This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
Project Name
Project Purpose
Planning Status
Decision
Expected
Implementation
Project Contact
R6 - Pacific Northwest Region, Occurring in more than one Forest (excluding Regionwide)
Blue Mountains Forest Plan
Revision
- Land management planning
EIS
In Progress:
DEIS NOA in Federal Register
03/14/2014
Est. FEIS NOA in Federal
Register 05/2015
Expected:08/2015
08/2015
Sabrina Stadler
541-523-1246
bluemtnplanrevision@fs
.fed.us
Description: Revision of Land Management Plans (Forest Plans) for the Malheur, Umatilla, & Wallowa-Whitman Forests.
Forest Plans provide stategic, program-level guidance for future management of forests and their natural
resources for the next 10-15 years.
Web Link: http://www.fs.usda.gov/goto/BlueMountainForestPlanRevisionComments
Location:
Granite Creek Watershed
Mining Plans
UNIT - Malheur National Forest All Units, Wallowa Valley Ranger District, Eagle Cap Ranger District, La Grande
Ranger District, Umatilla National Forest All Units, Whitman Ranger District. STATE - Oregon, Washington.
COUNTY - Asotin, Columbia, Garfield, Walla Walla, Baker, Grant, Harney, Morrow, Umatilla, Union, Wallowa,
Wheeler. LEGAL - Not Applicable. Forest-wide for Malheur, Umatilla, & Wallowa-Whitman (except for the
HCNRA).
- Minerals and Geology
EIS
In Progress:
NOI in Federal Register
10/11/2011
Est. DEIS NOA in Federal
Register 06/2014
Expected:02/2015
02/2015
Sophia Millar
541-426-5540
smillar@fs.fed.us
Description: Analyze proposed mining plans of operations within the Granite Creek Watershed on the Umatilla and WallowWhitman NFs.
Web Link: http://www.fs.fed.us/r6/w-w/projects/nepa_project.shtml?project=2209
Location:
Umatilla National Forest
04/01/2014 04:45 am MT
UNIT - North Fork John Day Ranger District, Whitman Ranger District. STATE - Oregon. COUNTY - Baker,
Grant. LEGAL - T8-10S R34-36 E WM. Granite Creek Watershed.
Heppner Ranger District (excluding Projects occurring in more than one District)
Page
1 of 12
R6 - Pacific Northwest Region
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
R6 - Pacific Northwest Region
Heppner Ranger District (excluding Projects occurring in more than one District)
Ditch Creek Fence and Spring
- Grazing management
On Hold
Project Contact
N/A
N/A
CE
Tim Collins
541-676-2114
tcollins@fs.fed.us
Description: Replace 6.5 miles of electric fence with 3-strand barbed wire fence along Mallory and Little Potamus and Gilbert
creeks. Develop 5 spring sites to provide water in the uplands for cattle and wildlife.
Location:
Ellis Commercial Thin
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Grant, Morrow. LEGAL - T5S, R28E, Sec
10,14, & 25. T8S, R26S Sec 22. T6S, R28E, Sec 12, 13, & 24. T6S, R29E, Sec 8, 9, & 17. South of Heppner
along Mallory, Little Potamus, and Gilbert creeks.
- Forest products
CE
Developing Proposal
Est. Scoping Start 10/2013
Expected:03/2014
07/2014
Jonathan Day
(541) 676-2129
jday@fs.fed.us
Description: The Ellis Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. This
project consists of one thinning unit totaling approximately 70 acres in size located south of the 2105 road.
Web Link: http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=41350
Location:
Herren Commercial Thin
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Grant, Wheeler. LEGAL - Township 6 S.,
Range 29 E., Section 3 Willamette Meridian. Heppner Ranger District - Approximately 36 miles southeast of
Heppner.
- Forest products
CE
Developing Proposal
Est. Scoping Start 10/2013
Expected:04/2014
07/2014
Jonathan Day
(541) 676-2129
jday@fs.fed.us
Description: The Herren Thin project proposes to reduce stocking levels by using a commercial timber sale. This project
consists of one thinning unit totaling approximately 70 acres located along the 5326020 road.
Web Link: http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=41362
Location:
Hog Creek Fence Replacement
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Morrow. LEGAL - Township 4 S., Range 28 E.,
Sections 25 & 26. Heppner Ranger District - Approximately 17 miles southeast of Heppner.
