PROJECT GUIDE For Designers, Contractors and Users SFU Burnaby Campus 2011 Project Guide v. 2.0 12/1/2011 Facilities Services Technical Standards Committee FACILITIES SERVICES PROJECT GUIDE | 3 Contents ABOUT THIS GUIDE 8 WELCOME8 AUDIENCE8 ACKNOWLEDGMENTS9 PART A : GETTING A PROJECT STARTED 11 SETTING THE CAMPUS CONTEXT 11 REGULATORY BODIES (DEVELOPMENT AND BUILDING PERMITS) 13 PROJECT DEVELOPMENT AND MANAGEMENT 15 GETTING BASE DRAWINGS AND INFORMATION 18 PART B: DOING CONSTRUCTION WORK ON CAMPUS 21 SCHEDULING OF WORK 21 SITE OFFICE AND ADMINISTRATION 22 TRAFFIC AND LOADING ACCESS 23 ENVIRONMENTAL REQUIREMENTS 24 JOB SITE SAFETY 25 SECURITY OF THE JOB SITE 25 WORK OUTSIDE OF THE CONSTRUCTION SITE 26 PROTECTING EXISTING 26 OTHER RULES AND REGULATIONS 28 PART C: DESIGNING FOR BURNABY CAMPUS SUSTAINABILITY AND GREEN BUILDING STANDARDS 29 29 4 | PROJECT GUIDE NAMING SYSTEMS ON CAMPUS 30 DESIGNING FOR UNIVERSAL ACCESS 31 DESIGNING PUBLIC AREAS & SPECIFIC FUNCTIONAL SPACES 32 SPECIFYING ARCHITECTURAL SYSTEMS 34 SPECIFYING HEATING AND VENTILATION SYSTEMS 39 DESIGNING WATER, SANITARY AND STORM SYSTEMS 41 SPECIFYING FIRE PROTECTION SYSTEMS 42 SPECIFYING ELECTRICAL SYSTEMS (FIRE ALARM, POWER AND LIGHTING) 42 SPECIFYING DATA AND TELECOMMUNICATION SYSTEMS 46 PART D: PROJECT DOCUMENTATION AND EXECUTION 47 OWNER’S (SFU) ROLE AND CONSULTANT TEAM 47 SOURCES OF INFORMATION 47 DESIGN INTERFACE WITH BASE BUILDING (for Renovation Projects) 48 PUBLIC REGULATORY REQUIREMENTS 48 COMMENCEMENT OF RENOVATION WORK 48 DOCUMENTING THE PROJECT: DRAWING AND SPECIFICATIONS 49 DOCUMENTING MECHANICAL PLANS AND CONTROLS 51 OPERATIONS & MAINTENANCE MANUALS 51 SYSTEM CONFIGURATION DOCUMENT 53 PREPARING CONTRACT DOCUMENTATION 54 COMMISSIONING55 SUBMITTING FINAL RECORD DOCUMENTATION 58 APPENDICES59 PROJECT GUIDE | 5 A-1. Burnaby Campus Map 59 A-2. Building List, Names, Official Acronyms and Building Numbers 59 A-3. SFU Legal Map (2011) 61 A-4. Consultant Disbursements Form 62 A-5. Project Initiating Form 66 A-6. Minor Project Checklist 67 A-7. Major Project Checklist 69 B-1. Contractor Integral Work under General Requirements 70 B-2. SFU Burnaby Campus Construction Map 72 B-3. Storm Water Management Standards 77 B-4a. EH&S Safety Procedures-Construction Safety Handout 79 B-4b. EH&S Safety Procedures-Contractor Asbestos Information 81 B-4c. EH&S Safety Procedures-Prime Contractor Handout 82 C-1. Burnaby Campus Climate Data (2011) 84 C-2. BC Building Code Seismic Slope Regulation & Technical Guidance 85 C-3. Energy Standards 87 C-4. Reference Levels by Building Floors 88 C-5. SFU Space Guidelines 90 C-6. SFU Room ID Standards 95 C-7. Door Numbering and Labeling Requirements 99 C-8. Green Standard - Common Area 100 C-9. Green Standard - Offices 103 C-10. Green Standard - Wet Labs 104 6 | PROJECT GUIDE C-11. Green Standard - Washrooms 110 C-12. Burnaby Recycling Bin Location Map 113 C-13. SFU Mechanical Systems Design Checklist 114 C-14. 2011 Energy Efficiency Act 117 C-15. SFU Standard Pipe and Duct Labeling Requirements 119 C-16. Burnaby Campus Mechanical Standards 133 C-17. Interior & Exterior Lighting Fixture Standard Products 151 D-1a. SFU Labeling and Identification System - Equipment Types List 152 D-1b. SFU Labeling and Identification System - Electrical Equipment ID Forms 202 D-1c. SFU Labeling and Identification System - Mechanical Equipment ID Forms 206 D-2. Printing Request Form 220 D-3. Record Submittal Checklist 221 PROJECT GUIDE | Revisions & Updates Date Description 06/30/2010 Final Draft released to Committee for final comments 08/09/2010 Project Guide v.1.0 12/01/2011 Project Guide v.2.0 11/21/2014 Minor Revision Revision (Page and Section #) 0 Part A Disclaimer Simon Fraser University Facilities Services provides these standards and guidelines which are to be applied as required in your project but in no way is intended to override or remove responsibility of the Consultant or the Contractor to provide best practice and advise on the proper system design or application for a specific project. Notwithstanding the requirements of these Standards, the Contract and the specific requirements of the contractual Agreement takes precedence over these standards. Refer also to www.sfu.ca/fs for most up-to-date standards. 7 8 | PROJECT GUIDE ABOUT THIS GUIDE WELCOME Burnaby Campus is the main campus for Simon Fraser University (SFU) situated on top of Burnaby Mountain, The campus enjoys unique environmental advantages such as cooler temperatures, and natural forested areas surrounding the campus. Sharing the mountaintop is a thriving residential community called UniverCity development, which is managed by SFU Community Trust (SFUCT). SFU works in cooperation with SFUCT on many issues particularly related to site work and planning. The design principles for American campus urbanism are well articulated in an article by Stefanos Polyzoides of Moule & Polyzoides, Architects and Urbanists, in an article titled On Campus-Making in America *(Polyzoides, S. (n.d.)). We hope that this Guide will help guide you when initiating and carrying out a construction project on Burnaby campus. AUDIENCE This Guide outlines basic information and general requirements for Consultants and Contractors providing Design and/or Construction Services at SFU Burnaby Campus. The document is to be read in conjunction with other detailed requirements and specifications provided by Facilities from time to time, and will be linked to these documents as much as possible. Guidelines are not intended to override Construction Specifications or Construction Contract terms but are meant to inform Designers and Contractors that are unfamiliar with: • SFU’s Design and Construction practices and standard forms of Contract • Design and Construction approval processes • Building Standards unique to the Burnaby Campus The Guidelines will aid Departments/Users to avoid unnecessary delays, confusion and unplanned expenses, while protecting adjacent occupants from unnecessary noise, disruptions and inconvenience. The Guidelines should be read in conjunction with other standards and project specific information provided by Facilities Services (FS). In the event of any conflict between the Guidelines and more detailed specification section information relevant to individual Divisions, the conflicts should be raised with SFU’s Project Representative for clarification. * On Campus-Making in America. Retrieved from http://www.mparchitects.com/articles/campusmaking PROJECT GUIDE | 9 ACKNOWLEDGMENTS This Project Guide has been compiled by the Facilities Services Technical Standards Committee with representatives from Development, Operations and with input from Facilities Administration: Facilities Development: Larry Waddell, KC Jones, Phil McCloy, Elizabeth Starr, Bill Nelson, Wendy Lee (Committee Chair) Facilities Operations: Bohdan Kosteckyj, Ron Sue, Keith Horne, Dana Sundmark, Frank De Vita, John Briggs, Lawrence Reason Facilities Administration: Mark Beese, Gerry Lopez The Project Guide has been endorsed by Larry Waddell, Director of Development and by Sam Dahabieh, Director of Operations. Notwithstanding this, the Committee members each assumes the responsibility for ensuring accuracy of the requirements included in this Guide, and the Chair has the responsibility for the wording and compilation of the text. Despite the best of intentions, errors and misunderstandings may arise. The user is encouraged to notify the Committee through the Chair (e-mail: wmlee@sfu.ca). It is the intention of the Committee that this Guide will continue to be updated and improved annually and errors and omissions will be corrected. Special thanks to Sook Suh (e-mail: ssuh@sfu. ca) who was invaluable in web enabling the Guide, preparing graphics, layout and assistance with research . The most current Guide will be uploaded to the departmental web site at www.sfu.ca/fs. Sam Dahabieh Larry Waddell Director, Facilities Operations Director, Facilities Development 10 | PROJECT GUIDE PART A | PROJECT GUIDE | 11 PART A : GETTING A PROJECT STARTED SETTING THE CAMPUS CONTEXT Description Burnaby Campus opened in 1965 with 6 buildings (Academic Quadrangle, Convocation Mall, WAC Bennett Library, Shrum Science Chemistry, University Theatre, Chancellor’s Gymnasium). Currently, about 40 % of the buildings are over 30 years old. The campus is laid out based on a master plan design by architects Arthur Erickson and Geoff Massey. The original buildings were organized on an east- west axis and constructed of exposed cast in place concrete and glass. More recent building exteriors have also included wood accents and metal cladding, but exposed concrete continues to be the dominant architectural vocabulary, forming a harmonious architectural aesthetic across campus. There are currently over 60 buildings on Burnaby campus and approximately 346,000 SM (2014 space report). The campus site area within the Ring Road is 174 hectares (430 acres) (see Appendix A-1: Burnaby Campus Map or printable map at www.sfu.ca/fs/ Campus-Facility-Profiles/Campus-Maps.html ). Building List (2014) The complete building list, official building names (and acronyms) and building numbers are attached in Appendix A -2. Street Address The whole Burnaby campus has one street address: 8888 University Drive Burnaby, B.C. V5A 1S6 Canada Post Mail is centrally delivered to Central Stores in Facilities Services Building and re-directed by internal campus mail to the various departments on campus. Legal Description for SFU Burnaby Campus PID: 028-300-131 Note: Confirm Legal description with Project Representative for the specific property. Lot 1 District Lots 31, 101, 102, 141, 144, 147, 209, 210 and 211 Group 1 New Westminster Land District Plan BCP 45523 (See Appendix A-3 : SFU Legal Map 2011) Revised November 25, 2014 12 | PROJECT GUIDE | PART A Climate Data & Geotechnical Site information The Burnaby Mountain campus is in a distinctly more severe climate than the surrounding areas of Burnaby and the Lower Mainland. Greater amounts of snowfall and increased freeze/thaw cycles over the winter season can be expected. The following information is from the data published in the BC Building Code (2012) but any later version can be adapted and the more stringent requirements should be used. Location: Elevation: Snowfall: Hourly Wind Pressures: Seismic data: Burnaby Mountain, Longitude: 122°55’04.960” W, Latitude: 49°16’42.200” N 330 m (Average) January 2.5% design temp. -7 degrees January 1% design temp. -9 degrees C July 2.5% design dry temp. 25 degrees C July 2.5% design wet temp. 17 Degree Days 3100 (Below 18 degrees C) 15 Min. Rain, mm 10 mm One day Rain, 1/50, mm 150 mm 1850 mm Annual Rain 1.93 Moisture Index (MI) Annual Total Precipitation 1950 mm Drving Rain Wind Pressures, 160 Pa 1/5 Ground Snow Load Ss = 2.9 kPa Sr = 0.7 kPa Probability 1/10 0.36 kPa Probability 1/50 Sa (0.2) Sa (0.5) Sa (1.0) Sa (2.0) 0.47 kPa 0.93 0.63 0.32 0.17 Peak Ground Acceleration (PGA) 0.46 (See Appendix C-1 : Burnaby SFU Climate Data from Environment Canada, Appendix C-2A: BC Building Code Seismic Slope Regulation & Technical Guidance, and Appendix C-2B: Determining ASHRAE 90.1-2010 Climate Zones) Geotechnical Site Information: The soils and bedrock conditions, encountered within the boundaries of the Burnaby Mountain campus of Simon Fraser University can be described in general terms as relatively thin surficial granular materials, over Sandstone or Conglomerate bedrock. Revised November 25, 2014 PART A | PROJECT GUIDE | 13 The granular material is generally composed of loose to dense sands, to sand and gravel, to a silty sand and gravel containing coarser cobble and boulder sizes. The thickness of the surficial granular material may range from less than 1 meter, up to and greater than 2 to 3 meters. The silty sand and gravel is generally of glacial origin (hardpan), but may also be the result of weathering of the local bedrock. In totally undeveloped areas, an organic cover of forest litter or debris, and topsoil may be encountered to depths of 300 to 500 mm. Frequently, however, within developed areas, organic or mineral fills may be encountered to depths of 3 meters and greater. The surficial granular material is underlain by Sandstone and/or Conglomerate bedrock. The bedrock surface may be moderately to highly weathered to depths of up to 2 to 3 meters, with the Sandstone generally showing greater depths of weathering than the Conglomerate. Depending on the specific location, ground water may be encountered within a given excavation. However, seepage is generally encountered at the soil rock interface and can usually be controlled by conventional pumping. Excavation of the highly to moderately weathered rock can usually be achieved with the use of conventional, large