Statement of Thomas P. D’Agostino Deputy Administrator for Defense Programs

advertisement
Statement of Thomas P. D’Agostino
Deputy Administrator for Defense Programs
National Nuclear Security Administration
Before the
House Armed Services Committee
Subcommittee on Strategic Forces
April 5, 2006
Chairman Everett, Representative Reyes and members of the Committee, thank you for the
opportunity to appear before you today to discuss our plans to revitalize and transform NNSA’s
nuclear weapons infrastructure to make it fully responsive to national security needs. In this
effort, we have benefited greatly from the work of the Secretary of Energy’s Advisory Board
(SEAB) Task Force on the Nuclear Weapons Complex Infrastructure recently chaired by Dr.
David Overskei. I will report today on our plans to implement several of the Task Force’s
recommendations.
Introduction
The Department is committed to ensuring the long-term reliability, safety and security of the
nation’s nuclear deterrent. Stockpile stewardship is working; the stockpile remains safe and
reliable. This assessment is based not on nuclear tests, but on cutting-edge scientific and
engineering experiments and analyses, including extensive laboratory and flight tests of warhead
components and subsystems. Each year, we are gaining a more complete understanding of the
complex physical processes underlying the performance of our aging nuclear stockpile.
To assure our ability to maintain essential military capabilities over the long term, however, and
to enable significant reductions in reserve warheads, we must make progress towards a truly
responsive nuclear weapons infrastructure as called for in the Nuclear Posture Review (NPR).
The NPR and its follow-on assessments have led to conceptual breakthroughs in our thinking
about nuclear forces, breakthroughs that have enabled concrete first steps in the transformation
of those forces and associated capabilities. Very importantly, the NPR articulated the critical
role of the defense research and development (R&D) and manufacturing base, of which a
responsive nuclear weapons infrastructure is a key element, in the NPR’s New Triad of strategic
capabilities. We have worked closely with the Department of Defense (DoD) in establishing the
following guidelines for stockpile and infrastructure transformation:
•
•
•
•
•
ensure long-term safety, reliability and security of the nation’s nuclear deterrent,
support current stockpile while transforming to a future stockpile and infrastructure,
execute the Reliable Replacement Warhead (RRW) program to enable transformation to
a responsive infrastructure,
respond on appropriate timescales to adverse geopolitical change, or to technical
problems with warheads or strategic delivery systems, and
provide opportunities for a smaller stockpile to meet the President’s vision for the lowest
number of warheads consistent with the nation’s security.
2
Last Spring, in testimony to the Congress, Amb. Brooks described NNSA’s emerging 2030
vision for a transformed nuclear weapons stockpile and supporting infrastructure, both enabled
by RRW concepts. Today, I will address concrete steps that this Department is taking to realize
this vision and do so in the context of recommendations from the SEAB Task Force which have
greatly influenced our thinking on transformation.
Success in realizing our vision for transformation will enable us to achieve over the long term a
smaller stockpile, one that is safer and more secure, one that offers a reduced likelihood that we
will ever again need to conduct an underground nuclear test, one that reduces the nation’s
ownership costs for nuclear forces, and one that enables a much more responsive nuclear
infrastructure. Most importantly, this effort will go far to ensure a credible deterrent for the 21st
century, thus reducing the likelihood we will ever have to employ our nuclear capabilities in
defense of the nation.
DOE’s Response to the Recommendations of the SEAB Task Force
At the request of Congress, the Secretary empanelled a Task Force under the SEAB, chaired by
Dr. Overskei, to assess the implications of Presidential decisions on the size and composition of
the stockpile; the cost and operational impacts of the new Design Basis Threat (DBT); and the
personnel, facilities, and budgetary resources required to support a smaller stockpile. The review
evaluated opportunities for the consolidation of special nuclear materials (SNM), facilities, and
operations across the nuclear weapons complex so as to minimize security requirements and the
environmental impacts of continuing operations.
The SEAB Task Force concluded that: (1) the status quo is neither technically credible nor
financially sustainable; (2) the Cold War stockpile should be replaced with a sustainable
stockpile; (3) NNSA should complement past investment in the three design labs with
investment in a modern 21st century production center; and (4) consolidation of SNM is feasible
and will save money and reduce DBT risk. These insights and associated recommendations have
not only guided our thinking on transformation, but have provided concrete, practical steps that
in large measure we have incorporated into our overall plan for 2030. We have carefully
analyzed the Task Force’s key recommendations and discuss them briefly here; several are
addressed in more detail later in this statement.
