Project Name
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
White Mountain National Forest, Forestwide (excluding Projects occurring in more than one Forest)
AMC Backcountry Facility
Permit Renewal
- Special use management
Developing Proposal
Est. Scoping Start 07/2014
Expected:08/2014
Project Contact
09/2014
CE
Sarah LaPlante
603-536-6237
slaplante@fs.fed.us
Description: Re-issue permits for the existing backcountry facilities (shelters and tentsites) currently operated by the
Appalachian Mountain Club. No additional use or increases in capacity are proposed as part of this project.
Location:
Administrative Radio Repeater
Improvement Project
UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Coos, Grafton. LEGAL
- Not Applicable. Backcountry facilities operated by AMC.
- Facility management
EA
In Progress:
Notice of Initiation 02/03/2014
Est. Comment Period Public
Notice 08/2014
Expected:12/2014
05/2015
Erica Roberts
603-536-6230
ericajroberts@fs.fed.us
Description: Install 3 new radio repeaters and relocate and enhance 1 existing repeater to increase FS radio coverage on the
WMNF where good coverage is lacking and allow for Forestwide communication; includes clearing trees for
helicopter use and new sites.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43438
Location:
Northern Pass Transmission
Line Special Use Permit
UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Carroll, Coos, Grafton.
LEGAL - Not Applicable. Carr Mountain, Mount Cabot, Mount Carrigain, and Wildcat Mountain. Will remove Milan
repeater.
- Special use management
EIS
In Progress:
NOI in Federal Register
02/11/2011
Est. DEIS NOA in Federal
Register 12/2014
Expected:11/2015
12/2015
Tiffany Benna
603-536-6241
tbenna@fs.fed.us
Description: Proposed power transmission line that would cross the WMNF in an existing corridor in Stark, Easton, Lincoln,
Woodstock. US Dep't of Energy is leading the NEPA analysis. WMNF decision is whether to issue a special use
permit to cross the Forest.
Web Link: http://www.northernpasseis.us/
Location:
07/01/2014 03:46 am MT
UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. For more information, see the project website at: www.northernpasseis.us.
Page
1 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Albany South Project
EA
Project Purpose
Decision
Expected
Implementation
Project Contact
R9 - Eastern Region
Androscoggin Ranger District (excluding Projects occurring in more than one District)
Patricia Nasta
- Recreation management
In Progress:
Expected:06/2015
10/2015
207-824-2813
- Wildlife, Fish, Rare plants
Notice of Initiation 07/15/2013
pnasta@fs.fed.us
- Forest products
Est. Comment Period Public
- Watershed management
Notice 10/2014
- Road management
Description: An integrated resource management project that proposes vegetation management to improve wildlife habitat and
forest health conditions, as well as recreation, watershed and transportation system improvements.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=39614
Location:
Androscoggin Ranger District
Education and Wellness Trail
Planning Status
UNIT - Androscoggin Ranger District. STATE - Maine. COUNTY - Oxford. LEGAL - Not Applicable. Town of
Stoneham, Oxford County, ME.
- Recreation management
In Progress:
Scoping Start 03/28/2014
Expected:09/2014
09/2014
CE
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Construct a loop hiking trail of ~1 mile from the Androscoggin Ranger Station, on the Fifth Hole Trail to beaver
ponds, then parallel to the river back to the office. For employees and visitors, and for conservation education
programs.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41627
Location:
Central Maine Power Co.
Special Use Permit
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Androscoggin Ranger Station, Gorham, NH.
- Special use management
In Progress:
Scoping Start 03/31/2014
CE
Expected:07/2014
07/2014
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Issue a new special use permit to CMP for a period of 30 years. CMP proposes to install utility poles and overhead
electrical lines along 1,400 feet of FR 3314 to a private inholding and residence.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42969
Location:
07/01/2014 03:46 am MT
UNIT - Androscoggin Ranger District. STATE - Maine. COUNTY - Oxford. LEGAL - Not Applicable. Forest
Road 3314, Mason Township, Oxford County, Maine.
Page
2 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Central Maine Power Company
Co. Special Use Permit
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Androscoggin Ranger District (excluding Projects occurring in more than one District)
- Special use management
Cancelled
N/A
Project Contact
N/A
CE
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Installation of overhead electrical lines along 1,400 feet of Forest Road 3314 to a private residence and inholding.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44061
Location:
Glen Ellis Falls Day Use Area
Site Improvement Project
EA
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Forest Road 3314, Mason Township, Oxford County, Maine.
