Office of Financial Management Washington State Major Project Status Report December 31, 2011 (Final) Agency Number: 699 Project Number: 062-697 School/Campus: Lake Washington Institute of Technology Project Title: Allied Health Building Bill Reference(s): 520-07-5207 Contact name, phone number, email: William F. Thomas Vice President, Administrative Services Lake Washington Institute of Technology (425) 739-8201 bill.thomas@lwtech.edu Agency: SBCTC Project Description: Construct 67,000 gross square feet of new instructional and support space for Allied Health education. The new facility is to provide classrooms, faculty offices, and laboratories for the education of nursing, medical assistants, medical transcription, physical therapy assistants, occupational therapy assistants,and funeral services. It will consolidate like instructional programs into a centralized location and enhance operational efficiency with improved circulation and resolution of long standing utility deficiencies. The project will provide a state of the art learning environment with a new network infrastructure, digital information system, and the facility will also provide a safe and secure environment with new security enhancements including a digital security system and a new building access control system. The Allied Health Building will provide functional, durable and flexible program space that meets the current and projected need for healthcare training and education in a modern facility supporting a critical services workforce that is in high demand within the Puget Sound Region. Square feet: Original: 67,000gsf Current: 83,500gsf Scope changes: Washington Network for Innovative Careers (WaNIC) joined with Lake Washington Technical College resulting in the need for the additional square footage to this building. This is a program consisting of seven K-12 Districts in the area. All of the additional square footage will be paid for by WaNIC. As a result, the project grew from 67,000gsf to 83,500gsf. The additional 16,500gsf will be used by WaNIC programs. 1 Project Total Cost: Phase Predesign Design Construction (MACC) Biennium 2005-07 2007-09 2009-11 Appropriation H51 I58 J00 Total Amount $ 197,000 $ 1,689,887 $19,769,500 $21,656,377 MACC = $ 19,405,000 Schedule: Pre-design Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule Jun 2006 Jul 2007 April 2009 June 2009 Jun 2010 Feb 2011 May 2011 Actual/Forecast Jun 2006 Jul 2007 July 2009 Aug 2009 Aug 2010 April 2011 December 2011 Variance (wks) 0 0 12 8 8 8 28 Project Status and discussion of Critical Path for Construction: Site: The size of the building site required a three story vertical solution to accommodate the programs. The site is restrained on all sides by existing construction and will require careful coordination during construction to maintain campus circulation and safety. Utilities: The primary electrical feeds to the existing building were relocated as part of the project which required careful coordination to avoid disruption of power to the existing buildings. Capacity of the serving utilities is adequate for the building but relocation of storm and sanitary lines was required. The electrical feeds and the sewer lines have been relocated successfully and are working as designed. Partnerships: The impact of partners in the building such as WaNIC has been approved and will be a part of this project. Occupancy: In April 2011, the College was issued the Temporary Occupancy Permit; the College has provided the Contractor the punchlist with an initial completion date of June 2011. Furnishings and program equipment are mostly delivered and setup. Classes began in the new facility Fall Quarter 2011. The punchlist work is in the final stages with the anticipated completion December 2011. Final Acceptance: final acceptance of the project has been delayed due to the longer than expected completion of the project punch list and the installation of the audio visual and security systems. It is estimated the project will be finalized and signed off in December 2011. 2 Contract Award History (Pre-Design and Design only) A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency $ $ $ $ Construction Contract (excl. sales tax) Bid Award Amount $ 19,769,500 Change Orders $ 2,864,896 Pending Changes $ 0 Total $ 22,634,396 Current Construction Contingency $ -0- 955,816 1,962,581 0 2,918,397 46,429 Potential for Project Cost Overruns/Claims The Allied Health Building Project faced a number of potential cost overruns and claims due to several factors. One of the factors impacting the project was the overall reduction in the project funding of approximately $3.66 million over the 2009-11 biennium. This was partially offset by $1.1 million from the construction contingency funds from the supplemental budget. The reductions based on the initial bid did not take into account the project items not included in the general contractor’s bid. These items included the necessary upgrades to the network infrastructure and phone system (total cost of $2.0 million) which were required in order to support the new facility. Additionally, not included in the contractor’s bid were the security systems (digital cameras and building access; cost $900,000). These items were not included for the contractor’s bid based on the College’s ability to manage these acquisitions and thereby save funds. In addition, other costs that are contributing to the total overruns include permit fees exceeding the budget allocation of $120,000, an unanticipated cost of $165,000 from King County for sewage treatment; and delay claims in the amount of $495,000 due to the underground water problems, underground utility relocation, and additional welding costs for the structure. However, due to prudent project and fiscal management, it is projected that total final project costs will exceed the current available project funds by approximately $500,000. Discussion of Project Quality Campus Image: The location of the Allied Health Building on the east side of the existing campus provides an opportunity to create a new image for the campus as it will be directly adjacent to the campus entry. The building will be more open and transparent than the existing campus buildings to provide a stronger visual connection to the activities occurring within the college to visitors entering campus. The exterior forms and materials will communicate the College’s commitment to technology, sustainability, and community. On-grade entrances: The building site and existing topography allows on-grade entrances for each of the three floors of the structure. We will maximize this opportunity to provide barrier-free access from the primary parking areas on campus. Multiple entrances also provide the opportunity to segregate student, public, and service entrances. 3 Enhanced Community Outreach: The new building with its health care programs provides an opportunity to alleviate growing needs for health care workers in the community and to expand partnerships with local providers for enhanced clinical services and educational opportunities. Flexibility in Educational Environments: The building will provide a variety of instructional spaces and specialized labs. These will be as flexible as possible to accommodate changes in educational delivery and technology necessary to reflect current practices in the health care delivery. Sustainability: The building design will reflect current and emerging sustainable design strategies, not only to meet the state mandated LEED certification goals but more importantly, to minimize operating costs and environmental impacts throughout the life of the building. Project Photographs 4