AN APPROACH FOR DEVELOPING COST ESTIMATING A PRELIMINARY METHODOLOGY FOR USCG VESSELS by MARK JAMES GRAY BaSC Mech. Eng., University of Water 1oo (1978) MaSC Mech. Eng., University of (1980) Water1oo SUBMITTED TO THE DEPARTMENT OF OCEAN ENGINEERING IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN NAVAL ARCHITECTURE AND MARINE ENGINEERING at the MASSACHUSETTS INSTITUTE OF TECHNOLOGY June 1987 0 Mark J. Gray, 1987 The author hereby grants to M.I.T. and to the U.S. Government permission tc reproduce and to distribute publicly copies of this thesis document in whole or in part. Signature of Author: Departmen f Ocean Engineering May 8, 1987 Certified by:- Ceifi -- e d. Henry . S. Marcus Associate Professor, Marine Systems Thesis Supervisor Accepted byl-----___+__ Ae yDouglas Carmicheal Chairman, Ocean Engino ring Departmental Committee Ir I AN APPROACH FOR DEVELOPING A PRELIMINARY COST ESTIMATING METHODOLOGY FOR USCG VESSELS by MARK JAMES GRAY Submitted to the Department of Ocean Engineering on May 8, 1987 in partial fulfillment of the requirements for the Degree of Master of Science in Naval Architecture and Marine Engineering ABSTRACT A study was done on methods used to estimate new ship construction costs during the feasibility/preliminary design phase. Costs were functionally related to SWBS weight groups and design and fabrication complexities. Other factors affecting shipyard construction costs include inflation, production learning and scheduling. Cost estimating relationships (CERs) are derived from historical data and are normalized to reflect technical cost trends in ship construction. The accuracy of the CERs is dependent upon the quality and range of the data. Cost risk or uncertainty can be quantified provided the probability distributions of the input data and CER regression coefficients are known. Five cost models are examined and found to be quite similar in their approach. Differences can be attributed to the different needs of the organizations that support their use. The models are applicable to a wide range of ship types and displacements, depending upon the data available during their development. Cost estimates during the feasibility design phase are thought to be accurate to within 10-20% of actual costs. In order for cost analysis to have a measurable impact during ship design, costing must be an integral part of the decisionmaking process. Before this can occur, management must have confidence in the costing team's ability to produce high quality esti mates. Thesis Supervisors Dr. Henry S. Marcus Title: Associate Professor of Marine Systems 2 ACKNOWLEDGEMENTS I would like to express my appreciation to the many people who assisted me in this research endeavor. Thanks to my thesis advisor, Professor Henry Marcus, not only for his guidance and direction, but also for allowing me the freedom to explore and learn on my own. Special thanks to Dennis Clark, Mike Jeffers and Bob Jones of the Costing and Design Systems Office, Code 1204 at David Taylor Naval Ship Research and Development Center (DTNSRDC), for their support and invaluable assistance in the research and for sharing with me their philisophical understanding of cost engineering in particular, and life in general. The assistance of Jim Herd, Tzee-Nan Lo and especially Ron Schnepper in the Ships Cost Analysis Division, NCA-2 at the Naval Center for Cost Analysis was greatly appreciated. Thanks also to Mike Hammes and Bob Simpson in the Cost Estimating & Analysis Division, SEA 017 at the Naval Sea Systems Command. These people gave freely of their time and effort during this study and supplied invaluable information. Several individuals in the United States Coast Guard deserve special mention. Thanks to Lt John Tuttle, Office of Acquisition and Lt Shawn Smith, Office of Research & Development for their continuing interest in this work, and to Richard Rounsevell of the Planning and Estimating Section in the Office of Engineering for his helpful suggestions. To all the people who spent the time talking and explaining the seemingly infinite aspects o cost estimating to me, thank you all. I hope that I have managed to include all of the useful insights that were given to me. I have saved my final note of appreciation and thanks for my wife Louise, who provided endless encouragement and love throughout this study. This thesis work was funded by the Office of Research & Development of the United States Coast Guard. TABLE OF CONTENTS Page A MT rl w I I I ACKNI _A WLEDGEMENTS . TABLIE ........... . OF CONTENTS .................... LIST OF FIGURES 2 ..... a . . 3 . . 4 .............. . . . . ................. LIST OF TABLES ................... . . . .... ..................... 8 ................. CHAP'TER 1 - INTRODUCTION . ............................... 14 . 1. 1 SHIP DESIGN PROCESS ............................ 1.2 SWBS WEIGHT GROUPS ............................. 1.3 ESTIMATE QUALITY ................. 1.4 EARLY SHIP DEFINITION .......................... . 20 . 24 . 27 ........... 30 . 1.5 1I . 1.4.1 Effect of Design & Construction Standards 34 1.4.2 Incorporating New Technology ............ 35 ........................... 36 SHIP PROGRAM COSTS .. 1.5.1 Reporting Ship Costs . ...................40 43 CHAPITER 2 - OVERVIEW OF SHIP COST ESTIMATING ............. 2.1 ESTIMATING BASIC CONSTRUCTION COSTS ............ 47 2.1.1 General ................................ 47 2.1.2 Should Cost versus Actual Cost .......... 2.1.3 Learning Rate ..................... 2.1.4 Scheduling ...... 2.1.5 Inflation and Escalation ................. 62 Calculating ROM Escalation ........ 68 2.1.5.1 2.2 .. Reliability of CERs ........................ 4 . 51 53 ........................ 58 CER DEVELOPMENT ................................ 2.2. 1 I. 70 74 TABLE OF CONTENTS Page 2.3 RISK ANALYSIS ..................................... 2.3.1 General .................................... 2.3.2 Analytical Methods ......................... 82 90 2.3.2.1 Cost Element Probability Distribution Functions .............. 90 2.3.2.1.1 Beta FDFs .................... 93 2.3.2.1.2 Gaussian PDFs ................ 96 2.3.2.1. Triangular PDFs .............. 96 2.3.2.1.4 Uniform PDFs ................ 99 99 2.3.2.2 Method of Moments ................... 2.3.3 Monte Carlo Methods ........................ 103 CHAPTER 3 - DESCRIPTION OF SPECIFIC SHIP COST MODELS ........ 105 3.1 ACQUISITION & LIFE--CYCLECOST ESTIMATING .......... 3.1.1 NAVSEA 3.1. 1.1 3.1.1.2 3.1.1.3 3.1.1.4 107 Code (:017Cost Model ................. General ............................. 1 07 11 C) Cost Estimating Relationships ....... 130 Input Information ................... Information .................. 132 Output ............................137 NCA Cost Model 3.1.2 3.1.2.1 General ............................. 3.1.2.2 Cost Estimating Relationships ....... 3.1.2.2.1 One-Digit Model .............. 3.1.2.2.2 Two-Digit Model .............. 3.1.2.3 Input Information ................... 3.1.2.4 Output Information .................. 3.1.3 3.1.3.2 3.1.3.3 3. 1.3.4 3.1.4 137 139 141 146 153 155 156 ASSET Cost Model ................ 3. 1.3.1 1C07 General................... *. . . . . 156 . Cost Estimating Relationshi ps ....... Input Information ......... * Output Information ........ . . . .. . . melm...... 161 m.. ....... . . . . . . . . . 183 189 USCG Cost Model ............................ 194 3.1.4.1 3.1.4.2 3.1.4.3 3.1.4.4 ............................. General Cost Estimating Relationships ....... Input Information ................... Output Information .................. 5 194 196 21 0 213 TABLE OF CONTENTS Page 3.1.5 3.1.6 RCA PRICE Hardware Model ................... 216 3.1.5.1 General 3.1.5.2 3.1.5.3 3.1.5.4 Cost Estimating Relationships ....... 219 Input Information ................... 233 Output Information ................ 234 216 Other Cost Models .......................... 238 3.1.6.1 3.1.6.2 3.1.6.3 3.2 ............................ FAST-E ........................ .. 238 239 Merchant Ship Cost Models . Private Contractor Models ........... 240 COST MODEL COMPARISONS ............................ 241 3.2.1 General 3.2.2 Range of 3.2.3 Model Characteristics .......... 241 pplicability ..................... 243 ........ 243 3.2.2.1 Vessel Type and Displacement 3.2.2.2 Ship Design Phase ................... 245 Model Input/Output Comparisons ............. 246 3.2.3.1 Minimum Input Requirements .......... 247 3.2.3.2 Cost Output Sensitivities ........... 252 3.2.3.2.1 Marginal Cost Factors ....... 252 3.2.3. 2.2 Program Cost Factors ......... 254 254 3.2.3.3 Cost Output Accuracy ................ CHAPTER 4 - DEVELOPING A SHIP COST ESTIMATING CAPABILITY .... 4. 1 COST MODEL DEVELOPMENT ........................... 4.1.1 Data Gathering .... 4. 1.1.1 4.2 259 262 264 ......................... Establishing User Needs ............. 267 4.1.2 Resource Requirements ...................... 4.1.3 Organizational Considerations .............. 271 COST MODEL SELECTION .............................. 270 274 CHAPTER 5 - CONCLUSIONS AND RECOMMENDATIONS ................. 276 5.1 CONCLUSIONS ................. 6 ............... 276 TABLE OF CONTENTS Page 5.2 RECOMMENDATIONS .................................. 281 5.2.1 General Recommendations .................... 282 5.2.2 USCG Recommendations ....................... 284 ................................................. REFER ENCES AFFEN IDIX A - SWBS WEIGHT 287 GROUP KEYS FOR COSTED MILITARY PAYLOAD .............. 292 APPENIDIX B - ASSET K N FACTORS ............................... AF'PEN IDIX C 294 - COST ESTIMATING SURVEY ....................... 304 APPEN DIX D - SWBS GROUP BREAKDOWN FOR THE .......... 309 APPENDIX E - ANVCE SHIP SAMPLE AND SWBS GROUP CERS .......... 320 NCA TWO-DIGIT COST MODEL ... APPENDIX F - PRICE H INPUT GLOSSARY AND DATA SHEET 7 .......... 332 LIST OF FIGURES Figure 1.1 No. Title F'age Cost Impact of Decisions a Design Process during 16 Cost Savings versus Cumulative Program Costs 17 1.3 The Ship Design 22 1.4 Exploratory 1.2 Process Cost Model Levels and Their Purpose 23 1.5 SWBS Group Descriptions 25 1.6 Typical NAVSEA Ship Acquisition Time Line 29 1.7 Systems Influence on Ship Design 33 1.8 Representative Life Cycle Cost Time Line 37 1.9 Inflation Rates 41 2.1 Weight Based Unit Production Prices 49 2.2 Unit and Cumulative Learning Curves 55 2.3 Disruption of the Learning Curve 57 2.4 Schedule Length versus Optimum Program Cost 59 2.5 Program Cost Comparisons 61 2.6 BLS Shipbuilding Composite Index 63 2.7 Cumulative Manpower Curves 65 2.8 CER Development Methodology 71 2.9 Confidence Interval about a Regression Line 8C) 2.10 The General Cost Risk 8 nalysis pproach 83 LIST OF FIGURES Title Figure No. Page 2.11 Uncertainty Measures Using Probability Density and Cumulative Density Functions 2.12 Cumulative Density Functions for Dependent and Independent Input Variables 89 The Normalized Beta Probability Density Function 94 2.14 Shape Variations using Beta PDFs 95 2.15 The Gaussian Probability Density Function 2.16 The Triangular Probability Density Function 2.13 98 Additive Moments for Method of Moment Calculations 1 )2 Decrease in Variance Error with Increasing Run Size for Monte Carlo Methods 104 Acquisition Review Milestones, Technical Definition and Cost Estimate Quality 109 3.2 Categories 111 3.3 Shipbuilding Inflation Factors for 1980 140 3.4 SIW Total Ship Labor Factors 142 3.5 One-Digit Propulsion Systems Material Cost 143 3.6 ASSET Applicability Within the Ship Design Process 157 3.7 ASSET Computational Modules 158 3.8 ASSET Cost Module Calculative Sequence 162 3.9 ASSET Life Cycle Cost Elements 168 3.10 Basis of USCGMaterial Cost to Non-Cost 2.17 2.18 3.1 of a Total End Cost Estimate Relationship for 1980 197 9 LIST OF FIGURES Figure No. Title 3.11 PRICE Parametric Modeling Systems 3.12 Typical MCPLXS Factors for Mechanical F age 217 Assembl ies 222 3. 13 MCFLXS Factors for Selected USN Vessels 224 3.14 Effect of Technology Improvement on Costs 225 3. 15 Influence of Schedule on Costs 226 3.16 The PRICE Calibration Process 228 3.17 FPRICEH Ship Calibration Data 230 3.18 Frigates & Destroyer MCPLXS vs PSTART Trend 231 4. 1 Cost Estimating Functions for the Ship Design Process 4.2 261 Factors Affecting the Cost Database and Cost FPredictions 265 4.3 BehaviouLral Information Processing Model 268 4.4 Point Estimate with Cost Reserve F'robab 5. 1 273 1i ty Cost Estimating Building Blocks 1 C) 278 LIST OF TABLES Title Tabl e No. 1.1 Example of Increasing F'age Level of Technical Definition 21 1.2 SWBS One-Digit Weight Groups 24 1. Examples of Increasing SWBS Level of Technical Definition 26 1.4 NAVSEA Ship Cost Estimate Classifications 27 1.5 Common Cost Driver Classifications 30 1.6 Minimum Lead Ship Construction Cost Data 52 1.7 Minimum O&S Cost Data 32 1.8 Navy Frigate Life Cycle Cost Breakdown 38 2. 