Operations Committee Meeting October 19-20, 2011 Helena, Montana Introductions Chairman Greg Archie reviewed the agenda and introductions were done. Agenda: Update Ops Committee membership and representation Lessons learned – Fire Season 2011 Team Assignment Reviews – I.C.’s please come prepared to discuss your team assignments from a lessons learned standpoint Team Mobilizations – NRCC and Team Zones please review mobilizations (lessons learned) NRCG Zones review and lessons learned NRCG Committee updates, issues, concerns Aviation Business – Please discuss IC cost summary (request from Poncin) Equipment Fire Use/Fire Management FPA NAC Prevention Training Recap of fire season safety – WW/Zachry Planning for spring Team Meetings Team Management – Re-apply? Recruitment, Other issues? Hosting of Wildland Fire Management Teams Update from Smokejumpers Update from NR IHC’s Operations Committee Chair Update Ops Committee membership and representation Zone Reps: South Central Zone-Bob Fry; Central Zone-Greg Archie; Eastern Zone-? ;North ID Zone-Mike Almas; NW Zone-Alan Osborn; North Dakota Zone-Doug Downs; Southwest Zone-Louis Hartjes Committee Reps: listed below under reports Greg Archie- Will be posting information on the NRCG website for the Operations committee. Lessons learned – Fire Season 2011 Team Assignments: Eastern MT Heintz team – 2 assignments – Pre-order a generator and the equipment to have power and phones in order to establish camp immediately; order a portable cell tower if possible-Communications is essential; Wisdom assignment was as a semi-short team, prefer to go long and then demob personnel as soon as possible this allows the ICP to get set up in a more timely manner; lag time in the cache management in getting supplies. NR Type 1 Turman team- Wally Bennett – 2 assignments – both national; Liaison officers are key for national assignments; spike camps with several hundred people require logistics being beefed up; Logistics are critical in the boundary waters assignments and also get some local folks for sections; information is critical also; be prepared for working with local resources and the issues in the boundary waters areas. NR Type 1 Poncin team- 2 assignments – Rust will be an issue if you don’t get out regularly – Make sure you have several communications solutions for phones and internet; challenge of 3 different delegations from different agencies; had some issues with basic resource ordering; needed more liaisons to deal with issues nationally; public information was high and needs to be ramped up immediately; treated the border patrol and other law agencies as a branch; negotiated from a short team up to a long team with a few others and it worked with the exception of the people not being ordered although they do understand the issues; need to discuss team length; don’t sign your name to a crew extension until you check with the geographic area. Western MT Fry team – Negotiated team size with the understanding we would demob ASAP and team was very good with that mental adjustment; Developed an Assignment Specific Medical Emergency Action Plan and will have it posted to the Lessons Learned website; Rust is a challenge when we are not ordered for 3 years in keeping up with qualifications. Operations Committee meeting minutes – NRCG October 19th & 20th, 2011 - - - - Eastern MT Benes team-John Thompson – 3 assignments – passed out a 2 page lessons learned – Struggled getting personnel to the assignment when they aren’t on the initial order; finance packages were an issue when taking over an incident from a transition, need to beef up finance to deal with it; Team staging was a challenge and we used it as a training opportunity to learn; Follow up on all initial ordering with multiple dispatches; Supply ordering was an issue and Logistics needs to engaged quicker; Team trailers were staged in various locations and worked well; Large phone companies are not as responsive as small rural companies, utilize cell phones more; Facilities utilized a single potable water tender for both showers and kitchen and had a good cost savings; Other complex incidents (all hazards) can affect supplies; people and personalities make or break a team; challenge team members to higher standards. Northern ID teams- Rick Kusicko – talked about both North ID teams lessons learned; Needed to fill assignments by utilizing both team rosters to staff one team; communication issues similar to other lessons from other teams; team review of accident procedures did help with an actual incident. Wildland Fire teams- Diane Hutton – 4 assignments – Really went out to write long term plans on a couple of assignments; fire policy was an issue for deciding the best process to manage wildland fires; challenge of going to a fire assignment that didn’t really fit the capability of a wildland fire team; communications