MAY 2015
6/5/2015
In May 2015, the primary focus of construction activities was the site grading, Module A interiors and the start of the tactical equipment in the range. Other exterior activities, such as pouring the heavy duty pavement and installing the screen wall support tubes, were ongoing in May. The electrical, plumbing and HVAC trade contractors continued their overhead work in Module A. Ongoing at that time, the acoustical ceilings contractor installed his grid and began dropping ceiling tile borders. Site grading of the west and north side the building started at the end of May.
Additionally, MEPFP work finished in the basement as the construction team initiated equipment start-up at the end of May. In the range, the firing range tactical equipment trade contractor began to work on their bullet trap, steel joint cover plates and angled baffles. The framing contractor installed the north plenum wall and Control Room ballistic window frames. The metal panel and glazing trade contractors installed their respective work at the east entryway with the east sidewalk & dock area poured at the end of April/early May. Most trade contractors maintained or increased their crew sizes throughout May so that they could continue working throughout the entire building. Further detail of the work that occurred in May is laid out in the schedule summary within this monthly report.
See full schedule as on 6/2/15 later in this report for exact dates of other construction activities.
Some key construction activities that occurred in May:
•
Range bullet trap work began on 5/4/15
•
Ceiling grid work began on 5/4/15
•
Drywall walls completed by 5/5/15 and ceilings completed by 5/12/15
•
Ceramic tile began on 5/11/15 and will be completed by 6/2/15
•
MEPFP ceiling finishes began on 5/12/15 and is ongoing
•
Steel for the screen wall was installed on 5/14/15
•
Storefront in Conference Room was installed 5/15/15
•
Stair 1 was installed by 5/18/15
•
Ballistic panel ceiling system began on 5/18/15 and is ongoing
•
Equipment start-up began on 5/20/15 and is ongoing
•
Curtainwall at Vestibule 1E was completed by 5/22/15
•
Nicor Gas Service into the building completed by 5/26/15
•
Prime and first coat painting is ongoing
•
Basement MEPFP work ongoing
Looking ahead to June, some key construction activates to occur:
•
Remaining site concrete sidewalks
•
Acoustical Ceiling Tiles
•
Installation of louvers
•
Completion of exterior metal panel system and screen wall
•
Continuation of equipment Start-up
•
Stair 1 concrete infill
•
Metal coping on roof to be completed
•
Carpet & Resilient Flooring contractor to mobilize and begin work
•
Curtainwall at Vestibule 1F
Activ ity
ID
CONSTRUCTION
Description
HTC1000 Fencing
HTC1020 Silt Fence
HTC1040 Protect Existing Structures
HTC1030 Stabilized Construction Entrance
HTC1050 Haul Road
HTC1250 Basement Excavation
