Document 11062495

advertisement
[DEC
Market-like Task Scheduling
Distributed
in
Computing Environments
Thomas W. Malone
Richard
E.
Fikes
Kenneth
R.
Grant
Michael
T.
Howard
MASSACHUSETTS
INSTITUTE OF TECHNOLOGY
50 MEMORIAL DRIVE
CAMBRIDGE, MASSACHUSETTS 02139
211989)
Market-like Task Scheduling
Distributed
in
Computing Environments
Thomas W. Malone
Richard
E.
Fikes
Kenneth
R.
Grant
Michael
T.
Howard
March 1986
CISRWPNo. 139
Sloan
WP No.
1785-86
c 1986 T.W. Malone, R.E. Fikes. K.R. Grant,
MT. Howard
Center For Information Systems Research
Sloan School of Management
Massachusetts Institute of Technology
0»f
,<moiko«'t^
DEC 2
1
1989
I
I
Abstract
This paper focuses on a class of market- like methods for decentralized scheduling of tasks in
distributed computing networks. In these methods, processors send out "requests for bids" on tasks to
be done and other processors respond with "bids" giving estimated completion times that can reflect
such factors as machine speed and data availability.
scheduling
is
A
simple and general protocol for such
described and simulated in a wide variety of situations (e.g., different network
configurations, system loads,
and message delay
times).
The
protocol
is
found to provide substantial
performance improvements over processing tasks on the machines at which they originate even
face of relatively large
in the
message delays and relatively innaccurate estimates of processing times. The
protocol also performs well in comparison to one simpler
final section of the paper, a prototype
system
is
and one more complex
alternative. In the
described that uses this protocol for sharing tasks
among personal workstations on a local area network.
Market-like Task Scheduling in Distributed Computing Environments
With the rapid spread of personal computer networks and the increasing
availability of low cost
VLSI
processors, the opportunities for massive use of parallel and distributed computing are becoming
more and more compelling
([JonSO); [Gaj85];
fundamental problems that must be solved by all such systems
This problem
on processors.
is,
One
[Dav 81bl; [Ens8l]; [Ber82I; [Bir821).
is
of the
the problem of how to schedule tasks
of course, a well-known one in traditional operating systems and
scheduling theory, and there are a number of mathematical and software techniques for solving
it
in
both single and multi-processor systems (e.g.,[Bri73]; [Cof73]; [Con671; [JonSO]; [KriTlJ; [Lam68);
[Kle81];[Wit80];[Vnt811).
Almost
where
all
all
the traditional
the information
work
is
in this area, however, deals with centralized scheduling techniques,
brought to one place and the decisions are made there. In highly parallel
systems where the information used in scheduling and the resulting actions are distributed over a
number
of different processors, there
scheduling techniques. For example,
to
may
be substantial benefits from developing decentralized
when a centralized scheduler
fails,
the entire system
is
brought
a halt, but systems that use decentralized scheduling techniques can continue to operate with
the remaining nodes.
Furthermore, much of the information used
distributed and rapidly changing (eg
,
momentary system
load).
in
scheduling
is
all
inherently
Thus, decentralized scheduling
techniques can "bring the decisions to the information" rather than having to constantly transmit the
information to a centralized decision maker. Because of these advantages, a growing body of recent
work has begun
such decentralized scheduling techniques in more detail
to explore
[Sin85]; [Liv82]; [Mal83|; [Lar821; [SmiSO],
[TenSlb]; [StrSl]
In this paper,
;
[SRC851; see Stankovic
we focus on a particular
(e.g.,
[StaSSJ;
[Sto771; [Sto781; [Cho79]; [Bry81I; [Sta84]; [Ten81al,
for a useful review).
class of decentralized scheduling techniques:
those involving
market-like "bidding" mechanisms to assign tasks to processors (eg, [Mal831; [Far72]; [SmiSO];
[Sin85]; [Far73]; [Sta84]).
Such techniques are remarkably
loading and current locations of data and related tasks
we
will describe a
(e.g.,
many forms
see [Sta84]).
In succeeding sections of
simple but powerful bidding protocol and present detailed simulation
and analytic results that explore the behavior of the protocol
results apply to
terms of the kinds of factors
job characteristics, processor capacities and speeds, current network
they can take into account:
the paper,
flexible in
in a
wide variety of stituations. These
of parallel computation, regardless of whether or not the processors are
geographically separated and whether or not they share memory.
Motivating example
Even though the simulation
results are applicable in
many
situations, the driving
motivated the development and analysis of our protocol was the increasingly
large
numbers of personal workstations connected by
the final section of the paper,
to
share tasks
One
local
we describe a prototype system,
(e.g.,
common
distributed systems becomes possible.
systems based on local area networks
[Bir82I; [BogSO]).
The
is to
that a
is
new philosophy
designing
for
traditional philosophy used in designing distributed
have dedicated personal workstations which remain
and various kinds of data base servers
(e.g.,
[Bir821; [Sch84]).
A system
file
flexible design.
In this
new
philosophy, personal workstations are
idle
servers, print
like Enterprise that
schedules tasks on the best processor available at run time (either remote or local) enables a
more
In
called Enterprise, that uses the protocol
not used by their owners, and dedicated special purpose servers such as
servers,
situation of
among workstations in such a network.
of the benefits of sharing tasks in such networks
when
area networks
example that
still
much
dedicated to their
owners, but during the (often substantial) periods of the day when their owners are not using them,
these personal workstations become general purpose servers, available to other users on the network.
"Server" functions can migrate and replicate as needed on otherwise unused machines (except for
those such as
file
servers and print servers that are required to run on specific machines).
programs can be written
to
take advantage of the
maximum amount
parallelism available on a network at any time, with
little
extra cost
of processing
when
Thus
power and
there are few extra
machines available.
Problem description and related work
In describing the problem on which
components of task scheduling
(2)
we are
focusing,
it is
useful, first of all, to distinguish
in distributed networks: (1) the
assignment of tasks
the sequencing of task once they have been assigned to processors.
between two
to processors,
and
Much previous work on
distributed load sharing has focused only on the task assignment problem (eg, [Liv82); [Sta85|;
[Cho79]) and used first come-first served (FCFS) sequencing.
It is
sequencing can have a major effect on system performance measures
clear,
(e.g.,
however, that task
see [Con67|).
The task
scheduling method we will describe solves both the task assignment and the task sequencing
problems simultaneously.
Another common simplifying assumption
much
in
previous work
processors in the scheduling network are identical
It is
(e.g.,
[Liv82]; [BrySl]) is that all
frequently the case, however, in our
motivating example of workstations on networks and in many other distributed processing
situations, that there are important differences
such as speed, ability
to
do certain tasks at
all,
between processors. These differences include factors
and whether the necessary the data or programs are
already present on the processor or must be transmitted from elsewhere on the network.
scheduling method
In
some cases
is
(e.g.,
processor at the
Our
designed to accomodate a wide variety of such processor differences.
[BrySll; [Sta841),
same time and
begun execution. These
to
it
is
desirable to be able to have
move tasks from one processor
capabilities often
add substantially
to the
to
more than one task on a
another after the tasks have
complexity of implementing a real
system, however, so we have simplified our analysis by omitting them.
The scheduling methods we
will consider
can be applied
in
any situation that has the properties we
have just described; tasks are sequenced one at a time on heterogeneous processors without being
moved or preempted afler execution begins.
Bidding mechanisms
We
mentioned above a number of advantages
(e.g., reliability
for task scheduling in distributed networks.
scheduling
to
be one in which
processors ("contractors"),
(2)
(1)
We
and
flexibility) of
bidding mechanisms
mechanism
for distributed task
define a bidding
task descriptions are broadcast (by "clients") to a set of possible
some subset
of the contractors respond with "bids" indicating their
availability (and possibly cost) for performing the task,
and
(3)
one of the bidders
is
selected to
perform the task.
Note that there are many characteristics of human markets that are not included
in this definition.
For example, bidding mechanisms as we have defined them here can assign tasks after only one
"round" of bid submissions. They need not include any of the iterative price adjustment, based on
supply and demand, that
is
widely discussed in microeconomic theory (eg, [Arr71|), and that
is
included in the network channel access scheduler described by Kurose, Schwartz, and Yemini
(KurSS).