issues are major and may need to be looked at by a committee in the off season to deal with the mobilization issue; utilized Google briefings to brief multiple agencies and worked well; fire behavior models are not accurate for bug kill; National caterer numbers were an issue. Mobilization issues – Discussion about the process of ordering Wildland Fire teams and Type 2 teams. Clarification was provided that the closest team in the 2 hour slots will be ordered for assignments within their areas, e.g. Eastern teams for eastern fires, Western team for WMT fires, North ID teams for North ID fires. Also discussed the issue of Long Term Planning issues. NRCC – Bob Gilman & Judy Heintz – Mobilization was discussed; 209s were discussed and the issues creating by monitoring vs limited suppression; let NRCC know about roster issues before you get into 2 hour call; Judy is working on the percentage of ADs on each team. Mark talked about the pre-orders being planned for both short and long assignments and reviewed for the current fire policy; cache system had some issues for ordering and tracking, had nothing to do with the ROSS; NRCG had Agency Reps utilized out of the GACC and it was well utilized. Wally showed a powerpoint of the Boundary water fire dispatch to Ely, MN and discussed the lessons learned. Greg shared one from the AZ dispatch. End of Day 1 Start of Day 2 - Brad McBratney talked about the SW wildland management team – The team will be hosted by the Northern Rockies in the future – Will need another NRs IC as Brad is not available during the fire season up here. Both Brad and Diane would like to share a trainee IC. NRCG Committee updates, issues, concerns Aviation – No Update due to time limitations – Greg Poncin is the Operations committee rep to the Aviation committee Business – Pam Okon – Discussed the Finance Chief situation – Business committee meeting in Helena Nov 1st and 2nd – Discussed courses being held and will continue with finance piece during operations courses – Discussed preference for the 260/261 courses and the format for holding them – Discussed the daily cost summary and how the questions and information is utilized – Doug Turman is the Operations committee rep but Greg Archie will attend the November meeting to cover for Doug Equipment – Tim Murphy – Updated Equipment meeting from this week meeting – Dozer boss is changing to Heavy Equipment bosses and ROSS recognizes it , quite a few HE boss trainees were trained recently – new 310-1 has a position called an ICPI Incident Contract Project Inspector tied to the Procurement Unit Leader – ICPI trainings April 24th-26 and May 2nd-4th and will be listed in the NRTC calendar – handed out contractor solicitation information and discussed it – need to get good performance evaluations especially on the good and bad performers - the contractor issues with local FDs still exist - Rick Seidlitz is the Operations committee rep to the Equipment committee, Brett Waters will be Rick’s backup Fire Use/Fire Management – Brad McBratney discussed whether the committee needs to be listed, proposed dropping the committee from the Operations committee – Committee has been dropped FPA – No Update NAC – Robert LaPlant discussed issues with Type 2 crews and Type 2 IA crews and is meeting with FMOs from November 29th – Dec 1st and looking for IC support at the meeting. Prevention – No current Operations rep identified to the Prevention committee Training – Paul Fieldhouse – Travel costs are an issue for courses – 310-1 has been updated and one significant change is taskbook experience from expired taskbooks can be utilized for new taskbooks – new currency criteria – National Geographic training group is looking into resurrecting some wildland fire on-line training modules & how that relates to Operations Committee meeting minutes – NRCG October 19th & 20th, 2011 the taskbooks – Succession planning was discussed – Type 3 simulation evaluations for Federal USFS is being discontinued – Training committee meeting in Mammoth next week – Will be a new outreach for Paul’s position as he will be retiring soon – Training center’s mission is being discussed along the lines of having USFS training being a major part of the mission and it was recommended that the Ops committee needs to be engaged in that discussion – S420 spreadsheet passed out and courses discussed – Passed out information sheet about a course which covers both S420 and L-480 and discussed it, the course will likely be held in the spring and sponsored by the Washington office – S520/620 candidates were discussed - Greg Archie is the Operations committee rep to the training committee Recap of fire season safety – Wayne Williams Wayne discussed work rest guidelines and driving guidelines which were updated in 2004 and reviewed them – weren’t good briefings about the border safety issues