Turn Over Packages, FAT and Commissioning San Francisco Bay Area Chapter Commuter Conference May 13th 2008 Misha Anissimov, Genentech Mike Britting, Hathaway Dinwiddie Leo Santini, Hathaway Dinwiddie FAT • Why do we need a Factory Acceptance Test? • Who Benefits, who are the stakeholders? • Who should be in charge, who should go? • Is it worth the cost? Basic FAT • • • • Establish what needs to be tested Establish who needs to attend Establish the schedule Establish who will be responsible for reporting and recording Commissioning Basics for the Owner Misha Anissimov, P.E. M.E. 101, Inc. What is Commissioning? • ASHRAE defines it as “A quality-focused process for enhancing the delivery of a project. The process focuses on verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated and maintained to meet the Owner’s Project Requirements. • TRANSLATION: The process of testing and challenging your building systems in such a way as to find all of the problems and mistakes before Building Turnover. Each problem found during Commissioning = One less problem found by the User. ” Establish the Team – (the Cx agent’s support network) • The Owner’s Representative : should have a solid working knowledge of Mechanical Systems design and function, and provide unbiased information to upper management. • Commissioning Agent : Reviews Controls, Writes FPT’s, executes FPT’s • Mechanical Engineer of Record : Own’s the system design and Sequence of Operation. • General Contractor’s MEP Coordinator : Will act as the “enforcer” in helping resolve issues between subcontractors. • Mechanical Contractor Project Manager and Field Start Up Technician • Controls Contractor Project Manager, Design Engineer and FIELD PROGRAMMER. Step 1 : Establish Scope . A detailed Commissioning (Cx) specification is needed to define systems/parameters to be tested, trends to be run, documentation that is required. Spend time achieving clarity in your own mind of exactly what you want to accomplish. . . ” If you are using a generic specification, supplement this with your own building-specific attachment. What are some unique tests you want to include? 72 hour trends of all building zones? A 5-day “quality of life” check? A Cx agent Overview class for Facilities? Unusual systems which may require special attention? 100% vs. 10% point to point? Get Facilities Involved. All facilities engineers have pet peeves. Maybe they hate variable primary chilled water systems. Include specific tests in the scope to specifically address Facilities and User concerns. Step 2: Choosing a Commissioning Agent - As always, word-of-mouth recommendations of Agents are a great starting point. This is 100% Labor….less cost means less Cx activity. - PROPOSALS: Ask for sample Issues logs (what kind of problems did they uncover in past jobs?), Ask for sample Functional Performance Tests-FPT’s (how are the tests written? Do the documents include generous amounts of hard data like pressure/temperatures/flows, or do the tests look too simplified “pass/fail” with no data recorded). Test data acquired in the field is useful later in troubleshooting. - INTERVIEW: Meet the lead Cx Manager who would be assigned to your project. Be sure you are getting an “A” list person, not a “B” list person. Is he or she an effective leader? Do they take charge? Ask them about a system you have had problems with in the past and how they would test it. Step 3: Preparation Preparation Preparation - THIRD PARTY OVERSIGHT: Be sure the contract and channels of communication are established so that the Owner always gets the “real deal” information from the Cx Agent. He is your person in