- Grazing management
On Hold
N/A
CE
N/A
Tim Collins
541-676-2114
tcollins@fs.fed.us
Description: Replace an existing 1.75 miles of electric fence with a 3-strand barbed-wire fence.
Location:
04/01/2014 04:45 am MT
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Morrow. LEGAL - Township 6 South, Range 27
East, Sections 3, 10, and 11. One and a half miles east of the Tupper Work Center running west along Skookum
Creek.
Page
2 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Decision
Heppner Ranger District (excluding Projects occurring in more than one District)
Kahler Dry Forest Restoration
EA
Planning Status
- Forest products
- Vegetation management
(other than forest products)
In Progress:
Scoping Start 03/11/2013
Est. 215 Comment Period Legal
Notice 01/2014
Expected:03/2014
Expected
Implementation
Project Contact
R6 - Pacific Northwest Region
06/2014
Jonathan Day
541-676-2129
jday@fs.fed.us
Description: The Kahler Dry Forest Restoration project seeks to restore dry upland forest conditions throughout the Kahler
Creek watershed through a combination of thinning and prescribed burning.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40712
Location:
Potamus Fuels Reduction
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Grant, Wheeler. LEGAL - T7S, R24E, Sec 13,
14; T7S, R24E, Sec 8-18, 20-24; T7S, R25E, Sec 4-10, 14-27, 34-36; T7S, R26E, Sec 31; T8S, R25E, Sec 1,
2, 11-14; T8S, R26E, Sec 5-30, 33-35. Kahler Creek watershed, Heppner Ranger District. Wheeler and Grant
Counties.
- Fuels management
EA
In Progress:
Scoping Start 02/15/2012
Est. Objection Period Legal
Notice 04/2013
Expected:06/2013
07/2013
Scott Wryn
541-676-2138
swryn@fs.fed.us
Description: Identify and reduce wildfire risk to public and private lands within the Potamus subwatersheds as identified in the
Morrow County Community Wildfire Protection Plan.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=29191
Location:
Rhea Commercial Thin
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Grant, Morrow. LEGAL - T5S R28E, T5S
R29E, T6S R28E, and T6S R29E. Within the Potamus WUI area as identified in the Morrow County Community
Wildfire Protection Plan.
- Forest products
CE
Developing Proposal
Est. Scoping Start 03/2013
Expected:07/2013
08/2013
Jonathan Day
(541) 676-2129
jday@fs.fed.us
Description: The Rhea Thin project proposes to reduce stocking levels by using a commercial timber sale. This project consists
of two thinning units totaling approximately 70 acres located along the 2100050 road.
Web Link: http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=41366
Location:
04/01/2014 04:45 am MT
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Morrow. LEGAL - Township 5 S., Range 28 E.,
Section 7. Umatilla National Forest, Heppner Ranger District. Approximately 16 miles southeast of the town of
Heppner, OR.
Page
3 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
Heppner Ranger District (excluding Projects occurring in more than one District)
Smith Commercial Thin
- Forest products
CE
Developing Proposal
Est. Scoping Start 03/2013
Expected:07/2013
Project Contact
R6 - Pacific Northwest Region
08/2013
Jonathan Day
541-676-2129
jday@fs.fed.us
Description: The Smith Commercial Thin project proposes to reduce stocking levels by using a commercial timber sale. This
project consists of one thinning unit totaling approximately 70 acres in size located north of the 5300750 road and
east of the 5300252 road.
Web Link: http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=41377
Location:
Swale Creek C & H Allotment
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Morrow. LEGAL - T 4 S, R 28 E, Section 25
and 26. Heppner Ranger District, approximately 25 miles from the town of Heppner, OR.
- Grazing management
EA
In Progress:
Comment Period Public Notice
09/04/2013
Expected:11/2013
03/2014
Tim Collins
541-676-2114
tcollins@fs.fed.us
Description: Authorization for the continued cattle grazing of the Swale Creek Allotment.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=29190
Location:
Umatilla National Forest
Clear Creek Tailings Road
Realignment
UNIT - Heppner Ranger District. STATE - Oregon. COUNTY - Grant, Morrow. LEGAL - T 5 S., R 27 E.,
Sections 13, 14, 22-27, and 34-36; T. 5 S., R28E., Sections 17-20, and 29-33; T. 6 S., R 27 E., Sections 1, 2,
11-14 and 22-26; T. 6 S., R 28 E., Sections 3-11, 15- 22 and 28-33; a. Central portion of the district
approximately 14 miles north of the town of Monument; Penland Lake, Ditch Creek area.