Jacob Lubera
- Recreation management
In Progress:
Expected:07/2014
05/2015
603-466-2713 x 224
- Heritage resource
215 Comment Period Legal
jlubera@fs.fed.us
management
Notice 10/20/2011
- Watershed management
- Facility management
Description: This project proposes to repair many of the facilities--including the access road, parking, picnic sites, trails,
signage and toilets--at this popular day use area.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33106
Location:
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Glen Ellis Falls Day Use Area.
Thomas Moore
Harvard Cabin Renovations and - Special use management
In Progress:
Expected:09/2014
09/2014
System Upgrades
603-466-2713 x226
- Facility management
Scoping Start 04/01/2014
tmmoore@fs.fed.us
CE
Description: Allow Harvard Mountaineer Club to replace two rotting logs in the cabin, install new windows and wood stove, and
install a 30' tall tower to increase radio coverage and hold new solar panels, which will allow them to replace
propane lanterns.
Location:
Maple Syrup Tree Tapping
Permit
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. Harvard Cabin.
- Special use management
On Hold
EA
N/A
N/A
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: 5-year special use permit to place several hundred taps in sugar maple trees on 75 acres and use of existing old
skid roads for tapping effort.
Location:
07/01/2014 03:46 am MT
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. Town of Randolph.
Page
3 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
Project Contact
R9 - Eastern Region
Androscoggin Ranger District (excluding Projects occurring in more than one District)
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Northern New Hampshire Bird
Dog Club Special Use Permit
Renewal
- Special use management
CE
Description: Renew the existing 5 year permit. The permit authorizes use of several informal walking trails, pre-approved
brushing, and the authorization to hold competitive grouse and woodcock timed hunting events in September and
October of each year.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42971
Location:
Parker Sugar Bush Special Use
Permit Renewal
In Progress:
Scoping Start 03/31/2014
Expected:08/2014
08/2014
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Kilkenny tract, informal trails along the Bog Dam Loop Road (FR 15), City of Berlin, Coos COunty, New
Hampshire.
- Special use management
In Progress:
Scoping Start 04/09/2014
Expected:07/2014
07/2014
CE
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Renew the expired 5 year special use permit that authorizes maple syrup tapping on 238 acres of NFS land. The
permit expired in June, 2013.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42972
Location:
Pond of Safety Accessible Trail
& Shoreline Access Hardening
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Town of Randolph, Coos County, New Hampshire: 238 acres of NFS land in Compartment 31, stands 4, 45, and
46.
- Recreation management
In Progress:
Scoping Start 03/28/2014
CE
Expected:07/2014
07/2014
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Replace user created trail from designated parking lot to canoe launch with accessible trail along an existing road
prism and harden shore using riprap to limit erosion. May include a small (3' square) landing to allow easier canoe
access.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40387
Location:
07/01/2014 03:46 am MT
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Pond of Safety, Randolph, NH.
Page
4 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
South Pond Road Association
Special Use Permit Renewal
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Androscoggin Ranger District (excluding Projects occurring in more than one District)
- Special use management
In Progress:
Scoping Start 03/31/2014
Expected:08/2014
Project Contact
08/2014
CE
Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: The purpose of This project is to renew the existing permit for a 5 year period. The permit authorizes the road
association use of Forest Roads 65, 65A and 65B to perform annual routine maintenance and snow plowing for
safe public access.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42967
Location:
Wild River Valley Trail Repairs
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
Forest Roads 65, 65A and 65B; Town of Stark, NH.
- Recreation management
CE
In Progress:
Scoping Start 03/06/2014
Expected:07/2014
07/2014
Travis Pellerin
603-466-2713
tpellerin@fs.fed.us
Description: Repair the Moriah Brook Trail footbridge crossing the Wild River and relocate six small sections (totaling
approximately 0.5 miles) of the Highwater Trail adjacent to the Wild River from damage that occurred during
Tropical Storms Irene and Sandy.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43261
Location:
White Mountain National Forest
Bog Pond Snowmobile Trail
Relocation
UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable.
The proposed project includes portions of trails located in the Wild River Valley on the north side of Evans Notch.
None of the proposals are in the Wild River Wilderness.
R9 - Eastern Region
Pemigewasset Ranger District (excluding Projects occurring in more than one District)
- Recreation management
- Watershed management
In Progress:
Scoping Start 04/02/2014
CE
Expected:07/2014
08/2014
Jennifer Burnett
603-536-6107
jburnett@fs.fed.us
Description: Reconstruct approximately 0.25 miles of the Bog Pond Snowmobile Trail so that its crossing of Harvard Brook is
relocated to a more sustainable location that better protects soil and water resources.
Location:
07/01/2014 03:46 am MT
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Bog Pond Trail in Lincoln, NH.
