St. Lucie Public Schools Purchasing Department

advertisement

St. Lucie Public Schools

Purchasing Department

329 N.W. Commerce Park Drive, Bldg. C

Port St. Lucie FL 34986

Voice – (772)336-6980 Fax – (772)336-6985

SUPERINTENDENT

Michael J. Lannon

March 28, 2013

All Prospective Proposers TO:

FROM:

RE:

Lanaee Gilmore, CPPO, CPPB

Purchasing and Warehousing Director

RFP 13-08 – Disaster Recovery & Debris Removal Services

ADDENDUM 3 TO RFP 13-08, Disaster Recovery and Debris Removal Services

This addendum is issued as a part of the aforementioned RFP. The changes incorporated herein are an amendment to and supersede those conditions shown in the original solicitation. The Proposer shall acknowledge receipt of this addendum by signing this form and returning with their submittal. Failure to do so may subject Proposer to disqualification.

The list of questions presented below is a culmination of questions from prospective Proposers. Each question to follow has been answered as completely and accurately as possible.

Q1.

I have received and reviewed the subject RFP and have concerns/questions. First and foremost, 44 CFR Part

13_36(h), FEMA 325 and FEMA 9580.201 attachment 1 require that all such bids be accompanied by a 5% bid bond. The same references require that the successful contractor be required to post 100% payment and performance

bonds upon issuance of a notice to proceed. Unless I missed it, these omissions need to be corrected to avoid

reimbursement issues. Secondly, although the document refers to termination for cause, I did not notice a

termination for convenience clause required by FEMA 325 and the other references.

A1. All records estimates, bidding, awards, work, certifications, bonds and payments will be submitted following FEMA standards. Since FEMA Standards are evolving, District personnel will review those Standards as applicable, and will work with the Contractor to perform to FEMA’s guidelines. The awarded contractor by submission of their proposal agrees to adhere to all FEMA standards and guidelines.

Termination for convenience can be found on page 13 in section 11(B).

Q2. Regarding the scope of services, specific services, item 3 (page 22) indicates that stumps are to be measured three

(3) feet above normal ground level. This is error. The correct point of measurement is two (2) feet.

A2. Item 3, Page 22, the measure has been changed from three (3) feet to two (2) feet.

Q3. In attachment A, the matrix requests pricing at 100,000, 500,000 and 1,000,000 cubic yards. The question is how this will be implemented? Crews are generally paid by the cubic yard. When the project reaches 500,000 cubic yards plateau, will the new rate be applied retroactively or prospectively only?

A3. The new rate will be applied prospectively.

Q4. For item 3, payment for the processing is by the cubic yard while the loading and hauling of the residue is by the ton.

The trucks will be measured and certified for the cubic yard rates. Will the trucks hauling the residue have to be recertified by tare weight before hauling from the TDSRS? Or will scales at the disposal facility measure the weights both in and out of the facility to establish the tonnage? Will scales be required and, if so, who will provide and pay

Page 1 of 6

for them? What happens if the chips/residue are recycled rather than deposited in a landfill? Secondly, FEMA desires that the management of the TDSRS and the processing (i.e. grinding, burning) be separate cost items. In this cost item, are we to combine these two elements as a single cost?

A5. Cost of Services Attachment A has been revised. See attached.

Q6. The matrix does not include dangerous leaning trees or dangerous hanging limbs. Does the district not anticipate having any?

A6. The matrix has hazardous tree, stump and limb removal which covers leaning trees or dangerous hanging limbs.

Q7. How far will the debris crews have to travel to the TDSRS and final disposal facilities on average?

A7. Fifty (50) miles

Q8. Who will be responsible for the tipping fees? Will the school board pay them directly or will the contractor pay the fees to be reimbursed at actual cost?

A8. The contractor shall pay the fees to be reimbursed at actual cost. The contractor will be required to provide verification of costs.

Q9. General Conditions, page 3 #23 makes mention of certain bonding requirements. Is there a bonding requirement with the RFP that needs to be submitted with the proposal?

A9. Not at this time. All records estimates, bidding, awards, work, certifications, bonds and payments will be submitted following FEMA standards. Since FEMA Standards are evolving, District personnel will review those Standards as applicable, and will work with the Contractor to perform to FEMA’s guidelines. The awarded contractor by submission of their proposal agrees to adhere to all FEMA standards and guidelines.

Q10. How are fees (e.g. landfill tipping fees, analytical fees, permit fees) being addressed?

A10. The contractor shall pay the fees to be reimbursed at actual cost. The contractor will be required to provide verification of costs.

Q11. How are the costs for disposal of Hazardous Waste being addressed?

A11. The contractor shall pay the fees to be reimbursed at actual cost. The contractor will be required to provide verification of costs.

Q12. Please explain specifically how the pricing of one proposal will be evaluated against the pricing from another proposal, including the answer to these questions: a.

Will each pricing proposal be analyzed and refined to become one total number which can then be compared to the other proposals, and if so, what is the formula that will be used to derive that total number?

A12. Yes. For example: Total Possible Points = 10

*Formula used for cost evaluation: Lowest cost divided by each cost multiplied by total possible

points = earned points.

For example: $120,243.75 / $154,350 multiplied by 10 = 7.79 (cost score) b. Will some of the line item prices offered be excluded from the pricing evaluation? If so, which line items will be included and which will be excluded?