HTC2350 Install Sump Pits
HTC1360 Basement Footing Excavation
HTC2380 Building Permit
HTC2440 Lost Day - Rain
HTC1280 Form and Pour Basement Concrete Footings
HTC1260 Range Footing Excavation
HTC1265 Lost Day - Rain
HTC2450 Form and Pour SW Basin Change
HTC1290 Form and Pour South Concrete Footings
HTC1350 Basement Deep Underground Plumbing
HTC2360 County Storm Water Permit
HTC1355 Basement Deep Underground Electrical
HTC1660 East Range Precast Walls
HTC1310 Basement Precast Walls
HTC1670 Remaining East & West Walls & Double Tees
HTC1675 Lost Day - Wind
HTC1340 Basement Steel
HTC2460 Basement Underground Plumbing & Electric
HTC2400 Lost Day - Wind
HTC1320 Water Proof Basement Precast
Orig
Dur
Start Finish
FY14
OCT NOV DEC JAN FEB MAR
FY15
APR
4
3
1
2
5
2
0
1
2
3
2
5
1
1
1
3
4
3
6
1
1
4
1
5
0
3
27AUG14 A 27AUG14 A
02SEP14 A 02SEP14 A
02SEP14 A 02SEP14 A
18SEP14 A 18SEP14 A
18SEP14 A 19SEP14 A
22SEP14 A 25SEP14 A
29SEP14 A 30SEP14 A
29SEP14 A 02OCT14 A
03OCT14 A
03OCT14 A 03OCT14 A
06OCT14 A 17OCT14 A
09OCT14 A 16OCT14 A
14OCT14 A 14OCT14 A
16OCT14 A 20OCT14 A
16OCT14 A 21OCT14 A
20OCT14 A 24OCT14 A
22OCT14 A
23OCT14 A 24OCT14 A
27OCT14 A 27OCT14 A
27OCT14 A 30OCT14 A
30OCT14 A 07NOV14 A
31OCT14 A 31OCT14 A
03NOV14 A 06NOV14 A
04NOV14 A 18NOV14 A
06NOV14 A 06NOV14 A
06NOV14 A 19JAN15 A nce t Existing Structure
Stabilized Construction Entranc
Haul Road
Basement Excavation
Install Sump Pits
Basement Footing Excavation
Building Permit
Lost Day - Rain
Form and Pour Basement Concrete Footings
Range Footing Excavation
Lost Day - Rain
Form and Pour SW Basin Change
Form and Pour South Concrete Footings
Basement Deep Underground Plumbing
County Storm Water Permit
Basement Deep Underground Electrical
East Range Precast Walls
Basement Precast Walls
Remaining East & West Walls & Double Tees
Lost Day - Wind
Basement Steel
Basement Underground Plumbing & Electric
Lost Day - Wind
Water Proof Basement Precast
MAY
Start date
Finish date
Data date
Run date
17SEP14
13AUG15
02JUN15
01JUN15
JUN JUL AUG E
Early bar
Target start point
Target finish point
Target bar
Progress bar
Critical bar
Progress point
Critical point
Start milestone point
Finish milestone point
Activ ity
ID
Description
HTC1400 1st Floor Hollowcore Precast
HTC1410 Roof Level Hollowcore Precast
HTC1680 South Precast Wall
HTC2470 Prep & Pour 1st Flr Hollow Core Topping
HTC1370 Stone Basement
HTC1690 Water Proof Range Precast
HTC2010 Hoist Roof Material & Accessories
HTC1120 Site Electric
HTC1140 Site Communication Duct Bank
HTC1985 TPO Roofing At Range Prep - Area #2
HTC1130 ComEd Transformer & Pad Delivery
HTC1380 Basement Vapor Barrier
HTC1390 Basement Slab on Grade
HTC2390 Remove Deadmen North Row
HTC2395 Remove Deadmen All Other Areas
HTC1330 Basement Exterior Footing Drain Tile
HTC1420 1st Floor CMU Walls
HTC1270 North Footing Excavation
