Chabot College - Facilities Committee Update November 11, 2010 Item Building Project / Designer Phase Activity / Issue Punch List Occupancy April 2010 Punch List Occupancy Jan 2010 1 CSSC/700 Community and Student Services Center - tBP 2 IOB/400 Instructional Office Building - LPA 3 Site Athletic Facilities - Verde Design DSA Close Out Awaiting DSA close Out 4 Site Football Field DONE PROJECT CLOSE-OUT COMPLETE 5 1900 Punch List Occupancy Jan 2010 6 Site Planetarium / Lecture Halls - DSK Pool Renovation - Aquatic Design Group DONE PROJECT CLOSE-OUT COMPLETE 7 Site M & O Facility - Gould On Hold On Hold 8 4000 PE Strength Fitness Center Construction Construction complete July 2011 9 800, 900, 1000 Classroom Building - HMC DSA Close Out B800 Occupancy Jan. 2009, B900 is occupied 10 500 Classroom Building - HMC DSA Close Out Occupancy Jan. 2010 11 Site Portable Offices Central Plant / Utility Loop - ESCO DSA Close Out Temporary Faculty Offices Charles Ham DONE 12 13 14 1000, 1400, 1200, 1300 508, 904, 1814, 2205 15 Art Gallery Doors, Industrial Tech Improvements, PAC Interior Improvements Phase 3 underway, Completion Dec. 2008 PROJECT CLOSE-OUT COMPLETE DONE PROJECT CLOSE-OUT COMPLETE Technology Enhanced Classroom Classroom Standards and Office Standards DONE PROJECT CLOSE-OUT COMPLETE DONE PROJECT CLOSE-OUT COMPLETE 16 Site Campus Security Plan - Catalyst Close Out Under Construction, complete Nov. 2008 17 300 Bidding Bid Opening 11-18-2010 18 Site Classroom Building - HMC College Landscape Guidelines RHAA DONE standard is complete 19 Site Asbestos Inspections - HMS On-site Investigation HazMat removal in B300 and B1400/1600 20 2500, 2600, 2700, 2800, 2900 PE Complex - SKW DSA review Budget Problems / Bleachers in Gym completed Aug 2009 21 Site Commissioning Authority - AEC On-going 22 Site District-Wide FF&E Consultant On-going IOB, CSSC and B4000 Dovetail working with each of the building user groups, faciities groups and architects Responsibility / Action On Hold Chabot College - Facilities Committee Update November 11, 2010 23 Site IT Infrastructure Project - ESCO Close Out Scope of work coupled with Central Plant item #11. 24 Site Site Design Committee On Call As Needed 25 100 Building Modernization - Steinberg Schematic Design Chaired by Tim Nelson Feasibility study complete - moderate scope being documented, budget to be determined 26 Site College Marquee - tBP Schematic Design CDs underway, soils boring completed 27 Site Complete Bricks being installed On-going suggestion to align plant materials with curriculum 28 Site Founders Plaza - CSSC/tBP Space / Program Relocation Dovetail 29 2200 Dental Hygiene - HMC Close Out 30 Site Campus Signage - HM PAC Rigging Beam Analysis George Famous Design Development Design under way DONE Analysis Done 32 Site Parking Lots - tBP Close Out 33 1400 / 1600 Renovation - CHA Construction Finished Aug. 2008 Punchlist underway Renovation of B1400 and two rooms in B1600, Construction complete August 2011 34 Site Solar - Chevron Energy DSA Close Out Solar Panels are operational 35 1700/1800 Renovation - Steinberg Working Drawings Construction Funding secured if 14D approval granted by 6-30-10 36 1600 Renovation - TBD FPP revisions FPP was revised Jun 2009. Awaiting state input 37 Site Soccer Field Restoration - Verde Construction Construction finish October 2010/in maintenance period 38 200 1100, 1500, 2000 Light Renovation - Dovetail Schematic Design Programming October 2010 Light Renovation Pre-Design Light Renovation Pre-Design 41 2300 B1200, SOTA Plaza Renovation - bfgc Budget challenges, SOTA Plaza may be an Add Alternate in bidding, Design Development Need Swing Space planning 42 Site Parking Lot F Restoration DONE February/March 2010 43 Site Traffic Signal Construction October 2010 start construction 44 Site Parking Lot G/H Security Schematic Design Design Process started 45 Site Villas Removal Removal complete February 2010 46 3400 Light Renovation DONE Design Team Selection 47 300, 500, 800, 900, 1000, 1100 Exterior Aesthetic Improvements Design Team Selection 31 39 40 48 Occupancy October 2009 - Project Close -Out Get design started to accommodate new BMW Program create budget, determine scope, hire Architect