1 Cost Estimating Methodologies 44 2.2 BLS Material 66 2.3 SWBS Group Escalation Weighting Factors 67 2.4 ROM Escalation Factors 69 2.5 Percentage of Basic Construction Cost 75 2.6 Percentage Deviation for SWBS Group CERs 77 2.7 Percentage Deviation for Total Ship Construction Costs 78 2.8 Index Breakdown Relationship between Confidence Internal and Standard Deviation for a Gaussian Distri bution 87 2.9 Comparison of FDF Characteristics 91 3.1 Percentages to Calculate Program Manager Cost Reserve 123 3.2 VAMOSC-Ships Cost Categories 128 3.3 NAVSEA Code 017 Ship Acquisition Cost Parameters 1 (:) 11 LIST OF TABLES Page Title Table No. NAVSEA Code 017 Fleet Escalation/Discounted Cost Parameters 132 3.54 NAVSEA Code 017 SWBS Output Summary 133 3.6 NAVSEA Code 017 P-8 Output 3.7 NCA Cost Model Ship Database 138 3.8 One-Digit SWES Group Cost Drivers 145 3.9 Two-Digit Cost Model Structure 147 3.10 Two-Digit Cost Model Cost Drivers 148 3.11 of Lightship Percentage Distribution for Two-Digit Model Groups 3.4 Summary 136 Weight Cost Parameters 151 3.12 NCA Lead Ship Shipyard 3.13 NCA Lead Ship Output 3.14 ASSET Cost Module Ship Database 160 3.15 NAVSEAProgram Cost Percentages 166 3.16 & Support Data for Operations Selected USN Ships 174 3.17 Summary 153 155 ASSET USN Ship Construction Escalation Index>es 182 3.18 ASSET Sailaway Ship Cost Parameters 183 3.19 ASSET Life Cycle Cost Parameters 185 3.20 ASSET Parameter Default Values 187 3.21 ASSET Ship Sailaway Output Summary 189 35.22 ASSET Life Cycle Cost Output 191 3.23 Follow Ship Reduction in Total Labor Manhours 205 12 LIST Table OF TABLES Title No. Page 3,.24 USCGCost Model Categories 208 3.25 USCG Ship Acquisition Cost Parameters 210 3.26 USCG Fleet Escalation/Discounted Cost Parameters 212 3.27 USCG Ship Output Summary 213 3.28 PRICE H Cost Output Categories 219 3.29 Fundamental Cost Drivers in the PRICE H Model 220 PRICE H Development & Production Cost Parameters 233 3.31 Description of PRICE H Cost Elements 235 3.32 Relating PRICE and SWBS-based Ship Costs 236 5. 233 Cost Model 244 3.34 Representative Lead Ship Construction Cost Parameters 248 Representative Multi-Ship Construction Cost Parameters 249 Representative Life-Cycle Cost Parameters 251 Naval Surface Combatant Marginal Cost Factors 253 3.38 Labor/Program Cost Sensitivity 255 3. 39 Material/Program Cost Sensitivity 256 4. 1 Organizational Cost Estimating Functions 260 4.2 Criteria for Parametric Contract Pricing 262 4.3 Cost Model User Features 269 3.30 3.36 3.37 Vessel Applicability 13 CHAPTER 1 INTRODUCTION For question; "How will the system answering one recently, due to the impositionof budgetary managers agencies, government mainly about ship design managers had to worry years, perform?" within constraints must also ask More another question; "Howmuchwill it cost?" led This increasing concern with system acquisition costs the of design-to-cost implementation 1970s (e.g., see Ref. of to in the early (DTC) policies 45). DTC required the early establishment realistic cost goals and a continuing effort to maintain them throughout the design and production period. This type of design strategy has led to the expanded use of synthesis models for cost and on trade-offs and has put more emphasis performance early definition of the complete ship system. Synthesis models (e.g., the US Navy's possible merit, to any particular qLuantify and assess the technical the ship's systems. how well -the effectiveness). capability and cost impacts The figure of merit ship accomplishes its make it ASSET program) or figur-e of of its effect on provides a measure of mission (e.g., military The iterative nature of trade-off studies allows a design to evolve which maximizes synthesis models minimizes for a cost figure of merit) the figure of merit upon the ship's design and subject to funding constraints. 14 technical, schedule using (or based and The importance of establishing a credible cost estimating capability early in the design phase cannot be overlooked. Figure 1.1 gives a qualitative indication of the cost impact decisions throughout important to note the major impact of decisions in the (i.e., a generic feasibility/conceptual) acquisition phase (e.g., process. see of It is planning Ref. 3). The trend indicates that the maximum leverage for costs occurs during the early design phases. Therefore, the ability to perform large number of performance/system versus cost trade-offs this early a during design stage will greatly assist in minimizing cost uncertainty during later design phases. The advantages of incorporating performance/system versus cost trade-offs for the USN's DDG 51 is documented in Ref. 5. The approach was described as a closed loop feedback control process involving the established design review budget, of and the design for conformance then making decisions to to change an the in the areas where the budget constraints were exceeded. Cost analysis during early design is in the enviable position of applying maximum effect for minimal cost (relative to the total versus program result The inverse effect for cost cumulative program cost is illustrated in Fig. relationship advanced cost). is particularly applicable to the technologies from the development program. into ship design. introduction of The impact 1.2. introduction greatest innovations early The of savings in the Attempts to incorporate innovation at later phases, when the design is committed to alternative technologies, can become prohibitively expensive. 15 t4 COST IMPACT OF DECISION NUMBER OF DECISION t4 I PHASE PLANNINGOTOOLINO MANUFACIURINQ O(SIGN HiASE - --- TIME Cost Impact of Decisions during a Design Process (Ref. 60) Figure 1.1 16 CL COST ($) Cost Savings versus Cumulative Program Costs (Ref. 15) Figure 1.2 17 Having established that potential cost savings are a primary motivation for early ship design definition, timely and stage credible estimation of ship costs during this help to: would operating costs; cost drivers, "reduce ship acquisition and and; cycle improve the naval engineering awareness The purpose of this study is and; life early analyze cost drivers and technologies impact on cost early in the ship design process" (Ref. techniques it follows that the of 26). twofold; to document the used to cost ships during these early design to address the major areas involved with the phases, establishment of cost estimating capabilities. Although these topics are listed sequentially, between there costing is a high degree of techniques and the needs and interrelationship resources of an organization that influence its costing requirements. The first step reference for that used, are each level, in this study is to describe the different levels of cost the technical detail a frame estimating of quality that is commensurate with and where in the ship design process these different estimate qualities can be found. Ship costing overlapping management, is is aspects a multi-faceted of discipl ine, engineering, economics, involving business statistics and human resources. The aim of Chapter 2 to provide a general understanding of the ship costing and its terminology. relationships and their The development ncertainty, of cost crucial to field estimating early stage estimating, is discussed in somedetail. A description found in Chapter of specific 3. cost estimating The methodologies 18 techniques can be from five models used by various US Navy agencies and the US Coast Guard are included. The is presented information of amount upon dependent the documentation available in the open literature or volunteered. fairly qualitative comparison of the models was A by proprietary nature of the material. the models estimating cost cost a as level. the chapters have concentrated on previous The ship Current typically relate ship weights to of technology function dictated technical aspects of cost estimating. Chapter 4 examines the management and human resources factors must be that considered before the technical cost estimating capability can be integrated within the organizational a entity, operating cost analysis environment. As with group must receive corporate any support all from levels of management if it is to contribute effectively. The chapter final recommendations of presents the Any discussion of the study. and conclusions must osting address the effects of the following areas on the credibility of the estimates received. These are: (1) the experience of the cost engineering estimating group; (2) algorithms, the and ; development of appropriate cost- (3) the range and applicability of the database. The all-encompassing recommendation for implementing a any within organization estimating capability maintaining a long-term commitment to its in the areas of personnel levels, collection functions. 19 is operation; that cost of primarily training standards and data SHIP DESIGN PROCESS 1.1 There are three principal divisions in the NAVSEA (Naval Sea Systems Command) ship design process; (1) exploratory design (2) acquisition design (3) service life design this Since estimating, cost are phases of study with stage early the exploratory and only The concern. studies, feasibility deals four preliminary design acquisition are phases acquisition design, ship new contract design and detail design. Fig. Sollows, the 1.3 (e.g., that the The design. the Navy or Coast Gard) dotted feasibility design phase, for order the design process from starting from a statement of mission requirements customer detail indicates this study. box in Fig. 1.3 with ending and encloses the which is the phase of primary interest Note the overlap with both exploratory studies and preliminary design. these Typically, phases can be differentiated other by the increase in technical definition of the ship a reduction progresses in the from technical uncertainty) exploratory through to detail each from (i.e., as the design design. At any given stage in the ship's design, all of the ship systems will be defined to the same level of detail. Table 1.1 illustrates increase in technical definition for a propulsion plant. 20 the Level Technical Definition 0 Whole Ship I Propulsion Plant 2 Propulsion Units 3 Gas Turbines 4 Engine Starter System Engine Starter 5 Example of Increasing Level of Technical Definition (Ref. 26) Table 1.1 In an R&Denvironment, the technical to a level commensurate with detail remain in levels the definition can increase design and yet the ship will the exploratory studies phase. Fig. 1.4 links the in'Table 1.1 with cost modelpurposefor ship designs in exploratory definition is phase. For example, required for a high degree of technical costing detailed technology assessments. Fig. 1.4 also illustrates the relationships number of systems examined (breadth), between the the number of parts added together for each system (depth), and the relative 21 being cost. If - b - MISSION REQUIREMENTS I __ - i I _ EXPLORATORY STUDIES -- I I I I I I I - I1I II I I - IL FEASIBILITY STUDIES ! i HI I i I II - II CONTRACT I DESIGN I DETAIL DESIGN The Ship Design Process (Ref. 60) Figure 1.3 22 MODEL LEVEL SWBS LEVEL COST MODEL PURPOSE *0 WHOLE SHIP EAR LIEST-STAGE, CONCEPT DEVELOPMENT; PROGRAM COSTS, SCHEDULING EFFECTS 1 ONE-DIGIT (GROUP) PROGRAM MANAGERS, RESOURCE APPLICATION AND APPORTIONING TWO-DIGIT I 2 (SUB-GROUP) 3 THREE-DIGIT (ELEMENT) DESIGN ANALYSIS, TECHNOLOGY ASSESSMENT, INTEGRATION ANALYSIS, ALTERNATIVE SYSTEMS ANALYSIS * · BREADTH . . ,am ~ -'-- ' D E P LE' T ASSE H c LEVEL I ASSESSMENT LEVEL II <$10K ASSESSMENT <$100K Exploratory Cost Model Levels and Their Purpose (Ref. 26) Figure 1.4 23 the definition is at the whole ship level, one part needs inexpensive. propulsion, parts As to be considered electrical, that each system i (and the cost of analysis) 1.2 the analysis cost systems increases number o the and only one system with hull, (e.g. etcr.) the breadth decreases, and as the broken down into increases the depth increases. SWBS WEIGHT GROUPS The ship common Ship Work Breakdown Structure (SWBS) provides a means of communicating the level of technical definition the is designer, shipyard and cost estimator. between The major elements of the SWBS system that are of interest for ship costing are listed in Table 1.2. Examples of some of the items that make Description SWBSGroup 100 Hul 1 Structure 200 Propulsion Plant 300 Electric Plant 400 Command 500 Auxiliary Systems 600 Outfit & Furnishings 700 Armament 800 Design & Engineering Services 900 Construction Services Surveillance Weight Groups SWBSOne-Digit Table 1.2 24 Definition Groop Oescriptlon I mull structure Shell plating or planklng;lonIqtudnl ad transversefraingqlInnerbttu plating; platform ard flats belao lowrist continus deck; fourth dieck;third deck;secoddeck; maindeckor harar dck forecastle de (irclrdlng platform, flats, and deckSbetween min aridgallery deck);gallery decl flight deck;ladin platform ad pecial purpoe decks Drve weatherdeck (includes catapult traugh)l superstructucas foldationsr for min propelling dchinerylfo.vdationsfor auxiliarles andother ilpmsnt!structural blUade trunksad enclosures;tructural spnsors; aror; aircraft fuel saddletankstructure; structuralcosting, forgings,and quivalentwldents; s chests;ballast nd buoyancyunits; doors ndclosures, qscial purpose; doos, hatches, maholes, rd scuttles nronballistic;doors htches, mnoles, aridscuttles, ballistic; ests ad king posts;omprtmnt tsting. 2 Propusion rs ad air eectorsl shafting, bearilngs, ad propellers; Boilers ad energyconverters; propulsionunits; maincondea cibustion air supplysystem;uptakesandMke pipes;propulsionontrol qulpment;mainstem systma feeduater md cwxensate systm; circulating and coolingwater ystem;fuel oil servicesysta; lue oil systma. 3 Electric plant Electric pr geration; per distrlbution switchbords; p distribution ad fixtures. 