North Fork John Day Ranger District (excluding Projects occurring in more than one District)
- Wildlife, Fish, Rare plants
- Road management
On Hold
EA
N/A
R6 - Pacific Northwest Region
N/A
Joy Archuleta
541-427-5364
jearchuleta@fs.fed.us
Description: Move dredge tailings and relocate about 3100 feet of Grant County Road 13. Survey and design in FY2010,
NEPA analysis & documentation FY 2011, implementation FY 2012/2013.
Location:
04/01/2014 04:45 am MT
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant. LEGAL - T9S, R35E, Sec
10, 14, 15. The project is located in Grant County, Oregon, in the Clear Creek Watershed on Grant County Road
13.
Page
4 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
North Fork John Day Ranger District (excluding Projects occurring in more than one District)
Columbia Power Special Use
Authorization for a New Term
- Special use management
On Hold
N/A
Project Contact
R6 - Pacific Northwest Region
N/A
CE
Christine Helberg
541-427-5351
chelberg@fs.fed.us
Description: Use and maintenance of the existing utility corridor.
Location:
Hidaway Mining EA
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant, Umatilla. LEGAL - T2-5S
R32E, T5-8S R31-33E, and T4-5S R31-35E (Willamette Principal Meridian). Powerline corridors that cross FS
lands: (1)near Albee, (2) east of Ukiah near Hwy 244 and (3) near Dale along Hwy 395 and FS road 3980.
- Minerals and Geology
EA
In Progress:
Scoping Start 12/21/2011
Est. 215 Comment Period Legal
Notice 01/2014
Expected:04/2014
07/2014
Christine Helberg
541-427-5351
chelberg@fs.fed.us
Description: Expansion of current exploration pits to a maximum of 30 ft wide by 25 ft deep using hand tools & limited
mechanical equipment. Use of an existing closed road & shelter. Placement of an outhouse. Limited use of a
spring for hand-washing of rock.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=30735
Location:
Junkens and Beeman Creek
Culvert Project
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Umatilla. LEGAL - T5S R33 1/2E
Sections 22, 23. Hidaway Creek drainage, Umatilla County, Oregon.
- Watershed management
In Progress:
Scoping Start 05/15/2012
CE
Expected:10/2013
07/2014
Allison Johnson
541-427-5305
ajohnson04@fs.fed.us
Description: Removal/replacement of one culvert on the Beeman-Junkens Creek 3015 OHV trail (1007140 rd) and
removal/replacement of two culverts on the Forest Service (FS) road 1007000 and two culvert
removal/replacements on the FS road 1007100.
Location:
04/01/2014 04:45 am MT
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant, Umatilla. LEGAL - T8S,
R33E, Sec. 18, 19, 30 and T8S, R32E, Sec. 24, 25. Junkens Creek and Beeman Creek, in the Desolation
watershed.
Page
5 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
North Fork John Day Ranger District (excluding Projects occurring in more than one District)
NFJD Aspen Restoration
- Wildlife, Fish, Rare plants
Developing Proposal
Est. Scoping Start 08/2013
CE
Expected:09/2013
Project Contact
R6 - Pacific Northwest Region
10/2013
Diane Shirley
541-427-5315
dshirley@fs.fed.us
Description: Restoration projects to protect/enhance/restore declining stands of quaking aspen to improve wildlife habitat.
Includes buck & pole fencing, tree planting and girdling, felling or removal of conifers up to 21" DBH.
Location:
North Fork John Day Ranger
District Waid Street House
Conveyance
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant, Morrow, Umatilla. LEGAL Entire North Fork John Day Ranger District; see project file for legal locations. District-wide, wherever aspen
stands occur.
- Land ownership management
- Facility management
In Progress:
Scoping Start 03/19/2013
Expected:09/2013
10/2013
CE
Bradley Lathrop
541-427-5335
hollyahutchinson@fs.fe
d.us
Description: Selling of the Forest Service owned house located at 301 East Waid Street, Ukiah, Oregon. This proposed
conveyance is authorized under the Forest Service Facility Realignment and Enhancement Act of 2005
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41426
Location:
Oriental Loop OHV Trail
Construction
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Umatilla. LEGAL - Section 14,
Township 5 South, Range 31 East, Willamette Meridian Surveyed. 301 East Waid Street, Ukiah, OR, 97880.
