-4.2 EL L Modernization, along with restoration, improves facilities. Modernization consists of alteration of facilities solely to implement new or higher standards (including regulatory changes), to accommodate new functions, or to renew building components that typically last more than 50 years (such as foundations and structural members). Restoration includes repair and replacement work to restore facilities damaged by inadequate sustainment, excessive age, disaster, accident, or other causes. Restoration and modernization do not include recurring sustainment tasks or certain environmental measures which are funded elsewhere. Other tasks associated with facilities operations (such as custodial services, grounds services, waste disposal, and the provision of central utilities) are also not included. Use of Modernization Factors AN C Modernization factors represent the average annual decrease in facility value over the useful service life due to obsolescence. Conversely, this value represents the average annual investment required to preserve the original facility value, adjusted for inflation, through modernization. As such, modernization factors are fractional values with no units (such as dollars) that are used in conjunction with plant replacement value to generate estimates of modernization funding requirements. Modernization factors are calculated using the following formula: Annual modernization factor = total depreciation (%) / useful service life C Where the total depreciation is a percent of total facility value, and the useful service life is expressed in years for each FAC. In turn, the modernization factor is used to generate the average annual modernization requirement using the following formula: Modernization requirement = PRV x modernization factor 3-5 OPERATION UNIT COSTS 3-5.1 Definition 9 A geographic location adjustment for costs of labor, material, and equipment. 9 UFC 3-701-01 March 2011 Facilities Operation describes the functions associated with the use of facilities or infrastructure: fire and emergency services, provision of energy utilities, provision of water/wastewater utilities, pavement clearance, refuse collection and disposal, real property leases, grounds maintenance and landscaping, pest control, custodial services, real property management and engineering services, energy management, and readiness engineering. 3-5.2 Use of Operation Unit Costs Operation requirement 3-6 10 ED Operation unit costs represent the annual average “bare” operational cost for each FAC, and serve as the basis for calculating annual facilities operations requirements for DoD using the following formula: = Facility Quantity x Operation Unit Cost x Locality Index UNIT COST HEIRARCHY 11 x Inflation Factor EL L Unit costs for DoD cost models are classified by the following hierarchy of data sources: Source 1: Standard, easily-accessible published data. Source 1 is the most desirable due to ease of access, wide applicability, and lack of bias. Examples include the DoD Tri-Service Committee on Cost Engineering, Service-specific cost guidance (USACE, USAF), commercial cost-estimating guidelines or models (e.g., M&S or Whitestone), or other Government-published cost guidance from federal, state, or local government agencies (e.g. Fairfax County (Virginia) Park Authority). AN C Source 2: Source 1 cost factors that are applied to facilities with similar but not identical characteristics (e.g., sewage waste treatment facilities and industrial waste treatment facilities). Source 2 also includes unpublished government or trade association cost data (e.g. CEAC), and Service-validated cost factors for non-standard facilities that have no commercial counterparts (e.g. missile launch facilities or military ranges). C Source 3: Includes unpublished project-specific data derived from Service project documents (e.g. DD Forms 1391) or by calculating costs from reported plant replacement value and inventory, or derived from using a ratio of sustainment to construction from a similar Source-1 Facilities Analysis Category (e.g. FAC 2115, Aircraft Maintenance Hangar, Depot derived from FAC 2111, Aircraft Maintenance Hangar). 3-7 REVISING UNIT COSTS Users of this UFC are encouraged to suggest revisions to the published cost factors, particularly for facilities unique to their mission. Submit proposed changes to the proponent office in accordance with the following guidelines: 10 For each operation function A geographic location adjustment for costs of labor, material, and equipment for each operational function, equivalent to the Area Cost Factor for construction or sustainment. 11 10 UFC 3-701-01 March 2011 Revised costs should come from an equivalent or superior source • Revised costs should be easily audited • Revised costs should be consistent with the functional definitions • Revised costs should be consistent with the scope of the Facility Analysis Category • Revised costs should be suitable for application throughout DoD C AN C EL L ED • 11 UFC 3-701-01 March 2011 Table 3: Unit Costs for DoD Facility Cost Models (not to be used for military construction projects) $1.42 1112 Rotary-Wing Landing Area, Surfaced Runway Overrun Area, Surfaced Runway, Unsurfaced Unmanned Aerial Vehicle Runway & Launch/Recovery Site Taxiway, Surfaced Rotary-Wing Taxiway, Surfaced Aircraft Apron, Surfaced Compass Calibration Pad, Surfaced Missile Launching Pad, Surfaced Aircraft Washing Pad, Surfaced Miscellaneous Airfield Pavement, Surfaced Aircraft Pavement Shoulder Miscellaneous Airfield Pavement, Unsurfaced Aircraft Rinse Facility Aircraft Fueling Facility Aircraft Defueling Facility Marine Fueling Facility Vehicle Fueling Facility Aircraft Operating Fuel Storage Marine Operating Fuel Storage Vehicle Operating Fuel Storage Other Operating Fuel SY $98.07 $1.07 $0.00 $0.2329 $0.0000 $0.0000 $0.0708 $0.1402 $0.0155 45 0.013300 SY $69.58 $1.09 $0.00 $0.2329 $0.0000 $0.0000 $0.1212 $0.1402 $0.0265 45 0.013300 SY SY $69.58 $9.88 $0.90 $0.24 $0.00 $0.00 $0.2329 $0.0166 $0.0000 $0.0000 $0.0000 $0.0000 $0.2828 $0.2828 $0.1402 $0.0006 $0.0618 $0.0618 45 45 0.013300 0.013300 SY SY $69.58 $69.58 $1.07 $1.07 $0.00 $0.00 $0.2329 $0.2329 $0.0000 $0.0000 $0.0000 $0.0000 $0.0708 $0.0708 $0.1402 $0.1402 $0.0155 $0.0155 60 60 0.009900 0.009900 SY SY $97.79 $97.79 $1.07 $1.07 $0.00 $0.00 $0.2329 $0.2329 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0708 $0.1402 $0.0497 $0.0000 $0.0155 60 60 0.009900 0.009900 SY $97.79 $1.07 $0.00 $0.2329 $0.0000 $0.0000 $0.0708 $0.0497 $0.0155 60 0.009900 SY $97.79 $1.07 $0.00 $0.2329 $0.0000 $0.0000 $0.0708 $0.0497 $0.0155 60 0.009900 SY $97.79 $1.07 $0.00 $0.2329 $0.0000 $0.0000 $0.0708 $0.1402 $0.0155 60 0.009900 SY $69.58 $1.07 $0.00 $0.2329 $0.0000 $0.0000 $0.0708 $0.0497 $0.0155 60 0.009900 $9.88 $0.24 $0.00 $0.0166 $0.0000 $0.0000 $0.0708 $0.0006 $0.0155 45 0.013300 $160.45 $1,976.58 $1,976.58 $361.84 $113,698.49 $4.31 $1.07 $8.15 $8.15 $0.42 $483.22 $2.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.2329 $0.7219 $0.7219 $0.0562 $29.38 $0.0099 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0708 $0.0000 $0.0000 $0.0000 $0.0000 $0.0019 $0.0497 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0155 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 30 30 30 37 25 31 0.021000 0.021000 0.021000 0.017000 0.025200 0.019900 GA $13.43 $2.15 $0.00 $0.0099 $0.0000 $0.0000 $0.0019 $0.0000 $0.0000 31 0.019900 GA $3.16 $2.15 $0.00 $0.0099 $0.0000 $0.0000 $0.0019 $0.0000 $0.0000 31 0.019900 GA $2.29 $2.15 $0.00 $0.0099 $0.0000 $0.0000 $0.0019 $0.0000 $0.0000 31 0.019900 1165 1166 1167 1211 1212 1221 1231 1241 1242 1243 1244 SY SY GM GM GM OL GA Refuse Collection $0.0000 Grounds Maint $0.2828 Pvmt Clearance $0.1402 Pest Control $0.0618 EL LE C 1164 AN 1163 Custodial Svcs $0.0000 D $168.95 1162 Real Prop Mgmt $0.2329 0.013300 SY 1131 1161 Sustainment 45 Fixed-Wing Runway, Surfaced 1121 1122 Replacement Modernization Factor (no units) 1111 1114 1115 UM Useful Svc Life (years) Water/ Wastewater $0.00 1113 FAC Title C FAC Unit costs ($FY 2011) 12 UFC 3-701-01 March 2011 (not to be used for military construction projects) 1403 1404 1411 1412 1413 1421 1422 1431 1441 1442 1443 1444 1445 1446 Water/ Wastewater LF OL $398.74 $103,812.23 $7.20 $777.37 $0.00 $0.00 $0.2558 $10.89 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 31 25 0.019900 0.025200 SF SF SF $1,826.65 $288.06 $509.41 $24.74 $3.21 $10.80 $0.00 $0.19 $0.10 $1.38 $0.4815 $1.20 $0.0000 $1.25 $1.25 $0.0000 $0.0883 $0.0883 $0.0078 $0.0078 $0.0078 $0.0000 $0.0000 $0.0000 $0.0000 $0.0331 $0.0331 50 50 50 0.011900 0.012000 0.012300 EA SF EA MI LF EA SF EA SF $47,943.40 $281.67 $9,861.38 $88,922.10 $67.35 $3,388.96 $288.06 $14,450.20 $288.06 $482.72 $7.62 $115.06 $152.26 $7.39 $48.99 $3.71 $283.79 $3.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.25 $0.00 $0.11 $101.81 $0.6919 $21.00 $188.83 $1.05 $5.94 $0.4843 $30.95 $0.4858 $0.0000 $1.25 $0.0000 $0.0000 $0.0000 $0.0000 $1.26 $0.0000 $1.26 $0.0000 $0.0883 $0.0000 $0.0000 $0.0000 $0.0000 $0.0888 $0.0000 $0.0888 $0.0000 $0.0078 $0.0000 $22.08 $0.0000 $0.0000 $0.0079 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0110 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0000 $0.0333 50 50 50 28 20 20 50 50 50 0.012300 0.012000 0.012300 0.022100 0.030100 0.030100 0.012000 0.012300 0.012000 SF SF $288.06 $245.52 $5.39 $4.68 $0.11 $0.11 $0.9901 $0.4455 $1.26 $1.26 $0.0888 $0.0888 $0.0079 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 50 45 0.012000 0.013400 SF $231.99 $3.54 $0.58 $0.5599 $0.0000 $0.0888 $0.1350 $0.0000 $0.0333 45 0.013300 SF $253.74 $3.18 $0.57 $0.5355 $1.26 $0.0888 $0.1350 $0.0000 $0.0333 50 0.012000 SF SF Refuse Collection Grounds Maint D Sustainment EL LE 1321 1331 1341 1351 1361 1362 1371 1381 1402 Custodial Svcs Pvmt Clearance Pest Control Modernization Factor (no units) Replacement C 1262 1311 1312 Storage POL Pipeline Liquid Fuel Loading/Unloading Facility POL Pump Station Communications Building Satellite Communications Building Communications Facility Aircraft Navigation Building Aircraft Navigation Facility Communications Lines Airfield Pavement Lighting Airfield Lighting Ship Navigation Building Ship Navigation Facility Air Defense Operations Building Missile Operations Building Emergency Operations Center / SCIF Airfield Fire And Rescue Station Aviation Operations Building Air Control Tower Helium Production/Storage Building Helium Storage Facility Ship Operations Building Photo/TV Production Building Operations Support Lab Operations Supply Building Miscellaneous Operations Support Building Working Animal Support Building Security Force Building Real Prop Mgmt Useful Svc Life (years) UM AN 1251 1261 FAC Title $841.23 $180.76 $2.91 $0.86 $0.19 $0.08 $1.54 $0.2118 $1.26 $0.9993 $0.0888 $0.1888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0333 $0.0111 35 45 0.017600 0.013900 $91,337.24 $192.25 $169.66 $1,270.48 $3.24 $4.20 $0.00 $0.18 $0.07 $184.48 $0.3457 $0.3792 $0.0000 $0.2554 $1.26 $24.66 $0.0888 $0.0888 $0.0000 $0.0079 