We agree with the Task Force’s recommendation for the immediate design of a Reliable
Replacement Warhead (RRW). Two teams from our nuclear weapons labs—one from Los
Alamos and one from Livermore, both supported by Sandia—are engaged in an RRW design
competition that will be completed later this year. If RRW is technically feasible, we will seek
authorization to proceed to engineering development and production.
The Task Force recommends that NNSA aggressively pursue dismantlement as part of
deterrence. We agree and we are. Accelerated warhead dismantlements help to demonstrate a
responsive infrastructure, assure other nations we are not building up our stockpile, and reduce
the security risks associated with safeguarding retired weapons.
3
The Task Force recommends that the Department establish an Office of Transformation to serve
as agent for change. As a result, NNSA is creating such an office within Defense Programs both
to drive change and lead nuclear weapons complex transformation.
The Task Force recommends that we manage risk more effectively in our R&D and production
activities by employing cost-benefit analysis and risk-informed decisions. We agree this is a key
issue for transformation. By being too risk averse, we hurt productivity at our facilities without
improving safety and security. Rather, by implementing methods to better manage risk,
including analysis of the costs and benefits of the policies and procedures for ensuring safe and
secure operations at our facilities, we will get the job done and do so safely and securely.
There are two key recommendations from the Task Force with which we partially agree, but
differ on specifics. The most sweeping recommendation was for DOE to establish, by 2015, a
Consolidated Nuclear Production Center (CNPC) to be the single site for all R&D and
production involving significant amounts (i.e., Category I/II quantities) of SNM. The CNPC
would provide a production capacity of, among other things, about 125 pits per year to the
stockpile. We generally agree with the stated production capacity requirements, but disagree on
a single site for all Cat I/II SNM-related R&D and production. Our approach will leverage
previous and ongoing investments in the current production complex to establish distributed
production centers of excellence. It includes transition of all R&D and production involving Cat
I/II quantities of plutonium (except sub-critical experiments at the Nevada Test Site) to a single
site—the so-called consolidated plutonium center—in the early 2020s.
Following its logic, the Task force also urges consolidation of all Category I/II quantities of
SNM to the CNPC as a means of reducing DBT and security capital costs. We strongly agree
with the principle of SNM consolidation but, in our 2030 vision, we plan to consolidate SNM to
fewer sites, and fewer locations within sites, but not to a single site.
The Task Force has contributed valuable insights that have reinforced the urgency of changing
course. Among other things, it called for a more integrated, interdependent nuclear weapons
enterprise to support a transformed nuclear deterrent. In response, we are seeking improved
ways to achieve such an enterprise. In the near-term, we will add incentives to current contracts
to promote integration and interdependence, working towards fewer and more standard contracts
and establishing more uniform technical and business practices where appropriate.
What do we mean by “responsive?”
What do we mean by “responsive nuclear weapons infrastructure?” By “responsive” we refer to
the resilience of the nuclear enterprise to unanticipated events or emerging threats, and the ability
to anticipate innovations by an adversary and to counter them before our deterrent is degraded.
Unanticipated events could include complete failure of a deployed warhead type or the need to
respond to new and emerging geopolitical threats.
The elements of a responsive infrastructure include the people, the science and technology base,
the facilities and equipment to support a right-sized nuclear weapons enterprise as well as
practical and streamlined business practices that will enable us to respond rapidly and flexibly to
4
emerging needs. More specifically, a responsive infrastructure must provide proven and
demonstrable capabilities, on appropriate timescales, and in support of DoD requirements, to:
•
•
•
•
•
•
•
Ensure needed warheads are available to augment the operationally deployed force,
Identify, understand, and fix stockpile problems,
Design, develop, certify, and begin production of refurbished or replacement warheads,
Maintain capability to design, develop, and begin production of new or adapted
warheads, if required,
Produce required quantities of warheads,
Dismantle warheads, and
Sustain adequate underground nuclear test readiness.
