MONTHLY REPORT MAY 2015 POWERCONSTRUCTION

advertisement

COLLEGE OF DUPAGE HOMELAND SECURITY TRAINING CENTER

MONTHLY REPORT

MAY 2015

POWERCONSTRUCTION

6/5/2015

Project Status

In May 2015, the primary focus of construction activities was the site grading, Module A interiors and the start of the tactical equipment in the range. Other exterior activities, such as pouring the heavy duty pavement and installing the screen wall support tubes, were ongoing in May. The electrical, plumbing and HVAC trade contractors continued their overhead work in Module A. Ongoing at that time, the acoustical ceilings contractor installed his grid and began dropping ceiling tile borders. Site grading of the west and north side the building started at the end of May.

Additionally, MEPFP work finished in the basement as the construction team initiated equipment start-up at the end of May. In the range, the firing range tactical equipment trade contractor began to work on their bullet trap, steel joint cover plates and angled baffles. The framing contractor installed the north plenum wall and Control Room ballistic window frames. The metal panel and glazing trade contractors installed their respective work at the east entryway with the east sidewalk & dock area poured at the end of April/early May. Most trade contractors maintained or increased their crew sizes throughout May so that they could continue working throughout the entire building. Further detail of the work that occurred in May is laid out in the schedule summary within this monthly report.

Schedule

See full schedule as on 6/2/15 later in this report for exact dates of other construction activities.

Some key construction activities that occurred in May:

Range bullet trap work began on 5/4/15

Ceiling grid work began on 5/4/15

Drywall walls completed by 5/5/15 and ceilings completed by 5/12/15

Ceramic tile began on 5/11/15 and will be completed by 6/2/15

MEPFP ceiling finishes began on 5/12/15 and is ongoing

Steel for the screen wall was installed on 5/14/15

Storefront in Conference Room was installed 5/15/15

Stair 1 was installed by 5/18/15

Ballistic panel ceiling system began on 5/18/15 and is ongoing

Equipment start-up began on 5/20/15 and is ongoing

Curtainwall at Vestibule 1E was completed by 5/22/15

Nicor Gas Service into the building completed by 5/26/15

Prime and first coat painting is ongoing

Basement MEPFP work ongoing

Looking ahead to June, some key construction activates to occur:

