VIRGINIA RAILWAY EXPRESS 1500 KING STREET | ALEXANDRIA, VA 22314 703.684.1001 | WWW.VRE.ORG TABLE OF CONTENTS CEO REPORT | MAY 2014 2 ON TIME PERFORMANCE 3 RIDERSHIP UPDATE 3 MONTHLY CITATIONS UPDATE 4 RIDERSHIP CHART 5 ON TIME PERFORMANCE GRAPHS 6 TRAIN UTILIZATION 7 PARKING UTILIZATION 8 BICYCLE COUNTS 8 FINANCIAL REPORT 12 RAIL OPERATIONS SAFETY UPDATE 13 CAPITAL PROJECTS 15 PROCUREMENT 16 PROGRESS REPORT/PROJECTS UNDERWAY SPOTSYLVANIA ALEXANDRIA KING STREET PEDESTRIAN TUNNEL L’ENFANT STORAGE TRACK LORTON PLATFORM EXTENSION BROAD RUN TRAIN WASH BROAD RUN PARKING EXPANSION FACILITIES UPDATE NEW PASSENGER CARS ON TIME PERFORMANCE REASON FOR DELAYS 3% On Time Performance (OTP) for the month of April 2014 rose slightly to 95.5% in comparison to March 2014. The Fredericksburg line realized 93.8% OTP while the Manassas line came in at 96.8%. Train delays were mainly caused by restricted speed orders; passenger handling; and train interference issues. 11% 26% 32% In April, VRE operated 660 trains with 30 trains experiencing a delay over five minutes. More delays were experienced on the Fredericksburg line (19) as a result of train interference. 2% 26% “Other” includes those trains that were delayed due to late turns, weather, maintenance of way and schedule related issues, etc. Train Interference - 24 Restricted Speed - 29 Signal/Switch Failure - 2 Mechanical Failure - 3 Passenger Handling - 24 Other - 10 TRIP DELAYS SYSTEM-WIDE FEB. MARCH APRIL Total delays 26 37 30 Average length of delay (mins.) 13 18 16 Number over 30 minutes 3 6 4 Total Days with heat restrictions 0 0/20 0/22 95% 94% 96% Total delays 16 20 19 Average length of delay (mins.) 16 17 19 Number over 30 minutes 3 4 3 93% 93% 94% Total delays 10 17 11 Average length of delay (mins.) 9 18 12 Number over 30 minutes 0 2 1 96% 95% 97% On-Time Performance FREDERICKSBURG LINE On-Time Performance MANASSAS LINE On-Time Performance 2 CEO REPORT | MAY 2014 RIDERSHIP UPDATE Total April 2014 ridership was 430,471, up from 425,792 realized in April 2013. The number of monthly service days remained the same as the previous year, so ridership has increased by 1.1%. There were no “S” schedules operated in April 2014. The April 2014 average daily ridership is 19,567, a slight increase from the average daily ridership of 19,354 achieved in April 2013. RIDERSHIP MONTH-TO-MONTH COMPARISON DESCRIPTION MONTHLY RIDERSHIP April 2014 430,471 April 2013 425,792 Service Days (Current/Prior) 22/22 Ridership Percent Change +1.1% MONTHLY CITATIONS UPDATE Keolis wrote 109 citations during the month of April, 8 less than in March. VRE waived 40 citations after riders showed proof of purchase of a monthly ticket. Additionally, another 23 were dismissed either for a one time courtesy or other unique circumstances. Of the remaining 46 citations that went to court, 5 were found guilty, 16 were guilty in absentia, 12 were continued on to a later date, and 13 were prepaid. 0 were found to be not guilty. FARE EVASION COURT ACTIONS 7% 33% 23% WAIVED CITATIONS VRE ACTIONS OCCURRENCES Waived – Passenger showed proof of a monthly ticket 36 Waived – One Time Courtesy 3 Waived – Per the request of the conductor 0 Waived – TVM Error Waived – Insufficient Information 0 0 0 1 0 0 TOTAL WAIVED CITATIONS 40 Waived – Defective Ticket Waived – Per Ops Manager Waived – Unique Circumstances Waived – Insufficient Processing Time 18% 19% Guilty - 5 Guilty in Absentia - 16 Prepaid Prior to Court - 13 Cont. to Next Court Date - 12 Dismissed - 23 Not Guilty - 0 CEO REPORT | MAY 2014 3 RIDERSHIP CHART DATE MSS AM MSS PM TOTAL MSS ACTUAL OTP TD FBG AM FBG PM FBG TOTAL ACTUAL OTP TD TOTAL TRIPS 1 4,670 4,974 2 4,596 4,945 3 4,716 4,961 4 3,585 3,659 7 4,308 4,546 8,855 100% 8 4,661 4,749 9,411 100% ACTUAL OTP TD 9,644 94% 5,353 5,272 10,625 100% 20,269 97% 9,541 100% 5,224 5,603 10,827 100% 20,368 100% 9,677 94% 5,255 5,674 10,928 100% 20,606 97% 7,244 100% 4,266 4,457 8,724 79% 15,968 90% 5,105 5,094 10,199 93% 19,054 97% 5,713 5,316 11,029 100% 20,440 100% 5 6 9 4,668 4,731 9,399 100% 5,301 5,096 10,397 100% 19,795 100% 10 4,368 4,692 9,060 100% 5,351 5,349 10,699 93% 19,759 97% 11 3,583 3,723 7,306 94% 4,521 4,380 8,901 86% 16,207 90% 14 4,107 4,047 8,154 100% 5,019 5,270 10,288 100% 18,442 100% 15 4,023 4,399 8,423 100% 5,383 5,378 10,761 100% 19,183 100% 16 4,075 4,266 8,340 100% 5,374 5,295 10,669 100% 19,009 100% 17 4,184 4,311 8,495 100% 5,354 5,444 10,798 86% 19,292 93% 18 3,012 2,815 5,827 94% 3,990 4,205 8,195 100% 14,022 97% 21 4,273 4,296 8,569 94% 4,802 4,780 9,582 86% 18,150 90% 22 4,670 4,709 9,379 94% 5,518 5,288 10,806 100% 20,185 97% 23 4,582 4,659 9,242 100% 5,496 5,583 11,080 93% 20,321 97% 24 4,597 4,524 9,121 100% 5,464 4,674 10,139 100% 19,260 100% 25 3,542 3,479 7,021 100% 4,185 3,963 8,148 100% 15,168 100% 28 4,198 4,318 8,516 94% 5,082 5,072 10,154 100% 18,670 97% 29 4,343 4,926 9,269 100% 5,721 5,705 11,426 100% 20,695 100% 12 13 19 20 26 27 30 4,503 4,433 8,936 75% 5,554 5,266 10,820 50% 19,757 63% 93,266 96,161 189,427 97% 113,031 112,164 225,195 94% 414,622 95% Amtrak Trains: 784 Amtrak Trains: 15,065 Amtrak Total: Adjusted total: 190,211 Adjusted total: 240,260 Adjusted Total: 430,471 # of Service Days: 22 Full Service Days: 22 Manassas Daily Avg. Trips: 8,610 Adjusted Avg.: 8,646 Fred'burg