Office of Financial Management Washington State Major Project Status Report June 01, 2007 Agency Number: 699 Agency: State Board for Community & Technical Colleges Project Number: 02-2-684 Project Title: Bates Phase III Expansion New Bill Reference: 26-03X-749 Project Description: 1. Bates Technical College now requires students enrolled in degree programs to enroll in and to complete 5 credit hours each in Human Relations, Mathematics and Communications. There is currently no classroom space available for this purpose at South Campus and there is a short fall of program classroom space. By adding dedicated academic classrooms and additional program classroom space, this need can be accommodated. 2. Bates' programs in Home and Family Life and Biotechnology have demonstrated their requirement for additional program space for classrooms, workrooms, offices and computer training. Relocating these programs to the new facility will address the current deficiencies. 3. To support KBTC's mandate to deliver all the community and technical college telecourses, an Advanced Technologies Center is required at South Campus. Allocating space designed for this purpose will allow the college to move forward on this initiative as well as meet existing and future needs to provide distance education. 4. Bates Technical College must convert their television format to digital to maintain the ability to communicate with new mandated technology. This project addresses the need for this conversion. 5. There is currently no library at the South Campus. Providing a campus library not only provides for student needs but also addresses accreditation requirements for library services. 6. Biotechnology program space is inadequate for enrollment and cannot expand in current location. Existing space does not support curriculum demands. Relocating and increasing program space permits the college to overcome the space and curriculum needs. 7. South Campus circulation is hampered by an unresolved interface between truck traffic and pedestrian traffic. Relocating the truck driving circuit out of the campus core will dramatically reduce the conflict and create desirable circulation for both pedestrians and vehicles. 8. There is currently a significant shortfall in South Campus student parking. 156 stalls will be lost with the construction of the new building. Replacement of the lost stalls is essential for providing access. The College’s primary goals of this project are as follows: Address the student needs at South Campus by: • • • • • • • Providing classrooms for academic courses to enhance the educational process for career training students seeking technical degrees Providing the necessary facilities for the Biotechnology program Providing classrooms and faculty office space for the Home & Family Life program Providing access to critical library materials and resources Developing a high-tech interactive multi-purpose room and Advanced Technologies Center to support delivery of educational programming through DTV Providing a safer environment by moving Truck Driving track facility to proposed land purchase site. This will allow students with driving training experience without compromising the safety of campus pedestrians. Mitigate shortfall in parking by relocating existing parking that will be displaced by the new structure. Transition to Digital Television • Deliver high quality educational programming statewide • Meet FCC requirements to broadcast in digital • Provide industry standard training opportunities in broadcast Project Total Cost: Phase Predesign Design Construction* Other (Approp/Non Approp) Total Biennium 2001-03 2003-05 2005-07 2003-05 Appropriation F54 BH3G H01 BH5G Amount $ 94,346 $ 1,796,206 $ 15,168,902 $ 17,059,454 * MACC = $ 9,796,387 Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule June 02 September 03 September 05 November 05 June 06 November 06 January 07 Actual/Forecast June 02 October 03 August 05 October 05 August 06 January 07 March 07 Variance (wks) 0 4 (4) (4) (8) (8) (8) Project Status and discussion of Critical Path for Construction: Phase I of the project (relocating Truck driving training and site development) has been completed. The college is using the new areas of Phase I for parking and Truck Driving Training. Phase II (new building) construction is approximately 86% complete. All site work for the project is complete. Irrigation is installed and tested and landscaping is complete. Interior casework installation is near completion. Finish work is being performed throughout the building. Critical path items still pending are aluminum sills and lighting. Merit has provided a construction schedule that shows substantial completion in February of 2007. The following schedule has been modified from the previous version to reflect current project status. Task NTP Contract time (395 CD) Substantial Completion Punchlist/closeout (62 CD) Final Completion Start 10/24/05 10/24/05 Dec 06 Jan 07 March 07 Roofing Shell and siding Mechanical and Electrical Site work Interior Casework Painting Flooring Doors and hardware Ceiling tiles complete complete complete complete Finish 10/24/05 11/23/06 Dec 06 March 07 March 07 complete complete complete complete complete Contract Award History Pre-design A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency $ 94,346 $ 682,555 $ 366,695 $ not determined $ not determined $ Potential for Project Cost Overruns/Claims Phase II has no known issues at this time. Construction Contract (excl. sales tax) Bid Award Amount $9,539,476.00 Change Orders $ 160,000.00 Pending Changes $___________ Total $9,699,476.00 Current Construction Contingency $ Discussion of Project Quality This project is the first part of a college wide Master Planning effort. We included quality checks in our approach to Pre-design by utilizing a Facilities Planning Committee. The taskforce included representation from college administration, faculty, students, local community, and local jurisdictions and was facilitated by Mithun Architects. Input has been and will continue to be provided by all parties concerning the project. McGranahan Architects were selected as the A/E firm for design of the Expansion Project. The Facilities Planning Committee was expanded to include additional representation from the local community. An approach to building design around LEED (silver) certification has been utilized by the Architects to address environmental interests and Tacoma Power has participated to provide assistance to the project. The overarching architectural goal of the project has been to create a heart to the college campus while focusing on student achievements as they relate to building design, aesthetics, functional use, and maintainability. An additional design goal is to minimize as much as possible the interaction of pedestrian and vehicular conflict on the interior of the campus. Overall success of the project design will address site conditions as well as building conditions. Merit Company has been selected as the construction contractor for this project. Merit Company has been presented with all the goals for this project and has committed to provide a successful project toward this end. The project has got off to a great start and good progress is being made. At approximately 50% complete the quality of the project looks to be very good. The schedule has been impacted by delays due to weather and delays in receiving steel. Courtyard site work is scheduled for August, while school is out of session, to minimize pedestrian impact. Interior framing is nearly complete and exterior siding is applied to approximately 50% of the areas designated for application. At approximately 86% complete. The quality of workmanship on the project appears to be good to high. The project team consisting of McGranahan Architects, Merit Company, E&AS and Bates Technical College have operated with common goals and a team approach to resolving project issues. Change orders for the project are currently less than 1% of the MACC. After final acceptance of the project, the quality of workmanship is consistent with previous reports at a rating of good to high. Building acoustics are very good throughout the facility. There are some classrooms that the air volume level at supply vents are on the high end of acceptable but still meet specified standards. Physical appearance of the facility is very appealing and the design intent of the project has been accomplished. There are noticeable cracks in concrete exposed floors that appear to be surface level stress cracks and non-structural concerns. The floor slab was used as a layout surface for cast in place tilt up panels poured on site. This may have contributed, along with other factors, to the quantity of stress cracks that are visible. The building was designed to have exposed structural and non-structural elements throughout the facility. This works very well as many building users are enrolled in trade related training programs. Training programs are now operating out of the new building and the initial occupancy has gone off with a great start. Project Photographs (Attached) Project overview View of Brick Faced Library Wing View of Main Entrance from Courtyard Main Entrance Interior View Library View of Stacks, Study Carrels and Circulation Desk View from Second Floor Balcony to Ext. Courtyard