Remaining site concrete sidewalks

Acoustical Ceiling Tiles

Installation of louvers

Completion of exterior metal panel system and screen wall

Continuation of equipment Start-up

Stair 1 concrete infill

Metal coping on roof to be completed

Carpet & Resilient Flooring contractor to mobilize and begin work

Curtainwall at Vestibule 1F

Activ ity

ID

CONSTRUCTION

Description

HTC1000 Fencing

HTC1020 Silt Fence

HTC1040 Protect Existing Structures

HTC1030 Stabilized Construction Entrance

HTC1050 Haul Road

HTC1250 Basement Excavation

HTC2350 Install Sump Pits

HTC1360 Basement Footing Excavation

HTC2380 Building Permit

HTC2440 Lost Day - Rain

HTC1280 Form and Pour Basement Concrete Footings

HTC1260 Range Footing Excavation

HTC1265 Lost Day - Rain

HTC2450 Form and Pour SW Basin Change

HTC1290 Form and Pour South Concrete Footings

HTC1350 Basement Deep Underground Plumbing

HTC2360 County Storm Water Permit

HTC1355 Basement Deep Underground Electrical

HTC1660 East Range Precast Walls

HTC1310 Basement Precast Walls

HTC1670 Remaining East & West Walls & Double Tees

HTC1675 Lost Day - Wind

HTC1340 Basement Steel

HTC2460 Basement Underground Plumbing & Electric

HTC2400 Lost Day - Wind

HTC1320 Water Proof Basement Precast

Orig

Dur

Start Finish

FY14

OCT NOV DEC JAN FEB MAR

FY15

APR

4

3

1

2

5

2

0

1

2

3

2

5

1

1

1

3

4

3

6

1

1

4

1

5

0

3

27AUG14 A 27AUG14 A

02SEP14 A 02SEP14 A

02SEP14 A 02SEP14 A

18SEP14 A 18SEP14 A

18SEP14 A 19SEP14 A

22SEP14 A 25SEP14 A

29SEP14 A 30SEP14 A

29SEP14 A 02OCT14 A

03OCT14 A

03OCT14 A 03OCT14 A

06OCT14 A 17OCT14 A

09OCT14 A 16OCT14 A

14OCT14 A 14OCT14 A

16OCT14 A 20OCT14 A

16OCT14 A 21OCT14 A

20OCT14 A 24OCT14 A

22OCT14 A

23OCT14 A 24OCT14 A

27OCT14 A 27OCT14 A

27OCT14 A 30OCT14 A

30OCT14 A 07NOV14 A

31OCT14 A 31OCT14 A

03NOV14 A 06NOV14 A

04NOV14 A 18NOV14 A

06NOV14 A 06NOV14 A

06NOV14 A 19JAN15 A nce t Existing Structure

Stabilized Construction Entranc

Haul Road

Basement Excavation

Install Sump Pits

Basement Footing Excavation

Building Permit

Lost Day - Rain

Form and Pour Basement Concrete Footings

Range Footing Excavation

Lost Day - Rain

Form and Pour SW Basin Change

Form and Pour South Concrete Footings

Basement Deep Underground Plumbing

County Storm Water Permit

Basement Deep Underground Electrical

East Range Precast Walls

Basement Precast Walls

Remaining East & West Walls & Double Tees

Lost Day - Wind

Basement Steel

Basement Underground Plumbing & Electric

Lost Day - Wind

Water Proof Basement Precast

MAY

Start date

Finish date

Data date

Run date

17SEP14

13AUG15

02JUN15

01JUN15

C.O.D - HTC Construction

Power Construction Company, LLC

O/A/C Meeting Update 06 02 15

JUN JUL AUG E

Early bar

Target start point

Target finish point

Target bar

Progress bar

Critical bar

Progress point

Critical point

Start milestone point

Finish milestone point

Activ ity

ID

Description

HTC1400 1st Floor Hollowcore Precast

HTC1410 Roof Level Hollowcore Precast

HTC1680 South Precast Wall

HTC2470 Prep & Pour 1st Flr Hollow Core Topping

HTC1370 Stone Basement

HTC1690 Water Proof Range Precast

HTC2010 Hoist Roof Material & Accessories

HTC1120 Site Electric

HTC1140 Site Communication Duct Bank

HTC1985 TPO Roofing At Range Prep - Area #2

HTC1130 ComEd Transformer & Pad Delivery