Daily Avg. Trips: 10,236 Adjusted Avg.: 10,921 Total Avg. Daily Trips: 18,846 Adjusted Avg.: 19,567 Total Number of Service Days to Date: 209 Average Daily Riders to Date: 17,901 Total Trips This Month: 430,471 Prior Total FY-2014: 3,310,785 Total Trips FY-2014: 3,741,256 Total Prior Years: 62,422,463 Grand Total: 66,163,719 15,849 NOTE: Adjusted Averages and Totals include all VRE trips taken on Amtrak trains, but do not include “S” schedule days. * designates “S” schedule day 4 CEO REPORT | MAY 2014 ON TIME PERFORMANCE SYSTEM PERFORMANCE 100% 95% 90% 85% 4/2014 3/2014 2/2014 1/2014 12/2013 11/2013 10/2013 9/2013 8/2013 7/2013 6/2013 5/2013 4/2013 3/2013 2/2013 1/2013 12/2012 11/2012 10/2012 9/2012 8/2012 7/2012 6/2012 5/2012 4/2012 3/2012 2/2012 1/2012 80% 4/2014 3/2014 2/2014 1/2014 12/2013 11/2013 10/2013 9/2013 8/2013 7/2013 6/2013 5/2013 4/2013 3/2013 2/2013 1/2013 12/2012 11/2012 10/2012 9/2012 8/2012 7/2012 6/2012 5/2012 4/2012 3/2012 2/2012 1/2012 80% FREDERICKSBURG LINE MANASSAS LINE PERFORMANCE BY LINE 100% 95% 90% 85% 5 CEO REPORT | MAY 2014 TRAIN UTILIZATION AVERAGE RIDERSHIP FREDERICKSBURG LINE 150% MIDWEEK PEAK 120% 100% Capacity 90% 60% 30% 0% 300 302 304 306 308 310 312 301 303 305 307 309 311 313 AVERAGE RIDERSHIP MANASSAS LINE Midweek Peak 100% Average Ridership 80% Capacity MIDWEEK PEAK 60% 40% 20% 0% 322 6 324 326 CEO REPORT | MAY 2014 328 330 332 325 327 329 331 333 335 337 PARKING UTILIZATION NUMBER OF SPACES FREDERICKSBURG LINE 1000 NUMBER IN USE Parking Spaces 800 600 400 200 0 FBG* LLR* BKV QAN RIP VRE Stations 2000 WDB *Denotes stations with overflow parking available that is now being included in final counts Num in Use NUMBER OF SPACES MANASSAS LINE Parking Spaces NUMBER IN USE Num Spaces 1500 LOR 1000 500 0 BRU MSS MPV BCV RRV BLV VRE Stations CEO REPORT | MAY 2014 7 BICYCLE COUNTS 20 No. of Bicycles Parked FREDERICKSBURG LINE MANASSAS LINE 15 10 5 0 FBG LLR BKV QAN WDB RIP LOR FRS* BRU MSS VRE Stations FINANCIAL REPORT MPV BCV RRV BLV *Denotes joint use facility—Riders of VRE and Metro cannot be differentiated. Num Spaces SUMMARY OF FINANCIAL RESULTS MEASURES DOLLARS Operating Ratio BUDGETED REVENUE 86,783,248 Budgeted Revenue YTD 68,382,965 Actual Revenue YTD 68,960,642 Cumulative Variance 577,677 Percent Collected YTD 86,783,248 Budgeted Expenses YTD 66,605,782 Operating Expenses YTD 63,542,639 NET INCOME (LOSS) FROM OPERATIONS These figures are preliminary and unaudited. CEO REPORT | MAY 2014 55% 59% 577,677 3,063,143 Percent Expended YTD 8 ACTUAL 78.80% BUDGETED EXPENSES Cumulative Variance GOAL 79.46% 3,063,143 76.75% 73.22% 3,640,820 Fare income for the month was $137,203 below the budget – an unfavorable variance of 4.28%. The cumulative variance for the year is 2.17% or $660,453 above the adopted budget. Revenue in FY 2014 is up 9.0% compared to FY 2013. The government shutdown in October did not have a material effect on fare revenue. The transit subsidy decreased effective January 1, 2014 and has had an impact on fare revenue which has led to a slight softening of fare projections. A summary of the financial results (unaudited) follows. Detail on the major revenue and expense categories is provided in the attached Operating Budget Report. Amounts shown reflect the amended FY14 budget. FINANCIAL REPORT, CONT. FY 2014 OPERATING BUDGET REPORT, APRIL 30, 2014 YTD VARIANCE CURR. MO. ACTUAL CURR. MO. BUDGET YTD ACTUAL YTD BUDGET Passenger Ticket Revenue 3,070,765 3,207,968 31,136,150 30,475,697 660,453 2.2% 36,600,000 Other Operating Revenue 4,000 14,550 165,416 138,223 27,193 19.7% 166,000 3,074,765 3,222,518 31,301,566 30,613,920 687,646 2.2% 36,766,000 – – 11,761,497 11,761,497 - 0.0% 11,761,497 2,607,724 2,736,142 25,874,786 25,994,809 (120,022) -0.5% 32,654,748 5,585,703 $ % TOTAL FY14 BUDGET OPERATING REVENUE Subtotal Operating Revenue Jurisdictional Subsidy (1) Federal/State/Other Jurisdictional Subsidy Appropriation from Reserve Interest Income Total Operating Revenue - - - - - 0.0% 2,928 1,341 22,794 12,740 10,054 78.9% 15,300 5,685,417 5,960,001 68,960,643 68,382,965 577,677 0.8% 86,783,248 OPERATING EXPENSES Departmental Operating Expenses 4,842,012 5,307,519 52,898,691 55,973,657 3,074,965 5.5% 68,345,145 Debt Service 575,611 575,611 10,632,125 10,632,125 - 0.0% 13,594,559 Other Non-Departmental Expenses 11,823 - 11,823 - (11,823) 5,429,446 5,883,130 63,542,639 66,605,782 3,063,142 4.6% 86,783,248 255,971 76,871 5,418,003 1,777,184 3,640,820 – – Total Operating Expenses NET INCOME (LOSS) FROM OPERATIONS CALCULATED OPERATING RATIO 4,843,544 59% (1) Total jurisdictional subsidy is $16,428,800. Portion shown is attributed to Operating Fund only. FISCAL YEAR REVENUE PER MONTH 2014 2013 2012 2011 4,000,000 3,500,000 3,000,000 2,500,000 2,000,000 JULY AUG. SEPT. OCT. NOV. DEC. JAN. FEB. MARCH APRIL MAY JUNE CEO REPORT | MAY 2014 9 FINANCIAL REPORT, CONT. FY 2014 YEAR END FINANCIAL PROJECTION Each month, the VRE Operations Board receives financial information in summary form which shows year-todate actual to budgeted fare revenue, grant revenue, and operating expenses. In December of each year, a revised budget for the year is prepared, based on the most current information as of that date. In December 2013, the Amended FY 2014 Budget was presented to the Board. A final recommendation