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 45 50 50 0.013900 0.012500 0.012300 $238.76 $180.76 $180.76 $3.52 $2.53 $4.25 $0.16 $0.04 $0.12 $0.4698 $0.1874 $0.4493 $1.26 $1.26 $1.26 $0.0888 $0.0111 $0.0888 $0.0079 $0.0079 $0.0079 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0111 55 45 55 0.010900 0.013900 0.011400 SF $117.71 $3.31 $0.83 $0.2093 $1.61 $0.0888 $0.1350 $0.0000 $0.0333 40 0.015000 SF $207.83 $4.08 $0.14 $0.3189 $0.2554 $0.0888 $0.1350 $0.0000 $0.0111 55 0.010900 EA SF SF SF SF SF C FAC Unit costs ($FY 2011) 13 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 1451 Strategic Missile Launch Facility Missile Guidance Facility Missile Access Shaft Missile Access Tunnel Missile Shelter Missile Defense Facility Ballistic Missile Control Facility Mechanical Security Barricade Overhead Cover Aircraft Arresting System Aircraft Catapult Aircraft Firing-In Butt Aircraft Blast Deflector Aircraft Shelter, Hardened Aircraft Shelter Aircraft Support Facility Nuclear Propulsion Support Facility Nuclear Weapons Support Facility Explosives Holding/Transfer Area Explosives Railway Holding Yard Explosives Holding/Transfer Facility Revetment Central Vehicle Wash Facility Explosive Ordnance Disposal Area Security Support Facility Miscellaneous Operations Support Facility Pier Wharf Pier/Wharf Access Trestle EA $4,902,723.78 SF EA LF SF EA SF 1459 1461 1462 1463 1464 1465 1466 1467 1481 1491 1492 1493 1494 1495 1496 1497 1498 1499 1511 1512 1513 Custodial Svcs $11,774.08 $395.93 $89,046.75 $739.97 $44.37 $648,499.38 $395.93 $5.58 $1,255.25 $10.43 $0.66 $7,566.30 $17.49 $0.16 $0.00 $0.00 $0.04 $0.00 $0.11 $0.8570 $190.70 $1.56 $0.0779 $1,384.15 $0.8570 $0.9993 $0.0000 $0.0000 $0.1110 $356.99 $0.2554 $0.0888 $0.0000 $0.0000 $0.0111 $15.52 $0.0888 EA $36,961.46 $3,327.18 $0.00 $0.0000 $0.0000 SF EA EA EA EA SF SF EA EA $28.65 $778,717.45 $147,230.68 $456,123.52 $42,404.19 $335.26 $136.48 $1,581,991.16 $134,425.31 $0.83 $8,344.35 $129,791.62 $32,378.77 $532.12 $1.39 $1.01 $10,234.62 $1,568.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.04 $0.04 $0.00 $0.00 $0.1339 $1,668.19 $315.31 $980.12 $90.81 $0.7497 $0.3042 $3,531.39 $287.88 EA $138,471.25 $1,615.60 $0.00 SY $50.26 $1.76 $0.00 EA EA EA EA EA AN 1458 Real Prop Mgmt $10,809.98 Refuse Collection $102.64 Grounds Maint $0.0000 Modernization Factor (no units) 45 0.013400 Pvmt Clearance $0.0000 Pest Control $307.93 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0000 $0.0000 $0.0111 $0.0000 $0.0111 45 60 60 33 33 33 0.013400 0.010000 0.010000 0.018300 0.018300 0.018300 $0.0000 $0.0000 $0.0000 $0.0000 15 0.040600 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.1110 $0.1110 $937.17 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 $89.89 $0.0000 $0.1349 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 $0.0000 $0.0000 15 10 10 15 29 40 45 45 30 0.040300 0.061000 0.061000 0.040300 0.020600 0.014900 0.013300 0.013300 0.020100 $295.85 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 30 0.020100 $0.1096 $0.0000 $0.0000 $0.2845 $0.0006 $0.0111 60 0.010000 $428,995.38 $8,371.94 $0.00 $830.25 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 60 0.010000 $7,543.13 $162.51 $0.00 $16.10 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 40 0.015000 $20,208.70 $7,858,232.87 $116.49 $31,350.01 $0.00 $0.00 $43.28 $16,410.26 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 36 30 0.016700 0.020000 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 C 1452 1453 1454 1455 1456 1457 $44,361.05 Water/ Wastewater $1,508.87 D UM EL LE FAC Title C FAC Useful Svc Life (years) SF EA $207.18 $14,425.46 $3.24 $192.50 $0.13 $0.00 $0.4722 $34.70 $0.2554 $26.65 $0.0888 $2.57 $0.1350 $0.0000 $0.0000 $0.0000 $0.0111 $7.70 36 50 0.016700 0.012000 SY SY SY $2,566.35 $2,566.35 $837.38 $30.08 $30.08 $30.08 $0.00 $0.00 $0.00 $2.17 $2.17 $2.17 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0500 $0.0500 $0.0500 $0.0111 $0.0111 $0.0111 50 50 37 0.011900 0.011900 0.016100 14 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 1531 1541 Marine Cargo Staging Area Shore Erosion Prevention Facility Small Craft Berthing Small Craft Building Miscellaneous Waterfront Facility Harbor Control Facility Offshore Mooring Facility Harbor Marine Improvements General Purpose Instruction Building Applied Instruction Building Band Training Facility Reserve Training Facility Physical Education Building Organizational Classroom Indoor Firing Range and Supporting Facility Flight Simulator Facility Physiological Training Facility Gas Training Facility General Purpose Simulator Facility Training Pool and Tank Range Support Building Training Aids Support Building Training Support Structure Observation Tower/Bunker Offshore Range Support Platform Maneuver/Training Land, Light Forces Maneuver/Training Land, Heavy Forces Weapons Impact Area SY LF $50.26 $336.02 FB SF EA 1711 1712 1713 1714 1715 1717 1718 1721 1722 1723 1724 1725 1731 1732 1733 1734 1735 1741 1742 1743 0.016100 0.016100 Custodial Svcs $0.0000 $0.0000 Refuse Collection $0.0000 $0.0000 Grounds Maint $0.0000 $0.0000 Pvmt Clearance $0.0006 $0.0000 Pest Control $0.0111 $0.0000 $1,776.25 $29.67 $47,468.44 $14.35 $1.53 $1,033.12 $0.00 $0.07 $0.00 $4.66 $0.0625 $101.66 $0.0000 $0.1110 $0.0000 $0.0000 $0.0111 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0000 37 37 37 0.016100 0.017000 0.016100 EA EA LF $472,207.14 $10,052.64 $336.02 $923.74 $870.80 $9.75 $0.00 $0.00 $0.00 $1,011.27 $21.53 $1.10 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 37 36 36 0.016100 0.016600 0.016600 SF $227.16 $4.61 $0.10 $0.3845 $0.2554 $0.0888 $0.1350 $0.0000 $0.0333 50 0.012000 SF SF SF SF $234.25 $150.79 $173.99 $200.09 $2.96 $4.40 $5.67 $3.38 $0.10 $0.10 $0.13 $0.07 $0.3845 $0.3140 $0.3408 $0.4065 $0.2554 $0.2554 $1.26 $1.26 $0.0888 $0.0888 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0333 $0.0333 50 50 55 45 0.012000 0.012000 0.010900 0.013300 SF SF $150.79 $198.16 $4.76 $4.02 $0.10 $0.01 $0.3140 $0.2775 $0.2554 $0.2554 $0.0888 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0111 50 45 0.012000 0.013300 SF SF $174.60 $105.10 SF SF $150.79 $174.60 $4.93 $2.61 $0.15 $0.10 $0.4892 $0.2528 $0.2554 $0.2554 $0.0888 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 50 50 0.012000 0.012000 $2.10 $3.40 $0.10 $0.09 $0.2702 $0.3457 $0.9993 $0.2554 $0.0888 $0.0888 $0.0079 $0.1350 $0.0000 $0.0000 $0.0000 $0.0333 45 50 0.013300 0.012000 $389,681.75 $189.46 $150.79 $11,281.35 $2.61 $2.03 $567.95 $0.13 $0.04 $834.54 $0.2698 $0.2945 $510.78 $0.2554 $0.1110 $0.0000 $0.0888 $0.0888 $0.0000 $0.0079 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0111 25 40 40 0.024000 0.015000 0.015000 $133.39 $144,788.39 $0.00 $0.29 $706.63 $0.00 $0.04 $0.00 $0.00 $0.1070 $352.45 $0.0000 $0.1110 $0.0000 $0.0000 $0.0888 $8.88 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $79.02 $0.0000 35 36 N/A 0.017100 0.016700 0.000000 AC $0.00 $0.64 $0.00 $0.0000 $0.0000 $0.0000 $4.59 $0.0000 $0.6251 N/A 0.000000 AC $0.00 $0.64 $0.00 $0.0000 $0.0000 $0.0000 $4.59 $0.0000 $0.6251 N/A 0.000000 AC $0.00 $0.64 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 EA SF SF SF EA EA AN 1611 1631 1641 37 37 $1.76 $9.75 Real Prop Mgmt $0.1096 $1.10 C 1551 1552 1591 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 D UM EL LE FAC Title C FAC Useful Svc Life (years) 15 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 1744 1745 1750 Parachute Drop Zone Parade and Drill Field General Purpose Small Arms Range Zero Range Field Fire Range Record Fire Range Night Fire Range Known Distance Range Sniper Range Pistol Range Machinegun Range General Purpose Direct Fire Range Grenade Launcher Range Grenade Machinegun Range Light Antiarmor Weapon Range Heavy Antiarmor Weapon Range Artillery Direct Fire Range Tank Stationary Gunnery Range Indirect Fire Range Scaled Indirect Fire Range Scaled Gunnery Range Armor Vehicle Crew Training Range Armor Vehicle Unit Training Range Fire and Movement Range Squad Defense Range Infantry Battle Course Urban Combat Training Range Convoy Live Fire Range Live Hand Grenade Range Engineer Qualification AC AC FP $0.00 $0.00 $55,254.45 FP FP FP FP FP FP FP FP FP 1763 1764 1765 1766 1767 1768 1769 1771 1772 1773 1774 1775 1776 1777 1781 1782 0.000000 0.000000 0.024200 Custodial Svcs $0.0000 $0.0000 $0.0000 Refuse Collection $0.0000 $0.0000 $0.0000 Grounds Maint $245.88 $1,785.12 $991.57 Pvmt Clearance $0.0000 $0.0000 $0.0000 Pest Control $0.0000 $0.0000 $0.0000 $5,614.05 $55,254.45 $95,861.28 $3,413.37 $9,141.70 $263,818.69 $55,727.99 $51,731.80 $0.00 $69.04 $216.66 $411.18 $120.60 $192.48 $701.09 $164.82 $558.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1.19 $45.17 $75.49 $8.32 $22.29 $293.74 $7.36 $126.14 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $10.94 $388.86 $388.86 $51.63 $170.24 $1,263.62 $26.65 $619.60 $1,239.19 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 25 25 25 25 25 25 25 N/A 0.024200 0.024200 0.024200 0.024200 0.024200 0.024200 0.024200 0.024200 0.000000 FP LN $28,059.23 $256.97 $136.67 $1,262.05 $0.00 $0.00 $68.42 $0.6266 $0.0000 $0.0000 $0.0000 $0.0000 $674.00 $25,873.97 $0.0000 $0.0000 $0.0000 $0.0000 25 25 0.024200 0.024200 FP $505,160.03 $624.63 $0.00 $1,231.73 $0.0000 $0.0000 $315.91 $0.0000 $0.0000 25 0.024200 LN $2,624,919.35 $18,479.61 $0.00 $6,400.34 $0.0000 $0.0000 $21,169.60 $0.0000 $0.0000 25 0.024200 EA EA $1,113,939.43 $6,377,689.07 $2,781.16 $38,965.83 $0.00 $0.00 $2,716.12 $15,550.72 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 25 0.024200 0.024200 EA EA EA LN $0.00 $9,928.53 $42,087.69 $3,725,126.59 $0.00 $171.50 $171.50 $36,372.22 $0.00 $0.00 $0.00 $0.00 $0.0000 $24.21 $102.62 $7,958.82 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $14,169.07 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 25 25 25 0.000000 0.024200 0.024200 0.024200 $23,409,000.0 0 $129,358.22 $211,036.69 $2,407,229.09 $834,842.42 $72,069.58 $0.00 $11,710.92 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 $1,019.15 $2,343.66 $10,481.87 $5,678.08 $0.00 $0.00 $0.00 $0.00 $279.81 $456.49 $2,400.53 $973.73 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $3,748.78 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 25 25 25 0.024200 0.024200 0.024200 0.024200 $560,950.60 $22,659.32 $318,010.56 $10,875.55 $147.62 $765.04 $0.00 $0.00 $0.00 $973.73 $49.01 $678.59 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $121.03 $46,176.47 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 25 25 0.024200 0.024200 0.024200 EA LN EA EA EA AN 1761 1762 N/A N/A 25 $0.64 $124.96 $281.86 Real Prop Mgmt $0.0000 $0.0000 $44.44 C 1751 1752 1753 1754 1755 1756 1757 1758 1760 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 $0.00 FP FP FP D UM EL LE FAC Title C FAC Useful Svc Life (years) 16 UFC 3-701-01 March 2011 (not to be used for military construction projects) 1792 1793 1794 1795 1796 1797 1798 1799 2111 2112 2113 2114 2115 2116 2118 2121 2123 2124 2125 Water/ Wastewater FP $2,137,135.07 $8,379.57 $0.00 $4,622.83 $0.0000 $0.0000 $19,138.60 $0.0000 $0.0000 25 0.024200 