Office of Financial Management Washington State Major Project Status Report December 31, 2008 Agency Number: 699 Agency: SBCTC Project Number: 06-1-309 & 08-2-130 School/Campus Big Bend Community College Project Title: Fine Arts Addition & Site Improvement/Turn-Around for GTA Bus Stop Shelter Bill Reference(s): 488-05-855 Contact Name, phone number, email: Gail Hamburg, Vice President for Financial & Administrative Services 509-793-2002 gailh@bigbend.edu Project Description: In order to solve ADA access issues, the Fine Arts Program at Big Bend Community College (BBCC) was moved to a converted, metal-skinned, grounds shop located on “Vocational Row” remote to the campus core and other transfer programs. This project will create new space for the Fine Arts Department specifically designed for a Fine Arts Program. Additionally, this project will move the Fine Arts Department back to the Academic Core of the campus adjacent to other programs for the arts. Square feet: 11,000 Scope Changes: In April 2008, the contractor was awarded project 08-2-130 as a change order totaling $313,397 because it was related and adjacent to the Fine Arts Building. The budget was able to provide for site work, curbing and sidewalks, but there was not enough funding to pave the Turn-Around Road. Big Bend Community College did fundraising for paving. The change order was substantially completed by the end of June, 2008. The paving by the donor was complete by the end of September, 2008. Background from Previous Reports The original proposed solution was to remodel Building 1100 (Wallenstien Theater) and build an addition onto the Theater for the Fine Arts Department. Upon closer examination, it was determined that it would make more sense for long-term, campus development not to attach the Fine Arts Building to the Theater. The Theater, because of design, age and condition make the changes required for the creation of a Performing Arts Center inefficient and ineffective for both project cost and program usage. The project scope has changed to the following: 1. construct a 11,000 GSF Fine Arts Building adjacent to the Theater but not attached to the Theater 2. Remodel of only critical systems and areas in the existing Theater (Interior and entrance area of the lobby, HVAC system, light, and sound systems.) 3. Demolish Building 4400, a 2,575 GSF, Air Force gasoline station and garage constructed in 1956. Building 4400 was planned for removal as part of the new campus entry project. The new Fine Arts Building will be constructed on the site of the existing 4400 Building. Project Total Cost: Phase Predesign Design Construction * Other (Approp/NonApprop) Total Biennium Appropriation 05-07 05-07 07-09 H25 H25 141 Amount $ $ $ $ 450,275 3,247,725 231,625 3,929,625 * MACC Schedule: Background Information – The Theater Remodel was completed January 2007. Theater Remodeling Portion Theater Remodeling Portion Budget Variance Schedule Actual/Forecast (wks) Predesign Complete Jan – 05 Jun – 05 20 Start Design Oct – 05 May - 06 31 Bid Date May – 06 May – 06 0 Notice to Proceed Jun – 06 May – 06 -4 50% Complete Aug – 06 June – 06 -8 Substantial Completion Oct – 06 Sep – 06 -4 Final Acceptance Nov – 06 Jan – 07 8 Current Schedule as of 6-19-08 Fine Arts Portion Budget Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Schedule Jan – 05 Oct – 05 May – 06 Jun – 06 Nov – 06 Jan – 07 Mar – 07 Fine Arts Portion Variance Actual/Forecast Jun – 05 June - 06 July – 07 Aug – 07 Jan – 08 June – 08 June – 08 (wks) 20 34 64 60 108 112 116 Project Status and discussion of Critical Path for Construction: Current Project Status as of 12-31-08 This project was substantially complete by June 30, 2008 with the exception of landscaping, classroom flooring, furniture and road paving. BBCC did fundraising to cover some of the budget shortfall. The landscaping and part of the paving were complete by September 30, 2008. The Fine Arts Building was occupied for Fall Quarter, 2008. Exterior and interior pictures are attached (5). Background from Previous Reports As of June 11, 2008 this project is substantially complete. The project will be complete by the end of June, 2008 with the exception of landscaping, classroom flooring, furniture and road paving. BBCC is fundraising to cover the budget shortfall. Previous - The project is 50% complete. Structural masonry is complete. Structural steel erection is 70% complete and roof dry-in is started and scheduled to be completed by mid-February. Membrane roofing is scheduled to be complete by the end of February. Metal roofing will follow steel work and can occur independent of membrane roofing. Substantial Completion may occur ahead of schedule – target date June 30, 2008 Building permits were issued by Grant County Planning Department on June 18, 2007 