DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES 00 63 00 SECTION 00 63 00 – CLARIFICATIONS AND PROPOSALS GENERAL It is understood that the purpose of Change Orders is to modify the contract and that requests for information, interpretation, or clarification are to explain project conditions without generating a proposal or change to the contract. CLARIFICATIONS Clarifications are responses to Request for information or interpretation (RFI’s). All clarifications must be in writing. If a clarification will impact the contract, the contractor shall follow the contract modification procedures per the contract. Clarifications shall be traced on the Contractor generated RFI Log. FIELD DIRECTIVES / FIELD ORDERS Field Directives / Field Orders shall be used in only urgent situations. A field Directive must be tracked on the Construction Change Directives Log and must be closed by an issued Change Order, Architects supplemental instructions or a RFI/Clarification item as soon as is possible. PROPOSED CHANGES All change proposals shell be requested and responded to in writing. Each change proposal shall include a description of construction schedule impacts and a date when the information in the proposal expires. All change proposals accepted by University of South Alabama will be converted to or incorporated in a Change Order in a timely fashion. Change proposals and proposal requests shall be tracked on the Contractor generated Item of Change Log. CHANGE ORDER PROCESS Contractor assembles all detailed pricing, including pricing from subs and vendors. Pricing must be on letterhead of company performing work. Contractor submits two (2) copies of pricing and backup to Design Professional for review. Design Professional provides university project manager with signed memo on company letterhead describing the work and agreeing with the cost of proposed change order. Owner will provide completed Alabama Building Commission Change Order Form, C-12, and sends to contractor for signatures including contractors bonding agent. University prepares Alabama Building Commission change order justification form B-11 and sends to Design Professional for Approval and signature. University Project Manager forwards Design Professional approval memo, and executed forms C-12 and B-11 to University Legal department for review and signature. The Contractor may bill for the Change Order on the next payment following receipt of the fully executed Change Order. UPDATED - JANUARY 20, 2015 Page 1 of 1