************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 12 15.16 (November 2012) -------------------------------Preparing Activity: USACE New UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated January 2016 ************************************************************************** SECTION TABLE OF CONTENTS DIVISION 32 - EXTERIOR IMPROVEMENTS SECTION 32 12 15.16 WARM-MIX ASPHALT AIRFIELD PAVING 11/12 PART 1 GENERAL 1.1 FULL PAYMENT 1.1.1 Method of Measurement 1.1.2 Basis of Payment 1.2 PERCENT PAYMENT 1.2.1 Mat and Joint Densities 1.2.2 Pay Factor Based on In-place Density 1.2.3 Payment Adjustment for Smoothness 1.2.4 Laboratory Air Voids and Theoretical Maximum Density 1.2.5 Mean Absolute Deviation 1.2.6 Pay Adjustment Based on Grade 1.3 REFERENCES 1.4 SYSTEM DESCRIPTION 1.4.1 Asphalt Mixing Plant 1.4.2 Hauling Equipment 1.4.3 Material Transfer Vehicle (MTV) 1.4.4 Asphalt Pavers 1.4.4.1 Receiving Hopper 1.4.4.2 Automatic Grade Controls 1.4.5 Rollers 1.5 SUBMITTALS 1.6 QUALITY ASSURANCE 1.6.1 Sublot Sampling 1.6.2 Additional Sampling and Testing 1.6.3 In-place Density 1.6.4 Surface Smoothness 1.6.4.1 Smoothness Requirements 1.6.4.2 Testing Method 1.7 ENVIRONMENTAL REQUIREMENTS PART 2 PRODUCTS 2.1 AGGREGATES 2.1.1 Coarse Aggregate 2.1.2 Fine Aggregate SECTION 32 12 15.16 Page 1 2.1.3 Mineral Filler 2.1.4 Aggregate Gradation 2.2 ASPHALT CEMENT BINDER 2.3 WMA TECHNOLOGIES/PRODUCTS 2.4 MIX DESIGN 2.4.1 JMF Requirements 2.4.2 Adjustments to JMF 2.5 RECYCLED WMA 2.5.1 RAP Aggregates and Asphalt Cement 2.5.2 RAP Mix PART 3 EXECUTION 3.1 CONTRACTOR QUALITY CONTROL 3.1.1 General Quality Control Requirements 3.1.2 Testing Laboratory 3.1.3 Quality Control Testing 3.1.3.1 Asphalt Content 3.1.3.2 Aggregate Properties 3.1.3.3 Temperatures 3.1.3.4 Aggregate Moisture 3.1.3.5 Moisture Content of Mixture 3.1.3.6 Laboratory Air Voids, VMA, Marshall Stability and Flow 3.1.3.7 Moisture Susceptibility 3.1.3.8 In-Place Density 3.1.3.9 Grade and Smoothness 3.1.3.10 Additional Testing 3.1.3.11 QC Monitoring 3.1.4 Sampling 3.1.5 Control Charts 3.2 PREPARATION OF ASPHALT BINDER MATERIAL 3.3 PREPARATION OF MINERAL AGGREGATE 3.4 PREPARATION OF WARM-MIX ASPHALT MIXTURE 3.5 PREPARATION OF THE UNDERLYING SURFACE 3.6 TEST SECTION 3.6.1 Sampling and Testing for Test Section 3.6.2 Additional Test Sections 3.7 TESTING LABORATORY 3.8 TRANSPORTING AND PLACING 3.8.1 Transporting 3.8.2 Placing 3.9 COMPACTION OF MIXTURE 3.9.1 General 3.9.2 Segregation 3.10 JOINTS 3.10.1 Transverse Joints 3.10.2 Longitudinal Joints 3.10.3 WMA-Portland Cement Concrete Joints -- End of Section Table of Contents -- SECTION 32 12 15.16 Page 2 ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-32 12 15.16 (November 2012) -------------------------------Preparing Activity: USACE New UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated January 2016 ************************************************************************** SECTION 32 12 15.16 WARM-MIX ASPHALT AIRFIELD PAVING 11/12 ************************************************************************** NOTE: This guide specification covers the requirements for bituminous intermediate and wearing courses (central-plant warm-mix) for airfields using Marshall or Gyratory compaction method. Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Do not edit or rewrite the unbracketed text without the express consent of the Corps of Engineers Transportation Systems Center (TSMCX), the Air Force major command (MAJCOM) paving engineers, or the Naval Facilities Engineering Command (NAVFAC). Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). ************************************************************************** PART 1 GENERAL ************************************************************************** NOTE: Modifications must be made to this guide specification during conversion to a project specification in accordance with the NOTES which are located throughout the document. These NOTES are instructions to the designer, and will not appear in the project specification. This guide specification only pertains to the warm-mix asphalt (WMA) aspects of the project and not to any surface preparation requirements dealing SECTION 32 12 15.16 Page 3 with aggregate base courses, milling, or tack and prime coats. Surface preparation requirements should be covered by either including them in this guide specification or by adding pertinent sections to the project documents. This specification utilizes a Quality Assurance and Quality Control (QA/QC) construction management philosophy. Quality Assurance refers to the actions performed by the Government or designated representative Engineer to assure the final product meets the job requirements (see paragraph QUALITY ASSURANCE). Results of QA testing are the basis for pay. Quality Control refers to the actions of the Contractor to monitor the construction and production processes and to correct these processes when out of control. Results of QC testing are reported daily on the process control charts maintained by the Contractor. Quality Control is covered in paragraph CONTRACTOR QUALITY CONTROL. ************************************************************************** 1.1 1.1.1 FULL PAYMENT Method of Measurement ************************************************************************** NOTE: For unit-price contracts, include first bracketed statements and delete the second set. For lump sum contracts, delete the first bracketed statements and include the second set. Lump sum contracts should not be used when the job exceeds 1000 metric tons. ************************************************************************** [The amount paid for will be the number of metric short tons of WMA mixture used in the accepted work. WMA mixture shall be weighed after mixing, and no separate payment will be made for weight of asphalt cement or other additives incorporated herein.] [Measurement of the quantity of WMA, per ton placed and accepted, shall be made for the purposes of assessing the pay factors stipulated below.] 1.1.2 Basis of Payment ************************************************************************** NOTE: For unit-price contracts, include first bracketed statements and delete the second set. For lump sum contracts, delete the first bracketed statements and include the second set. Include prescriptive unit price based on the Government/Engineer estimate for payment adjustment. lump sum contracts should not be used when the job exceeds 1000 metric tons. ************************************************************************** [Quantities of WMA, determined as specified above, will be paid for at respective contract unit prices or at reduced prices adjusted in accordance with paragraphs PERCENT PAYMENT and QUALITY ASSURANCE. Payment will constitute full compensation for furnishing all materials, equipment, SECTION 32 12 15.16 Page 4 plant, and tools; and for all labor and other incidentals necessary to complete work required by this section of the specification.] [The measured quantity of WMA will be paid for and included in the lump sum contract price. If less than 100 percent payment is due based on the pay factors stipulated in paragraph QUALITY ASSURANCE, a unit price of [_____] per ton will be used for purposes of calculating the payment reduction.] 1.2 PERCENT PAYMENT When a lot of material fails to meet the specification requirements for 100 percent pay as outlined in the following paragraphs, that lot shall be removed and replaced, or accepted at a reduced price which will be computed by multiplying the unit price by the lot's pay factor. The lot pay factor is determined by taking the lowest computed pay factor based on either laboratory air voids, in-place density, grade or smoothness (each discussed below). Pay factors based on different criteria (i.e., laboratory air voids and in-place density) of the same lot will not be multiplied together to get a lower lot pay factor. At the end of the project, an average of all lot pay factors will be calculated. If this average lot pay factor exceeds 95.0 percent and no individual lot has a pay factor less than 75.1 percent, then the percent payment for the entire project will be 100 percent of the unit bid price. If the average lot pay factor is less than 95.0 percent, then each lot will be paid for at the unit price multiplied by the lot's pay factor. For any lots which are less than 2000 metric short tons, a weighted lot pay factor will be used to calculate the average lot pay factor. 1.2.1 Mat and Joint Densities The average in-place mat and joint densities are expressed as a percentage of the average theoretical maximum density (TMD) for the lot. The average TMD for each lot will be determined as the average TMD of the two random samples per lot. The average in-place mat density and joint density for a lot are determined and compared with Table 1 to calculate a single pay factor per lot based on in-place density, as described below. First, a pay factor for both mat density and joint density are determined from Table 1. The area associated with the joint is then determined and will be considered to be 3 m 10 feet wide times the length of completed longitudinal construction joint in the lot. This area will not exceed the total lot size. The length of joint to be considered will be that length where a new lane has been placed against an adjacent lane of WMA pavement, either an adjacent freshly paved lane or one paved at any time previously. The area associated with the joint is expressed as a percentage of the total lot area. A weighted pay factor for the joint is determined based on this percentage (see example below). The pay factor for mat density and the weighted pay factor for joint density is compared and the lowest selected. This selected pay factor is the pay factor based on density for the lot. When the TMD on both sides of a longitudinal joint is different, the average of these two TMD will be used as the TMD needed to calculate the percent joint density. Rejected lots shall be removed and replaced. Rejected areas adjacent to longitudinal joints shall be removed 100 mm 4 inches into the cold (existing) lane. All density results for a lot will be completed and reported within 24 hours after the construction of that lot. SECTION 32 12 15.16 Page 5 Total area of lot = 30,000 square feet. (4) Length of completed longitudinal construction joint = 2000 feet. a. Step 1: Determine pay factor based on mat density and on joint density, using Table 1: Mat density of 93.2 percent = 98.3 pay factor. Joint density of 91.5 percent = 97.3 pay factor. b. Step 2: Determine ratio of joint area (length of longitudinal joint x 10 ft) to mat area (total paved area in the lot): Multiply the length of completed longitudinal construction joint by the specified 10 ft. width and divide by the mat area (total paved area in the lot). (2000 ft. x 10 ft.)