capacity, track mounted excavators. Deeper excavations within the less weathered or fresh rock would required less conventional rock breaking equipment or blasting. Both the Surficial silty sand and gravel and the weathered zones of bedrock are highly susceptible to disturbance if exposed to water ponding and construction traffic. Same Geotechnical reports are available at Facilities Services that maybe helpful in design, cross-referencing and preliminary scope development. REGULATORY BODIES (DEVELOPMENT AND BUILDING PERMITS) The University Act and the Government of British Columbia SFU Is constituted under the Universities Act as an independent agency of the crown and operates under the authority of its own Board of Governors. Operating budgets and capital funds are provided by the Province of British Columbia. The Ministries responsible for the University are the Ministry of Advanced Education and Labour Development and the Ministry of Finance. The City of Burnaby Planning of Burnaby Campus follows the City of Burnaby’s Official Community Plan (OCP) and the City of Burnaby’s Preliminary Planning Approval (PPA) process (in a simplified version) is followed, including public meeting(s) held on the campus for the campus community on planning changes. The BC Building Code (latest edition) and Fire Code is applied on projects, including the requirements for Schedules from Registered Professionals as part of the permitting Revised November 25, 2014 14 | PROJECT GUIDE | PART A process.. Building Permits and all Trade Permits are required from the City of Burnaby. Contractors are responsible for obtaining all permits and approvals prior to the commencement of the work. The Contractor(s) shall provide a copy of the permit to the Facilities Services Representative prior to commencement of the work. Such permits include, but are not limited to: • City of Burnaby Building Permit (all work other than purely cosmetic or nonstructural/ non code-related work) • Health Department (where applicable) • Sprinkler permit (where applicable) • Plumbing permit • Electrical permit Evidence of applicable permits and approvals must be posted at the site, prior to the commencement of the work. Refer also to requirements in City of Burnaby Building Department web site for latest bulletins. The City of Burnaby and SFU enjoy a cooperative working relationship. Nevertheless it is difficult, over time, to ensure continuity of message and intent as regulations, practices and policies on both sides change. For continuity of message, clarity of intent and ensuring implementation of the long term vision, Facilities Services MUST accompany ALL consultants presenting documents or clarifying requirements with the City of Burnaby. Depending on the Project, it is typically preferred if all communication with Burnaby goes through Facilities. All meetings with Burnaby must be documented and minutes distributed to all parties in attendance. Previous commitments or undertakings (on SFU’s part) should be first reviewed with SFU’s Project representative. The City of Burnaby Building Inspector conducts field reviews for New Buildings and Major Improvements in existing buildings. SFU Departments Facilities Services Development Manager / Project representative has the responsibility for determining and retaining the Registered Professional(s) (i.e., architect, structural/ mechanical/ electrical engineer, commissioning authority, and/or other professionals) required for the design and execution of the Project. Apart from Facilities Services, a number of University Departments are often consulted for detailed requirements and approvals during the Design Development and Construction process, including: Information Technology Services (which includes data and communications and CaRS), Campus Security, and Environmental Health and Safety. Other agencies such as the Registrar’s Office and Student Services, and the Disability Resource Centre, etc. may also be consulted as project applicable. Revised November 25, 2014 PART A | PROJECT GUIDE | 15 SFU Policies SFU Policies that relate to projects are listed below. Refer to SFU web site for details and for latest updates. www.sfu.ca/policies.html • AD1-3 Traffic and Parking Regulations • AD1-4 Control of Keys and Access Cards • AD 1-9 Furniture • AD-13-1 Annual Capital Allowance Projects • AD13-2 Minor Capital Project Requests (total cost over $1500) • AD13-3 Work Orders (total cost under $1500) • GP 16 Non-Smoking Policy • GP 18 Human Rights Policy • GP 22 Fire Safety • GP 32 Environmental Management Policy • GP38 Sustainability Policy PROJECT DEVELOPMENT AND MANAGEMENT Development and Project Management All capital construction projects on Burnaby Campus are planned, budgeted and managed through Facilities Services, Development. Maintenance and energy projects are generally managed through the operations group. See Appendix A-4. Consultant Disbursements Form. Consultants CAPITAL PROJECTS Capital Projects were traditionally differentiated as major capital, Reweal and Renovation projects based on project budget (typically $1.5 M). However, requirements for Renewal & Renovation and/or major projects may apply to either/or both. RENEWAL AND RENOVATION PROJECTS Renewal and Renovation Projects Contracts typically (but not necessarily) have a Revised November 25, 2014 16 | PROJECT GUIDE | PART A Construction Value of up to $1.5 M and are funded by a variety of sources, such as through departmental funding, through annual capital budget allowances or provincial funded smaller projects. Department funded projects (Renovation & Minor porjects) : To expedite Project delivery, minimize Consultant costs (that are charged back to the Client Department) and to ensure institutional standards are maintained, the Departmental Renovations and Minor Projects Services section may design, tender, award and oversee projects and construction contracts with its internal staff of Architects, designers and engineers. See Appendix A-5 : Project Initiating Form. See Appendix A-6: Departmental Renovations and Minor Project Checklist. Departmental Renovation and Minor Projects typically use a Short Form Consultants Contract as well as a Short Form Construction Contract, SFU’s insurance and disbursement requirements. MAJOR CAPITAL PROJECTS Major Capital Projects generally have a value of greater than $1.5M and are directly funded by the province or through federal programs or through private donors or partnerships. Typically a Programmer is hired 6 months before a major capital Project commences to assist the User Group document their Requirements and to describe these requirements in a Building Program, defining functional needs and size. This Program then allows a Quantity Surveyor (Cost Consultant) hired independently from the Design Team, to establish the Project Budget for the planned new Facility. Major Projects (major renovations and new buildings)will typically have a full complement of consultants to design, tender and oversee the construction. Generally, the consultants are led by a prime consultant architect but may also include overseeing and coordination of other Consultants retained by the Owner. See Appendix A-7 : Major Project Checklist . Major capital projects funded by the Provincial Government are required to be certified LEED Gold (or equivalent rating system). To achieve this, the project team must integrate LEED rating criteria as early as possible in the design process to prepare a target scorecard, and to monitor the design to ensure these goals are met. PROCURING CONSULTANT SERVICES FOR MAJOR PROJECTS SFU follows AIT and TILMA requirements for open public tendering. For Consultant work over $50,000, SFU posts an RFP for Consulting Services on BC Bid. Revised November 25, 2014 PART A | PROJECT GUIDE | 17 CONSULTANT AGREEMENTS Typically, the Prime Consultant Agreement is executed under RAIC Document Six (2006) or most current version, with SFU Supplementary Conditions (refer to Appendix E-1). The SFU Short Form Consultant Contract may also be used in smaller projects. Although the project team is generally retained by the Prime Consultant/Architect, SFU may retain geotechnical consultants, Owner’s commissioning authority and other specialty consultants such as signage and furniture. Contractors Major Projects uses a variety of Construction Contracts and Project Delivery mechanisms. Most commonly, an Expression of Interest (EOI) or a Request for Proposal (RFP) is issued on BC Bid for Stipulated Sum or for Construction Management at Risk (CM at Risk) services. In CM at Risk contracts, the bid terms fix the Contractors overhead and profit and Division 1 costs. SFU may choose to convert this to a Stipulated Sum Contract after the sub-trades are tendered and awarded. SFU typically requires a 10% Bid Bond as well as a 50% Labour and Materials Bond and a 50% Performance Bond on the General Contractor. The standard form of contract is CCDC2 (2008) with SFU Supplemental General Conditions for CCDC2 2008. These Supplemental General Conditions outline SFU’s specific conditions including insurance, liability and dispute resolution. Pre-approved Contractors Facilities Services and Procurement Services are working to develop a list of preapproved contractors. Once in place, the intention is that the list will be reviewed and updated on an annual basis. Contact Facilities Services for more information. Considerations for Contractors interested in applying for Pre-qualification: • For Renewal and Renovation work, the Contractor must demonstrate its capacity and experience work in Institutional Projects / Occupied Buildings of similar size. • Due to its negotiated Non Affiliation Clause with the trade Unions forming the Poly Party, Minor Capital Projects under $120,000 will only use fully certified, qualified, union contractors and subcontractors. This requirement applies to all trades that are reasonably available from union shops. • Contractors must be able to qualify for Bonding if required by the contract. • All contractors must comply with all SFU Policies and SFU Construction rules and regulations and fully cooperate with Facilities Services, Campus Security and Environmental Health and Safety regulations. Revised November 25, 2014 18 | PROJECT GUIDE | PART A GETTING BASE DRAWINGS AND INFORMATION The following information is managed by Facilities Records and is available on request to Consultants working on projects. To request hard copy drawings or electronic files, please complete a Printing Request Form and contact Records Services. See Appendix D-2: Printing Request Form. [Note : All CAD files provided by SFU are provided for information and reference only, based on the best available data available at the time of transfer. Field verify the information as required prior to commencement of any work.] Available Drawing Information Details/Description Examples Information Listings Campus Maps and Site Plans Provide all campus information for the locations of buildings, department and infrastructure services. PDF, Illustrator & AutoCAD formats are available Campus Map/Directory Signage Map / Emergency Phone Map/ Wheelchair Access & Elevator Map/Construction Map/ Recycling Bin Location Map/ Open Space Map SFU Legal Map Provide the legal description of SFU SFU Burnaby Legal Map Burnaby lot. PDF and AutoCAD formats are available. Floor Plans / Key Plans Architectural key plans are available All buildings for each building. Key plans are related to a space inventory database in Archibus and include room numbers, building numbers and floor level. Each floor plan & key plans are available in AutoCAD and PDF format As- built/ Consultant Record drawings Provide as Built and construction drawings of major & minor building projects and renovations. All hardcopy & electronic drawings are organized by building number and division code. Available in PDF or TIF and AutoCAD format. Revised November 25, 2014 All buildings PART A | PROJECT GUIDE | 19 Other Record drawings Provide as-built and construction drawings of renovations. Hard copies are kept in flat files in Records area, digital files may be available in CAD and PDF. Minor project records are retained based on File Plan Retention Schedules In-house Technologists and consultants drawings for renovations of buildings post-construction Supplementary Campus Site Drawings Provide supplementary drawings & images based on the site map. PDF & AutoCAD are available Building map / Landscape / Land Survey / Topographic maps / Aerial photos Provide all campus underground services base on the site map. The utility maps are available in PDF & CAD format Central Heating/Compressed Air /Gas / Electrical / Fire hydrant / Sanitary Sewer / Storm Drain / Water Distribution. Utilities Maps Utility