- Recreation management
On Hold
CE
N/A
N/A
Janel Lacey
541-427-5394
jlacey@fs.fed.us
Description: Designate 9.6 miles of new OHV trail to provide additional access to the Winom-Frazier OHV Complex from the
Oriental Campground. Most of the route would occur on existing open and closed roads, with only 1-2 miles of
new construction.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=35259
Location:
04/01/2014 04:45 am MT
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant, Umatilla. LEGAL - Follows
existing open and closed roads beside Oriental Creek from Oriental Creek Campground on the N. Fork John Day
River to the Winom-Frazier OHV Trail system. T. 6 S. R. 33 E., sections 26, 27, 34, and 35; and T. 7 S., R. 33 E.,
sections 3 and 10.
Page
6 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Expected
Implementation
North Fork John Day Ranger District (excluding Projects occurring in more than one District)
Paradise Trail Reroute
- Recreation management
On Hold
N/A
Project Contact
R6 - Pacific Northwest Region
N/A
CE
Janel Lacey
541-427-5394
jlacey@fs.fed.us
Description: Reroute the lower portion of the Paradise Trail to install grade-reducing switchbacks (3.4 miles), bringing the
grade from 40% to 10-15% for the entire trail. Decommission 1.1 miles of existing, steep trail.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=35258
Location:
Ruby Creek Snowmobile Trail
Grooming
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant. LEGAL - T 6 S., R. 34 E.
sections 2 and 3. The trail is located within the North Fork John Day Wilderness.
- Recreation management
On Hold
N/A
N/A
CE
Janel Lacey
541-427-5394
jlacey@fs.fed.us
Description: This is an existing, un-groomed snowmobile trail. In order to groom the trail, a bridge will be constructed over
Ruby Creek and trees less than six inches DBH along each side of the trail will be removed to a 14-foot width.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33727
Location:
Umatilla National Forest
UNIT - North Fork John Day Ranger District. STATE - Oregon. COUNTY - Grant. LEGAL - T9S R35E Secs
14, 15, 17 & 18. Approximately three miles southwest of the town of Granite, OR.
Pomeroy Ranger District (excluding Projects occurring in more than one District)
Asotin Creek Prescribed Fire
Project
- Fuels management
EA
In Progress:
Scoping Start 03/14/2011
Est. 215 Comment Period Legal
Notice 02/2014
Expected:09/2014
R6 - Pacific Northwest Region
10/2014
Tara Hanger
509-843-4676
thanger@fs.fed.us
Description: Implement prescribed fire on approx. 7900 acres of FS land & 2400 acres of WA Dept of Fish and Wildlife land to
reduce fuels (ground, ladder, canopy biomass) and rehabilitate grass and shrubs to improve wildlife forage. Will
rescope in February 2012.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34631
Location:
04/01/2014 04:45 am MT
UNIT - Pomeroy Ranger District. STATE - Washington. COUNTY - Asotin, Garfield. LEGAL - T9N,R4E,
Sections 14-16, 21-23, 24-28 and 35; T9N, R43E Sections 2-4, 9-10 and; T9N, R44E, Sections 16-17, 19-21
and 30. Forest Service and WA Dept of Fish and Wildlife land in Garfield and Asotin Counties, WA.
Page
7 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Pomeroy Ranger District (excluding Projects occurring in more than one District)
Seven Sisters Spring
Development
- Wildlife, Fish, Rare plants
On Hold
N/A
Expected
Implementation
Project Contact
R6 - Pacific Northwest Region
N/A
CE
William Dowdy
509-843-4687
wdowdy@fs.fed.us
Description: Fence off the spring area to exclude cattle. Water will be piped to a new trough approximately 100 feet away from
spring. Trough will be outside of fenced area on a gravel pad. Overflow water will be piped back inside fenced
area.
Location:
Wenaha Wild and Scenic River
Comprehensive River
Management Plan
UNIT - Pomeroy Ranger District. STATE - Washington. COUNTY - Asotin. T7N., R43E, Section 1.
