Project Name
07/01/2015 to 09/30/2015
Mt. Hood National Forest
This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
R6 - Pacific Northwest Region, Regionwide (excluding Projects occurring in more than one Region)
Aquatic Invasive Species order to prevent the spread or introduction of aquatic invasive species
CE
- Wildlife, Fish, Rare plants Completed Actual: 03/03/2015 07/2015
Description:
The purpose of this order is to prevent the spread or introduction of aquatic invasive plant or animal species.
Public involvement is targeted for the Umatilla, Willamette, Mt. Baker-Snoqualmie, Gifford Pinchot, and Colville
NFs.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44360
James Capurso
208-557-5780 jcapurso@fs.fed.us
Location: UNIT - R6 - Pacific Northwest Region All Units. STATE - Oregon, Washington. COUNTY - Asotin, Clark,
Columbia, Cowlitz, Ferry, Garfield, King, Klickitat, Lewis, Pend Oreille, Pierce, Skagit, Skamania, Snohomish,
Stevens, Walla Walla, Whatcom, Baker, Clackamas, Douglas, Grant, Jefferson, Lane, Linn, Marion, Morrow,
Umatilla, Union, Wallowa, Wheeler. LEGAL - Not Applicable. Order will apply to all Forests in Region 6, however targeted scoping is with the Umatilla, Gifford Pinchot, Mt. Baker/Snoqualmie, Willamette and Colville NFs tribal and public scoping lists.
Mt. Hood National Forest, Occurring in more than one District (excluding Forestwide)
Cooper Spur-Government
Camp Land Exchange
EIS
R6 - Pacific Northwest Region
- Land ownership management In Progress:
NOI in Federal Register
10/13/2010
Est. DEIS NOA in Federal
Register 06/2016
Expected:02/2017 02/2017 Michelle Lombardo
503-668-1796 mlombardo@fs.fed.us
Description: The Forest Service would convey 120 acres of property at Government Camp and acquire 770 acres of private land at Cooper Spur. This land exchange was mandated by Congress in the Omnibus Public Land Management
Act of 2009.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33072
Location: UNIT - Zigzag Ranger District, Hood River Ranger District. STATE - Oregon. COUNTY - Clackamas, Hood
River. LEGAL - Not Applicable. Government Camp, Oregon, and Cooper Spur area, Oregon.
07/01/2015 04:33 am MT Page 1 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest, Occurring in more than one District (excluding Forestwide)
Road Decommissioning for
Habitat Restoration, Increment
#3 (Barlow and Hood River
Ranger Districts)
EA
R6 - Pacific Northwest Region
- Wildlife, Fish, Rare plants
- Watershed management
- Road management
Expected:05/2016 http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34050
05/2016 Casey Gatz
541-352-1255 cgatz@fs.fed.us
Description:
Decommissioning roads to improve hydrologic function and reduce adverse impacts to aquatic habitat on the
Barlow and Hood River Ranger Districts.
Web Link:
In Progress:
Notice of Initiation 04/30/2014
Est. Comment Period Public
Notice 10/2015
USGS Volcanic Monitoring
Stations in the Mt. Hood
Wilderness
EA
Location: UNIT - Barlow Ranger District, Hood River Ranger District. STATE - Oregon. COUNTY - Hood River, Wasco.
LEGAL - Not Applicable. The project area includes the White River watershed and Tygh Creek subwatershed.
- Special use management
- Research and Development
In Progress:
Scoping Start 03/16/2015
Est. Comment Period Public
Notice 03/2016
Expected:08/2016 08/2016 MaryEllen Fitzgerald
503-668-1429 mfitzgerald@fs.fed.us
Description: Four monitoring stations would be installed in Mt. Hood Wilderness. They would be assembled and maintained by
U.S. Geological Survey. The data would assess volcanic activity and assist in communications regarding volcanic hazards and public safety.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=46254
Location: UNIT - Zigzag Ranger District, Hood River Ranger District. STATE - Oregon. COUNTY - Clackamas, Hood
River. LEGAL - Not Applicable. Mt. Hood Wilderness.