4 Cwsuicatlon aId control ad armanrt mtrol systemscountermeasure Kavigatioralwytamard equllpent; interior onwications syti; ships' protective syta (exceptelectronic) electronic yrstm includingelectronic ounterasurms. distrlbtion systms(cable)j lighting syst - S allilary sytm Heatingsystmrmventilation system;air-conditioningsyste; refrigerating pas, plant and rqulpnts gas, HWA, cargopipinq, orgen-itrogen, aviation lub oil systemsplumbingIrstallatics; firmin, flushing.ad prilrer system;fire etingulshing system;dralnage,trlming, heeling,and bllast syst ; freshwtersystm sppr ad deckdrains; fuel arnddesel oil fillingr, venting, tog, aid trarsfer ystm; t heatingsyste; premaed-air systms auillary stem exmustst am,ad ta drainsi boyancy trol Wystm(floodingandventingurlrinesl); lcellanemaspiping systemidistilling plat; steeringgearsystnm;ruddcr vindes, capstns cranea, aid acor-andlinq ystm; elevastors oving suirways, andcargao hadlirq imL t; operatinggearfor retractable elevatingunitsl aircraft elevators; aircraft arrestinggearberrilrs madbarrice ctapults andjet blast defloctors, hydrofoilsad lift system. 6 Outfit d furnishnq Hill fittings; bots, bott sto, aid hadllrng; rigqgingd carv ; ladders d gratings, nnstructural bulkhad for andnonstructul doors; painting; deckcovering;hull Insulatlon;storeron, stoaages, ad lockers;equipment utility paes; equilpent for rkshops;equipent for galley, pantry, cullery, ad cmlssry outfit; furnishings for living s ; furnishingsfor offloe spaces, electronic, ad radar; furnishinqgfor medicalad dentalqpaces. 7 Armmt Guns,uwnts, ad lar s Designad Designo d erglrertingq srvice. _gineering hddl Ing. nlrqdevlc; ma iintlon-handllngsystem amuniton stoaqe; pcial weapnsoage aad services 9 Construction service Staging,scaffolding,andcritbling lanchin; trals handlingandrval; cleairg ship services. d dckirng tporary utilitle ~~_ ........... SWBSGroup Descriptions (Ref. 54) Figure 1.5 25 _ andservices; materLal make up each of one-digit group groups can be found in Fig. 700 is 100 through 1.5. The summation equal to the weight of the whole ship less load items. The SWBS classification system specified at any of three levels; Each higher definition, The level as can three-digit definition. definition indicates Fig. be SWBS 1.4 allows one-, a the two-, higher degree shows the the SWBS to be and three-digit. seen from the examples level represents ship of in Table highest levels technical of 1.3. level of technical as they apply to costing during the exploratory phase of ship design. SWBS Level Breakdown Technical Description Whole Ship 1-Digit Weight Hull Structure - Group 100 Electric Plant - Group 300 2-Digit Weight Hull Decks - Group 130 Lighting Systems - Gr-oup330 3-Digit Weight Second Deck - Group 152 Lighting Fixtures - Group 32 Examples of Increasing SWBS Level of Technical Definition Table 1.3 All of the ship costing techniques presented in this use the SWBS weight groups as the means to classify weights. 26 study 1.3 ESTIMATE QUALITY Estimate quality is related to a variety of majority of which are programmatic in nature factors, (i.e., the acquisition strategy plans). In this section, the estimate quality as related to technical definition only is discussed. NAVSEA uses a cost estimate classification system which uses letters the of increasing alphabet level of design to designate definition estimate (i.e., quality. decreasing uncertainty) these are ROM (Rough Order of Magnitude), D, C. Table 1.4 shows the SWBS level of technical In level of Class F, definition appropriate for each estimate classification. Estimate Classification SWBS Technical Definition NAVSEA Cost Phase ROM Less than Feasibility Study Planning F Feasibility Study 1-Digit Weights Planning/ Programming D Preliminary Design 2-/ 3- Digit Weights Programming (maybe Budget) C End Preliminary Design 3-Digit Weights Budget NAVSEA Ship Cost Estimate Classifications (Ref. 16) Table 1.4 27 the around is concerned study This estimate. feasibility The is estimate in with ship cost estimating corresponding phase, a to one-digit SWBS group. Therefore class wei gr; -or ar, approximate listed in Table The 1.2 and Fig. overlap SWBS one-digit each of the 100-700 will groups SWBS 1.5. means that occurs between design phases weights are available in the exploratory (i.e., conceptual) studies, latter that stages of all through feasibility design. stages of preliminary and on into the initial studies, of primary the technical input to the estimator for this degree of quality be F Class technical level of definition for this the and Of course, one-digit SWBS weights can be calculated by simply adding up become weights of higher level components whenever they the available. The NAVSEA cost phases referred to in Table 1.4 are into the estimates planning, are programming generated 1.6 shows budget in both the planning how phases. Fig. picture" of ship acquisition. is and these phases fit In Fig. phase. and divided Class programming into the to supply guidance to the various Navy agencies in the acquisition process. 28 "big 1.6, the initial estimate a ROM estimate and the POM (Program Objective Memorandum) issued F is involved )( Complete Contract Plans Contract and Specif1cat1ons Award Class "C" Congressional i .: .. B 'asic'::.'" IContractors budqet ruction:: Submtlt *'Const e Date:: Bids :.':: Bas, Initial Estimate ."..... :.:::/ i I Progr amm1in .... :'7"[ Budgeting Start of Constructl1on .. · · (' Planning l '.*: POM 8 Months Launch Delivery ~~~~~~~~~~~~~~~I 2 to 5 Yedrs - I .<<-{ I- Approxlmdtely 2 Years I 11 to 18 Months I - -I Typical NAVSEAShip Acquisition Time Line (Ref. 16) Figure 1.6 29 I ! 1.4 EARLY SHIP DEFINITION In order to estimate acquisition costs estimator requires categories 1.5 a -ertain amount of information which relate to the ship's definition, realistically, in configuration, several technical and the design and fabricating specifications. Table lists and describes these categories as they are in this study. The inputs for each of the cost models in are Chapter the 3 classified according to the addressed discussed cost driver categories listed in Table 1.5. Description Cost Driver Technology technology available, stateof-the-art design influences Ship Design weights, margins, design standards, component selection Manufacturing fabrication techniques, degree of automation, learning Programmatic type of contract, procurement strategy Economic escalation, inflation & interest rates, discounting Operations & Support maintenance, personnel, fuel, spares Common Cost Driver Classifications (Ref. 19) Table 1.5 30 As of a means for providing the the necessary information for each cost driver categories in Table 1.5, various models have provide a been developed. Synthesis models are large number of feasible ship consistently, synthesis intended designs, quickly and in accordance with a set of design specifications. Detailed discussions of synthesis models for Coast Guard and patrol boats can be found in Refs. The US Navy CONcept to introduced the CONFORM FORMulation) 7 and 8, cutters respectively. (slrface ship continuing to provide consistent feasibility designs and cost estimates (e.g., see Ref. 46). Fig. 1.7 illustrates the systems development of a feasible ship design. within constraints the manpower levels, imposed by maintenance and that influence The design must the R&D supply the operate community, naval capabilities, and manufacturing practises. An indication of the minimum amount of information to estimate 1.6. The GFM exclusively comprise the lead ship construction of cost is given (Government Furnished Material) those items of ordnance the combat system. and required in Table consists almost electronics that Follow ship costs can be related to lead ship -costs through the application of learning theory. A similar list for O&S (Operating and Support) costs is given in Table 1.7. This list represents the information required by the USCG's unpublished C CASHWHARS patrol financial analysis program. boat feasibility studies have Recent used ASSET synthesis model as a front-end to the CASHWHARS program. the Ship Type Hul11 material and Fabrication methods Listing of major GFNI items Seven SWBS Group Weights Propulsion Plant and SHP Electrical Plant Capacity and Number Crew Size Special Equipments (e.g., active fin stabilizers, etc.) Minimum Lead Ship Construction Cost Data (Ref. 6) Table 1.6 Interest & Inflation Rates Fuel Costs Vessel Maintenance Schedules Operating Hours Mission Profile Crewing Vessel Life Minimum O&S Cost Data (Ref. 34) Table 1.7 _1··-· y-- -- / NIXATA Systems Influence on ShiS Design (Ref. 47) Figure 1.7 33 1.4.1 Effect of Design & Construction Standards Kehoe et al (Ref. 49) looked at the effect country design practices on the size cost of a typical antisubmarine of different and total ship warfare (ASW) frigate. investment cost included the basic shipbuilders NATO investment The cost, GFM, total and other related costs (e.g., standard allowances for change orders, electronics escalation, and weapons cost growth and cost growth for future characteristics changes). The seven major design listed practises below were examined; (1) design & construction margins (2) hull forms (3) design displacement (4) sustainability (5) survi vabi 1 i ty (6) in-service margins (7) habitability Sustainability and design margins were found to be the most contributing factors for increased ship size and cost. Ship construction significantly example, the higher use costs can for different of military also be specification instead specifications will result in increased costs. to be levels. For expected of commercial 1.4.2 Incrporating Typically, New Technology uncertain cost predictions are not the greatest hurdle to be overcome when considering the introduction of a technology (Ref. political, influences. 22). Far greater impact can be expected new with national security, environmental, energy and societal However, only the cost issue is addressed in this secti on. When judging whether the use of a new material or technology to be incorporated into a ship design is cost effective, the cost analysis should be based on its LCC, including R&D, design, manufacture and O&S. The high degree of uncertainty expected with such an analysis must be quantifiable to allow for risk trade-off studies. Cost risk analysis is discussed in Chapter 2. For shipyard applications, the decision to implement new technologies is primarily based on the economic benefits expected from predicted productivity and efficiency gains. Since the services and skills of the shipbuilder only account for about 20% of the total productivity amount ship from program new of the total costs cost, major technologies affect a (Ref. 24). 55 gains in shipyard relatively small 1.5 SHIP PROGRAM COSTS Program costs are often referred to as the life cycle (LCC) for the particular system. into three areasi investment, and; (1) LCCs are generally categorized research operations cost and and development support (O&S). (R&D); (2) Fig. 1.8 illustrates a representative time line of LCC expenditures. Note that there is generally some degree of overlap between each cost category. R&D costs technology are for the work associated making items or innovation design features available to ship at key commitment points. associated with high the There is often developmental work with combat system installations. R&D costs are not O&S costs for conventional vessels are the specifically addressed in this study. Investment and major components of LCCs (Ref. 36). Ship investment costs include construction, government furnished material (GFM), outfitting, post delivery and other miscellaneous costs. The term investment costs is used interchangeably with acquisition costs. Ship O&S costs include direct/indirect military direct/indirect personnel, ship operations and maintenance and direct 36 ship H-INVESTMENT .. ___ COST OPERATING AND ISUPPORT PROGRAM PROGRAM PECULIAR COSTS R&D COSTS -- · ·· 0 · . - TIME Representative Life Cycle Cost Time Line (Ref. 60) Figure 1.8 37 COST ,I moderization costs. development, frigate. Table acquisition Based on a 30 1.8 and presents O&S LCCs year ship life, Category the breakdown for a 360 ton the O&S costs Percentage Breakdown Operating & Support (*) Indirect Support 2 Maintenance 10 Moderni zati on 18 Operations 15 Personnel 12 57 Acqui sition Combat systems 17 Machinery 18 Hu 1l 4 39 4 Development (*) based on a 30 year ship life Navy Frigate Life Cycle Cost Breakdown (Ref. 36) Table 1.8 of Navy are significantly greater. A lower percentage for acquisition costs be can reduced. R&D US if the combat capabililty of expected The following vessels Management vessel is percentage breakdown for the FFG-7 isi 1.61 Investment - 35.2, and; O&S - 63.2. Navy the are recorded by of O&S Costs) program, the VAMOSC The O&S costs for (Visibility and a brief description of which can be found in Section 3.1.1.2. There design are a number of things that can be done during to reduce the main elements of the O&S costs and the decrease total LCC (e.g., see Ref. 36). ship thereby However, these improvements generally result in a higher acquisition cost (Refs. 5 and 50). Although, design the process, decisions. There importance of LCCs are not overlooked in the acquisition are costs tend to dominate the three main reasons for the influence of acquisition costs over LCCs (see Ref. is design controlling 5): (1) there a more immediate impact for the acquisition'costs; (2) there is considerably less uncertainty associated with acquisition cost estimates, andl (3) there is greater flexibility in the future funding of O&S costs. The in emphasis on minimum procurement cost has been reflected fixed displacement and hull length constraints or some design criterion dimensions which constrains (e.g., see Refs. hull 47 and 48). .9 size and other principal 1. 