the trenches making sure everything works. - PLANNING: I like to start with dedicated Cx meetings early..right after 95% CD Documents are issued. That means dedicated Commissioning Meetings once a week, starting with a thorough document design review process - 75% of Commissioning Problems are controls related. Start with a detailed Controls Sequence of Operation Review by the Cx Agent, Mechanical Engineer, and FACILITY’S rep. You are building a Cx TEAM. - After SOO , Get the Controls Programmers involved. Ask for Logic Diagrams to understand how the system will be programmed. A Few Words about FPT’s • Actively Review Functional Performance Tests – especially key tests. Focus on the “Objectives” and the “Results” you would like to see. • Beware of Boiler Plate FPT’s. Are the tests custom tailored to your systems? • FPT’s are common sense and are the “battle plan” of Commissioning. Step 4: Execution • The SOO’s have been scrubbed, you know how the Control Systems will be programmed, the Functional performance tests have been created and reviewed by the Owner, you have adequate staffing for all trades-contractors, and you have PGE power to all systems! You are ready to start Cx activities! • Embrace “PROBLEMS”: The more you find now, the better. • Keep FACILITIES Involved: Witnessing tests is great facilities training….and establishes a comfort level before turnover. • Cx is a coordinated team effort – and delays WILL occur. Avoid the temptation to accelerate Cx activities—this will result in errors. Cx agents are not painters/sheetrockers, etc. Start with a REALISTIC schedule and then ADD SOME EXTRA. A Few Words About Scheduling • Substantial Completion – Certificate of Occupancy does not mean the Building is ready for User Move-In. • Ideal Move – In Date should lag 4 – 8 weeks or so behind substantial completion • Cx activity issues TAKE TIME to resolve. Simple Issues are quick. Design Issues can take weeks. • Case Study: A simple Lab Building with a top notch team, with Mechanical Engineering Owner oversight, and a thorough review process is projected to have the Cx Issues resolved 3 – 4 weeks after substantial completion. THIS IS NORMAL. Turn Over Packages • What is the Turn Over Package (TOP)? • Why is the TOP essential for successful Project completion? • What is needed for a TOP? The Owner’s Perspective • Establish the requirements for contractor turnover packages • Assign defined roles & responsibilities and incorporate into the Contract Documents • Establish ongoing TOP meetings • Manage and support the turnover plan/schedule throughout the Project Case Study: Genentech TI Project Leo Santini, MEP Coordinator Hathaway Dinwiddie Summary: The Contractor’s Perspective • • • • • Know your contract and specifications Define and/or clarify all questionable items Formalize the complete organization of the TOP Team members buy-in Provide a means of signing off and tracking documents as the Project progresses • Develop an outline/schedule for key turn over items • Follow through and execution - maintain visibility and communication among all team members Key Items in Turnover Package • • • • • • • • O&M’s delivered to Facilities for SOP’s Seismic calcs, inspection & approval letters Start-up data BAS AT box programming data VFD parameters data Accurate BAS as-builts and control sequences EH&S Binder Sound consultant calculations, and reports Other Turnover Items & Activities • Training & Coordination – Equipment is running. Coordinate days and times with Facilities • Final Punch List – Final punch walks occur weeks before substantial completion. Final punch completion and Owner backcheck completed