Impact of Rising Construction Costs on the Measure B Bond Program Chabot-Las Positas Community College Measure B Bond Program Chabot-Las Positas Co mmunit y College Distr ict Measure B Bond Program 2 Agenda CLPCCD Measure B Bond Program Program Cost Overview/Status Update • Program Cost Estimate Baseline/Schedule Program Cost Estimate Baseline/Schedule vs. Actual Market Conditions/Impacts • Updated Cost Projection per College - Estimating Basis/Assumptions and Approach • Chabot College Las Positas College Chabot-Las Positas Community College Measure B Bond Program 3 CLPCCD Measure B Bond Program § Purchasing power has been significantly diminished due to market conditions § As a result, the District needs to reassess program scope and budget allocations Chabot-Las Positas Community College Measure B Bond Program 4 Actual + Projected Escalation % Escalation 60% 41% 30% 2% - 4% / YR te a tR e k ar M al e R jection o r P Bond 12% Years 1999 2003 Chabot-Las Positas Community College Measure B Bond Program 2005 2007 5 2009 Program Re-Estimated Cost vs. Timeline $ Millions $775.4 $577.1 Ac tua lE sc ala tio n Total Dollars P ed t c e roj ion t a l a Esc $497.6 03/04 11/05 04/07 09/09 (Rev. MDPT) Reflects Program duration from 03/04 through 2012 Chabot-Las Positas Community College Measure B Bond Program 6 09/11 09/13 Bond Base Value Based on 9/01/03 cost basis • Based upon a seven year Program duration • Assumes a 3% Annual Escalation Factor to mid-March ‘07 • Original Bond ’07 Dollars (March ‘07) Chabot College Projects $240,548,271¹ Las Positas College Projects $208,236,275² $48,864,873³ District Wide Projects $497,649,419 Total As of 04/20/05 (Reassignment of two IT related projects to District-Wide Category) ¹ Remove Project 552550, Classroom/Labs/College Services (CC) ² Remove Project 553840, Computers & Equipment for Classrooms & Labs (LPC) ³ Add Projects 551011 and 551012 to Total Chabot-Las Positas Community College Measure B Bond Program $12,616,616 $ 9,088,371 $21,704,987 7 Components of Capital Costs Land • Hard Costs • Soft Costs • Contingencies • Escalation Factors • Chabot-Las Positas Community College Measure B Bond Program Land Costs • Surveys • Demolition • Sitework Brick and Mortar • Furniture, Fixtures & Equipment A/E • PM/CM/Testing & Inspection, etc. Design • Construction (C.O., unforeseen conditions) Actual • Projected to mid-point of construction 8 Re-Estimating Basis/Assumptions and Approach § The original Bond budget (September 2003) was analyzed to compare the original assumptions on escalation and assumed mid- point of construction with the current data on escalation and projected mid-points of construction (based on the development of a master schedule). § The building costs of elements in each building were reviewed and updated for current market conditions. Chabot-Las Positas Community College Measure B Bond Program 9 Re-Estimating Basis/Assumptions and Approach § The various markups for Overhead and Profit and bid and project contingencies, were revisited as appropriate. § Where hard data was available on projects already committed and bid, these figures were incorporated into a matrix. § The assumed escalation rates are based on a reasonable assessment of projected market conditions. Chabot-Las Positas Community College Measure B Bond Program 10 Re-Estimating Basis/Assumptions and Approach Objective: To update the projected Construction/Project costs to reflect the current market conditions and anticipated escalation moving forward. Escalation: Actual Escalation § Actual escalation to November 29, 2005 was built into the current construction costs and escalation rates for future time periods to mid points of construction were isolated by project to arrive at a total projected construction cost Future Projected Escalation § § § Escalation to the mid-point of construction has been included with each building or sitework package. December 2005-06 California increases in construction 7% Future years – California increases in construction 5% per annum Chabot-Las Positas Community College Measure B Bond Program 11 Program Manager’s Estimate November 2005 • Based upon a nine year Program • Used Escalation Factor 7% First Year, 5% Thereafter from December 2005 • Value Chabot College Projects $427,500,000 Las Positas College Projects $299,000,000 District Wide Projects $48,900,000 Total Measure B Funds <$498,000,000> Loss of Purchasing Power Chabot-Las Positas Community College Measure B Bond Program $775,400,000 $277,400,000 12 Cost Escalation Resulting from Market