Planning for spring Team Meetings Team meeting dates are set for March 20th and 21st in Missoula for C&GS – If you are going to have your team meeting in conjunction contact Judy Heintz at NRCC and let her know for logistical purposes. Team Management – Re-apply – Recruitment - Other issues Discussion about teams and the use of them, 2 Wildland Fire teams will be maintained to utilize the unique capabilities and a white paper will be put together by Brad McBratney, Jess Secrest, and Diane Hutton to outline those characteristics to the NRCG Board and Agency Administrators. Poncin team discussed reapplying for the team and what strengths and weaknesses will likely look like. His team will be reapplying this year All ICs prior to December 1st will need to get Judy Heintz their weaknesses so they can be included in the application process letter. Turman team – Wally talked for Doug about team status – will go one more year before reapplying for the entire year Heintz team – Brett talked for Tom about team status – In fairly good shape – right sizing is key Fry team – Fry talked about team status – Operations has lots of people but no stability for coordination of the section prior to dispatch and would like to resolve that Benes team – John Thompson talked for Stan – stable will not need to reapply Kusicko team – Rick will have the team reapplying – Logistics is the only question Hutton team – Diane will need a trainee for plans and logistics and her Ops are both retiring McBratney team – Brad will have his team reapplying – Operations will be short but has a long list of trainees – everything seems to be ok Update Ops Committee membership and representation Zone Reps: South Central Zone-Bob Fry; Central Zone-Greg Archie; Eastern Zone- no one represented; North ID ZoneMike Almas ;NW Zone-Alan Osborn; ND Zone – Doug Downs; SW MT Zone-Louis Hartjes; Update from Smokejumpers No Update Update from NR IHC’s Fred Thompson – updated us about Hotshot crew status – issues with weight when flying to Alaska and crews need to meet the weight limits and this issue will be discussed – Hotshots are training to deal with Incidents within Incidents and are willing to be utilized more – Also interested in being involved in the Planning during an incident and utilized in more diverse aspects in managing incidents. Brad McBratney will facilitate getting someone to talk at the HS meeting about managing fires with multiple objectives. Operations Committee Chair Greg will continue as the Operations committee chair and Bob Fry will continue as the vice-chair. NRCG Board meeting Board would like to meet with the ICs at the November 15th and 16th Board meeting. Greg Poncin will represent the T-1 ICs, Stan Benes will for the Type 2 ICs. Next meeting date and location Operations Committee meeting minutes – NRCG October 19th & 20th, 2011 The meeting will be on February 15th & 16th starting at 12pm. The location will be in the new training room at the Central Land Office at DNRC Helena. FOR INFORMATION ON DOCUMENTS CONTACT CHAIRMAN GREG ARCHIE AT garchie@mt.gov. A SPREADSHEET CONTAINING THE ATTENDEES ACCOMPANIES THESE MINUTES. Respectfully submitted, Bob Fry bob.fry@montanadma.org Ops committee vice-chair Operations Committee meeting minutes – NRCG October 19th & 20th, 2011 NORTHERN ROCKIES COORDINATING GROUP OPERATIONS COMMITTEE MEETING DATES: October 19TH & 20TH, 2011 MEETING LOCATION: HELENA, MT ATTENDEES REPRESENTING EMAIL 19-Oct Greg Archie Chair, Central Zone Rep garchie@mt.gov X Alan Osborn Northwest Zone Rep aosborn@fs.fed.us X Greg Poncin NR IC gponcin@mt.gov X Judy Heintz NRCC jheintz@blm.gov X Tom Heintz EMT IC theintz@fs.fed.us X Jess Secrest EMT IC jsecrest@fs.fed.us X Patti Koppenol NRCG Board pkoppenol@fs.fed.us X Bob Fry SCZ Rep/NR WMT IC bob.fry@montanadma.org X Diane Hutton NR WFMT IC dhutton@fs.fed.us X John Monzie DNRC jmonzie@mt.gov X Wally Bennett NR IC wbennett@mt.gov X Bob Gilman NR Fire Ops rgilman@blm.gov X Dave Larsen MT DES dlarsen@mt.gov X Paul Fieldhouse NR Training Center pfieldhouse@fs.fed.us X Rick Kusicko NID IC rkusicko@q.com X Wayne Williams MT DNRC wwilliams@mt.gov X Doug Downs US FWS doug_downs@fws.gov X John Thompson Benes IMT DIC J75thomp@blm.gov X Louis Hartjes SWZ, FWS louis_hartjes@fws.gov X Tim Murphy NRCG Equip Committee timurphy@fs.fed.us X Fred Thompson USFS hotshot rep fredthompson@fs.fed.us X Mark Heppler East side Dispatch/NR dispatch mheppler@blm.gov X Paul Grimstad MT DES pgrimstad@mt.gov X Mike Almas North ID Zone rep malmas@fs.fed.us X Brad McBratney WFIC bmcbratney@fs.fed.us Brett Waters EMT DIC brettwaters1@gmail.com X Pam Okon Business rep pokon@mt.gov X Robert LaPlant NRCC Robert.laplant@blm.gov X Cobey Williamson WMT Zone Dispatch cowilliamson@mt.gov X Operations Committee meeting minutes – NRCG October 19th & 20th, 2011 20-Oct X X X X X X X X X X X X X X X X X X X X X X X X X X