EA $87,930.50 $796.34 $0.00 $187.25 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 EA $35,865.02 $122.74 $0.00 $76.53 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 EA $1,315,959.22 $25,413.16 $0.00 $2,818.24 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 EA FP EA $0.00 $155,461.83 $1,977,983.45 $0.00 $842.92 $232.11 $0.00 $0.00 $0.00 $0.0000 $336.28 $4,868.13 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 25 25 0.000000 0.024200 0.024200 SF $176.80 $0.66 $0.00 $5,107.79 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 FP $4,111.24 $88.46 $0.00 $8.89 $0.0000 $0.0000 $75.95 $0.0000 $0.0000 25 0.024200 EA $92,170.19 $381.31 $0.00 $196.23 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 EA $44,945.05 $997.28 $0.00 $95.71 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024200 SF $234.89 $2.50 $0.04 $0.4868 $0.1110 $0.1888 $0.0079 $0.0000 $0.0111 40 0.015700 SF SF $217.01 $295.79 SF $180.39 SF SF EA SF Refuse Collection Grounds Maint D Sustainment EL LE 1791 Custodial Svcs Pvmt Clearance Pest Control Modernization Factor (no units) Replacement C 1790 Range Light Demolition and Flame Training Range Miscellaneous Training Facility Aircraft Weapons Calibration Range Attack Helicopter Weapons Range Aircraft Weapons Range Air Defense Range Fire And Rescue Training Facility Urban Combat Training Area, Non-Fire Hand Grenade Range, Non-Firing Infiltration Course, Live Fire Confidence/Obstacle Course Aircraft Maintenance Hangar Aircraft Maintenance Shop Aircraft Corrosion Control Hangar Aircraft Engine Test Building Aircraft Maintenance Hangar, Depot Aircraft Maintenance Shop, Depot Aircraft Engine Test Facility Missile Maintenance/Assembly Building Missile/Launcher Maintenance Support Facility Missile Test Tower Missile Maintenance/Assembly Real Prop Mgmt Useful Svc Life (years) UM $3.22 $2.07 $0.09 $0.04 $0.3845 $0.6580 $0.1110 $0.9993 $0.0888 $0.0111 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 40 40 0.015700 0.015700 $3.07 $0.12 $0.3553 $0.1110 $0.1888 $0.0079 $0.0000 $0.0111 50 0.012500 $261.42 $1.54 $0.09 $0.4868 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 40 0.015700 $236.34 $2.27 $0.09 $0.3845 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 40 0.015700 $2,902,784.81 $20,389.67 $0.00 $4,619.85 $12,991.50 $144.35 $0.0000 $0.0000 $433.05 50 0.011900 $200.64 $2.71 $0.12 $0.6175 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 31 0.020300 AN 1783 FAC Title C FAC Unit costs ($FY 2011) SF $200.64 $2.67 $0.12 $0.4140 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 31 0.020300 EA SF $235,469.55 $200.64 $5,073.90 $2.38 $0.00 $0.09 $618.03 $0.6175 $0.0000 $0.9993 $0.0000 $0.1888 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0111 30 31 0.020100 0.020300 17 UFC 3-701-01 March 2011 (not to be used for military construction projects) 2135 2136 2137 2141 2142 2143 2144 2145 2146 2151 2152 2153 2154 2161 2162 2163 2171 2172 Water/ Wastewater Refuse Collection Grounds Maint SF $429.66 $17.88 $0.12 $0.9757 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 31 0.020300 SF $646.05 $24.00 $0.12 $1.38 $0.0000 $0.1888 $0.0079 $0.0000 $0.0111 50 0.012500 EA SF SF $11,203.90 $157.56 $180.76 $594.80 $1.78 $2.21 $0.00 $0.09 $0.12 $23.91 $0.2921 $0.2529 $0.0000 $0.9993 $0.9993 $0.0000 $0.0888 $0.0888 $0.0000 $0.0079 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 37 50 50 0.016700 0.012500 0.012500 EA $7,858,232.87 $7,721.89 $0.00 $16,410.26 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 37 0.017000 SF EA SF SF $200.64 $4,640,216.06 $197.19 $197.19 $2.69 $98,559.15 $3.40 $1.94 $0.09 $0.00 $0.09 $0.09 $0.3967 $9,937.43 $0.3700 $0.3700 $0.9993 $0.0000 $0.9993 $0.9993 $0.0888 $0.0000 $0.0888 $0.0888 $0.0079 $0.0000 $0.0079 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0000 $0.0111 $0.0111 50 6 50 50 0.012500 0.103700 0.012500 0.012500 SF $197.19 $3.73 $0.09 $0.3578 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 SF $197.19 $3.80 $0.09 $0.3578 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 EA $69,126.01 $1,670.12 $0.00 $149.77 $180.55 $18.06 $0.0000 $0.0000 $54.17 50 0.011900 EA SF $15,766,632.6 0 $157.56 SF $140.45 D Sustainment EL LE 2132 2133 2134 Custodial Svcs Pvmt Clearance Pest Control Modernization Factor (no units) Replacement C 2131 Building, Depot Intercontinental Ballistic Missile Processing Facility Ship Maintenance Drydock Marine Railway Marine Maintenance Shop Marine Maintenance Support Facility Landing Craft Wash Facility Nuclear Repair Shop Fixed Crane Structure Vehicle Maintenance Shop Vehicle Maintenance Shop, Depot Vehicle Maintenance Shop, National Guard Vehicle Maintenance Shop, Reserve Vehicle Maintenance Facility Launch Vehicle Test Facility Weapon Maintenance Shop Weapon Maintenance Shop, Depot Special Weapon Maintenance Shop Weapon Maintenance Facility, Depot Ammunition Maint Shop Ammunition Maint Shop, Depot Ammunition Maint Facility, Depot Electronic and Communication Maint Shop Electronic and Communication Maint Real Prop Mgmt Useful Svc Life (years) UM $5,225.00 $0.00 $35,803.14 $0.0000 $960.35 $0.0000 $0.0000 $2,881.05 50 0.011900 $2.64 $0.09 $0.2921 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $2.32 $0.09 $0.3210 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $200.64 $2.71 $0.09 $0.4926 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $163.99 $3.46 $0.09 $0.3210 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $163.99 $163.99 $2.98 $3.14 $0.09 $0.09 $0.3261 $0.3261 $0.1110 $0.1110 $0.0888 $0.0888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 50 50 0.012500 0.012500 $163.99 $4.28 $0.09 $0.3261 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 SF $158.53 $2.53 $0.09 $0.3651 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 SF $158.53 $1.98 $0.09 $0.3651 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 SF SF SF SF SF AN 2126 FAC Title C FAC Unit costs ($FY 2011) 18 UFC 3-701-01 March 2011 (not to be used for military construction projects) 2183 2184 2191 2192 2211 2221 2231 2233 2241 2242 2251 2252 2261 2262 2264 2265 2271 2281 2291 3101 Water/ Wastewater EA $871,898.73 $11,940.43 $488.57 $2,008.10 $0.0000 $61.07 $0.0000 $0.0000 $0.0000 50 0.012500 SF $157.56 $3.02 $0.09 $0.3578 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 SF $157.56 $2.63 SF SF $157.56 $208.79 $3.19 $5.02 SF $157.56 $3.57 EA $354,022.88 $16,461.00 SF SF SF SF SF $150.83 $158.46 $155.74 $648.24 $153.70 $1.78 $2.40 $2.29 $24.00 $1.95 SF $94.97 $2.05 SF SF $156.57 $94.97 SF $223.83 SF SF EA SF Refuse Collection Grounds Maint D Sustainment EL LE 2182 Custodial Svcs Pvmt Clearance Pest Control Modernization Factor (no units) Replacement $0.09 $0.2921 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $0.09 $0.09 $0.3752 $0.3967 $0.1110 $0.1110 $0.0888 $0.0888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 50 50 0.012500 0.012500 $0.09 $0.2775 $0.1110 $0.0888 $0.0079 $0.0000 $0.0111 50 0.012500 $0.00 $2,867.33 $0.0000 $344.22 $0.0000 $0.0000 $1,032.66 50 0.011900 $0.08 $0.08 $0.08 $0.08 $0.08 $0.3851 $0.4728 $0.2534 $1.38 $0.2426 $0.9993 $0.9993 $0.9993 $0.0000 $0.9993 $0.1888 $0.1888 $0.1888 $0.1888 $0.1888 $0.0079 $0.0079 $0.0079 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 $0.0111 $0.0111 $0.0111 55 55 55 50 55 0.011400 0.011400 0.011400 0.012500 0.011400 $0.08 $0.2426 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.011400 $1.87 $1.93 $0.08 $0.08 $0.2426 $0.2426 $0.9993 $0.9993 $0.1888 $0.1888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 55 55 0.011400 0.011400 $3.60 $0.08 $0.3739 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.011400 $94.97 $2.57 $0.08 $0.3739 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.010900 $1,026.37 $10.45 $0.08 $2.16 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.011400 $3,270,823.25 $56,549.46 $0.00 $6,712.39 $0.0000 $34.44 $0.0000 $0.0000 $103.33 55 0.010900 $158.53 $1.97 $0.08 $0.3973 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.011400 C 2181 Shop, Depot Electronic and Communication Maint Facility Installation Support Vehicle Maint Shop Installation Support Equipment Maint Shop Railroad Equipment Shop Parachute And Dingy Maintenance Shop Facility Engineer Maintenance Shop Facility Engineer Maintenance Facility Aircraft Production Plant Missile Production Plant Ship Production Plant Ship Building Dry-dock Tank/Automotive Production Plant Tank/Automotive Production Facility Weapon Production Plant Weapon Production Facility Ammunition Production Plant Ammunition Production Facility Ammunition Demilitarization Plant Ammunition Demilitarization Facility Electronic and Communication Production Plant Miscellaneous Support Production Plant Construction Material Production Plant RDT&E Laboratory Real Prop Mgmt Useful Svc Life (years) UM AN 2173 FAC Title C FAC Unit costs ($FY 2011) SF $157.24 $3.38 $0.08 $0.3967 $0.9993 $0.1888 $0.0079 $0.0000 $0.0111 55 0.011400 EA $1,522,503.00 $27,265.00 $488.51 $3,632.35 $0.0000 $1,186.39 $0.0000 $0.0000 $209.36 55 0.011400 SF $244.78 $2.56 $0.16 $0.4698 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 30 0.010900 19 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 3102 SF $275.85 SF 3902 3903 Medical Research Laboratory Biosafety Level 3 Laboratory Biosafety Level 4 Laboratory Aircraft RDT&E Facility Missile and Space RDT&E Facility Ship and Marine RDT&E Facility Tank and Automotive RDT&E Facility Weapons RDT&E Facility Ammunition, Explosive, and Toxic RDT&E Facility Electronic and Communication RDT&E Facility Propulsion RDT&E Facility Miscellaneous Item and Equipment RDT&E Facility Underwater Equipment RDT&E Facility RDT&E Technical Service Facility RDT&E Range Building RDT&E Range Facility RDT&E Range Complex Miscellaneous RDT&E Facility RDT&E Area Aerodynamic wind tunnel AC EA 3904 Propulsion engine test cell EA 4111 4121 Bulk Liquid Fuel Storage Bulk Liquid Storage, Other Than Fuel Liquid Oxygen Storage Ammunition Storage, Depot and Arsenal 3111 3121 3131 3141 3151 3161 3171 3181 3191 3201 3211 3711 3712 3713 3901 4122 4211 Custodial Svcs $0.9993 Refuse Collection $0.0888 $275.85 $10.63 $0.16 $0.6366 $0.9984 $0.0887 SF $275.85 $15.81 $0.16 $0.6366 $0.9984 SF SF $228.61 $223.05 $2.42 $3.04 $0.16 $0.16 $0.4698 $0.6548 SF $244.78 $2.29 $0.16 SF $244.78 $2.46 SF SF $244.78 $244.78 $3.10 $3.53 SF $244.78 $2.43 SF SF $244.78 $244.78 $2.87 $3.18 SF $244.78 $2.87 SF $244.78 SF EA EA EA $159.16 $221,534.15 $646,055.55 $221,534.15 30 0.020000 Pest Control $0.0111 $0.0079 $0.0000 $0.0111 20 0.030100 $0.0887 $0.0079 $0.0000 $0.0111 20 0.030100 $0.9993 $0.9993 $0.0888 $0.0888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 55 55 0.010900 0.010900 $0.3371 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 55 0.010900 $0.16 $0.3664 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 55 0.010900 $0.16 $0.16 $0.6548 $0.4698 $0.9993 $0.9993 $0.0888 $0.0888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 55 55 0.010900 0.010900 $0.16 $0.4698 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 55 0.010900 $0.16 $0.16 $0.4698 $0.3664 $0.9993 $0.9993 $0.0888 $0.0888 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 55 55 0.010900 0.010900 $0.16 $0.4526 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 55 0.010900 $2.40 $0.16 $0.3140 $0.9993 $0.0888 $0.0079 $0.0000 $0.0111 55 0.010900 $2.33 $1,714.88 $7,537.55 $4,510.88 $0.16 $0.00 $0.00 $0.00 $0.2702 $540.36 $1,383.59 $540.36 $0.1110 $0.0000 $0.0000 $0.0000 $0.0888 $20.74 $53.10 $20.74 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $62.23 $159.30 $62.23 40 40 36 40 0.015000 0.015000 0.016600 0.015000 $0.00 $7,155,430.58 $0.00 $16,334.57 $2.22 $0.0000 $0.0000 $0.0000 $0.6251 $3,209.50 N/A 55 0.000000 0.010900 $0.00 $0.0000 $122,718.4 8 $0.0000 $0.0000 $1,069.83 $41,763.96 $0.0000 $1,308,982.5 2 $100,354.73 $0.0000 $0.0000 $0.0000 $0.0000 55 0.010900 BL GA $0.00 $613,284,571. 