1 .ReportingShip Observed Costs in ship costs, differences if can explainable, reflect differences in the subsystems of the ships as a function of technology changes, inflation, or productivity differences. If and remaining differences major the data, the should reflect the technology level and productivity inflation characteristics of are backed out the ship of subsystems, thus enabling analysts to establish specific cost trends in the data. in Variations productivity a are very much function location stability in the shipyard's workload and its geographic (Ref. 2). is often difficult to remove the productivity that account for different levels of shipyard shifts (see It .1.2). section However, the effects efficiency of inflation removed by expressing ship costs in so-called base year Other dollar terms used are then year dollars, dollar amount for a previous fiscal year (FY), of can be dollars. referring to the and futre year dollars for future costs. Cost f igures required can be converted inflation rates variation in inflation inflation rates consistently for to any base year provided are available. rates Fig. 1.9 for several years. Department of Defense (DoD) shows the Note that equipment economy. higher than that for the general 40 the is _ _ ~ .. _ _ ii , . DoD- All US Economy __ ~~~~~~~ |~~ __ _ _ __ l _ Equipment ~~ ~~~ _ _ _ _ _ _ - 9.3 9.8 10.6 1976 5.2 8.1 9.0 1977 5.8 10.2 1978 7.4 9.4 1979 8.5 1980 9.0 8.1 10.6 13.2 10.4 11.4 10.3 11.0 __I Source: 10.9 9.4 _ ~~~~ _ i _ US Department of Commerce, Bureau of Economic Analysis Inflation Rates (Ref. 17) Figure 1.9 41 ~ Aircraft 1975 1981 - - For the calculation of total LCCs, discounted technique O&S costs are generally on a year by year basis using the net (e.g., see Refs. present 1 and 34). If, for simplicity, costs are assumed equal to the same amount, A (base value the O&S year $), each year throughout the vessel 's life, then the net present value for the O&S costs, NPV (base year $), NPV A ( (+i)/(l+d) is given by the expression; + ( (l+i)/(+d) )2 + (1. + ( (l+i)/(l+d) )L ... where 1) ) i = yearly escalation rate d yearly discount rate L = ship life in years The escalation at rate is used to equate a given sum of the present time (i.e., money base year) with another sum of money at any future time. Discounting inflation, to the to is the reverse of the compounding effect of in that the discount rate movesfrom the future back present. To explain in other terms, escalation is required account for inflationary trends which decrease the present day because of money in the future, the whereas discounting time value of money from expected value is returns of used on investment. Obviously, the two effects are opposite. The discount rate is often taken as 10% (e.g., Refs. 42 and 34). CHAPTER 2 OVERVIEW OF SHIP COST ESTIMATING Cost and estimating is concerned with all aspects of production economics that influence the development, operation (including construction portion retirement) of any of government a construction ship. agency's Within and the shipbuilding budget, there are three primary elements of cost: (1) costs incurred for management of the acquisition program The (2) costs incurred for the procurement of GFM (3) shipyard costs for construction of vessels costs associated with the management of the ship acquisition are programmatic in nature. These include the effects of inflation, profit and other economic factors orders and various cost contingency margins. For instance, a two change in total program costs after programmatic effects ncluded This estimating construction (e.g., chapter the that see Ref. deals 5). with the traditional costs involved with GFM purchases services, (BCC). Direct funds costs dollar change in production costs translates to about a dollar are change Programmatic significantly impact on the total program costs. one plus labor methods and shipyard referred to as basic construction costs and material BCCs make up only 25% of must be appropriated for each new the (Ref. 23). Table 2.1 lists the various methodologies generally used to come up with cost estimates in this area. 43 ship of Delphi Analogy Engineering Cost Estimating Relationships (CER) Parametric Cost Estimating Methodologies Table 2.1 The Delphi technique of experience individuals iterative one, involved. The working from approach for this method the towards a consensus among method Delphi upon rely estimates and often vary widely best the Therefore, another. Delphi suLch, As opinion. expert as the solicitation can be described is frequently used to of the one to is an persons extrapolate outside of the range of existing cost data. Analogy the comparison of new existing with This technique requires historical on similar existing systems for it to be feasible. Analogy are the most economical to produce of all the methods estimates listed on to determine costs. systems data rlies in Table 2.1. The engineering estimating and method is referred is the "accepted" method of as to obtaining bottoms-up reliable estimates (e.g., budget quality). This technique is characterized by separate material and labor 44 costing on a component by component structure the typically basis, (e.g., the SWBS groups aggregated (e.g., work for Navy ships). definition available, technical highly using some form of breakdown Depending component can upon range whole ship) to very detailed from (5-digit SWBS). Bottoms-up estimating is generally the most time consuming and costly of all the methodologies NAVSEA The Code 017 for the same level of detail. model described in Chapter 3 uses the traditional engineering approach for cost estimating. The previous relationships, such as method can be described as using whereby costs labor hours. estimating, cost-to-cost are estimated from elements of cost Parametric and CERs use cost-to-noncost which involves the use of inputs such as performance (e.g., SHP), weight, etc. to arrive at a system cost. Parametric and CERs are derived using multi-variable and single variable regression techniques, respectively, on existing data. Therefore, these methodologies represent averaged system cost trends and are called top-down economical estimates. Parametric and CERs are the most techniques to use as they give quick answers to what if questions, provided these changes can be properly reflected in the noncost variable(s). CERs can only be used to predict costs if the new ships have systems similar to those in past ships. models found in construction costs. as Chapter 3 use The NCA, CERs to USCG and ASSET calculate basic Increased system definition can be expressed a separate CER whenever there is sufficient cost data at that level to define a unique trend. The more design features that can be accounted for by using different trends, there is in the analysis. 45 the more flexibility Parametric detailed models generally estimates (i.e., serve as a cross using the engineering method). have proven useful for evaluating future technology and can influence long term priorities. check for They assessments, The RCA PRICE model is a well-known parametric model. Cost-to-noncost into for computerized models. estimates Ref. relationships 6). to is requirements, an Although be one effects win time see high approval Low estimates can result from unreal difficulty in guestimating unknown and/or over-optimism manhours). can the general estimating philosophy has always been conservatism (Ref. 51), which serves to minimize the of unknowns that always arise as ship design (technical) definition database the the factors that contribute to a low estimate important, of (e.g., important factor given variables or predicting technology impacts, (e.g., underestimating incorporated of the results accept low estimates as a means to against a competing system. performance typically This leads to quick turn around as well as consistency Consistency motivation are improves. is thin, For there unknowns conservatively, advanced naval is a natural vehicles, tendency where to the estimate resulting in higher estimated costs and risks. (Ref. 46). As the concept nears an acquisition commitment, the high cost alternative estimates may eliminate from competition. an otherwise In a recent SWATH feasible design, hull structure estimates reflected a tremendous difference in cost per 46 pound compared to conventional monohulls, even though the material and fabrication specifications were identical (e.g., see Ref. 46). 2.1 ESTIMATING BASIC CONSTRUCTION COSTS 2.1.1 General Basic for ship construction, and material profit. is defined as construction Note contracting, the contract award including all production labor, overhead, costs plus an amount for cost of money the use of the word price in this price price (COM) and definition. In indicates dollar amounts inclusive of fee or profit. If the fee or profit is excluded, the dollars amounts are referred to as costs. An the estimate of CC is developed two major parameters of ship costs and labor hours. separate manufacturing aggregate rate; by utilizing construction estimates costs, material Direct labor costs are calculated or engineering rates or overhead is estimated an for using appropriate as a percentage of the direct labor costs. Overhead costs costs represent that portion of fixed and variable allocated to the production of each ship but not related to its construction. directly Examples of fixed overhead include rent, insurance, depreciation of buildings and equipment, and the cost of money. Variable overhead costs change with the level shipyard and include in the taxes, employee activity benefits, communication and travel costs, and production related expenses. During the feasibility phase of the ship design basic construction material and direct labor costs are 47 process, estimated using two primary approaches: (1) wherever ship definition permits, vendor quotes are solicited for the equipment involved; definition ship wherever (2) sufficient not is to support a vendor quote, material and labor costs are estimated by a CER. of form either in the CERs reflect historical ship cost data, similar return costs or cost proposals/pricing exercises for Labor hour CERs are based on a review of CPRs (contractor ships. , reports) performance historical proposals, costs, return previous estimates and shipyard experience. relate non-cost design parameters to costs. Typically, CERs in costs, new ship cost estimating, ($), functionally are (see Table 1.2), so thatl related to SWBS weights C = f C (2.1) (weight) represents some functional Fig. relationship. where f( ) shows weight based cost estimates in terms of dollars per for a wide range of products. will products depending vary for The cost per pound upon pound similar differences their 2.1 in complexity. Other costs, systems variables besides weight may correlate depending upon the application. often use shaft better For example, horsepower (SHP) as an with propulsion independent variable for estimating costs. Material estimates for hull structure 48 include a scaling Illl -- * ^ 9 -~~~_ lOOM .S I 100.000_ 10.000- Z 1000- 0- 100- 1010.10.010.0010.0001- I 0.0001 I I 0.001 0.01 I 0.1 I 1 I 10 I 100 ---I 1000 ----I SELLINGPRICEOF UNITS (S/lb) Weight Based Unit Production Prices (Ref. 19) Figure 2.1 49 ----I `-I 10.000 100000 1M -- I -- ' 10M 100M factor which accounts for the impact of offs, mill tolerance, weld rod and scrap, cut-outs, transportation. cut- Typical factors add an additional 15% to weight based quotes. Ships can have the same weight in a functional area hull structure) and yet have different costs. (e.g., Cost variations of this type are due to differences in materials, fabricating, level of technology, design plus a variety of other factors. process, explain Early in these factors can be incorporated into CERs general cost trends. However, as design and definition increases throughout the design process, the to technical the top-down approach inherent in the use of CERs becomes less tenable. Design definition supports the solicitation of vendor quotes for most areas. of the high value components Whenever within the functional actual equipment costs and weights are obtained from quotes they can be incorporated into the cost estimates for ship construction costs. This is done by reducing the appropriate weight the groups by the equipment weights available, weight group costs using the relationships (CERs), and appropriate recalculating cost then adding the equipment estimating costs to these updated values. This method of shopping list additions will tend to increase the accuracy of any cost estimates data is obtained The since the directly from the manufacturer. use of actual equipment data is especially helpful for determining accurate electronics and armament hardware costs. The principal their reason for this is that their costs depend mainly upon performance and sophistication, quantified as weight, characteristic. As space, a which are not as easily or any other physical or technical result, it 50C is difficult to develop a functional relationship such as Eqn. (2.1) to explain historical cost trends in electronics and armament. For Navy . systems) In 1980, on software costs. dollars the effects the DoD spent However, software