data is currently being converted to a GIS database and some GIS data may be available Reports Provide specialized information on physical assets: geotechnical information, facilities conditions, etc. Reports are stored in the central document management system (Docushare) as PDFs Project Specifications Provide building specs info provided Building specs and schedby consultants. Available in PDF on ules Docushare for some older buildings (scanned) and for all newer buildings. Hard copies may be available Geotechnical reports/ Condition assessment reports/ specialized remediation reports, etc. RECORDS MANAGEMENT SERVICES: A searchable Access database of SFU drawings by building name/number is available and can be accessed at the self-serve station in the Records area. Copying & plotting services of documents & drawings are free to SFU members and consultants. However, for large volume printing, the printing costs incurred by external printers will be charged back to the requester. For further request & information services from Records Department, please contact Irinel Filip at Irinel_Filip@sfu.ca or Sook Suh at ssuh@sfu.ca . Revised November 25, 2014 20 | PROJECT GUIDE PART B | PROJECT GUIDE | 21 PART B: DOING CONSTRUCTION WORK ON CAMPUS SCHEDULING OF WORK Hours of operation SFU’s normal hours of operation are from 8:00 a.m. until 4:30 p.m., Monday through Friday. Work requiring Facilities Services trade assistance should be scheduled between 8:30 a.m. to 4:00 p.m., bur are subject to negotiations from the Owner’s representative. Noisy work must be coordinated with SFU, and scheduled typically before 8:00 a.m. or after 6:00 p.m. Minimize impact on university events and activities The university operates year round and critical activities and events must not be disrupted. Facilities Services may require disruptive construction activities or noise be shut down on specified days such as Convocations (two times per year, typically beginning of October and the second week of June. Confirm with project coordinator), exams (for 2 weeks/ three times per year) and other public events that may occur from time to time. Research and experiments (often involving live organisms) run 24/7, 365 days a year and are NEVER shut down. Consideration must be given and planned for well in advance to ensure the environmental conditions required for this research is maintained during the project. Further details on scheduling of construction activities are provided below. Revised November 24, 2014 22 | PROJECT GUIDE | PART B Utility Shutdowns and Service interruptions Disruptions to existing services (electrical, data, heating, water) must be minimized and planned at least 2 weeks (10 working days) in advance. Any downtime must be kept to an absolute minimum. The request must include the specific date requested for the shut down, the likely duration and the Facilities back up required to ensure smooth shut down and start up. All major shutdowns must be shown clearly on the construction schedule. The number, duration and approximate timing of all shutdowns must be indicated on the construction schedule. These shutdowns must be coordinated through SFU’s Project Representative. SFU personnel will be on hand at the shutdowns as required. Facilities Services must be notified in advance of any work on the structural electrical, fire alarm, HVAC or plumbing systems. Campus Security must also be notified of any disruptions to the fire alarm system or areas the contractor is working in that require devices to be bagged. SITE OFFICE AND ADMINISTRATION General Conditions cover basic Contractor mobilization costs, including GC site office and servicing of the site during the work. An itemized list is attached in Appendix B-1: Contractor Integral Work under General Requirements. Contractual Liability coverage The User’s contractor(s) must show, prior to commencement of work, evidence that they are adequately and properly covered by insurance, according to the following terms: That the contractor carries a general liability policy containing a limit of at least. • $5,000,000 inclusive of bodily injury and property damage, with property damage written on an “occurrence basis” That the User’s General Liability Policy also contains: • Cross Liability Clause • Severability of Interest Clause • 30 days Notice of Cancellation to each Additional Named Insured Permits and Notices • Building permits must be posted on site • A list of sub-contractors, complete with company names, addresses, and telephone Revised November 24, 2014 PART B | PROJECT GUIDE | 23 numbers, must be provided to Facilities Services at commencement of work and a copy available on site • For Projects under $120,000 union sub-trades are required. Proof of Standing may be requested. Contractor(s) must comply with the requirements of the applicable Provincial Health Safety Act as well as SFU Environmental Health and Safety (EH&S) office. Site Office Drawings The Contractor must maintain a neat set of Issued for Construction drawings on site for mark up of changes and as-built information. A neat set of as-built mark up drawings, verified and initialled by the Contractor, must be provided at the end of the project, together with CAD Record drawings (see Appendix D-3: Requirements for Record Submittals). Contractor Parking Any vehicle owner who requires parking outside of the construction site must make arrangements with SFU Parking Services to obtain the correct parking permit, and the vehicles must then be parked in the appropriately designated areas. Deliveries All deliveries of materials and equipment must be sent directly to the construction site. SFU will not receive any items at their Central Stores operation. Washrooms Major projects shall provide their own washroom facilities. In minor projects, Contractor’s employees may use only existing building washrooms prearranged with the Project representative. TRAFFIC AND LOADING ACCESS Construction vehicle Access SFU Parking Services is responsible for monitoring traffic flow and parking on campus. Please note there is a 3.7 M. height restriction for access through the Rotunda/ Transportation Centre tunnel . Construction vehicles are NOT allowed to go through the Rotunda . See Appendix B-2 : Burnaby Campus Construction Map . Revised November 24, 2014 24 | PROJECT GUIDE | PART B Loading Area There are several Loading bay areas on Campus. Review with Facilities the allocated Contractors drop off areas. The time limit of 30 minutes is strictly enforced unless previously authorized by Campus Security. Use of existing building elevators Should a particular item be of such size or configuration that it is physically impossible to use the designated route or freight elevators, alternate arrangements must be reviewed with operations staff. Staging and Storage Contractor(s) are restricted to the enclosed construction premises for all work and storage of all construction materials, tools and equipment. ENVIRONMENTAL REQUIREMENTS Maintaining a clean site All trades MUST clean up after themselves and remove all excess materials from the job site. Construction Waste All contractors are expected to sort and recycle construction waste to meet Metro Vancouver Build smart standards. Drywall, metals, wood waste, cardboard, etc. must be recycled. As much as possible, construction waste is to be diverted from landfill. Packaging must be removed by the Supplier/Contractor and recycled. In major renewal and new buildings, contractors will be required to comply with LEED requirements for construction waste diversion including submitting a full Construction Waste Management Plan prior to starting work on site and making regular reporting to LEED compliance consultant. Absolutely no dumping at Facilities Services works yard is permitted without prior permission. Managing Site runoff and storm water For major projects, the Contractor should submit a storm water management plan for approval, including measures to divert soil erosion and storm water detention and retention strategies. Burnaby campus is a watershed for adjoining communities and every effort should be made to avoid polluting the creeks and waterways, including No Dumping (refer to Appendix B-3 : SFU Storm Water Management ). Revised November 24, 2014 PART B | PROJECT GUIDE | 25 For projects with earthworks, the Contractor must provide wheel-washing requirements within the Construction zone to avoid salt runoff into the waterways. JOB SITE SAFETY SFU Environmental Health and Safety and Work Safe BC Comply with all requirements of Work Safe BC and safety instructions from SFU Environmental Health and Safety (EH&S). During the construction period, the contractor(s) must keep operable fire extinguishers on the premises, as required by codes and by-laws, and shall be insured for any loss, whatsoever, of any of their materials. Contractor(s) must also keep adequate first aid facilities. Safety shoes must be worn at all times. A First Aid Kit must be made available to all workers on site (refer to Appendix B-4a-4c : EH &S Safety Procedures). SFU Health Services SFU has its own Health Services department which is staffed by registered doctors and nurses. This facility is available in the case of emergencies only. The contractor is responsible for meeting all of the Work Safe BC requirements with respect to first aid attendance, etc. Medical Emergencies A “Medical Emergencies Procedure” will be provided by the Development Manager/ Project Representative at the initiation of site work. SECURITY OF THE JOB SITE Construction site security Contractor(s) shall be fully responsible for securing the Construction Premises and protection of the User’s contents throughout the construction period. SFU Security is responsible for monitoring security throughout the existing buildings. The security for the construction site is the responsibility of the contractor, but SFU’s Security department must be kept informed of any unusual situations such as working at night or off hours. No security will be provided or compensation paid by SFU for materials or work stolen, lost, damaged or destroyed. Construction site access All access points to the construction site must be double-locked. This means that a lock Revised November 24, 2014 26 | PROJECT GUIDE | PART B supplied by the contractor and a lock supplied by SFU will be connected together so that both parties can have access to the area. WORK OUTSIDE OF THE CONSTRUCTION SITE Any work which is to be carried out outside of the Construction Site is to be approved by SFU’s Development /Project Representative prior to the work being carried out. This approval is to be requested in writing a minimum of 48 hours in advance (unless it relates to shutdowns of any of SFU’s utility systems, see above). The written request is to clearly indicate the extent of the area that the work will take place in, a schedule outlining the sequence of the work and a clear description of the extent of the work (see Appendix B-1: Contractor Integral Work under General Requirements). This relates to the parking of any delivery vehicles that will be in place for more than 10 minutes. Proper safety precautions must be in place prior to any work starting. As well, all routes for pedestrians and vehicles must be maintained or appropriately re-routed. Where required, the contractor must supply personnel to direct traffic. Any work which takes place in occupied areas must be clearly shown on the construction schedule as well as adequate notice given to SFU’s Project Representative. If this involves working outside of the normal SFU working hours, clearance from Parking and Security must also be obtained. PROTECTING EXISTING Protecting existing HVAC systems No work shall commence until arrangements have been made with the Facilities Services for protection of all base building mechanical equipment. If there is any dirt in the filters, or the heating system, it will be the Contractors responsibility to return them to their original state in accordance with the Facilities Service’s specifications. Maintaining access for equipment servicing Contractors must maintain access panels in drywall walls, ceiling and floor construction as necessary for SFU personnel access to services or equipment where it is required. The access panel should be sized to enable easy servicing of the equipment. Common areas Any damage caused to common areas of the building (elevators, hallways, floors, loading bay, entrances/exits, lobbies, etc.) will be repaired at the Contractor’s expense. Sticky mats will be placed inside and outside the work area. Revised November 24, 2014 PART B | PROJECT GUIDE | 27 Ceiling tiles If ceiling tiles must be moved to do the Work, they must be removed, piled and covered neatly to protect