HTC1380 Basement Vapor Barrier

HTC1390 Basement Slab on Grade

HTC2390 Remove Deadmen North Row

HTC2395 Remove Deadmen All Other Areas

HTC1330 Basement Exterior Footing Drain Tile

HTC1420 1st Floor CMU Walls

HTC1270 North Footing Excavation

HTC2340 UnderCut North & Replace UnSuitables Ftgs

HTC1500 Pumps

HTC1480 Chillers

HTC1300 Form & Pour North Ftgs & Foundations

HTC2270 Plumbing Equipment

HTC1990 TPO Roofing At Range Area #3

HTC1430 Electric Room & Stair 2 CMU Walls

HTC1540 Basement Piping

HTC1550 Basement Electric

HTC1700 Range Footing Drain Tile

HTC2410 Lost Day - Rain

HTC1490 Air-Handling Units

HTC1510 Basement Plumbing

HTC1460 Backfill Basement Walls

HTC1710 Backfill Range Walls

HTC1530 Basement Fire Protection

Orig

Dur

Start Finish

1 07NOV14 A 07NOV14 A

1 07NOV14 A 10NOV14 A

1 10NOV14 A 10NOV14 A

5 10NOV14 A 14NOV14 A

4 10NOV14 A 18NOV14 A

3 10NOV14 A 15DEC14 A

3 11NOV14 A 13NOV14 A

5 11NOV14 A 02MAR15 A

5 12NOV14 A 24MAR15 A

4 17NOV14 A 21NOV14 A

1 18NOV14 A 18NOV14 A

2 18NOV14 A 19NOV14 A

2 18NOV14 A 24NOV14 A

1 19NOV14 A 19NOV14 A

1 19NOV14 A 19NOV14 A

3 19NOV14 A 23DEC14 A

7 20NOV14 A 20JAN15 A

4

5

25NOV14 A 05DEC14 A

5

2

25NOV14 A 18DEC14 A

1

3

26NOV14 A 26NOV14 A

2

5

26NOV14 A 03DEC14 A

8

5

26NOV14 A 30DEC14 A

3

1

01DEC14 A 05DEC14 A

7

3

01DEC14 A 12DEC14 A

5

15

01DEC14 A 13JAN15 A

15 01DEC14 A 15MAY15 A

01DEC14 A 02JUN15 *

02DEC14 A 14JAN15 A

08DEC14 A 08DEC14 A

09DEC14 A 16DEC14 A

10DEC14 A 14JAN15 A

11DEC14 A 16JAN15 A

11DEC14 A 20JAN15 A

16DEC14 A 23DEC14 A

FY14

OCT NOV DEC

FY15

JAN FEB MAR APR MAY JUN JUL

1st Floor Hollowcore Precast

Roof Level Hollowcore Precast

South Precast Wall

Prep & Pour 1st Flr Hollow Core Topping

Stone Basement

Water Proof Range Precast

Hoist Roof Material & Accessories

TPO Roofing At Range Prep - Area #2

ComEd Transformer & Pad Delivery

Site Electric

Site Communication Duct Bank

Basement Vapor Barrier

Basement Slab on Grade

Remove Deadmen North Row

Remove Deadmen All Other Areas

Basement Exterior Footing Drain Tile

1st Floor CMU Walls

North Footing Excavation

UnderCut North & Replace UnSuitables Ftgs

Pumps

Chillers

Form & Pour North Ftgs & Foundations

Plumbing Equipment

TPO Roofing At Range Area #3

Electric Room & Stair 2 CMU Walls

Basement Piping

Basement Electric

Range Footing Drain Tile

Lost Day - Rain

Air-Handling Units

Basement Plumbing

Backfill Basement Walls

Backfill Range Walls

Basement Fire Protection

AUG E

Activ ity

ID

Description

HTC2020 Above Ceiling MEP Rough In Range Prep

HTC1860 North Structual Steel

HTC1720 Form and Pour Range Mechanical Chase

HTC1870 Steel Joist Framing

HTC1850 Backfill North Foundation Walls and Footings

HTC1470 Boilers

HTC1086 Lost Day Exterior Activities - Extreme Cold

HTC1090 Sanitary Sewers

HTC1087 Lost Day Exterior Activities - Extreme Cold

HTC1088 Lost Day Exterior Activities - Extreme Cold

HTC1089 Lost Day Exterior Activities - Extreme Cold

HTC1880 Steel Decking & Detailing

HTC1520 Basement Duct

HTC1930 Metal Exterior Framing

HTC1740 Stone Range

HTC1560 Precast Leave Out Panels at Area Well

HTC1750 Vapor Barrier/ Reinforcing Range

HTC1100 Site Storm Utility Drainage Piping

HTC1425 Doors Frames for CMU

HTC1760 Slab on Grade Range

HTC1570 Water Proof Area Well Precast Walls

HTC1900 North Undergound Electric