nearly billion $3 projected amounts for 1990 are in excess of $32 billion dollars (e.g., There of on costs is becoming more important (especially for development combat acquisition programs, see Ref. 17). are several models in use for estimating the design and support costs associated with software development. The names of some of the (COnstructive these models 2.1.2 more well-known SLIM, COst MOdel), are and PRICE-S. can be found in Refs. 17, 18 and Jensen, COCOMO Information on 19. Should Cost versus Actual Cost When dealing with GFM quotes, the models distinction costs it is important to understand between should costs and actual costs. are based on time-and-motion studies of various working under mean generally easily conditions. controlled accessible tradesmen conditions Controlled that all tools and materials are Should available are few generally supply should cost information for throughout the work and that there and interruptions. Manufacturers major items and ancillary with these tendency vendor for hardware costs. Care must be exercised quotes, over-optimism since there is and bias on the an understandable part of vendors, resulting in low cost estimates for the particular item(s). In materials contrast, must be under actual working conditions, shuttled between the workplace tools and and supply depot(s) and there are continual disruptions due to a variety of reasons. The result of these differences is that actual costs can be expected to exceed should costs by 15 to 20 percent (Ref. The effects of modular construction and other considerations on investigated. However, this difference have yet it would seem to 2). producibility be adequately logical that any producibility improvement would reduce the difference between the two. Should described should cost have different above for vendor quotes. cost identify can interpretations The US Navy may study of a sole-source contractor's inefficiences reasonable cost eliminated. The to in the results initiate facilities the operation and determine government would be of the study form the than if basis to what these a a were for the government's position during contract negotiations. Finally, independent a should review team of analysts. cost study can also refer of a proposed program budget estimate to by an a Their purpose is to establish a range of costs that can be expected for the program. 2.1.3 Learnin.gRate as well as many other industries, experiences Shipbuilding, a learning or improvement process when multiple units are constructed in orderly phased sequence. The accumulated by industry verify that learning takes place being historical data (Ref. These empirical data provide the basis for what is referred 43). to as learning curve theory. is that each time the total quantity theory The ships of built doubles, the manhours, material, or basic construction cost of the ships is reduced by a constant percentage of the previous manhours, material, or basic construction cost. a For learning rate, given the cost N CSI N Nt h ship, (2.2) R / log 2) C 1 = lead ship cost where the relationship; CN (S), can be calculated from the following CN = C1 N(log of (.2) ($) R = the fractional learning rate (%/100) Eqn. (2.2) is relationship. curve referred to as the unit learning or Since each point on a Boeing curve learning a theoretical individual unit cost as a percentage of represents the lead ship production cost, the area under this curve up to a given quantity equals the total production cost for that amount. Estimators have a choice of working with unit or average explained manhours cumulative curves. The difference in these two approaches can using the following example. If the eighth were 90 percent of the fourth ship manhours, other hand, ship then learning would be expressed as a 90% unit learning curve. be the On the if the average manhours of all eight ships were 90 percent of the average manhours of the first four ships, then the learning would be expressed as learning a 90% cumulative average curve. Fig. 2.2 illustrates that a unit learning rate of 94% to a cumulative learning rate of 97% . equivalent are used correctly, for follow the rates total ship have been learning rates of about 90% Unit cost. acquisition Provided they the choice of unit versus cumulative calculations does not affect ship is noted for Navy destroyers and frigates (e.g., see Refs. 25 and 30). The of factors, level skill on occurs that a variety on depends schedule learning of amount any including required), (i.e., technology, construction time and time between starts. skill level jobs exhibiting rates close to unity, learning in reduction Conversely, systems have learning there is little or that is, with subsequent labor minimal system manuf acturi ng complexity Low production performance of no task. the requiring highly skilled tradesmen can show significant learning effects, so that there is a sharp reduction of labor between the lead and follow ship. less learning that takes place between the first and lst (e.g., see result outfitting shipyard Ref. efficiency 20). Innovations like robotics in lower production costs from and consistency of learning effects. 54 the is, more highly automated the fabrication process The and ships zone increases application, not in from 97 of Lead Ship Cost SHIP CONSTRUCTION COST AVERAGE COST 94 of UNIT COST Lead Ship Cost -- LEAD FOLLOW SHIP SHIP Unit and Cumulative Learning Curves (Ref. 1) Figure 2.2 55 Learning phased their of theory sequence. is defined for production in an BIW (Bath Iron Works) reached a high point in production learning during a time period in which a number Navy destroyers were built in a relatively short (Ref. orderly time frame 23). When production occurs in multiple lots, too slowly, or with too great a time gap between construction starts, costs do not follow Eqn. lapse in production, follow ship (2.2). Fig. 2.3 illustrates that for a the shipyard experiences a jump upon resumption of building. in costs Break in Production I I Recurring Unit I Production Cost I I I I I I I I I .1 I I Cumulative Quantity Disruption of the earning Curve (Ref. 17) Figure 2.3 57 Scheduling 2.1.4 construction The highly dependent construction. costs upon the for a ship or group procurement of ships for chosen strategy is This strategy indicates the number of vessels, the length of each construction period, the time between construction and the number of lots that the starts in. From this partial listing, vessels are to it can be seen that be built production learning and scheduling effects are interrelated. Pre-outfitting, modular and zone construction, increased use of automation and other fabrication improvements are resulting in construction times. shorter reduction thereby manhours, reducing offset by increased engineering and support efforts being as production costs. current indications are that the production savings are However, 16). of the The effect of these changes is (Ref. An overall drop in total construction costs can be expected these advanced techniques become more fully the fabrication process. The impact of producibility gains reduced because shipyard costs only affect a further into integrated is relatively small amount of the total program budget (Ref. 24). Fig. 2.4 illustrates that an optimum results in the lowest production costs, (i.e., schedule overtime, increases in costs. results in project schedule while compression of the more shifts) results in significant Although stretching out of the schedule also increased costs due to inflation and reduced learning U A IL O z 0 , 0 z UNRELIABLE SCHEDULE (PERCENT OF TYPICAL) I Schedule Length versus Optimm Program Cost (Ref. 61) Figure 2.4 59 effects, these are generally less severe in magnitude. also an optimum phasing of design and when construction construction starts immediately after design is There is schedules, complete. Overlapping of these schedules will result in increased costs, as shown in Fig. 3.15. Variations can in expenditures and government funding significantly affect program costs. Fig. 2.5 patterns compares multiple and single lot production costs using the RCA PRICE cost model (see section In 3.1.5). the feasibility design phase, there exists a great deal of uncertainty regarding production scheduling. Lowest costs can be expected for an "optimum" construction period combined with single lot procurement strategy. 60: a II LOT 2 - LOT 6 5 UNITS LOT 6 LOT 5 4 UNITS LOT 5 80 PROGRAM COST% 60 LOT 4 4 UNITS LOT 2 21 UNITS LOT 4 1 LOT LOT 3 4 UNITS LOT 3 LOT 2 4 UNITS LOT 2 DEVELOPMENT PLUS PRODUCTION OF 29 UNITS 40 20 LOT 1 LOT 1 LOT DEVELOPMENT PLUS 8 PRODUCTION UNITS _ PRICE H ESTIMATE _ CURRENT ESTIMATES _ _ Program Cost Cmparisons (Ref. 26) Figure 2.5 61 _ _..... PRICEH ESTIMATE _ A_ . _ A_ J~ . IJDo P rnLIC " ESTIMATE 2.1.5 Inflation and Escalation The rate inflation, technical of change in economic conditions, aspects of a cost model decrease will (Ref. 23). Inflation or is defined alternatively, of the amount of product a fixed amount of money buy relative to some base year. It wage is important inflation, determined by a to realize each that when looking at product price or industry unique set of cost and market regional labor rate differences), consequently price or rate is wage factors (e.g., and their inflation rates will differ from case to case. Using forecasted prices that are not truly representative of a specific product can to serious miscalculations of future if an estimate of the average year as can affect cost estimates more substantially than the as the price increase of a product over time, the such lead cost estimates. For example, annual inflation is low by 3% for a system to be manufactured seven years from per now, the result is a cost overrun of 23 percent. The indices visible measures of inflation are the that are often quoted. vari ous These indices range from price highly aggregate indicators such as the wholesale price index (WPI) down to disaggregate commodities. there the At producer higher indices (PPI) levels of aggregation is less fluctuation disaggregate price levels. for (e.g., specific the WPI), in the indices than would be found Fig. 2.6 shows the percent at yearly variation in the BLS (Bureau of Labor Statistics) composite index used by the US Navy for estimating 62 contract escalation. The 4 10 (U 12 - (50/ zw (C) I.li 4 _ 1 n 1w a I 1966 1970 -. rL.... 9 I 1975 FISCAL YEAR Ccaposite Index (Ref. 62) BIS Shipbuilding Figure 2.6 63 1980 I 1985 fluctuations can technology, be caused by a number inventory, competition, of and factors, including the overall effect of inflation on the economy. Escalation accounts for the change in cost expected between contract award and ship delivery due to inflation. Currently, the USN has extended the the delivery date. and procedures escalation coverage out to 8 Outyear pricing defines inflation factors for differences past estimating general developing estimates with base dates in the future. the months ship costs The failure to identify among relative escalation rates for important labor, material and energy cost inputs can lead to serious errors in forecasting program costs. Escalation building 53). amounts are computed based on a specified period and an assumed manhour profile (e.g., Figure see 2.7 shows a cumulative manpower curve for representative 6 Ref. ships of a 36 month award to delivery period assuming a 6 month interval between construction starts. Total labor amounts for this example are in the vicinity of 91,000 manmonths. The use of more aggregate material price and earning indexes can lead to estimates. escalation, energy errors in material and labor cost escalation To provide a best estimate of a project's future cost a inputs composite of the project's labor, material should be constructed to the greatest detail practicable. 64 degree and of aM 4W 4S@ 30 2O oeo S 6 12 18 24 38 36 MONTHS Cumulative ManpowerCurves (Ref. 62) Figure 2.7 65 42 48 54 60 66 Historically, costs inflate in Section material composite material Table and equipment for domestic materials 1.5.1. Because index illustrated in of this, the the 50/50 labor calculates its own escalation rates: government example. shipbuilding at different rates than as mentioned applications, and naval 2.6 Fig. 2.2 indicates the PPIs and weightings is that used to calculate a whole ship BLS material index. PP I Description 10-1 11-4 11-7 Iron and Steel General Purpose Machinery Electrical Machinery and Equipment BLS Material Index Breakdown Table 2.2 66 Weighting .45 .40 .15 an are NAVSEA also develops escalation indices for the SWBS weight groups. Table 2.3 shows the weightings that are used to develop a single ship weighted average for a non-combatant surface ship. SWBS Group o10 Description Weighting Hul 1 Structure .092 200 Propulsion Plant .118 500 Electric Plant .093 400 Command & Surveillance .015 500 Auxiliary Systems .281 600 Outfit & Furnishings .354 700 Armament .005 800 Integration/Engineering .026 900 Assembly & Support Services .016 SWBS Group Escalation Weighting Factors Table 2.3 67 importance cf The effect on and escalation during the construction process cannot overlooked. accounted program accurately predicting inflation The for) cost growth from unexpected inflation may result in decreased stretchouts. reduction More drastic production measures may its be (if not rates and entai1 the in units procured or even cancellation of the program. In any event, these actions lead to higher per unit costs, deployment shortfalls and reduced capabilities. 