for the projected surplus will be presented as part of the FY 2016 Budget in December 2014. The information below is a projection of year-end revenue and expenses for FY 2014. Major points are as follows: •The overall projected surplus for FY 2014 is projected at $4.2M •Fare revenue is estimated to be approximately $400k above the budgeted amount, assuming ridership remains stable •Other Revenue allows for the budgeted transfer from the Capital Reserve of $4.8M, but does not require the budgeted transfer from the Operating Reserve of $800k. The Capital Reserve transfer is primarily comprised of funds for the replacement railcars ($1.5M) and the FY 2013 surplus ($3.0M) designated for the reserve. •The operating budget is projected to show a $3.7M surplus. Major contributing factors are: –Diesel fuel was budgeted for 1.6M gallons at $3.50 per gallon ($5.6M). Through nine months of the year, YTD consumption is 1.1M gallons with an average cost per gallon of $3.19, resulting in an EOY projection of approximately 1.4M gallons with a projected expense of $4.7M; a savings of $900k –Approximately $350k will carry over to FY 2015 for operating items which are underway, but will not be completed in FY 2014. These expenses are in primarily in Equipment Operations. –Unspent operating contingency of $600k –Insurance premium savings of $250k –Other departmental savings are projected are estimated at $1.3M. Departments include Planning, Chief of Staff/Public Affairs, Equipment Operations and Engineering/Construction. For FY 2015, preliminary uses for the projected surplus are as follows: •The FY 2015 state operating assistance of $8.9M was below the budgeted amount of $10.3M by $1.4M. However, the amount of track access funding exceeded the budget by $300k, creating a net shortfall is $1.1M. •FY 2014 carryover railcar enhancements budgeted at $350k •The balance to the Capital Reserve 10 CEO REPORT | MAY 2014 FINANCIAL REPORT, CONT. THE CHART BELOW SUMMARIZES ACTUAL TO BUDGET DATA BY MAJOR CATEGORY: FY 14 YEAR END OPERATING BUDGET PROJECTION (IN MILLIONS) DESCRIPTION REVISED BUDGET CURRENT ESTIMATE VARIANCE % Fare Revenue 36.6 37.0 0.4 1.1% Local Subsidy* 11.8 11.8 – 0.0% Fed/State Revenue 32.6 33.6 1.0 3.0% Other Revenue 5.8 4.7 (1.1) -23.4% Total Revenue 86.8 87.1 0.3 0.3% Operating Expenses 68.3 64.7 3.6 5.6% Debt Service 13.6 13.6 – 0.0% Non-Operating 4.9 4.9 – 0.0% Total Expenses 86.8 83.2 3.6 4.1% – 3.9 3.9 Net Income (Loss) *The local subsidy amount shown here is the amount needed for operations; total subsidy is $16.4M CEO REPORT | MAY 2014 11 RAIL OPERATIONS SAFETY UPDATE Operation Lifesaver (OL) is a national non-profit organization dedicated to public education and awareness of the importance of railroad grade crossing safety and trespass prevention. Recently, it partnered with the Association of American Railroads, Federal Railroad Administration, commuter and freight railroads to launch a national campaign themed “See Tracks, Think Train.” VRE has always been a supporter of OL’s mission and activities and recently hosted their crews at our Quantico station to provide an appropriate backdrop for the filming of the video that will be used as a core component of the campaign. For more information on the campaign, visit www.oli.org. VRE hosts OLI at Quantico as they film the PSA for their national “See Tracks, Think Train” campaign. Virginia Railway Express (VRE) was recently notified by the Transportation Security Administration (TSA) that it has received a near perfect score and a “Gold Standard” rating on its 2014 Baseline Assessment for Security Enhancement (BASE) audit. The BASE program is designed to establish a security standard for individual system security programs and assess progress in enhancements and implementation. The review focuses on categories identified by the transit community as fundamentals for a sound transit security program. They include a review of physical and cyber security plans, security training, drills and training initiatives, public outreach efforts and background check programs. VRE is proud of the results of this audit but like TSA, understands that the task of improving safety and security for passengers, employees and the community is an unending task. We have enjoyed an excellent relationship with TSA and look forward to future opportunities to strengthen our partnership. 12 CEO REPORT | MAY 2014 CAPITAL PROJECTS SPOTSYLVANIA VRE has issued construction contracts for both the station and third track. Once the land purchase is completed by Spotsylvania County, VRE can issue a notice to proceed (NTP) and construction work can begin on the station. Spotsylvania has asked VDOT to handle land acquisition for them. VDOT is proceeding with their land acquisition process. In the mean time, the pre-construction kick off meeting for the third track construction was held on December 19th for all stakeholder, NTP for the third track project was issued on December 23rd, and construction has started. Contractor Mobilization and Access is almost complete. Clearing and Grubbing for the entire project is near completion. Crash Walls have been completed at the US Rte 17 overhead bridge, and new embankment for Third Track roadbed fill operations have started in earnest with some of the wetter weather