HTC2340 UnderCut North & Replace UnSuitables Ftgs
HTC1500 Pumps
HTC1480 Chillers
HTC1300 Form & Pour North Ftgs & Foundations
HTC2270 Plumbing Equipment
HTC1990 TPO Roofing At Range Area #3
HTC1430 Electric Room & Stair 2 CMU Walls
HTC1540 Basement Piping
HTC1550 Basement Electric
HTC1700 Range Footing Drain Tile
HTC2410 Lost Day - Rain
HTC1490 Air-Handling Units
HTC1510 Basement Plumbing
HTC1460 Backfill Basement Walls
HTC1710 Backfill Range Walls
HTC1530 Basement Fire Protection
Orig
Dur
Start Finish
1 07NOV14 A 07NOV14 A
1 07NOV14 A 10NOV14 A
1 10NOV14 A 10NOV14 A
5 10NOV14 A 14NOV14 A
4 10NOV14 A 18NOV14 A
3 10NOV14 A 15DEC14 A
3 11NOV14 A 13NOV14 A
5 11NOV14 A 02MAR15 A
5 12NOV14 A 24MAR15 A
4 17NOV14 A 21NOV14 A
1 18NOV14 A 18NOV14 A
2 18NOV14 A 19NOV14 A
2 18NOV14 A 24NOV14 A
1 19NOV14 A 19NOV14 A
1 19NOV14 A 19NOV14 A
3 19NOV14 A 23DEC14 A
7 20NOV14 A 20JAN15 A
4
5
25NOV14 A 05DEC14 A
5
2
25NOV14 A 18DEC14 A
1
3
26NOV14 A 26NOV14 A
2
5
26NOV14 A 03DEC14 A
8
5
26NOV14 A 30DEC14 A
3
1
01DEC14 A 05DEC14 A
7
3
01DEC14 A 12DEC14 A
5
15
01DEC14 A 13JAN15 A
15 01DEC14 A 15MAY15 A
01DEC14 A 02JUN15 *
02DEC14 A 14JAN15 A
08DEC14 A 08DEC14 A
09DEC14 A 16DEC14 A
10DEC14 A 14JAN15 A
11DEC14 A 16JAN15 A
11DEC14 A 20JAN15 A
16DEC14 A 23DEC14 A
FY14
OCT NOV DEC
FY15
JAN FEB MAR APR MAY JUN JUL
1st Floor Hollowcore Precast
Roof Level Hollowcore Precast
South Precast Wall
Prep & Pour 1st Flr Hollow Core Topping
Stone Basement
Water Proof Range Precast
Hoist Roof Material & Accessories
TPO Roofing At Range Prep - Area #2
ComEd Transformer & Pad Delivery
Site Electric
Site Communication Duct Bank
Basement Vapor Barrier
Basement Slab on Grade
Remove Deadmen North Row
Remove Deadmen All Other Areas
Basement Exterior Footing Drain Tile
1st Floor CMU Walls
North Footing Excavation
UnderCut North & Replace UnSuitables Ftgs
Pumps
Chillers
Form & Pour North Ftgs & Foundations
Plumbing Equipment
TPO Roofing At Range Area #3
Electric Room & Stair 2 CMU Walls
Basement Piping
Basement Electric
Range Footing Drain Tile
Lost Day - Rain
Air-Handling Units
Basement Plumbing
Backfill Basement Walls
Backfill Range Walls
Basement Fire Protection
AUG E
Activ ity
ID
Description
HTC2020 Above Ceiling MEP Rough In Range Prep
HTC1860 North Structual Steel
HTC1720 Form and Pour Range Mechanical Chase
HTC1870 Steel Joist Framing
HTC1850 Backfill North Foundation Walls and Footings
HTC1470 Boilers
HTC1086 Lost Day Exterior Activities - Extreme Cold
HTC1090 Sanitary Sewers
HTC1087 Lost Day Exterior Activities - Extreme Cold
HTC1088 Lost Day Exterior Activities - Extreme Cold
HTC1089 Lost Day Exterior Activities - Extreme Cold
HTC1880 Steel Decking & Detailing
HTC1520 Basement Duct
HTC1930 Metal Exterior Framing
HTC1740 Stone Range
HTC1560 Precast Leave Out Panels at Area Well
HTC1750 Vapor Barrier/ Reinforcing Range
HTC1100 Site Storm Utility Drainage Piping
HTC1425 Doors Frames for CMU