2. 1.5. 1 Calculating ROM Escalation The for methodology estimating outyear (i.e., ROM and information contained in this (Rough Order of Magnitude) non-budget year) pricing Memorandum dated 3 April 017 that are Table The escalation is taken from a escalation an contract award in the last quarter fiscal year and post delivery, in months of the 8 months after the delivery date. The cost for each ship is the sum of 100%of direct overhead and 100%of material NAVSEA given These percentages are based on the number of assumed for percentages multiplied against the cost of the ship are 2.4. between 1986. section dollars and cost labor, 95%of of money (see Section 3.1.1). Other escalation assumptions used in the determination factors include: of the base date is 8 months prior to ROM the award date; start of construction 12 months after the award date; 50/50labor/material composite (e.g., see Fig. ship construction expenditure curves (e.g, escalation for 2.6); specified see Fig. 2.7), and; energy and fringe benefits growth. For awarded after FY 90, the factors for FY 90 are to used. 68 ships Post Delivery - Award Date (months) FY Award 60 72 84 96 9.4 10.8 12.1 13.5 14.8 6.8 8.0 9.3 10.6 11.9 13.2 5.8 7.0 8.3 9.6 10.9 12.2 24 36 48 6.4 8.0 89/07 5.5 90/07 4.6 Date 88/07 (*) (*) year/month ROM Percentage Escalation Factors Table 2.4 The following example is given for a FY 88 shipl (1) (2) (3) (4) (5) (6) Base date Award date Start of construction Post delivery date Target cost (000's) Delivery - Award date (7) Escalation = (5) x escalation 87/11 88/07 89/07 92/06 $250,000 48 factor = $250 M x 9.4% = $24 M The escalation or the FY 88 $250 M ship is $24 M. 69 Changes adjusted the in base date of 8 months prior to For changes 0.4% for each month. by award in the start construction from 12 months after award are adjusted by each month. For the following example of 0.1% for of a FY 89 ship; (1) (2) Base date Award date 88/06 88/11 (3) Start of construction 90/01 (4) (5) (6) (7) Post delivery date Target cost (000's) Delivery - Award date Adjustment for Base date 88/11 to 88/06, change 93/10 $271,000 60 of -3 months -3 (8) are x .4% = -1.2% Adjustment for Start of construction 88/11 to 90/01, change of +2 months +2 (9) (5) x Escalation x .1% = +0.2% (escalation + adjustments) = $271 M x (9.3 -1.2 + 0.2) = $23 M for the FY 89 $271 M ship is $23 M. The escalation 2.2 CER DEVELOPMENT This section describes a methodology for calculating estimating relationships (CERs) from given cost illustrates collection data, cost the six steps is the first step. involved in the data. Fig. procedure. Data is obtained from returns and ship operational information. sources that have the data do not want to give it up, cost 2.8 Data historical Often the so that it must be paid for in some manner (e.g., a contract to assemble the relevant data). In addition, the data gathered is not always in the form that it is needed for CER development. For example, most shipyards their do not group costs according to SWBS weight group internal accounting procedures. 7o0 for Therefore, a significant CERDevelopnent Methodology (Ref. 63) Figure 2.8 71 portion of the development work and expenses can be involved in data collection (Ref. 2). The second step of the process is primarily concerned normalizing the converting data. The most widely used the costs to a common base year . with normalization Previous is mention has been made for removing producibility effects from the data as (e.g., see Refs. 9 and 23). well Once the data is in a usable format, the factors in the ship design, construction and operation which may be thought to have an effect on costs must be determined. based It Variables are also chosen upon their easy availability within the design community. was found that SWBS weight groups and SHP for propulsion are the factors used most in ship costing. Having costs, the relationships selected the analyst must independent variables decide on one or to relate more with which to statistically curvefit the to rational data. A rational CER means not just an equation that "fits" the data, but one which has some basis in engineering. For the cost models reviewed in Chapter 3, three types of CERs are used; (1) linear (e.g., NAVSEA Code 017 and NCA) Cost = A + Bx (2) log - (2.3) log (e.g., USCG) log Cost = A + B log x 72 (2.4) (3) log - linear (e.g., Cost and B are unique A where (2.5) to be and analysis for determined is x or operational cost variable or construction = A x constants regression from equation ASSET) design, the chosen. element These equations do not include the RCA PRICE model, which uses a multiple-variable regression relationship to proprietary each relate cost to non-cost variables (i.e., parametric analysis). Although any data can be curvefit, the instance, uncertainty) cost cost the element can Experience For least (i.e., variable giving the least variance the tests. of fit" and other significance for "goodness curves it remains to test when compared to the data may be selected used in the CER also (e.g., see prove to be invaluable 2.2.1). Section in the as selection process. a As result is of these tests selected as the and most a rationalizations, appropriate for the particular CER situation. It is important to realize that the CER represents an historical trend to costs and therefore it is strictly applicable only within the range for which the data exists. these This means that algorithms should be used to predict costs of newer having systems similar to those found in past ships. 73 ships 2.2.1 Reliability of CERs There are two areas in which errors in CER development can be found: measurement and stochastic errors. Measurement error is not addressed in this study. This section discusses some of the methods available for determining the probabilistic error goodness of highly fit) dependent available for CERs. upon Confidence in any derived the quality and quantity of CER cost and on whether the derived CER can accurately observable cost trends. However, (i.e., is data reflect if large departures are made from the database designs, errors will increase in magnitude. Generally, available, for the any better statistical curvefit, the fit, provided the the more variable data chosen exhibits an explainable trend. Smaller subsystems are found to be more specifically design volume, power or groups (Ref. 23). variables than are more general example, can related to weight, relationships for whole ship cost to ship For displacement be expected to have a higher variance than those individual SWBS group weight costs. other Because of this, found for whole ship costs are usually estimated as a summation of SWBS group costs. Although it would be desirable to reduce error for every SWBS group CER, of the dollars. Section costs. material typically, the estimating only a small portion system elements account for the majority of investment Table 2.5 shows the SWBS weight group and subgroup (see 3. 1.2) These cost percentages of construction the shipyard costs include all direct construction labor and costs except for armament (SWBS 700) and communications and control (SWBS 400), which are for installation only. 74 Percentages Group SWBS Subgroup Subgroup Group 1A 11.67 C 2.33 2.33 2.17 D 1 2A 14.50 B 2.67 1.67 C D 18.33 3.33 2 3.50 B 7.67 4A 2.67 22.33 11.17 4.67 Ec 7.00 4 7.33 5A B 12. 00 1.00 1.33 C D 5 21.33 6A 1. 33 5. B C D E 00 7.33 2.17 2.33 6 3.67 7 7 100.00 Percentage of Basic Construction Cost (Ref. 23) Table 2.5 16.00 3.67 100.00 The sum of the top ten of the subgroups in Table 2.5 account for 75% of the total Therefore, CER for shipyard maximum development effort construction costs (Ref. the majority reduction of errors, should be directed at 2). of minimizing the uncertainty of the high cost driver categories. The main propulsion, SWSS group cost drivers found in Table auxiliary equipment and hull. 2.5 are The ANVCE study found that the relative importance of each of these three groups was function of the particular ship design. a For example, the complex lift system in hydrofoils made the auxiliaries group the dominant cost element, while for advanced monohulls the propulsion group was the highest percentage cost (Ref. 54). Cost studies are driver impacts are particularly useful for and are often expressed as marginal cost usually interfaced generated with cost using synthesis model CERs. The expressed in terms of dollars per ton. analyses In can be found order to developed for percentage of values were trade-off factors. programs factors which are They are typically Examples of marginal cost in Refs. 5, 13, 35 and 42. evaluate the "goodness of fit" the ANVCE study (see Appendix deviation calculated of the estimated for each 76 SWBS of E), versus group. The the the CERs average actual cost percentage l i 1 i i i Percentage of Deviation from Data Bass Upper Limit Lower LimiEt~ vere Cost Group -14.3 1. Hull structure 8.2 2. Propulsion 6.4 ·26.0 -15.0 3. Electric plant 11.1 28.7 -19.4 4. Comnunication 13.0 37.9 -24.5 9.5 39.0 -22.6 and control 30.0 5. Aux i liary systems 6. Outfit and furnishings 14.1 43.0 -23.1 7. Armament 21.2 83.5 -27.3 8. Design and engineering services 10.9 36.4 -22.0 14.4 54.3 -30.5 12.1 42.1 -22.1 9. Construction services Average Total Dev. . . . . Percentage Deviation for SBS Group CERs (Ref. 54) Table 2.6 77 Ship Deviatioan from -Ship Class Data Base (%) Class Deviat on from Data Base (% PF 109 SWATH DE 5.8 6.3 PGH 1 PGH 2* 6.2 -37.4 SWATH MCM DLGN 25 DLGN 35 DLGN 36 3.0 -5.1 -5.8 -4.2 PCH 1 PHM 1* AGEH 1 DBH 8.5 -26.8 22.3 5.5 DLGN -0.1 ARCTIC 13.9 SEV JEFF A* -28.1 JEFF B* 2KSES (B) 2KSES (R) -30.6 -15.3 - 9.3 38 CPIC PG 92 PG 92 PGG 1 PGG 1 (P) (T) (P) (T) Snip sample data base. -15.5 8.7 6.5 2.9 32.2 with actual returned costs in Percentage Deviation for Total Ship Construction Costs (Ref. 54) Table 2.7 78 deviation for one point can be written as; I Cestimated Cactual I / Cactual x 10% FD where PFD= the percentage deviation of a single (2.6) data point Cestimated = the cost calculated from the appropriate SWBS CER = the corresponding cost data point Cactal The absolute estimates are percentage study. value weighted deviations Armament signs ensure that the over- and evenly. shows the for the SWBS group CERs from (SWBS 700) shows Although there are wide deviations average for Table 2.6 the within each group is muchless. greatest underaverage the ANVCE uncertainty. any one cost group, the This further illustrates that the CERsrepresent overall trends and are not intended to be representative of any one ship design. Deviations of estimated total ship construction costs (i.e., total labor database due to plus material) from actual are shown in Table 2.7. the addition of change costs for ANVCE The large under-estimates orders and other production costs in the return cost data which are not for in the SWBS group CERs. the are unforeseen accounted It is important to remember that the deviations shown in Tables 2.6 and 2.7 indicate how well the CERs can reproduce the database, not how successfully the CERs will predict the costs of ships not in the database. Variance Fig. 2.9 is often used as a measure of uncertainty for CERs. illustrates that the calculated variance can define 79 a / / .0/ Y 11 / Z/000, w I _I ! I I_ I I __ I_ _ I _I . ____ x Confidence Interval about a Regression Line (Ref. 55) Figure 2.9 80 - __ l_ - probability allows of fit distribution about the CER regression line certain statistical tests to be carried out for (e.g., see Refs. 19, 28 and 56). Most analysts which goodness assume a Gaussian or normal distribution (see Section 2.35.2.1.2)with zero mean about range. Ref. the line and constant variance throughout 28 discusses the variance on cost risk analysis. 