by substantial completion date. • As Builts – Architectural backgrounds freeze 30 days before substantial completion • Final Building Turnover – Checklist signature and date by Owner Project Engineering, Facilities and Contractor Building Turnover Checklist MEP System Turn Over Checklists TOP Manuals: Table of Contents GENERAL DOCUMENTATION Volume I: SUBMITTALS Volume II: PROJECT SPECIFICATIONS Volume III: SYSTEMS DOCUMENTATION Volume IV: Volume VII: A. B. C. D. E. F. G. Project Directory TOP Matrix As-Builts Record Set CD Master Punchlist Warranty Letters RFI Log w/Responses O & M Manuals A. B. Submittal Log Approved Submittals A. B. C. Specification Listing Record Specifications Record Basis of Design (BOD) DRY-SIDE HVAC Central Air Handling Economizer Return Air Fan General Lab Exhaust "H" Area Exhaust Fans Radioisotope Exhaust Fans Air Terminal Zones IDF/MDF Backup AC Units Mechanical Room, Boiler Room Exhaust Fans Refrigeration Room Ventilation, Refigerant Leak Detection, Purge & EPO Bag In / Bag Out Filtration System LABORATORY SUPPORT EQUIPMENT D.I. Point of Use Polishers Chemical Fume Hoods Radioisotope Hoods Bio Safety Cabinets Volume VIII: "DIRTY" PROCESS UTILITIES Laboratory Vacuum Volume IX: Volume X: Volume XI: "CLEAN" PROCESS UTILITIES RO/DI Water System Carbon Dioxide Laboratory Compressed Dry Air Volume XII: Volume XIII: Volume XIV: Volume XV: Volume XVI: BUILDING UTILITIES Domestic HW/CW Natural Gas Sanitary Waste & Vent Lab Waste & Vent Storm/Roof Drainage Volume XVII: Volume XVIII: Volume XIX: Volume XX: FIRE/LIFE SAFETY SYSTEMS Fire Alarm & HVAC Interface Elevator Recall and Safety Sequences Fire Sprinkler Flammable Vapor Detection (LEL) Volume V: WET-SIDE HVAC Preheat/Reheat - Boilers, Pumps Condenser Water - Towers, Pumps Refrigerated Water - Chillers, Pumps Volume XXII: Volume XXIII: Volume XXIV: Volume XXV: Volume XXVI: ELECTRICAL & SPECIALTY SYSTEMS Normal Power Service & Distribution Emergency/Standby Distribution Grounding Lighting & Lighting Control Generator & ATS UPS, Batteries Security Including CCTV FMS - Facility Management System Volume VI: CONTROLS SYSTEMS BAS - Building Automation System Volume XXVII: ENVIRONMENTAL HEALTH & SAFETY EH&S - Environmental Health & Safety Volume VII: LABORATORY SUPPORT EQUIPMENT D.I. Point of Use Polishers Chemical Fume Hoods Radioisotope Hoods Bio Safety Cabinets Volume XXI: APPENDICES Appendix A: Appendix B: Appendix C: Seismic Bracing Drawings, Calcs and Inspection Sign-off - Mechanical/Plumbing Eqpt & Overhead Balance Report - Air & Water Commissioning Plan and Report CENTRAL AIR HANDLING GENERAL CONTRACTOR MEP SIGN-OFF GNE FACILITIES SIGN-OFF SYSTEM DOCUMENTATION GNE ENGINEERING SIGNOFF TAB SECTION System Docs: TOP Matrix SECTION 3 - EQUIPMENT TESTING/INSTALLATION VERIFICATION SECTION 3a - PIPING A Piping Specifications B Piping Documentation SECTION 1-GENERAL A System Overview i. Equipment List x ii. BOD - Basis of Design x C i. Construction Drawings and/or P&IDs ii. Vendor Furnished Drawings x iii. As-Built Drawings x C Punchlists/Mechanical Completion Letter x D Balance Report x E Startup/Commissioning Test Plan F i. Commissioning Plan x ii. Final Commissioning Report x Warranty G Owner Training Documentation ii. Contractor/Vendor Supplied Equipment Submittals/Drawings x iii. Equipment Prefunction Checklist x iv. HEPA Filter Certification v. Seismic and/or Structural Calculations x vi. Labeling Document x vii. Recommended Spare Parts List i. ii. Field Test Results x iii. Contractor/Vendor Startup Reports x iv. Hood Certifications (GNE) SECTION 3 - EQUIPMENT TESTING/INSTALLATION VERIFICATION SECTION 3a - PIPING A Piping