/30000 sq.ft. = 0.6667 ratio of joint area to mat area (ratio). c. Step 3: Weighted pay factor (wpf) for joint is determined as indicated below: wpf = joint pay factor + (100 - joint pay factor) (1 - ratio) wpf = 97.3 + (100-97.3) (1-.6667) = 98.2 percent d. Step 4: Compare weighted pay factor for joint density to pay factor for mat density and select the smaller: Pay factor for mat density: 98.3 percent. joint density: 98.2 percent Weighted pay factor for Select the smaller of the two values as pay factor based on density: 98.2 percent 1.2.3 Payment Adjustment for Smoothness a. Straightedge Testing. Location and deviation from straightedge for all measurements shall be recorded. When between 5.0 and 10.0 percent of all measurements made within a lot exceed the tolerance specified in paragraph Smoothness Requirements below, after any reduction of high spots or removal and replacement, the computed pay factor for that lot based on surface smoothness, will be 95 percent. When more than 10.0 percent of all measurements exceed the tolerance, the computed pay factor will be 90 percent. When between 15.0 and 20.0 percent of all measurements exceed the tolerance, the computed pay factor will be 75 percent. When 20.0 percent or more of the measurements exceed the tolerance, the lot shall be removed and replaced at no additional cost to the Government/Owner. Regardless of the above, any small individual area with surface deviation which exceeds the tolerance given above by more than 50 percent, shall be corrected by diamond grinding to meet the specification requirements above or shall be removed and replaced at no additional cost to the Government/Owner. b. Profilograph Testing. Location and data from all profilograph measurements shall be recorded. When the Profile Index of a lot exceeds the tolerance specified in paragraph Smoothness Requirements by 16 mm/km 1.0 inch/mile, but less than 32 mm/km 2.0 inches/mile, after any reduction of high spots or removal and replacement, the computed pay factor for that lot based on surface smoothness will be 95 percent. When the Profile Index exceeds the tolerance by 32 mm/km 2.0 SECTION 32 12 15.16 Page 7 Total area of lot = 30,000 square feet. (4) Length of completed longitudinal construction joint = 2000 feet. a. Step 1: Determine pay factor based on mat density and on joint density, using Table 1: Mat density of 93.2 percent = 98.3 pay factor. Joint density of 91.5 percent = 97.3 pay factor. b. Step 2: Determine ratio of joint area (length of longitudinal joint x 10 ft) to mat area (total paved area in the lot): Multiply the length of completed longitudinal construction joint by the specified 10 ft. width and divide by the mat area (total paved area in the lot). (2000 ft. x 10 ft.)/30000 sq.ft. = 0.6667 ratio of joint area to mat area (ratio). c. Step 3: Weighted pay factor (wpf) for joint is determined as indicated below: wpf = joint pay factor + (100 - joint pay factor) (1 - ratio) wpf = 97.3 + (100-97.3) (1-.6667) = 98.2 percent d. Step 4: Compare weighted pay factor for joint density to pay factor for mat density and select the smaller: Pay factor for mat density: 98.3 percent. joint density: 98.2 percent Weighted pay factor for Select the smaller of the two values as pay factor based on density: 98.2 percent 1.2.3 Payment Adjustment for Smoothness a. Straightedge Testing. Location and deviation from straightedge for all measurements shall be recorded. When between 5.0 and 10.0 percent of all measurements made within a lot exceed the tolerance specified in paragraph Smoothness Requirements below, after any reduction of high spots or removal and replacement, the computed pay factor for that lot based on surface smoothness, will be 95 percent. When more than 10.0 percent of all measurements exceed the tolerance, the computed pay factor will be 90 percent. When between 15.0 and 20.0 percent of all measurements exceed the tolerance, the computed pay factor will be 75 percent. When 20.0 percent or more of the measurements exceed the tolerance, the lot shall be removed and replaced at no additional cost to the Government/Owner. Regardless of the above, any small individual area with surface deviation which exceeds the tolerance given above by more than 50 percent, shall be corrected by diamond grinding to meet the specification requirements above or shall be removed and replaced at no additional cost to the Government/Owner. b. Profilograph Testing. Location and data from all profilograph measurements shall be recorded. When the Profile Index of a lot exceeds the tolerance specified in paragraph Smoothness Requirements by 16 mm/km 1.0 inch/mile, but less than 32 mm/km 2.0 inches/mile, after any reduction of high spots or removal and replacement, the computed pay factor for that lot based on surface smoothness will be 95 percent. When the Profile Index exceeds the tolerance by 32 mm/km 2.0 SECTION 32 12 15.16 Page 7 inches/mile, but less than 47 mm/km 3.0 inches/mile, the computed pay factor will be 90 percent. When the Profile Index exceeds the tolerance by 47 mm/km 3.0 inches/mile, but less than 63 mm/km 4.0 inches/mile, the computed pay factor will be 75 percent. When the Profile Index exceeds the tolerance by 63 mm/km 4.0 inches/mile or more, the lot shall be removed and replaced at no additional cost to the Government/Owner. Regardless of the above, any small individual area with surface deviation which exceeds the tolerance given above by more than 79 mm/km 5.0 inches/mile or more, shall be corrected by grinding to meet the specification requirements above or shall be removed and replaced at no additional cost to the Government/Owner. 1.2.4 Laboratory Air Voids and Theoretical Maximum Density Laboratory air voids will be calculated in accordance with ASTM D3203/D3203M by determining the density of each lab compacted specimen using the laboratory-prepared, thoroughly dry method in ASTM D2726/D2726M and determining the theoretical maximum density (TMD) of every other sublot sample using ASTM D2041/D2041M. Laboratory air void calculations for each sublot will use the latest theoretical maximum density values obtained, either for that sublot or the previous sublot. The mean absolute deviation of the four laboratory air void contents (one from each sublot) from the JMF air void content will be evaluated and a pay factor determined from Table 2. All laboratory air void tests will be completed and reported within 24 hours after completion of construction of each lot. The TMD is also used for computation of compaction, as required in paragraph: Mat and Joint Densities above. 1.2.5 Mean Absolute Deviation An example of the computation of mean absolute deviation for laboratory air voids is as follows: Assume that the laboratory air voids are determined from 4 random samples of a lot (where 3 specimens were compacted from each sample). The average laboratory air voids for each sublot sample are determined to be 3.5, 3.0, 4.0, and 3.7. Assume that the target air voids from the JMF is 4.0. The mean absolute deviation is then: Mean Absolute Deviation = (|3.5 - 4.0| + |3.0 - 4.0| + |4.0 - 4.0| + |3.7 4.0|)/4 = (0.5 + 1.0 + 0.0 + 0.3)/4 = (1.8)/4 = 0.45 The mean absolute deviation for laboratory air voids is determined to be 0.45. It can be seen from Table 2 that the lot's pay factor based on laboratory air voids, is 100 percent. Table 2. Pay Factor Based on Laboratory Air Voids Mean Absolute Deviation of Lab Air Voids from JMF Pay Factor, Percent O.60 or less 100 0.61 - 0.80 98 0.81 - 1.00 95 SECTION 32 12 15.16 Page 8 Table 2. Pay Factor Based on Laboratory Air Voids Mean Absolute Deviation of Lab Air Voids from JMF Pay Factor, Percent 1.01 - 1.20 90 Above 1.20 reject (0) 1.2.6 Pay Adjustment Based on Grade ************************************************************************** NOTE: The grade and surface smoothness requirements specified below are for the final wearing surface only. If there is a requirement to test and control the grade and smoothness for the intermediate courses, i.e., when the intermediate courses will be exposed to traffic, slight modifications to this specification will be required. ************************************************************************** Within 5 working days after completion of a particular lot incorporating the final wearing course, test the final wearing surface of the pavement for conformance with specified plan grade requirements. All testing shall be performed in the presence of the Contracting Officer/Engineer. The final wearing surface of pavement shall conform to the elevations and cross sections shown and shall vary not more than 9 mm 0.03 foot for runways or 15 mm 0.05 foot for taxiways and aprons from the plan grade established and approved at site of work. Finished surfaces at juncture with other pavements shall coincide with finished surfaces of abutting pavements. Deviation from the plan elevation will not be permitted in areas of pavements where closer conformance with planned elevation is required for the proper functioning of drainage and other appurtenant structures involved. The grade will be determined by running lines of levels at intervals of 7.6 m 25 feet, or less, longitudinally and transversely, to determine the elevation of the completed pavement surface. Detailed notes of the results of the testing shall be kept and a copy furnished to the Government/Engineer immediately after each day's testing. When more than 5 percent of all measurements made within a lot are outside the 9 or 15 mm 0.03 or 0.05 foot tolerance, the pay factor based on grade for that lot will be 95 percent. In areas where the grade exceeds the tolerance by more than 50 percent, remove the surface lift full depth; and replace the lift with WMA to meet specification requirements, at no additional cost to the Government/Owner. Diamond grinding may be used to remove high spots to meet grade requirements. Skin patching for correcting low areas or planing or milling for correcting high areas will not be permitted. 1.3 REFERENCES ************************************************************************** NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's SECTION 32 12 15.16 Page 9 Reference reference Reference the issue Article to automatically place the in the Reference Article. Also use the Wizard's Check Reference feature to update dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. ************************************************************************** The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) AASHTO M 156 (2013) Standard Specification for Requirements for Mixing Plants for Hot-Mixed, Hot-Laid Bituminous Paving Mixtures AASHTO M 320 (2010; 2015) Standard Specification for Performance-Graded Asphalt Binder AASHTO T 308 (2010; R 2015) Standard Method of Test for Determining the Asphalt Binder Content of Hot Mix Asphalt (HMA) by the Ignition Method AASHTO T 329 (2015) Standard Test Method for Moisture Content of Hot Mix Asphalt (HMA) by Oven Method ASPHALT INSTITUTE (AI) AI MS-2 (2015) Asphalt Mix Design Methods ASTM INTERNATIONAL (ASTM) ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing ASTM C1252 (2006) Standard Test Methods for Uncompacted Void Content of Fine Aggregate (as Influenced by Particle Shape, Surface Texture, and Grading) ASTM C127 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate ASTM C128 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate ASTM C131/C131M (2014) Standard Test Method for Resistance SECTION 32 12 15.16 Page 10 to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates ASTM C142/C142M (2010) Standard Test Method for Clay Lumps and Friable Particles in Aggregates ASTM C29/C29M (2009) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate ASTM C566 (2013) Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying ASTM C88 (2013) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate ASTM D140/D140M (2015) Standard Practice for Sampling Bituminous Materials ASTM D1461 (2011) Moisture or Volatile Distillates in Bituminous Paving Mixtures ASTM D2041/D2041M (2011) Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures ASTM D2172/D2172M (2011) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures ASTM D2419 (2014) Sand Equivalent Value of Soils and Fine Aggregate ASTM D242/D242M (2009; R 2014) Mineral Filler for Bituminous Paving Mixtures ASTM D2489/D2489M (2008) Estimating Degree of Particle Coating of Bituminous-Aggregate Mixtures ASTM D2726/D2726M (2014) Bulk Specific Gravity and Density of Non-Absorptive Compacted Bituminous Mixtures ASTM D3203/D3203M (2011) Percent Air Voids in Compacted Dense and Open Bituminous Paving Mixtures ASTM D3381/D3381M (2013) Viscosity-Graded Asphalt Cement for Use in Pavement Construction ASTM D3665 (2012) Random Sampling of Construction Materials ASTM D3666 (2013) Standard Specification for Minimum Requirements for Agencies Testing and SECTION 32 12 15.16 Page 11 Inspecting Road and Paving Materials ASTM D4125/D4125M (2010) Asphalt Content of Bituminous Mixtures by the Nuclear Method ASTM D4791 (2010) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate ASTM D4867/D4867M (2009; R 2014) Effect of Moisture on Asphalt Concrete Paving Mixtures ASTM D5444 (2015) Mechanical Size Analysis of Extracted Aggregate ASTM D6307 (2010) Asphalt Content of Hot Mix Asphalt by Ignition Method ASTM D6925 (2014) Standard Test Method for Preparation and Determination of the Relative Density of Hot Mix Asphalt (HMA) Specimens by Means of the Superpave Gyratory Compactor ASTM D6926 (2010) Standard Practice for Preparation of Bituminous Specimens Using Marshall Apparatus ASTM D6927 (2015) Standard Test Method for Marshall Stability and Flow of Bituminous Mixtures ASTM D946/D946M (2009a) Penetration-Graded Asphalt Cement for Use in Pavement Construction ASTM D979/D979M (2015) Sampling Bituminous Paving Mixtures STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION (CALTRANS) CTM 526 (2002) Operation of California Profilograph and Evaluation of Profiles U.S. ARMY CORPS OF ENGINEERS (USACE) COE CRD-C 171 1.4 (1995) Standard Test Method for Determining Percentage of Crushed Particles in Aggregate SYSTEM DESCRIPTION Perform the work consisting of pavement courses composed of mineral aggregate and asphalt material heated and mixed in a central mixing plant and placed on a prepared course. WMA designed and constructed in accordance with this section shall conform to the lines, grades, thicknesses, and typical cross sections shown on the drawings. Construct each course to the depth, section, or elevation required by the drawings and rolled, finished, and approved before the placement of the next course. Submit proposed Placement Plan, indicating lane widths, longitudinal joints, and transverse joints for each course or lift. SECTION 32 12 15.16 Page 12 1.4.1 Asphalt Mixing Plant Plants used for the preparation of WMA shall conform to the requirements of AASHTO M 156 with the following changes: a. Truck Scales. Weigh the asphalt mixture on approved scales furnished by the Contractor, or on certified public scales at the Contractor's expense. Scales shall be inspected and sealed at least annually by an approved calibration laboratory. b. Testing Facilities. Provide laboratory facilities at the plant for the use of the Government's Engineer's acceptance testing and the Contractor's quality control testing. c. Inspection of Plant. The Contracting Officer Engineer shall have access at all times, to all areas of the plant for checking adequacy of equipment; inspecting operation of the plant; verifying weights, proportions, and material properties; checking the temperatures maintained in the preparation of the mixtures and for taking samples. Provide assistance as requested, for the Government Engineer to procure any desired samples. d. Storage Bins. The asphalt mixture may be stored in non-insulated storage bins for a period of time not exceeding 3 hours. The asphalt mixture may be stored in insulated storage bins for a period of time not exceeding 8 hours. The mix drawn from bins shall meet the same requirements as mix loaded directly into trucks. 1.4.2 Hauling Equipment Trucks used for hauling WMA shall have tight, clean, and smooth metal beds. To prevent the mixture from adhering to them, the truck beds shall be lightly coated with a minimum amount of paraffin oil, lime solution, or other approved material. Petroleum based products shall not be used as a release agent. Each truck shall have a suitable cover to protect the mixture from adverse weather. When necessary to ensure that the mixture will be delivered to the site at the specified temperature, truck beds shall be insulated or heated and covers (tarps) shall be securely fastened. 1.4.3 Material Transfer Vehicle (MTV) ************************************************************************** NOTE: A Material Transfer Vehicle (MTV) is required for runway and taxiway construction. The use of an MTV is optional for shoulder construction. ************************************************************************** Material transfer Vehicles shall be required due to the improvement in smoothness and decrease in both physical and thermal segregation. To transfer the material from the hauling equipment to the paver, use a self-propelled, material transfer vehicle that can deliver material to the paver without making contact with the paver. The MTV shall be able to move back and forth between the hauling equipment and the paver providing material transfer to the paver, while allowing the paver to operate at a constant speed. The Material Transfer Vehicle will have remixing and storage capability to prevent physical and thermal segregation. 1.4.4 Asphalt Pavers Mechanical spreading and finishing equipment shall consist of a SECTION 32 12 15.16 Page 13 Table 3. Straightedge Surface Smoothness--Pavements Pavement Category All other airfields and helicopter paved areas b. Direction of Testing Tolerance, mm inches Longitudinal 61/4 Transverse 61/4 Profilograph Testing: The finished surfaces of the pavements shall have no abrupt change of 3 mm 1/8 inch or more, and all pavement shall have a Profile Index not greater than specified in Table 4 when tested with an approved California-type profilograph. If the extent of the pavement in either direction is less than 60 m 200 feet, that direction shall be tested by the straightedge method and shall meet requirements specified above. Table 4. Profilograph Surface Smoothness--Pavements Pavement Category Runways Taxiways Shoulders (outside edge strip) Direction of Testing Maximum Specified Profile Index (mm/kminch/mile) Longitudinal 1107 Transverse (Use Straightedge) Longitudinal 1409 Transverse (Use Straightedge) Transverse (Use Straightedge) Longitudinal Not required Calibration Hardstands and Compass Swinging Bases All Other Airfield and Helicopter Paved Areas 1.6.4.2 (Use Straightedge) Longitudinal 1409 Transverse 1409 Testing Method After the final rolling, but not later than 24 hours after placement, the surface of the pavement in each entire lot shall be tested in such a manner as to reveal all surface irregularities exceeding the tolerances specified above. Separate testing of individual sublots is not required. If any pavement areas are diamond ground, these areas shall be retested immediately after grinding. The area corrected by grinding shall not exceed 10 percent of the total area of the lot. The entire area of the pavement shall be tested in both a longitudinal and a transverse direction on parallel lines. The transverse lines shall be 4.5 m 15 feet or less SECTION 32 12 15.16 Page 19 apart, as directed. The longitudinal lines shall be at the centerline of each paving lane for lines less than 6.1 m 20 feet and at the third points for lanes 6.1 m 20 feet or greater. Other areas having obvious deviations shall also be tested. Longitudinal testing lines shall be continuous across all joints. a. Straightedge Testing. The straightedge shall be held in contact with the surface and moved ahead one-half the length of the straightedge for each successive measurement. The amount of surface irregularity shall be determined by placing the freestanding (unleveled) straightedge on the pavement surface and allowing it to rest upon the two highest spots covered by its length, and measuring the maximum gap between the straightedge and the pavement surface in the area between these two high points. b. Profilograph Testing. Profilograph testing shall be performed using approved equipment and procedures described in CTM 526. The equipment shall utilize electronic recording and automatic computerized reduction of data to indicate "must-grind" bumps and the Profile Index for the pavement. The "blanking band" shall be 5 mm 0.2 inches wide and the "bump template" shall span 25 mm 1 inch with an offset of 10 mm 0.4 inch. The profilograph shall be operated by an approved, factory-trained operator on the alignments specified above. A copy of the reduced tapes shall be furnished the Government Engineer at the end of each day's testing. c. Bumps ("Must Grind" Areas). Any bumps ("must grind" areas) shown on the profilograph trace which exceed 10 mm 0.4 inch in height shall be reduced by diamond grinding until they do not exceed 7.5 mm 0.3 inch when retested. Such grinding shall be tapered in all directions to provide smooth transitions to areas not requiring grinding. The following will not be permitted: (1) skin patching for correcting low areas, (2) planing or milling for correcting high areas. At the Contractor's option, pavement areas, including ground areas, may be rechecked with the profilograph in order to record a lower Profile Index. 1.7 ENVIRONMENTAL REQUIREMENTS ************************************************************************** NOTE: The temperature requirements in Table 5 are included to avoid problems with the Contractor achieving density because the mix cools too fast. Waivers to these requirements, for isolated incidences during production, are applicable if the density requirements are still met. ************************************************************************** The WMA shall not be placed upon a wet surface or when the surface temperature of the underlying course is less than 4 degrees C 40 degrees F. PART 2 2.1 PRODUCTS AGGREGATES Aggregates shall consist of crushed stone, crushed gravel, crushed slag, screenings, natural sand and mineral filler, as required. The portion of material retained on the 4.75 mm No. 4 sieve is coarse aggregate. The portion of material passing the 4.75 mm No. 4 sieve and retained on the SECTION 32 12 15.16 Page 20 SD-06 Test Reports Aggregates; G[, [_____]] QC Monitoring SD-07 Certificates Asphalt Cement Binder; G[, [_____]] Testing Laboratory WMA Additive 1.6 QUALITY ASSURANCE ************************************************************************** NOTE: It is highly recommended to keep the Government Engineer's QA testing separate and distinct from the Contractor's QC testing. However, it is recognized that in-house testing capability to provide the QA testing required by this section will not always be available; in this case, it is recommended that an independent material testing company be hired to provide the QA testing for the project. The cost of this testing to assure good long-term performance is very small relative to the overall cost of the construction, and especially compared to