81 implications of the data non-constant RISK ANALYSIS 2.3 2.3.1 General in Uncertainty the ship design process has typically as low, medium or The sum of these uncertainties is usually accounted for example, described in qualitative terms, high risk. been for by incorporating various construction margins (Ref. 28). Risk analysis attempts to quantify the uncertainties that are inherent in the select any predictive method in such a way that the user can level and type of risk to be accepted and provide a means of to elements the individual contribution of various identifying the overall risk. In simple terms, schedule are (uncertainty) can be divided into Included in these cost, schedule or technical. three categories: categories risk the changes, effects of inflation, technologies, new shipyard productivity, plus others. In this section, some of the techniques that have evolved to estimate the cost risks in shipbuilding will be examined. An addressed important area in risk that the uncertainty associated with the cost is of the estimator will go a long way The experience the uncertainty in the system cost. important cost terms of Experience is to is not analyst. reducing particularly in areas where costs associated with technical changes must be extrapolated from existing data. The general In the first probabilistic cost risk methodology step, input estimates distribution, as is indicated in terms of are e:pressed opposed to in Fig. 2.10. a a traditional deterministic (i.e., point) value. These inputs include the cost II -- Weight WBS Structure With Cost Factors Or Radr Renge . _ W CERs Each A IA Probability Distribution All Categories Summed P(C) Analytically or by Monte Carlo Cost Dollr OUTPUT INPUTS * The Distribution of Possible Costs as a CDF * Physical or Performance Parameters for CFqs * Direct Cost Estimates The General Cost Risk Analysis Approach (Ref. 32) Figure 2.10 83 of GFM, performance characteristics, weight, and other technical required in most cost estimating methodologies. definitions a example, cost about analyst may know something the For lowest most likely value, and upper bound of an input or perhaps bound, the mean and variance of its distribution. second step in a general risk analysis is to The input non-cost the variables functions distribution probabi ity separate to (PDF) transform subsystem cost the CERs using developed. The PDF shows the probability of occurrence of a given costs estimate. It is important to note that since based on regression analysis, are they introduce an the CERs additional uncertainty into the process. step is the summation of the separate The final PDFs, subsystem using either analytical or simulation (i.e., Monte Carlo) to obtain the total PDF for the ship. However, the most methods, useful presentation of cost uncertainty indicates the probability of exceeding a given sum (generally the most This is the type of distribution the risk analysis of output likely shown in Fig. process; 2.11 as the final it is referred probability distribution (CDF) and is the cumulative estimate). to as result the of integrating the area under the PDF. 2.15 Fig. and Eqns. (2.11-12) illustrate the relationship between the PDF ( p(x) or frequency ) and the CDF ( P() and pessimistic values are the best estimates of optimistic lower and upper Note the The ). bounds, respectively, characteristic effect S-shape the for the cost of the system. of the of defining systems more 84 The CDF. fully and therefore MOST LIKELY PROBABILITY DENSITY (FREQUENCY) I I I OPTIMISTIC PESSIMISTIC COST ,,, 1uu 90 PROBABILITY THAT COST WILL NOT BE EXCEEDED 10 0 OPTIMISTIC PESSIMISTIC COST Density Uncertainty Measures Using Probability and Cumulative Density Functions (Ref. 19) Figure 2.11 85 obtaining a more reduction in the interesting to accurate cost estimate would be seen width note of costs under that, according the to S by curve. Eqn. It with zero uncertainty would reduce to is (2.12), probability of any point estimate being correct is zero. system the a the Only single a point estimate. In this study, risk is defined as the uncertainty measure of a ship costing estimate. uncertainty to be found the variance (see Eqn. Although there are several measures of in the literature (e.g., see Ref. 18), 2.14) is probably the most familiar. The variance is often used with the mean to define a coefficient variance (COV), which is simply the square root of the variance divided by the mean value. Since COV of the COV increases in relation to uncertainty, values should be expected during conceptual and design, and smaller values for contract design. the uncertaintyof weight using existence of this concept, constant COVsfor classes of larger preliminary Ref. 29 treats and suggests items (i.e., the hull, propulsion, etc.). Both material and labor contribute to the uncertainty estimate. However, the uncertainties are usuallymuch more significant. be positively skewed (i.e., there is a physical given task. produces of any associated with labor costs Individual labor costs tend to skewed right in Fig. limit on the minimum time to 2.14), since accomplish a At the total job level, the:summation of these tasks a close approximation to the normal distribution (Ref. 29). Cost interval estimates are often used to epress uncertainty where in a point estimate: is the most likely X for example, estimate value. $X + or - 10%, such However, a statement can be misleading without a proper statistical frame of reference. For a randomly distributed variable, the level of provide confidence or variance associated with the estimate will the appropriate frame. The level of confidence, or confidence interval, gives the probability of the variable actually falling within the specified limits expressed (i.e., $X + or - 10%) at any given time and is typically as a percentage. For a normal distribution, shows the variation of confidence levels with number of Table 2.8 standard deviations (square root of the variance) about the mean (also the most likely value for a Gaussian distribution due to symmetry). Number of Standard Confidence Interval (%) Deviations about the Mean 38.30 ). 5 68.26 1.0 86.64 1.5 95.44 2.0 99.74 3.0 Relationship between Confidence Interval and Standard Deviations for a Gaussian Distribution Table 2.8 87 that the greater the range for It is obvious from Table 2.8 the estimate, the higher expressed as standard deviations about the mean, the confidence that the estimate will be within the specified range. The relationship further illustrates that a cost interval or estimate must be associated with a confidence measure of the standard deviation as related to a interval particular probability distribution. The previous discussion points out the used in risk analysis. major assumptions These are as followsl or subsystems; is made up of a set of elements (1) a system (2) total system cost is the sum of the element (3) there is a cost estimating relationship costs; (CER) for each element; (4) variables, the inputs to the CER are treated as random and; (5) the element costs are stochastically (i.e., statistically) independent The last assumption has been used in several analyses (e.g., see ,Cefs. the input 19 and 28). However, the influence variables can have a significant of dependency among effect on the system CDF and subsequent cost risk analysis (e.g., total see Refs. 31 and 32). The input variation in the CDF for independent variables reduction is shown in Fig. 2.12. versus The obvious dependent effect in the cost uncertainty for independent inputs dependent ones. Therefore, is a versus the assumption of independent inputs B8 I _ 1.0 .8 .6 r 0 VC 3 X 2 0 .4 240 260 280 300 Cumulative Dersity Functions for Dependent and Independent Input Variables (Ref. 33) Figure 2.12 89 320 360 results in an overly optimistic prediction of uncertainty when dependency does indeed exist. The cost estimating methods discussed in this study use SWBS weight groups program as major will show, ship weights, input parameters. As any ship synthesis there is a high degree of dependency performance characteristics, and other among technical inputs. 2.3.2 Analytical Methods 2.3.2.1 Cost Element FPDFs In the context of this study, a cost element can refer to a sub-system cost (i.e., SWBS weight group cost, GFM, etc.), a noncost input for a CER constants cost or the regression in a CER. Analytical of (i.e., weight, SHP, etc.), methods provide analysts with a certain expectations and dispersion in certainty by measure fitting probability distribution functions with well-known and understood properties to the cost elements. In reality, the actual shape of the PDF is unknown. However, it is possible to identify some logical characteristics (e.g., see Ref. 31). These include; (1) it should have fixed, positive upper and lower bounds; There including (2) it should not necessarily (3) it should be unimodal, and; (4) it should be computationally are several PDFs that be symmetric; satisfy simple. these (in decreasing order of complexity), 90 requirements, Beta, Gaussian, triangular and distribution distribution uniform distributions. can be generated The Gaussian as a limiting form or of normal the beta (Ref. 33). Table 2.9 indicates the variation of skewness and kurtosis among these four distributions. Skewness is a measure of symmetry about the mean and can be calculated using the expression; skew = ( mean - mode ) / standard deviation where the standard deviation is the square root of the (e.g., see Eqn. 2.14). Kurtosis provides peakedness of the distribution (i.e., of (2.7) observations under the curve), variance a measure with high Distribution Skewness Beta any value Triangular indicating values Kurtosi s > 1.8 O 5 -. 565 to .565 2.4 0 1.8 Uniform Comparison of PDF Characteristics Table 2.9 91 the a comparison of the spread less spread. Gaussi an of use of any distribution requires that a minimum The amount information for each cost element be provided to the analyst. of This method (i.e., opinion) and is generally in the form of the most likely information expert can be obtained by the Delphi value (mode), lowest bound and upper bound. In some cases the user may not wish to set absolute lower may be a low estimate and an associated probability of the probability of and upper limits. supplied with underrun, the In such an instance, mode, a the cost analyst high estimate and overrun. The of the preceding cost element data will completely specify any four PDFs. If it is only possible to assign and upper lower bounds to the element, the uniform distribution is used. 92 2.. 2.1.1 Beta PDFs A range of normalized beta F'DFsare shown in Fig. indicated required by Eqn. to function. (2.8), uniquely parameters alpha and determine the shape of the than zero (Ref. 33). Eqns. how these parameters are related to the mean and The random beta As are normalized For the beta distributions to be unimodal, both alpha and beta must be greater show the 2.13. variable X, on the interval (2.9-10) variance. 0 to 1 can be rescaled and shifted to the cost element range of "a" (low value) to "b" (high value), using the transformation The beta because it distribution is well suited to can assume (peakedness) and skewness. model any variety "a + (b-a)X". many shapes with costing varying itself to the procedure of graph which the analyst selects a graph from a family of skewness. selection, an example of such a series of plots, variance and skewness. 93 showing This in distributions which best characterizes the cost element uncertainty. is kurtosis These properties allow the analyst to amount of variance (dispersion) and lends analysis Fig. 2.14 differences in 4 3.6 F U N C T I 0 3 2.5 2 N V A L U E 1.5 ! 0 X VALUES whe re f(x) - r(a+ ) xai ( r(a)*r(s) having mean 14 and variance 11 - 0 2 B a (C) (++) (ar+B) 2(Q+B+1 ) The Normalized Beta Probability (Ref. 33) Figure 2.13 94 (2.8) 2 a a+ B- Density Function (2.9) (2.10) ri SkwSud Skw^lod left LI0 mo XuX H L M L M . L M z i H L M H L M L M N L M H L M n L M H Medium LW V'erCl H Shape Variations using Beta PDFs (Ref. 33) Figure 2.14 95 Gaussian PDFs 2.3.2.1.2 The form of the Gaussian distribution function is shown in (or normal) Fig. 2.15 and probability by Eqn. (2.11). Whereas the beta PDF requires four parameters to define its shape and range (i.e., alpha, beta, high and low values), the Gaussian PDF only needs a mean and variance (see Eqns. 2.13-14). The symmetric applicable elements of the Gaussian curve is to the distribution of a large number of and elements. shape is not particularly applicable to generally independent single cost Also, the distribution has no finite endpoints. These character stics limit its use in cost risk analysis. Trianqular 2.3.2. 1.3 tri.ngular The simpl i city Its shape most li kel shape PDFs distribution anc' wide range of applicability (e.g., due to see Ref. can be determined with only knowledge of the its 33). lower, y, and high estimates. Fig. 2.16 indicates the possible a of triangular distribution for three (most like,ly values), between is very popular the lower m. different modes The location of the mode in the range es;timate, a, and the high estimate, determines the degree c)f skewness for the cost element. The analytic form for this PDF is shown in Eqn. (2.15), and the resulting mean and variance for a triangular distribution can be calculated integration using Eqns. (2.16-17), respectively. of this PD)F gives CDFs in good agreement complex analytical functions (Ref. 3). with The more *a I. P(x) .I 0.0 p(x) where 1-- p(x)- P(x) =and a, ,)/( p(t)d (2.11) (2.12) the mean value of x and oa the variance of x. N fx=N ~ (2.13) Xi il 2 k N (Xi ', x,)2 i-i where range of index i from 1 to N is over all members of class The Gaussian Probability Density Function Figure 2.15 97 (2.14) 3 2 F R E a U E N C y .I where -) a)(b 2(x - x- ) 2 (b (b - m) (b - a) im p . x< m (2.15) f(x) - having ; a mean and variance ; m x< b 2 (2.16) a + m +bb 3 2 aO a(a - nm)+ b (b - a) + mn 18 The Triangular Probability Density Function Figure 2.16 98 b) (2.17) Uniform PDFs 2.3.2.1.4 For cost element are known, the uniform a estimate lower the "b", of this function, mean and variance f (x) = 1 / (b - a) (2. 18) mean = (a + b) (2.19) / 2 = (a - b) 2/ (2.20) 12 Method of Moments analyzing method of moments provides the capability of The the risk (uncertainty) inherent in the summation of and dependent using For can be used. of PDFs are as follows; variance 2.3.2.2 distribution a to "a" and an upper value equal to density probability simplest equal of and upper bounds when only the lower situations cost elements polynomial CERs. that are input directly In this study, the independent or estimated following additive polynomial relationship will be discussed; Cost = C 1Cos 1 + C22 + C 3 + ... + CN N (2.21) (2.21) C s represent the independent or dependent subsystem where the costs. The values of C are estimated from CERs of the form: C = X + X2X P where the X s are cost elements a constant. ignored in (2.22) + error term or regression constants and F is The error term is generally unknown and is typically subsequent calculations. 