finally subsiding. Future site of Spotsylvania Station and Parking Lot with fill operations north and south. Fill operations for Third Track north of US 17 to Pedestrian Underpass at Benchmark. ALEXANDRIA KING STREET PEDESTRIAN TUNNEL PROJECT VRE Operations Board approved the issuance of a task order contract to Gannett Fleming for the design & construction management work at their December 20, 2013, meeting. The project team is moving forward to accomplish the following milestones: • NEPA Documentation – Complete December 2012 - Complete • Public Information Meeting – Spring 2013 – Complete • Geotechnical investigation and utility locating – June 2014 • Design – Completion by early 2015 • Construction Advertisement – To be Determined, Estimated Spring 2015 • Construction – To be Determined, Estimated Start Summer 2015, Estimated Completion late 2016 CEO REPORT | MAY 2014 13 CAPITAL PROJECTS, CONT. L’ENFANT STORAGE TRACK VRE will meet with CSX soon to review the final design and approve the scope of work. HDR has completed the final wayside power design which is under VRE review. Once approved, the wayside power design will be forwarded to PEPCO for electric service design and to CSX for review and approval. LORTON PLATFORM EXTENSION VRE accepted construction bids in early March and received Board approval at the March meeting to award a contract to Hammerhead Construction of Dulles, Virginia. Construction is expected to commence during the spring of 2014. This project will extend the existing platform at the VRE Lorton Station by approximately 256 feet to accommodate longer VRE trains. VRE also received Board approval in March to execute an agreement with CenturyLink to relocate a communication line in the project area. BROAD RUN TRAIN WASH VRE has reviewed the 90% design plans. Plan submission to Prince William County and the City of Manassas is on hold while VRE seeks additional funding sources for construction. BROAD RUN PARKING EXPANSION VRE is currently reviewing 30% design documents. Once the FTA approves the Categorical Exclusion (CE) application, design work will resume with the next milestone review at the 60% level. FACILITIES UPDATE VRE facilities team has multiple projects underway and completed the following within the past month: 1.Replaced temporary passenger crosswalks at L’Enfant, Brooke and Leeland Stations. 2.Install roadway asphalt at Crossroads Maintenance and Storage Facility. 3.Roof repairs at VRE Fredericksburg office. Projects scheduled to be completed within the 2nd Quarter of calendar year 2014. 1.Evaluate electrical power infrastructure at Broad Run; replace electrical lines as necessary. 2.Elevator cab and hoist-way rehabiliation at Rippon and Franconia Springfield stations. 3.Roof repairs at Rippon Station. 4.Install network fire detection system at VRE Fredericksburg office. 5.Remove discarded ties and asphalt from the right of ways at various locations within the service area. 6.Install portable generator connections at all stations with elevators; long term all stations will be equipped for portable generator operations. 7.Correct drainage pipe slope at Crossroads maintenance and storage facility. 14 CEO REPORT | MAY 2014 NEW PASSENGER CARS Base Order (8) Gallery IV Cars VRE anticipates the first four (4) new passenger cars to be ready for shipment from Rochelle, IL on or about May 12, 2014. Extensive testing of the new emergency lighting system has resulted in the need to modify software. This has delayed delivery. In addition, minor material shortages have delayed final assembly and VRE acceptance of the cars. Option Order (7) Gallery IV Cars VRE modified the existing Contract with Sumitomo Corporation of America (SCOA) to add seven (7) option cars to the existing order. The Contract Amendment was finalized by the end of December 2013. The project kick off meeting was held on March 17th. Material purchases and the preliminary Buy America audit is currently underway. PROCUREMENT PROCUREMENT IN PROCESS AND POSTED ON WEBSITE: • Sale of Gallery Style Passenger Cars • VRE Mobile Ticketing System • Electronic Fuel Injector Assemblies for VRE Passenger Locomotives • Installation of Security Cameras at the VRE Broad Run Station • Wheelset Rehabilitation • Heavy Interior Cleaning of VRE Rail Cars • Positive Train Control CEO REPORT | MAY 2014 15 COMMUTER STATIONS & PARKING PROJECTS Project & Code Alexandria - King St Pedestrian Tunnel Amtrak Joint Recapitalization Project Broad Run Parking Expansion FranconiaSpringfield Station Rehabilitation Lorton Station Expansion Description Design and installation of a new pedestrian tunnel between the VRE/Amtrak and METRO stations and modifications to eastern platform to allow service from Track #1. Amtrak and VRE joint benefit recapitalization projects Environmental Analysis and Engineering to expand parking by 700 spaces To make repairs & improvements to the Franconia Springfield Station Eastern Platform & Passenger Walkway Expansion of station by extending eastern platform and adding a second platform Task COMMUTER STATION & PAR Task Description % of Total Task Completion Calendar Completion Date (Est.) 8C-05-2012 95% 2nd Quarter 2013 Prepare a feasibility study with limited survey to investigate challenges associated with designing, permitting and