We have worked closely with the DoD to establish goals for “responsiveness,” that is, timelines
to address stockpile problems or deal with new or emerging threats. For example, our goal is to
understand and fix most problems in the stockpile within 12 months of their discovery.
Alternatively, we seek an ability to design, develop, certify, and begin production of refurbished
or replacement warheads within 48 months of a decision to begin engineering development. In
both cases, these timelines would restore us to a level of capability comparable to what we had
during the Cold War. These goals will help guide our program by turning the concept of
responsiveness into a measurable reality.
Today’s nuclear weapons infrastructure and how we got where we are
Today’s nuclear weapons enterprise consists of eight, geographically separated sites that
comprise the R&D and production capabilities of the complex. There are three nuclear weapons
design laboratories: Los Alamos National Laboratory (LANL), Lawrence Livermore National
Laboratory (LLNL) and Sandia National Laboratories (SNL). In addition, numerous R&D
activities, including sub-critical experiments, are carried out at the Nevada Test Site (NTS). The
production complex, which has undergone significant downsizing since the end of the Cold War,
consists of the following “one of a kind” facilities: the Y-12 Plant (uranium and other
components), Pantex Plant (warhead assembly, disassembly, disposal, HE components), Kansas
City Plant (KCP) (non-nuclear components), and Savannah River Site (SRS) (tritium extraction
and handling). In addition, production activities for specific components occur at two national
labs: Sandia (neutron generators) and Los Alamos (plutonium/beryllium parts, detonators).
Each of these sites, with the exception of KCP, routinely conduct operations with substantial
quantities of plutonium, or highly-enriched uranium, or both. War reserve nuclear warheads are
assembled at Pantex. As such, these are some of the most sensitive facilities in the United States.
The increased anticipated threats to the physical security of weapons-usable nuclear materials,
post 9/11, have led to enormous increases over the past five years in the costs to secure the
complex. Any approach to transformation must address this problem.
Budgets for nuclear weapons programs declined precipitously following the end of the Cold
War, leading to a decline of the nuclear weapons enterprise. Sites were closed, downsized, or
consolidated, and restoration of capabilities at new sites took longer than planned. The lack of
new requirements on which to justify the cost of modernizing production capabilities (indeed, the
cancellation of several ongoing warhead development programs) coupled with significant
5
workforce attrition led to loss of key production capabilities needed to sustain the nuclear
weapons stockpile into the future. The introduction of new environmental and safety standards
and regulations, along with the requirement to clean-up facilities no longer needed, increased the
costs of doing business and limited productivity for any work that continued.
These factors, combined with the 1992 moratorium on underground nuclear testing, forced the
adoption of a new strategy. We would not continue the Cold War practice of replacing weapons
in the stockpile every 15-20 years; rather, we would emphasize science and technology in
seeking to extend the life of warheads in the existing stockpile beyond their originally planned
lifetime. This was the genesis of the program called science-based stockpile stewardship whose
major focus is predicting the effect of changes in an aging stockpile, providing a readiness
posture for refurbishing weapons as needed, and developing tools to assess and accept weapon
component changes.
Because we had, during the 1980’s, just completed a cycle of warhead modernization and
production, there was no strong driver to sustain production capabilities. The limited funding
available was focused primarily on the R&D complex in order to preserve the scientific and
technical capabilities that would be required to certify the future stockpile. As a result, the
production complex continued to be seriously underfunded and key capabilities further degraded.
As a result of decisions taken during the Cold War, today’s stockpile consists of highlyoptimized warheads designed to tight specifications (e.g., maximum explosive yield with
minimum size and weight). This was the most cost effective way to meet then existing military
requirements but also led to warheads that were designed relatively close to so-called “cliffs” in
performance. It also forced the use of certain hazardous materials that, given today’s health and
safety standards, cause warheads to be more costly to maintain and remanufacture. Maintaining
the capability to produce these materials causes the supporting infrastructure to be larger and
more costly than it might otherwise be, and certainly less responsive. If we were designing the
stockpile today under a test moratorium and to support an operationally-deployed force in which
most delivery systems will carry many fewer warheads than their maximum capacity, we would
manage technical risk differently, for example, by “trading” size and weight for increased
performance margins, enhanced safety and security, system longevity, and ease of manufacture
and certification.