In fact, our early experiments with
an
iterative pricing
assignment [Mal82] discouraged us from pursuing
with guaranteeing convergence at
all
this
((Arr60];
mechanism
for distributed task
approach further because of the
difficulties
[ArrTlD and because of the extremely
computationally intensive nature of the iterative process.
Several of the systems mentioned above ([Far721; [Sta84); [Ram84]) use non-iterative bidding
mechanisms, but
for scheduling
problems
differer\t
from the one we are considering. One previous
system, however, can be used for problems of the type in which we are interested: The contract net
protocol ([SmiSOI; [SmiSlI; [Dav83|)
is
a very general protocol for distributing tasks in a network of
heterogenous processors based on whatever task specific criteria are provided by the system designer.
award" sequence allows
mutual selection of clients and contractors; that
Its
"announcement,
is,
contractors choose which clients to serve and clients choose which contractors to use.
bid,
system ([Sin85]) which
is
for
In order to achieve
criteria
later
based in part on the contract net protocol and on an earlier report of the
system described here ([Mal83I), shows how the protocol can be modified
number of messages
A
to substantially
reduce the
required.
any particular scheduling objective with these systems, however,
must be developed. The most important way
contract net protocol
is
in
which our scheduling protocol
by specializing the selection criteria
to
contractors on the basis of estimated completion times (from
to
perform the
We
job).
generalized contract net protocol allows us to
will see
make
differs
from the
two primary dimensions:
contractors select clients' tasks in the order of numerical task priorities,
minimum requirements
specific selection
among
and
(1)
(2) clients select
the contractors that satisfy the
below how this simple specialization of the
direct use of a variety of optimality results
traditional scheduling theory, including those about minimizing
mean
from
flow times, and to do detailed
evaluations of the effect of numerous factors on scheduling performance.
One of the
potential problems that arises in bidding systems like the contract net protocol stems from
the fact that only idle processors submit bids.
any information about the loads and
evaluated.
This
may
in the
absence of
capabilities of processors that are busy at the time the bids are
be undesirable, for example, in situations where only slow processors are
available at the time the task arrives, but a
sections below,
Thus assignment decisions are made
we consider two
much
faster processor will
become available soon.
alternative solutions to this problem.
In the
Our primary scheduling
method, called the Distributed Scheduling Protocol, uses the simple technique of canceling and
restarting tasks
if
the later bid
is
sufficiently better
We also consider, in a later section, a much more
elaborate alternative method in which processors maintain detailed future schedules of tasks they
have agreed
to
perform and use this information in submitting their bids.
investigate the performance of both these methods in a variety of situations.
THE DISTRIBUTED SCHEDULING PROTOCOL
Our simulation
results
.
Figure
1
primary scheduling process, the Distributed Scheduling Protocol
illustrates the steps in our
(DSP):
1
The
client broadcasts
task,
a "request for bids ". The request for bids includes the priority of the
any special requirements, and a summary description of the task that allows
contractors to estimate
2.
processing time.
its
Idle contractors respond with "bids" giving their estimated completion times.
contractors respond with "acknowledgements
"and add the
Busy
task to their queues (in order of
priority).
3.
When a contractor becomes
4.
(a) If more
submits a bid for the next task on
its
queue.
than one bid has been received when the client evaluates bids, the task
the best bidder.
is set
idle, it
The length
of time to wait before evaluating bids
is
is
sent to
a parameter that
depending on the message delay time.
(b) If no bids
have been received when the client evaluates bids, the task
is
sent to the first
subsequent bidder.
(c)
If a later bid is "significantly better" than the early one, the client cancels the task
first
bidder and sends the task
to the later
late bid is "significantly better"
simulations below.
effects
If
and cannot be
is
bidder The criterion for deciding whether a
a parameter, the effect of which
the later bid
is
not significantly better (or
restarted), the client sends a cancel
5.
When a contractor finishes a task,
6.
When a client
it
on the
message
if
is
examined
in the
the task has side-
to the later bidder.
returns the result to the client.
receives the result of a task,
it
broadcasts a "cancel" message so that all the
contractors can remove the task from their queues.
A more detailed description of the
DSP, including complete specifications of the message contents,
provided by Malone, Fikes, and Howard ([Mal83]).
Global Scheduling Objectives
is
One
of the advantages of this protocol is that
it
assigned from the mechanism of actually scheduling tasks according
sequences jobs according to their order in a priority
are assigned are
made
list
while the policy decisions about
at a higher level in the system (see [Lam68]).
The DSP
kind of separation of policy and mechanism.
sequencing jobs according
to priorities
scheduling as a
list
one level of the system
In this approach,
(e.g., [Cof731).
DSP
level.
how
priorities
allows precisely the
protocol itself
assigned at some higher
priorities are
to these priorities (e.g., [Cof731,
[Lam68]). Traditional schedulers for centralized computing systems often use
basis for layering the design of a system
how
separates the policy decisions about
same
concerned only with
is
By assigning these
priorities in
different ways, the designers of distributed systems can achieve different global objectives.
example,
it is
well
known
For
that in systems of identical processors, the average waiting time of jobs
minimized by doing the shortest jobs
first
[Con67].
is
Thus, by assigning priorities in order of job
on priority result
length, the completely decentralized decisions based
in a globally
optimal
sequencing of tasks on processors.
Optimality results for
mean flow time and maximum flow
time. Traditional scheduling theory (e.g.,
[Con671) has been primarily concerned with minimizing one of two objectives:
time of jobs (Fave)--the average time from availability of a job until
maximum flow time of jobs (Fmai)-the time until the completion of the
maximizes the utilization of the processors being scheduled
[Cof73|.
scheduling theory, involving the "tardiness" of jobs in relation
to
it is
(I)
the average flow
completed, and
last job
(2)
the
Minimizing F^ax ^Iso
(A third class of results from
to their respective deadlines,
appears
be less useful in most computer system scheduling problems.) The most general forms of both these
problems are NP-complete ([Bru74], [Iba77I), so much of the literature
comparing scheduling heuristics
in
we consider cases where
known
exactly.
[Con67] and
all
In these cases,
LPT is guaranteed
value [Gra69I.
If
,
[Dav81a|, [JaiBO]).
suggest the value of using two simple heuristics, shortest processing time
(SPT) and longest processing time
First,
has involved
terms of bounds on computational complexity and "goodness" of
the resulting schedules relative to optimal schedules (eg
A number of results
in this field
first
to
(LPT), to achieve the objectives F^ve and Fmai. respectively.
jobs are available at the
if all
same time and
the processors are identical, then
produce an Fmax that
some processors are uniformly
is
faster
their processing times are
SPT
exactly minimizes Fave
no worse than 4/3 of the
than others, then the
minimum
LPT
consider cases where all jobs are available at the
in advance. Instead the processing times
same time but
is
Next, we
their exact processing times are not
have certain random distributions
with different expected values for different jobs.
possible
heuristic
guaranteed to produce an Fmax no worse than twice the best possible value [Gon77).
known
first
In these cases,
if
(e.g.,
exponential)
the system contains identical
processors on which preemptions and sharing are allowed, then
SPT and LPT
expected values of F,ve and Fn,,i, respectively, (IWebSZl, [Gla79J). Finally,
the jobs are not all available at the
we consider
cases where
and have exponentially
arrive randomly
In these cases, if the processors are identical
distributed processing times.
then
same time but instead
exactly minimize the
and allow preemption,
LPT exactly minimizes Fmax [VanSl].
Other scheduling objectives.
DSP can
the traditional ones of minimizing
also be used to achieve
many
other possible objectives besides
mean or maximum flow time for independent jobs. For example:
Many
(1) Parallel heuristic search.
artificial intelligence
programs use various kinds of
heuristics for determining which of several alternatives in a search space to explore next. For
example, in a traditional "best
first" heuristic search, the single
at each point is always chosen to be explored next [N'ilSO].
most promising alternative
By using the
heuristic evaluation
function to determine priorities for DSP, a system with n processors available can be always
Furthermore,
exploring the n most promising alternatives rather than only one.
if
the
processors have different capabilities, each task will be executing on the best processor
available to
The DSP
way
it,
given
its priority.
protocol can also, of course, be used in heuristic searches in a
to assign a fixed set of
([Sin85])
subtasks to processors.
system uses a bidding protocol
Their use of the protocol appears
to
to assign
more straightforward
For example, Singh and Genesereth's
deduction steps to distributed processors.
be minimizing Fmax by giving highest priority to the most
costly tasks.