constructing a tunnel under a Rich Dalton live CSX track. Site Investigation Compile soils data and perform in-situ testing to prepare for final design phase and provide VDOT with environmental information. Eric Johnson 8H-10-2013 15% 2nd Quarter 2014 Design & Construction Administration Design & construction administration for pedestrian tunnel and modifications to east platform. Rich Dalton 8F-12-2013 5% 1st Quarter 2015 Joint study with Amtrak and MARC re: meeting current and forecasted growth for target years 2017 and 2030. Christine Hoeffner 100% Completed Upgrade and replace wayside power station for VRE storage Rich Dalton tracks at the Coach yard 100% Completed Washington Union Terminal Rail Service Improvement Plan Coach Yard Wayside Power Upgrade WUT Canopy Roof Repairs Repairs of canopy roof at WUT lower level platforms Rich Dalton 70% 4th Quarter 2014 Alexandria - King St Station Platform Elevation Raise west platform elevation Rich Dalton 0% TBD 90% 1st Quarter 2014 EA & PE Perform environmental analysis and engineering and provide construction administration to expand parking by 700 spaces Eric Johnson 11D-04-2011 30% 3rd Quarter 2014 Repairs & Improvements Infrastructure repairs and improvements to eastern platform and passenger walkway at VRE Franconia-Springfield Station. Kip Foster 9F-06-2011 100% Completed 3rd Quarter 2013 Flagging Services & Protection Provide flagging services during platform level repairs and overhead pedestrian bridge work. Kip Foster 9G-06-2011 100% Completed 2012 PE and Environmental EA and PE to extend the exiting platform and construct a second platform. Eric Johnson 10A–10-2010 100% Completed 4th Quarter 2012 Station Expansion Design Prepare construction documents and provide construction administration for 250' platform expansion with upgraded LED lighting Eric Johnson 8B–05-2012 90% 4th Quarter 2014 Platform Extension Construction Construction of 250' platform extension with upgraded LED lighting Eric Johnson 8B–03-2014 0% 4th Quarter 2014 Utility Relocation Relocate CenturyLink communications line to accommodate platform extension and future second platform Eric Johnson 8C–03-2014 0% 2nd Quarter 2014 Construction Management Services Provide construction management and inspection services during construction of platform extension Eric Johnson 9A–04-2014 0% 4th Quarter 2014 Feasib stakeho Receiv design re execute s Design kic Amtr Project sc 30% des design ef Substant Permit Rece Constru CSX fo Receive Received managem Kip Foster Development of a new VRE station in Spotsylvania County (Station Only, NO Parking) near the Crossroads Yard Station Design Design of the new platform and head house. Kip Foster 9F-06-2012 & 9G-06-2012 100% Completed 2nd Quarter 2013 Station Construction Construction of the new platform and head house. Kip Foster 9F-05-2013 0% TBD Macintosh HD:Users:Loren:Documents:VRE:CEO_Report:2014_May_CEOreport:Data:[2014-05 May CIP Progress 16 Board Item Number Feasibility Study Rolling Road Platform Extension Spotsylvania Station (New Station) Project Manager CEO REPORT | MAY 2014 Contrac N & PARKING PROJECTS Calendar ompletion ate (Est.) Status d Quarter 2013 Feasibility study was distributed to stakeholders Jan 2013. Comments received from all stakeholders. Preparing final draft addressing comments. Preparing for final design once VDOT provides approval of use of GEC contract. d Quarter 2014 Received Board approval in March to execute CSX force account agreement, including design review, flagging for field work and right-of-entry. Will seek Board approval in May to execute AECOM task order supplement to include additional soil borings. Field work to be scheduled following coordination with CSX, City of Alexandria and Amtrak. t Quarter 2015 Design kickoff meeting held in early February. Currently arranging stakeholders meeting and design criteria meetings. Design will proceed once field work completed. Change Order, Budget & Schedule Change Notes & Updates Supplement No. 1, October 2013, $26,709 Vendor Total Adopted CIP Budget Thru FY14 ($) Total Board Approved Funds ($) Total Contractual Commitment Expenditures s To-Date ($) To-Date ($) AECOM $ 10,226,000 $ 162,711 $ 147,919 $ 140,487 $ 79,321 $ 76,650 $ 29,718 AECOM Gannett Fleming $ - $ 1,814,559 $ 1,728,151 $ 10,156 TOTALS $ 10,226,000 $ 2,056,591 $ 1,952,720 $ 180,361 $ 1,000,000 $ 1,000,000 $ 987,625 ompleted Project completed. Final invoice received 2/28/14; payment authorized 3/20/14. Amtrak $ 1,000,000 ompleted Project completed. Last invoice received 4/12/2013 Amtrak $ 750,000 $ 750,000 $ 750,000 $ 515,968 h Quarter 2014 Amtrak has spent all allocated budget, but performed only 70% of the work. Amtrak requesting additional $300k to complete the project. Project has been stopped; VRE and Amtrak reconciled work performed and payment up to the initial $600K project budget; Amtrak to submit revised agreement and estimate to complete the project. Amtrak $ 600,000 $ 600,000 $ 600,000 $ 573,953 Amtrak $ 278,867 $ 278,867 $ - $ - TOTALS $ 2,628,867 $ 2,628,867 $ 2,350,000 $ 2,077,547 Dewberry $ 3,420,000 $ 2,031,263 $ 1,846,603 $ 384,272 TOTALS $ 3,420,000 $ 2,031,263 $ 1,846,603 $ 384,272 $ 455,950 $ 449,002 $ 448,779 $ 132,000 $ 124,765 $ 27,842 $ 587,950 $ 573,767 $ 476,621 TBD Project scoping underway. Amtrak is in the process of writing an agreement to be submitted to VRE for review. Quarter 2014 d Quarter 2014 30% design submitted. Awaiting FTA approval of CE application submitted in August. 