them from damage. Facilities Services is not responsible for supplying or replacing any ceiling tile or damage to T-bar. The General Contractor must inspect ceiling tile with the project representative before the start of the construction work. The General Contractor is responsible for the replacement of all ceiling tiles damaged during construction. Ceiling tile damaged during Construction must be repaired and, if necessary, replace with tile purchased from the Facilities Services’s stock. Blinds and window coverings Damage to roller shades will result in the replacement of the complete blind, at the Contractors expense. Poly must be used to seal off working areas to prevent dust migration. Poly must be used to seal off elevator doors to prevent dust from entering the elevator shaft. Surplus Light Fixtures Surplus fixtures must be delivered to Facilities Services in the location within the Building designated for storage of surplus items. Doing X-Ray for construction work on Campus X-rays of existing concrete slabs or walls may occasionally be required to determine if the area where a hole is planned to be cored for new piping or conduits is clear of electrical conduit and rebar buried in the concrete. X-rays must be performed by an agency certified by the Canadian Nuclear Safety Commission. By law they are required to secure an area for a radius of 50 feet from the center of the shot. No one is allowed in this area during the time the x-ray shot is made. The technicians must mark the 50 foot safety zone with signs and caution tape then check the area for people before making the shot. Anyone found in the area is required to move outside the 50 foot safety zone before the shot can be made. Personal are on hand while the shot is being made to ensure no one enters the area during the procedure. The actual X-ray takes on average 10 to 15 minutes depending on the thickness of the concrete. Adjacent departments should be notified. Anyone having materials sensitive to radiation exposure in their office or lab is required to have them removed from the 50 foot safety zone prior to the date and times scheduled for the x-ray procedure or have them safely stored in some protective manner. Work must be scheduled for early morning or evening to avoid as much disruption as possible. All concerns or questions should be directed to the SFU project representative. Revised November 24, 2014 28 | PROJECT GUIDE | PART B Call before you dig on Burnaby Campus SFU owns and maintains its own utilities infrastructure on campus. The utilities include water, sanitary sewer, storm sewer, electrical duct banks, street lighting, gas, hot water heating distribution mains, and fiber optic cables. Some roads are also designed as ground water recharge systems. Depending on the location, infrastructure may be owned by SFU, SFU Community Trust (SFUCT), City of Burnaby and private utility companies in the public and private road/trails/right of ways. It is critical to check with SFU Records in Facilities Services for utilities drawings and engineering information on SFU utilities http://www.sfu.ca/fs/Campus-Facility-Profiles/ Other Contacts: SFUCT utilities contact Jesse Galicz at galicz@univercity.ca and Dale Mikkelsen at mikkelsen@univercity.ca City of Burnaby utilities is online at BC One Call at http://www.bconecall.bc.ca/ OTHER RULES AND REGULATIONS No smoking on campus SFU campus is a no smoking zone and no smoking is permitted in any building, within 10 metres of any entrance or air intakes or in loading bays. Smoking is only allowed in the designated covered exterior smoking areas. Other Rules Contractor employees shall abide by all rules and regulations for SFU including the construction guidelines and any changes thereto that Facilities Services may make from time to time. Revised November 24, 2014 PART C | PROJECT GUIDE | 29 PART C: DESIGNING FOR BURNABY CAMPUS SUSTAINABILITY AND GREEN BUILDING STANDARDS figure C-1: Blusson Hall Courtyard In addition to LEED certification requirements for major capital projects, Facilities Services upholds these green building principles to be applied in designing projects: • Design and construct green building projects that meet the highest environmental standards as project budget allows • Select environmentally preferable products wherever feasible • Design to minimize waste (water, material and energy waste), using integrated design of systems to reduce life cycle costs • Optimize and manage water use The design team is encouraged to integrate these principles into the design processes from the beginning to maximize benefits of integrated design. See Appendix C-3: SFU Energy Standards. Revised November 24, 2014 30 | PROJECT GUIDE | PART C NAMING SYSTEMS ON CAMPUS Assigning Building Names The University Architect/Chief Facilities Officer, in consultation with the Board of Governors, President and Vice-Presidents can provide and approve official building names. At the same time, each building name is assigned a commonly used acronym and 3-digit building number. Obtain these from Records staff. Campus Reference Levels Every level of every building on campus is placed relative to a campus reference level that ranges from Level 00 (approximately 305 m) to Level 17 (about 370 m), representing the almost 70 m rise in elevation in the site. Consult with the Project Representative to designate the reference floor levels. See Appendix C-4 : SFU Building Floor Reference Level. Space Standards See Appendix C-5 : SFU Space Guidelines. Room Numbering Tip: Have room numbers assigned as soon as plans are fixed so that floor plans and drawings, door and equipment schedules and signage packages can all be referenced to the one set of room numbers from Send the request to ssuh@sfu.ca Building room numbering and floor level standards are critical to provide a consistent way finding identification system across campus. The same methodology is applied to both stand alone buildings and to interconnected buildings. To ensure standards are consistent, Records staff is responsible for assigning all room numbers. The following is provided for general guidance on basic principles applied: • The main building ground entry level is always designated as 1000 level, ascending by 1,000’s i.e. 1000 level, 2000 level, etc. • In a terraced building where grade access might occur at more than one level, the lowest grade access level is designated as the 1000 level • The first level below ground is 100 level and floors below this descending by 100’s i.e. 100 level, 00 level, 0 level. Exceptions: In service or maintenance buildings, parkades and open air or slab on grade structures, etc., the ground entry level is designated as 100 level, floor levels ascending by 100’s, i.e. 100 level, 200 level etc. • Each building floor level is also referenced back to a campus wide Reference level, so that every building on the campus has a reference level relative to the floors of adjacent buildings. This is a useful mechanism due to the terraced buildings on Burnaby Mountain. Revised November 24, 2014 PART C | PROJECT GUIDE | 31 • Consultants are not allowed to assign construction numbers to room floor plans. All construction drawings must incorporate the final, approved room numbers. In assigning the room numbers, Records staff will also automatically “reserve” the room numbers in Archibus, the university space inventory records. Do not assign (temporary) Project room numbers. See Appendix C-6: SFU Room ID Standards. Door Numbering Following Guidelines Appendix C-7 : Door Numbering and Labeling Requirements. DESIGNING FOR UNIVERSAL ACCESS This requirement applies to the design and construction of new buildings and renovation work on existing buildings on campus to make buildings fully accessible and usable by all the public, including, disabled persons. SFU’s long term strategic plan is to provide and maintain a primary east west circulation corridor at the 3000 level as a wheel chair accessible corridor across the campus. Design attention must be given to circulations paths from parking areas to building entrances, circulation routes between buildings, as well as circulation corridors within buildings. The many terraced levels on Burnaby campus can also pose unique circulation challenges for wheelchair users and special attention must be paid to the proximity of elevators and appropriate coordination of door hardware with security access controls along the travel path of wheelchair users. All Consultants must ensure that all design work (in both new and existing building projects) provides handicap accessible design as required by current codes, including but not limited to British Columbia Building Code and Master Municipal Construction Documents (MMCD). In addition, comply with any additional requirements over and above code, where directed by SFU project representative. It is also the responsibility of the primary consultant to incorporate design specifications that include way finding signage directing persons with disabilities to the accessible areas and features. All sign work is to comply with SFU Sign Standards as outlined elsewhere in this document. During the design phase, the Consultant should arrange with the Project representative to review access design specifications with SFU Director, Centre for Students with Disabilities. Revised November 24, 2014 32 | PROJECT GUIDE | PART C DESIGNING PUBLIC AREAS & SPECIFIC FUNCTIONAL SPACES Public Circulation and Study Areas Facilities Services manages all public spaces such as public corridors, atrium, lobbies, lounges and study spaces. Since campus buildings are often open 24/7, these public spaces are heavily used, and attention should be paid to designing durable, functional spaces that are well lit and designed appropriately. See Appendix C-8 : SFU Green standard - Common Area. figure C-2: Blusson Hall Corridor Offices See Appendix C-9: Green Standard - Offices Wet -Labs See Appendix C-10: Green Standard - Wet- Labs Link to Green Fume Hood web-site . Washrooms See Appendix C-11 Green Standard - Washrooms Revised November 24, 2014 PART C | PROJECT GUIDE | 33 Recycling Within interior spaces, waste receptacles and recycling containers are provided by Facilities Operations. Convenient Recycling Centers should be created for separating recyclables including mixed paper, returnable bottles and pop cans, and for other recyclables such as plastic containers, tin cans, etc. See Appendix C-12: Burnaby Campus Recycling Bin location Map_2010). The building loading dock is also the collection point for recyclables. Provision should be made for the containers for recycling materials which include cardboard, Styrofoam, etc. Consult with Facilities Waste Management for space arrangement and figure C-3: Central Stores Loading Bay requirements. Custodial Rooms Custodial rooms are required for every building, equipped with: • Slop sink: 3’-0” large on the floor, concrete or a durable fiberglass material with one temperature control tap, a faucet, and a hose connection. • Walls: Locate the slop sink in the corner with ceramic tile (or other completely water repellent material) on both walls out at least a foot past the edges of the slop sink. The backer board behind the ceramic tile is Hardy plank. Revised November 24, 2014 34 | PROJECT GUIDE | PART C • Flooring: Non slip vinyl with an abrasive strip embedded to prevent slipping. • Shelving: A minimum of five wall mounted shelves for storage of janitorial material and enough space on the floor to store both a janitors mop pail, a cleaners cart with cleaning supplies and a large garbage can. • Lighting: The lighting should be energy efficient and is auto on/off....controlled off door position indicator switch. • Electrical: Duplex outlets, no more than 6 m apart, are required in the corridors and the classrooms for vacuuming/floor washing machines. Do NOT put janitorial outlets on any circuits that are used for classrooms, a/v or data. SPECIFYING ARCHITECTURAL SYSTEMS Exterior Glazing Systems Aluminum frames on campus buildings are typically PPG Canada K61213ZX D600 EZX Dark Moss Green. The alternate is anodized aluminum. Ceilings (T-bar and drywall systems): The original campus buildings built in the 1960’s and 70 were imperial. The buildings after 1990 are metric. Specify matching system grids, and do not use soft conversions for dimensions. Ceilings in typical areas are a suspended T-bar system on a 610 x 1220 mm grid for ceiling tile and light fixtures (except for older buildings which are on an imperial 2’ x 4’ grid) Limit the use of inaccessible (drywall) ceilings because of the following: • There is difficulty in accessing sprinkler and electrical components above drywall ceiling for maintenance and future renovations. • It limits