Projections for Planning Purposes Only B-1241 (C11)

advertisement
Projections for Planning Purposes Only
Not to be Used without Updating after November 1, 2005
Table 6.A Estimated costs and returns per ACRE
Cotton-Conventional Seed & Till-12 Row-Dryland
Lower Coastal Bend - 800# Yield Goal, TCE District 11, 2006
_______________________________________________________________________
ITEM
UNIT
PRICE
QUANTITY
AMOUNT YOUR FARM
_______________________________________________________________________
dollars
dollars
INCOME
Cotton Lint
lb
0.56
800.0000
448.00 _________
Cotton Seed
ton
90.00
0.6600
59.40 _________
--------TOTAL INCOME
507.40 _________
DIRECT EXPENSES
Custom
Fert. Application
Pick and Module
Ginning - Picker
Herbicides
Triflurilan
Cotton PreEmge Herb
Ctn-EarlySeasonHerb
Ctn-MidSeasonHerb
Defoliants-Picker
Insecticides
Fleahopper Control
Bollworm Control
TBW-BAW-AW-BW Ctrl
Boll Weevil Program
Seed
Cotton Seed
CottonSeed-InsectTrt
Fertilizer
24-8-0
Zinc
Other
pickup charge
crop ins/cotton
Growth Regulators
Mepiquat Chloride
Surfactant/Adjuvant
C.O.C.
Silicone Surfactant
OPERATOR LABOR
Implements
Tractors
Self-Propelled
DIESEL FUEL
Tractors
Self-Propelled
REPAIR & MAINTENANCE
Implements
Tractors
Self-Propelled
INTEREST ON OP. CAP.
acre
lintlb
lintlb
3.50
0.09
0.11
1.0000
800.0000
800.0000
3.50
72.00
88.00
_________
_________
_________
pt
lb
oz
oz
lb
2.13
7.00
70.50
1.11
38.00
3.0000
1.0000
0.1000
16.0000
0.2000
6.39
7.00
7.05
17.76
7.60
_________
_________
_________
_________
_________
oz
oz
oz
acre
0.72
2.89
1.48
23.14
3.2000
2.5000
9.0000
1.0000
2.30
7.23
13.32
23.14
_________
_________
_________
_________
0.35
0.15
52.8000
52.8000
18.48
8.24
_________
_________
222.00
2.25
0.1500
1.0000
33.30
2.25
_________
_________
2.80
13.22
1.0000
1.0000
2.80
13.22
_________
_________
oz
0.22
5.0000
1.10
_________
pt
oz
1.24
0.68
0.8125
1.6000
1.01
1.10
_________
_________
11.00
11.00
11.00
0.0150
0.3790
0.0720
0.16
4.18
0.80
_________
_________
_________
2.20
2.20
4.1859
0.6926
9.23
1.52
_________
_________
3.72
4.95
2.72
15.75
1.0000
1.0000
1.0000
1.0000
3.72
4.95
2.72
15.75
--------379.82
127.58
_________
_________
_________
_________
6.68
8.34
4.56
--------19.58
--------399.40
108.00
_________
_________
_________
thous
thous
ton
lb
acre
acre
hour
hour
hour
gal
gal
ACRE
ACRE
ACRE
ACRE
TOTAL DIRECT EXPENSES
RETURNS ABOVE DIRECT EXPENSES
FIXED EXPENSES
Implements
Tractors
Self-Propelled
ACRE
ACRE
ACRE
6.68
8.34
4.56
TOTAL FIXED EXPENSES
TOTAL SPECIFIED EXPENSES
RETURNS ABOVE TOTAL SPECIFIED EXPENSES
1.0000
1.0000
1.0000
_________
_________
_________
_________
_________
RESIDUAL ITEMS
Management Charge
%
507.40
0.0500
25.37 _________
RESIDUAL RETURNS
82.63 _________
Land Charge
acre
55.00
1.0000
55.00 _________
RESIDUAL RETURNS
27.63 _________
_______________________________________________________________________
Note: Cost estimates are based on producer and specialist input.
Information presented is prepared solely as a general guide & not intended to recognize or predict the costs & returns from any one operation.
These projections were collected & developed by TCE staff & approved for publication.
B-1241 (C11)
Projections for Planning Purposes Only
Not to be Used without Updating after November 1, 2005
Information presented is prepared solely as a general guide & not intended to recognize or predict the costs & returns from any one operation.
These projections were collected & developed by TCE staff & approved for publication.