Mt. Hood National Forest Barlow Ranger District (excluding Projects occurring in more than one District)
Dog River Pipeline
Replacement
EA
R6 - Pacific Northwest Region
- Special use management On Hold N/A N/A Casey Gatz
541-352-1255 cgatz@fs.fed.us
Description: The existing Dog River pipeline, which is an important component of The Dalles' public drinking water supply, is deteriorating, leaking from tree damage, and exhibiting corrosion. This project proposes to replace the existing pipeline.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34721
Location: UNIT - Barlow Ranger District. STATE - Oregon. COUNTY - Hood River, Wasco. LEGAL - T2S, R10E,
Sections 2, 3, 4, 9, 10, and 11. The Dog River pipeline conveys water from the Dog River diversion dam to the south fork of Mill Creek.
07/01/2015 04:33 am MT Page 2 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Clackamas River Ranger District (excluding Projects occurring in more than one District)
Goat Mountain Thin
EA
R6 - Pacific Northwest Region
- Forest products Expected:01/2016 http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43852
08/2016 James Roden
503-630-8767 jroden@fs.fed.us
Description:
Thinning second-growth stands on approximately 2,800 acres of mid-aged stands ranging in age from 30 to 60 years old in parts of the Middle Clackamas, Lower Clackamas, and Lower Molalla River Watersheds.
Web Link:
In Progress:
Scoping Start 03/05/2014
Est. Comment Period Public
Notice 08/2015
Indian Henry Campground
EA
Location: UNIT - Clackamas River Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable.
Sourth Fork Clackamas River and Clear Creek.
- Recreation management
- Facility management
On Hold N/A N/A James Roden
503-630-8722 jroden@fs.fed.us
Description: Assessment of options to deal with removing hazard trees caused by root diseases in Indian Henry Campground and modernization of facilities. Most of campground is closed at this time due to hazard.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42342
Lemiti Fuels Reduction Project
EA
Location: UNIT - Clackamas River Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable.
Indian Henry Campground.
- Forest products
- Fuels management
In Progress:
Scoping Start 09/21/2012
Est. Comment Period Public
Notice 08/2015
Expected:01/2016 07/2016 James Roden
503-630-8767 jroden@fs.fed.us
Description: Fuels reduction and salvage of bug killed lodgepole pine on approximately 2,300 acres. Fuel treatments would include a mix of actions such as harvesting and removing trees, precommercial thinning, pruning, slash piling and pile burning.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38290
Location: UNIT - Clackamas River Ranger District. STATE - Oregon. COUNTY - Clackamas, Marion. LEGAL - Not
Applicable. Lemiti Butte.
07/01/2015 04:33 am MT Page 3 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Clackamas River Ranger District (excluding Projects occurring in more than one District)
Restoration 2015
EA
R6 - Pacific Northwest Region
- Wildlife, Fish, Rare plants
- Watershed management
Expected:01/2016 http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38291
06/2016 Tom Horning
503-630-8798 thorning@fs.fed.us
Description:
Formerly called Restoration 2014. Fish habitat, watershed restoration, & water quality restoration projects. Projects include instream log & boulder placement, side channel creation, road closure, decommissioning & repair of vehicle damage.
Web Link:
In Progress:
Comment Period Public Notice
04/25/2014
Location: UNIT - Clackamas River Ranger District. STATE - Oregon. COUNTY - Clackamas, Marion. LEGAL - Not
Applicable. district wide.
Mt. Hood National Forest Hood River Ranger District (excluding Projects occurring in more than one District)
Lava Restoration
EA
R6 - Pacific Northwest Region
- Forest products
- Vegetation management
(other than forest products)
- Watershed management
- Road management
Completed Actual: 04/29/2015 05/2015 Casey Gatz
541-575-3031 cgatz@fs.fed.us
Description:
Improve forest health in West, East & Middle Fork of Hood River subwatersheds. Treatments include plantation thinning, firewood removal & huckleberry enhancement, plus decommissioning 2.1 miles and closing (year round & seasonal) 22.3 miles of roads.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40686
Polallie Cooper Hazardous
Fuels Reduction
EA
Location:
- Forest products
- Fuels management
In Progress:
Scoping Start 02/16/2015
Est. Comment Period Public
Notice 07/2015
Expected:02/2016 02/2016 Casey Gatz
541-352-1255 cgatz@fs.fed.us
Description: Reduce fuels loading in fire adapted plant communities in the Cooper Spur Wildland Urban Interface located in the
East Fork of Hood River watershed. Treatments may include plantation thinning, firewood removal, fuel break & natural stand thinning.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40687
Location:
UNIT - Hood River Ranger District. STATE - Oregon. COUNTY - Hood River. LEGAL - T1S R8.5E Sections
25 and 36, T1S R9E Sections 1 and 6-36. West, East & Middle Fork of Hood River Subwatersheds.