09 $47,018,204.2 0 $59.38 $2.10 $4.93 $0.09 $0.00 $0.00 $0.1290 $0.0042 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 30 28 0.020600 0.022100 SF SF $47.35 $241.66 $0.92 $2.18 $0.00 $0.00 $0.1118 $0.5160 $0.1110 $0.1110 $0.0111 $0.0111 $0.0079 $0.0807 $0.0000 $0.0000 $0.0111 $0.0111 24 55 0.025800 0.010900 20 Grounds Maint $0.0079 Modernization Factor (no units) Pvmt Clearance $0.0000 AN 3104 Real Prop Mgmt $0.6371 C 3103 $5.75 Water/ Wastewater $0.16 D UM EL LE FAC Title C FAC Useful Svc Life (years) UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 4212 Intercontinental Ballistic Missile Storage Facility Ammunition Storage, Installation Liquid Propellant Storage, Ammunition Related Battery Storage, Weapon Related Open Ammunition Storage Cold Storage, Depot Cold Storage, Installation Covered Storage Building, Depot Covered Storage Shed, Depot Hazardous Materials Storage, Depot Controlled Humidity Storage, Depot Covered Storage Building, Installation Covered Storage Shed, Installation Hazardous Materials Storage, Installation Controlled Humidity Storage, Installation Vehicle Storage, Covered Storage Silo, Loose Material Small Arms Storage, Installation Open Storage, Depot Open Storage, Installation Hospital Medical Laboratory Morgue Veterinary Facility Medical Warehouse Ambulance Shelter Dental Facility SF $295.81 SF 4241 4251 4311 4321 4411 4412 4413 4414 4421 4422 4423 4424 4425 4426 4427 4511 4521 5100 5302 5303 5304 5306 5307 5400 Custodial Svcs $0.1110 $250.36 $2.63 $0.00 $0.5160 $0.1110 $0.0111 GA $1.27 $0.09 $0.00 $0.0030 $0.0000 SF $169.78 $4.57 $0.00 $0.3967 SY SF SF SF $38.18 $169.78 $87.06 $116.96 $1.76 $2.38 $2.85 $1.42 $0.00 $0.04 $0.04 $0.00 SF $71.38 $0.88 SF $146.93 $3.00 SF $116.00 $1.55 SF $89.90 $2.24 SF $44.46 $0.90 SF $146.93 SF $116.00 SF SF $63.42 $26.60 SF SY SY SF SF SF SF SF SF SF Refuse Collection $0.0111 Grounds Maint $0.0807 Modernization Factor (no units) 55 0.010900 Pvmt Clearance $0.0000 Pest Control $0.0111 $0.0807 $0.0000 $0.0111 55 0.010900 $0.0000 $0.0000 $0.0000 $0.0000 46 0.013400 $0.1110 $0.0111 $0.0807 $0.0000 $0.0111 45 0.013400 $0.1114 $0.3967 $0.3967 $0.2118 $0.0000 $0.1110 $0.1110 $0.1110 $0.0000 $0.0111 $0.0111 $0.0111 $0.7264 $0.0079 $0.0079 $0.0079 $0.0006 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 $0.0111 $0.0111 60 45 45 45 0.010000 0.013200 0.013200 0.013200 $0.00 $0.0792 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 36 0.016500 $0.00 $0.3045 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 45 0.013200 $0.00 $0.1972 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 45 0.013200 $0.00 $0.1874 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 45 0.013200 $0.00 $0.0792 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 36 0.016500 $5.37 $0.04 $0.3045 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 45 0.013200 $1.51 $0.04 $0.1972 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 45 0.013200 $0.66 $0.90 $0.00 $0.00 $0.1535 $0.0440 $0.1110 $0.1110 $0.0111 $0.0111 $0.0079 $0.0079 $0.0000 $0.0000 $0.0111 $0.0111 40 36 0.014800 0.016500 $242.12 $2.79 $0.00 $0.5160 $0.1110 $0.0111 $0.0079 $0.0000 $0.0111 55 0.010800 $38.18 $38.18 $444.65 $238.76 $163.47 $165.27 $116.72 $82.96 $405.98 $0.18 $0.18 $6.17 $7.99 $4.04 $3.30 $1.30 $0.67 $10.02 $0.00 $0.00 $0.18 $0.18 $0.18 $0.18 $0.04 $0.07 $0.18 $0.1096 $0.1096 $0.5307 $0.4698 $0.4771 $0.4771 $0.1972 $0.1659 $0.5282 $0.0000 $0.0000 $1.61 $1.61 $1.61 $1.61 $0.9993 $0.1110 $1.61 $0.0000 $0.0000 $0.1221 $0.1221 $0.1221 $0.1221 $0.0111 $0.0111 $0.1221 $0.0509 $0.0509 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.0006 $0.0006 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0111 $0.0111 $0.0333 $0.0333 $0.0333 $0.0333 $0.0333 $0.0333 $0.0333 75 75 30 20 50 45 50 35 30 0.008000 0.008000 0.020000 0.020000 0.012000 0.013300 0.013200 0.017000 0.020000 AN 4231 Real Prop Mgmt $0.8156 C 4221 $7.62 Water/ Wastewater $0.00 D UM EL LE FAC Title C FAC Useful Svc Life (years) 21 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) UM Replacement Sustainment 5500 5501 6100 Dispensary And Clinic Ambulatory Care Clinic General Administrative Building Small Unit Headquarters Building Large Unit Headquarters Building Printing And Reproduction Plant Automated Data Processing Center Pentagon Remote Delivery Facility Administrative Structure, Underground Alternate Joint Communications Center Administrative Structure, Other Than Buildings Family Housing Dwelling Family Housing Trailer/Relocatable Family Housing Trailer Site Family Housing Garage/Carport Family Housing Storage Facility Miscellaneous Family Housing Support Facility Trailer Court Support Facility Family Housing Attendant Facility Enlisted Unaccomp Personnel Housing Enlisted Unaccomp Personnel Housing, Transient Student Barracks Annual Training/Mobilization SF SF SF $304.49 $427.33 $216.52 SF 6104 6105 6106 6200 6201 6900 7110 7120 7130 7141 7142 7143 7145 7146 7210 7212 7213 7214 Refuse Collection $0.1221 $0.1221 $0.0888 Grounds Maint $0.1350 $0.1350 $0.1350 Pvmt Clearance $0.0000 $0.0000 $0.0000 Pest Control $0.0333 $0.0333 $0.0333 $172.06 $3.56 $0.13 $0.3724 $1.26 $0.0888 $0.1350 $0.0000 $0.0333 55 0.010800 SF $280.32 $4.20 SF $71.14 $3.23 SF $234.25 $2.92 SF SF SF $540.50 $150.27 $226.69 $7.03 $9.65 $2.26 SF $237.79 $2.92 EA $6,691.16 $196.78 SF FA $118.36 $34,654.55 $2.18 $892.95 FA SF $6,547.43 $52.85 SF $20.20 SF SF SF SF $0.13 $0.3894 $1.26 $0.0888 $0.1350 $0.0000 $0.0333 55 0.010800 $0.08 $0.1954 $0.9993 $0.1888 $0.1350 $0.0000 $0.0333 45 0.013200 $0.43 $0.4527 $1.26 $0.0888 $0.1350 $0.0000 $0.0333 45 0.013200 $0.13 $0.09 $0.13 $0.3453 $0.2772 $0.4382 $1.25 $0.1109 $1.26 $0.0887 $0.0887 $0.0888 $0.1349 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0111 $0.0333 55 55 45 0.010800 0.010800 0.013200 $0.43 $0.4523 $1.25 $0.0887 $0.1349 $0.0000 $0.0333 55 0.010800 $0.00 $16.02 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 26 0.023100 $0.14 $0.00 $0.1752 $100.73 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 60 20 0.010000 0.030300 $412.43 $1.03 $0.00 $0.00 $15.78 $0.0782 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 20 35 0.030300 0.017200 $0.94 $0.00 $0.0876 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 30 0.020100 $52.85 $2.40 $0.07 $0.3457 $0.1110 $0.0888 $0.1350 $0.0000 $0.0333 55 0.010900 $107.17 $1.46 $0.07 $0.2251 $0.1110 $0.0888 $0.1350 $0.0000 $0.0333 55 0.010900 $78.06 $3.69 $0.18 $0.1832 $0.1110 $0.0888 $0.1350 $0.0000 $0.0333 40 0.015000 $182.69 $3.70 $0.18 $0.3724 $0.0000 $0.0000 $0.1350 $0.0000 $0.0000 55 0.010900 C 6103 0.020000 0.020000 0.010800 Custodial Svcs $1.61 $1.61 $1.26 AN 6102 30 30 55 $7.29 $5.38 $3.01 Real Prop Mgmt $0.4771 $0.4503 $0.3457 C 6101 Modernization Factor (no units) Water/ Wastewater $0.18 $0.18 $0.13 D FAC Title EL LE FAC Useful Svc Life (years) SF $163.84 $5.13 $0.18 $0.3724 $0.0000 $0.0888 $0.1350 $0.0000 $0.0000 55 0.010900 SF SF $151.76 $163.84 $4.53 $3.30 $0.18 $0.06 $0.3724 $0.3310 $0.0000 $0.0000 $0.1221 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 55 41 0.010900 0.014700 22 UFC 3-701-01 March 2011 (not to be used for military construction projects) 7233 7234 7235 7240 7241 7242 7250 7251 7311 7312 7313 7314 7321 7322 7323 7331 7332 7333 7340 7341 7342 7343 Water/ Wastewater SF $220.39 $3.84 $0.18 $0.4498 $1.61 $0.1220 $0.1349 $0.0000 $0.0333 55 0.010900 SF SF SF $175.93 $314.40 $43.78 $4.89 $4.96 $2.51 $0.18 $3.16 $7.20 $0.3310 $0.6036 $0.1246 $0.0000 $1.61 $0.1110 $0.0888 $1.69 $0.0888 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0333 $0.0600 $0.0333 55 40 45 0.010900 0.015000 0.013400 SF $52.85 $1.01 $0.00 $0.0685 $0.0000 $0.0000 $0.1350 $0.0000 $0.0000 35 0.017200 SF SF EA $169.78 $150.79 $4,903.85 $5.40 $4.86 $95.72 $0.04 $5.49 $0.00 $0.4283 $0.4259 $8.91 $0.1110 $1.61 $0.0000 $0.0111 $0.0888 $0.0000 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0000 40 40 35 0.015000 0.015000 0.017200 SF $201.06 $5.32 $0.18 $0.3651 $0.0000 $0.0888 $0.1350 $0.0000 $0.0000 55 0.010900 SF SF $173.99 $222.83 $5.37 $5.32 $0.18 $0.18 $0.3651 $0.3651 $0.0000 $0.0000 $0.0888 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 55 N/A 0.010900 0.010900 SF $180.76 $1.28 $0.18 $0.0774 $0.0000 $0.0000 $0.1350 $0.0000 $0.0000 41 0.014700 SF SF SF $4.97 $231.99 $230.16 $0.20 $3.70 $5.06 $0.00 $0.07 $0.18 $0.0120 $0.4186 $0.5180 $0.0000 $0.0000 $1.61 $0.0000 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 41 45 45 0.014700 0.013300 0.013300 SF SF $248.42 $269.13 $5.60 $3.72 $0.13 $0.10 $0.3578 $0.3578 $1.26 $1.26 $0.0888 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 50 55 0.012000 0.010900 $79.92 $169.78 $43.37 $204.50 $204.50 $3.67 $5.68 $1.25 $5.77 $3.66 $1.98 $0.08 $0.18 $3.16 $3.16 $0.4987 $0.2969 $0.0980 $0.4041 $0.6036 $1.61 $0.9993 $0.1110 $1.61 $1.61 $1.69 $0.1888 $0.0888 $1.69 $1.69 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0600 $0.0333 $0.0333 $0.0600 $0.0600 45 45 35 35 35 0.013400 0.013400 0.017200 0.017200 0.017200 $321.22 $5.60 $0.52 $0.5623 $1.61 $1.69 $0.1350 $0.0000 $0.0600 45 0.013400 SF SF SF SF SF SF Refuse Collection Grounds Maint D Sustainment EL LE 7232 Custodial Svcs Pvmt Clearance Pest Control Modernization Factor (no units) Replacement C 7218 7220 7231 Barracks Unaccompanied Housing for Wounded Warriors Recruit/Trainee Barracks Dining Facility Miscellaneous UPH Support Building Unaccomp Personnel Housing Garage/Carport Dining Support Facility Latrine/Shower Facility Miscellaneous UPH Support Facility Officer Unaccompanied Personnel Housing Officer UPH, Transient Service Academy Unaccomp Pers Housing Emergency Unaccomp Personnel Housing EUPH Tent Pad Fire Station Facility Prison/Confinement Facility Police Station Drug and Alcohol Abuse Center Bread/Pastry Kitchen Ice/Dairy Products Plant Greenhouse Exchange Eating Facility Non-Exchange Eating Facility Open Mess and Club Facility Thrift Shop Bus Station Laundry/Dry Cleaning Facility Clothing Sales Store Real Prop Mgmt Useful Svc Life (years) UM AN 7215 FAC Title C FAC Unit costs ($FY 2011) SF SF SF $142.77 $81.94 $160.13 $3.50 $2.90 $3.94 $0.07 $0.07 $7.20 $0.2702 $0.2537 $0.3992 $0.1110 $0.1110 $0.9993 $0.0888 $0.0888 $0.1888 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0333 $0.0111 $0.0333 38 50 45 0.015800 