(2)
Arbitrary market with priority points.
human
user of the system a fixed
number
DSP
Another obvious use of
is to
assign each
of priority points in each time period
their programs) can then allocate these priority points to tasks in
Users
any way they choose
(or
in
order to obtain the response times they desire (see [Sut68) for a similar-though non-
automated-scheme, and Mendelson ([MenSS])
for a related analysis
not micro-level priorities, but macro-level chargeback policies
(3) Incentive
market with priority points.
If the
make
at determining,
).
personal computers on a network are assigned
to different people, then a slight modification of the arbitrary
people an incentive to
aimed
market
in (2)
can be used
their personal computers available as contractors.
modified scheme, people accumulate additional priority points for their
time their machine acts as a contractor
for
someone
else's task.
own
to give
In this
later use. every
8
Estimating processing time
As described above, DSP requires bidders
information
is
used by
DSP
to estimate their completion times for different tasks.
This
only to rank different tasks and different contractors, so only rough
estimates are needed. In some cases, historical processing times for similar jobs might provide a basis
for
making even more
Our simulation
precise estimates, possibly using parameters such as the size of the input
studies below include an examination of the consequences of
files.
making these estimates
very poorly.
Alternative Scheduling Protocols
For comparison purposes, we now consider two alternative protocols. The
The second
designed to remedy one of the possible deficiencies of DSP.
method that provides a comparison with designs where no attention
is
first protocol is
is
a scheme
a random assignment
given to the scheduling
decision.
Alternative 1
-
Eager assignment
As discussed above, one of the
possible deficiencies of DSP
provided by processors that are not ready
task on a machine that
another
much
faster
is
to start
that no estimates of completion times are
immediately. That
available immediately (possbily their
machine becomes available soon.
processing time on the
is
first
machine
is
wasted.
If not,
If
own
the task
is,
DSP may
clients using
start a
local machine), only to find that
is
canceled and restarted,
the job finishes later than
it
all
the
could have.
If
reasonable estimates of completion times on currently busy machines are available, then clients
would know enough
to
wait for faster machines that were not immediately available.
In this alternative scheduling protocol, tasks are assigned to contractors as soon as possible after the
tasks become available and then reassigned as necessary
contractor maintains a schedule of tasks
finish times,
submitted.
and
so the contractor
By analogy with
it is
when
conditions change. In this way, each
expected to do, along with their estimated start and
can make estimates of when
it
could complete any
new
task that
"lazy" evaluation of variables ([Fri76|, [Hen76]) the original
DSP
is
could
be called "lazy assignment" because clients defer assigning a task to a specific contractor until the
contractor
is
actually ready to start.
assignment," since
it
This alternative protocol, therefore, will be called "eager
assigns tasks to contractors as soon as possible.
This alternative
may
be
thought of as a logical extension of the "immediate bid responses" used in the contract nets protocol
([SmiSO], [SmiSl]), and
is
also similar to the
"STB" scheduling alternative considered by Livny
&
Melman([Liv82]).
In this protocol, all contractors bid
estimates
on
all
tasks even
higher priority
is
who submitted
it.
than expected
scheduled.
When new
Then the
client picks the best bid
to complete, the contractor notiiies the
to note that
DSP,
amount
"bump
may
on other
bump
is
a lot of bumping, this scheduling process
is
the reservations of other tasks of lower priority,
finite
number
of bumps.
of rescheduling in rapidly changing situations,
its
To reduce the
bumping occurs
amount
original estimate by the
tolerance" parameter.
this alternative is clearly
it
to reschedule their tasks
Distributed Computing System ([Far731;
the currently estimated completion time of job exceeds
specified in the
While
where there
can only
a task takes longer
no longer available by the time the task arrives.
new task can never cause more than a
finite G>ut possibly large)
when
in cases
to converge. Since tasks
the scheduling of a
only
even
is
when
to the contractor
later tasks in its schedule that their
These clients may then try
[Far 731) when a processor that has bid on a task
guaranteed
owners of
A related kind of bumping process occurs in the
important
and sends the task
tasks are added to a contractor's schedule, or
reservations have been "bumped."
It is
contractor
starting time for a task by flnding the first time in its schedule at which no task of
its
contractors.
A
they are currently busy.
if
more elaborate and may require much more message
traffic
than the
also result in better schedules for situations with processors of widely varying
capabilities.
Alternative 2
-
Random assignment
In the second alternative protocol, clients pick the first contractor
who responds
to their request for
bids and contractors pick the first tasks they receive after an idle period. Contractors do not bid at all
when they are executing a
does not receive any bids,
it
and they answer
when they
If
a client
continues to rebroadcast the request for bids periodically.
When
task,
all
requests for bids
contractors receive a task after already beginning execution of another one, the
(with a
"bump" message) and
the client
who submitted
it
when more than one
new
idle.
task
continues trying to schedule
In the simulations discussed below, the selection of the first bidders
available, and of the first task
are
task
is
it
is
rejected
elsewhere.
when more than one machine
waiting, are both modeled as
is
random
choices since the delay times for message transmission and processing are presumably random. (In
reality, fast contractor
machines might often respond more quickly
to
requests for bids than slow ones
10
and so would be more
mechanism
in
Thus the performance
likely to be the first bidders.
of this scheduling
a real system might be somewhat better than the simulated performance.)
SIMULATION RESULTS
In
many
environments, including our motivating example of
real distributed scheduling
workstations on a network, minimizing the
primary scheduling
meet
objective.
this objective is usually
mean
Unfortunately, as
flow time of independent jobs
we noted
It
is
effects of
In this section,
results of a series of simulation studies that investigate the performance of the
and compare
assignment).
it
sequencing
therefore appropriate to rely heavily on
simulations to investigate strategies for achieving this objective
situations
likely to be the
above, the problem of scheduling tasks to
NP-hard, and other analytic results about the
strategies (other than random) are quite scarce.
is
we summarize the
DSP
in a variety of
two alternatives described above (eager assignment and random
to the
We also report several analytic results that are useful for comparisons to the simulation
results.
Simulation Method
Priorities. Since the objective to be
jobs, priorities in all simulations
minimized by scheduling
assumed
is
were determined according
to
be the
mean
flow time of
to the shortest processing
time
first
(SPT) heuristic, except in the random alternative where priorities are not used.
Network configurations. Ten diiTerent configurations of machines on the network were defined.
was
configurations, a total of 8 units of processing power
achieved in different ways: a single machine of speed
speed 4 and 2 machines of speed
2; etc.
We
will
8;
In all
available, but in different cases this
or 8 machines of speed
I;
or
I
was
machine of
denote different network configurations below by a
sequence of the machine speeds they contain (eg, "422").
Job
loads.
For
all
the simulations, jobs were
processing on any machine in the network.
the
amount of processing
in
assumed
The job
each job was assumed
time units on a processor of speed
I).
System
to be
independent of each other and suitable for
arrivals were
to
assumed
to
be a Poisson process and
be exponentially distributed (with a
utilization
mean
of 60
was defined as the expected amount of
processing requested per time interval divided by the total amount of processing power in the system,
and three different
levels of system utilization (O.I,
5,
and
0.9)
were simulated.
11
In order to increase the
power of comparisons between different simulations at the same
common random numbers was used
variance reduction technique called
level, the
350-354). In this technique, the
the different simulations
same sequence
By reducing the
of random
numbers
utilization
(see [Law82a], pp.
used to generate jobs in each of
is
variation between simulations that
is
due
to
random job
generation, this technique increases the statistical power of the comparisons between the factors of
interest (different network configurations
A
Statistical tests for equilibrium.
and scheduling methods).
generic problem in simulation studies
is
determining how
jobs to simulate. In all the simulations reported below, the procedure developed by
when
([Law79]) was used to determine
report for the steady state mean.
to
many
Law and Carson
terminate the simulation and what confidence intervals to
This procedure was recommended by
Law and Kelton ([Law82a,
Law82b]) after comprehensive surveys of both fixed-sample-size and sequential procedures.
procedure
is
based on the idea of comparing successive batches of jobs to determine whether the
means are correlated. When
means
to
The
the
number of batches and
the batch sizes are large enough for the batch
mean and variance
be uncorrelated, then the grand
are unbiased estimates of the steady
state values for the simulation (see [Law79|).