HTC1760 Slab on Grade Range
HTC1570 Water Proof Area Well Precast Walls
HTC1900 North Undergound Electric
HTC1942 Lost Day - Large Amount of Snow
HTC1810 Insulated Panels Inside Precast Tees
HTC1940 Foil Faced Insulation
HTC2430 Stone North Pad
HTC1820 Continuous Unistrut To Precast Tees
HTC1992 TPO Roofing At Range Area #3A & Ice Melt
HTC1440 Stair 2 Install
HTC1890 North Undergound Plumbing
HTC1580 Backfill Mech Area Well Walls
HTC1955 TPO Roofing North - Areas #1A, B, C & 4
HTC1830 Range Above Ceiling MEP
HTC1834 Lost Day Exterior Activities - Extreme Cold
Orig
Dur
2
5
3
5
20
1
5
4
8
3
1
10
1
3
1
3
3
5
4
2
10
7
1
5
1
1
1
3
2
2
5
4
30
5
Start Finish
16DEC14 A 15APR15 A
23DEC14 A 02JAN15 A
29DEC14 A 12JAN15 A
29DEC14 A 12JAN15 A
29DEC14 A 10FEB15 A
31DEC14 A 05JAN15 A
05JAN15 A 05JAN15 A
06JAN15 A 19FEB15 A
07JAN15 A 07JAN15 A
08JAN15 A 08JAN15 A
09JAN15 A 09JAN15 A
12JAN15 A 16JAN15 A
15JAN15 A 12MAY15 A
19JAN15 A 23FEB15 A
20JAN15 A 23JAN15 A
23JAN15 A 26JAN15 A
26JAN15 A 28JAN15 A
26JAN15 A 04FEB15 A
26JAN15 A 06FEB15 A
28JAN15 A 30JAN15 A
30JAN15 A 10FEB15 A
30JAN15 A 10MAR15 A
02FEB15 A 02FEB15 A
02FEB15 A 17FEB15 A
03FEB15 A 16MAR15 A
05FEB15 A 12FEB15 A
09FEB15 A 20FEB15 A
09FEB15 A 13MAR15 A
12FEB15 A 18FEB15 A
13FEB15 A 20FEB15 A
13FEB15 A 12MAR15 A
16FEB15 A 09MAR15 A
16FEB15 A 28APR15 A
18FEB15 A 18FEB15 A
FY14
OCT NOV DEC
FY15
JAN FEB MAR APR MAY JUN JUL
Above Ceiling MEP Rough In Range Prep
North Structual Steel
Form and Pour Range Mechanical Chase
Steel Joist Framing
Backfill North Foundation Walls and Footings
Boilers
Lost Day Exterior Activities - Extreme Cold
Sanitary Sewers
Lost Day Exterior Activities - Extreme Cold
Lost Day Exterior Activities - Extreme Cold
Lost Day Exterior Activities - Extreme Cold
Steel Decking & Detailing
Basement Duct
Metal Exterior Framing
Stone Range
Precast Leave Out Panels at Area Well
Vapor Barrier/ Reinforcing Range
Site Storm Utility Drainage Piping
Doors Frames for CMU
Slab on Grade Range
Water Proof Area Well Precast Walls
North Undergound Electric
Lost Day - Large Amount of Snow
Insulated Panels Inside Precast Tees
Foil Faced Insulation
Stone North Pad
Continuous Unistrut To Precast Tees
TPO Roofing At Range Area #3A & Ice Melt
Stair 2 Install
North Undergound Plumbing
Backfill Mech Area Well Walls
TPO Roofing North - Areas #1A, B, C & 4
Range Above Ceiling MEP
Lost Day Exterior Activities - Extreme Cold
AUG E
Activ ity
ID
Description
HTC1836 Lost Day Exterior Activities - Extreme Cold
HTC1450 Pour Stair 2 Concrete
HTC2024 Above Ceiling MEP Rough In North
HTC1770 2x4 Framing of Range Walls
HTC2370 Connection to Storm System
HTC1105 Site Storm Drainage System
HTC1910 North Vapor Barrier
HTC1920 Pour North Slab On Grade
HTC2030 Framing Interiior Walls
HTC1080 Site Water Utility Distribution
HTC1170 Site Grading South & West Sides
HTC2050 Door Frames for Stud Walls