the cost of a pavement failure. Although not recommended, this guide specification may be modified to require the Contractor to hire an independent material testing laboratory to perform the QA testing listed in this section. The results would need to be forwarded daily to the Contracting Officer Engineer as the basis for acceptance and pay. This should only be done if there is no way of hiring an independent testing laboratory to perform the QA testing. The QA testing program includes material tests to determine laboratory air voids and in-place density, which are needed to determine percent payment. The project engineer may choose to have additional tests conducted by the QA test agency to monitor aggregate gradation, asphalt content, Marshall stability and flow. These tests would serve as a check to the Contractor's QC testing. Marshall stability and flow could be done at minimal cost since the specimens have to be made anyway for laboratory air void determination. This additional testing, if conducted, is not included as part of this specification since the parameters are not used as a basis of pay. For projects with less than 2000 total metric tons, the entire project can be considered as a single lot. In this case, sublot sampling could occur over several days' production, which could lead to higher sublot variability. ************************************************************************** SECTION 32 12 15.16 Page 16 The Government Engineer's quality assurance (QA) program for this project is separate and distinct from the Contractor's quality control (QC) program specified in Part 3. Testing for acceptability of work will be performed by the Government Engineer or by an independent laboratory hired by the Contracting Officer Engineer, except for grade and smoothness testing which shall be performed by the Contractor. Acceptance of the plant produced mix and in-place requirements will be on a lot to lot basis. A standard lot for all requirements will be equal to 2000 metric short tons. Where appropriate, adjustment in payment for individual lots of WMA will be made based on in-place density, laboratory air voids, grade and smoothness in accordance with the following paragraphs. Grade and surface smoothness determinations will be made on the lot as a whole. Exceptions or adjustments to this will be made in situations where the mix within one lot is placed as part of both the intermediate and surface courses, thus grade and smoothness measurements for the entire lot cannot be made. In order to evaluate laboratory air voids and in-place (field) density, each lot will be divided into four equal sublots. 1.6.1 Sublot Sampling One random mixture sample for determining laboratory air voids, theoretical maximum density, and for any additional testing the Contracting Officer Engineer desires, will be taken from a loaded truck delivering mixture to each sublot, or other appropriate location for each sublot. All samples will be selected randomly, using commonly recognized methods of assuring randomness conforming to ASTM D3665 and employing tables of random numbers or computer programs. Laboratory air voids will be determined from three laboratory compacted specimens of each sublot sample in accordance with ASTM D6926. The specimens will be compacted within 2 hours of the time the mixture was loaded into trucks at the asphalt plant. Samples will not be reheated prior to compaction and insulated containers will be used as necessary to maintain the temperature. 1.6.2 Additional Sampling and Testing The Contracting Officer Engineer reserves the right to direct additional samples and tests for any area which appears to deviate from the specification requirements. The cost of any additional testing will be paid for by the Government/Owner. Testing in these areas will be treated as a separate lot. Payment will be made for the quantity of WMA represented by these tests in accordance with the provisions of this section. 1.6.3 In-place Density For determining in-place density, one random core (100 mm 4 inches or 150 mm 6 inches in diameter) will be taken by the Government Engineer from the mat (interior of the lane) of each sublot, and one random core will be taken from the joint (immediately over joint) of each sublot, in accordance with ASTM D979/D979M. Each random core will be full thickness of the layer being placed. When the random core is less than 25 mm 1 inch thick, it will not be included in the analysis. In this case, another random core will be taken. After air drying to meet the requirements for laboratory-prepared, thoroughly dry specimens, cores obtained from the mat and from the joints will be used for in-place density determination in accordance with ASTM D2726/D2726M. SECTION 32 12 15.16 Page 17 1.6.4 Surface Smoothness ************************************************************************** NOTE: Edit these paragraphs as appropriate to the project. It is desired to restrict surface smoothness testing and evaluation to either straightedge method or profilograph method. Retain the one and delete the other; otherwise, retain both as a Contractor's option. Generally, designer should require use of the profilograph method. If the profilograph method is allowed, and there are areas with dimensions less than 60 m 200 feet in any direction, part of the straightedge method must be retained for these short runs. ************************************************************************** Use [one] [both] of the following methods to test and evaluate surface smoothness of the finished surface of the pavement final grade. All testing shall be performed in the presence of the Contracting Officer Engineer. Detailed notes of the results of the testing shall be kept and a copy furnished to the Government Engineer immediately after each day's testing. The profilograph method shall be used for all longitudinal and transverse testing, except where the runs would be less than 60 m 200 feet in length and the ends where the straightedge shall be used. Where drawings show required deviations from a plane surface (crowns, drainage inlets, etc.), the surface shall be finished to meet the approval of the Contracting Officer Engineer. 1.6.4.1 a. Smoothness Requirements Straightedge Testing: The finished surfaces of the pavements shall have no abrupt change of 3 mm 1/8 inch or more, and all pavements shall be within the tolerances specified in Table 3 when checked with an approved 4 m 12 foot straightedge. Table 3. Straightedge Surface Smoothness--Pavements Pavement Category Runways and taxiway Shoulders (outside edge strip) Calibration hardstands and compass swinging bases Direction of Testing Tolerance, mm inches Longitudinal 31/8 Transverse 61/4 Transverse 61/4 Longitudinal Not required Longitudinal 31/8 Transverse 31/8 SECTION 32 12 15.16 Page 18 Table 3. Straightedge Surface Smoothness--Pavements Pavement Category All other airfields and helicopter paved areas b. Direction of Testing Tolerance, mm inches Longitudinal 61/4 Transverse 61/4 Profilograph Testing: The finished surfaces of the pavements shall have no abrupt change of 3 mm 1/8 inch or more, and all pavement shall have a Profile Index not greater than specified in Table 4 when tested with an approved California-type profilograph. If the extent of the pavement in either direction is less than 60 m 200 feet, that direction shall be tested by the straightedge method and shall meet requirements specified above. Table 4. Profilograph Surface Smoothness--Pavements Pavement Category Runways Taxiways Shoulders (outside edge strip) Direction of Testing Maximum Specified Profile Index (mm/kminch/mile) Longitudinal 1107 Transverse (Use Straightedge) Longitudinal 1409 Transverse (Use Straightedge) Transverse (Use Straightedge) Longitudinal Not required Calibration Hardstands and Compass Swinging Bases All Other Airfield and Helicopter Paved Areas 1.6.4.2 (Use Straightedge) Longitudinal 1409 Transverse 1409 Testing Method After the final rolling, but not later than 24 hours after placement, the surface of the pavement in each entire lot shall be tested in such a manner as to reveal all surface irregularities exceeding the tolerances specified above. Separate testing of individual sublots is not required. If any pavement areas are diamond ground, these areas shall be retested immediately after grinding. The area corrected by grinding shall not exceed 10 percent of the total area of the lot. The entire area of the pavement shall be tested in both a longitudinal and a transverse direction on parallel lines. The transverse lines shall be 4.5 m 15 feet or less SECTION 32 12 15.16 Page 19 apart, as directed. The longitudinal lines shall be at the centerline of each paving lane for lines less than 6.1 m 20 feet and at the third points for lanes 6.1 m 20 feet or greater. Other areas having obvious deviations shall also be tested. Longitudinal testing lines shall be continuous across all joints. a. Straightedge Testing. The straightedge shall be held in contact with the surface and moved ahead one-half the length of the straightedge for each successive measurement. The amount of surface irregularity shall be determined by placing the freestanding (unleveled) straightedge on the pavement surface and allowing it to rest upon the two highest spots covered by its length, and measuring the maximum gap between the straightedge and the pavement surface in the area between these two high points. b. Profilograph Testing. Profilograph testing shall be performed using approved equipment and procedures described in CTM 526. The equipment shall utilize electronic recording and automatic computerized reduction of data to indicate "must-grind" bumps and the Profile Index for the pavement. The "blanking band" shall be 5 mm 0.2 inches wide and the "bump template" shall span 25 mm 1 inch with an offset of 10 mm 0.4 inch. The profilograph shall be operated by an approved, factory-trained operator on the alignments specified above. A copy of the reduced tapes shall be furnished the Government Engineer at the end of each day's testing. c. Bumps ("Must Grind" Areas). Any bumps ("must grind" areas) shown on the profilograph trace which exceed 10 mm 0.4 inch in height shall be reduced by diamond grinding until they do not exceed 7.5 mm 0.3 inch when retested. Such grinding shall be tapered in all directions to provide smooth transitions to areas not requiring grinding. The following will not be permitted: (1) skin patching for correcting low areas, (2) planing or milling for correcting high areas. At the Contractor's option, pavement areas, including ground areas, may be rechecked with the profilograph in order to record a lower Profile Index. 1.7 ENVIRONMENTAL REQUIREMENTS ************************************************************************** NOTE: The temperature requirements in Table 5 are included to avoid problems with the Contractor achieving density because the mix cools too fast. Waivers to these requirements, for isolated incidences during production, are applicable if the density requirements are still met. ************************************************************************** The WMA shall not be placed upon a wet surface or when the surface temperature of the underlying course is less than 4 degrees C 40 degrees F. PART 2 2.1 PRODUCTS AGGREGATES Aggregates shall consist of crushed stone, crushed gravel, crushed slag, screenings, natural sand and mineral filler, as required. The portion of material retained on the 4.75 mm No. 4 sieve is coarse aggregate. The portion of material passing the 4.75 mm No. 4 sieve and retained on the SECTION 32 12 15.16 Page 20 0.075 mm No. 200 sieve is fine aggregate. The portion passing the 0.075 mm No. 200 sieve is defined as mineral filler. Submit sufficient materials to produce 90 kg 200 lb of blended mixture for mix design verification. All aggregate test results and samples shall be submitted to the Contracting Officer Engineer at least 14 days prior to start of construction. Aggregate testing shall have been performed within 90 days of performing the mix design. 