the flexibility of the occupancy of the space on the floor above regarding changes (i.e. HVAC and electrical). Access panels (600 x 600 mm. minimum) must be provided as required for access to electrical, mechanical and sprinkler. Plans must specify, where necessary, access panels to all valves, fire and balancing damper, VAV boxes (including isolation valves), sprinkler mains, clean-outs, telephone conduit, etc., in all G.W.B. ceilings and walls. This includes stubbed-out drainage, vent, and cold water pipes. Specifying Interior Doors Matching existing standards within a building is imperative to maintain the consistent aesthetic across the campus, and should be followed unless impractical, out of production or non-code complying. Revised November 24, 2014 PART C | PROJECT GUIDE | 35 Tip: As an alternative to the standard single door application and depending on the application and location, the Project Representative may approve the installation of a combination wood and glazed sidelight in wood frames, glass entry door, glass entry door and sidelight or double glass entry doors. Note that any of these alternatives will increase project cost to the department. Non-building standard doors may be used only if approved by Facilities Services. Glass entry door hardware must be ADA compliant and conform to the BC Building Code 2004 and SFU’s Hardware standards. Due to security failures use of aluminum frames is generally discouraged and should only be used in places approved by Facilities. When they are used, aluminum frames must be reinforced with a cross bar or steel, to prevent break-ins. All interior doors are solid core, and alternatives must be approved by both the department and the Project Representative. Door Hardware and Secure Access Campus Security is the authority to guide the determination of an appropriate security plan for the building and the appropriate level and type of security measures to apply. Campus Security must be consulted regarding all access control devices. The following general guidelines are provided: • Wherever possible, all exterior building entrance and exit doors must have a proximity card reader and be wired back to Campus Security for electronic lockdown. • Campus Security provides the Project (as a Project cost) with permanent Abloy cores and specifies the key schedule. The Contractor as part of the Project cost installs the permanent cores. All lock sets must be keyed to the building master system. • Locking hardware on required egress doors from a suite are required to comply with BCBC Article 3.3.1.12 and shall be operable with one hand and one releasing operation. If / where threat of break in is a concern, request to exit devices should be installed to send an alarm back to Campus Security. Keys & Cylinders Facilities Services through Campus Security will provide building standard cylinders and two keys for each building standard demising door which must be keyed to the Building master system. Construction cores are provided by the GC in Major Projects. Lockable interior door(s) must have the lock(s) key-coded to the Building master-key system, for maintenance and emergency access. Any ‘exception’ requiring special or high security locking must have the approval of Facilities Operations to ensure janitorial and/or emergency access are provided as required. Standard specification is for Permanent Schlage lock sets (installed by General Contractor) with Abloy keyways (installed by the university). Door numbering is done early in the project and alphanumeric door tags related to the room numbers are assigned at that time. Door tags are installed by the project and coordinated with Campus security. All requests for keys should go through Campus Security, who will require written authorization and a deposit from the User. All doors are required to be on the building Revised November 24, 2014 36 | PROJECT GUIDE | PART C standard key system. User Individual Access Control / Security Systems Campus Security must be notified if any ‘individual security system’ is being contemplated by a Departmental office. In general, the Burnaby Campus has an open door 24/7 policy and corridors are treated as streets, allowing access through to a variety of Departments. Access control on corridors is not generally encouraged and will only be granted on an exceptional basis. If requested, the Campus standard security card access system can be extended to the Departmental User entry door at the User’s expense. The installation must include tying into the Building fire alarm system so the lock will release upon a fire alarm signal. Refer to Sentence 3.4.6.15(4) of the BC Building Code 1998 regarding releasing requirements for the electromagnetic locking devices on exit doors. Campus Security and Facilities Services must ensure verification that the installation has been tested and operates correctly. Note that electromagnetic locking devices on exit doors may have been provided on the buildings on an equivalency basis. Interior Finish on Exterior Walls The interior finish on exterior walls 5/8” or more shall be drywall with a paint finish. Contractors shall not fix to or puncture the exterior drywall membrane for the installation of partitions, furniture, electrical outlets, etc. Demising Partitions (between Departments and as designated) As a standard, demising partitions to delineate between Departmental areas must be full height and typically 64 mm steel studs, with 64 mm batt insulation fill (where required) and 16 mm drywall each side; taped, up to the slab above, as a minimum on one side. Apply acoustic sealant along the perimeter. Inter office security is paramount in faculty offices and the demising walls should continue to underside of the slab, not stop at the suspended ceiling. Corridors and/ or any paint in common areas is generally required to be SFU white. Deviations may be allowed in paint colour finishes on the interior side of the demising partitions, subject to Facilities Services’ approval. Costs are estimated not only to paint initially, but to repaint, should the room occupant and/or department is moved. Confirm if fire fighting provisions pertaining to distances for access by a fire hose might impact the requirement for fire separations. Contractor should confirm dimensions on site when abutting existing walls. Gypsum board surfaces are generally NOT to receive vinyl, fabric, or other wall covering. Partition walls should be aligned with window mullions, but should not be attached to the mullion. Care should be taken in the connection design to permit removal of interior partitions without damaging the mullions. Revised November 24, 2014 PART C | PROJECT GUIDE | 37 Sound Transmission The following methods are acceptable to reduce sound transmission between offices: • Additional layers of G.W.B. applied to partitions above and below ceiling. • Acoustic wall covering applied on Departmental side of area. • Studs increased to 89 mm with 89 mm acoustic batt insulation. • Lead sheath laminated between G.W.B. and extended above ceiling. Flooring Typically resilient flooring is either sheet vinyl with heat welded seams, linoleum heat welded sheet goods or tiles such as rubber. Bases are typically 4” black rubber. Resilient flooring (including seams) should be sealed. Flooring with raised profiles are discouraged at this time. Tip: Furniture and case goods are provided as part of major capital projects. Minor capital projects do not fund furniture ; these must be paid for by the department. To assist users in maintaining and keeping up the furniture on campus, Facilities Services maintains a Furniture Access database of furnishings acquired in major projects. Generally, purchasing agreements negotiated during tender will include buying agreements for some of the specified products for fixed periods of time following completion of the project. Departments can take advantage of this preferred pricing for procurement of small quantities not originally supplied with the project. Contact the Project Representative or Procurement Buyer for details. Polished concrete floors are a good option for corridors and public circulation areas for maintenance as well as a environmentally preferred choice. Polished concrete floors must have a 2” topping, poured separately from the structural slab. Carpet is generally discouraged and will be provided only if funded by the Department. This is due to higher cost to replace, maintain and clean carpets and the higher custodial costs which may be charged back to the Department. Where carpet is requested, only modular carpet tile should be specified. Where carpet tiles are to be installed, use a premium grade, low VOC (solvent free) acrylic waterproof release type adhesive as recommended by carpet tile manufacturers. The User shall tape all raised floor joints with painters tape prior to carpet installation. Finished flooring in office and classroom areas should be installed before the walls are installed, allowing for ease of removal and adjustment back to the original configuration. Furniture and Case Goods Systems furniture is generally discouraged because of their high initial capital cost, the increased maintenance costs to stock parts and replace broken components and the costs to reorganize new layouts. Many of the case goods for classrooms and offices are supplied by Calstone which has a reliable track record for institutional quality furnishings. Consultants and users are encouraged to consider specifying these products as Calstone has a take back policy that returns goods rendered surplus due to reconfiguration of space. The products are returned to the plant for refurnishing and reassembly into new product. Millwork For major projects such as new buildings and major renovations, new millwork should Revised November 24, 2014 38 | PROJECT GUIDE | PART C be specified as Custom or Premium Grade, as outlined in the AWMAC (Architectural Woodwork Manufacturers Association of Canada) Standards Manual, complete with a two year AWMAC Guarantee on all millwork and wood doors and frames. In minor projects and small renovations, often involving existing millwork to be modified, this requirement does not apply. Blinds and Sun Control Tip: Blinds can help keep heat in (in winter) and help to save energy. Departments and individual Users are requested to close the blinds at the end of the day Standard window coverings on the campus are roller shade blinds which should be provided on all exterior windows. The roller shade blinds typically are not to be removed or altered by Contractors or its sub contractor(s). Departmental generated projects must protect the blinds with plastic bags, as part of their projects expense, during renovations. If existing blinds need to be taken down to install partition walls, the cost is borne by the project. Departmental and Room Signage SIGNAGE PROVIDED BY THE PROJECT: • Standard elevator lobby directional signage • Departmental entrance door SIGNAGE PROVIDED BY THE DEPARTMENT/USER (COORDINATED BY FACILITIES): • Departmental/ User ID signage on the main floor lobby directory. Irrespective of who funds the signage, all Departmental signage must be approved by Facilities Services before installation. Departmental signage requests can be made online by completing a sign request form to Facilities Operations. For departmental funded signage, it is recommended that the Department provides drawings of the proposed signage to the Facilities Services representative before fabrication begins. SFU Burnaby signage standards are currently being updated with the new SFU logo. Departments are strongly discouraged from using scotch tape etc to tape paper signs to the walls and doors as they destroy the wall surface and ultimately, detract from the overall appearance. Refer to Appendix C-18: SFU Interior Signage Guidelines Room and Door Numbering/Labeling For rooms within a larger room and which are only accessible through the larger room, the interior rooms have a decimal designation off the main room number (e.g. 103.1). Room doors should have the same number as the room (e.g. 103A door for 103 room). For rooms with more than one entry door, add a unique alpha reference (e.g. 103A, 103B, etc.) for each door. Revised November 24, 2014 PART C | PROJECT GUIDE | 39 Every Project must provide and install lamacoid labels designating the door number on every door supplied on the project. The label is to be applied on the upper hinge side of the door. Consult with the Project Representative on labelling standards and supplier . See Appendix C-7 : Door Numbering & Labeling Requirements. Specifying Elevator and Loading Dock Equipment ELEVATOR SPECIFICATIONS There are about 65 elevators of various types and manufacturers on campus. The