In practice, this test
was quite
Each simulation was run
stringent.
until a
90 percent confidence
computed with a width of less than 15 percent of the estimated mean. The number
interval could be
of jobs required ranged from 1200 jobs in
some
of the simulations for system utilization of 0.1 to over
75,000 jobs in some of the simulations for system utilization of 0.9.
In
many
simulation studies, some number of jobs are discarded from the beginning of the analysis to
remove the
"start up" values
from the overall mean. However, as Law and Kelton ([Law82b]) and
Gafarian, Ancker, and Morisaku ([Gaf78]) have noted, there are no generally satisfactory methods for
determining how
many
jobs to discard.
discarding any jobs. Since,
later batches,
above, but
it
it
may
if
Therefore,
we adopted the conservative approach of not
anything, this increases the variance between the
increase the
number
the jobs also included an estimated
take).
mean
In addition to the actual
amount of processing
have made of how long the job would
of early
and
of jobs necessary to pass the steady state test described
will not result in biased estimates of the steady state
Accuracy ofjob processing time estimates
means
for
(see [Law82al).
amount
each job
These estimates are used
(i.e.,
to
of processing in each job,
the estimate a user might
determine job priorities and
estimated completion times. In order to examine extreme cases, these estimates were either perfect (0
12
percent error) or relatively inaccurate
(
+ /- 100 percent
error).
In the case of inaccurate estimates,
the errors were uniformly randomly distributed over the range.
Communications
delays.
In order to simulate "pure" cases of the different scheduling
mechanisms,
most of our simulations treat communication among machines as perfectly reliable and
instantaneous.
In real situations
where communication delays are negligible relative
processing times, this assumption of instantaneous communications
is
to job
appropriate.
In other simulations, designed to explore the effect of communication delays,
we assumed constant
delays for the transmission of all messages. The values for message delay that were simulated were
equivalent to 0%, 5%,
10<!fc,
and 15% respectively of the average job processing time. The simulations
include only the effect of message delays; they do not include any other factors such as processing
overhead needed
to
Even though, as we
transmit and receive messages.
will see below, the effect of increasing
results cannot be obtained by simply adding the total
for 4
communication delays
message delay time per job
is
quite linear, the
(the delay required
messages) to the results for no delays. This simple approach does not work because
it
neglects
the time saved by having the announcements of waiting jobs already queued at processors that are
busy when the jobs are
first
announced.
Restarting after late bids. In most of the simulations of DSP, late bids are never accepted no matter
how much of an improvement they are over
test the effect of this
the earlier bids. In one series of simulations, designed to
parameter, a range of values for this "late bid improvement" parameter
is
investigated.
Bumping and
rebroadcasting.
In keeping with the spirit of simulating "pure" scheduling methods,
jobs in the eager simulations are rescheduled every time their scheduled start time
In a real system, jobs would ordinarily have to be
rescheduled.
bumped by more than some
In other words, the performance of the eager
is
delayed at
all.
tolerance before being
method could only get worse
if
fewer
bumps were made.
Similarly, in the
random assignment simulations,
time interval of the simulation until the job
is
clients rebroadcast their requests for bids in every
successfully assigned to a contractor.
simulates the best scheduling performance the random method could achieve;
occurred less often, the performance could only get worse.
if
Thus, this
rebroadcasting
,
13
Analytic methods
It is
possible to derive analytically several simple results that can be used for comparison with the
simulation results.
Random assignment and
randomly
to identical
processors
is
sequencing on identical processors.
processors as they become available and sequenced randomly on these
equivalent to an
M/M/m queuing system,
The expected queue length and waiting time
L =
W=
[(mA/p)'n(X/ii)PoJ
L/m\ +
r
1
Our simulations
/
[m!(l-A/p)21
for
that
is,
a system with
m servers for one queue.
such a system are, respectively:
,
1/p
m-l
P= 1/ ^
where
The case where tasks are assigned
(mX/p)'/i!
+ [(m\/n)'"/m!l / 1 - \/\i)
=
do, in fact, generate confidence intervals that include these values for the cases
where they can be computed. In these cases, only the analytically derived results are reported.
Optimal assignment (with jobs moving during execution and with random sequencing). Even though
our simulations assume that jobs cannot be moved once they have begun execution there
formula
for the flow
times that would result
if jobs
is
a simple
could be moved during execution in such a
way
that the fastest processors were always in use (see (Sta85]). This formula provides a lower bound for
the results of optimal assignment.
machines
to
However,
it
assumes that tasks are sequenced randomly on the
which they are assigned Since our simulated scheduling methods include sequencing as
well as assignment, they might do better or worse than these analytic results depending on the
relative importance of sequencing
approximate lower bound
for
j.
Letting the
in a
given situation. They do, however, provide an
rough comparison purposes.
In order to obtain these results,
yijifi^
and assignment
we assume that the processor
number of processors be N, we define
service rates p, are ordered so that p,
a
14
=
M(0
l.V^j
=1
.
7
=
M(0)
1.
Using straightforward assumptions about the state transition probabilities and the conservation of
flow principle, Stankovic ([StaSS]) shows that the expected queue length and waiting time for such a
system are, respectively:
w
where
=
PA
P^=\
ly
—
—
y
j
V
\JlM{j)+
+
N-l
+a-\/\iiN))
-2
n.
l-\/\i(N)
——
I
)
(1 -.\/p(JV))j.
j=0
Local processing only. One question of interest in our study
time that
locally
is
possible from scheduling jobs
is
the
amount of speedup
anywhere on the network as opposed
to
in
mean
processing
all
flow
jobs
on the machine at which they originate. As noted above, analytic results are not available for
the effect of sequencing in this situation. However,
it is
possible to use the simulation results for the
case with only one machine in the network to estimate of the effect of sequencing and then compute
the overall flow times that would result from all machines performing their local scheduling
similarly.
To do
this,
we take advantage
of the fact that the time units used in the simulation are arbitrary and
can be scaled as desired. For example, the mean flow time
that of a single machine of speed
time units. In general,
type
i,
C =
Ej
Sin,
let n,
8,
be the
is
machine of speed
I is
8 times
since the two simulations are indistinguishable except for the
number
of machines of type
i,
s,
be the speed of the machines of
be the total processing capacity on the network, and
network containing only a single machine of speed
network
for a single
1.
Then the
Wi
be the
mean
flow time in a
the average flow time in the total
15
W = Ei(ni/C)Wi.
Results
Relative effects of system load, network configuration,
We
first
DSP
investigate the results of
and accuracy ofprocessing time estimates
scheduling with a variety of system loads, network
configurations, and accuracies of processing time estimates.
factors,
much
lists
message delays were kept constant
better they were
(i.e.,
(at 0),
and
In order to focus on the effect of these
were never accepted, no matter how
late bids
the "late bid improvement" parameter was effectively infinite). Table
1
these results, Figure 2 shows the effect of system load for a typical configuration (1 machine of
speed 4 and 4 machines of speed
constant both system load (at
1),
50%
and Figure 3 shows the
utilization)
effect of
network configuration holding
and accuracy of processing time estimates
(at
0%
error).
Both system load and network configuration have a major impact on mean fiow time
we
factor of 4 for the range of conditions
(as
much
as a
studied), while the accuracy of processing time estimates
does not appear to be a major factor in performance (at most a difference of about 15% when estimates
have errors of up to 100%).
Figure 3 shows that the effect of dividing the same amount of processing f)ower into more and more
processors
is
almost linear and that the number of processors used has a much greater impact on flow
time than the
maximum
of the graph where the
range of processor speeds. Even
number of processors ranges from
if
I
we
to 4,
restrict our attention to the first part
we
see that this
makes a
difference of
approximately a factor of 3 in flow time, while changing from a configuration with identical
processors to one with a speed range of a factor of 4
makes only about a 12 percent
difference in flow
time.