2.1.1 Coarse Aggregate ************************************************************************** NOTE: The requirement for sulfate soundness (requirement b., below) may be deleted in climates where freeze-thaw does not occur. However, in those areas where freeze-thaw does not occur, requirement b. should remain if experience has shown that this test separates good performing aggregates from bad performing aggregates. This requirement should be retained for all Navy projects. Percentage of Wear (ASTM C131/C131M) must not exceed 40. Aggregates with a higher percentage of wear may be specified, provided a satisfactory record under similar conditions of service and exposure has been demonstrated. ************************************************************************** Coarse aggregate shall consist of sound, tough, durable particles, free from films of material that would prevent thorough coating and bonding with the asphalt material and free from organic matter and other deleterious substances. The coarse aggregate particles shall meet the following requirements: a. The percentage of loss shall not be greater than 40 [_____] percent after 500 revolutions when tested in accordance with ASTM C131/C131M. b. The sodium sulfate soundness loss shall not exceed 12 percent, or the magnesium sulfate soundness loss shall not exceed 18 percent after five cycles when tested in accordance with ASTM C88. c. At least 75 percent by weight of coarse aggregate shall have at least two or more fractured faces when tested in accordance with COE CRD-C 171. Fractured faces shall be produced by crushing. d. The particle shape shall be essentially cubical and the aggregate shall not contain more than 20 percent, by weight, of flat and elongated particles (3:1 ratio of maximum to minimum) when tested in accordance with ASTM D4791. e. Slag shall be air-cooled, blast furnace slag, and shall have a compacted weight of not less than 1200 kg/cubic meter 75 lb/cu ft when tested in accordance with ASTM C29/C29M. f. Clay lumps and friable particles shall not exceed 0.3 percent, by weight, when tested in accordance with ASTM C142/C142M. 2.1.2 Fine Aggregate ************************************************************************** SECTION 32 12 15.16 Page 21 NOTE: The lower limit for uncompacted void content (requirement c., below) should be set at 45 for fine aggregate angularity unless local experiences indicate that a lower value can be used. There are some aggregates which have a good performance record and have an uncompacted void content less than 45. In no case should the limit be set less than 43. ************************************************************************** Fine aggregate shall consist of clean, sound, tough, durable particles. The aggregate particles shall be free from coatings of clay, silt, or any objectionable material and shall contain no clay balls. The fine aggregate particles shall meet the following requirements: a. The quantity of natural sand (noncrushed material) added to the aggregate blend shall not exceed 15 percent by weight of total aggregate. b. The individual fine aggregate sources shall have a sand equivalent value greater than 45 when tested in accordance with ASTM D2419. c. The fine aggregate portion of the blended aggregate shall have an uncompacted void content greater than 45.0 percent when tested in accordance with ASTM C1252 Method A. d. Clay lumps and friable particles shall not exceed 0.3 percent, by weight, when tested in accordance with ASTM C142/C142M. 2.1.3 Mineral Filler Mineral filler shall be nonplastic material meeting the requirements of ASTM D242/D242M. 2.1.4 Aggregate Gradation ************************************************************************** NOTE: Delete from Table 5, the gradations that will not be used as a part of this project. Generally, the layer thickness should be at least 75 mm 3 inches for gradation 1, 50 mm 2 inches for gradation 2 and 37 mm 1.5 inches for gradation 3 shown in Table 6. Use of gradation 1 must be limited to intermediate courses. Gradation 2 is suitable for intermediate and surface courses. Use of gradation 3 must be limited to shoulders and leveling courses. Do not use gradation 1 for surface courses. ************************************************************************** The combined aggregate gradation shall conform to gradations specified in Table 5, when tested in accordance with ASTM C136/C136M and ASTM C117, and shall not vary from the low limit on one sieve to the high limit on the adjacent sieve or vice versa, but grade uniformly from coarse to fine. The JMF shall be within the specification limits; however, the gradation can exceed the limits when the allowable deviation from the JMF shown in Tables 8 and 9 are applied. SECTION 32 12 15.16 Page 22 Table 5. Aggregate Gradations Gradation 1 Gradation 2 Gradation 3 Sieve Size, mm inch Percent Passing by Mass Percent Passing by Mass Percent Passing by Mass 25.01 100 --- --- 19.03/4 90-100 100 --- 12.51/2 68-88 90-100 100 9.53/8 60-82 69-89 90-100 4.75No. 4 45-67 53-73 58-78 2.36No. 8 32-54 38-60 40-60 1.18No. 16 22-44 26-48 28-48 0.60No. 30 15-35 18-38 18-38 0.30No. 50 9-25 11-27 11-27 0.15No. 100 6-18 6-18 6-18 0.075No. 200 3-6 3-6 3-6 2.2 ASPHALT CEMENT BINDER ************************************************************************** NOTE: Performance Graded (PG) asphalt binders should be specified wherever available. The same grade PG binder used by the state highway department in the area should be considered as the base grade for the project (e.g. the grade typically specified in that specific location for dense graded mixes on highways with design ESALS less than 10 million). The exception would be that grades with a low temperature higher than PG XX-22 should not be used (e.g. PG XX-16 or PG XX-10), unless the Engineer has had successful experience with them. Typically, rutting is not a problem on airport pavements. However, at airports with a history of stacking on end of runways and taxiway areas, rutting has accrued due to the slow speed of loading on the pavement. If there has been rutting on the project or it is anticipated that stacking may accrue during the design life of the project, then the following grade "bumping" should be applied for the top 125 mm 5 inches of paving in the end of runway and taxiway areas: for aircraft tire pressure between 0.7 and 1.4 MPa 100 and 200 psi, increase the high temperature one grade; for aircraft tire SECTION 32 12 15.16 Page 23 pressure greater than 1.4 MPa 200 psi, increase the high temperature two grades. For Navy projects, a high temperature increase of two grades is required. Each grade adjustment is 6 degrees C. Polymer Modified Asphalt, PMA, has shown to perform very well in these areas. The low temperature grade should remain the same. The Engineer may lower the low temperature grade to comply with the recommendations of the FHWA's software program "LTPPBind", if it is believed to be appropriate. ************************************************************************** Asphalt cement binder shall conform to AASHTO M 320 Performance Grade (PG) [_____]. [As an alternate, ASTM D3381/D3381M Table 2, Viscosity Grade [_____] or ASTM D946/D946M Penetration Grade [_____] may be used]. Test data indicating grade certification shall be provided by the supplier at the time of delivery of each load to the mix plant. When WMA technology involves additives, the asphalt cement shall be graded with the asphalt cement additive included. Copies of these certifications shall be submitted to the Contracting Officer Engineer. The supplier is defined as the last source of any modification to the binder. The Contracting Officer Engineer may sample and test the binder at the mix plant at any time before or during mix production. Samples for this verification testing shall be obtained in accordance with ASTM D140/D140M and in the presence of the Contracting Officer Engineer. These samples shall be furnished to the Contracting Officer Engineer for the verification testing, which shall be at no cost to the Contractor. Submit 20 L 5 gallon sample of the asphalt cement specified for mix design verification and approval not less than 14 days before start of the test section. 2.3 WMA TECHNOLOGIES/PRODUCTS WMA technologies/products shall have a record of good performance and shall be included on the local state DOT's qualified products list, if the DOT maintains a qualified products list. Also, the WMA technologies/products shall be included in at least two out of the following three states DOT's qualified products lists: Texas, Virginia and Florida. These qualified products lists can be found at each state DOT's website. 2.4 MIX DESIGN ************************************************************************** NOTE: Use 75 blow Marshall hand-held hammer compaction or 75 gyration Superpave gyratory compaction for all pavements designed for tire pressures of 690 kPa 100 psi or higher. Use 50 Blow Marshall hand-held hammer compaction or 50 gyration Superpave gyratory compaction for all shoulder pavements and pavements designed for tire pressures less than 690 kPa 100 psi. For Marshall mixes, delete the column in Table 6 which does not apply, unless the project includes both 75 Blow and 50 Blow mixes. SECTION 32 12 15.16 Page 24 Table 8. Action and Suspension Limits for the Parameters to be Plotted on Individual and Running Average Control Charts Individual Samples Parameter to be Plotted Running Average of Last Four Samples Action Limit Suspension Limit 0.4 0.5 Asphalt content, percent deviation from JMF target; plus or minus value Action Limit Suspension Limit 0.2 0.3 Laboratory Air Voids, percent No specific action and suspension limits set since deviation from JMF target value this parameter is used to determine percent payment In-place Mat Density, percent of TMD No specific action and suspension limits set since this parameter is used to determine percent payment In-place Joint Density, percent of TMD No specific action and suspension limits set since this parameter is used to determine percent payment TSR, percent minimum 73 70 Gradation 1 13.3 13.0 13.5 13.0 Gradation 2 14.3 14.0 14.5 14.0 Gradation 3 15.3 15.0 15.0 15.0 VMA Table 8 cont'd. Marshall Compaction Stability, N pounds (minimum) 75 blow JMF 78301760 72901640 95602150 90302030 50 blow JMF 4230950 3690830 60001350 54701230 8 min. 7 min. 9 min. 8 min. 16 max. 17 max. 15 max. 16 max. 8 min. 7 min. 9 min. 8 min. 18 max. 19 max. 17 max. 18 max. Flow, 0.25 mm 0.01 inches 75 blow JMF 50 blow JMF SECTION 32 12 15.16 Page 33 3.2 PREPARATION OF ASPHALT BINDER MATERIAL The asphalt cement material shall be heated avoiding local overheating and providing a continuous supply of the asphalt material to the mixer at a uniform temperature. The temperature of asphalt binder shall be no more than 132 degrees C 270 degrees F when added to the aggregates. 