0.012000 0.013900 SF $160.13 $2.82 $0.07 $0.2702 $0.9993 $0.0888 $0.1350 $0.0000 $0.0333 50 0.012000 23 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 7344 7345 Postal Facility Exchange Automobile Facility Exchange Sales Facility Bank and Credit Union Car Wash Facility Commissary Education Center Dependent School Dependent School Support Facility Chapel Facility Religious Education Facility Nursery and Child Care Facility Family Service Center Homeless Support Facility Forestry Guard Station Locker Room Air Raid/Fallout Shelter Miscellaneous Personnel Shelter Public Restroom/Shower Ceremonial Hall Exchange Support Facility Exchange Warehouse Private Vehicle Inspection Facility Hobby And Craft Center Automobile Craft Center Golf Club House and Sales Club and Organization Building Bowling Center Library, General Use Recreation Center Indoor Skating Rink SF SF $85.95 $119.58 SF SF SF SF SF SF SF 7371 7372 7380 7381 7382 7383 7384 7385 7386 7387 7388 7389 7411 7412 7413 7414 7415 7416 7417 7418 0.012000 0.015000 Custodial Svcs $0.9993 $0.9993 Refuse Collection $0.0888 $0.0888 Grounds Maint $0.1350 $0.1350 Pvmt Clearance $0.0000 $0.0000 Pest Control $0.0333 $0.0111 $160.13 $162.06 $63.96 $213.62 $211.69 $212.01 $162.39 $3.15 $3.64 $2.29 $2.00 $3.53 $3.74 $5.19 $0.07 $0.13 $1.34 $0.07 $0.10 $0.10 $0.04 $0.2702 $0.3213 $0.5319 $0.3359 $0.4138 $0.3538 $0.3585 $0.9993 $1.26 $0.0000 $0.2554 $1.26 $1.26 $0.1110 $0.0888 $0.0888 $0.0888 $0.0888 $0.0888 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0000 $0.0333 $0.0333 $0.0333 $0.0333 50 55 30 40 50 45 45 0.012000 0.010900 0.020100 0.015000 0.012000 0.013300 0.013300 SF SF $285.64 $269.69 $3.23 $3.77 $0.10 $0.10 $0.4235 $0.3457 $0.2554 $1.26 $0.0888 $0.0888 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 50 50 0.012000 0.012000 SF $238.27 $2.50 $0.10 $0.4114 $1.61 $0.0888 $0.1350 $0.0000 $0.0333 45 0.013300 SF SF SF SF SF SF $287.09 $0.00 $207.18 $126.90 $226.69 $28.65 $3.82 $0.00 $0.99 $3.35 $3.34 $0.83 $0.10 $0.18 $0.00 $0.18 $0.00 $0.00 $0.3894 $0.0000 $0.4722 $0.2155 $0.4382 $0.1340 $1.26 $1.61 $0.0000 $1.61 $0.0000 $0.0000 $0.0888 $0.0888 $0.0888 $0.0888 $0.0000 $0.0000 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0000 $0.0333 $0.0000 $0.0000 50 N/A 36 36 45 36 0.012000 0.000000 0.016700 0.016700 0.013400 0.016700 SF SF SF SF SF $139.20 $92.38 $160.13 $128.30 $180.76 $3.55 $2.28 $3.29 $1.62 $1.32 $0.18 $0.07 $0.09 $0.04 $0.07 $0.4065 $0.2118 $0.2702 $0.1996 $0.1874 $1.61 $0.1110 $0.1110 $0.1110 $0.9993 $0.0888 $0.0888 $0.0888 $0.0111 $0.0888 $0.1350 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0333 $0.0333 $0.0333 36 50 50 45 40 0.016700 0.011900 0.011800 0.013200 0.015000 $142.77 $136.01 $163.99 $321.22 $3.87 $2.47 $4.68 $4.23 $0.07 $0.07 $0.07 $0.07 $0.3578 $0.2873 $0.3310 $0.5623 $0.9993 $0.9993 $1.26 $1.26 $0.0888 $0.0888 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0333 $0.0333 50 40 50 45 0.011900 0.014900 0.011900 0.013300 $235.37 $232.96 $229.09 $123.42 $3.07 $3.36 $4.24 $2.17 $0.10 $0.07 $0.07 $0.04 $0.3992 $0.4016 $0.3773 $0.3075 $0.9993 $0.2554 $0.2554 $0.1110 $0.0888 $0.0888 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0333 $0.0333 40 55 50 45 0.014900 0.010900 0.011900 0.013300 SF SF SF SF AN 7361 7362 50 40 $3.62 $3.55 Real Prop Mgmt $0.2529 $0.2534 C 7346 7347 7348 7349 7351 7352 7353 Modernization Factor (no units) Water/ Wastewater $0.12 $0.07 SF SF SF SF D UM EL LE FAC Title C FAC Useful Svc Life (years) 24 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 7421 Indoor Physical Fitness Facility Indoor Swimming Pool Auditorium and Theater Facility Transient Lodging Recreational Lodging Transient and Recreational Lodging Support Facility Stable Boathouse Miscellaneous MWR Facility Miscellaneous MWR Support Playground Outdoor Swimming Pool Golf Course Golf Driving Range Golf Pitch and Putt Course Outdoor Recreation Area Recreational Pier Marina Outdoor Playing Court Athletic Field Running Track Stadium Pavilion Outdoor Theater Recreational Camp and Trailer Park Miscellaneous Outdoor Recreation Facility Wildlife Management Area Museum Monument and Memorial Cemetery Columbarium SF $200.09 SF SF 7444 7445 7446 7447 7511 7512 7513 7514 7515 7516 7517 7518 7521 7522 7523 7524 7531 7532 7541 7542 7543 7601 7602 7603 7604 Custodial Svcs $0.1110 $201.06 $165.92 $3.32 $2.13 $0.07 $0.07 $0.3943 $0.3286 $0.1110 $0.1110 $0.0888 $0.0888 SF SF SF $203.54 $78.16 $24.61 $5.11 $3.35 $1.22 $0.18 $0.18 $0.04 $0.3651 $0.1752 $0.2786 $1.61 $1.61 $0.1110 SF SF SF $23.04 $30.22 $229.91 $0.63 $0.71 $2.35 $0.09 $0.09 $0.07 $0.1104 $0.0620 $0.2750 SF $86.82 $3.48 $0.07 EA EA EA EA EA EA EA EA EA EA EA EA SF EA EA $171,487.59 $1,610,375.00 $2,366,632.69 $163,164.30 $118,116.77 $15,370.01 $7,628.89 $626,190.75 $64,569.88 $189,593.29 $142,018.93 $2,038,189.50 $57.18 $166,329.36 $321,443.41 $3,582.03 $11,281.35 $65,288.98 $2,801.43 $30,368.08 $990.84 $437.07 $14,131.97 $1,664.05 $3,876.94 $3,345.16 $59,762.13 $0.36 $7,059.03 $15,496.62 $72,754.18 EA AC SF EA EA CF $0.00 $124.24 $6,801.45 $0.00 $135.00 Refuse Collection $0.0888 45 0.013300 Pest Control $0.0333 $0.1350 $0.1350 $0.0000 $0.0000 $0.0333 $0.0333 40 45 0.014900 0.013300 $0.0888 $0.0888 $0.0888 $0.1350 $0.1350 $0.1350 $0.0000 $0.0000 $0.0000 $0.0333 $0.0333 $0.0333 41 45 55 0.014700 0.013400 0.010900 $0.1110 $0.1110 $0.1110 $0.1888 $0.0111 $0.0888 $0.0079 $0.0079 $0.0079 $0.0000 $0.0000 $0.0000 $0.0600 $0.0333 $0.0333 36 31 45 0.016600 0.019200 0.013300 $0.1784 $0.1110 $0.0888 $0.0079 $0.0000 $0.0333 45 0.013300 $0.00 $567.95 $208,651.02 $11,691.69 $104,325.51 $0.00 $0.00 $13,466.19 $0.00 $11,591.72 $0.00 $11,591.72 $0.00 $0.00 $28,975.46 $452.74 $3,385.78 $8,327.23 $1,468.28 $3,028.84 $32.40 $9.77 $2,459.60 $98.20 $459.75 $304.15 $6,967.49 $0.1452 $984.46 $589.70 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0888 $33.31 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $4,104.72 $0.0000 $4,104.72 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $99.94 $0.0000 25 25 25 25 25 25 31 37 25 25 25 25 35 25 25 0.024000 0.024000 0.024000 0.024000 0.024000 0.024000 0.019300 0.016100 0.024000 0.024000 0.024000 0.024000 0.017100 0.024000 0.024000 $2,030.86 $0.00 $171.80 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 25 0.024000 $0.00 $3.38 $222.50 $0.00 $0.00 $0.00 $0.12 $0.00 $0.00 $0.00 $0.0000 $0.4016 $16.06 $0.0000 $0.0000 $0.0000 $1.26 $0.0000 $0.0000 $0.0000 $0.0000 $0.0888 $0.0000 $0.0000 $0.0000 $0.0000 $0.1350 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $0.0000 $0.0000 $0.0000 N/A 55 60 N/A 60 0.000000 0.010900 0.010000 0.000000 0.010000 25 Grounds Maint $0.1350 Modernization Factor (no units) Pvmt Clearance $0.0000 AN 7441 7442 7443 Real Prop Mgmt $0.4065 C 7422 7431 $3.35 Water/ Wastewater $0.07 D UM EL LE FAC Title C FAC Useful Svc Life (years) UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 8111 8112 Electrical Power Source Stand-By/Emergency Power Electrical Power Source, Hydroelectric Electrical Power Source, Wind Generated Electrical Power Distribution Line, Overhead Exterior Lighting, Pole Electrical Power Distribution Line, Underground Electrical Power Substation Electrical Power Switching Station Electrical Power Transformers Heat Source Heat Distribution Line Heat Gas Production Plant Heat Gas Storage Heat Gas Distribution Line Refrigeration and Air Conditioning Source Chilled Water and Refrigerant Distribution Line Sewage Treatment Industrial Waste Treatment Water Separation Facility Septic Tank and Drain Field Septic Lagoon and Settlement Ponds Sewage Lift Stations Sewer and Industrial Waste Line Refuse Collection and Recycling Facility KW KW $352.89 $268.29 MW 8121 8122 8123 8131 8132 8133 8211 8221 8231 8232 8241 8261 8271 8311 8312 8313 8314 8315 8316 8321 8331 0.014000 0.014000 Custodial Svcs $0.0000 $0.0000 Refuse Collection $0.0000 $0.0000 Grounds Maint $0.0000 $0.0000 Pvmt Clearance $0.0000 $0.0000 Pest Control $0.0000 $0.0000 $2,382,667.00 $15,704.49 $0.00 $2.52 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 KW $2,171.00 $15.71 $0.00 $2.52 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 LF $24.52 $0.29 $0.00 $0.0585 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 EA LF $3,388.96 $29.97 $48.99 $0.61 $0.00 $0.00 $15.84 $0.1497 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 45 0.014000 0.014000 KV $200.18 $17.19 $0.00 $0.4727 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 KV $10.71 $0.25 $0.00 $0.0253 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 KV $34.41 $5.20 $0.00 $0.0923 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 45 0.014000 MB LF MB EA LF TR $47,683.87 $191.76 $3,770.70 $95,882.70 $18.07 $3,926.44 $877.12 $2.48 $17.07 $57.95 $0.12 $74.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $28.34 $0.4941 $9.04 $80.90 $0.1983 $7.89 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 34 34 34 24 36 14 0.018200 0.018200 0.018200 0.025800 0.017100 0.044700 LF $108.99 $3.57 $0.00 $0.1095 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 28 0.022100 $5,975.42 $6,521.12 $91.32 $3.97 $117.53 $117.53 $0.54 $0.01 $0.00 $0.00 $0.00 $0.00 $11.53 $11.53 $0.2080 $0.0131 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 50 50 24 0.011900 0.011900 0.011900 0.025000 $0.48 $0.0030 $0.00 $0.0052 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 24 0.025000 EA LF $202,959.28 $53.20 $1,179.23 $1.72 $319.79 $0.00 $527.78 $0.1300 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $137.05 $0.0000 24 60 0.025000 0.009900 EA $242,137.32 $4,447.58 $320.08 $528.26 $0.0000 $0.0000 $0.0000 $0.0000 $137.18 45 0.013300 KG KG KG GA GA AN 8114 45 45 $15.71 $19.58 Real Prop Mgmt $2.53 $1.07 C 8113 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 D UM EL LE FAC Title C FAC Useful Svc Life (years) 26 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) Replacement Sustainment 8332 8333 8334 8411 8412 8413 8414 8415 8421 Incinerator Sanitary Landfill Hazardous Waste Landfill Water Source, Potable Water Treatment Facility Water Storage, Potable Water Well, Potable Desalinization Plant Water Distribution Line, Potable Water Pump Facility, Potable Water Source, Fire Protection Water Distribution Line, Fire Protection Water Impoundment, Fire Protection Water Pump Facility, Fire Protection Water Tank, Fire Protection Water Source, NonPotable Water Storage, NonPotable Reservoir, Water Water Distribution Line, Non-Potable Water Pump Facility, NonPotable Road, Surfaced Road, Unsurfaced Vehicle Bridge Vehicular Tunnel Vehicle Parking, Surfaced Vehicle Parking and Staging Area, Unsurfaced Vehicle Staging Area, Surfaced TH AC AC KG KG GA KG KG LF $301,052.74 $622,973.96 $1,245,947.92 $0.00 $2,210.09 $2.90 $36.16 $7,509.28 $25.40 $1,492.00 $5,331.45 $4,048.28 $0.00 $21.10 $0.03 $4.24 $150.48 $1.04 KG $72.24 $0.02 GM $98.24 $0.12 LF $25.40 $1.04 MG $0.00 $0.00 KG $72.24 $0.02 GA $2.90 $0.0003 KG $54.24 GA $0.90 8432 8433 8434 8435 8441 8442 8443 8451 8452 8511 8512 8513 8514 8521 8522 8523 MG LF KG SY SY SY LF SY SY SY 45 36 36 N/A 50 50 50 50 60 0.013300 0.016600 0.016600 0.000000 0.011900 0.011900 0.011900 0.011900 0.009900 Real Prop Mgmt $14.08 $1,334.15 $2,668.31 $0.0000 $8.18 $0.0052 $0.0188 $16.03 $0.0949 Custodial Svcs $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 Refuse Collection $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 Grounds Maint $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 Pvmt Clearance $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 Pest Control $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.00 $0.2108 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.00 $0.0987 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.00 $0.0949 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.00 $604.21 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 $0.00 $0.2108 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.00 $0.0052 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.09 $0.00 $0.0188 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $0.0003 $0.00 $0.0052 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 AN 8431 $0.00 $25.40 $0.00 $1.04 $0.00 $0.00 $0.0000 $0.0949 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 50 0.000000 0.011900 $72.24 $0.02 $0.00 $0.2108 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 50 0.011900 $26.13 $11.02 $1,066.28 $19,840.11 $30.61 $11.49 $0.65 $0.57 $13.54 $13.30 $1.76 $0.