Despite efforts over the past five years to restore key capabilities, our current nuclear weapons
infrastructure is not responsive. We had been unable to produce certain critical components for
warheads (e.g., plutonium parts, tritium) for many years. And today’s business practices—in
particular, the way we manage risk in authorizing potentially hazardous activities at our labs and
plants—have become ineffective, significantly degrading productivity at these facilities. The
story is not all bad, however, as we are making progress in several areas:
•
We restored tritium production in the Fall of 2003 with the irradiation of special fuel rods
in a Tennessee Valley Authority reactor, and anticipate that we will have a tritium
extraction facility on-line in FY 2007, well in advance of need.
6
•
We have largely restored uranium purification capabilities at our Y-12 plant, and are
modernizing other capabilities so that we can meet demanding schedules of warhead life
extension programs (LEPs), including, significantly, the B61 and W76 LEPs which are
scheduled to begin production in 2006 and 2007 respectively.
•
We are on track to deliver, in 2007, a certified W88 pit to the stockpile and restore a
small (10 pit/year) war reserve production capacity at LANL.
•
We have taken steps to recruit and retain a strong workforce with the right skills for the
focused mission.
•
We are devoting substantial resources to restoring facilities that have suffered from years
of deferred maintenance.
•
We seek improved ways to manage risk including rigorous analysis of the costs and
benefits associated with the means for ensuring safe and secure nuclear operations.
That said, much remains to be done to achieve stockpile and infrastructure transformation.
Among other things, we must maintain the strong scientific and technical base that is the
foundation of stockpile stewardship, while continuing efforts to restore the production complex.
Our challenge is to find ways to carry this out that reduce duplication of effort, support
consolidation of facilities and SNM, and promote more efficient operations complex-wide.
Concrete First Steps to the 2030 Stockpile and Infrastructure
The “enabler” for transformation is our concept for the RRW. The RRW will benefit from
relaxed Cold War design constraints that maximized yield to weight ratios. This will allow us to
design replacement components that are easier to manufacture; are safer and more secure;
eliminate environmentally dangerous, reactive and unstable materials; and increase design
margins thus ensuring long-term confidence in reliability and a correspondingly reduced chance
we will ever need to conduct a nuclear test for stockpile confidence. RRW, we believe, will
provide enormous leverage for a more efficient and responsive infrastructure and opportunities
for a smaller stockpile.
The 2030 nuclear weapons complex that we envision will thus support a smaller stockpile
consisting of warheads employing designs and technologies developed in the RRW program as
well as legacy warheads from the Cold War that have been refurbished in warhead life extension
programs. By that time, we will have gained enough experience with RRW to be in a position to
address whether that approach could provide sufficient stockpile diversity to permit evolution to
a stockpile based entirely on RRW designs. If this is the case, it will likely still take another
decade or more to complete that transition. Thus we must be prepared to support some number
of legacy warheads, and their associated LEPs, even as we seek to evolve to a stockpile
consisting primarily of RRW designs.
The envisioned 2030 infrastructure to support the stockpile would have the following
characteristics:
7
•
•
•
•
a strengthened, but consolidated R&D infrastructure;
a modern production complex with a consolidated plutonium center and increased
production throughput;
consolidation of Cat I/II materials to fewer sites and fewer locations within sites, and
streamlined business practices, including a more effective approach to managing risks
inherent to our operations.
The future R&D complex would retain two independent centers of excellence for nuclear
warhead design/development located at LANL and LLNL, each supported by Sandia for nonnuclear component design. At the same time, following the recommendations of the SEAB Task
Force, we plan to eliminate redundant capabilities and programs reflected in today’s complex.
For example, starting this year, major scientific and experimental facilities (e.g., Omega, Z, NIF,
DARHT) will become national, shared user facilities managed to benefit the entire complex.
Plutonium R&D involving Cat I/II quantities, currently carried out at both LLNL and LANL,
would be relocated to a single-site for plutonium R&D and production—the so-called
consolidated plutonium center. We intend to cease operations at the Tonopah Test Range by the
end of 2009 and exploit non-NNSA operated ranges to conduct required flight tests. In the
2020’s, large-scale hydrodynamic test facilities would transition to the NTS. In eliminating
redundancies, however, we must ensure that intellectual competition required for truly
independent peer review and assessment (critically important for an anticipated continued
moratorium on nuclear tests), and essential capabilities for nuclear weapons science and
technology, are preserved.
