R&D programme Research brief Performance and installation criteria for sanding systems T797 Background The installation of sanding systems onto multiple units is covered by Railway Group Standard GM/RT2461 - Sanding Equipment Fitted to Multiple Units and On-Track Machines, issue 1. Since this standard was produced, the industry has gained significant operational knowledge through service experience. From this there have been a number of developments in the performance and operation of sanding systems. This research project examined the relevance of the existing sanding requirements. It undertook testing and research to propose and support future changes to these requirements. Aims The aims of this research were: • To understand the rationale for selecting the existing GB interface criteria set out in GM/RT2461 Issue 1. • To establish the equivalent interface criteria for sanding systems in other European networks. • To determine whether evidence already exists to support changing the GB sander interface criteria. • To understand the dynamic performance of the sand delivery systems and to determine the optimum design parameters • To determine the benefits of withdrawing the current GM/RT2461 requirement restricting the installation of the first active sander after the leading bogie on multiple units of 2 or more vehicles. R&D programme: Research brief T797 - November 2015 1 • To identify the benefits of utilising distributed active sanding systems along different arrangements of multiple unit formations and the most appropriate distribution of sanders for the typical arrangements of GB multiple units from single vehicles up to formations with 6 vehicles. • To consider how to specify the interface criteria for the deposited sand between the wheel and the rail at the point of delivery and also the appropriate measures to ensure end of train detection. Method This project was delivered in 3 phases. Phase 1 reviewed legacy sanding work and international requirements to understand the rationale for selecting the existing GB interface requirements. Phase 2 conducted laboratory based tests to understand the dynamic performance of sander delivery systems and to determine the optimum alignment relative to the wheel/rail interface. Phase 3 outlined recommendations to achieve distributed sanding systems along different arrangements of multiple unit formations, including recommendations for standards change. The laboratory based tests investigated the effect that different setup parameters of a sanding system has on performance. The wheel rail test rig at the University of Sheffield was used. The rig was modified to install a sanding system representative of that typically installed on GB multiple units. The scope of the tests was delivered in two stages: Stage 1 - Preliminary and investigative tests Stage 2 - Dynamic tests to determine the optimum alignment of sanding nozzles relative to the wheel/rail interface The aim of Stage 1 was to observe and assess the dynamic performance of the three set-ups identified in the research project T796 Understanding the current use of sanders on multiple units, to determine which appeared to be most effective at getting sand into the wheel/rail interface. The most 2 R&D programme: Research brief T797 - November 2015 effective setup and the impact of changing other setup parameters were then investigated in more detail by modifying variables such as: • Height of hose or nozzle above rail • Distance of hose or nozzle from wheel • Angle of hose or nozzle to rail The aim of Stage 2 was to undertake a series of dynamic tests using the optimum setup conditions determined in Stage 1 to investigate the effect of the changes on adhesion and track circuit operation. Findings Phase 1 The research found that the existing criteria were based on a specific set of tests performed on two and three car diesel multiple units and that most other countries do not have defined criteria for the installation and operation of sanding systems. The research also identified recent studies and testing activities which could support changes to the Railway Group Standard once results have been validated. Phase 2 The laboratory based tests identified a number of specific conclusions in relation to the performance of sanders: • Fitting a plain nozzle to the end of a wide bore hose focuses the sand more effectively towards the wheel/rail interface and increases the amount of sand passing through this interface. • A 25% reduction in sand flow rate from 2kg/min to 1.5kg/min when passing sand through a 25mm bore hose results in a disproportionate reduction in the amount of sand passing through the wheel/rail interface. • The most effective set-ups were those where the sand hose or plain nozzle was set at a shallow angle to the rail (10° to 15°) and aimed just in front of the wheel and rail contact. As the angle to the rail increases the amount of sand passing through the nip decreases. • The addition of a plain nozzle compared to a plain hose allows the sand flow rate to be reduced whilst still achieving the same amount of sand passing through the wheel/rail interface as the plain hose. R&D programme: Research brief T797 - November 2015 3 • For a given set of test conditions, use of a nozzle with a horizontal or vertical chamfer does not affect performance compared to a plain nozzle. • For a given hose length, the use of a narrow bore 19mm hose requires a significantly higher air pressure to achieve the same flow rate as a 25mm bore hose of the same length. However, the narrower bore hose appears to achieve a better performance in terms of the amount of sand passing through the wheel/rail interface. • As the longitudinal distance and height of the sand hose from the wheel/rail interface increases the performance of the sander reduces. • Performance of the sander is affected by the lateral offset and twist of the sand hose or nozzle and the optimum performance is achieved when the