B-1241 (C11)
Projections for Planning Purposes Only
Not to be Used without Updating after November 1, 2005
Table 6.B
Estimated resource use and costs for field operations, per ACRE
Cotton-Conventional Seed & Till-12 Row-Dryland
Lower Coastal Bend - 800# Yield Goal, TCE District 11, 2006
_______________________________________________________________________________________________________________________________________________
POWER UNIT COST EQUIPMENT COST
ALLOC LABOR
OPERATING/DURABLE INPUT
OPERATION/
SIZE/
POWER UNIT
PERF TIMES
-------------- -------------- ----------------------------------TOTAL
OPERATING INPUT
UNIT
SIZE
RATE OVER MTH DIRECT
FIXED DIRECT
FIXED HOURS
COST
AMOUNT PRICE
COST
COST
_______________________________________________________________________________________________________________________________________________
------------dollars----------dollars
---------dollars--------Stalk Shredder
24'
V Ripper
22'
Fert. Application
acre
24-8-0
ton
Zinc
lb
Triflurilan
pt
Field Cultivator
60'
Field Cultivator
60'
Planter
12R-30''
Cotton Seed
thous
CottonSeed-InsectTrt thous
Sprayer(600-825 Gal) 90'
Cotton PreEmge Herb lb
Sprayer(600-825 Gal) 90'
Ctn-EarlySeasonHerb oz
Cultivator
12R
Sprayer(600-825 Gal) 90'
Ctn-MidSeasonHerb
oz
C.O.C.
pt
Cultivator
12R
Sprayer(600-825 Gal) 90'
Fleahopper Control
oz
Mepiquat Chloride
oz
Sprayer(600-825 Gal) 90'
Fleahopper Control
oz
Sprayer(600-825 Gal) 90'
Mepiquat Chloride
oz
Bollworm Control
oz
Sprayer(600-825 Gal) 90'
TBW-BAW-AW-BW Ctrl
oz
Sprayer(600-825 Gal) 90'
Defoliants-Picker
lb
Silicone Surfactant oz
Pick and Module
lintlb
Ginning - Picker
lintlb
pickup charge
acre
Boll Weevil Program acre
crop ins/cotton
acre
MFWD 170
Track 300
0.069
0.080
1.00
1.00
1.00
Aug
Aug
Nov
2.17
3.90
1.42
1.99
0.83
0.19
1.40
0.35
0.06
0.08
0.76
0.88
6.58
7.31
1.0000
3.50
3.50
3.50
0.1500 222.00
33.30
33.30
1.0000
2.25
2.25
2.25
3.0000
2.13
6.39
6.39
Track 300 0.025 1.00 Nov
1.22
0.62
0.37
0.69
0.02
0.28
3.18
Track 300 0.025 1.00 Jan
1.22
0.62
0.37
0.69
0.02
0.28
3.18
MFWD 170
0.060 1.00 Mar
1.89
1.23
1.44
2.49
0.07
0.82
7.87
52.8000
0.35
18.48
18.48
52.8000
0.15
8.24
8.24
0.009 1.00 Mar
0.53
0.57
0.00
0.10
1.20
1.0000
7.00
7.00
7.00
0.009 1.00 Apr
0.53
0.57
0.00
0.10
1.20
0.1000 70.50
7.05
7.05
MFWD 170
0.060 1.00 Apr
1.89
1.23
0.26
0.53
0.06
0.66
4.57
0.009 1.00 May
0.53
0.57
0.00
0.10
1.20
16.0000
1.11
17.76
17.76
0.8125
1.24
1.01
1.01
MFWD 170
0.060 1.00 May
1.89
1.23
0.26
0.53
0.06
0.66
4.57
0.009 1.00 May
0.53
0.57
0.00
0.10
1.20
1.6000
0.72
1.15
1.15
2.0000
0.22
0.44
0.44
0.009 1.00 May
0.53
0.57
0.00
0.10
1.20
1.6000
0.72
1.15
1.15
0.009 1.00 Jun
0.53
0.57
0.00
0.10
1.20
3.0000
0.22
0.66
0.66
2.5000
2.89
7.23
7.23
0.009 1.00 Jul
0.53
0.57
0.00
0.10
1.20
9.0000
1.48
13.32
13.32
0.009 1.00 Jul
0.53
0.57
0.00
0.10
1.20
0.2000 38.00
7.60
7.60
1.6000
0.68
1.10
1.10
1.00 Aug
800.0000
0.09
72.00
72.00
1.00 Aug
800.0000
0.11
88.00
88.00
1.00 Aug
1.0000
2.80
2.80
2.80
1.00 Aug
1.0000 23.14
23.14
23.14
1.00 Aug
1.0000 13.22
13.22
13.22
------- ------- ------- ------- ------ ------------- -------TOTALS
18.42
12.90
3.72
6.68
0.46
5.14
336.79
383.65
INTEREST ON OPERATING CAPITAL
15.75
UNALLOCATED LABOR
0.00
TOTAL SPECIFIED COST
399.40
_______________________________________________________________________________________________________________________________________________
Note: Cost estimates are based on producer and specialist input.
Information presented is prepared solely as a general guide & not intended to recognize or predict the costs & returns from any one operation.
These projections were collected & developed by TCE staff & approved for publication.
B-1241 (C11)
Download