Comparing the
results in Table
1
for
DSP
with the analytically derived results for optimal
assignment (with moving during execution and random sequencing), we see that
assignment
is
comparison
to this
important
(i.e.,
where processor speed ranges are
large),
DSP
in those cases
where
does reasonably well in
rough "lower bound". In the cases where assignment makes no difference
where processor speeds are
identical),
DSP
DSP does intelligent sequencing as well
does
much
as assignment.
(i.e
,
better than the rough "lower bound" because
16
Increasing the size of the bidding network while keeping overall utilization constant
The
results
power
we have
in the
just seen all involve configurations in which the total
network
different ways.
From
is
amount
of processing
among
processors in
constant (a total of 8 processing units), but divided
the point of view of a network designer, another relevant question
processors to combine in one bidding network, that
is,
how many
is
how many
processors to group together for the
purpose of sharing tasks. To answer this question, we assume that the speed of each processor and the
overall utilization remain constant
We
and then consider the
can estimate this effect in two ways.
The
first,
effect of adding processors to the
purely analytic, method uses the well-known
formulas given above for random scheduling on identical machines
random sequencing).
Since the machines are identical,
assignment method, but random sequencing
ways of analytically computing the
results of the
DSP
is
all
(i.e.,
both random assignment and
random assignment
certainly not optimal
(e.g.,
is
see [Con67]). Since simple
simulations to estimate the effect of (shortest processing time
of the
same speed (speed
1).
as good as any
sequencing are not known, the second method uses the
effects of
These estimates are then adjusted analytically
machines,
network.
to refer to
To make
first)
sequencing.
networks with different numbers of
this adjustment,
we
scale time units as described
Wn^ is the mean flow time for a network with N identical machines of speed
network with N machines of speed would have a mean flow time of W-sf.s* = (s/s')Wm
above.
If
s'
s,
then a
g.
Table 2 shows the results of both these methods, and Figure 4 plots the results for the second method.
It is
clear that using either
random
or
SPT
sequencing, pooling work from several processors can,
indeed, have a significant impact on flow time. This effect, however,
utilization.
little
There
is
is
very dependent on the system
essentially no benefit at low utilizations; at moderate utilizations, there
is
very
additional benefit after about 4 machines, and even for heavy utilizations, most of the benefits
have been exhausted by about 8 machines.
It is
important to realize that this result
known formulas
for
is
quite general.
random scheduling; our simulation
The
results
analytic results are based on well-
show that the
effect holds for
SPT
sequencing as well. The shape of the curves shown in the figure does not depend on processor speeds
or average job processing times; changes in these factors merely change the scale of the vertical axis.
Our result does depend on the assumption of exponentially
argument given by Sauer and Chandy [SauSl]
to explain their results
pooling jobs from several processors should be even
coefficients of variation in service time. Their
distributed service times, but the intuitive
suggests that the benefits of
more pronounced
in
argument says that with high
systems with greater
coefficients of variation,
multiprocessor systems perform better than single processor systems because a few very long jobs can
bottleneck a single processor while in a multiprocessor system, only one of the processors
monopolized and other jobs can
still
be processed on the other processors.
is
This argument also
suggests that in systems with very high coefTicients of variation, the benefits of adding
more
processors might extend further than in systems with exponential service times.
The implication
of this result for system design
significant benefits from pooling
no need
to
reducing
mean
-
quite important.
work generated by different machines
have large numbers of machines
several separate networks of 8
is
all
It
suggests that there can be
network but that there
in a
on the same bidding network.
In
is
most situations,
10 processors each should perform as well, from the point of view of
flow time, as a single network including all the processors together.
Effects of message delays
One
of the possible problems with pooling
are involved)
forth
is
work from several machines (even
only a few machines
that the message delays required for scheduling and for transferring results back and
might overwhelm the flow time benefits obtained from pooling. Figure 5 compares the results of
pooling jobs by network scheduling to the results of processing
all
jobs locally on the machines at
which they originate. The configurations simulated were chosen from our
to represent the situation in
machines or the
maximum
results in Figure 5
is
maximum number
of total
range of processor speeds).
show that pooling of work can,
delays are quite substantial.
scheduling
total set of configurations
which the least benefit would result from pooling (only two identical
machines) and the situations in which the most benefit would result (the
The
if
even when message
With moderate loads (50%) and large numbers of processors, pooled
superior to strictly local processing even
average job processing time!
in fact, be beneficial,
Even
in the
identical machines), pooled scheduling
is
when message delays exceed 20%
of the
configuration where pooling has the least benefit (two
preferred at moderate loads up to about the point where
message delays exceed 5% of the average job processing time.
Effects of "late bid
improvement" parameter
Figure 6 shows the effect of varying the amount of improvement required in "late" bids before jobs
will be cancelled
machine.
If
we
on the machines
let tg
to
which they were originally sent and restarted on the
late bidding
be the estimated completion time in the earlier bid, tL be the estimated
completion time in the late bid, and
t
be the time at which the late bid
is
evaluated, then the
18
"improvement"
is
i
=
1
-
(tt
-
toVCtg
Late bids must exceed some criterion parameter
- 1).
to
before
they will be accepted.
We
have simulated the configuration in which this factor could make the most difTerence (the
configuration with the
maximum
single job in this situation
is
0.75
range of processor speeds). The most improvement possible
(if
for a
a processor of speed 4 becomes available immediately after a bid
has been awarded to a processor of speed
1).
Therefore, setting
iq
at 0.75 or greater will result in no
rescheduling.
As Figure 6 shows,
at all, no matter
at low utilizations performance is
how
improved by rescheduling
small, but at moderate utilizations, performance
utilizations, the
maximum
to
25 percent.
processing time "wasted" on the
plentiful
job
is
any improvement
slightly
in the
worse by this
range of 0.4 to
0.6.
benefit from using this parameter appears to be about 5
percent, while at low utilizations using this parameter
on the order of 20
made
somewhere
strategy. In both cases, the optimal setting for io appears to be
At moderate
is
for
This result
is
may
result in overall flow time
improvements
sensible since the only cost of rescheduling
first processor,
and with low
utilization, this processing
anyway. As utilizations increase, the cost of "wasting" time on the
first
is
the
time
is
processor to which a
assigned increases and the potential benefit from using this parameter becomes negligible.
Evaluation of alternative scheduling methods
Figure 7 shows the results of DSP and the two alternative scheduling methods "eager" and "random."
In all cases,
DSP is at
least as good as,
and
in
some
cases,
much
better than the
more complicated and
expensive "eager" scheduling method. With perfect estimates of processing amounts, both
eager assignment are consistently as good as or better than random assignment.
processing time estimates,
DSP
DSP and
With poor
suffers little performance degredation, but the performance of eager
degrades quite substantially~in some cases eager becomes significantly worse than random.
particularly striking, in view of the fact that the eager
method was motivated by problems arising
with large numbers of processors and large speed differences
method performs worst
in precisely those situations.
It is
among
processors, that the eager
We believe that two primary
factors account for
this result:
(1)
"Stable world illusion."
In the eager assignment method, each job
machine that estimates the soonest completion time. But
and are assigned
later
and
to the
same machine, then they
will
if jobs
is
of higher priority arrive later
keep "bumping" the
later times. In other words, jobs are assigned to
assigned to the
first
job back to
machines on the assumption that no
13
more jobs
will arrive (i.e., that the
world will remain stable). Even though in the simulation,
jobs are rescheduled every time any
the time the job
rescheduled,
is
it
machine that could have completed
In
some of our simulations
this effect, that
is,
newjobs arrive that delay their estimated
may
it
by
already have missed a chance to start on another
before
it
will
now be completed.
(not included here), the bids included
bids included an estimate of
how long
an extra factor
to correct for
the starting time of the job would be
delayed by jobs that had not yet arrived, but could be expected
to arrive before the job
began
Even though the
(See [Mal86] for the derivation of this correction factor.)
execution.
start time,
inclusion of this correction factor did improve the performance of the eager
assignment
method somewhat, the changes were not substantial.
(2)
Unexpected availability.
When
a job takes longer than expected, or when higher priority
jobs arrive at a processor, all the clients
are notified with
"bump" messages and given a chance
takes less time than expected or
processor
who submitted jobs scheduled
may become
when
later
on that processor
to reschedule their jobs.