The future production complex will be smaller than today’s complex, distributed geographically,
and modernized with manufacturing, production, assembly/disassembly facilities and equipment
that employ 21st century “cutting edge” technologies. The following describes our proposed plan
for the 2030 complex.
•
Highly-Enriched Uranium (HEU) operations: All R&D and production involving Cat
I/II quantities of HEU would be carried out at a single site located at Y-12. Storage of
HEU, currently distributed at several locations within Y-12, would be consolidated to a
single facility on that site—the HEU Materials Facility (HEUMF). All production of
HEU parts and secondary assemblies, and associated disassembly of retired components,
would be carried out at a single facility that is currently being planned—the Uranium
Processing Facility or UPF. When these two facilities are jointly operating, it would
permit a major consolidation of activity within Y-12, enabling a substantial reduction in
floor space and substantially reduced annual costs for physical security at that site.
•
Plutonium operations: All R&D (except sub-critical experiments at NTS), surveillance,
and production involving Cat I/II quantities of plutonium would be transferred to the
consolidated plutonium center. The center would have a baseline production capacity of
125 pits per year net to the stockpile by 2022. The location of the center remains to be
determined but it would be situated at an existing Cat I/II site. To support interim pit
production needs prior to 2022, the plutonium facility at Tech Area 55 at LANL would be
upgraded by 2012 to a production rate of 30-50 war reserve pits per year continuing until
the center can meet the needs of the stockpile. To support plutonium operations at
8
LANL, and to absorb Cat I/II plutonium R&D currently being carried out at Building 332
at LLNL, the Chemistry and Metallurgy Research–Replacement (CMRR) facility would
be operated as a Cat I/II facility up to 2022. Once the consolidated plutonium center is
operational, all Cat I/II activities at TA-55 and CMRR would be transitioned there.
•
Tritium: Tritium production and stockpile support services would remain at the SRS.
•
Non-nuclear component production: Where possible and cost-effective, relatively
more non-nuclear components would be purchased from commercial suppliers compared
with today. A new, modern and efficient non-nuclear production facility would be in
operation by 2012 and sized to produce components and conduct operations that cannot
be purchased commercially (e.g. use control components and component final assembly).
•
Warhead assembly/disassembly operations involving HE and SNM: All weapons
assembly and disassembly would be carried out at Pantex modernized for increased
throughput for the long-term. The NTS Device Assembly Facility could be employed as
a backup for weapon assembly/disassembly to hedge against a single-point failure.
We have come to understand that an infrastructure that is not continuously exercised cannot be
responsive. In our vision, therefore, the entire complex would carry out a continuous cycle of
research, non-nuclear testing, weapons development, production, certification, surveillance,
retirement and dismantlement. This concept, I should add, is also a key element of the SEAB
Task Force’s vision for the 2030 complex.
Why not a CNPC?
We agree with much of what the SEAB Task Force recommends, except in one critical area—we
simply cannot commit to a CNPC at this point, even setting aside the serious question of political
feasibility. Let me explain why.
Briefly, the Task Force developed three “business cases” for transforming the nuclear weapons
complex, two of which are characterized as “high risk.” The preferred “least-risk” option would
accelerate site selection, environmental assessment, and CNPC construction leading to initial
operation in 2015, seek rapid consolidation of SNM thereafter, accelerate dismantlements, and
carry out early implementation of the other major transformation recommendations. According
to Task Force estimates, this option would require an additional $1B per year for weapons
program activities for the next ten years, leading to a net savings through 2030 of $15B in
comparison with the “flat budget” case.
But, accelerating a CNPC will not let us avoid near term spending to restore and modernize
production capabilities to meet LEP schedules and support the existing stockpile. Nor is it
plausible that a CNPC could be designed, built and operating by 2015. The Task Force
underestimates the challenges of transitioning a skilled workforce to a new location, particularly
in such unique and highly-skilled jobs as materials processing/component manufacture involving
HEU or plutonium. As a result, a CNPC approach would almost certainly lead to substantial
delays in completing LEPs, reduced support to the stockpile, and a resulting negative impact on
our nation’s deterrent. On the other hand, our approach achieves many of the benefits of the
9
Task Force’s approach—consolidation of SNM and facilities, integrated R&D and production
involving SNM, aggressive dismantlements—in a way that supports near-term national security
needs, is technically feasible, and is affordable over both the near and longer term.