UNIT - Hood River Ranger District. STATE - Oregon. COUNTY - Hood River. LEGAL - T1S, R9E Sections
10-11, 14-15, 35-39, PB43 & PB44; T1S R10E Sections 4-10, 17-18 & 32-33. East Fork Hood River
Watershed; Pinnacle Creek, East and Middle Fork of the Hood River, and Dog River Subwatersheds.
07/01/2015 04:33 am MT Page 4 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Hood River Ranger District (excluding Projects occurring in more than one District)
Portland General Electric (PGE)
Regulator Replacement at Mt.
Hood Meadows Ski Area CE
CE
*NEW LISTING*
R6 - Pacific Northwest Region
- Special use management Developing Proposal
Est. Scoping Start 07/2015
Expected:08/2015 09/2015 MaryEllen Fitzgerald
503-622-3191ext 625 mfitzgerald@fs.fed.us
Description: Because of low voltage problems caused by above ground regulators, PGE has proposed to replace the existing pole mounted regulator with a more reliable, in-ground vault.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=47135
Tilly Jane Hazardous Fuels
Reduction
CE
Location: UNIT - Hood River Ranger District. STATE - Oregon. COUNTY - Hood River. LEGAL - T3S, R9E, Section 4
SE SE. Northwest of the Mt. Hood Meadows Ski Area's administration building.
- Recreation management
- Heritage resource management
- Fuels management
Completed Actual: 05/11/2015 06/2015 Casey Gatz
541-352-1255 cgatz@fs.fed.us
Description: The purpose of the project is to remove ladder fuel on 34 acres within and around the Tilly Jane Campground to protect the historic site and campground from a large scale disturbance.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=46653
Location: UNIT - Hood River Ranger District. STATE - Oregon. COUNTY - Hood River. LEGAL - Township 02 S.,
Range 09 E., Section 14, 15. Willamette Meridian. The proposed project would occur on 34 acres within and around the Tilly Jane Campground located on the Hood River Ranger District of the Mt. Hood National Forest.
Mt. Hood National Forest Zigzag Ranger District (excluding Projects occurring in more than one District)
Bull Run Land Exchange
EA
R6 - Pacific Northwest Region
- Wildlife, Fish, Rare plants
- Land ownership management
In Progress:
Scoping Start 08/12/2010
Est. Comment Period Public
Notice 01/2016
Expected:08/2016 09/2016 Leanne Veldhuis
503-622-2030 lveldhuis@fs.fed.us
Description: The Mt. Hood National Forest would convey 2,890 acres of land to the City of Portland, and acquire 2,440 acres of city land, all in the Bull Run Watershed Management Unit.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33120
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas, Multnomah. LEGAL - Not
Applicable. Within the Bull Run Watershed Management Unit.
07/01/2015 04:33 am MT Page 5 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Zigzag Ranger District (excluding Projects occurring in more than one District) R6 - Pacific Northwest Region
Forest Plan Amendment to
Update the Bull Run Watershed
Management Unit Land Use
Allocation
CE
- Land management planning Cancelled N/A N/A Leanne Veldhuis
503-622-2030 lveldhuis@fs.fed.us
Description: Change all Land Use Allocations to DA-1 (Bull Run Watershed)and DA-3 (Research Natural Area) and update the
Plan Standards & Guidlines to comply with Omnibus Parks & Public Lands Management and Little Sandy River
Watershed Protection Acts.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=45411
Lady Creek Water System
Replacement
CE
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable. Bull Run
Watershed Management Unit.