3.3 PREPARATION OF MINERAL AGGREGATE The aggregate for the mixture shall be heated and dried prior to mixing. No damage shall occur to the aggregates due to the maximum temperature and rate of heating used. The temperature of the aggregate and mineral filler shall not exceed 132 degrees C 270 degrees F when the asphalt binder is added. The temperature shall not be lower than is required to obtain complete coating and uniform distribution on the aggregate particles and to provide a mixture of satisfactory workability. 3.4 PREPARATION OF WARM-MIX ASPHALT MIXTURE The aggregates, asphalt cement, and WMA additives, if added separately at the plant, shall be weighed or metered and introduced into the mixer in the amount specified by the JMF. The combined materials shall be mixed until the aggregate obtains a thorough and uniform coating of asphalt binder (testing in accordance with ASTM D2489/D2489M may be required by the Contracting Officer) and is thoroughly distributed throughout the mixture. The moisture content of all WMA upon discharge from the plant shall not exceed 0.5 percent by total weight of mixture as measured by ASTM D1461. 3.5 PREPARATION OF THE UNDERLYING SURFACE ************************************************************************** NOTE: If the underlying surface to be paved is an unbound granular layer, a prime coat should be applied, especially if this layer will be exposed to weather for an extended period of time prior to covering with an asphalt mixture. Benefits derived from a prime coat include an additional weatherproofing of the base, improving the bond between the base and WMA layer, and preventing the base from shifting under construction equipment. If the prime coat requirement is not a separate pay item and is waived from this contract, an adjustment to the contract price should be made. Environmental laws in certain states may not allow prime coats to be applied. If the underlying surface to be paved is an existing asphalt or concrete layer, a tack coat should always be used to ensure an adequate bond between layers. Tack and prime coat requirements will need to be covered in the contract documents. ************************************************************************** Immediately before placing the WMA, the underlying course shall be cleaned of dust and debris. A [prime coat] [and/or] [tack coat] shall be applied in accordance with the contract specifications. SECTION 32 12 15.16 Page 34 Table 6. Marshall Design Criteria Test Property 75 Blow Mix 50 Blow Mix (4) Select the JMF asphalt content corresponding to an air void content of 4 percent. Verify the other properties of Table 6 meet the specification requirements at this asphalt content. Table 6. Superpave Gyratory Compaction Criteria Test Property Value 4(1) Air voids, percent Percent Voids in mineral aggregate (minimum) See Table 7 Dust Proportion(2) 0.8-1.2 TSR, minimum percent 75 (1) Select the JMF asphalt content corresponding to an air void content of 4 percent. Verify the other properties of Table 6 meet the specification requirements at this asphalt content. (2) Dust Proportion is calculated as the aggregate content, expressed as a percent of mass, passing the 0.075 mm No. 200 sieve, divided by the effective asphalt content, in percent of total mass of the mixture. Table 7. Minimum Percent Voids in Mineral Aggregate (VMA)(1) Aggregate (See Table 5) Minimum VMA, percent Gradation 1 13 Gradation 2 14 Gradation 3 15 (1) Calculate VMA in accordance with AI MS-2, based on ASTM D2726/D2726M bulk specific gravity for the aggregate. 2.4.2 Adjustments to JMF The JMF for each mixture shall be in effect until a new formula is approved in writing by the Contracting Officer Engineer. Should a change in sources of any materials be made, a new mix design shall be performed and a new JMF approved before the new material is used. The Contractor will be allowed to make minor adjustments within the specification limits to the JMF to optimize mix volumetric properties. Adjustments to the original JMF shall be limited to plus or minus 4 percent on the 4.75 mm No. 4 and coarser sieves; plus or minus 3 percent on the 2.36 mm No. 8 to 0.30 mm No. 50 sieves; and plus or minus 1 percent on the 0.15 mm No. 100 sieve. Adjustments to the JMF shall be limited to plus or minus 1.0 percent on the 0.075 mm No. 200 sieve. Asphalt content adjustments shall be limited to plus or minus 0.40 from the original JMF. If adjustments are needed that SECTION 32 12 15.16 Page 27 exceed these limits, a new mix design shall be developed. 2.5 RECYCLED WMA ************************************************************************** NOTE: Reclaimed Asphalt Pavement (RAP) should not be used for surface mixes, except on shoulders. It can be used very effectively in lower layers, or for shoulders. The Contractor should be able to use RAP, up to 30 percent, as long as the resulting recycled mix meets all requirements that are specified for virgin mixtures. Remove these paragraphs if RAP is not used. ************************************************************************** Recycled WMA shall consist of reclaimed asphalt pavement (RAP), coarse aggregate, fine aggregate, mineral filler, and asphalt cement. The RAP shall be of a consistent gradation and asphalt content and properties. RAP stockpiles shall be free from contamination, including coal-tar sealers. When RAP is fed into the plant, the maximum RAP chunk size shall not exceed 50 mm 2 inches. The individual aggregates in a RAP chunk shall not exceed the maximum size aggregate of the gradation specified in Table 6. The recycled WMA mix shall be designed using procedures contained in AI MS-2. The job mix shall meet the requirements of paragraph MIX DESIGN. RAP shall only be used for shoulder surface course mixes and for any intermediate courses. The amount of RAP shall be limited to 30 percent. 2.5.1 RAP Aggregates and Asphalt Cement The blend of aggregates used in the recycled mix shall meet the requirements of paragraph AGGREGATES. The percentage of asphalt in the RAP shall be established for the mixture design according to ASTM D2172/D2172M using the appropriate dust correction procedure. 2.5.2 RAP Mix ************************************************************************** NOTE: The appropriate test should be selected to conform to the grade of new asphalt specified. If a penetration grade is specified, use penetration test. If a viscosity grade is specified, use a viscosity test. If a PG asphalt binder is specified, use the dynamic shear rheometer and bending beam tests. ************************************************************************** The blend of new asphalt cement and the RAP asphalt binder shall meet the [penetration] [viscosity] requirements in paragraph ASPHALT CEMENT BINDER. For PG graded asphalt binders, adjust as follows: a. a. For 0-20 percent recycled binder content - no change in virgin binder selection. b. For 20+ to 30 percent recycled binder content - select virgin binder one grade softer than normal. SECTION 32 12 15.16 Page 28 a. Pave the WMA side of the joint in a direction parallel to the joint. b. Place the WMA side sufficiently high so that when fully compacted the WMA will be greater than 3 mm 1/8 inch but less than 6 mm 1/4 inch higher than the PCC side of the joint. c. Compaction shall be provided with steel wheel rollers and at least one rubber tire roller. The rubber tire roller shall be at least 18 metric tons 20 tons in weight and have tires that are inflated to at least 620 kPa 90 psi. Avoid spalling the PCC during placement and compaction of the WMA. Steel wheel rollers shall be operated in a way that prevents spalling the PCC. Any damage to PCC edges or joints shall be repaired as directed by the Contracting OfficerEngineer. If damage to the PCC joint or edge exceeds a total of 1 m 3 feet, the PCC panel shall be removed and replaced at no additional expense to the Government. d. After compaction is finished the WMA shall be leveled by grinding so that the WMA side is less than 3 mm 1/8 inch higher than the PCC side. The WMA immediately adjacent to the joint shall not be lower than the PCC after the grinding operation. Transition the grinding into the WMA in a way that ensures good smoothness and provides drainage of water. The joint and adjacent materials when completed shall meet all of the requirements for grade and smoothness. Measure smoothness across the PCC-WMA joint using a 4 m 12 feet straightedge. The acceptable tolerance is 3 mm 1/8 inch. e. Consider the WMA next to the PCC as a separate lot for evaluation. Lots are based on individual lifts. Do not comingle cores from different lifts for density evaluation purposes. Take four cores for each lot of material placed adjacent to the joint. The size of lot shall be 3 m 10 feet wide by the length of the joint being paved. Lots are based on individual lifts and shall not be comingled for density evaluation purposes. Locate the center of each of the four cores 150 mm 6 inches from the edge of the concrete. Take each core at a random location along the length of the joint. The requirements for density for this lot, adjacent to the joint, are the same as that for the mat specified earlier. f. All procedures, including repair of damaged PCC, shall be in accordance with the approved Quality Control Plan. -- End of Section -- SECTION 32 12 15.16 Page 39 the Contractor in writing of any noted deficiencies concerning the laboratory facility, equipment, supplies, or testing personnel and procedures. When the deficiencies are serious enough to adversely affect test results, the incorporation of the materials into the work shall be suspended immediately and will not be permitted to resume until the deficiencies are corrected. 3.1.3 Quality Control Testing Perform all quality control tests applicable to these specifications and as set forth in the Quality Control Program. The testing program shall include, but shall not be limited to, tests for the control of asphalt content, aggregate gradation, temperatures, aggregate moisture, moisture in the asphalt mixture, laboratory air voids, stability, flow, in-place density, grade and smoothness. A Quality Control Testing Plan shall be developed as part of the Quality Control Program. 3.1.3.1 Asphalt Content A minimum of two tests to determine asphalt content will be performed per lot (a lot is defined in paragraph QUALITY ASSURANCE) by one of the following methods: extraction method in accordance with ASTM D2172/D2172M, Method A or B, the ignition method in accordance with the AASHTO T 308, ASTM D6307, or the nuclear method in accordance with ASTM D4125/D4125M, provided each method is calibrated for the specific mix being used. For the extraction method, the weight of ash, as described in ASTM D2172/D2172M, shall be determined as part of the first extraction test performed at the beginning of plant production; and as part of every tenth extraction test performed thereafter, for the duration of plant production. The last weight of ash value obtained shall be used in the calculation of the asphalt content for the mixture. 