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.0552 $0.0164 $2.23 $0.0552 $0.1042 $0.0164 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.1016 $0.1016 $0.0000 $0.1016 $0.0254 $0.0254 $0.0500 $0.0006 $0.0500 $0.0500 $0.0500 $0.0006 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 28 28 46 N/A 32 32 0.021400 0.021400 0.013000 0.000000 0.018700 0.018700 $26.14 $1.76 $0.00 $0.0797 $0.0000 $0.0000 $0.0254 $0.0006 $0.0000 32 0.018700 C 8422 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 D UM EL LE FAC Title C FAC Useful Svc Life (years) 27 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) UM Replacement Sustainment 8524 8525 8526 8531 8541 8601 8611 8612 SY SY SY SF EA MI LF EA $35.62 $1,450.64 $26.14 $53.16 $160,632.82 $523,717.92 $9,494.23 $114,736.64 $0.00 $22.94 $1.76 $0.59 $2,202.58 $19,535.77 $132.04 $2,579.00 LF LF EA LF $2.63 $215.88 $1,713,772.63 $1,371.36 $0.0037 $0.54 $2,440.54 $6.34 8715 8721 8722 8811 Sidewalk and Walkway Pedestrian Bridge Miscellaneous Paved Area Parking Garage/Building Traffic Control Signals Railroad Track Railroad Bridge Miscellaneous Railroad Facility Storm Drainage Retaining Structure Grounds Drainage Dams Levees and Dikes for Grounds Drainage Storm Water Ponds Boundary Fence and Wall Security Fence Dam MG LF LF EA $0.00 $1.66 $2.81 $1,124,689.08 8812 Lock EA 8813 8814 Navigation Revetments Training Dikes/Wing Dams/Pile Dikes Flood Control Structures Flood Control Levee/Floodwall Fish Facilities Utility Building Installation Gas Production Plant Installation Gas Storage Vehicle Scales Miscellaneous Pump Station Energy Management and Control System Hazardous Waste Storage Or Disposal Facility LF LF $0.00 $33.25 $69.73 $36,687,241.0 0 $36,687,241.0 0 $215.88 $1,371.36 EA LF $617,113.79 $1,371.36 8831 8910 8921 8922 8923 8924 8925 8926 0.021400 0.013000 0.018700 0.013300 0.040300 0.015400 0.013400 0.020600 Custodial Svcs $0.0000 $0.0000 $0.0000 $0.1110 $0.0000 $0.0000 $0.0000 $0.0000 Refuse Collection $0.0000 $0.0000 $0.0000 $0.0111 $0.0000 $0.0000 $0.0000 $0.0000 Grounds Maint $0.0000 $0.0000 $0.0000 $0.1372 $0.0000 $0.0000 $0.0000 $0.0000 Pvmt Clearance $0.0000 $0.0000 $0.0006 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 Pest Control $0.0000 $0.0000 $0.0000 $0.0333 $0.0000 $0.0000 $0.0000 $0.0000 $0.00 $0.00 $0.00 $0.00 $0.0093 $1.11 $144.19 $1.11 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 34 36 39 39 0.018200 0.016600 0.015800 0.015800 $0.00 $0.00 $0.00 $8,200.44 $0.0000 $0.0827 $0.0826 $91,237.24 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $12,447.10 $0.0000 $0.0000 $0.0000 $519.85 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $732.18 N/A 26 26 39 0.000000 0.023100 0.023100 0.015800 $8,207.97 $91,320.94 $0.0000 $12,458.52 $520.33 $0.0000 $732.85 39 0.015800 $0.54 $6.34 $0.00 $0.00 $1.10 $1.10 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 39 39 0.015800 0.015800 $2,964.81 $6.34 $0.00 $0.00 $101.57 $1.10 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 39 39 0.015800 0.015800 $310,613.94 $161.43 $282,800.25 $1,491.92 $3.56 $7,497.81 $0.00 $0.00 $0.00 $0.0000 $0.3992 $684.57 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $16.66 $0.0000 $0.0079 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0333 $49.97 39 55 55 0.015800 0.011400 0.010800 $75,252.40 $48,907.03 $12,525.35 $1,025.00 $1,110.58 $133.98 $0.00 $0.00 $0.00 $79.21 $50.65 $493.58 $0.0000 $0.0000 $0.0000 $14.40 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $43.21 $0.0000 $0.0000 30 30 50 0.020600 0.020600 0.012300 EA $195,092.77 $14,425.83 $0.00 $699.10 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 14 0.044700 EA $242,137.32 $4,460.01 $0.00 $528.26 $0.0000 $55.52 $0.0000 $0.0000 $166.56 45 0.013700 EA SF EA EA EA EA C $1,124,689.08 AN 8821 8822 28 46 32 45 15 40 46 30 Real Prop Mgmt $0.0942 $2.38 $0.1096 $0.0841 $245.43 $2,087.41 $18.44 $239.62 C 8711 8712 8713 8714 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 D FAC Title EL LE FAC Useful Svc Life (years) 28 UFC 3-701-01 March 2011 (not to be used for military construction projects) Unit costs ($FY 2011) UM Replacement Sustainment 8927 8928 8929 Utility Vaults Loading Platform/Ramp Miscellaneous Utility Facility Installation Gas Distribution Line Utility Tunnel Miscellaneous Storage Tank and Basin Miscellaneous Component of Other Facility Government Owned land State Owned Land Withdrawn Public land Licensed and Permitted Land Public Land Land Easement In-leased Land Foreign Land Building Improvements and Acquisitions Clearing, Grading, and Landscaping Demolition Cut and Fill Dredging Other Real Property Improvements Contaminated Facility or Area Not Real Property EA EA EA $22,932.40 $16,833.97 $2,048.25 LF 9110 9111 9120 9130 9140 9210 9220 9230 9311 9321 9331 9341 9351 9391 9411 9999 Refuse Collection $0.0000 $0.0000 $0.0000 Grounds Maint $0.0000 $0.0000 $0.0000 Pvmt Clearance $0.0000 $0.0000 $0.0000 Pest Control $0.0000 $0.0000 $0.0000 $18.07 $0.52 $0.00 $0.1983 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 36 0.017100 LF GA $56.97 $0.80 $0.32 $0.0030 NA $0.00 $0.00 AC AC AC AC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 AC AC AC AC NA $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 NA $0.00 NA NA NA NA $0.00 $0.00 $0.00 $0.00 NA NA $0.00 $0.00 $0.0975 $0.0023 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 60 45 0.010300 0.013700 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 $0.00 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A N/A N/A N/A 0.000000 0.000000 0.000000 0.000000 $0.00 $0.00 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A N/A N/A N/A N/A 0.000000 0.000000 0.000000 0.000000 0.000000 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A N/A N/A N/A 0.000000 0.000000 0.000000 0.000000 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 $0.00 $0.00 $0.00 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 $0.0000 N/A 0.000000 C 8999 0.013300 0.020000 0.013700 Custodial Svcs $0.0000 $0.0000 $0.0000 AN 8931 8951 45 30 45 $126.06 $94.89 $300.03 Real Prop Mgmt $48.44 $26.09 $8.36 C 8930 Modernization Factor (no units) Water/ Wastewater $0.00 $0.00 $0.00 D FAC Title EL LE FAC Useful Svc Life (years) 29 UFC 3-701-01 March 2011 CHAPTER 4 COST ADJUSTMENT FACTORS 4-1 LOCATION ADJUSTMENTS Table 4-1 provides area cost factors (ACFs) to be used for adjusting “bare” unit costs to location-specific costs for the most common locations. A complete table of all DoD sites that includes locality indices (LI) for adjusting operation costs is available as part of the supporting documentation download file accompanying this UFC on the Whole Building Design Guide web site: http://www.wbdg.org/ccb/DOD/UFC/ARCHIVES/ufc_3_701_01_FY11supplement.zip. EL L ED For military construction projects, use the MILCON ACFs with the primary facility unit costs from Chapter 2 or approved Air Force, Army, or Navy MILCON Pricing Guide. For calculating Plant Replacement Value, use the MILCON ACFs with the appropriate replacement unit costs from Chapter 3. For calculating sustainment costs, use the sustainment ACFs with the appropriate sustainment unit costs from Chapter 3. For calculating operation costs, use the appropriate operation function LI with the corresponding operation cost from Chapter 3. Do not use the MILCON ACFs to modify parametric cost estimates, detailed quantitytake-offs, unit price book (UPB) line items, commercial cost data, or user-generated unit costs. These cost estimating methods and databases have their own processes and factors for adjusting costs to different locations. C MILCON and sustainment ACFs were developed using the Tri-Service Cost Engineering ACF software program. Operation LIs were developed by Whitestone Research Corporation specifically for application in the DoD Facilities Operation Model. C AN In general, the Tri-Service Cost Engineering ACF software program evaluates the local costs for a United States market basket of 8 labor crafts, 17 construction materials, and 4 equipment items. These labor, materials, and equipment (LME) items are representative of the types of products, services, and methods used to construct most military facilities in the United States. Each of the LME costs is normalized and weighted to represent its contribution to the total cost of a typical facility. The normalized LME is then modified by seven matrix factors that cover local conditions affecting construction costs. These matrix factors include weather, seismic, climatic (frost zone, wind loads, and HVAC systems), labor availability, contractor overhead and profit, life support and mobilization, and labor productivity versus the U.S. standard. The resultant ACF for each location is normalized again by dividing by the 96-Base-City average to provide a final ACF that reflects the relative relationship of construction costs between that location and the 96-Base-City average as 1.00. MILCON ACFs were calculated using a LME ratio of 35/63/2. Sustainment ACFs were calculated using a LME ratio of 53/46/1. 