- Special area management
EA
In Progress:
Scoping Start 05/14/2013
Est. 215 Comment Period Legal
Notice 01/2014
Expected:08/2014
09/2014
Larry Randall
775-884-8140
lrandall@fs.fed.us
Description: Develop a comprehensive river management plan for Wenaha River which is part of the Wild and Scenic River
System.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40801
Location:
Umatilla National Forest
UNIT - Pomeroy Ranger District. STATE - Oregon. COUNTY - Wallowa. Entire mainstem of the Wenaha River
approximately 22 miles.
Walla Walla Ranger District (excluding Projects occurring in more than one District)
Edwards Waterline Special Use
Permit Renewal
- Special use management
Developing Proposal
Est. Scoping Start 03/2014
CE
*NEW LISTING*
12/2014
Jeff Bloom
509-522-6277
jhbloom@fs.fed.us
Description: The project would issue a new special use permit for the operations and maintenance of the existing water line and
diversion for a term of 20-years, with the new permit expiring December 31, 2036.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44087
Location:
04/01/2014 04:45 am MT
Expected:11/2014
R6 - Pacific Northwest Region
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Umatilla. LEGAL - NE Corner of the NW
1/4, SW 1/4 of Sec 21, T6N, R38E, W.M. On China Creek in Mill Creek drainage. Size is 0.10 acres.
Page
8 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Walla Walla Ranger District (excluding Projects occurring in more than one District)
Grande Ronde Landscape
Prescribed Fire
CE
*NEW LISTING*
R6 - Pacific Northwest Region
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union, Wallowa. LEGAL - T4N R40E sec. 1,
2, 10, 11, 12, 14 & T5N R40 E sec. 24, 25, 36 & T5N R41E sec. 18, 19, 20, 21, 28, 29. Southeast of
Lookout Mountain, situated between National Forest system road 6200000 and the Grande Ronde river.
- Special use management
Developing Proposal
Est. Scoping Start 03/2014
Expected:11/2014
12/2014
CE
*NEW LISTING*
Project Contact
Tyson Albrecht
- Vegetation management
Developing Proposal
Expected:05/2014
09/2014
509-522-6283
(other than forest products)
Est. Scoping Start 03/2014
talbrecht@fs.fed.us
- Fuels management
Description: The project objective is to reduce hazardous fuels along a strategic landscape break according to the Forest
Landscape Wildfire Strategy which seeks increased defensibility in key areas, as well as retention of large, fire
resistant trees. 1,531 ac.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43835
Location:
Langdon Lake Water
Cooperative Permit Renewal
Expected
Implementation
Jeff Bloom
(509) 522-6277
jhbloom@fs.fed.us
Description: The project would involve the issuance of a new 20-year special use permit for the use of the existing
improvements. There would be no ground disturbing activities associated with the implementation of this project,
other than routine maintenance.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44055
Location:
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Umatilla. LEGAL - T.4N., R.38E., Section
32. Tollgate Quad, within the vicinity of Langdon Lake 1.10 acres.
Jeff Bloom
509-522-6277
jhbloom@fs.fed.us
Oregon Department of
Transportation Storage Area
Permit Renewal
- Special use management
CE
Description: The proposed action would issue a special use permit to replace an expired one for a 20-year term for the
operations and maintenance of the existing improvements (storage areas).
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44091
*NEW LISTING*
Location:
04/01/2014 04:45 am MT
Developing Proposal
Est. Scoping Start 03/2014
Expected:11/2014
12/2014
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - T2N, R38E, Sec 11, SE,
SE; T3N, R38E, Sec 26 SW 1/4; T3N, R38E, Sec 9, S 1/2, SE 1/4. Along Oregon 204 in upper Little Phillips Cr;
Andies Prairie Rock Pit; & Spout Springs Rock Pit. Size is 6 Acres.
Page
9 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Walla Walla Ranger District (excluding Projects occurring in more than one District)
Pinical Vegetation Management - Forest products
Project
Developing Proposal
Est. Scoping Start 03/2014
Expected:06/2014
Expected
Implementation
R6 - Pacific Northwest Region
07/2014
CE
*NEW LISTING*
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - T4N; R40E; Section 9 and
10. The Unit is located between the 6200, 6200-390 and 6200-391 roads and is approx. 70 acres.
- Wildlife, Fish, Rare plants
- Watershed management
- Road management
Developing Proposal
Est. Scoping Start 03/2014
Expected:09/2014
09/2014
CE
*NEW LISTING*
Developing Proposal
Est. Scoping Start 04/2014
Expected:09/2014
10/2014
Steve Anderson
509-522-6041
sranderson@fs.fed.us
Description: This project would isolate a spring and associated wet area with poor drainage from the snowmobile trail. This
would be accomplished by placing pit run aggregate and filter cloth in layers over the trail so it will be able to
freeze.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44094
Location:
04/01/2014 04:45 am MT
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - T2N, R38E S26, NE1/4, SE
1/16. Intersection of road 3734 with Little Phillips Creek, adjacent to highway 204 plus about ¾ mile of 3734 road
from that point.