Page
5 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Bowen Brook Integrated
Resource Management
EA
Project Purpose
EA
Decision
Expected
Implementation
Project Contact
R9 - Eastern Region
Pemigewasset Ranger District (excluding Projects occurring in more than one District)
Desiree Johnston
- Recreation management
Developing Proposal
Expected:08/2015
01/2016
603-447-5448 x128
- Wildlife, Fish, Rare plants
Est. Notice of Initiation 07/2014
dajohnston@fs.fed.us
- Forest products
- Vegetation management
(other than forest products)
- Watershed management
- Road management
Description: An integrated resource project designed to move the Wild Ammonoosuc North Habitat Mgt Unit (HMU) toward
desired conditions through timber, wildlife habitat, recreation, fisheries and aquatic management, road
improvements and decommissioning.
Location:
Loon Mountain South Peak
Learning Center
Planning Status
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Towns of Bath, Easton and Landaff, Grafton County, NH.
- Land management planning
- Recreation management
- Special use management
In Progress:
Comment Period Public Notice
04/28/2014
Est. Objection Period Legal
Notice 07/2014
Expected:08/2014
09/2014
Joseph Gill
603-466-2713 x221
jgill@fs.fed.us
Description: Allow construction of two fixed-grip chairlifts, approx. 26 acres of new or realigned teaching ski terrain and
expansion of snowmaking to new area with existing water. Approx. 60% of lifts and ski terrain on NFS lands. Add'l
work on private lands
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37025
Location:
Loon Pond Dam Repair
CE
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Lincoln, NH.
Loon Mountain Ski Area.
- Watershed management
- Special use management
Developing Proposal
Est. Scoping Start 09/2014
Expected:12/2014
05/2015
Jon Morrissey
603-536-6101
jmorrissey@fs.fed.us
Description: The Town of Lincoln has proposed repair work for the Loon Pond Dam in order to comply with federal reqirements
for the town water supply. The town has a right to use and maintain the dam for purposes specified in their deed.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43389
Location:
07/01/2014 03:46 am MT
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. The dam to be maintained is on Loon Pond west of Loon Mountain Ski Area in the town of Lincoln, NH.
Page
6 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Mt Tecumseh Communication
Site Special Use Permit
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Pemigewasset Ranger District (excluding Projects occurring in more than one District)
- Special use management
Developing Proposal
Est. Scoping Start 07/2014
Expected:12/2014
12/2014
CE
*NEW LISTING*
Project Contact
Justin Preisendorfer
603-536-6105
jpreisendorfer@fs.fed.u
s
Description: Re-issue a 30-year permit/lease for the Mt. Tecumseh Communication Site to replace the existing permit, which
expires in 12/2014, with no changes proposed to the existing communication site or operations of the site.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44752
Location:
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Mt. Tecumseh.
Tom Giles
603-536-6102
tjgiles@fs.fed.us
Rumney Rocks Management
Project Supplemental Analysis
and Decision
- Recreation management
EA
Description: Update Environmental Assessment to include rock removal for trail construction by either mechanical means or
controlled blasting. Other trail work was covered in 2009 decision. Also adds a permanent toilet adjacent to the
Main Cliff parking area.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38661
Location:
Time Warner Cable Fiber Optic
Cable Permit Issuance
In Progress:
Objection Period Legal Notice
05/15/2014
Expected:06/2014
06/2014
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Rumney Rocks Climbing Area, Buffalo Road, Rumney, NH.
- Special use management
Completed
CE
Actual: 05/02/2014
05/2014
Justin Preisendorfer
603-536-6105
jpreisendorfer@fs.fed.u
s
Description: Issue a 30-year permit to Time Warner Cable for existing fiber optic cable formerly under special use permit in the
Town of Waterville Valley, NH
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41006
Location:
07/01/2014 03:46 am MT
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. In the Town of Waterville Valley, NH extending from West Branch Road to the ski area and up to
Schwendi Hut.
Page
7 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Time Warner Cable Fiber Optic
Cable Special Use permit
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Pemigewasset Ranger District (excluding Projects occurring in more than one District)
- Special use management
Developing Proposal
Est. Scoping Start 07/2014
Expected:08/2014
08/2014
CE
*NEW LISTING*
Thomas Paquette
802-767-4261 x 521
tpaquette@fs.fed.us
Description: Issue a permit to Time Warner Cable Northeast LLC allowing them to extend fiber optic cable service to the
existing wireless communication site on Mt. Tecumseh, including installing buried conduit under approx.