Conditions § Expansion of construction activity (Public and Private) in Bay Area and Northern California § Competition from other Bond Programs and Public Works Projects § § § § § College of San Mateo Contra Costa College Diablo Valley College Los Medanos College San Ramon Valley Center § § § § § San Joaquin Delta College Evergreen Valley College Foothill-De Anza CCD West Valley-Mission CCD Dublin Unified School District § Demand for construction materials for: § § § § Rebuilding for Hurricanes Iraq War and Rebuilding Efforts Afghanistan Rebuilding Efforts Global expansion in China, Asia, India and Eastern Europe Chabot-Las Positas Community College Measure B Bond Program 13 Cost Escalation Resulting from Market Conditions Materials § § § § § § § Steel and steel component products Aluminum and aluminum component products All wood products: Timber/Boards/Composites/By-products Concrete Gypsum Products Petroleum Based Products: Asphalt/Paints/Sealants PVC Pipe and Conduit Labor Costs § § § § Workforce availability Hurricane reconstruction Local and national infrastructure replacements Engineering and construction workforce retirements Chabot-Las Positas Community College Measure B Bond Program 14 San Francisco Building Cost Index* 4800 +6.3 4700 4600 +9.9 4500 4400 4300 4200 +1.7 +0.5 4100 +3.7 -0.5 4000 +3.1 3900 -0.7 +4.8 3800 3700 +2.0 3600 +1.2 3500 12/95 12/96 12/97 12/98 12/99 12/00 12/01 12/02 12/03 12/04 11/05 *ENR Index tracks skilled labor of bricklayers, carpenters and structural ironworkers for twenty (20) cities; including San Francisco. Also included in the index: supply cost (non-installed) of structural steel, Portland cement and lumber. Chabot-Las Positas Community College Measure B Bond Program 15 Unit Rate Comparison (’99 – ’03) Unit rates are installed costs including subcontractors overhead and profit Item Concrete in place Rebar Steel Deck Steel Stair Ext Door Drywall Suspended Drywall Steel Ductwork Ceramic wall tile Paint to walls Watercloset Overhead and Profit 1999 Mid '03 Difference % Average Annual Increase 120/CY .60/lb 2.00/sf 7,000/flt 1,000/ea 5.40/sf 6.00/sf 5.70/lb 10.00/sf 0.60/sf 900/ea 10% $135/cy 0.65/lb $2.00/sf $8,000/flt $1,200/ea $9.50/sF $8.00/sf $6.15/lb $11.0/sf $0.75/sf $950/ea 12% $15/cy $0.05/lb $1.5/sf $1,000/flt $200/ea $4.1/sf $2.00/sf $0.45/lb $1.0/sf 0.15/sf 50/ea 5% 13% 8% 0% 14% 20% 76% 33% 8% 10% 25% 6% 20% 3% 2% 0% 4% 5% 19% 8% 2% 3% 6% 1% 5% Sources of data: Analysis of bids/estimates received from contractors Reconciliation of estimates with contractors Quotes received from suppliers/vendors Chabot-Las Positas Community College Measure B Bond Program 16 Unit Rate Comparison (’03 – ’05) Unit rates are installed costs including subcontractors overhead and profit Item Mid '03 Nov '05 Concrete in place Rebar Steel Deck Steel Stair Ext Door Drywall Suspended Drywall Steel Ductwork Ceramic wall tile Paint to walls Watercloset Overhead and Profit $135/CY 0.65/lb $2.00/sf $8,000/flt $1,200/ea $9.50/sf $8.00/sf $6.15/lb $11.0/sf $0.75/sf $950/ea 12% $200/cy 0.90/lb $3.50/sf $15,000/flt $1,500/ea $12.0/sf $13.00/sf $8.50/lb $13/sf $.85/sf $1300/ea 17% Difference $65/cy $0.25/lb $1.50/sf $7,000/flt $300/ea $2.50/sf $5.00/sf $2.35/lb $2.00/sf $0.10/sf 350/ea 5% Sources of data: Analysis of bids/estim ates received from contractors Reconciliation of estim ates w ith contractors Quotes received from suppliers/vendors Chabot-Las Positas Community College Measure B Bond Program 17 % 48% 38% 75% 88% 25% 26% 63% 38% 18% 13% 37% 42% Average Annual Increase 24% 19% 38% 44% 13% 13% 31% 19% 9% 7% 18% 21% Escalation Impacts § State Chancellor’s Office proposes to Department of Finance (DOF) a +30% adjustment in the building guidelines effective with 2006/2007 FPPs. § DSA Advised 11/18/05: § Project size x <$5,000,000 (smaller/less complex) Review time: 3-5 months § Project size x > $10,000,000 (larger projects) Review time: 6+ months § Award of Bid No. 05-05 Construction of the MultiDisciplinary Education Building, Las Positas College: § “Considering the unfavorable bid climate and building price increases in the construction industry, the bids were very competitive…many other Districts are receiving bids that exceed their costs estimates by 25% - 30%”. Chabot-Las Positas Community College Measure B Bond Program 18 Problem Statement “As a result of an unprecedented increase in construction costs, the voter approved $497M program is now estimated to cost $775M”. Chabot-Las Positas Community College Measure B Bond Program 19 Strategies § Develop more