When
a job
jobs scheduled on a processor are canceled, the
available sooner than expected, but in these cases, the clients
who
submitted jobs that were scheduled elsewhere but who might now want to reschedule on the
There can thus be situations where
newly available machine are never notified.
fast
processors are idle while high priority jobs wait in queues on slower processors. This appears
to be a serious
weakness of the eager assignment method.
implemented, an addition
them
have
specified, but not
to the protocol that notifies all clients of such situations
to reschedule their tasks.
traffic
We
The
cost of this addition
and system complexity, and we believe
it
and allows
would be even greater message
unlikely that the resulting performance
would be significantly better than the much simpler lazy assignment method.
IMPLEMENTATION OF THE ENTERPRISE SYSTEM
In this section,
we describe
detailed description
runs processes on a
assigned
to the best
is
several highlights of the Enterprise system implementation.
provided by Malone, Fikes, and
local
Howard
([Mal831).
The system schedules and
area network of high-performance personal computers.
machine available
at run-time (whether that
is
The assignment takes
estimated completion time:
machine speed and currently loaded
prototype version of the system
is
implemented
in Interlisp-D
Processes are
the machine on which the task
two primary factors that affect
originated or another one).
into account
A more
files
needed
for the task
A
and runs on the Xerox 1100 (Dolphin),
20
1108 (Dandelion), and 1132 (Dorado) Scientific Information Processors connected with an Ethernet.
testing, but
The prototype version has received limited
no significant operational experience has been
obtained.
As shown in Figure
8,
the system
is
an Inter-Process Communication (IPC)
different machines, can send
messages
facility
to
each other.
When
messages over a "best
PUPs
(see [BogSO]) to provide
medium such
efforts" physical transport
procedure calls ([Bir84], [Tho831) in which messages are passed
on the remote machines.
layer provides
the different processes are on different
Enterprise uses a pre-existing protocol that
an Ethernet [Met76].
first
by which different processes, either on the same or
machines, the IPC protocol uses internetwork datagrams called
reliable non-duplicated delivery of
The
partitioned into three layers of software.
to
as
highly optimized for remote
is
remote machines as procedure calls
The next layer of the Enterprise system
is
the Distributed Scheduling
Protocol (DSP) which, using the IPC, assigns and sequences the task on the best available machine.
Finally, the top layer is a
Remote Process Mechanism, which uses both the DSP and IPC
to create
processes on different machines that can communicate with each other.
The implementation assumes that the owners
into a
mode where the machines respond
of idle workstations voluntarily put their machines
to requests for bids
from the network.
Shock and Hupp
[Sho82| describe an alternative mechanism for locating and activating idle machines on a network
without their owners' intervention.
Several augmentations of the
failures
to
and delays,
(2)
DSP protocol were made
to account for (1) processor or
the unique status of the "local" processor, and
(3)
human
communication
users
who might
try
"game" the system.
Unreliable processors
and communications
In addition to the messages involved in the bidding cycle, clients periodically query the contractors to
which they have sent tasks about the status of the tasks.
any other message
in the DSP), the client
If
a contractor fails to respond to a query (or
assumes the contractor has
failed.
Failures might result
from hardware or software malfunctions or from a person preempting a machine
any
for other uses.
In
case, unless the task description specifically prohibits restarting failed tasks, the client
automatically reschedules the task on another machine.
periodic queries from one of its clients, the contractor
aborts that client's task.
Similarly,
if
a contractor
assumes the client has
failed
fails to
receive
and the contractor
21
Since a task can be restarted several times during
its
lifetime (e.g
,
because of processor failures or
because of a late bid improvement), there can be .different "incarnations" of the same process [Nel81|.
Because messages can sometimes be delayed or
to earlier
guaranteed
to
confusions might result from messages referring
To prevent such confusions, each task
incarnations of a current task.
identifier that is
lost,
is
assigned a task
be unique across time and space. In order to do this, a timestamp of
the most recent "milestone event" in the
life
of the process
is
included in the task identifier.
Milestone events are the sending of either a request for bids or a task message concerning the task.
Both these events render obsolete
to
DSP messages
all
previous
DSP messages concerning the
task. Before responding
about a particular task, therefore, both clients and contractors check
message concerns the most recent incarnation of the
to
be sure the
task. (These task identifiers serve the
same
purpose as the call identifiers used by Birrell and Nelson [Bir84]).
In view of benefits described above from using "late bid
improvement" rescheduling
in lightly loaded
systems (as ours was), and in view of the unpredictable delays in message transmission, the
Enterprise system implements a variation of the
DSP
always accepted, rather than waiting any fixed time
significantly better, the task
is
protocol in which the first bid for a task is
to
evaluate bids.
Then
if
a later bid is
rescheduled.
The "remote or local" decision
With the variation of DSP just described,
client
first
machine
offers to be its
own
if
the local machine submits bids for
contractor), then the local
machine
will
its
own
tasks
(i.e.,
the
presumably always be the
bidder and will therefore receive every task. To prevent this from happening, the client waits for
other bids during a specified interval before processing
assumed
to
its
own
bid.
Since contractor machines are
be processing tasks for only one user at a time, the client machine's
inflated by a factor that reflects the current load on the client machine.
can express their willingness
to
(Human
own
bid
is
also
users of a processor
have tasks scheduled locally by setting either of these two
parameters.)
"Gaming' the system
If
people supply their
own estimates
of processing times for their tasks
also used to determine priority, there
is
and these time estimates are
a clear incentive for people to bias their processing time
estimates in order to get higher priority. To counteract this incentive, the current implementation of
Enterprise has an "estimation error tolerance" parameter.
was estimated
to take (i.e.,
more than the estimation error
If a
task takes significantly longer than
it
tolerance), the contractor aborts the task
22
and
notifies the client that
it
was "cut
off."
This cutoff feature prevents the possibility of a few people
or tasks monopolizing an entire system.
Conclusion
Any
designer of a parallel processing computing system, whether the processors are geographically
distributed or not,
must solve the problem of scheduling tasks on processors.
presented a simple heuristic method for solving this problem and analyzed
simulation studies of a wide variety of situations. This scheduling heuristic
decentralized implementation in which separate decisions
processors lead to a globally coherent schedule.
Our
of this and similar heuristics in such a situation.
from sharing tasks among processors
benefits are
still
present even
in
made by a
(4)
its
we
performance with
particularly suited to a
set of geographically distributed
results were encouraging about the desirability
(1)
substantial performance improvements result
systems with more than light loads;
when message delay times are as much
(2) in
many
cases, these
as 5 to 20 percent of the average
task processing time; (3) the additional benefits from pooling tasks
machines are small; and
is
In this paper,
among more than
large errors in estimating task processing times cause
little
8 or 10
degradation
in scheduling performance.
Finally,
we described a prototype system
for personal
workstations on a network in which programs
can easily take advantage of the
maximum amount of processing power and
a network at any time, with
extra cost
little
when
parallelism available on
there are few extra machines available.
Acknowledgements
The
first
part of this work was performed while three of the authors (Malone, Fikes, and Howard)
were at the Xerox Palo Alto Research Center. The work has been supported by the Xerox Palo Alto
Research Center, the Xerox University Grants Program, and the Center
for
Information Systems
Research, MIT. Portions of this paper appeared previously in Malone, Fikes, and
The authors would
like to
Howard
([Mal83]).
thank Michael Cohen, Randy Davis, Larry Masinter, Mike Rothkopf,
Vineet Singh, Henry Thompson, and Bill van Melle for helpful comments. They would also like
thank Rodney Adams and--especiaIly--Debasis Bhaktiyar
results are reported here.
for
to
running many of the simulations whose
24
References
[Arr60]
& Hurwicz, L.
Decentraliztion and computation in resource
(Ed.) Essays in Economics and Econometrics.
Chapel Hill: University of North Carolina Press, 1960, pp. 34-104
(Reprinted in K.J. Arrow and L. Hurwicz (Eds.) Studies in resource
Allocation Processes. Cambridge: Cambridge University Press, 1977, pp
Arrow, K.,
allocation. In
R.W. Pfouts
41-95).