3.1.3.2 Aggregate Properties Aggregate gradations shall be determined a minimum of twice per lot from mechanical analysis of recovered aggregate in accordance with ASTM D5444 or ASTM D6307. For batch plants, aggregates shall be tested in accordance with ASTM C136/C136M using actual batch weights to determine the combined aggregate gradation of the mixture. The specific gravity of each aggregate size grouping shall be determined for each 18,000 metric tons 20,000 tons in accordance with ASTM C127 or ASTM C128. Fractured faces for gravel sources shall be determined for each 18,000 metric tons 20,000 tons in accordance with COE CRD-C 171. The uncompacted void content of manufactured sand shall be determined for each 18,000 metric tons 20,000 tons in accordance with ASTM C1252 Method A. 3.1.3.3 Temperatures Temperatures shall be checked at least four times per lot, at necessary locations, to determine the temperature at the dryer, the asphalt cement in the storage tank, the asphalt mixture at the plant, and the asphalt mixture at the job site. 3.1.3.4 Aggregate Moisture The moisture content of aggregate used for production shall be determined a minimum of once per lot in accordance with ASTM C566. SECTION 32 12 15.16 Page 30 3.1.3.5 Moisture Content of Mixture The moisture content of the mixture shall be determined at least twice per lot in accordance with AASHTO T 329. 3.1.3.6 Laboratory Air Voids, VMA, Marshall Stability and Flow Mixture samples shall be taken at least four times per lot and compacted into specimens, [using [50] [75] blows per side with the Marshall hand-held hammer as described in ASTM D6926.] [using [50] [75] gyrations of the Superpave gyratory compactor as described in ASTM D6925.] After compaction, the laboratory air voids and VMA of each specimen shall be determined[, as well as the Marshall stability and flow, as described in ASTM D6927].. The VMA shall be within the limits of Table 8. 3.1.3.7 Moisture Susceptibility Determine the Tensile Strength Ratio (TSR) by ASTM D4867/D4867M for test section production and at least once for every five lots. TSR values shall be not less than 75 percent. 3.1.3.8 In-Place Density Conduct any necessary testing to ensure the specified density is achieved. A nuclear gauge or other non-destructive testing device may be used to monitor pavement density. 3.1.3.9 Grade and Smoothness Conduct the necessary checks to ensure the grade and smoothness requirements are met in accordance with paragraph QUALITY ASSURANCE. 3.1.3.10 Additional Testing Any additional testing, which the Contractor deems necessary to control the process, may be performed at the Contractor's option. 3.1.3.11 QC Monitoring Submit all QC test results to the Contracting Officer Engineer on a daily basis as the tests are performed. The Contracting Officer Engineer reserves the right to monitor any of the Contractor's quality control testing and to perform duplicate testing as a check to the Contractor's quality control testing. 3.1.4 Sampling When directed by the Contracting Officer Engineer, sample and test any material which appears inconsistent with similar material being produced, unless such material is voluntarily removed and replaced or deficiencies corrected by the Contractor. All sampling shall be in accordance with standard procedures specified. 3.1.5 Control Charts For process control, establish and maintain linear control charts on both individual samples and the running average of last four samples for the parameters listed in Table 8, as a minimum. These control charts shall be posted as directed by the Contracting Officer Engineer and shall be kept SECTION 32 12 15.16 Page 31 current at all times. The control charts shall identify the project number, the test parameter being plotted, the individual sample numbers, the Action and Suspension Limits listed in Table 8 applicable to the test parameter being plotted, and the Contractor's test results. Target values (JMF) shall also be shown on the control charts as indicators of central tendency for the cumulative percent passing, asphalt content, and laboratory air voids parameters. When the test results exceed either applicable Action Limit, take immediate steps to bring the process back in control. When the test results exceed either applicable Suspension Limit, halt production until the problem is solved. When the Suspension Limit is exceeded for individual values or running average values, the Contracting Officer Engineer has the option to require the Contractor to remove and replace the material represented by the samples or to leave in place and base acceptance on mixture volumetric properties and in place density. Use the control charts as part of the process control system for identifying trends so that potential problems can be corrected before they occur. Decisions concerning mix modifications shall be made based on analysis of the results provided in the control charts. The Quality Control Plan shall indicate the appropriate action which shall be taken to bring the process into control when certain parameters exceed their Action Limits. Table 8. Action and Suspension Limits for the Parameters to be Plotted on Individual and Running Average Control Charts Individual Samples Parameter to be Plotted Running Average of Last Four Samples Action Limit Suspension Limit 4.75 mm No. 4 sieve, Cumulative Percent Passing, deviation from JMF target; plus or minus values 6 8 4 5 0.6 mm No. 30 sieve, Cumulative Percent Passing, deviation from JMF target; plus or minus values 4 6 3 4 0.075 mm No. 200 sieve, Cumulative Percent Passing, deviation from JMF target; plus or minus values 1.4 2.0 1.1 1.5 SECTION 32 12 15.16 Action Limit Suspension Limit Page 32 Table 8. Action and Suspension Limits for the Parameters to be Plotted on Individual and Running Average Control Charts Individual Samples Parameter to be Plotted Running Average of Last Four Samples Action Limit Suspension Limit 0.4 0.5 Asphalt content, percent deviation from JMF target; plus or minus value Action Limit Suspension Limit 0.2 0.3 Laboratory Air Voids, percent No specific action and suspension limits set since deviation from JMF target value this parameter is used to determine percent payment In-place Mat Density, percent of TMD No specific action and suspension limits set since this parameter is used to determine percent payment In-place Joint Density, percent of TMD No specific action and suspension limits set since this parameter is used to determine percent payment TSR, percent minimum 73 70 Gradation 1 13.3 13.0 13.5 13.0 Gradation 2 14.3 14.0 14.5 14.0 Gradation 3 15.3 15.0 15.0 15.0 VMA Table 8 cont'd. Marshall Compaction Stability, N pounds (minimum) 75 blow JMF 78301760 72901640 95602150 90302030 50 blow JMF 4230950 3690830 60001350 54701230 8 min. 7 min. 9 min. 8 min. 16 max. 17 max. 15 max. 16 max. 8 min. 7 min. 9 min. 8 min. 18 max. 19 max. 17 max. 18 max. Flow, 0.25 mm 0.01 inches 75 blow JMF 50 blow JMF SECTION 32 12 15.16 Page 33 3.2 PREPARATION OF ASPHALT BINDER MATERIAL The asphalt cement material shall be heated avoiding local overheating and providing a continuous supply of the asphalt material to the mixer at a uniform temperature. The temperature of asphalt binder shall be no more than 132 degrees C 270 degrees F when added to the aggregates. 3.3 PREPARATION OF MINERAL AGGREGATE The aggregate for the mixture shall be heated and dried prior to mixing. No damage shall occur to the aggregates due to the maximum temperature and rate of heating used. The temperature of the aggregate and mineral filler shall not exceed 132 degrees C 270 degrees F when the asphalt binder is added. The temperature shall not be lower than is required to obtain complete coating and uniform distribution on the aggregate particles and to provide a mixture of satisfactory workability. 3.4 PREPARATION OF WARM-MIX ASPHALT MIXTURE The aggregates, asphalt cement, and WMA additives, if added separately at the plant, shall be weighed or metered and introduced into the mixer in the amount specified by the JMF. The combined materials shall be mixed until the aggregate obtains a thorough and uniform coating of asphalt binder (testing in accordance with ASTM D2489/D2489M may be required by the Contracting Officer) and is thoroughly distributed throughout the mixture. The moisture content of all WMA upon discharge from the plant shall not exceed 0.5 percent by total weight of mixture as measured by ASTM D1461. 3.5 PREPARATION OF THE UNDERLYING SURFACE ************************************************************************** NOTE: If the underlying surface to be paved is an unbound granular layer, a prime coat should be applied, especially if this layer will be exposed to weather for an extended period of time prior to covering with an asphalt mixture. Benefits derived from a prime coat include an additional weatherproofing of the base, improving the bond between the base and WMA layer, and preventing the base from shifting under construction equipment. If the prime coat requirement is not a separate pay item and is waived from this contract, an adjustment to the contract price should be made. Environmental laws in certain states may not allow prime coats to be applied. If the underlying surface to be paved is an existing asphalt or concrete layer, a tack coat should always be used to ensure an adequate bond between layers. Tack and prime coat requirements will need to be covered in the contract documents. ************************************************************************** Immediately before placing the WMA, the underlying course shall be cleaned of dust and debris. A [prime coat] [and/or] [tack coat] shall be applied in accordance with the contract specifications. SECTION 32 12 15.16 Page 34 3.6 TEST SECTION Prior to full production, place a test section for each JMF used. Construct a test section consisting of a maximum of 250 tons and two paver passes wide placed in two lanes, with a longitudinal cold joint. The test section shall be of the same depth as the course which it represents. The underlying grade or pavement structure upon which the test section is to be constructed shall be the same as the remainder of the course represented by the test section. The equipment used in construction of the test section shall be the same equipment to be used on the remainder of the course represented by the test section. The test section shall be placed as part of the project pavement as approved by the Contracting Officer Engineer. 