HTC1942 Lost Day - Large Amount of Snow

HTC1810 Insulated Panels Inside Precast Tees

HTC1940 Foil Faced Insulation

HTC2430 Stone North Pad

HTC1820 Continuous Unistrut To Precast Tees

HTC1992 TPO Roofing At Range Area #3A & Ice Melt

HTC1440 Stair 2 Install

HTC1890 North Undergound Plumbing

HTC1580 Backfill Mech Area Well Walls

HTC1955 TPO Roofing North - Areas #1A, B, C & 4

HTC1830 Range Above Ceiling MEP

HTC1834 Lost Day Exterior Activities - Extreme Cold

Orig

Dur

2

5

3

5

20

1

5

4

8

3

1

10

1

3

1

3

3

5

4

2

10

7

1

5

1

1

1

3

2

2

5

4

30

5

Start Finish

16DEC14 A 15APR15 A

23DEC14 A 02JAN15 A

29DEC14 A 12JAN15 A

29DEC14 A 12JAN15 A

29DEC14 A 10FEB15 A

31DEC14 A 05JAN15 A

05JAN15 A 05JAN15 A

06JAN15 A 19FEB15 A

07JAN15 A 07JAN15 A

08JAN15 A 08JAN15 A

09JAN15 A 09JAN15 A

12JAN15 A 16JAN15 A

15JAN15 A 12MAY15 A

19JAN15 A 23FEB15 A

20JAN15 A 23JAN15 A

23JAN15 A 26JAN15 A

26JAN15 A 28JAN15 A

26JAN15 A 04FEB15 A

26JAN15 A 06FEB15 A

28JAN15 A 30JAN15 A

30JAN15 A 10FEB15 A

30JAN15 A 10MAR15 A

02FEB15 A 02FEB15 A

02FEB15 A 17FEB15 A

03FEB15 A 16MAR15 A

05FEB15 A 12FEB15 A

09FEB15 A 20FEB15 A

09FEB15 A 13MAR15 A

12FEB15 A 18FEB15 A

13FEB15 A 20FEB15 A

13FEB15 A 12MAR15 A

16FEB15 A 09MAR15 A

16FEB15 A 28APR15 A

18FEB15 A 18FEB15 A

FY14

OCT NOV DEC

FY15

JAN FEB MAR APR MAY JUN JUL

Above Ceiling MEP Rough In Range Prep

North Structual Steel

Form and Pour Range Mechanical Chase

Steel Joist Framing

Backfill North Foundation Walls and Footings

Boilers

Lost Day Exterior Activities - Extreme Cold

Sanitary Sewers

Lost Day Exterior Activities - Extreme Cold

Lost Day Exterior Activities - Extreme Cold

Lost Day Exterior Activities - Extreme Cold

Steel Decking & Detailing

Basement Duct

Metal Exterior Framing

Stone Range

Precast Leave Out Panels at Area Well

Vapor Barrier/ Reinforcing Range

Site Storm Utility Drainage Piping

Doors Frames for CMU

Slab on Grade Range

Water Proof Area Well Precast Walls

North Undergound Electric

Lost Day - Large Amount of Snow

Insulated Panels Inside Precast Tees

Foil Faced Insulation

Stone North Pad

Continuous Unistrut To Precast Tees

TPO Roofing At Range Area #3A & Ice Melt

Stair 2 Install

North Undergound Plumbing

Backfill Mech Area Well Walls

TPO Roofing North - Areas #1A, B, C & 4

Range Above Ceiling MEP

Lost Day Exterior Activities - Extreme Cold

AUG E

Activ ity

ID

Description

HTC1836 Lost Day Exterior Activities - Extreme Cold

HTC1450 Pour Stair 2 Concrete

HTC2024 Above Ceiling MEP Rough In North

HTC1770 2x4 Framing of Range Walls

HTC2370 Connection to Storm System

HTC1105 Site Storm Drainage System

HTC1910 North Vapor Barrier

HTC1920 Pour North Slab On Grade

HTC2030 Framing Interiior Walls

HTC1080 Site Water Utility Distribution

HTC1170 Site Grading South & West Sides

HTC2050 Door Frames for Stud Walls

HTC2080 Drywall

HTC2040 MEP Wall Rough Module A

HTC1950 Metal Panel Exterior

HTC1590 Excavate for Screen Wall Foundations

HTC1730 Footing & Pier Concrete for East Screen Wall

HTC1970 Glazed Alum Curtain Wall North Entrance

HTC1735 Backfill Ftgs & Piers for East Dock Area

HTC1630 Stair 1 CMU

HTC1972 Punch Window Ribbons

HTC2090 Taping and Sanding

HTC1150 Install Concrete Pavement Heavy Duty

HTC1180 Exterior Lighting

HTC1175 Site Grading on East Side (South Portion)