[Arr71]
[Ber82]
Arrow, K., & Hahn,
Holden Day, 1971.
F.
General Competitive Analysis. San Francisco,
Berhard, R. Computing at the speed limit.
IEEE Spectrum, July
C A:
1982, 26-
31.
[Bir84]
Birrell, A. D.,
and Nelson,
B. J.
Implementing remote procedure
calls.
ACM Transactions on Computer Systems. 1984, 2(1), 39-59.
[Bir82]
Birrell, Andrew D., Levin, Roy, Needham, Roger M., Schroeder, Michael
D., Grapevine: An Excercise in Distributed Computing. Communications
ofthe
25(4), April 1982.
ACM,
[Bog80]
Boggs, David R., Shoch, John F., Taft, Edward A., Metcalfe, Robert M.,
Pup: An Internetwork Architecture. IEEE Transactions on
Communications, COM-28, (4), April 1980.
[Bri73]
Brinch Hansen, P., Operating Systems Principles. Prentice-Hall,
Englewood Cliffs, New Jersey, 1973.
[Bru74]
Bruno, J., CofTman, E. G., & Sethi, R. Scheduling independent tasks to
reduce mean finishing time. Communications of the ACM, 1974, 17, 382-
Inc.,
387.
[BrySl]
Bryant, R., & Finkel, R. A stable distributed scheduling algorithm.
Proceedings of the Second International Conference on Distributed
Computer Systems, April 1981.
[Cho79]
Chow, Y. and Kohler, W. Models
for
dynamic load balancing in a
IEEE Transaction on
heterogeneous multiple processor system.
Computers. May 1979, C-18.
[Cof73]
Coffman, Edward G., Jr., and Denning, Peter J., Operating Systems
Theory. Prentice-Hall,
[Con67]
Inc.,
Englewood
Cliffs,
New Jersey,
1973.
R. W., Maxwell, W. L., Miller, L. W. Theory of Scheduling.
Addison-Wesley Publishing Company, Reading, Massachusetts, 1967.
Conway,
[Dav81a] Davis, E. and Jaffe, J. M. Algorithms for scheduling tasks on unrelated
processors. Journal of the ACM, 1981 (October), 28, 721-736.
[DavSlb] Davies, D., Holler, E., Jensen, E., Kimbleton, S., Lampson, B., LeLann, G.,
Thurber, K., and Wateon, R. Distributed systems-Architecture and
implementation: Lecture notes in computer science, vol. 105. New York:
Springer- Verlag, 1981.
[Dav83]
Davis, R., and Smith, R. G., Negotiation as a Metaphor for Distributed
Problem Solving. Artificial Intelligence. Volvmie 20 Number 1, January
1983.
[Ens81]
Enslow, P.
11,
[Far72]
What is a distrubted data processing system?. Computer, vol.
June 1980.
Farber, D. J. and Larson, K. C. The structure of the distributed computing
system-- Software. In J. Fox (Ed.), Proceedings of the Symposium on
Computer-Communications Networks and
Teletraffic,
Brooklyn,
NY:
Polytechnic Press, 1972, pp. 539-545.
[Far73]
Farber, D.,etal. The distributed computer system. Proceedings of the 7th
Annual IEEE Computer Society International Conference, February 1973.
[Fri76]
Friedman, D. & Wise, D. CONS should not evaluate its arguments.
Automata, Languages and Programming, Edinburgh University Press,
1976,257-284.
[Gaj85]
Gajski,
D aand Peir, J.
Essential Issues in Multiprocessor Systems.
IEEE
Computer, June 1985, pp. 9-27.
[Gaf78]
Gafarian, A. V., Ancker, C. J., & Morisaku, T. Evaluation of commonly
used rules for detecting "steady state' in computer simulation. Nav. Res.
Logist. Q.. 1978, 25, pp. 511-529.
[Gla79]
Glazebrook, K. D. Scheduling tasks with exponential service times on
parallel processors. Journal of Applied Probability, 1979, 16, 685-689.
[Gon77]
Gonzales, T., Ibarra, O. H., and Sahni, S. Bounds for LPT schedules on
uniform processors, SI
Journal of Computing, 1977,6, 155-166 (as cited
AM
by[Jaffee]).
[Gra69]
Graham, R. L. Bounds on multiprocessing timing anomalies. SIAM
Journal of Applied Mathematics, 1969 (March), 17, 416-429 (summarized
in Coffman and Denning, pp. 100-106.).
[Hen76] Henderson, P. & J. Morris, Jr. A lazy evaluator. Record Third Symposium
on Principles of Programming Languages, 1976, 95-103.
[Iba77]
and Kim, C.E. Heuristic algorithms for scheduling
independent tasks on nonidentical processors. Journal of the ACM, 1977
Ibarra, 0. H.
(April), 24, 280-289.
M. Efficient scheduling of tasks without full use of processor
resources. Theoretical Computer Science, 1980, 12, 1-17.
[JafSO]
JafTe, J.
[Jon80]
Jones, A. K., and Schwarz, P. Experience Using Multiprocessor Systems A Status Report. Computing Surveys, Volume 12, Number 2, June 1980.
26
[KleSl]
Kleinrock, L., and Nilsson, A. On optimal scheduling algorithms for timeshared systems. Journal of Association of Computing Machinery, 28, 3, pp.
477-486, July 1981.
[Kor82]
Komfeld, W. A. Combinatorially implosive algorithms. Communications
of the
ACM,
1982 (October), 25, 734-738.
[Kri71]
Kriebel, C. H., & Mikhail, O. I. Dynamic pricing of resources in computer
networks. In C. H. Kriebel, R. L. Van Horn, & J. T. Heames (Eds.),
Management Information Systems: Progress and Perspectives. Pittsburgh:
Carnegie Press, 1971, pp. 105-124.
[Kur85]
Kurose, J., Schwartz, M., Yemini, Y. A microeconomic approach to
decentralized optimization of channel access policies in multiaccess
networks. IEEE 1985.
,
[Lani68} Lampson, B.
W. A scheduling philosophy for multiprocessing systems.
Communications of the ACM, 1968 (May),
[Lar82]
Larsen, R., McEntire,
Silver Spring,
P.,
and
11, 347-359.
O'Reilly, J. Tutorial: Distributed control.
MD: IEEE Computer Society Press,
1982.
& Carson, J. S. A sequential procedure for determining the
length of a steady-state simulation. Operations Research, 1979, 27, pp.
1011-1025.
[Law79] Law, A. M.,
[Law82a]Law, A. M., & Kelton, W. D. Simulation modeling and analysis.
York: McGraw-Hill, 1982a.
New
& Kelton, W. D. Confidence intervals for steady-state
simulaitons, O: A survey of sequential procedures. 1982b Management.
Science, vol 28, 5. May 1982, pp. 550-562.
[Law82b]Law, A. M.,
[Liv82]
Livny, M., & Melman, M. Load balancing in homogeneous broadcast
distributed systems. Proceedings of the Computer Network Performance
Symposium, Maryland, 1982.
[Mal82]
Malone, T. A decentralized method for assigning tasks to processors.
Research meorandum, Cognitive and Instructional Sciences Group, Xerox
Palo Alto Research Center, Palo Alto, Calif., August 9, 1982
[Mal83]
T., Fikes, R., Howard, M., Enterprise: A market-like task
scheduler for distributed computing environments. Working paper, Xerox
Palo Alto Research Center, Palo Alto, CA, October, 1983 (Also available as
CISR
# 1 1 1 Center for Information Systems Research, Massachusetts
Institute of Technology, Cambridge, MA, October, 1983).
Malone,
WP
,
[Mai 86] Malone, T. W. and Rothkopf, M. H. Strategies for scheduling parallel
processing computer systems. Paper in preparation, Sloan Scnool of
Management, MIT.
[Men85] Mendelson, H. Pricing computer services: Queueing effects.
Communications of the ACM, 28,3, March 1985.
27
[Met76]
Metcalfe, R. M., and Boggs, D. R., Ethernet: distributed packet switching
for local computer networks. Communications of the ACM. 19 (7), July
1976.
[Nel81]
Nelson, B.J. Remote Procedure Call. Xerox Palo Alto Research Center,
CSL-81-9, May 1981.