- Special use management Completed Actual: 06/03/2015 07/2015
Description:
Replace and upgrade existing Lady Creek waterlines serving recreation residence cabins because the existing lines are leaking and have reached the end of their service life. These waterlines are along National Forest System
Roads 2620, 220E and 2632.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=45932
Leanne Veldhuis
503-622-2030 lveldhuis@fs.fed.us
Mazama Lodge Parking Area
Expansion
EA
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - T3S, R7E, Section 11 and
T3S, R8E, Section 32. Water line serves the recreation residents along National Forest Service Roads 2620,
220E, and 2632.
- Special use management In Progress:
Scoping Start 09/10/2014
Est. Comment Period Public
Notice 01/2016
Expected:07/2016 07/2016 Leanne Veldhuis
503-622-2030 lveldhuis@fs.fed.us
Description:
The Mazamas are proposing to expand an existing 3-4 stall parking area located south of the Mazama Lodge on
NFSR 2600530 into approximately 66 parking stalls and one bus pull-out, to mitigate a long-standing visitor safety issue.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=45241
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - T 3 S, R 8 1/2 E, Sec 24,
WM. The proposed project area is located on National Forest System Road (NFSR) 2600530, just north of US
Highway 26 and Oregon Highway 173.
07/01/2015 04:33 am MT Page 6 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Zigzag Ranger District (excluding Projects occurring in more than one District)
Pioneer Bridle Trail CE
CE
R6 - Pacific Northwest Region
- Recreation management Completed Actual: 06/04/2015 06/2015 McKenzie Jensen
503-622-2026 mckenziejensen@fs.fed
.us
Description: The Pioneer Bridle trail will need to be relocated and reconstructed in sections where the ODOT highway expansion project will effect the trail location. Aproximately 1/2 mile of trail over a 2-mile stretch will be relocated.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42351
Portland General Electric (PGE)
Buried Line Replacement near
Summit Ski Area CE
CE
*NEW LISTING*
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable. The
Pioneer Bridle trail is located between Glacier View Snopark and Tollgate Trailhead.
- Special use management In Progress:
Scoping Start 06/29/2015
Expected:07/2015 09/2015
Description:
In order to provide safe and reliable power, PGE has proposed to replace a current buried powerline that is failing due to aging. This new line (about 1,300 feet in length) will be installed adjacent to the existing line, which will remain in ground.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=47133
MaryEllen Fitzgerald
503-622-3191ext 625 mfitzgerald@fs.fed.us
Sandy River Trail
Reconstruction
CE
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - T3S R8E Section SW13 and NW24. The proposed replacement powerline is near the Summit Ski Area.
- Recreation management Completed Actual: 06/04/2015 06/2015 McKenzie Jensen
503-622-2026 mckenziejensen@fs.fed
.us
Description: Portions of the Sandy River Trail would be reconstructed by installing drainage structures including drain dips, waterbars, rock armoring and check dams.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42410
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable. The bridge is located on the Pacific Crest Trail where the trail crosses the Muddy Fork River. The easiest way to access the trail bridge is by Ramona Falls Trailhead.
07/01/2015 04:33 am MT Page 7 of 8 Mt. Hood National Forest
Project Name Project Purpose Planning Status Decision
Expected
Implementation
Project Contact
Mt. Hood National Forest Zigzag Ranger District (excluding Projects occurring in more than one District)
Skibowl Mountain Bike Trail
Addition
CE
*NEW LISTING*
R6 - Pacific Northwest Region
- Recreation management
- Special use management
In Progress:
Scoping Start 04/27/2015
Expected:07/2015 07/2015 Shawnee Hinman
541-352-1245 sfhinman@fs.fed.us
Description: Construct an additional 2 miles of downhill mountain bike trails within the Mt. Hood SkiBowl permit boundary. The proposed trail would go from the Upper Bowl Chairlift to Lower Bowl Chair area. Some of the trail would be within existing roads.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=46854
Location: UNIT - Zigzag Ranger District. STATE - Oregon. COUNTY - Clackamas. LEGAL - Not Applicable. Mt. Hood
SkiBowl Ski Area Permit Area.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at
(202) 720-2600 (voice and TDD).
To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.
This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
07/01/2015 04:33 am MT Page 8 of 8 Mt. Hood National Forest