HTC1620 Set Condensing Units

HTC1110 Nicor Gas Service

HTC2060 Drywall Ceiling

HTC2100 Prime Painting & First Coat

HTC1790 Bullet Trap

HTC2110 Ceiling Grid

HTC1160 Install Concrete Sidewalks

HTC1200 Start of Owner's Landscaping

HTC2170 Ceramic Tile

5

10

10

4

0

15

Orig

Dur

4

5

6

10

3

4

4

15

10

2

3

10

15

15

63

3

10

2

13

5

2

2

1

5

20

10

1

1

Start Finish

19FEB15 A 19FEB15 A

20FEB15 A 20FEB15 A

24FEB15 A 12MAY15 A

27FEB15 A 09MAR15 A

05MAR15 A 05MAR15 A

05MAR15 A 16MAR15 A

11MAR15 A 11MAR15 A

12MAR15 A 12MAR15 A

13MAR15 A 30MAR15 A

17MAR15 A 19MAR15 A

17MAR15 A 17APR15 A

19MAR15 A 30MAR15 A

19MAR15 A 05MAY15 A

24MAR15 A 13APR15 A

24MAR15 A 19JUN15 *

27MAR15 A 30MAR15 A

31MAR15 A 02APR15 A

31MAR15 A 17APR15 A

06APR15 A 08APR15 A

08APR15 A 15APR15 A

08APR15 A 17APR15 A

20APR15 A 18MAY15 A

23APR15 A 14MAY15 A

24APR15 A 12JUN15 *

27APR15 A 07MAY15 A

28APR15 A 28APR15 A

28APR15 A 26MAY15 A

29APR15 A 12MAY15 A

30APR15 A 12JUN15 *

04MAY15 A 16JUN15

04MAY15 A 03JUN15 *

04MAY15 A 12JUN15 *

08MAY15 A

11MAY15 A 02JUN15

FY14

OCT NOV DEC

FY15

JAN FEB MAR APR MAY JUN JUL AUG E

Lost Day Exterior Activities - Extreme Cold

Pour Stair 2 Concrete

Above Ceiling MEP Rough In North

2x4 Framing of Range Walls

Connection to Storm System

Site Storm Drainage System

North Vapor Barrier

Pour North Slab On Grade

Framing Interiior Walls

Site Water Utility Distribution

Site Grading South & West Sides

Door Frames for Stud Walls

Drywall

MEP Wall Rough Module A

Metal Panel Exterior

Excavate for Screen Wall Foundations

Footing & Pier Concrete for East Screen Wall

Glazed Alum Curtain Wall North Entrance

Backfill Ftgs & Piers for East Dock Area

Stair 1 CMU

Punch Window Ribbons

Taping and Sanding

Install Concrete Pavement Heavy Duty

Exterior Lighting

Site Grading on East Side (South Portion)