- Recreation management
CE
*NEW LISTING*
William Dowdy
509-843-4687 or 509522-6042
wdowdy@fs.fed.us
Description: Remove the culvert in Forest Road 3734 over Little Phillips Creek and fill and reshape the channel and flood plain
to create correct bankful and floodplain width and to mimic channel form up and downstream and to eliminate fishtrapping culvert pool.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44056
Location:
Snowmobile Trail Stabilization
Deanna Engelmann
509-522-6054
dlengelmann@fs.fed.us
Description: The activities would involve a thin-from-below silvicultural cutting treatment, with incidental large trees infected
with root disease and/or dwarf mistletoe also removed. Openings/gaps would encourage regeneration of disease
resistant tree species.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44078
Location:
Road 3734 Culvert Removal
with Partial Road
Decommissioning
Project Contact
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - T4N, R38E, S10, SW of
NE. At Summer homes adjacent to OR HWY 204.
Page
10 of 12
Umatilla National Forest
Project Name
Umatilla National Forest
Project Purpose
Planning Status
Decision
Walla Walla Ranger District (excluding Projects occurring in more than one District)
Thomas Creek Restoration
Project
- Forest products
Developing Proposal
Est. Notice of Initiation 03/2014
Expected:07/2015
Expected
Implementation
R6 - Pacific Northwest Region
07/2015
EA
*NEW LISTING*
Carrie Spradlin
509-522-6059
cspradlin@fs.fed.us
Description: Approximately 1,663 acres of mechanical treatments are proposed, along with 975 acres of small diameter hand
thinning. Mechanical treatments would have a restoration focus and both lumber and chip materials would be
produced.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43943
Location:
Tollgate Fuels Reduction
Project
Project Contact
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - Portions of T1N R37E sec.
1,2,12, T1N R38E sec. 1,2,3,4,5,6,7,8,9,10,11 and 12, T2N R37E sec. 12,3,14,15,22,23,24,25,26 and 36, T2N
R38E sec. 5,7,8,9,16,17,18,19,20,21,27,28,29,30,31,32,33,34 and 35. East of Highway 204 and south of Forest
Road 3100000, within the vicinity of Phillips Creek, Dry Creek and other associtaed drainages.
- Fuels management
EIS
In Progress:
Objection Period Legal Notice
12/13/2013
Expected:07/2014
07/2014
Kimpton Cooper
509-522-6009
kmcooper@fs.fed.us
Description: The project seeks to conduct fuels reduction activities within the Tollgate Wildland Urban Interface (WUI).
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=28356
Location:
Verizon Cell Site Fence Project
- Special use management
CE
*NEW LISTING*
Developing Proposal
Est. Scoping Start 03/2014
Expected:11/2014
12/2014
Jeff Bloom
509-522-6277
jhbloom@fs.fed.us
Description: The project proposes to install security chain link fence around a cellular tower and propane tank that provides fuel
for an auxiliary generator. A backhoe and jackhammer would be used to dig holes for the posts and a trench for
ground wire.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44048
Location:
04/01/2014 04:45 am MT
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Umatilla. Located within Tollgate Wildland
Urban Interface, established in Umatilla County CWPP.
UNIT - Walla Walla Ranger District. STATE - Oregon. COUNTY - Union. LEGAL - T.3N., R38E. Sec 15. NE
1/4. Spout Springs Communications Site, Size 0.1 acres.
Page
11 of 12
Umatilla National Forest
Project Name
Project Purpose
Planning Status
Decision
Expected
Implementation
Project Contact
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial
status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited
bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at
(202) 720-2600 (voice and TDD).
To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA
is an equal opportunity provider and employer.
This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
04/01/2014 04:45 am MT
Page
12 of 12
Umatilla National Forest
Related documents
Download