detailed Program definition § Confirm scope and facility requirements based upon the College Educational Master Plans § Accelerate the construction of new facilities to a five year timeline and schedule § Define Project Re-Prioritization § Project Delivery: Combine Projects into Procurement Packages/”Economies of Scale” § Procure Bulk Purchases of Equipment and Materials § Reassess level of LEED Certification Chabot-Las Positas Community College Measure B Bond Program 20 Strategies § Conduct Continuous Program Reassessment to Match Local Market Conditions § Include Bid Alternate Opportunities § Manage realistic expectations of facilities/projects that can be implemented § Develop Project Scope and Budgeting based on State Chancellor’s Office and Title V Community College Space and Capacity Standards Chabot-Las Positas Community College Measure B Bond Program 21 Example of 5-Year Accelerated Schedule Cash Flow Requirements $600,000,000 $600,000,000 $500,000,000 $500,000,000 6 Months $400,000,000 $400,000,000 11 Months 3rd $100 Million 2nd $100 Million $300,000,000 $300,000,000 14 Months $200,000,000 $200,000,000 To Complete 1st $100 Million $100,000,000 $100,000,000 $84,000,000 Est. District Yearly Budget Chabot-Las Positas Community College Measure B Bond Program 22 JU L O CT JU L O CT JA N AP R JU L O CT JA N AP R JU L O CT JA N AP R N R AP JA CT O JU L AP R JU L O CT JA N AP R 20 0 5 20 05 20 05 20 06 20 06 20 06 20 06 20 07 20 07 20 07 20 07 20 08 20 08 20 08 20 08 20 09 20 09 20 09 20 09 20 10 20 10 20 10 20 10 $0 Conclusions By implementing the proposed strategies, the District can: § Maximize number of projects with available funding § Minimize future loss of purchasing power § Manage Stakeholder expectations § Complete projects faster § Reduce Program Management level costs Chabot-Las Positas Community College Measure B Bond Program 23 Articles § “Construction Costs Skyrocket, Forcing Districts to Cutback on Prop. 39 Campus Projects”, The News, Summer 2005, Community College League of California § Fact Finding Report – Executive Summary, Swinerton Management & Consulting , January 9, 2006 § “Resolution of lawsuit allows community college upgrades”, San Jose Mercury News, December 13, 2005 § CLPCCD Award of Bid No. 05-05 Construction of the Multi-Disciplinary Education Building, Las Positas college, June 21, 2005 § “Construction at Colleges Corralled by Costs.” Los Angeles Times, August 23, 2005 § CLPCCD Facilities Planning & Management Monthly Report – Measure B Projects – November 2005 § “Focus on Escalating Costs and Market Conditions” “Is there anything we can do?” Construction Management Association of America (CMAA) News; Winter 2005; Southern California Chapter § “Worrying about Labor Shortages” ENR Sourcebook – November 14, 2005 § The Colleges of Contra Costa County, Board Report, October 26, 2005 Chabot-Las Positas Community College Measure B Bond Program 24 Budget Analysis Chabot-Las Positas Community College Measure B Bond Program 25 Budget Analysis Chabot-Las Positas Community College Measure B Bond Program 26 Year 2 / Jan – Mar ’07 Chabot-Las Positas Community College Measure B Bond Program 27 Year 2 / April – June ’07 Chabot-Las Positas Community College Measure B Bond Program 28 Year 2 / July – Sept ’07 Chabot-Las Positas Community College Measure B Bond Program 29 Year 2 / Oct – Dec ’07 Chabot-Las Positas Community College Measure B Bond Program 30 Year 3 / Jan – Mar ’08 Chabot-Las Positas Community College Measure B Bond Program 31 Year 3 / April – June ’08 Chabot-Las Positas Community College Measure B Bond Program 32 Year 3 / July – Sept ’08 Chabot-Las Positas Community College Measure B Bond Program 33 Year 3 / Oct – Dec ’08 Chabot-Las Positas Community College Measure B Bond Program 34 Year 4 / Jan – Mar ’09 Chabot-Las Positas Community College Measure B Bond Program 35 Year 4 / April – June ’09 Chabot-Las Positas Community College Measure B Bond Program 36 Year 4 / July – Sept ’09 Chabot-Las Positas Community College Measure B Bond Program 37 Year 4 / Oct – Dec ’09 Chabot-Las Positas Community College Measure B Bond Program 38 Year 5 / Jan – Mar ’10 Chabot-Las Positas Community College Measure B Bond Program 39 Year 5 / April – June ’10 Chabot-Las Positas Community College Measure B Bond Program 40 Year 5 / July – Sept ’10 Chabot-Las Positas Community College Measure B Bond Program 41 Year 5 / Oct – Dec ’10 Chabot-Las Positas Community College Measure B Bond Program 42 Year 6 / Jan – Mar ’11 Chabot-Las Positas Community College Measure B Bond Program 43