HTC2080 Drywall
HTC2040 MEP Wall Rough Module A
HTC1950 Metal Panel Exterior
HTC1590 Excavate for Screen Wall Foundations
HTC1730 Footing & Pier Concrete for East Screen Wall
HTC1970 Glazed Alum Curtain Wall North Entrance
HTC1735 Backfill Ftgs & Piers for East Dock Area
HTC1630 Stair 1 CMU
HTC1972 Punch Window Ribbons
HTC2090 Taping and Sanding
HTC1150 Install Concrete Pavement Heavy Duty
HTC1180 Exterior Lighting
HTC1175 Site Grading on East Side (South Portion)
HTC1620 Set Condensing Units
HTC1110 Nicor Gas Service
HTC2060 Drywall Ceiling
HTC2100 Prime Painting & First Coat
HTC1790 Bullet Trap
HTC2110 Ceiling Grid
HTC1160 Install Concrete Sidewalks
HTC1200 Start of Owner's Landscaping
HTC2170 Ceramic Tile
5
10
10
4
0
15
Orig
Dur
4
5
6
10
3
4
4
15
10
2
3
10
15
15
63
3
10
2
13
5
2
2
1
5
20
10
1
1
Start Finish
19FEB15 A 19FEB15 A
20FEB15 A 20FEB15 A
24FEB15 A 12MAY15 A
27FEB15 A 09MAR15 A
05MAR15 A 05MAR15 A
05MAR15 A 16MAR15 A
11MAR15 A 11MAR15 A
12MAR15 A 12MAR15 A
13MAR15 A 30MAR15 A
17MAR15 A 19MAR15 A
17MAR15 A 17APR15 A
19MAR15 A 30MAR15 A
19MAR15 A 05MAY15 A
24MAR15 A 13APR15 A
24MAR15 A 19JUN15 *
27MAR15 A 30MAR15 A
31MAR15 A 02APR15 A
31MAR15 A 17APR15 A
06APR15 A 08APR15 A
08APR15 A 15APR15 A
08APR15 A 17APR15 A
20APR15 A 18MAY15 A
23APR15 A 14MAY15 A
24APR15 A 12JUN15 *
27APR15 A 07MAY15 A
28APR15 A 28APR15 A
28APR15 A 26MAY15 A
29APR15 A 12MAY15 A
30APR15 A 12JUN15 *
04MAY15 A 16JUN15
04MAY15 A 03JUN15 *
04MAY15 A 12JUN15 *
08MAY15 A
11MAY15 A 02JUN15
FY14
OCT NOV DEC
FY15
JAN FEB MAR APR MAY JUN JUL AUG E
Lost Day Exterior Activities - Extreme Cold
Pour Stair 2 Concrete
Above Ceiling MEP Rough In North
2x4 Framing of Range Walls
Connection to Storm System
Site Storm Drainage System
North Vapor Barrier
Pour North Slab On Grade
Framing Interiior Walls
Site Water Utility Distribution
Site Grading South & West Sides
Door Frames for Stud Walls
Drywall
MEP Wall Rough Module A
Metal Panel Exterior
Excavate for Screen Wall Foundations
Footing & Pier Concrete for East Screen Wall
Glazed Alum Curtain Wall North Entrance
Backfill Ftgs & Piers for East Dock Area
Stair 1 CMU
Punch Window Ribbons
Taping and Sanding
Install Concrete Pavement Heavy Duty
Exterior Lighting
Site Grading on East Side (South Portion)
Set Condensing Units
Nicor Gas Service
Drywall Ceiling
Prime Painting & First Coat
Bullet Trap
Ceiling Grid
Install Concrete Sidewalks
Start of Owner's Landscaping
Ceramic Tile
Activ ity
ID
Description
Orig
Dur
Start Finish
HTC1775 Stl Jt Cover, Insulation & Plywood Range Walls
HTC2230 Projection Screens & AV
HTC1640 Stair 1 Install
HTC2130 MEP Ceiling Finishes
HTC1600 Steel for Screen Wall
HTC1960 Alum Storefront Conference Room #1010
HTC1977 Curtainwall At Vesibule 1E on East side
HTC1840 Ballistic Panel Ceiling System
HTC1177 Grading Remaining East Counterclockwise
HTC2280 Equipment Start up