Not “business as usual”
“Business as usual” is not sustainable, will not be successful, and cannot be the path we choose.
Indeed, our Complex 2030 vision represents a significant departure from the current strategy. I
will illustrate with a few key points.
Progress on RRW
Progress on RRW has been remarkable. Last year, the DoD and DOE jointly initiated an RRW
competition in which two independent design teams from our nuclear weapons laboratories—
LLNL and LANL both in partnership with Sandia and the production complex—are exploring
RRW options. A competition of this sort has not taken place in over 20 years, and the process is
providing a unique opportunity to train the next generation of nuclear weapons designers and
engineers. Both teams are confident that their designs will meet established requirements and be
certifiable and producible without nuclear testing. The program is on schedule—preliminary
designs are being completed. An intensive, in-depth peer review process is underway that will
lead to selection of a preferred option for engineering development.
Consolidation of Cat I/II SNM
We will start consolidating Category I/II SNM to fewer sites, and to fewer locations within sites,
in 2006. We will improve the security posture at our national laboratories by phasing out
operations involving Cat I/II quantities of SNM. This includes eliminating the need for a Cat I/II
SNM security posture at Sandia by 2008. Our plan is to remove all Cat I/II SNM from LLNL by
the end of 2014. By 2022, all R&D/production activities involving Cat I/II SNM would cease in
facilities operated by LANL. As that is accomplished, these labs could transition to a common
defense industry site security posture with reduced security costs. The consolidated plutonium
center, once operational, would host all R&D, surveillance, and manufacturing operations
involving Cat I/II quantities of plutonium. The Uranium Processing Facility (UPF) at Y-12
would consolidate existing HEU contained in legacy weapons, dismantle legacy warhead
secondaries, support associated R&D, and provide a long term capacity for new secondary
production. As a result, Y-12 would reduce its production and SNM storage footprint by about
90%, leading to significantly reduced costs for physical security at that site.
Consolidation of Facilities
In addition to the consolidation described above, NNSA plans to create a new, non-nuclear
component production facility by 2012 to significantly reduce infrastructure costs associated
with overall non-nuclear production. It plans to cease operations at the Tonopah Test Range
further driving cost effectiveness. LLNL would cease Cat I/II operations with plutonium and
close the Site 300 hydrodynamic test facility. The NTS would become the only site for largescale hydrodynamic testing including testing involving significant quantities of SNM and high
explosives. As a result of these plans—SNM consolidation, non-nuclear consolidation and the
construction of new more efficient, right-sized facilities—by the 2020s, the physical footprint of
the weapons complex would be substantially reduced.
10
Consolidated Plutonium Center
Our plan for a consolidated plutonium center is not based on the concept for a modern pit facility
(MPF) but on a far broader and more aggressive concept employing consolidation to a single site
of all R&D and production involving Cat I/II quantities of plutonium. It will be a small,
modular, and flexible facility. We will be engaging Congress as we develop this concept further
including budget profiles. The pit production capacity that we seek through the center is
essential to our long-term evolution to a responsive nuclear weapons infrastructure. Indeed, our
need to work with plutonium, and have capacity to manufacture pits in quantity, did not go away
simply because Congress zeroed the President’s request for the MPF project in the FY 06 budget.
The production capacity that can be established at TA-55—about 30-50 pits per year—is not
sufficient to meet anticipated future needs. There are three reasons why we believe this to be
true. First, our best estimate of minimum pit lifetime is 45-60 years. That estimate is under
review at our national laboratories. Nonetheless, we must anticipate that, as the stockpile ages,
we will need to replace substantial numbers of plutonium pits in stockpiled warheads. Second,
even if pits were to live forever, we will require substantial production capacity in order to
introduce, once feasibility is established, significant numbers of RRW warheads into the
stockpile by 2030. We should not assume that RRW could employ pit reuse and still provide
important efficiencies for stockpile and infrastructure transformation. Finally, at significantly
smaller stockpile levels than today, we must anticipate that an adverse change in the geopolitical
threat environment, or a technical problem with warheads in the operationally-deployed force,
could require us to manufacture and deploy additional warheads on a relatively rapid timescale.