range of elevators include hydraulic and traction type, accessible and freight elevators. The majority of these units are maintained by Kone under the current maintenance contract. There are 7 elevators in the Residence buildings that are currently maintained by Otis. There are projects budgeted each year to upgrade elevators, as well as aesthetic improvements. There are loading docks and receiving areas at most of the academic buildings on campus. The main receiving point on campus for deliveries is Central Stores in the Facilities Services Building. SPECIFYING HEATING AND VENTILATION SYSTEMS Specifying systems to be compatible and consistent with existing mechanical systems is essential. Systems must integrate high efficiency performance standards to save energy for the University wherever possible. Components must be of industrial quality and designed and installed to facilitate access for maintenance. Refer to Appendix C-13: SFU Mechanical systems Design Checklist See Appendix C-14: 2011 Energy Efficiency Act for standard regulation. Central Heating and Ventilation system The majority of the campus is heated from 5 gas fired boilers in the Heating Plant centrally located in the basement of the Library building. There are 4 main campus heating zones. The heating mains are typically not buried underground but run through the interconnected buildings, parking garages and service tunnels. Recent progress has been made to provide sub-meters at each building entry point to better understand the energy consumption on campus and contain rising energy costs. Individual buildings are serviced by Air Handling Units (AHU’s) to distribute conditioned air throughout the space. Air Handling Systems generally control the temperature of the spaces and the amount of fresh air make up required. These functions are generally controlled through the Building Automation Systems or DDC system. Revised November 24, 2014 40 | PROJECT GUIDE | PART C Piping All heating, chilling and domestic water lines must be insulated regardless of the length of run and must be labelled to SFU standard pipe and duct labelling requirements See Appendix C-15: SFU Standard Pipe and Duct Labeling Requirements. Cooling No cooling is generally required or provided for general use spaces; cooling is restricted to spaces with specific user requirements e.g. for controlled environmental needs to support research and equipment. This no-cooling policy reduces energy consumption and energy costs of the university by taking advantage of the cooler temperatures of the mountaintop campus to maintain temperatures at a comfortable level. DDC Temperature Control The temperature control or Direct Digital Control (DDC) system is part of the Building Management Control System across campus. The DDC system has been installed to gain more efficient control of heating, ventilation and air-conditioning (HVAC) systems. Wall mounted temperature sensors have been located on each floor and all sensors, controllers and actuators are electronic and tie directly into the control system for quick response and reporting. The control system is monitored at Facilities Services during normal hours and at Campus Security offices during off hours. figure C-4: DDC Control System Revised November 24, 2014 PART C | PROJECT GUIDE | 41 GENERAL All DDC based controls shall be interfaced with the existing DDC Andover and/or Delta control systems. Andover system shall be installed and/or installations supervised by Houle Electric Ltd. Delta system shall be installed and/or installations supervised by ESC Controls Ltd. The company present service contracts guaranty the system operation. All installed control equipment shall be of the same manufacturers with the latest technology updates and backward comparable capabilities. All control software shall have existing/comparable control algorithms and logic that can be easily custom built or adjusted by users. All modifications of the existing DDC controls and new controls shall be updated with the latest available technologies and revise existing graphics to include changes. All new control points shall be connected to the closest existing or new Infinity Andover or Delta control panels if spare points are available. When existing panels are full, then new Infinity Andover or Delta control panels with minimum 8 input/ output points shall be installed. New panels shall be capable of interfacing with existing systems. Any new panels shall be located in the mechanical rooms. All required up-grade of existing controls graphical displays and all related cost shall be included in the project scope of work. COMMISSIONING Commissioning shall meet ASHRAE Commissioning standards. For new buildings or major renovations, commissioning shall comply to LEED requirements. The Controls Contractor shall assist Electrical Contractor during the variable frequency drive start-ups and testing. Controls Contractor shall assist Balancing Contractor during the balancing, start-ups and testing of mechanical systems. See Appendix C-16 : Burnaby Campus Mechanical Standards. DESIGNING WATER, SANITARY AND STORM SYSTEMS Water Tower The City of Burnaby supplies the Water Tower which acts as the reservoir to provide domestic water as well as water provisions for fire fighting for campus buildings. From the Water Tower, water is distributed to campus buildings and is limited to a constant Revised November 24, 2014 42 | PROJECT GUIDE | PART C pressure of about 80 m(68-110 psi). Water, Sanitary and storm systems Domestic water, sanitary and storm systems are connected to the City of Burnaby services. Back flow protection is provided on the domestic water service. Facilities Services is a certified Water Purveyor for the campus and does regular water quality testing of the potable water supplied on campus. Refer to Appendix C- 16 : Burnaby Campus Mechanical Standards. Specifying Plumbing Systems Connection points for water, ventilation and sanitary stacks are to be centralized in building core service areas. Departmental renovations affecting plumbing should always be coordinated through Facilities Services to ensure that system compatibility is maintained. Water supply lines to User facilities shall be tied into existing valves located in the Building core service areas. Separate isolation valves are to be provided for each User premises. Hot and cold water lines must be insulated with preformed fiberglass insulation. Plumbing fixtures for washrooms and shower stalls must be low flow type to conserve water. SPECIFYING FIRE PROTECTION SYSTEMS The buildings pre 1990 are generally not-sprinkled. Facilities Services is working to increase the number of sprinkled buildings on campus. SPECIFYING ELECTRICAL SYSTEMS (FIRE ALARM, POWER AND LIGHTING) Fire Alarm Systems SFU is equipped with Simplex and Honeywell Fire Alarm Systems. Each building has a standalone single stage addressable fire detection and alarm system. The fire system panels are generally either Honeywell CLS 3000, FS 20, FS 90 and Simplex 4100 models. The annunciator panel is situated at each building entrance. All Honeywell panels are networked together to the ebi front end monitored by security. Revised November 24, 2014 PART C | PROJECT GUIDE | 43 The Simplex panels are similarly monitored by a separate head end at Campus Security. Some buildings are sprinkled, most are not. Gas detection systems exist in some labs, the boiler plant and in cafeteria kitchens. Honeywell currently holds the contract to perform annual testing services on the Honeywell and Simplex fire systems. Facilities electricians perform the monthly tests and the end device testing for the annual verification. Honeywell reviews this testing and signs off, noting any deficiencies. Any emergency maintenance or repair on either system requires a call out to Honeywell or Simplex. Power Distribution System - High Voltage The main incoming electrical service is dual 64 kV fed overhead up the east side of Burnaby Mountain to a main substation. Two 20 mVA transformers step this down to 12 kV. Three sets of dual 12 kV underground feeders run from the substation to three receiving substations (Transportation Centre, Saywell Hall and TASC1). From there the 12 kV main and transfer feeder daisy chain from building to building using junction boxes to tap off. Each building has a 12 kV substation fed from the main and transfer feeder through load breaks and 12 kV main breakers. Most building substations use EPE supplied equipment so the architecture and equipment is standardized across the campus. Over time, most of the original 12 kV oil breakers have been upgraded to more reliable vacuum breakers. The step down transformers are cast coil, a longer lifetime variation of the dry type units. Transformers mostly step down to 480 Volts which is the standard building distribution level. There is virtually no 347/ 600 V distribution at SFU Burnaby. Some transformers step down to 120/ 208 V directly. There is a capital plan to pro-actively replace substation transformers in the 6 or 7 oldest buildings with new units due to the fact that they exceed their rated lifetime. Power Distribution System- Low Voltage From 480 V, buildings use smaller distribution transformers ranging from 30 kVA to 225 kVA to convert to 208 V. These are gradually being replaced with more energy efficient harmonics mitigating units as they reach end of life. There is a capital plan to replace the bus and breakers in large 480 V and 208 V panel boards in the oldest buildings, as these components have reached end of life. The 480 V panels have recently been scanned with infrared to find overheating points. The report listed deficiencies which are being rectified by electrical staff. The 208 V panels have not been infrared scanned, but will soon have PM routines applied to them. Due to the architecture of many of the buildings there is a significant amount of surface mounted lighting and electrical components on concrete. There is very little raised floor area except for data centre floors. All power wiring must be in conduit with the exception of drops to luminaires. The length of BX cable in the ceiling space per drop is not to exceed 10 feet. Where Revised November 24, 2014 44 | PROJECT GUIDE | PART C aesthetics of running surface mounted power is important, Wire mold (not panduit) shall be installed rather than conduit. Where there are visible junction boxes recessed in concrete, they should have a decorative cover, not a galvanized metal cover. Emergency Power Most buildings have a dedicated standby emergency generator that serves the life safety and other power requirements of the facility. The generator may be either 480 V or 208 V and range from 25 kW to 1000 kW. They feed the emergency load through one or more transfer switches. Generators are tested monthly on load, and annually using a dummy load. There is about 7000 kW of diesel generator capacity over 19 units. Average loading levels on these units is about 50 %. Some generators only serve life safety (fire system, emergency lighting) and others serve elevators, lab equipment etc as well. A few generators serve more than one building. Three Residence buildings have no generator backup, McTaggart Cowan, Hamilton Hall and the Townhouses. Generators are designed to start automatically and power the load within a minute of a power outage. Lighting- Interior (Refer to Appendix C-17: Interior Light Fixture Standard Products) The following is a minimum standard base building lighting standard. The User’s lighting layout shall be reviewed and approved by the Facilities Services’ electrical consultant. Building standard office/ classroom floor light fixture is a recessed fluorescent 2X2 fixture with one electronic 120/ 277 V ballast per fixture. Preferred fixture for this application is the Ledalite Pure FX line. Basic design lighting level will be an average minimum of 50 foot candles at desk level on an open floor basis. figure C-5: Interior Lighting in TASC 1 All recessed or suspended fluorescent light fixtures must be seismically restrained. Most base building fixtures are connected to a low voltage lighting control system. Some of the older buildings use GE relay panels, others use Douglas panels. A few buildings have no low voltage control. One renewed building is using a new “Encilium” lighting control system that does not use relays, but networked control devices on each fixture. Existing building 4 foot fluorescent fixtures are lamped with 2 x 28 Watt - T8, 3500 K, 85-87 CRI lamps. Most buildings use T8 fixtures, but several newer buildings have T5 fluorescent lamp systems. Revised November 24, 2014 PART C | PROJECT GUIDE | 45 There are a large number of compact fluorescent recessed and surface mount fixtures, particularly in