30 UFC 3-701-01 March 2011 Both CONUS and OCONUS construction market surveys were conducted in 2010. The CONUS survey covered 376 locations that included 96 Base Cities (two per state in the continental US), and an additional 280 locations. The OCONUS survey included 99 locations, and was based on a market basket of goods for typical US labor, material, equipment, and construction methods. CONUS and OCONUS surveys are now being performed annually. When local materials and construction methods differ from those represented by the published ACF, specific adjustments may need to be added to your project estimate to account for any differences. ED There is no easy correlation between the current MILCON ACFs and previous MILCON ACFs for specific locations. No common benchmarks exist because both the Base City average and the relationships between cities change each cycle. It is possible, however, to compare differences between several locations in this database with differences between the same locations in previous databases. EL L The ACF is not intended to or capable of responding to rapid changes in the market place. Examples include Acts of God, accelerated construction schedules, changes in the demand and supply for construction materials, labor, and equipment. An increased demand for labor beyond what the local market can supply may require the enticement of premium pay, overtime hours, temporary living expenses, and travel expenses. C AN C Users may request revisions to published ACFs when market conditions unexpectedly change. Each request must be initiated by the USACE District senior cost engineer through HQUSACE or by the NAVFAC regional cost engineer to their corresponding NAVFAC Atlantic or Pacific Tri-Service Cost Engineering committee member. The local cost engineer shall provide updated market basket ACF software input factors to HQUSACE or NAVFAC for them to update the Tri-Service Cost Engineering ACF software. 31 4-1.1 UFC 3-701-01 March 2011 Area Cost Factors Table 4-1: Area Cost Factors Inside US MILCON 0.86 0.86 0.86 0.75 0.85 0.86 0.86 0.85 0.86 1.78 4.41 1.67 2.53 2.70 3.43 2.90 2.00 4.33 1.98 1.67 1.89 2.06 1.67 1.89 0.99 1.01 1.00 1.11 0.98 1.00 0.97 1.26 1.26 0.89 0.91 0.91 0.93 0.88 0.88 1.21 1.24 1.28 1.25 1.12 0.93 1.19 Sustainment 0.83 0.83 0.83 0.70 0.82 0.85 0.85 0.82 0.85 1.79 4.13 1.69 2.44 2.59 3.22 2.75 2.01 4.04 1.99 1.69 1.89 2.06 1.69 1.89 0.98 1.00 0.99 1.10 0.98 0.99 0.96 1.28 1.28 0.88 0.89 0.89 0.91 0.86 0.86 1.27 1.28 1.32 1.31 1.15 0.90 1.25 C AN C EL L ED ALABAMA AVERAGE ANNISTON ARMY DEPOT FORT MCCLELLAN FORT RUCKER MAXWELL AIR FORCE BASE MOBILE MOBILE AREA MONTGOMERY REDSTONE ARSENAL ALASKA AVERAGE ADAK NAVAL STATION ANCHORAGE CG- JUNEAU CG- KETCHIKAN CG- KODIAK CG- PRINCE WILLIAM SOUND CLEAR AIR FORCE BASE EARECKSON AIR FORCE BASE EIELSON AIR FORCE BASE ELMENDORF AIR FORCE BASE FAIRBANKS FORT GREELY FORT RICHARDSON FORT WAINWRIGHT ARIZONA AVERAGE DAVIS MONTHAN AIR FORCE BASE FLAGSTAFF FORT HUACHUCA LUKE AIR FORCE BASE NAVAJO ARMY DEPOT TUCSON YUMA MCAS YUMA PROVING GROUND ARKANSAS AVERAGE FORT CHAFFEE FORT SMITH LITTLE ROCK AIR FORCE BASE PINE BLUFF PINE BLUFF ARSENAL CALIFORNIA AVERAGE 29 PALMS MARINE CORPS BASE BARSTOW BEALE AIR FORCE BASE CAMP PENDLETON MARINE CORPS BASE CENTERVILLE BEACH CG- ALAMEDA 32 UFC 3-701-01 March 2011 Inside US Sustainment 1.33 1.31 1.37 1.34 1.26 1.25 1.32 1.29 1.22 1.19 1.16 1.29 1.17 1.17 1.21 1.78 1.16 1.37 1.92 1.19 1.26 1.34 1.26 1.35 1.28 0.99 1.02 0.96 1.09 1.02 0.96 1.02 1.02 0.94 0.96 1.02 1.17 1.14 1.20 1.20 1.14 1.08 1.13 1.13 1.04 0.84 0.92 0.80 0.93 0.84 1.16 C AN C EL L ED CG- PETALUMA CHINA LAKES NAVAL WEAPONS CENTER CONCORD EDWARDS AIR FORCE BASE EL CENTRO NAVAL AIR FIELD FORT HUNTER LIGGETT FORT IRWIN FORT ORD LEMOORE LOS ANGELES AREA MARCH AIR RESERVE STATION MONTEREY AREA POINT MUGU PORT HUENEME AREA SACRAMENTO AREA SAN CLEMENTE ISLAND SAN DIEGO SAN FRANCISCO SAN NICOLAS ISLAND SEAL BEACH SHARPE ARMY DEPOT SIERRA ARMY DEPOT STOCKTON AREA TRAVIS AIR FORCE BASE VANDENBERG AIR FORCE BASE COLORADO AVERAGE AIR FORCE ACADEMY BUCKLEY AIR FORCE BASE CHEYENNE MOUNTAIN COLORADO SPRINGS DENVER FORT CARSON PETERSON AIR FORCE BASE PUEBLO ARMY DEPOT ROCKY MOUNTAIN ARSENAL SCHRIEVER AIR FORCE BASE CONNECTICUT AVERAGE BRIDGEPORT NEW LONDON NEW LONDON AREA STRATFORD ENG PLANT DELAWARE AVERAGE DOVER DOVER AIR FORCE BASE WILMINGTON FLORIDA AVERAGE CAPE CANAVERAL EGLIN AIR FORCE BASE HOMESTEAD AIR RESERVE STATION JACKSONVILLE AREA KEY WEST NAVAL AIR STATION MILCON 1.27 1.26 1.29 1.30 1.22 1.21 1.28 1.25 1.17 1.13 1.10 1.25 1.13 1.13 1.15 1.75 1.13 1.29 1.88 1.13 1.21 1.28 1.21 1.29 1.24 0.99 1.02 0.96 1.09 1.02 0.96 1.02 1.02 0.95 0.96 1.02 1.14 1.11 1.16 1.16 1.11 1.06 1.11 1.11 1.02 0.85 0.92 0.82 0.92 0.86 1.17 33 UFC 3-701-01 March 2011 Inside US Sustainment 0.96 0.85 0.89 0.82 0.79 0.82 0.78 0.82 0.78 0.84 0.80 0.85 0.88 0.84 0.93 0.88 0.91 0.88 0.94 0.81 0.85 2.14 2.33 2.10 2.03 2.10 2.10 2.10 2.17 2.10 2.47 2.10 2.10 2.10 0.92 0.90 0.93 0.93 1.26 1.15 1.37 1.31 1.37 1.39 1.00 1.00 1.16 0.94 1.06 0.99 1.02 C AN C EL L ED MACDILL AIR FORCE BASE MAYPORT MIAMI ORLANDO AREA PANAMA CITY PANAMA CITY AREA PENSACOLA AREA TYNDALL AIR FORCE BASE WHITING FIELD GEORGIA AVERAGE ALBANY ATHENS ATLANTA FORT STEWART FORT BENNING FORT GILLEM FORT GORDON FORT MCPHERSON KINGS BAY MOODY AIR FORCE BASE ROBINS AIR FORCE BASE HAWAII AVERAGE BARKING SANDS FORD ISLAND FORT DERUSSY FORT SHAFTER HICKAM AIR FORCE BASE HONOLULU KANEOHE BAY PEARL HARBOR POHAKULOA SCHOFIELD BARRACKS TRIPLER ARMY MEDICAL CENTER WHEELER ARMY AIR FIELD IDAHO AVERAGE BOISE MOUNTAIN HOME MOUNTAIN HOME AIR FOCE BASE ILLINOIS AVERAGE BELLEVILLE CHICAGO FOREST PARK (CHICAGO) GLENVIEW (CHICAGO) GREAT LAKES (NTC) ROCK ISLAND ARSENAL SAVANNAH ARMY DEPOT SCOTT AIR FORCE BASE INDIANA AVERAGE CRANE NWSC FORT BENJAMIN HARRISON GRISSOM AIR RESERVE BASE MILCON 0.95 0.86 0.89 0.83 0.81 0.84 0.80 0.84 0.80 0.85 0.83 0.87 0.88 0.87 0.94 0.88 0.92 0.88 0.96 0.83 0.86 2.14 2.33 2.10 2.03 2.10 2.10 2.10 2.17 2.10 2.47 2.10 2.10 2.10 0.94 0.91 0.97 0.97 1.20 1.10 1.29 1.31 1.29 1.31 0.97 0.96 1.11 0.94 1.05 0.99 1.02 34 UFC 3-701-01 March 2011 Inside US Sustainment 0.96 0.93 1.00 1.04 0.95 1.12 0.91 1.15 1.04 1.03 0.93 0.93 0.89 0.90 1.02 1.02 0.84 0.91 0.95 0.00 0.87 0.83 0.78 0.83 0.92 0.92 0.92 0.83 1.02 1.03 1.01 1.20 1.01 1.14 1.01 0.97 0.96 1.00 1.00 0.96 1.00 1.00 0.95 1.00 1.00 1.00 0.98 0.98 1.10 1.23 1.19 C AN C EL L ED INDIANAPOLIS LOGANSPORT IOWA AVERAGE BURLINGTON DES MOINES IOWA ARMY AMMO PLANT KANSAS AVERAGE FORT LEAVENWORTH FORT RILEY KANSAS ARMY AMMO PLANT MANHATTAN MCCONNELL AIR FORCE BASE WICHITA KENTUCKY AVERAGE FORT CAMPBELL FORT KNOX LEXINGTON LEXINGTON/BLUE GRASS AD LOUISVILLE LOUISVILLE NAVAL AIR STATION LOUISIANA AVERAGE BARKSDALE AIR FORCE BASE FORT POLK LOUISIANA ARMY AMMO PLANT NAS, JRB, NEW ORLEANS NEW ORLEANS NEW ORLEANS ARMY BASE SHREVEPORT MAINE AVERAGE BANGOR BRUNSWICK AREA CG- SOUTHWEST HARBOR CUTLER WINTER HARBOR KITTERY/PORTSMOUTH PORTLAND MARYLAND AVERAGE ABERDEEN PROVING GROUND ANDREWS AIR FORCE BASE ANNAPOLIS BALTIMORE BETHESDA CHELTONHAM (DC) CHESAPEAKE BEACH FORT DETRICK FORT GEORGE G MEADE INDIAN HEAD LEXINGTON PARK PATUXENT RIVER AREA THURMONT MASSACHUSETTS AVERAGE ARMY MAT & MECH LAB MILCON 0.94 0.93 0.99 1.04 0.95 1.12 0.94 1.13 1.07 1.05 0.96 0.96 0.92 0.89 1.02 1.02 0.84 0.91 0.95 0.00 0.89 0.86 0.82 0.86 0.93 0.93 0.93 0.86 1.04 1.04 1.03 1.21 1.03 1.14 1.03 0.98 0.96 0.99 0.99 0.96 0.99 0.99 0.94 0.99 0.99 0.99 1.01 1.01 1.10 1.18 1.14 35 UFC 3-701-01 March 2011 Inside US Sustainment 1.27 1.21 1.44 1.19 1.26 1.27 1.17 1.24 1.24 1.10 1.10 1.12 1.11 1.13 0.85 0.86 0.84 0.84 0.86 0.86 0.97 1.01 1.06 1.01 1.06 1.00 1.11 1.10 1.08 1.06 1.10 1.10 0.97 0.95 0.95 0.99 0.99 1.27 1.33 1.21 1.29 1.29 1.26 1.30 1.08 1.03 1.12 1.25 1.24 1.24 1.32 C AN C EL L ED BOSTON CG- CAPE CODE CG- MARTHA'S VINEYARD FITCHBURG FORT DEVENS HANSCOMB AIR FORCE BASE MICHIGAN AVERAGE DETRIOT DETROIT ARSENAL KI SAWYER AIR FORCE BASE MARQUETTE MINNESOTA AVERAGE DULUTH MINNEAPOLIS MISSISSIPPI AVERAGE BILOXI COLUMBUS COLUMBUS AIR FORCE BASE GULFPORT AREA KEESLER AIR FORCE BASE MERIDIAN NAVAL AIR STATION MISSOURI AVERAGE FORT LEONARD WOOD KANSAS CITY LAKE CITY ARMY AMMO PLANT SEDALIA ST LOUIS ARMY AMMO PLANT WHITEMAN AIR FORCE BASE MONTANA AVERAGE BILLINGS GREAT FALLS MALMSTROM AIR FORCE BASE NEBRASKA AVERAGE CORNHUSKER ARMY AMMO PLANT GRAND ISLAND OFFUTT AIR FORCE BASE OMAHA NEVADA AVERAGE CREECH AIR FORCE BASE FALLON HAWTHORNE HAWTHORNE ARMY AMMO PLANT LAS VEGAS NELLIS AIR FORCE BASE NEW HAMPSHIRE AVERAGE CONCORD PORTSMOUTH NEW JERSEY AVERAGE BAYONNE MOT CG- CAPE MAY EARLE NAVAL WEAPONS STATION MILCON 1.21 1.18 1.42 1.15 1.22 1.21 1.15 1.21 1.21 1.08 1.08 1.07 1.07 1.07 0.87 0.88 0.86 0.86 0.88 0.88 0.98 0.98 1.07 0.98 1.03 0.99 1.08 1.09 1.09 1.07 1.11 1.11 0.96 0.95 0.95 0.98 0.98 1.26 1.29 1.22 1.29 1.29 1.22 1.25 1.08 1.04 1.12 1.18 1.17 1.22 1.25 36 UFC 3-701-01 March 2011 Inside US Sustainment 1.25 1.32 1.25 1.25 1.24 1.28 1.25 0.95 0.96 0.95 1.00 0.98 0.95 1.01 1.08 1.04 1.12 1.40 1.15 1.36 1.59 1.12 1.04 1.04 1.05 1.59 1.52 1.04 0.81 0.94 0.93 0.83 0.88 0.79 0.94 0.88 0.78 0.82 1.04 0.95 0.95 1.14 1.14 0.91 0.89 0.95 0.89 0.94 0.89 0.96 0.90 C AN C EL L ED FORT DIX FORT MONMOUTH LAKEHURST MCGUIRE AIR FORCE BASE NEWARK PICATINNY ARSENAL TRENTON NEW MEXICO AVERAGE ALAMOGORDO ALBUQUERQUE CANNON AIR FORCE BASE HOLLOMAN AIR FORCE BASE KIRTLAND AIR FORCE BASE WHITE SANDS MISSILE RANGE NEW YORK AVERAGE ALBANY NEW YORK BUFFALO CG- MONTAUK FORT DRUM LONG ISLAND NEW YORK CITY NIAGARA ROME LABORATORY SCOTIA SENECA ARMY DEPOT STATION ISLAND US MILITARY ACADEMY WATERVLIET ARSENAL NORTH CAROLINA AVERAGE CAMP LEJEUNE AREA CHERRY POINT FAYETTEVILLE FORT BRAGG GREENSBORO NEW RIVER POPE AIR FORCE BASE SEYMOUR JOHNSON AFB SUNNY POINT NORTH DAKOTA AVERAGE GRAND FORKS GRAND FORKS AIR FORCE BASE MINOT MINOT AIR FORCE BASE OHIO AVERAGE DAYTON RAVENA ARMY AMMO PLANT WRIGHT-PATTERSON AFB YOUNGSTOWN OKLAHOMA AVERAGE ALTUS AIR FORCE BASE FORT SILL MILCON 1.20 1.25 1.20 1.20 1.17 1.21 1.20 0.96 0.97 0.95 1.01 0.99 0.95 1.02 1.06 1.03 1.10 1.33 1.15 1.29 1.50 1.10 1.05 1.03 1.05 1.05 1.48 1.03 0.86 0.99 0.98 0.88 0.92 0.84 0.99 0.92 0.82 0.87 1.08 0.99 0.99 1.17 1.17 0.90 0.88 0.94 0.88 0.92 0.93 1.00 0.94 37 UFC 3-701-01 March 2011 Inside US Sustainment 0.90 0.77 0.89 0.89 0.92 1.05 1.05 1.05 1.14 1.08 0.99 1.05 0.96 0.99 0.99 1.21 0.95 1.13 1.17 1.17 1.12 1.16 1.08 0.84 0.94 0.89 0.89 0.79 0.79 0.89 0.85 0.96 0.97 0.97 0.95 0.84 0.88 0.83 0.86 0.86 0.83 0.77 0.89 0.89 0.91 0.80 0.86 0.89 0.97 0.83 0.89 C AN C EL L ED LAWTON MCALESTER ARMY AMMO PLANT OKLAHOMA CITY TINKER AIR FORCE BASE VANCE AIR FORCE BASE OREGON AVERAGE PENDLETON PORTLAND UMATILLA ARMY DEPOT PENNSYLVANIA AVERAGE CARLISLE BARRACKS INDIANTOWN GAP MR LETTERKENNY ARMY DEPOT MECHANICSBURG AREA NEW CUMBERLAND ARMY DEPOT PHILADELPHIA PITTSBURGH TOBYHANNA ARMY DEPOT WARMINSTER WILLOW GROVE RHODE ISLAND AVERAGE NEWPORT PROVIDENCE SOUTH CAROLINA AVERAGE BEAUFORT AREA CHARLESTON CHARLESTON AIR FORCE BASE COLUMBIA FORT JACKSON GOOSE CREEK SHAW AIR FORCE BASE SOUTH DAKOTA AVERAGE ELLSWORTH AIR FORCE BASE RAPID CITY SIOUX FALLS TENNESSEE AVERAGE ARNOLD AIR FORCE BASE CHATTANOOGA MEMPHIS MILLINGTON NAVAL SUPPORT ACTIVITY VOLUNTEER ORDINANCE WORKS TEXAS AVERAGE BROOKS AIR FORCE BASE CAMP BULLIS CG- HOUSTON CORPUS CHRISTI AREA DALLAS DYESS AIR FORCE BASE FORT BILSS FORT HOOD FORT SAM HOUSTON MILCON 0.94 0.81 0.93 0.93 0.96 1.03 1.02 1.03 1.11 1.04 0.99 1.05 0.96 0.99 0.99 1.15 0.93 1.11 1.11 1.11 1.09 1.13 1.05 0.88 0.99 0.92 0.92 0.83 0.83 0.92 0.88 1.00 1.01 1.01 0.98 0.86 0.90 0.85 0.87 0.87 0.85 0.79 0.91 0.91 0.92 0.85 0.88 0.93 1.01 0.86 0.91 38 UFC 3-701-01 March 2011 Inside US Sustainment 0.89 0.85 0.85 0.89 0.83 