All this argues for a production capacity that exceeds that planned for TA-55. Indeed, for
planning purposes, an annual production capacity of about 125 war reserve pits per year is about
right. The SEAB Task Force agrees with this estimate.
Driving the Science and Technology (S&T) Base
A robust scientific underpinning to stockpile stewardship and certification is essential for the
long-term future as some legacy Cold War warheads are retained for the next few decades and as
the stockpile is transformed via RRW. We must drive the science base even as we seek new
efficiencies. In this regard, we will develop a weapons program S&T roadmap by the end of
2007 defining the full set of capabilities needed to sustain the future stockpile. NNSA will
partner with the DOE Office of Science, and other national R&D sponsors, on leading edge
science and engineering needed both for national security and for broader scientific,
technological, and economic competitiveness.
Warhead Dismantlements
We will increase dismantlements planned for FY 07 by nearly 50% compared to FY 06. The
Department has committed to increasing average annual warhead dismantlements at the Pantex
Plant by 25% and has established an average annual secondary dismantlement requirement at Y12. More classified detail is available in the March 2006 Dismantlement Report to Congress.
Out-year funding in the FY 08 budget submittal will be consistent with the revised plan.
Warhead dismantlements are a key element of our strategy to ensure that stockpile and
infrastructure transformation is not misperceived by other nations as “restarting the arms race.”
We earlier noted that a continued commitment to a nuclear test moratorium is reinforced by our
11
efforts on RRW. In a similar way, our commitment to a smaller stockpile is made concrete by
our record of accelerated dismantlements.
Streamlined Business Practices and More Effective Risk Management
We plan to create a fully integrated, interdependent weapons complex with several uniform
business enhancements. We will manage risk, rather than seek to eliminate it, by applying riskanalytical techniques to programmatic, safety, security, and environmental decisions. We will
make the Phase X/6.X warhead acquisition process more relevant to stockpile and infrastructure
transformation. We will move to fewer and more standard Management and Operating (M&O)
contracts to capitalize on integration and interdependencies within the complex. In the nearterm, multi-site incentives will be added to the current contracts for a nuclear weapons complex
with shared risks and rewards. Contracts will reflect a new way of doing business, acquisition
activities will be centralized, and all large-scale experimental facilities will become user facilities
for the entire complex with committees to review priorities for work.
“Getting the job done”
Over the next 18 months, we will seek to demonstrate that the transformation path I have
described today is fully viable. We will continue support to the nuclear deterrent through
successful execution of the planned programs of refurbishment, surveillance, limited life
replacement, dismantlement, and other core activities. Among other things we will:
•
•
•
•
•
•
•
•
Eliminate the warhead surveillance backlog by the end of FY 2007,
Accelerate dismantlement of retired weapons (~50% increase from FY06 to FY07),
Streamline the safety authorization basis process while ensuring safe nuclear operations,
Increase Pantex throughput by the end of FY 2006,
Achieve first production for the B61 LEP in FY 2006, and the W76 LEP in FY 2007,
Deliver a certified war reserve W88 pit in FY 2007,
Demonstrate 10 W88 pits per year war reserve production capacity at LANL in FY 2007,
Extract tritium in 2007 from rods irradiated in a commercial nuclear reactor.
At the same time, we will demonstrate we are moving forward on transformation:
•
•
•
•
•
•
•
Complete the RRW study and move forward with concept,
Begin the National Environmental Policy Act (NEPA) process in 2006 to inform
decisions on the 2030 complex,
Begin to implement plans to ramp up to 30-50 pits per year at LANL by 2012,
Create an Office of Transformation within Defense Programs in 2006 to lead
transformation,
Acquire, in 2006, a systems engineering and integration contractor (such as being used
for managing LEPs) to support, more broadly, NNSA decision-making on weapons,
Drive uniformity in management of Readiness in Technical Base and Facilities (RTBF)
through common work breakdown structure, activity-based costing, and reducing federal
management to one program office in 2006,
Initiate a Supply Chain Management Center at Kansas City by the end of 2007 to
centralize some procurement activities consistent with the Task Force’s recommendation.