public areas. Most mercury vapour fixtures have been replaced with newer type lamp sources. There is minimal incandescent used on campus with the notable exception of lecture theatres. The perceived requirement to use dimmable lamps has hindered the replacement of these incandescent with a more efficient alternative. There is much research underway to find a more efficient dimmable light source for lecture theatres, art galleries and display areas. Lighting – Exterior (Refer to Appendix C- 17 : Exterior Light Fixture Standard Products) Until recently, most street, parking lot and walkway lighting used pole mounted high pressure sodium and metal halide fixtures. Much of the system is fed from 277 and 480 V circuits, controlled by time clocks in various electrical rooms. This plant is at an age where there is significant maintenance to keep fixtures operational. Some fixtures are in poor condition, and many did not meet the “Dark Sky” requirements. Over the last few years there has been an initiative to gradually replace the oldest poles/ fixtures and lighting bollards with new technology LED fixtures. Some streets and walkways have been converted to LED with great success, improving aesthetics as well as safety and security at night. Some parkade fixtures have been converted to LED fixtures, and there are plans to complete the conversion in future. Parking lots have not yet been upgraded to LED, but several areas are being tested with new fixtures on existing poles. Some street sections that were not previously illuminated have had new poles and fixtures installed. Wall mounted high pressure sodium fixtures on building perimeters are gradually being replaced with compact fluorescent wall pack fixtures. figure C-6. RUUD / BETA Exterior Lighting Fixture Revised November 24, 2014 46 | PROJECT GUIDE | PART C Lighting – Controls Most buildings with GE or Douglas systems were standalone, with no remote monitoring or control. The policy now is to interface these lighting control systems to the building DDC system. This allows remote monitoring and control of lighting zones from one point. Sweep off schedules for evenings and weekends are applied to these buildings. As well, touch screen light control points are being trialed as an alternative to central switches. Buildings without central low voltage lighting control, such as the Academic Quad require a different solution. Concourse 3000 level lights have had no control except at the circuit breaker. These breakers are being replaced with motorized type that can be controlled remotely through connection to the DDC system. There have been recent projects to greatly increase the number of occupancy sensors controlling lighting in offices, classrooms, washrooms and other spaces. There will be more application of occupancy sensors in the near future. Photocell sensors have not been widely used to control lighting in areas that have a large daylight component. Gradually these lighting zones will be upgraded to day lighting control. Outdoor lighting is controlled by individual time clocks in various electrical rooms, with the inevitable problems in adjusting schedules. A wireless clock system is proposed to replace wired clocks on campus with wireless equivalents. The radio transmitter that would sync the clocks could also control wireless relays, which could replace the individual time clocks. Central control of outdoor lighting circuits would be possible for the first time. Plenums All exposed wiring located in a supply or return air plenum is required to have a FT-4 rating or enclosed in a noncombustible raceway (conduit). Other requirements for plenum spaces must comply with Article 3.6.4.3 of the BC Building Code 1998. Heating, ventilation and air-conditioning (HVAC) and plumbing specifications SPECIFYING DATA AND TELECOMMUNICATION SYSTEMS Consult with Information Technology (IT) Services on specific requirements. Network Cables and Wires Any cables and wires should be installed and secured in an orderly, logical manner. Neither exposed wires nor exposed BX are allowed. All exposed wiring must be run in conduit, perpendicular and parallel to walls and ceilings. Routes of any exposed conduit, particularity in public corridors, must be reviewed and approved by the Owner’s Representative prior to proceeding with the installation. All possible measures should be taken to avoid ever exposing conduit in a public area. Revised November 24, 2014 PART C | PROJECT GUIDE | 47 Telephone/Communications Departments/ Users are required to make arrangements directly with Information Technology (IT) Services for supply and installation of their voice and data systems. Plenum approved cable must be used when a conduit system is not installed. Revised November 24, 2014 48 | PROJECT GUIDE | PART D Revised November 24, 2014 PART D | PROJECT GUIDE | 49 PART D: PROJECT DOCUMENTATION AND EXECUTION OWNER’S (SFU) ROLE AND CONSULTANT TEAM Facilities Development will only engage qualified Designers and Engineers for structural, architectural, mechanical (heating ventilation air-conditioning), fire protection and electrical designs for work on the Burnaby Campus. The Consultant’s services includes inspection of construction and consultation on problems arising during construction. Changes to the Contract must be approved by the various Consultants before submitting the proposed Change Order to SFU’s Owner’s Representative/Project Representative. Only SFU can approve an equivalent or alternate product or approve a Change Order. On Projects where an Architect is the Prime Consultant, they are required to be the Payment Certifier. The Consultants and Contractors may not make changes without the above approvals. Designers and Consultants shall prepare drawings for acceptance and written approval and sign-off by the Facilities Services Project Representative. Design Consultants shall familiarize themselves with all relevant regulations applicable to the design, construction, use of material, and operations of the Premises, including the B.C. Building Code, the amended National Building Code and Occupational Environmental Regulations. The design of the improvements must comply with these and other relevant regulations. SOURCES OF INFORMATION Further information can be obtained from Facilities Services’ Project Representative, Facilities Services’ Record Services and web site (www.sfu.ca/fs), Information Technology (IT) Services, Campus Security and Environmental Health and Safety. It is the responsibility of the Consultants to verify site conditions and to obtain the relevant building code information required. DESIGN INTERFACE WITH BASE BUILDING (for Renovation Projects) Advise Facilities Services as soon as possible, and in writing, of any changes contemplated changes affecting the base building systems. These changes may impact Revised November 24, 2014 50 | PROJECT GUIDE | PART D air distribution and balancing, lighting controls, exiting, etc. of the building systems. Drilling of holes in the aluminum window frames is not permitted. Maintain safety clearances to comply with building codes and city regulations, with respect to access to Fire Department valve cabinets. PUBLIC REGULATORY REQUIREMENTS Drawings and specifications must comply with applicable building codes, City of Burnaby by-laws, and statutes. COMMENCEMENT OF RENOVATION WORK All drawings for renovation work on campus must be reviewed and approved by Facilities Services. Facilities Services Owner’s Representatives will provide guidance or advice to Designers, Contractors and Users. Approval to proceed with construction will not be given until all information and engineering drawings and necessary permits are obtained. The steps to be followed prior to construction start include: • Site visit and verification of design information • Concept Plan Approval to confirm Building Code compliance • The User’s final working drawings shall have been approved by the Facilities Services. • The Consultants shall have obtained all necessary approvals and permits from all regulatory bodies having jurisdiction over Improvement work and evidence of all such approval and permits shall be provided to the Facilities Services. • Contractor and sub-contractors working on Projects under $120,000 shall be fully qualified and union members in good standing. • The Contractor shall furnish proof of insurance as required by Facilities Services in the format approved by Facilities Services and SFU’ Risk Manager. DOCUMENTING THE PROJECT: DRAWING AND SPECIFICATIONS Architects/Designers As/if required, Facilities will engage a Registered Professional to prepare drawings which are necessary for the construction of the Improvements. Consultants shall inform themselves regarding By-law and code requirements before Revised November 24, 2014 PART D | PROJECT GUIDE | 51 preparing drawings. By giving approval to such plans, Facilities Services does not waive the Consultants responsibility to ensure that any and all Improvements meet building standards with respect to design and/or construction. Preparing documents to meet Departmental standards The detailed requirements below are primarily listed for minor projects such as departmental renovations. Major projects have extensive documentation requirements that will be reviewed with the Owner’s Representative. Standard Drawing Requirements • Standard sheet size: ARCH D 24” x 36” (in major projects, drawing size as reqd.) • Standard Title Block Information • Building Name, floor and room numbers as applicable • Project Name and Number • Sheet Number • Drawing File Number • Revision History – revision number and date • Drawing Phase (IFT, IFC, Records, etc.) • Consultant Information Drawings and specifications are required to be sufficient in scope and detail to fully depict the proposed Improvements and their relationship to the Base Building construction. Drawing Information Drawings shall consist of at least the following (as a minimum): • Floor Plan (1:100 scale minimum) • Show the Premises in relation to the corridors, stairs, fire extinguisher cabinets, partition, doors, etc. as well as all built-in furniture and fixtures. • Reflected Ceiling Plan (1:100 scale minimum) • Show partition layout, lights, sprinklers, etc., including modifications proposed to the Base Building systems. • Sections at 1:50 to 1:20, indicate partition details, doors, etc. Revised November 24, 2014 52 | PROJECT GUIDE | PART D • Room Finish, Door and Hardware Schedule, indicate all elements including keying which must be to building standard. • Mechanical Plans • Electrical Plans • Telephone, Data and Power Outlet Plan at 1:100 scale (minimum), indicate with dimensions, location of all telephone, data and power outlets. Specifications Detailed specifications are required, naming the manufacturers, colours, dimensions, construction methods, schedules, etc. Specifications should follow Master Format 2004. Specification volumes double sided spiral bound. Room Finish, Door and Hardware Schedules COMPLETE DETAILS SFU Locksmith will specify key locksets with reference to building’s master system. SFU will provide the room numbers for all the rooms on a set of drawings. This typically occurs during Design Development as soon as the wall locations are confirmed. No construction numbers are allowed on any drawings. SFU has very specific hardware standards (Attached in Appendix E-2A, E-2B ). No deviation from these standards is allowed without permission in writing from both FS and Campus Security. Telephone, Communications and Security devices Plan (1:100 scale minimum) SFU requires the low voltage consultant to be a firm that specializes in data, voice and security. Ideally this firm is independent from the electrical consultant firm. The electrical consultant provides the infrastructure (conduit and cabling) for all the low voltage wiring. The IT drawings indicate all the locations of all telephone, communications and security devises with dimensions and special computer and communications equipment noted. DOCUMENTING MECHANICAL PLANS AND CONTROLS For renovations, Indicate changes to the Base Building systems and include appropriate specifications. Revised November 24, 2014 PART D | PROJECT GUIDE | 53 Final Control Diagrams Provide before acceptance in both hard and soft copy. Show: • Changes to contract documents as well as addenda and contract extras • Changes to interface wiring • Major routing of conduit • Signal levels, set-points, reset curves, schedules • Where possible, bind with specified Operating and Maintenance Manuals • Provide listing of alarm messages. • Provide soft copy of updated drawings on system and soft copy back up. • Provide 1 non fading “as built” copy showing control and/or adjustment procedures. Seal in plastic