0.89 0.89 0.80 0.67 0.89 0.80 0.86 0.74 0.79 0.88 1.02 1.07 1.01 1.06 1.02 1.01 1.07 0.92 0.91 0.94 0.89 0.92 0.92 0.95 0.95 1.00 0.92 0.91 0.92 1.00 0.91 0.92 0.92 0.92 1.00 0.93 0.87 0.95 0.98 0.92 1.09 1.24 1.24 1.20 1.17 1.09 C AN C EL L ED FORT WORTH GOODFELLOW AIR FORCE BASE INGLESIDE NAVAL STATION KELLY FIELD KINGSVILLE AREA LACKLAND AIR FORCE BASE LAUGHLIN AIR FORCE BASE LONE STAR ARMY AMMO PLANT LONGHORN ARMY AMMO PLANT RANDOLPH AIR FORCE BASE RED RIVER ARMY DEPOT REESE AIR FORCE BASE SAN ANGELO SAN ANTONIO SHEPPARD AIR FORCE BASE UTAH AVERAGE DUGWAY PROVING GROUND FORT DOUGLAS HILL AIR FORCE BASE OGDEN SALT LAKE CITY TOOELE ARMY DEPOT VERMONT AVERAGE BURLINGTON MONTPELIER VIRGINIA AVERAGE CAMP PEARY CHESAPEAKE DAHLGREN FORT A. P. HILL FORT BELVOIR FORT EUSTIS FORT LEE FORT MONROE FORT MYER FORT PICKETT FORT STORY LANGLEY AIR FORCE BASE NORFOLK QUANTICO RADFORD ARMY AMMO PLANT RICHMOND VINT HILL FARMS WALLOPS ISLAND YORKTOWN WASHINGTON AVERAGE BANGOR BREMERTON CG- PORT ANGELES CG- SEATTLE EVERETT MILCON 0.91 0.89 0.91 0.89 0.91 0.87 0.91 0.93 0.85 0.74 0.91 0.85 0.78 0.80 0.89 1.04 1.09 1.04 1.08 1.04 1.04 1.09 0.96 0.94 0.98 0.91 0.94 0.94 0.96 0.96 1.00 0.94 0.94 0.94 1.00 0.94 0.94 0.94 0.94 1.00 0.95 0.89 0.96 1.02 0.94 1.08 1.21 1.21 1.18 1.15 1.08 39 UFC 3-701-01 March 2011 Inside US Sustainment 1.02 1.16 1.24 1.25 1.16 1.24 1.02 1.16 1.28 1.10 0.94 0.91 0.97 1.32 1.10 1.13 1.15 1.15 1.06 1.15 0.98 0.96 1.01 1.01 1.01 1.01 1.01 1.01 Outside US MILCON Sustainment 1.63 1.63 1.47 1.47 1.18 1.18 1.08 1.08 1.26 1.26 1.14 1.14 2.34 2.34 2.23 2.23 1.92 1.92 1.77 1.77 1.46 1.46 1.33 1.33 1.14 1.14 1.04 1.04 AN C EL L ED FAIRCHILD AIR FORCE BASE FORT LEWIS INDIAN ISLAND KEYPORT MCCHORD AIR FORCE BASE SILVERDALE SPOKANE TACOMA WHIDBEY ISLAND YAKIMA FIRING RANGE WEST VIRGINIA AVERAGE BLUEFIELD CHARLESTON SUGAR GROVE WISCONSIN AVERAGE BADGER ARMY AMMO PLANT CG - STURGEON BAY FORT MCCOY MADISON MILWAUKEE WYOMING AVERAGE CASPER CHEYENNE F E WARREN AIR FORCE BASE WASHINGTON DC AVERAGE BOLLING AIR FORCE BASE FORT MCNAIR WALTER REED ARMY MEDICAL CENTER MILCON 1.02 1.14 1.21 1.22 1.14 1.19 1.02 1.14 1.26 1.09 0.94 0.92 0.96 1.31 1.08 1.12 1.10 1.13 1.05 1.12 1.02 1.01 1.04 1.04 1.00 1.00 1.00 1.00 47.9200 97.8700 C AFGHANISTAN KUBUL AFGHANI ALBANIA TIRANA ALBANIAN LEKE ALGERIA ALGIERS ALGERI AMERICAN SAMOA AMERICAN SAMOA US DOLLAR ANTIGUA ANTIGUA ANTIGUA DOLLAR AUSTRALIA PERTH AUSTRALIA AZERBAIJAN BAKU Currency Exchange Rate 72.2122 1.0000 2.6150 1.1053 40 UFC 3-701-01 March 2011 Outside US MANAT AZORES LAJES EURO BAHAMAS ANDROS ISLAND BAHAMA DOLLAR BAHRAIN ASKAR BAHRAINI DINAR BELGIUM BRUSSELS MONS/CHIEVERES EURO BOSNIA SARAJEVO MARKA BULGARIA SOFIA LEV CAMBODIA PHNOM PENH RIEL CANADA ARGENTIA/NEWFOUNDLAND CANADIAN DOLLAR CHINA HONG KONG YUAN CRETE SOUDA BAY EURO CROATIA ZAGREB LEV CUBA GUANTANAMO US DOLLAR CZECH REPUBLIC PRAGUE CZECH KORUNY DIEGO GARCIA DIEGO GARCIA US DOLLAR EGYPT CAIRO EGYPTIAN POUND ESTONIA TALLINN EURO MILCON Sustainment 1.14 1.14 1.80 1.80 1.57 1.57 1.41 1.41 1.66 1.66 1.48 1.48 Currency Exchange Rate 0.8028 0.7491 1.0000 ED 0.3770 1.41 1.47 1.36 1.34 1.40 1.28 1.27 1.27 1.21 1.21 AN C EL L 0.7491 1.02 1.02 0.91 0.91 1.10 1.10 1.32 1.32 1.34 1.34 1.25 1.25 1.22 1.22 1.18 1.18 1.30 1.30 1.20 1.20 1.10 1.10 1.01 1.01 1.66 1.66 1.51 1.51 1.15 1.15 1.09 1.09 2.53 2.53 2.35 2.35 1.53 1.53 1.41 1.41 0.92 0.92 0.84 0.84 1.3824 1.3824 4155.0000 1.0581 6.8279 0.7491 C 1.3824 1.0000 18.3817 1.0000 5.445 0.7491 41 UFC 3-701-01 March 2011 Outside US FRANCE MARCEILLE EURO GEORGIA REPUBLIC TBILISI GEORGIA LARI GERMANY FRANKFURT KAISERSLAUTERN GRAFENWOEHR/HOHENFELS EURO GREECE ATHENS EURO GREENLAND THULE DANISH KRONE GUAM GUAM US DOLLAR HORN OF AFRICA DJIBOUTI DJIBOUTIAN FRANC HUNGARY BUDAPEST HUNGARIAN FLORINT ICELAND REYKJAVIK KRONA INDIA NEW DELHI INDIAN RUPEE INDONESIA JAKARTA MILCON Sustainment 1.47 1.47 1.38 1.38 0.93 0.93 0.82 0.82 1.26 1.32 1.20 1.20 1.23 1.28 1.24 1.16 1.34 1.34 1.28 1.28 2.67 2.67 2.56 2.56 Currency Exchange Rate 0.7491 ED 1.7202 0.7491 AN C EL L 0.7491 2.21 2.21 2.11 2.11 2.05 2.05 1.80 1.80 1.02 1.02 0.93 0.93 1.98 1.98 1.89 1.89 1.43 1.43 1.33 1.33 1.04 1.04 0.97 0.97 1.98 1.98 1.79 1.79 1.13 1.13 1.09 1.09 1.30 1.30 1.23 1.23 1.49 1.48 1.41 1.54 1.43 1.39 1.39 1.33 1.45 1.34 5.5819 1.0000 157.0000 192.628 105.2688 46.0582 C INDONESIAN RUPIAH IRAQ BAGHDAD IRAQUI DINAR IRELAND DUBLIN EURO ISRAEL TEL AVIV SHEKELS ITALY NAPLES SIGONELLA AVIANO GAETA 12859.790 0 1153.5000 0.7491 3.7213 42 UFC 3-701-01 March 2011 Outside US Sustainment 1.57 1.44 1.44 1.47 1.40 1.51 1.35 1.43 1.45 1.35 1.38 1.33 1.40 1.26 1.35 1.36 Currency Exchange Rate 0.7491 ED 91.2524 1.31 1.31 1.19 1.19 1.06 1.17 1.06 1.04 1.02 1.05 1.04 1.04 1.04 0.96 1.08 0.95 0.94 0.93 0.95 0.95 0.95 0.95 0.99 0.99 0.90 0.90 1.59 1.59 1.44 1.44 2.64 2.64 2.58 2.58 0.94 0.94 0.86 0.86 1.32 1.32 1.20 1.20 0.86 0.86 0.79 0.79 2.20 2.20 2.07 2.07 1.02 1.02 0.92 0.92 1.33 1.33 1.27 1.27 EL L AN C VICENZA EURO JAPAN ATSUGI MISAWA OKINAWA TOKYO IWAKUNI YOKOSUKA YEN JORDAN AMMAN JORDANIAN DINAR SOUTH KOREA DMZ ZONE AREA KUNSAN OSAN SEOUL TONG DU CHON TAEGU PYONGTAEK PUSAN SOUTH KOREAN WON KOSOVO PRISTINA EURO KUWAIT KUWAIT CITY KUWAITI DINAR KWAJALEIN KWAJALEIN US DOLLAR LATVIA RIGA LATVIAN LAT LEBANON BEIRUT LEBANON POUND LITHUANIA VILNIUS LITHUANIAN LITAS MIDWAY ISLAND MIDWAY ISLAND US DOLLAR MOROCCO CASABLANCA DIRHAM NETHERLANDS OSS EURO MILCON 1099.5183 0.7491 0.2872 1.0000 C 0.5007 1504.5000 2.4406 1.0000 7.9797 0.7491 43 UFC 3-701-01 March 2011 Outside US Sustainment 1.23 1.23 1.09 1.09 2.28 2.28 2.17 2.17 1.63 1.63 1.52 1.52 1.49 1.49 1.36 1.36 1.20 1.20 1.09 1.09 1.23 1.23 1.10 1.10 0.99 0.99 0.91 0.91 1.26 1.26 1.17 1.17 1.18 1.18 1.09 1.09 1.38 1.38 1.25 1.25 0.99 0.99 0.90 0.90 1.39 1.39 1.23 1.23 2.04 2.04 1.89 1.89 1.43 1.43 1.33 1.33 1.37 1.39 1.36 1.28 1.29 1.28 1.13 1.08 1.17 1.15 1.04 0.98 1.07 1.06 Currency Exchange Rate 1.4000 1.0000 ED 6.0905 0.3851 EL L 1.0000 AN C NEW ZEALAND WELLINGTON NEW ZEALAND DOLLAR NORTHERN MARIANA SAIPAN US DOLLAR NORWAY OSLO NORWEGIAN KRONE OMAN RUWI RIAL PANAMA PANAMA CITY US DOLLAR PHILIPPINES SUBIC BAY PHILPPINE PESO POLAND WARSAW ZLOTYCH PORTUGAL LISBON EURO PUERTO RICO SAN JUAN US DOLLAR QATAR DOHA RIYAL ROMANIA BUCHAREST ROMANIAN LEU SAUDI ARABIA RIYADH SAUDI RIYAL SEYCHELLES ISLAND SEYCHELLES ISLAND US DOLLAR SINGAPORE SINGAPORE CITY SINGAPORE DOLLAR SPAIN ROTA MORON EURO THAILAND BANGKOK CHANG RAI KORAT MILCON 46.2300 2.8741 0.7491 1.0000 3.6412 2.9636 C 3.7502 1.0000 1.4246 0.7491 44 UFC 3-701-01 March 2011 Outside US 4-2 Sustainment 1.18 1.20 1.15 1.08 1.10 1.06 1.05 1.05 0.94 0.94 1.25 1.25 1.11 1.11 1.36 1.35 1.37 1.31 1.36 1.35 1.35 1.25 1.23 1.28 1.21 1.27 1.25 1.29 1.37 1.37 1.37 1.37 2.45 2.45 2.32 2.32 Currency Exchange Rate 33.1230 1.4139 ED 8.0055 EL L 3.6728 0.5917 1.0000 1.0000 C BAHT TURKEY ANKARA INCIRLICK TURKISH LIRA UKRAINE KIEV HRYVNIA UNITED ARAB EMIRATES DUBAI DIRHAM UNITED KINGDOM FAIRFORD/CROUGHTON LAKENHEATH MENWITH HILL MILDENHALL ST. MAWGAN WEST RUISLIP BRITISH POUND VIRGIN ISLANDS ST. THOMAS US DOLLAR WAKE ISLAND WAKE ISLAND US DOLLAR MILCON ESCALATION AN Tables 4-2, 4-3, and 4-4 provide escalation (inflation) factors used to adjust unit costs in Tables 2 and 3 (expressed in base-year dollars) to the desired year, as follows: 4-2.1 Military Construction C Military construction project estimates that use unit costs from Table 2 should use the military construction escalation factor from table 4-2 for the expected midpoint of construction as described in UFC 3-700-01A. 45 UFC 3-701-01 March 2011 Table 4-2: Military Construction Escalation Rates Historical MonthENR DoD Year Indices SPI (raw) (Note 4) 100.00 104.89 98.32 96.83 2011 2012 2013 2014 2015 2016 1.50% 1.60% 1.70% 1.70% 1.80% 1.80% Oct-10 Oct-11 Oct-12 Oct-13 Oct-14 Oct-15 Oct-16 2017 1.80% Oct-17 EL L 3745 4129 4265 4431 4535 (Note 3) (Note 5) 1.0000 1.0150 1.0312 1.0487 1.0665 1.0857 1.1052 1.1251 C Oct-03 Oct-04 Oct-05 Oct-06 Oct-07 Oct-08 Oct-09 Oct-10 (Note 2) ED (Note 1) Budget Guidance Projected FY Annual Midpoint Escalation factor escalation of rate constr AN Note 1: The historical index through October 2007 is the Engineering News Record Building Construction Index (ENR BCI). Note 2: The historical index from October 2007 is the DoD Selling Price Index (SPI), representing the average of the RLB Construction Cost Index, Turner Construction Cost Index, and Saylor Subcontracting Index. DoD established the SPI to more accurately represent actual (historical) market escalation as experienced by DoD as the project owner for the type of construction in the portfolio. Previously, DoD used the Engineering News Record Building Cost Index (BCI). The BCI tracks the cost of three basic materials and one skilled labor type, but does not account for other pricing influences (such as risk and competition) that impact total delivered price to the project owner. Saylor ceased publishing their index in October 2009, and the BLS PPI for NAICS 236223 is now the third index used in the computation. C Note 3: Annual rates for military construction budget authority published by USD (Comptroller) in December 2010. Note 4: Midpoint of construction is the assumed month and year half way through a typical 15 month project awarded in April of the fiscal year. Interpolate between published escalation factors as necessary. Note 5: The escalation factor is the cumulative (compounded) annual inflation rate from the base year. Use these factors to escalate project estimates using unit costs in Table 2 to the expected midpoint of construction, in accordance with UFC 3-700-01A. 4-2.2 Plant Replacement Value Escalation Rates Plant Replacement Value (PRV) calculations that use replacement unit costs from Table 3 should use the escalation factor from table 4-3 for the desired program year. 46 UFC 3-701-01 March 2011 Table 4-3: PRV Escalation Rates Budget Guidance Projected FY Annual Program Escalation factor escalation Year rate 2011 2012 2013 2014 2015 2016 (Note 2) 1.50% 1.60% 1.70% 1.70% 1.80% 1.80% 2011 2012 2013 2014 2015 2016 1.0000 1.0150 1.0312 1.0488 1.0666 1.0858 ED (Note 1) 4-2.3 EL L Note 1: Annual rates for military construction budget authority published by USD (Comptroller) in December 2010. Note 2: Use these factors to adjust plant replacement value to future years. Facilities Sustainment and Operation C AN C Modeled facilities sustainment and operation cost estimates that use unit costs from Table 3 should use the O&M escalation factor from table 4D for the desired program year. 47 UFC 3-701-01 March 2011 Table 4-4: Operation and Maintenance Escalation Rates Budget Guidance FY Annual escalation rate Projected Program Escalation factor Year (Note 1) 1.40% 1.50% 1.70% 1.70% 1.70% 1.70% 2011 2012 2013 2014 2015 2016 1.0000 1.0140 1.0292 1.0467 1.0645 1.0826 ED 2011 2012 2013 2014 2015 2016 (Note 2) C AN C EL L Note 1: Annual rates for O&M budget authority published by USD (Comptroller) in December 2010. Note 2: Use these factors to adjust sustainment and operation costs to future years. 48