60% design effort will begin after CE approval is obtained. Initial comments have been generated from the 30% design review. mpleted 3rd arter 2013 Substantial Completion and owner occupancy in June. Punchlist complete. Fairfax County Permit closed out. Contract closeout pending contractor response to closeout notification. Change Order # 1, Canopy Roof/Gutters/Downspouts, $39,230 --- Change Order # 2, Stringer Repair/Replacement, $47,440 --- Change Order # 3, Structural Steel Repairs/Rehab, $45,682 --- Change Order # 4 - $4,928 Window Jamb Rehab and Replacement --- Change Order # 5 - $222 - Gutter Repair Vista Contracting, Inc. No additional flagging expected. Force account estimate for flagging in the amount of $124,765. CSX Trans. ompleted 2012 $ TOTALS $ 522,000 522,000 mpleted 4th arter 2012 Completed HDR $ 306,350 $ 278,500 $ 271,476 h Quarter 2014 HDR providing procurement assistance. HDR $ 103,400 $ 94,000 $ 87,694 h Quarter 2014 Received Board approval in March to award construction contract to Hammerhead Construction. Contract awarded in late April Will seek Board approval in May to execute CSX force account agreement for design review and flagging during construction, once estimate received from CSX. Hammerhead Construction $ 991,980 $ 901,800 d Quarter 2014 Received Board approval in March to execute communications line relocation agreement with CenturyLink. Agreement executed in early April. CenturyLink $ 66,664 $ 60,604 h Quarter 2014 Received Board approval in April to execute task order with Gannett Fleming for construction management and inspection services during construction of platform extension. Task order executed in late April. Gannett Fleming $ 164,786 $ 149,805 mpleted 2nd arter 2013 TBD Permitting complete with Spotsylvania County. Contract executed and CE issued by FHWA. once County acquires land. $ 2,820,000 TOTALS $ 2,820,000 TOTALS $ - $ 3,422,500 STV NTP to be issued Hammerhead Construction TOTALS $ 3,422,500 $ 1,633,180 $ 1,484,709 $ 359,170 $ - $ - $ - $ 405,912 $ 369,011 $ 205,332 $ 2,583,900 $ 2,349,000 $ 51,638 $ 2,989,812 $ 2,718,011 $ 256,970 TAB 1 CEO REPORT | MAY 2014 17 TRACK & INFRASTRUCTURE PROJECTS Project & Code L'Enfant Storage Track Spotsylvania Third Track Expansion (Crossroads to Hamilton -­‐ Fredericksburg) Descrip0on Construct ~1,400 feet of Storage Track North of the L'Enfant Sta0on Planorm, including Wayside Power (Capacity of 2 Trainsets) TRACK & INFRASTRUCTU Task Task Descrip0on Project Manager Board Item Number % of Total Task Comple0on Calendar Completion Date (Est.) Storage Track Construc0on Construct ~1,400 of track north of L'Enfant Sta0on Eric Johnson 8B-­‐10-­‐2006 100% Completed 4th Quarter 2010 Wayside Power Design Design wayside power for stored train sets Eric Johnson 90% 1st Quarter 2014 Wayside Power Construc0on Construc0on of wayside power for stored train sets Eric Johnson N/A 30% 3rd Quarter 2014 Air Compressor Procurement Procurement and installa0on of air compressor equipment for new storage track air system (eVA). Eric Johnson N/A 100% Switch & Signaliza0on Design Design of storage track switches and signals Eric Johnson 9B-­‐06-­‐2011 90% 2nd Quarter 2014 Third Track Civil Design Environmental Analysis and Final Design Kip Foster 100% Completed 2nd Quarter 2013 Third Track Signal Design Signal design and engineering support Kip Foster 9E-­‐06-­‐2012 100% 1st Quarter 2014 Track & Signal Construc0on Construc0on of Signals Kip Foster 9H-­‐09-­‐2013 25% n/a Track Work & Structures Construc0on of Track & Structures Kip Foster 9C-­‐06-­‐2013 20% HDR sub W Completed 3rd Air comp Quarter 2008 CSX previ con0nue one m Permikng Revi Signal Construct approximately 2.5 miles of third track leading to the new Spotsylvania Sta0on Clearing Phase 1 4th Quarter 2014 Phase 2 start. Co 2nd Quarter 2015 Macintosh HD:Users:Loren:Documents:VRE:CEO_Report:2014_May_CEOreport:Data:[2014-05 May CIP PLANNING, COMMUNICATIONS & INFORMATION TECHNOLOGY PLANNING, CPROJECTS OMMUNICATIONS & INFO Project & Code Gainesville Haymarket Expansion Planning Descrip0on Expansion of VRE Service to Gainesville & Haymarket, VA Task Task Descrip0on Project Manager Board Item Number % of Total Task Comple0on Calendar Completion Date (Est.) G/H Expansion Analysis (Feasibility) Develop expansion alterna9ves for VRE Service to G/H Chris0ne Hoeffner 9D-­‐12-­‐2007 Complete Complete G/H Expansion Project Development, Environmental and Design Perform planning and project development ac9vi9es, environmental analysis and engineering design Chris0ne Hoeffner 0% TBD Construc9on (Future) Future Track Construc9on TBD 0% TBD 0% TBD Mobile Ticke9ng Development and Implementa9on of a Mobile Ticke9ng System Chris Henry System Planning Prepare system plan to cover 20+ year planning horizon Chris0ne Hoeffner 8H-­‐09-­‐2013 1st Quarter 2014 9F-­‐04-­‐2013 18 Macintosh HD:Users:Loren:Documents:VRE:CEO_Report:2014_May_CEOreport:Data:[2014-­‐05 May CIP Progress CEO REPORT | MAY 2014 $1,500,000 VRE Ops STRUCTURE PROJECTS Total Board Contractual Total Adopted CIP Budget Thru Approved Funds Commitments To-­‐ FY14 ($) ($) Date ($) Total