laminate in rigid metal bound loose leaf. OPERATIONS & MAINTENANCE MANUALS General O&M Manuals (both hard and soft copy) to be custom designed and contain material pertinent to project only, and to provide full and complete coverage of subjects referred to in controls section. • Provide 2 soft copies and 2 hard copies in hard back, 3-post hard covered binders. • Binders to be 2/3 maximum full • Provide index to full volume in each binder. • Identify contents of each manual on cover and spine. • Include names, addresses, telephone numbers of each sub contractor having installed equipment, local representative for each item of equipment, each system. • Provide Table of Contents in each manual. Assemble each manual to conform to Table of Contents with tab sheets placed before instructions covering subject. • Furnish 1 complete set of hard and soft copies prior to system or equipment tests. Furnish remainder upon acceptance. • Include complete coverage in concise language readily understood by operating personnel using common terminology of functional and operational requirements of system. Do not presume knowledge of computers, electronics or in depth control theory include copies of all approved shop drawings. Revised November 24, 2014 54 | PROJECT GUIDE | PART D Functional description to include: • Functional description of theory of operation • Design philosophy • Specific functions of design philosophy and system • Full details of data communications, including data types and formats, data processing and disposition data link components, interfaces and operator tests or self test of data link integrity • Explicit description of hardware and software functions, interfaces, requirements for components in functions and operating modes • Description of person machine interactions required to supplement system description, known or established constraints on system operation, operating procedures currently implemented or planned for implementation in automatic mode. Systems Operation: • Complete step by step procedures for operation of system including required actions at each OWS. • Operation of computer peripherals, input and output formats. • Emergency, alarm and failure recovery • Step by step instructions for start-up, back up equipment operation, execution of all systems functions and operating modes, including key strokes for each command so that operator need only refer to these pages for keystroke entries required to call up display or to input command. SOFTWARE TO INCLUDE: • Documentation of theory, design, interface requirements, functions, including test and verification procedures. • Detailed descriptions of program requirements and capabilities • Data necessary to permit modification, relocation, reprogramming and to permit new and existing software modules to respond to changing system functional requirements without disrupting normal operation. • Software modules, fully annotated source code listings, error free object code files ready for loading via peripheral device • Complete program cross reference plus any linking requirements, data exchange requirements, necessary subroutine lists, data file requirements, other information necessary for proper loading, integration, interfacing, program execution. Revised November 24, 2014 PART D | PROJECT GUIDE | 55 • Software for each new controller and single section referencing all Controller common parameters and functions MAINTENANCE: Document maintenance procedures including inspection, periodic preventive maintenance, fault diagnosis, repair or replacement of defective components, including calibration, maintenance, repair of sensors, transmitters, transducers, Controller interface firmware’s, plus diagnostics and repair/replacement of system hardware. Test procedures and reports: record implementation, description of test procedures. Provide for measurement or observation of results. SYSTEM CONFIGURATION DOCUMENT Basic system design and configuration Provisions and procedures for planning, implementing, recording hardware and software modifications required during installation, test and operating lifetime of system. Information to ensure co- ordination of hardware and software changes, data link or message format/content changes, sensor or control changes in event that system modifications are required. Full documentation of new system configurations. Identifications • Submit for approval samples of nameplates, identification tags and list of proposed wording. • Follow SFU labeling and identification system (attached in Appendices D-1a-1c ). Electrical Plans • In renovations, indicate changes to the Base Building systems and include appropriate specifications. • Project Construction Schedule (preliminary and final) The Consultant, in consultation with the Project representative from Facilities Services, will outline expected dates for the start and completion of drawing development, tendering and construction along with completion and occupancy dates. This schedule should be submitted at the commencement of Schematic Design and any Changes must receive the approval of the Owner’s Representative. Revised November 24, 2014 56 | PROJECT GUIDE | PART D PREPARING CONTRACT DOCUMENTATION Submitting Working Drawings for Approval Throughout the duration of the project, the Consultant and /or Contractor will be required to submit the following required documents: The Consultant shall submit drawings for review and approval by Facilities Services and the User Group at approximately 30%, 60% complete and issued for tender sets. Outline specifications should be provided at 30%. At 60% complete, draft specs sections for all sub-consultants should be provided for coordination. Some key areas for review are: • Universal Access: the Burnaby Campus’ interconnected floor plates built on a mountain often provides unique challenges for persons with disabilities. Preliminary drawings will be checked from the standpoint of physical compatibility and any problems encountered shall be returned to the Consultant and/or his agent for solution. • Fire exiting: Special consideration must be paid to occupancy load calculations and path to exits. The interconnected buildings require special consideration to ensure safe existing is provided from suites. • Impact on existing systems. • Long term maintenance and operations. Obtain approval from Facilities Services Owner’s Representative upon receipt of advice of corrections to any problems. Prior to Construction Provide Facilities Services Project representative with: • Building Permit Number and a copy of the Permit. • Proof of Contractor’s Liability Insurance Policy. • Copy of Contractor’s Worker’s Compensation Board, Letter of Certification. Prior to Substantial completion • Fire Alarm Verification. • The Contractor is also responsible for obtaining all the required inspections and signoffs (i.e., building, electrical, plumbing, sprinkler, fire department, health, etc). As-Built drawings & Maintenance Manuals • HVAC Balancing Report Revised November 24, 2014 PART D | PROJECT GUIDE | 57 • Final Building Inspection Permit • Final Electrical Inspection Permit • Final Plumbing Inspection Permit COMMISSIONING Commissioning Team Commissioning to be carried out under general direction of the Commissioning Engineer (Contractor’s staff ) and where applicable, the Owner’s Commissioning Authority, and in presence of the Consultant, Consultant team and the Owner as requested. Approvals Obtain approval to start commissioning from the Consultant at least 7 days prior to start. Information to include: • Systems to be commissioned • Procedures, anticipated results • Names of commissioning personnel • Purpose • Assurance that systems meet design criteria, design intents and requirements of specifications • Design Requirements • Commissioning Engineer to confirm with the Consultant that Design Criteria and Design Intents are still applicable • Commissioning personnel to be fully aware of and qualified to interpret Design Criteria and Design Intents Coordination Coordinate commissioning procedures with other Divisions. Commissioning Plan Information to include: • Systems to be commissioned Revised November 24, 2014 58 | PROJECT GUIDE | PART D Note: Facilities Services, at its discretion, will hold back funds until the Record Drawings are received in acceptable form. Refer to Appendix D-2: Printing Request Form & Appendix D-3: Records Submittal checklist • Procedures, anticipated results • Names of commissioning personnel • Purpose • Assurance that systems meet design criteria, design intents and requirements of specifications • Design Requirements • Commissioning Engineer to confirm with the Consultant that Design Criteria and Design Intents are still applicable • Commissioning personnel to be fully aware of and qualified to interpret Design Criteria and • Design Intents Timing • Commissioning to commence only after satisfactory completion of start up, verification of performance and specified test period • Commissioning of occupancy , weather , and seasonal sensitive systems to take place during four (4) consecutive seasons, after facility has been accepted, taken over and fully occupied. • Commission systems considered as life safety systems before affected parts of facility are occupied. Instrumentation • Provide sufficient permanent and temporary instrumentation. Verify locations, access, illumination for readings. • Instrumentation accuracy tolerances: higher order of magnitude than equipment, or system, being tested. • Locations to be approved, readily accessible and readable. • Application: to conform to normal industry standards. Operations of Systems • Operate systems as long as necessary to commission entire project • Supervision and Monitoring • Commissioning to be supervised by qualified supervisory personnel • Monitor progress Revised November 24, 2014 PROJECT GUIDE | 59 • Keep detailed records of activities and results. Documentation Documentation, O&M Manuals and training of O&M personnel to be complete to satisfaction of the Consultant before starting commissioning. Verification of Results Commissioning Engineer shall verify 30 % of reported results. Demonstration Demonstrate to the Consultant and the Owner operation of systems including sequence of operations in regular and emergency modes, under normal and emergency conditions, start up, shut down, interlocks, lock outs. Final Settings Upon completion of commissioning to satisfaction of the Consultant, set and lock devices in final position, permanently mark settings. Final Report • Submit report to Consultant. • Report to include: Measurements, final settings, certified test results. • Bear signature of commissioning technician and supervisor. Use of O&M Personnel O&M personnel to assist in commissioning procedures as part of training. Equipment Demonstrations At the completion of the project, the General Contractor shall provide equipment demonstrations of all newly installed mechanical and/or electrical equipment to the Facilities Services staff as requested. SUBMITTING FINAL RECORD DOCUMENTATION Drawings Prior to the application for substantial completion the Contractor should review the red-line site mark up set and stamp and sign to certify completeness and accuracy. The 60 | PROJECT GUIDE Prime Consultant shall obtain these site mark ups/ as built drawings from the Contractor and review them for their completeness. Once approved, the respective Disciplines will in turn convert these as built drawings into “Record Drawings”. The Designer and Mechanical and Electrical Consultants will submit to Facilities a complete set of Record drawings in print form as well as CAD files, with all deviations neatly indicated. See Appendix D-3 : Record Submittal Requirements. Specifications Update Specification sets with approved change orders inserted in the front . Provide a soft copy of the specifications with Records submittals. Operation and Maintenance Manuals At completion of project, two maintenance manuals must be submitted in 3-post hard covered binders as well as in soft copy in a labelled CD. Each manual must include (as a minimum) the following information: • Description of operation • Shop drawings of all equipment • Extended warranties • Maintenance and operating instructions • List of manufacturer and trade names • List of supply sources for maintenance • Paint formulas • Hardware products supplied and installed • Balance report • Name of company, contact person and phone number and e-mail address of ALL sub trades that supplied and installed products to the site • All Permits, licenses and final inspections • Copy of Substantial Completion Certificate --------------------------------------------------------------------------------------------------------------