sander is longitudinally aligned with the centre of the wheel. In terms of insulation and dispersion, for clean dry rail and the specific low speed test conditions, the laboratory based tests demonstrated that when sand is laid at a rate of: • 7.5g/m, normal wheel/rail contact is restored following the passage of 1 wheelset. • 9.5g/m, normal wheel/rail contact is restored following the passage of 3 wheelsets. • 11.5g/m, normal wheel/rail contact is restored following the passage of 7 wheelsets. • 13.5g/m, normal wheel/rail contact not restored even after the passage of 10 wheelsets. Track testing would be required to validate these laboratory based findings. In terms of adhesion improvement, the results show that: • When sand is laid at a rate equivalent to 5.5g/m, the adhesion level increases but it is inconsistent. • When sand is laid at a rate equivalent to 7.5g/m or higher, the adhesion level in the sanded area increases to approximately that of clean dry rail, 4 R&D programme: Research brief T797 - November 2015 but rates higher than 7.5 g/m do not offer any further improvement in adhesion. Phase 3 This phase found that: • Because of the small potential improvement in adhesion performance, there are no real benefits from withdrawing the current GM/RT2461 requirement restricting the installation of the first active sander after the leading bogie on multiple units of 2 with 8 wheelsets or more. This also allows the leading wheelset to be used to detect low adhesion conditions to trigger sanders. • There are benefits of increased performance in low adhesion by using distributed active sanding systems along different arrangements of multiple unit formations. Potential arrangements for distributed sanders have been proposed for typical arrangements of GB multiple unit formations from single vehicles up to sets with 6 vehicles. Adhesion Research Group (ARG), a subgroup of the Vehicle/Track System Interface Committee, has considered 11 recommendations from the research. How they are likely to be progressed is identified in the brackets in the list below. • R1: Investigate the performance of a single sander that varies its delivery rate with speed compared to a single fixed rate sander and also the benefit of 2 distributed fixed rate sanders. (Track testing) • R2: For existing sander installations, try and quantify the amount of sand lost when sanding at speed (the amount of sand deployed that does not pass through the wheel rail interface) to determine how to make the systems more efficient. (Track testing) • R3: Optimise sanders on existing vehicles by implementing the actions identified in a briefing note issued to industry in August 2013 Recommendations for simple checks and improvements to multiple unit sander systems. (Briefing note) • R4: Undertake track testing to verify the findings of the laboratory tests. (Track testing) • R5: Future revisions to the Railway Group Standard should allow the use of distributed sanding systems. (Standards) R&D programme: Research brief T797 - November 2015 5 • R6: Maintain the leading wheelsets free from sand to ensure front of train detection whenever possible. (Standards) • R7: If sand is applied ahead of the leading wheelset, in order to maintain detection of the leading wheelset, the sanding delivery should be limited to 2.25g/m. Vehicle detection using the passage of following wheelset permits higher sand delivery rates. (Standards) • R8: Track testing is required to determine the upper limit of sand density (in terms of g/m) that leads to a wheelset becoming isolated from the rail. Tests can then be undertaken to determine how many wheelsets are required to disperse sand laid at this rate before sand can be re-applied (Track testing) • R10: Further testing should be conducted as this is required to determine if sanding with the leading car sanders on two coupled two car units during a service brake application presents a risk to train detection. (Track testing) • R11: Future revisions to the Railway Group Standard should allow the additional use of dedicated traction sanders (where fitted) on single multiple units when an emergency brake is demanded and low adhesion is detected. The potential loss of train detection in these circumstances will need to be reported to and managed by the signaller. (Standards) Deliverables The outcome of this research is fully described in three detailed research reports along with a summary report that bring together all the results. Additionally a briefing note that outlines recommendations for simple checks and improvements to multiple unit sander systems has been prepared and was issued to train operators in advance of autumn 2013 preparation. These reports are available via www.SPARKrail.org. 6 R&D programme: Research brief T797 - November 2015 Next Steps The outcome of the research was reviewed and accepted by the ARG and the research was presented to industry during a cross industry RSSB conference in May 2013. The output of this research has contributed to a test specification to enable track testing to be carried out to determine the performance of the sanding equipment under normal and emergency operation, and the possible trade-off from increased risk from loss of train detection. It is expected that this validation work will provide the necessary evidence needed to support proposals for standards change. Notwithstanding this ARG has put forward proposals for standards change to allow the additional use of dedicated traction sanders (where fitted) on single and coupled multiple units when an emergency brake is demanded and low adhesion is detected. Recommendations relating to maintenance and optimising current sanders are now being implemented by industry. Contact For more information please contact: Operations Professional Lead Research and Development Programme RSSB enquirydesk@rssb.co.uk Floor 4, The Helicon 1 South Place London EC2M 2RB R&D programme: Research brief T797 - November 2015 7