Set Condensing Units

Nicor Gas Service

Drywall Ceiling

Prime Painting & First Coat

Bullet Trap

Ceiling Grid

Install Concrete Sidewalks

Start of Owner's Landscaping

Ceramic Tile

Activ ity

ID

Description

Orig

Dur

Start Finish

HTC1775 Stl Jt Cover, Insulation & Plywood Range Walls

HTC2230 Projection Screens & AV

HTC1640 Stair 1 Install

HTC2130 MEP Ceiling Finishes

HTC1600 Steel for Screen Wall

HTC1960 Alum Storefront Conference Room #1010

HTC1977 Curtainwall At Vesibule 1E on East side

HTC1840 Ballistic Panel Ceiling System

HTC1177 Grading Remaining East Counterclockwise

HTC2280 Equipment Start up

HTC2120 SAT Cut Tiles

HTC1980 East & West Large Louvers

HTC1205 Start of Remaining Owner's Landscaping

HTC1650 Pour Stair 1 Concrete

HTC2210 Corner Guards and Wall Rub Strips

HTC1800 Target System

HTC2164 Ballistic Frames & Doors

HTC2150 SAT Drop Tiles

HTC2160 Wood Doors and Hardware

HTC2140 Millwork

HTC1974 CurtainWall At Vestibule 1F on West side

HTC2000 Sheet Metal Coping

HTC2180 Resilient Flooring and Accessories

HTC2250 Plumbing Fixtures

HTC2330 MEP Trim

HTC1780 Ballistic Wall Panels

HTC2190 Carpet Tile

HTC1610 Metal Screenwall Panels

HTC2220 Toilet and Bath Accessories

HTC2290 Testing, Adjusting, and Balancing for HVAC

HTC2260 Final Painting

HTC2200 Operable Panel Partitions

HTC2300 Indoor Air Quality Testing

HTC2310 Commissioning of HVAC

5

3

11MAY15 A 29JUN15

17 11MAY15 A 08JUL15

12MAY15 A 18MAY15 A

10 12MAY15 A 05JUN15

2 14MAY15 A 14MAY15 A

5 15MAY15 A 28MAY15 A

5 18MAY15 A 22MAY15 A

15 18MAY15 A 29JUN15

8 20MAY15 A 15JUN15

10 20MAY15 A 18JUN15

5 26MAY15 A 04JUN15

4 01JUN15 A 10JUN15

0 01JUN15 *

1 15JUN15 15JUN15

4 17JUN15 22JUN15

10 30JUN15 13JUL15

7 03JUL15 13JUL15

8 05JUN15 * 16JUN15

10 30JUN15 13JUL15

5 08JUN15 * 12JUN15

5 15JUN15 * 19JUN15

5 15JUN15 * 19JUN15

5 25JUN15 01JUL15

5 22JUN15 26JUN15

5 07JUL15 13JUL15

10 30JUN15 13JUL15

5 30JUN15 06JUL15

4 10JUN15 15JUN15

5 29JUN15 03JUL15

10 16JUN15 29JUN15

7 03JUL15 13JUL15

3 09JUL15 13JUL15

5 30JUN15 06JUL15

15 23JUN15 13JUL15

FY14

OCT NOV DEC

FY15

JAN FEB MAR APR MAY JUN JUL AUG E

Stl Jt Cover, Insulation & Plywoo

Projection Screens & A

Stair 1 Install

MEP Ceiling Finishes

Steel for Screen Wall

Alum Storefront Conference Room #

Curtainwall At Vesibule 1E on East side

Ballistic Panel Ceiling System

Grading Remaining East Cou

Equipment Start up

SAT Cut Tiles

East & West Large Louvers

Start of Remaining Owner's Lands

Pour Stair 1 Concrete

Corner Guards and Wall Rub Str

Target System

Ballistic Frames & Doors

SAT Drop Tiles

Wood Doors and Hardware

Millwork

CurtainWall At Vestibule 1F

Sheet Metal Coping

Resilient Flooring and Acces

Plumbing Fixtures

MEP Trim

Ballistic Wall Panels

Carpet Tile

Metal Screenwall Panels

Toilet and Bath Accessor

Testing, Adjusting, and

Final Painting

Operable Panel Partition

Commissioning o

Activ ity

ID

Description

HTC2240 Window Shade System

HTC2320 Ventilation Effectivness Testing

HTC2322 Inspections

HTC2321 Owner/Architect/Engineer Punchlist

HTC2328 Turn Over Meeting

HTC2335 Finish

HTC2326 Training, As Builts, O & Ms

HTC2323 Contractors Complete Punchlist

HTC2324 FFE

HTC2325 Move in

Orig

Dur

Start Finish

3 09JUL15 13JUL15

5 07JUL15 13JUL15

6 22JUL15 29JUL15

6 14JUL15 21JUL15

1 27JUL15 * 27JUL15

0

5 28JUL15 * 03AUG15

12 17JUL15

7 24JUL15

03AUG15

03AUG15

3 30JUL15

03AUG15

03AUG15

FY14

OCT NOV DEC

FY15

JAN FEB MAR APR MAY JUN JUL AUG E

Window Shade Syste

Ventilation Effect

Inspections

Owner/Arch

Turn Over Me

Finish

Training, A

Contrac

FFE

Move in

Bullet Trap Framing on 5/5/15

Ceiling Grid in Simulator Room on 5/5/15

Range Prep Gun Cleaning Stations

Ductwork Rough-In on 5/11/15

Concrete Drive into Range on 5/15/15

Conference Room Storefront Glazing on 5/15/15

Ceramic Tiling Work in Women's Toilet on 5/18/15

Installation of Angled Baffles in Range on 5/21/15

Control Room Ballistic Window Frame Install on 5/28/15

Office Sidelites Installed on 5/29/15

Painting Classroom 1001A/B Door Frames on 5/29/15