HTC2120 SAT Cut Tiles
HTC1980 East & West Large Louvers
HTC1205 Start of Remaining Owner's Landscaping
HTC1650 Pour Stair 1 Concrete
HTC2210 Corner Guards and Wall Rub Strips
HTC1800 Target System
HTC2164 Ballistic Frames & Doors
HTC2150 SAT Drop Tiles
HTC2160 Wood Doors and Hardware
HTC2140 Millwork
HTC1974 CurtainWall At Vestibule 1F on West side
HTC2000 Sheet Metal Coping
HTC2180 Resilient Flooring and Accessories
HTC2250 Plumbing Fixtures
HTC2330 MEP Trim
HTC1780 Ballistic Wall Panels
HTC2190 Carpet Tile
HTC1610 Metal Screenwall Panels
HTC2220 Toilet and Bath Accessories
HTC2290 Testing, Adjusting, and Balancing for HVAC
HTC2260 Final Painting
HTC2200 Operable Panel Partitions
HTC2300 Indoor Air Quality Testing
HTC2310 Commissioning of HVAC
5
3
11MAY15 A 29JUN15
17 11MAY15 A 08JUL15
12MAY15 A 18MAY15 A
10 12MAY15 A 05JUN15
2 14MAY15 A 14MAY15 A
5 15MAY15 A 28MAY15 A
5 18MAY15 A 22MAY15 A
15 18MAY15 A 29JUN15
8 20MAY15 A 15JUN15
10 20MAY15 A 18JUN15
5 26MAY15 A 04JUN15
4 01JUN15 A 10JUN15
0 01JUN15 *
1 15JUN15 15JUN15
4 17JUN15 22JUN15
10 30JUN15 13JUL15
7 03JUL15 13JUL15
8 05JUN15 * 16JUN15
10 30JUN15 13JUL15
5 08JUN15 * 12JUN15
5 15JUN15 * 19JUN15
5 15JUN15 * 19JUN15
5 25JUN15 01JUL15
5 22JUN15 26JUN15
5 07JUL15 13JUL15
10 30JUN15 13JUL15
5 30JUN15 06JUL15
4 10JUN15 15JUN15
5 29JUN15 03JUL15
10 16JUN15 29JUN15
7 03JUL15 13JUL15
3 09JUL15 13JUL15
5 30JUN15 06JUL15
15 23JUN15 13JUL15
FY14
OCT NOV DEC
FY15
JAN FEB MAR APR MAY JUN JUL AUG E
Stl Jt Cover, Insulation & Plywoo
Projection Screens & A
Stair 1 Install
MEP Ceiling Finishes
Steel for Screen Wall
Alum Storefront Conference Room #
Curtainwall At Vesibule 1E on East side
Ballistic Panel Ceiling System
Grading Remaining East Cou
Equipment Start up
SAT Cut Tiles
East & West Large Louvers
Start of Remaining Owner's Lands
Pour Stair 1 Concrete
Corner Guards and Wall Rub Str
Target System
Ballistic Frames & Doors
SAT Drop Tiles
Wood Doors and Hardware
Millwork
CurtainWall At Vestibule 1F
Sheet Metal Coping
Resilient Flooring and Acces
Plumbing Fixtures
MEP Trim
Ballistic Wall Panels
Carpet Tile
Metal Screenwall Panels
Toilet and Bath Accessor
Testing, Adjusting, and
Final Painting
Operable Panel Partition
Commissioning o
Activ ity
ID
Description
HTC2240 Window Shade System
HTC2320 Ventilation Effectivness Testing
HTC2322 Inspections
HTC2321 Owner/Architect/Engineer Punchlist
HTC2328 Turn Over Meeting
HTC2335 Finish
HTC2326 Training, As Builts, O & Ms
HTC2323 Contractors Complete Punchlist
HTC2324 FFE
HTC2325 Move in
Orig
Dur
Start Finish
3 09JUL15 13JUL15
5 07JUL15 13JUL15
6 22JUL15 29JUL15
6 14JUL15 21JUL15
1 27JUL15 * 27JUL15
0
5 28JUL15 * 03AUG15
12 17JUL15
7 24JUL15
03AUG15
03AUG15
3 30JUL15
03AUG15
03AUG15
FY14
OCT NOV DEC
FY15
JAN FEB MAR APR MAY JUN JUL AUG E
Window Shade Syste
Ventilation Effect
Inspections
Owner/Arch
Turn Over Me
Finish
Training, A
Contrac
FFE
Move in