Expenditures To-­‐Date ($) Calendar ompletion Date (Est.) Status Change Order, Budget & Schedule Change Notes & Updates Vendor ompleted 4th uarter 2010 Track Complete n/a CSX Trans. Quarter 2014 HDR submiTed final wayside power design in early April. AWer VRE review, design will be submiTed to PEPCO to ini0ate design of electric service on Virginia Avenue and to CSX for review. Supplement to GEC V Task Order 7 in the amount of $8,600 executed in late December 2012. HDR $ -­‐ $ 50,925 $ 50,884 Quarter 2014 Wayside power construc0on to follow PEPCO's design and construc0on of electric service. NVE $ 3,219,000 $ -­‐ $ 688,480 $ 208,390 $ -­‐ $ 37,531 $ 37,531 Kaeser Compressors, Inc. ompleted 3rd Air compressor system delivered and stored at Crossroads Yard. Installa0on no longer included in scope of work. Inves0ga0ng alternate uses for equipment. uarter 2008 nd Quarter 2014 CSX previously an0cipated comple0on of track and signal modifica0on design in May 2013. Design work con0nues as of early May 2014. CSX expects to complete design and provide es0mate in approximately one month. Will seek Board approval for CSX construc0on force account agreement once es0mate received from CSX. CSX Trans. TOTALS Permikng complete, agency construc0on no0fica0ons issued. Design plans circulated for signature. Final mpleted 2nd Revision completed. Construc0on Plans circulated to contractors and other stakeholders. Pre-­‐ uarter 2013 Construc0on Conference held December 19, 2014. Quarter 2014 $ 830,000 $ 706,000 $ 442,794 Signal Design for Phase 1 and Phase 2 complete. Design checked by CSX. Signal Construc0on underway. $ 250,000 $ 225,000 $ 126,821 $ 3,219,000 $ 1,080,000 $ 1,707,936 $ 866,420 STV $ 817,703 $ 743,366 $ 396,034 CSX Trans. $ 1,009,800 $ 917,400 $ -­‐ $ 32,500,000 n/a CSX Trans. 100% design completed. Signal Construc0on Underway. Clearing and Grubbing complete. Crash Wall construc0on completed. Drainage Extensions preparing to ase 1 4th rter 2014 Phase 2 start. Construc0on Pads for trackwork in process. Borrow Material Fill Opera0ons for New Third Track nd Quarter 2015 Embankment and Trackbed have started. $ 20,522,611 $ 20,522,611 $ -­‐ CA # 1 -­‐ Access from Crossroads Pkwy ($112,715) CA # 2 -­‐ Load Test for Micropiles ($47,900) Abernathy CA # 3 -­‐ Subgrade Stabiliza0on ($86,583) CA # Construc0on 4&5 -­‐ Weather Extensions (0me only) Corp CA # 6 -­‐ Proposed Sta0on Site Fill ($155,899) TOTALS $ 8,880,073 $8,475,890 $1,710,972 $ 32,500,000 $ 31,230,187 $ 30,659,267 $ 2,107,006 TAB 2 S & INFORMATION TECH. PROJECTS Calendar ompletion ate (Est.) Status Change Order, Budget & Schedule Change Notes & Updates Vendor Complete Feasibility Study Completed on 9/28/2009 Aerial Survey Deferred to NEPA/PE. Revised Consultant Responsibility for Cost Es9ma9ng from Belstar to VHB/DMJM VHB TBD $1,500,000 allocated in FY14 NVTA regional funding. Awai9ng execu9on of a project agreement with NVTA. TBD Future Construc9on Related to Expansion TBD Quarter 2014 Funding Sources TBD Currently Pending Legal Ac9vi9es GEC task order ($35,000) for supplemental public outreach/communica9ons support issued 9/30/13 Total Board Approved Funds ($) Contractual Total Commitments Expenditures To-­‐Date ($) To-­‐Date ($) $ 1,537,338 $ 1,397,338 $ 1,042,749 TBD $ 3,037,338 $ -­‐ $ -­‐ $ -­‐ TBD $ -­‐ $ -­‐ $ -­‐ TOTALS $ 3,037,338 $ 1,537,338 $ 1,397,338 $ 1,042,749 GlobeSherpa $ 3,510,627 $ -­‐ $ -­‐ $ -­‐ $ 3,510,627 $ -­‐ $ -­‐ TOTALS VRE Ops Board adopted plan 1/17/14. Brochure complete. Final report under review by VRE. Total Adopted CIP Budget Thru FY14 ($) P.B. $ 185,000 $ 150,000 $ 185,000 $ 176,163 TOTALS $ 185,000 $ 150,000 $ 185,000 $ 176,163 TAB 3 CEO REPORT | MAY 2014 19 YARD PROJECTS YARD PROJEC Project & Code Descrip0on Task Crossroads Warehouse Design Broad Run Yard Train Wash and Crossroads Yard Warehouse Design and construcIon of Broad Run Yard train wash and Crossroads Yard warehouse. Yard Fall ProtecIon Task Descrip0on Project Manager Conceptual and final design of new Crossroads Eric Johnson warehouse. Board Item Number % of Total Task Comple0on Calendar Completion Date (Est.) 10D-­‐04-­‐2012 100% Completed 4th Quarter 2012 Crossroads Warehouse ConstrucIon ConstrucIon of new Crossroads warehouse. Eric Johnson 11E-­‐04-­‐2011 100% Completed 2nd Quarter 2013 Broad Run Train Wash Design Conceptual and final design and construcIon Eric Johnson administraIon for Broad Run train wash 9D-­‐06-­‐2012 90% 2nd Quarter 2014 Broad Run Train Wash ConstrucIon Future ConstrucIon/InstallaIon Work related to Broad Run train wash TBD TBD n/a n/a Kip Foster 9C-­‐01-­‐2013 100% Completed 3rd Quarter 2013 InstallaIon of fall protecIon systems at Broad Run and Crossroads yards Review of B County and sub Macintosh HD:Users:Loren:Documents:VRE:CEO_Report:2014_May_CEOreport:Data:[2014-­‐05 May CIP Progress ROLLING STOCK PROJECTS Project & Code Passenger Railcar Procurement PosiOve Train Control (PTC) Descrip0on To Acquire Fimeen (15) New Railcars from Sumitomo to add to the exisOng VRE Passenger Car Fleet ROLLING STOCK PR Task Task Descrip0on Project Manager Board Item Number % of Total Task Comple0on Calendar Completion Date (Est.) New Railcar Manufacture (8 cars) Base Order of 8 New Passenger railcars Rich Dalton 10C-­‐01-­‐2012 80% 1st Quarter 2016 New Railcar Manufacture (7 cars) OpOon Order of 7 New Passenger railcars Rich Dalton 8B-­‐11-­‐2013 0% 1st Quarter 2018 New Railcars Engineering Oversight (7 Cars) On site engineering through warranty administraOon under MEC V task order STV-­‐ 0038 under MEC V Rich Dalton 10A-­‐01-­‐2014 0% 4th Quarter 2017 New Railcars Engineering Oversight (8 Cars) On site engineering through warranty administraOon under MEC V task order STV-­‐ 0017 under MEC V Rich Dalton 9E-­‐02-­‐2012 68% 4th Quarter 2015 PosiOve Train Control InstallaOon and Infrastructure PosiOve Train Control for all locomoOves and cab control cars (total 41), as mandated by the Rich Dalton Rail Safety Improvement Act of 2008. 