12
Via these near term actions, the NNSA will strengthen the confidence of the DoD, other key
stakeholders, and its own employees that we can achieve our longer-term objectives.
How the FY 07 budget request supports the vision for the 2030 complex
NNSA’s FY 07-11 budget proposal continues significant efforts to start us down the path to a
responsive nuclear weapons infrastructure. As the “enabler” for transformation, we are
requesting a ten percent increase in funding for the RRW program over last year. In addition,
various implementation actions for the 2030 strategy are being incorporated into existing
program elements that are part of the FY 07 budget request. Examples include:
•
•
•
•
•
•
•
•
Accelerated dismantlements including upgrades to Bldg 12-44 & 12-64 at Pantex,
Interim pit manufacturing capacity in the pit campaign,
Shipments to support material consolidation,
Highly Enriched Uranium Materials Facility (HEUMF),
Uranium Processing Facility (UPF),
Initial steps in facility transformation in the RTBF account,
LANL Criticality Experiments Facility relocation to NTS,
Component Evaluation Facility at the Pantex Plant.
Our FY 07 budget request is fully consistent with our 2030 vision—“responsive infrastructure”
is broken out as a new line in the Directed Stockpile Work budget category. This will partially
fund the continuing business case development needed to assure efficient implementation of
transformation, as well as immediate start of the NEPA process.
Conclusion
Transformation will, of course, take time. We are starting now with improving business and
operating practices, both in the federal workforce and across the nuclear weapons complex, and
through restoring and modernizing key production capabilities. Full infrastructure changes,
however, may take a couple of decades. The major challenge is to ensure a transition path to the
future that is both affordable and feasible while continuing to meet the near-term needs of the
current stockpile.
But let me take you forward 25 years when the Administration’s emerging vision for the nuclear
weapons enterprise of the future has come to fruition. The deployed stockpile—almost certainly
considerably smaller than today’s plans call for—has largely been transformed. RRWs have
relaxed warhead design constraints imposed on Cold War systems. As a result, they are more
easily manufactured at fewer facilities with safer and more environmentally benign materials.
These replacement warheads have the same military characteristics, are carried on the same types
of delivery systems, and hold at risk the same targets as the warheads they replaced, but they
have been re-designed for reliability, security, and ease of maintenance. Confidence in the
stockpile remains high without nuclear testing because RRW offers substantially increased
performance margins and because of our deeper understanding of nuclear phenomena enabled by
the stockpile stewardship program and the R&D tools that come with it.
By 2030, according to our vision, the deployed stockpile will be backed up by a much smaller
non-deployed stockpile than today. The elimination of dangerous and toxic materials has
13
enabled a more efficient and less costly production complex and obviated the need for large
numbers of spare warheads to hedge against reliability problems. The world in 2030 will not
have gotten more predictable than it is today. We still will worry about a hedge against
geopolitical changes and attempts by others to instigate an arms race. But that hedge is no longer
in aging and obsolete spare warheads but in the responsive infrastructure.
The 2030 responsive infrastructure will provide capabilities, if required, to produce weapons
with different or modified military capabilities. The weapons design community that was
revitalized by the RRW program will be able to adapt an existing weapon within 18 months and
design, develop, and begin production of a new design within 4 years of a decision to enter
engineering development—goals that were established in 2004. Thus, if Congress and the
President direct, we will be able to respond quickly to changing military requirements.
Security remains important in our future world. But the transformed infrastructure has been
designed with security in mind. More importantly, new, intrinsic features built into the growing
number of RRWs have improved both safety and security. In short, the vision I set forth is of a
world where a smaller, safer, more secure and more reliable stockpile is backed up by a robust
industrial and design capability to respond to changing technical, geopolitical or military needs.
This isn’t the only plausible future, of course. But it is the one we should strive for. It offers the
best opportunity for achieving the President’s vision of the smallest stockpile consistent with our
nation’s security. It provides a hedge against an inherently uncertain future. That’s why we are
embracing this vision of transformation. We should not underestimate the challenge of
transforming the enterprise, but it is clearly the right path for us to take.
Download