Specifications vii. Pipe Brazing/Soldering Procedure(s) Installation Documentation/Field Verification Pressure Test Report ii. Flushing Report iii. Cleaning and/or Passivation Report iv. Sanitization Plan and Report v. Field QC Reports/Particulate Report x i. Ductwork Submittal x ii. Insulation Submittal x iii. Shop Drawings iv. Seismic Details and Stamped Drawings x v. Specialty Ductwork x Installation Documentation i. Ductwork Leak Tests x ii. Seismic Inspection reports & Sign-off x SECTION 4 - ELECTRICAL A Electrical Specifications B Single Line Diagrams C Electrical Documentation D FAT Test Results Welder Certification Ductwork Specifications x B Test Reports Weld Procedure(s) vi. Ductwork Documentation A System Documentation x Seismic Details and Stamped Drawings v. B C Installation Guide and O&M Manuals Specialty Piping / Plumbing Fixture Submittals iv. A x i. iii. SECTION 3b - DUCTWORK x SECTION 2 - EQUIPMENT Piping Submittal Valving Submittals i. B Drawings x i. ii. i. Electrical Commodities Submittal ii. Seismic Details, Stamped Drawings and Inspection Reports/Sign-off Electrical Equipment Checkout i. Ground System Testing ii. Transformer Testing/Reports a. Tilt-Meter Testing b. Insulation Resistance Test Report iii. Megger Testing a. Switchgear/Switchboards FMS - FACILITY MANAGEMENT SYSTEM x SECURITY, INCLUDING CCTV x UPS, PDU & BATTERIES x x x x x x x x x x x x x x x x GENERATOR & ATS x x EMERGENCY/STANDBY POWER DISTRIBUTION x x GROUNDING SYSTEM x x LIGHTING & LIGHTING CONTROL x x NORMAL POWER SERVICE & DISTRIBUTION x x FIRE SPRINKLER x x x FLAMMABLE VAPOR DETECTION SYSTEMS (LEL, %O2) x x x ELEVATOR RECALL AND SAFETY SEQUENCES DOMESTIC HW / CW x FIRE ALARM SYSTEM AND HVAC INTERFACE x LAB WASTE & VENT x x STORM/ROOF DRAINAGE x x NATURAL GAS x x SANITARY WASTE & VENT x x LABORATORY COMPRESSED AIR x x CARBON DIOXIDE x x RO/DI WATER PURIFICATION x x LABORATORY VACUUM REFRIGERATED WATER CHILLERS, PUMPS, ETC. x x VBSE'S - VENTILATED BALANCE SAFETY ENCLOSURES PREHEAT-REHEAT BOILERS, PUMPS CONDENSER WATER TOWERS, PUMPS x x BIO SAFETY CABINETS BAG IN / BAG OUT FILTRATION SYSTEM x x CHEMICAL FUME HOODS IDF/MDF BACKUP AC UNITS x x RADIOISOPTOPE HOODS AIR TERMINAL ZONES x x D.I. POINT OF USE POLISHERS RADIOISOTOPE EXHAUST FANS x BAS - BUILDING AUTOMATION SYSTEM GENERAL LAB EXHAUST "H" AREA EXHAUST FANS Equipment List Basis of Design (BOD) SYSTEM DOCUMENTATION MECHANICAL ROOM, BOILER ROOM EXHAUST FANS REFR ROOM VENTIL, REFRIGERANT LEAK DETECTION, PURGE, EPO CENTRAL AIR HANDLING ECONOMIZER RETURN AIR FAN i. ii. TAB SECTION TOP VOLUME NO. Master TOP Matrix SECTION 1-GENERAL A System Overview B Drawings x x i. Construction Drawings and/or P&IDs x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x ii. Vendor Furnished Drawings x x x x x x x x x x x x x x x x x x x x x x x iii. As-Built Drawings x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x C Punchlists/Mechanical Completion Letter x x x x x x x x x x x x x D Balance Report x x x x x x x x x x x x x E Startup/Commissioning Test Plan F Warranty x x x x x x x x x x x x x x x x x x x x x x i. Commissioning Plan x x x x x x x x x x x x x x ii. Final Commissioning Report x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x G Owner Training Documentation x x x x x x x x x x x x x x x SECTION 2 - EQUIPMENT A System Documentation i. B Installation Guide and O&M Manuals x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x ii. Contractor/Vendor Supplied Equipment Drawings/Submittals x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x iii. Equipment Installation Checklist (Including Identification) x x x x x x x x x x x x x x x x x