Page 2 of 6

A12. Day rates will not be used in the evaluation of costs. Day rates are informative for the District to evaluate the cost over a period of time that we will be incurring. This information is useful to our Finance Dept. for estimating and funding disaster projects that we will be reimbursed. c. Will extended totals (unit price multiplied by estimated quantity) be used to evaluate pricing, and if so, what estimated quantities and what line items will be used to derive the extended totals that will be evaluated?

A12.

See revised attachment A.

Q13 . Who will be responsible for tipping fees at the final disposal site?

A13. The contractor shall pay the fees to be reimbursed at actual cost. The contractor will be required to provide verification of costs.

Q14. Do the line items for stumps include the price to haul them away or will they be hauled away under line items for debris removal.

A14. Debris will be hauled away under line items for debris removal.

Please be advised of the following changes:

1.

On page 24, Section K, the language has been changed to:

K. OVERTIME LABOR RATES

Although some work may be required by the School Board at night and on weekends, and after normal school hours, prices submitted shall not increase based on when work is performed. Contractor shall bill at the same price as bid under the RFP.

**********RFP DUE DATE AND TIME REMAINS, APRIL 9, 2013 AT 3:00 P.M.**********

Attachment: Revised Attachment A – Cost of Services (dated March 28, 2013).

__________________________________________

Company Name

_________________________________________

Name (Please Print)

___________________________________________ __________

Signature (Authorized Representative of Company) Date

Page 3 of 6

5.

4.

3.

2.

School District of St. Lucie County RFP 13-08

Disaster Recovery and Debris Removal Services

REVISED (March 28, 2013)

COST OF SERVICES – ATTACHMENT A

1. Removal, loading, hauling of all eligible debris and/or residue from designated work zones within the TDSRS as specified.

Estimated Qty. Unit Unit Price Estimated Total

1,000,000

500,000

100,000

Cubic Yard

Cubic Yard

Cubic Yard

Total Estimated Cost

Management of all eligible debris and/or residue at all TDSRS sites.

Estimated

Qty.

1,000,000

Unit

Cubic Yard

Unit Price Estimated

Total

P rocessing of all eligible debris and/or residue at all TDSRS sites.

Estimated

Qty.

1,000,000

Unit

Cubic Yard

Unit Price Estimated

Total

Remove, load, haul and final disposal of all eligible debris and/or residue to a designated and authorized landfill or recycling facility from TDSRS.

Estimated Qty.

15,000

19,000

38,000

Unit

Cubic Yard

Cubic Yard

Cubic Yard

Unit Price

Total Estimated Cost

Estimated Total

Hazardous Stumps, as specified (to include any fill dirt and seeding required to level and restore the removal area).

Diameter Estimated Qty.

12” to 24”

25” to 48”

1,000

500

Greater than 48” 100

Unit

Each

Each

Each

Unit Price

Total Estimated Cost

Estimated

Total

Page 4 of 6

School District of St. Lucie County RFP 13-08

Disaster Recovery and Debris Removal Services

Cost of Services – Attachment A- March 28, 2013 (cont.)

5A. Personnel and Equipment

Cost Proposal/Hourly Cost

Personnel Hourly

Rate

Day Rate

1. Climber with gear

2. Superintendent with Truck

3. Foreman with Truck

4. Operator with Chainsaw

Total Estimated Costs (lines 1 thru 4)

5B. Survey Personnel with Equipment

Personnel Hourly

Rate

Day Rate

1. Inspector with Vehicle

2. Safety Superintendent

3. Laborer

4. Project Coordinator

5. Field Hazardous Material Manager

6. Hazardous Material Containment Area Manager

7. Field Project Supervisor

8. Hazardous Material Containment Area Foreman

9. Field Hazardous Material Technician

10. Hazardous Material Containment Area Technician

11. Health and Safety Specialist

12. Project Engineer

13. Equipment Operator

14. Asbestos Abatement Supervisor

15. Asbestos Abatement Worker

16. Asbestos Inspector

17. Truck Driver

18. Administrative Assistant

19. Clerical

Total Estimated Costs (lines 1 thru 19)

6. Other

Cost Proposal/Other Costs

Unit

1. Storm Sewer Cleaning

2. Dead animal removal and disposal

3. Fill dirt

4. Backhoe (or equivalent) rental fee

5. Chipper Rental

6. Track hoe Rental

Foot

Each

Pound

Hour

Hour

Hour

7. 40 Yard Dumpster Rental Daily

Total Estimated Costs (lines 1 thru 7)

Other Costs Not Listed

Hour

Hour

Unit Price

Page 5 of 6

School District of St. Lucie County RFP 13-08

Disaster Recovery and Debris Removal Services

Please note: Estimated quantities to be used for evaluation of line items 5A through 6 is one (1).

Day rates will not be used in evaluation of bid as per Addendum 3, but is required in bid submittal.

TOTAL BID PRICE (

SUM OF EXTENDED PRICE LINE ITEMS 1 THROUGH 6 excluding other costs not listed. Other cost not listed will be considered optional services.)

$________________________________________________________________

COMPANY NAME: ________________________________________________________________________________________

ADDRESS: _________________________________________________________________________________________________

CITY: ___________________________________________________________STATE:__________ZIP:_____________________

CONTACT PERSON: ______________________________________________________________________________________

TELEPHONE:______________________________________EMAIL ADDRESS____________________________________

AUTHORIZED SIGNATURE________________________________________________DATE_________________________

Page 6 of 6

Download