2,000%u2019 of ski trails.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44754
Location:
Tripoli Road Campsite
Relocation and Roadside
Hazard Tree Removal Project
Project Contact
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Within the Waterville Valley Ski Resort permit boundaries, Waterville, NH.
- Recreation management
- Watershed management
EA
In Progress:
Notice of Initiation 12/15/2010
Est. Comment Period Public
Notice 10/2014
Expected:02/2015
06/2015
Tom Giles
603-536-6102
tjgiles@fs.fed.us
Description: Relocation and redesign of all of the campsites along Tripoli Road to sites along adjacent spur roads to mitigate
safety and resource concerns. Removal of hazard trees along Tripoli Road and spur roads to address safety
concerns.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=31039
Location:
Waterville Valley Fan Gun
Project
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Tripoli Road, Mack Brook Road and Hix Mountain Spur Road between Exit 31 on I-93 and the town of
Waterville Valley.
- Recreation management
- Special use management
Developing Proposal
Est. Scoping Start 06/2014
CE
*NEW LISTING*
08/2014
Thomas Paquette
802-767-4261 x 521
tpaquette@fs.fed.us
Description: Install 8 snowmaking fan guns and 2 transformers along World Cup trail. All items would be placed on pre-cast
concrete pads. A few trees would be cut at one transformer and some blasting may occur. Power and water lines
would be placed in trench.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44290
Location:
07/01/2014 03:46 am MT
Expected:07/2014
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Waterville Valley Ski Area.
Page
8 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Waterville Valley Half-pipe
Reconstruction Project
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Pemigewasset Ranger District (excluding Projects occurring in more than one District)
- Recreation management
- Special use management
Developing Proposal
Est. Scoping Start 06/2014
Expected:07/2014
08/2014
CE
*NEW LISTING*
Meserve Brook Watershed
Restoration
Thomas Paquette
802-767-4261 x 521
tpaquette@fs.fed.us
Description: Remove the half pipe on Exhibition trail, restoring trail to freestyle terrain. Lower the walls, bring the trail tread back
toward grade level, and use extra fill from walls to form three small landings for other terrain features.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44289
Location:
White Mountain National Forest
Project Contact
UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not
Applicable. Waterville Valley Ski Area.
R9 - Eastern Region
Saco Ranger District (excluding Projects occurring in more than one District)
- Wildlife, Fish, Rare plants
- Watershed management
In Progress:
Scoping Start 03/20/2014
Expected:06/2014
06/2015
CE
Sheela Johnson
603-536-6231
smjohnson@fs.fed.us
Description: Restoration of aquatic and riparian habitat in and adjacent to Lower Meserve Brook
Location:
Neuts Brook Snowmobile Trail
Relocation Project
UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll. LEGAL - Jackson Township,
Carroll County, New Hampshire. Lower Meserve Brook , Jackson, NH.
- Recreation management
On Hold
CE
N/A
N/A
Brian Johnston
603-466-2713
bmjohnston@fs.fed.us
Description: Relocate the existing snowmobile trail to the edge of the Forest Service administrative site or off the site to a
private land location to eliminate safety concerns associated with the current trail location that bisects the
administrative site.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34515
Location:
07/01/2014 03:46 am MT
UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll. LEGAL - Not Applicable. The trails
current location runs through Bartlett Experimental Forest's administrative site, and a new location is needed to
connect the trail to the Town of Bartlett.
Page
9 of 10
White Mountain National Forest
Project Name
White Mountain National Forest
Presidential Range Dry River
Wilderness Area Trails Project
Project Purpose
Planning Status
Decision
Expected
Implementation
R9 - Eastern Region
Saco Ranger District (excluding Projects occurring in more than one District)
- Recreation management
Completed
CE
Actual: 04/29/2014
Project Contact
06/2014
Desiree Johnston
603-447-5448
dajohnston@fs.fed.us
Description: Sections of the Dry River Trail, Rocky Branch Trail and Isolation Trail in the Presi-Dry Wilderness were damaged
by Hurricane Irene and need repair or a nearby relocation. Rocky Branch Shelter 2 is to be decommissioned and
tent sites designated.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41776
Location:
UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll, Coos. LEGAL - Cutts Grant and
Sargents Purchase in Coos County, NH, and Jackson in Carroll County, NH. Sections of Dry River Trail above the
footbridge, Rocky Branch Trail between Shelters 1 and 2, and intermittent sections of Isolation (west) Trail. Rocky
Shelter 2 is near the jcn. of Isolation Trail.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial
status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited
bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at
(202) 720-2600 (voice and TDD).
To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA
is an equal opportunity provider and employer.
This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
07/01/2014 03:46 am MT
Page
10 of 10
White Mountain National Forest
Download