x x x x x x x x x x iv. HEPA Filter Certification v. x x Seismic and/or Structural Calculations x x x x x x x x x x x x x vi. Labeling Document x x x x x x x x x x x x x vii. Recommended Spare Parts List x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x Test Reports i. FAT Test Results ii. Field Test Results x x x x x x x x x x x x x x x x x x iii. Contractor Startup Reports x x x x x x x x x x x x x x x x x x iv. Hood Certification x x x x x x x x SECTION 3 - EQUIPMENT TESTING/INSTALLATION VERIFICATION SECTION 3a - PIPING A Piping Specifications B Piping Documentation x x x x x x x x x x x x x i. Piping Submittal and Material Certifications x x x x x x x x x x x x x x x ii. Valving Submittals and Material Certifications x x x x x x x x iii. Specialty Piping / Plumbing Fixture Submittals and Material Certifications x x x x x x x x iv. Seismic Details and Stamped Drawings x x x x x x x x v. Weld Procedure(s) x x x x vi. Welder Certification x x x x Pipe Brazing/Soldering Procedure(s) vii. C x x x x i. Pressure Test Report and Drawings x x x x x x x x x x x x x Installation Documentation/Field Verification ii. Flushing Report and Drawings x x x iii. Cleaning Report and Drawings x x x iv. Sanitization Plan and Report v. Field QC Reports x Ductwork Specifications B Ductwork Documentation x x x x x x x x i. Ductwork Standards x x x x x x x x ii. Insulation Data x x x x x x x x x x x x x SECTION 3b - DUCTWORK A x x x x x x x x x x x x x TOP Manuals: Review Sheet GENENTECH BLDG 46, 47, 48 TOP REVIEW SHEET N AME : D ATE : S YSTEM /S COPE : REVIEW SHEET SECTION COMMENTS RESPONSIBLE CORRECTED Turn Over Schedule ID Task Name Responsible 8 S 1 2 BUILDING 47 TURNOVER SPARE PARTS IDENTIFIED & TURNED OVER 3 Spare Parts Identified by Facilities GNE 4 Pricing Submitted to GNE for Approval GNE 5 Order Spare Parts Therma, REI, H 6 Spare Parts Turned Over to GNE Therma, REI, H 7 FINAL PUNCHLIST (REFER TO PROJECT SCH) 8 Final Punchlist Walkthrough 9 Issue Final Punchlist 10 Make Corrections & Backcheck 11 12 13 14 15 Final Punchlist Complete P&W, GNE P&W, GNE All Subs, HD, P&W, GN P&W, GNE BALANCE REPORT Issue Balance Reports for TOP (Preliminary) Therma Issue Final Balance Reports Therma COMMISSIONING PACKAGE 16 Executed System Protocols Complete AEI 17 Provide Final Commissioning Overview Package AEI 18 AS-BUILTS, BOD, & SPECS RECORD SET 19 Final as-built, BOD & Specs Submitted to P&W 20 Other As-Builts Submitted to HD 21 Siemens Issue BAS as-builts 22 P&W Compile and Issue Record Set for TOP Therma, REI, Siemens Security Siemens FLS BFP, Walker FMS Siemens BAS P&W Mar 24, '08 M W F Mar 31, '08 Apr 7, '08 S T T S M W F Apr 14, '08 Apr S T T S M Turn Over Schedule - Continued ID 23 24 25 Task Name Responsible WARRANTY LETTERS Submit warranty letters ALL SUBS TOP MANUALS 26 Submit Remaining TOP System Installation Docs 27 Submit Start-up & Testing Docs 28 Facilities & Engineering TOP Binder Review 29 Make TOP Revisions 30 TOP Substantially Complete 31 Insert Remaining Docs 32 RO/DI Piping Sanitization Reports 33 D.I. Point-of-use Polisher Docs 34 Final Balance Report 35 Final Commissiong Package & Presentation 36 As-Built Record Set 37 Mar 31, '08 Apr 7, '08 S T T S M W F EH&S Binder & Section 7 EH&S Docs 38 System Training (See Training Schedule) 39 Certificate of Occupancy (Refer to Project Schedule for ac 40 Permit Binder Submitted Therma, REI, Siemens, BF Thyssen Krupp, Walker FMS, HD Therma, REI, Siemens, Walker FM GNE Therma, REI, Siemens, BF Thyssen Krupp, Walker FMS, HD Therma Therma/HD Therma AEI P&W GNE, HD Therma, REI, Siemens, GNE, H HD All Subs, HD Apr 14, '08 Apr 21, '08 S T T S M W F Ap S Q&A