3.6.1 Sampling and Testing for Test Section ************************************************************************** NOTE: Table 9 applies only to the test section. The limits in Tables 1, 2, and 8, apply to a number of tests run from a lot. This is why the limits listed in Table 9 are different from those listed in Tables 1, 2, and 8. Select the appropriate VMA requirement to match the selected gradation. Select the appropriate stability and flow value to match the laboratory compactive effort (50 or 75 blows). ************************************************************************** One random sample shall be taken at the plant, triplicate specimens compacted, and tested for stability, flow, laboratory air voids, and Tensile Strength Ratio (TSR). A portion of the same sample shall be tested for theoretical maximum density (TMD), aggregate gradation and asphalt content. Four randomly selected cores shall be taken from the finished pavement mat, and four from the longitudinal joint, and tested for density. Random sampling shall be in accordance with procedures contained in ASTM D3665. The test results shall be within the tolerances or exceed the minimum values shown in Table 9 for work to continue. If all test results meet the specified requirements, the test section shall remain as part of the project pavement. If test results exceed the tolerances shown, the test section shall be removed and replaced at no cost to the Government Owner and another test section shall be constructed. Table 9. Test Section Requirements for Material and Mixture Properties Property Specification Limit Aggregate Gradation-Percent Passing (Individual Test Result) 4.75 mm No. 4 and larger JMF plus or minus 8 2.36, 1.18, 0.60, and 0.30 mmNo. 8, No. 16, No. 30, and No. 50 JMF plus or minus 6 0.15 and 0.075 mmNo. 100 and No. 200 JMF plus or minus 2.0 SECTION 32 12 15.16 Page 35 Table 9. Test Section Requirements for Material and Mixture Properties Property Specification Limit Asphalt Content, Percent (Individual Test Result) JMF plus or minus 0.5 Laboratory Air Voids, Percent (Average of 3 specimens) JMF plus or minus 1.0 VMA, Percent (Average of 3 specimens) See Table 8 Tensile Strength Ratio (TSR) (At 7 percent plus/minus 1 percent air void content) 75 percent minimum Conditioned Strength 415 kPa 60 psi minimum Mat Density, Percent of TMD (Average of 4 Random Cores) 92.0 - 96.0 Joint Density, Percent of TMD (Average of 4 Random Cores) 90.5 minimum Table 9. cont'd - Marshall Compaction Stability,N specimens) pounds (Average of 3 Flow, 0.25 mm 0.01 inches (Average of 3 specimens) 3.6.2 [6000] [9560] [1350] [2150] minimum [8 - 16] [8 - 18] Additional Test Sections If the initial test section should prove to be unacceptable, the necessary adjustments to the JMF, plant operation, placing procedures, and/or rolling procedures shall be made. A second test section shall then be placed. Additional test sections, as required, shall be constructed and evaluated for conformance to the specifications. Full production shall not begin until an acceptable section has been constructed and accepted. 3.7 TESTING LABORATORY ************************************************************************** NOTE: Include bracketed sentence for Corps-managed projects. ************************************************************************** The laboratories used to develop the JMF, perform Contractor Quality Control testing, and for Government Engineer acceptance testing shall meet the requirements of ASTM D3666. All required test methods shall be performed by an accredited laboratory. [The Government will inspect the laboratory equipment and test procedures prior to the start of WMA operations for conformance with ASTM D3666. The laboratory shall maintain this validation for the duration of the project.] Submit a certification of compliance signed by the manager of the laboratory stating that it meets these requirements to the Contracting Officer Engineer prior to the start of construction. The certification shall contain as a minimum: a. Qualifications of personnel; laboratory manager, supervising technician, and testing technicians. SECTION 32 12 15.16 Page 36 b. A listing of equipment to be used in developing the job mix. c. A copy of the laboratory's quality control system. d. Evidence of participation in the AASHTO Materials Reference Laboratory (AMRL) program. 3.8 3.8.1 TRANSPORTING AND PLACING Transporting Transport the WMA from the mixing plant to the site in clean, tight vehicles. Schedule deliveries so that placing and compacting of mixture is uniform with minimum stopping and starting of the paver. Provide adequate artificial lighting for night placements. Hauling over freshly placed material will not be permitted until the material has been compacted as specified, and allowed to cool to 60 degrees C 140 degrees F. 3.8.2 Placing The mix shall be placed in lifts of adequate thickness and compacted at a temperature suitable for obtaining density, surface smoothness, and other specified requirements. Upon arrival, the mixture shall be placed to the full width by an asphalt paver; it shall be struck off in a uniform layer of such depth that, when the work is completed, it shall have the required thickness and conform to the grade and contour indicated. Waste mixture shall not be broadcast onto the mat or recycled into the paver hopper. Collect waste mixture and dispose off site. The speed of the paver shall be regulated to eliminate pulling and tearing of the asphalt mat. Placement of the mixture shall begin along the centerline of a crowned section or on the high side of areas with a one-way slope. The mixture shall be placed in consecutive adjacent strips having a minimum width of 3 m 10 feet. The longitudinal joint in one course shall offset the longitudinal joint in the course immediately below by at least 300 mm 1 foot; however, the joint in the surface course shall be at the centerline of the pavement. Transverse joints in one course shall be offset by at least 3 m 10 feet from transverse joints in the previous course. Transverse joints in adjacent lanes shall be offset a minimum of 3 m 10 feet. On isolated areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impractical, the mixture may be spread and luted by hand tools. 3.9 3.9.1 COMPACTION OF MIXTURE General a. After placing, the mixture shall be thoroughly and uniformly compacted by rolling. The surface shall be compacted as soon as possible without causing displacement, cracking or shoving. The sequence of rolling operations and the type of rollers used are at the discretion of the Contractor, with the exception that application of more than three passes with a vibratory roller in the vibrating mode is prohibited. The speed of the roller shall, at all times, be sufficiently slow to avoid displacement of the hot mixture and be effective in compaction. Correct at once any displacement occurring as a result of reversing the direction of the roller, or from any other cause. b. Furnish sufficient rollers to handle the output of the plant. Continue rolling until the surface is of uniform texture, true to grade and SECTION 32 12 15.16 Page 37 cross section, and the required field density is obtained. To prevent adhesion of the mixture to the roller, keep the wheels properly moistened, but excessive water will not be permitted. In areas not accessible to the roller, thoroughly compact the mixture with hand tampers. Remove the full depth of any mixture that becomes loose and broken, mixed with dirt, contains check-cracking, or is in any way defective, replace with fresh hot mixture and immediately compact to conform to the surrounding area. This work shall be done at the Contractor's expense. Skin patching will not be allowed. 3.9.2 Segregation The Contracting Officer Engineer can sample and test any material that looks deficient. When the in-place material appears to be segregated, the Contracting Officer Engineer has the option to sample the material and have it tested and compared to the aggregate gradation, asphalt content, and in-place density requirements in Table 10. If the material fails to meet these specification requirements, the extent of the segregated material will be removed and replaced the full depth of the layer of asphalt mixture at no additional cost to the Government. When segregation occurs in the mat, take appropriate action to correct the process so that additional segregation does not occur. 3.10 JOINTS The formation of joints shall be made ensuring a continuous bond between the courses and to obtain the required density. All joints shall have the same texture as other sections of the course and meet the requirements for smoothness and grade. 3.10.1 Transverse Joints The roller shall not pass over the unprotected end of the freshly laid mixture, except when necessary to form a transverse joint. When necessary to form a transverse joint, it shall be made by means of placing a bulkhead or by tapering the course. The tapered edge shall be cut back to its full depth and width on a straight line to expose a vertical face prior to placing the adjacent lane. The cutback material shall be removed from the project. In both methods, all contact surfaces shall be given a light tack coat of asphalt material before placing any fresh mixture against the joint. 3.10.2 Longitudinal Joints Longitudinal joints which are irregular, damaged, uncompacted, cold (less than 80 degrees C 175 degrees F at the time of placing the adjacent lane), or otherwise defective, shall be cut back a maximum of 75 mm 3 inches from the top edge of the lift with a cutting wheel to expose a clean, sound, near vertical surface for the full depth of the course. All cutback material shall be removed from the project. Cutting equipment that uses water as a cooling or cutting agent shall not be permitted. All contact surfaces shall be given a light tack coat of asphalt material prior to placing any fresh mixture against the joint. 3.10.3 WMA-Portland Cement Concrete Joints Joints between WMA and PCC will require specific construction procedures for the WMA. The following criteria are applicable to the first 3 m 10 feet or paver width of WMA adjacent to the PCC. SECTION 32 12 15.16 Page 38 a. Pave the WMA side of the joint in a direction parallel to the joint. b. Place the WMA side sufficiently high so that when fully compacted the WMA will be greater than 3 mm 1/8 inch but less than 6 mm 1/4 inch higher than the PCC side of the joint. c. Compaction shall be provided with steel wheel rollers and at least one rubber tire roller. The rubber tire roller shall be at least 18 metric tons 20 tons in weight and have tires that are inflated to at least 620 kPa 90 psi. Avoid spalling the PCC during placement and compaction of the WMA. Steel wheel rollers shall be operated in a way that prevents spalling the PCC. Any damage to PCC edges or joints shall be repaired as directed by the Contracting OfficerEngineer. If damage to the PCC joint or edge exceeds a total of 1 m 3 feet, the PCC panel shall be removed and replaced at no additional expense to the Government. d. After compaction is finished the WMA shall be leveled by grinding so that the WMA side is less than 3 mm 1/8 inch higher than the PCC side. The WMA immediately adjacent to the joint shall not be lower than the PCC after the grinding operation. Transition the grinding into the WMA in a way that ensures good smoothness and provides drainage of water. The joint and adjacent materials when completed shall meet all of the requirements for grade and smoothness. Measure smoothness across the PCC-WMA joint using a 4 m 12 feet straightedge. The acceptable tolerance is 3 mm 1/8 inch. e. Consider the WMA next to the PCC as a separate lot for evaluation. Lots are based on individual lifts. Do not comingle cores from different lifts for density evaluation purposes. Take four cores for each lot of material placed adjacent to the joint. The size of lot shall be 3 m 10 feet wide by the length of the joint being paved. Lots are based on individual lifts and shall not be comingled for density evaluation purposes. Locate the center of each of the four cores 150 mm 6 inches from the edge of the concrete. Take each core at a random location along the length of the joint. The requirements for density for this lot, adjacent to the joint, are the same as that for the mat specified earlier. f. All procedures, including repair of damaged PCC, shall be in accordance with the approved Quality Control Plan. -- End of Section -- SECTION 32 12 15.16 Page 39