9E-­‐09-­‐2013 0% 1st Quarter 2015 Oversight Oversight -­‐ PosiOve Train Control for all locomoOves and cab control cars, as mandated Rich Dalton by the Rail Safety Improvement Act of 2008. 9A-­‐03-­‐2013 5% 1st Quarter 2014 Contract Am Kick Off mee To install and implement PosiOve Train Control (PTC) for all VRE LocomoOves Macintosh HD:Users:Loren:Documents:VRE:CEO_Report:2014_May_CEOreport:Data:[2014-­‐05 May CIP Progress 20 Man CEO REPORT | MAY 2014 Task ord D PROJECTS Calendar ompletion ate (Est.) Status mpleted 4th uarter 2012 mpleted 2nd arter 2013 Final payment issued in early April. Total Adopted CIP Budget Thru FY14 ($) Total Board Approved Funds ($) Contractual Total Commitments Expenditures To-­‐Date ($) To-­‐Date ($) Change Order, Budget & Schedule Change Notes & Updates Vendor STV Task Order #3 Supplement #1 for $146,414 for addiIonal Crossroads warehouse engineering services STV/RWA $ 629,248 $ 619,334 $ 619,311 Contract Amendment No. 1 -­‐ MulIple change orders increasing Contract amount by $124,409 and Contract Ime by nine days. Contract Amendment No. 2 -­‐ MulIple change orders increasing Contract amount by $87,774 and Contract Ime by 173 days. Trinity ConstrucIon Group, Inc. $ 2,600,000 $ 2,092,364 $ 2,125,632 $ 5,723,959 nd Quarter 2014 Review of Broad Run train wash 90% design completed. Plan submission to Prince William Supplement No. 1 -­‐ Increased contract amount by County and City of Manassas on hold while seeking addiIonal construcIon funding. STV to $3,864 for third party construcIon cost esImate. submit recommendaIons for Crossroads train wash modificaIons shortly. n/a mpleted 3rd uarter 2013 $ 307,513 $ 283,421 $ 174,875 STV/RWA TBD TOTALS Contract Closeout complete. Change Order / Contract Amendment # 1 ($14,896) issued. Increased contract amount from $154,074 to $168,970. $ -­‐ $ -­‐ $ -­‐ $ 5,723,959 $ 3,536,761 $ 2,995,119 $ 2,919,818 Industrial Turn Around $ 230,000 $ 169,482 $ 168,970 $ 168,970 CorporaIon (ITAC) TOTALS $ 230,000 $ 169,482 $ 168,970 $ 168,970 TAB 4 STOCK PROJECTS Calendar ompletion ate (Est.) Status Quarter 2016 Manufacturing of 8 base order passenger railcars final assembly in process Quarter 2018 Contract Amendment Executed; preliminary delivery schedule submiXed by SCOA/Project Kick Off meeOng held on March 20, 2014 Change Order, Budget & Schedule Change Notes & Updates Vendor Total Board Contractual Total Adopted CIP Budget Thru Approved Funds Commitments FY14 ($) ($) To-­‐Date ($) Total Expenditures To-­‐Date ($) The car numbers are designated as V820 -­‐ V827; the cars are in final assembly. -­‐delivery of first 4 cars in May 2014; Sumitomo -­‐ last 4 cars in June 2014 -­‐ delivery has been delayed to Nippon Sharyo resolve technical issues with emergency lighOng system. $ 23,140,000 $ 21,240,000 $ -­‐ Sumitomo -­‐ Nippon Sharyo $ 14,805,714 $ 14,805,714 $ -­‐ Contract Amendment Executed 12/19/2013 to increase the contract amount and order of cars. $ 39,419,714 Quarter 2017 Kick Off meeOng held on March 20, 2014; reviewing project schedule milestones and CDRL submiXal list The car numbers are designated as V828-­‐834 STV $ 892,500 $ 849,245 $ -­‐ Quarter 2015 ConOnuing to provide manufacturing and engineering oversight STV conOnues to provide oversight of the car construcOon in IL. Resident inspector acOve at Rochelle operaOon 5/5/2014 STV $ 1,474,000 $ 1,250,000 $ 888,255 Quarter 2015 Preparing contract documents for WRE AuthorizaOon to award a sole source contract to Wabtec was approved by both Commissions on 10-­‐3-­‐13, preparing sole source documentaOon and Scope of Work -­‐ under final legal review -­‐ 5/5/2014 Quarter 2014 Task order issued on March 13, 2013 to STV for engineering and oversight work for implementaOon. MEC IV Task Order 0026 PTC ImplementaOon oversight -­‐ DefiniOon Phase -­‐ Matrix of tasks was reviewed and approved by VRE for plan development and preparaOon underway for scope of work including hardware pricing and quotes, STV is also developing back office operaOon; updated 5/5/2014 TOTALS $ 39,419,714 $ 40,312,214 $ 38,144,959 $ 888,255 WRE $ 8,821,989 $ 7,980,877 $ 550,645 $ 47,023 STV TOTALS $ 8,821,989 $ 7,980,877 $ 550,645 $ 47,023 TAB 5 CEO REPORT | MAY 2014 21 NOTES __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ 22 CEO REPORT | MAY 2014 NOTES __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ CEO REPORT | MAY 2014 23 NOTES __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ 24 CEO REPORT | MAY 2014 NOTES __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ CEO REPORT | MAY 2014 25 1500 KING STREET | ALEXANDRIA, VA 22314 | 703.684.1001 | WWW.VRE.ORG