for the fine arts portion this project. Bid documents are complete and the bid opening is scheduled for July 25, 2007. The estimated base bid cost range is $1,750,000 to $2,250,000 and the contract time is 300 days. Correctional Industries completed the demolition of Building 4400 March 15, 2006. The theater remodeling portion of this project was bid on May 10, 2006 and the notice to proceed was issued May 22, 2006 for a base bid of $199,000. As of June 30, 2006 the theater remodel was 60% complete and scheduled to complete September 1, 2006. The fine arts portion of this project is in design development phase and more alternates will be added to the bid package to accommodate inflation and the current high cost of materials and labor. It is anticipated that the project budget will require three lecture rooms in this building to be framed but left unfinished until further funding is found. Even with three classrooms left unfinished, the building may have to be reduced in size by as much as 2,000 square feet. The Theater Remodeling portion of this project was substantially complete onschedule and ready for instruction by fall quarter 2006 with the following major exception: Grant County Public Utility District (GCPUD) was not able to install the larger transformer required to power the new electric boiler (the existing fuel oil burning boiler was replaced). GCPUD’s transformer installation delay required the college to rent a diesel powered generator for the month of October to supply heat to the building. Rental cost was $6,000 per month plus transportation from Tacoma, Washington which was supplied by the College Commercial Truck Driving School to cut costs. The GCPUD transformer was installed and the new electric boiler was brought on-line November 6, 2006. A punchlist inspection of the Theater Remodeling project was conducted on October 17, 2006 revealing compatibility problems between the dimming system and the ballasts for the newly installed house lights. Problems were also discovered with the plumbing from the new electric boilers to the heating coils. Temporary measures were designed and implemented to keep the building heated and lit. New ballasts for the lights were ordered but unavailable and plumbing corrections are in progress. Back ordered ballasts are projected to set back final project completion as much as two months. Contract Award History Theater Remodeling Portion Theater Remodeling Portion A/E Agreement Construction Contract (excl. sales tax) Original Agreement $ 173,054 Bid Award Amount $199,999 Amendments $ 0 Change Orders $ 2,246 Pending Changes* $ 0 Pending Changes* $ 25,500 Total $ 173,054 Total $227,745 Current Design Current Construction Contingency $ .00 Contingency $ 25,000 * Tax *Tax & Electrical Service Fine Arts Portion A/E Agreement Original Agreement Amendments Pending Changes* Total Current Design Contingency * Tax $ $ $ $ 243,866 135,832 379,698 $ $ 0 0 Fine Arts Portion Construction Contract (excl. sales tax) Bid Award Amount $2,513,800 Change Orders $ 498,355 Pending Changes $ 0 Total $3,012,155 Current Construction Contingency $ 0 $ 243,985 Potential for Project Cost Overruns/Claims The contractor was awarded project 08-2-130 as a change order totaling $313,397 because it was related and adjacent to the Fine Arts Building. The budget was able to provide for site work, curbing and sidewalks, but there was not enough funding to pave the Turn-Around Road. Big Bend Community College is fundraising for paving. The change order will be substantially completed by the end of June, 2008. The budget for the Fine Arts Building was not adequate to fund landscaping, furniture and some flooring. The BBCC Maintenance & Operations Department will complete landscaping for the building, floors to the three classrooms will be unfinished (raw concrete) and BBCC is fundraising for furniture. Discussion of Project Quality Both the design consultant, Bernardo Wills Architects, and the general contractor, T.W. Clark, provided extraordinary service through excellent collaboration with each other and the college. This is the smoothest running capital project ever experienced by BBCC. The building is affordable, sustainable and soundly built. Aesthetically, this building is compatible with rest of the campus and it has been completed on schedule. Background from Previous Reports The building will be designed for flexibility and long-term effectiveness for Big Bend Community College. The bid documents will specify 2 multipurpose classrooms with a third lecture/lab style classroom. The design will accommodate adding graphic arts and computer assisted drawing classes/programs to the Art Department while providing room for growth of the Fine Arts Program. Project Photographs Photographs of site preparation are attached (8).