[Nil80]
Nilsson.N.J. Principlesof Artificial Intelligence. Palo Alto, CA: Tioga
Publishing Co., 1980.
[Ram84] Ramamritham, K. and Stankovic, J. Dynamic task scheduling
distriubted hard real-time systems. IEEE Software, July 1984.
[Sau81]
Sauer, C. H.
& Chandy, K. M.
Englewood Cliffs,
[Sch84]
Computer Systems Performance Modeling.
N.J.: Prentice Hall, 1981, pp. 296-297.
Schroeder, M., Birrell, A., and Needham, R. Experience With grapevine:
of a Distributed System.
Transaction on Computer
Systems. 1984, 2(1), 3-23.
ACM
The Growth
[Sho82]
in
WORM
Programs - Early Experience
Shoch, John F., Hupp, Jon A., The
with a Distributed Computation. Communications of the ACM, 25(3),
March 1982.
[Sin85]
Singh, V. & Genesereth, M. A variable supply model for distributing
deductions. Proceedings of the International Joint Conference on Artificial
Intelligence, August 1985, Los Angeles, CA.
[Smi80]
Smith, R. G., The Contract Net Protocol: High-Level Communication and
Control in a Distributed Problem Solver IEEE Transactions on Computers
Volume C-29 Number 12, December 1980.
[Smi81]
Smith, R. G. and Davis,
R.,
Frameworks for Cooperation
in Distributed
Problem Solving. IEEE Transactions on Systems, Man. and Cybernetics,
VolumeSMC-11 Number 1, January 1981.
[Sta84]
J. and Sidhu, I. An adaptive bidding algorithm for processes,
and distributed groups. In Proceedings of the Fourth Interational
Conference on Distributed Computing Systems, May 1984.
Stankovic,
clusters
[Sta85]
Stankovic, J. An application of bayesian decision theory to decentralized
control of job scheduling. IEEE Transactions ofConputers, 1985, C-34, 2,
pp. 117-130.
[SRC85] Stankovic, J., Ramaritham, K., and Cheng, S. Evaluation of a flexible task
scheduling algorithm for distributed hard real-time systems. IEEE
Transactions on computer, C-34, 12, December 1985.
[Sto77]
Stone, H. Multiprocessor scheduling with the aid of network flow
algorithms. IEEE Transactions on Software Engineering, vol Se-3,
January 1977.
28
[Sto78]
Stone, H. and Bokhari, S. Control of distributed processes. Computer, vol.
11, pp. 97-106, July 1978.
[Sut68]
Sutherland,
A
I. E.
futures market in
the ACM, 1968 (June), 11,449-451.
computer time. Communications of
[Ten81a] Tenney, R., Strategies for distributed decisionmaking, IEEE Transactions
on Systems, Man and Cybernetics, vol. SMC-11, pp. 527-538, August 1981.
[Ten81b] Tenney, R. and Sandel, Jr., N. Structures for distributed decisionmaking.
IEEE Transactions on Systems, Man and Cybernetics, vol. SMC-11, pp.
517-527, August 1981.
[Tho83]
Thompson, H. Remote Procedure Call. Unpublished documentation
Interlisp-D system, Xerox Palo Alto Research Center, Palo Alto, CA;
for
January, 1983.
[Van81]
Van der Heyden,
L. Scheduling jobs with exponential processing and
arrival times on identical processors so as to minimize the expected
makespan. Mathematics of Operations Research, 1981,6,305-312.
[VntSl]
Van Tilborg, A. M., & Wittie, L. D. Distributed task force scheduling in
multi-microcomputer networks. Proceedings of the National Computer
Conference, 1981, 50, 283-289.
rWeb82] Weber, R. R. Scheduling jobs with stochastic processing requirements on
parallel machines to minimize makespan or flowtime. Journal of Applied
Probability, 1982, 19, 167-182.
[Wit80]
Wittie, L. and van Tilborg, A. MICROS, A distributed operationg system
for micronet, A reconfigurable network computer. IEEE Transactions on
Conputing,
vol.
C-29, December 1980.
cv
Table
1
Mean flow times and 90% confidence intervals for the distributed scheduling
protocol in various situations (different network configurations, system loads, and
accuracies of processing time estimates)
90%
Network
Configuration
Utilization
30
Table
50%
Network
Configuration
1
(cont.)
Utilization
31
Table
10%
Network
Configuration
1
(cent.)
Utilization
32
Table 2
Effect on mean flow time of adding
processing capacity while keeping utilization constant
(Random sequencing and SPT sequencing)
Utilization
50%
10%
90%
NO. of
machines
Random
SPT
Random
SPT
Random
SPT
66.64
61.28 ± 3.04
120.00
101.60 t 5.92
600.00
245.20 ± 18.16
60.60
57.44 ± 2.64
80.00
74.28 ±5.12
315.79
150.92 + 10.28
60.01
57.78 ± 2.42
65 22
65.04 ± 2.74
178.16
107 40 t 6 34
60 00
60.43 ± 2.60
60.89
60.66 ± 2.67
112.61
81.14 ± 2.52
33
Request for Bids
Acknowledgement
S:;i,
Bid
v."fl««fr^'^'*.
i
^
"W^O^
^
CONTRACTOR
MACHINE
CLIENT
MACHINE
Figure
Messages
in
1
the Distributed Scheduling Protocol
34
80.0
M
70.0
__
:iOOt arror
e
3
60.0
X
n
50.0
I
o
40.0
?trftct Estimatts
w
300
I
m
20.0
e
10.0
0,0
0.0
9
.1
System
1
Utilization
Figure 2
Effect
on mean flow time of system utilization and accuracy of processing time
estimates (for DSP with network configuration 41111)
35
80.0
M
70.0
-_
60.0
-_
e
3
n
_
50.0
'
Sptid Rang*
•
40.0
w
30.0
•a Rangt
•
4
T
I
m
20
e
10.0
0.0
I
0.0
20
40
I
60
Number of Machines
Figures
Effect
on mean flow time of network confiauration
80
2
36
250.0
__
90X Utiliittion
M
e
3
n
200.0
__
150.0
I
o
w
sot Util Kation
100.0
m
50.0
lOX Uti
I
itation
0.0
0.0
2.0
40
6.0
Number of Machines
Figure 4
Effect
on mean flow time of adding processing capacity
while keeping overall utilization constant
DSP with perfect processing time estimates
and identical machines of speed 1)
(for
8.0
37
Mean Flow Time
O
1
o
z
o
3
it
oa —
<e«<
o
A
•^
»«
n
<t 1^
1 =
°
S n
3 3 *
i/»
Ifi-
5'
c
"
5
^
e
o
s
o
o
iS
o
o
o
38
80.0
M
70.0
-_
e
3
n
_
60.0
50.0
I
o
40.0
SOX jti
w
1
'zat ion
30.0
tot util i^atton
I
m
200
i
[
I
F
e
10.0
0.0
00
15
Late Bid
30
45
60
75
tmprovement Criterion
Figure 6
Effect on mean flow time of various settings
for "late bid improvement" criterion, ip
(DSP with perfect estimates of processing time.
Network configuration 41 1 1 1)
90
105
39
Poor Estimates
( i 100% Error)
Perfect Estimates
H
o
n
o
1-
•
<v
Q.
3
t
o o
I
T
i5
5
1
i«
w«
vO
a> («
"•
3X1
3
o»
S
c
3
M C
At
cr
c
-Si.
3
§5
3
c
2
v»
2
3
H
1-
1
01
^2
«^ n
» <
5
^
Q.
3
JO
ft.
rt>
3"
1 ^
c
—
n
b
3
n
II
ISJ
it
(t
^* fO
^*
^
w*
3"
«< Q.
3
e
5<*
H
321
5
c
o
30
at
3
re
II
S --
S
e
S
e
^
1
S
e
\
S
o
H
40
\
1
I
ENTERPRISE
System
Level 2
Level
Pup Internetwork Datagram
1
\
Level
Ethernet
\
Arpanet
Packet radio
Figure 8
Protocol layers used in the Enterprise
system
2384 067
B^SEN15|jIDue
MIT tlBR4RIES
3
DUPL
2
TOAD 00S7T021
^
Download