99 For costs that are input C = X1. directly, Using the moment of methods, the estimation of the total system cost PDF involves four basic steps: (1) calculate individual sets of moments for each CN in Eqn. (2.21); (2) add the N sets of moments (3) fit a PDF with moments in calculated (i.e., the first step, Eqn. used of first origin (moments (2); additive moments, Eqn. 2.22) are calculated. expressions knowledge equal to the sums numerically integrate the PDF to obtain the CDF. (4) In together; to calculate the A s, for each CER (2.23) shows that the moments additive the Taylor series representation moment about Ref. CER, and three central (the mean value), the mean). of the require 32 indicates that the moments these four will provide sufficient information to determine the FDF moments asymmetry and shape and yet allow easy computations. The Taylor series ,i' of mean is X. straightforward Expansion and would to about the mean, higher probably and values is order be The first additive moment does not include the accurate. series input variable, each derivatives (2.23) is expanded in Eqn. Taylor the merely the value of the CER calculated using for all Xis. Subsequent moments the CER partials, each evaluated at its i require more the slim of mean value. For directly inputted costs, the value of the partials would be mean equal to one and the cost, variance moments would be equal additive (i.e., A 1 and A 2 ) and a combination 1 00 to the of the central moments. If second the values of C N step complete properties then into A k moments) linear D the N (Ref. 33). dependence, which moments, as the A moments the of the sum is equal to the (i.e., the A k moment sum of the individual transformed independent, in the method of moments is the addition of sets of A moments For can be assumed (Ref. have 33). of the sum is equal to the sum of the the A must moments the same Therefore, be additive the D k moment individual D k moments. The relationship between the moments is given by Eqn. (2.24). Once then a the total system cost moments have been PDF can be fit using the values calculated. calculated, The actual system cost moments will fall between the independent total dependent values obtained using Several (2.23-24), respectively. methods have been used for fitting a given distribution. 28 and 33 outline Refs. Eqns. and the methodology involved in fitting the moments to a Beta distribution. If an independent Gaussian distribution is assumed for the elements, only the first two additive moments (mean and variance) need to be calculated (Ref. 29). For dependent variables, the mean and standard deviation are summed for the total system cost. Since than the a square of a standard deviation summation variance associated with summation (for dependent the variables same is values), greater independent ones. This is illustrated in Fig. 2.12. 1 01 is greater the risk than for Al= C (ul, u2, . . Uj) A2 = ( acGX) ax, )2 U 1(2) A3 = ( ac(x) X, )S U 1(3) A, =Z aax ac(x) (2.23) )4 (U,(4) - 3u,((2)2 ) where the partials are evaluated at u,, . and u,(,) is the kth central moment of X,. D 1 = C (u, 2 )2 Ul(2) a(x, (2.24) accx) )9 U((3) 3 £(x, 3 4 u2, ) aC(X) D2 4 , - where ( ac(x) )4 -AX, Dk U/( 4) dependent Ak = independent additive moment additive moment Additive Moments for the Methodof Moment Calculations Figure 2.17 102 2.3.3 Monte Carlo Methods Monte Carlo or computer simulation methods are techniques in which the constant regression is determined by selecting random numbers subject to probability law. defined within value generated for a cost element or CER If the generated random number the limits of a pre-determined probability range, a falls then a particular value for the variable is chosen. Because variables the method involved, that the full this respect, simulates a random sampling of the several computer runs must be made to ensure range of values for each variable the Monte Carlo method is is obtained. iterative, In since the exact number of calculations is not known beforehand. Several simulations techniques numerical more that Slice (see Ref. Monte Carlo techniques have been developed ef f i cient and less time to make consuming. Two are discussed include Stratified 32). They differ from so-called random sampling methods by the Sampling and straightforward number and size distribution of intervals along the probability range. Figure Sampling as estimated the The additive 2.18 shows the decrease in error for the compared error is from the differences between the simulation values of greater simple moments and those convergent reduction to nature Monte Carlo. obtained from exact calculations. of the simulations is obvious in errors associated with number of efficiency and The Stratified accuracy of simple Monte Carlo is easily seen. 103 runs. Stratified from the Also, the Sampling over _11_ 9% f la C to (A tZ On a. LU 1000 10,000 100,000 Number of Runs Decrease in Variance Error with Increasing Run Size for MonteCarlo Methods (Ref. 32) Ficure 2.18 104 1,000,000 CHAPTER 3 DESCRIPTION OF SPECIFIC SHIP COST MODELS There is certainly no shortage of cost models in use at this time. use There by models are probably a dozen or so official cost models the US Navy alone, kept "official" within not to mention a myriad the agencies estimates. In to addition, involved in the ship or shipbuilding of independently the majority of in private check the companies industry possess their own cost models. It is important to understand that these cost models serve different functions for different organizations. For example, the cost models at NAVSEA Code 017 are intended to provide estimates for ship construction. budetary The models in use at the Naval Center for Cost Analysis are used by OPNAV to provide independent checks on new ship construction bids that are received. models are used by NAVSEA design teams to perform cost Cost trade-off analyses. Contractor cost models are used to submit contract bids for new ship construction. Also, there are government agencies that are interested in the development of cost models. the development For instance, of ASSET and RCA PRICE cost models at DTNSRDC future Navy applications. for The intent of this chapter is to provide a of cross-section conceptual/preliminary cost models in use at The first part of the chapter is a description of five this time. cost representative which are applicable for this type of models stage early These include NAVSEA Code 017, Naval Center for cost estimating. Cost Analysis (NCA), ASSET, USCG and RCA PRICE. All order models require an estimation of the that costs can be determined. for accounted using for each model parameters Due to the databases, the qualitative one. variety in are Technology differences of As methods. the models and their use, of description a weights SWBS the as well a input necessary are listed. proprietary nature of cost comparison of these Perhaps further models models is their and pirimarily a studies could focus on a more quantitative study involving specific vessel costing comparisons. Typically, the point estimates during conceptual design are plus or minus 15-25% range. range may be reduced to 5-15%. of assumptions After preliminary However, design, the due to the large number inherent in any cost estimate, it would that any "reasonable" cost estimate can be rationalized. 10)6 in appear 3.1 ACQUISITION & LIFE-CYCLE COST ESTIMATING 3. 1.1 NAVSEA CODE 017 3. 1. 1.1 General SEA Code is This office of the Naval Sea Systems Command (NAVSEA). Analysis charged the responsibility for with official ship cost purposes and for for estimates the Department annual shipbuilding budget (e.g., see Ref. the preparing Navy's programming and planning and Estimating 017 refers to the Office of Cost (DoD) Defense of 16). These responsibilities encompass ship cost estimating and analysis at the initial design feasibility serves as study phase through production award. advisor in trends emerging on to NAVSEA all elements the historic, of cost SEA 017 current, and estimating also and cost analysis. Generally, the Shipbuilding and Appropriation (SCN). An SCN procurement item procurement shipbuilding Navy Conversion, that SEA 017 estimates are used in the preparation of account, has been authorized by Congress must be full funded or work must cease. the This full funded policy ensures that monies are for all reasonable and expected costs through the ship available construction and post-del ivery period. Ship estimates cost prepared under this policy are said to be "end costed". every Since treated have as official NAVSEA ship cost estimate a potential budget candidate, been established certain to ensure the estimate is proper context. These are as follows: 1. a written OPNAV (Operations, NAVY) cost and 1(-)7 be requirements is treated feasibility request must be in hand to in its 2. formal technical design inputs (e.g., SWBS weight groups) must be available 3. an approved acquisition strategy and shipbuilding schedule must be available 4. a cognizant Program Manager must be involved It obvious that ship cost estimating within the becomes NAVSEA community operates within a controlled environment. There are four principal divisions in the acquisition design process: feasibility studies, preliminary design, contract design and design. detail their relationship and The first three new ship design phases milestones to the key Navy acquisition and to the quality of SEA 017 cost estimates are shown in Figure 5.1. detail The phase or design agent. shipbuilder various design phases, the is the of responsibility As the design proceeds through the quality of the cost estimates increases inputs. with the range and depthof the technical proportionately In study, this a calculating Class the cost estimating methodology F estimate is considered estimates The quality. calculated level of breakdown. is is This outlined. to be of feasibility design method is essentially the same used Class D and C estimates. However, Class used class "ball to D and C estimates calculate use one-digit two-/three-digit based on technical definition available at the completion 1 ()8 of park" The Class C estimate is considered bdget-quality the Preliminary Design. for whereas a Class F estimate is from the light ship weight estimate at the SWBS, the and of C D Acauisition Review Milestones, Technical Definition and Cost Estimate Quality (Ref. 16) Figure 3.1 109 3. 1. 1.2 Cost Estimating Relationships The based cost estimating methodology outlined in this section is upon the input/output model. information printout available in Ref. 16 from the Unit Price Analysis and (UPA) cost UPA model was designed to address the cost The an elements discussed in this section. Cost estimating relationships used within and preliminary design phases, feasibility SEA 017 for are calculated from manhour and material costs divided by the weight of the selected seven major SWBS groups. These factors are updated annually based on historical data as well as return costs on previously awarded shipbuilding awards. contracts In addition, and the past year's bid data on new all GFM lists are reviewed and adjusted as required. As SEA previously mentioned, ship cost estimates generated 017 are said to be "end costed". constitute major a total end cost estimate category codes The cost categories by that are shown in Figure 3.2. The (MCCs) conform to the cost collection/accounting and budgetary systems of NAVSEA. The categories of an end cost estimate can be separated into three groupings; shipbuilder portion, material (GFM), and miscellaneous GA The sum of the basic construction, escalation portion The and change order cost government furnished (general & administrative). construction plans, categories contract constitute the of monies that are paid to the shipbuilder/design agent. GFM portion is made up of government ordnance/air, propulsion. H,M&E The (hull, remainder mechanical supplied & electronics, electrical), of the program costs are 110 and associated -C------------------C-·l Gro 100 200 300 400 600 704 800 900 Other Support MCC800 Test and Inst rutentat on MCC541 Stock ShoreBased Spares NC 533 Program Manager Reserve lCC951 total Dollats Categories of a Total End Cost Estimate (Ref. 16) Figure 3.2 111 -------- with a variety of G&A costs. The basic construction cost (MCC 211) is the central element of the NAVSEA ship cost estimating process. Basic construction is defined as construction. the It original contract includes award all allowable price labor, for ship overhead and material costs plus an amount for cost of money (COM) and profit. Labor manhours, MH (hrs), and material costs, MC (M), cost factors are developed for each of the SWBS weight groups 100-700, such that; MH. = KL. W. 1 where 1 (3.1) 1 Wi = appropriate SWBS weight group (LT) KL i = appropriate manhour cost factor (hrs/LT) MCi =i KM where KM (3.2) = appropriate material cost factor ($M/LT) Estimates groups W of labor manhours and material costs 800 and 900 are typically sum of manhours and material estimated dollars for SWBS as a percentage of the for groups 100 through 700, such that; MH = FL 8 (MH1 + MH2 + .. + MH7) MH 9 = FL9 (MH1 + MH 2 + ... + MH 7) (53.3) MC8 = FMB (MC1 + MC2 MC9 = FM9 (MC1 + MC2 + + MC7 ) + .. + MC7) 112 where FLi = appropriate labor fraction (%/100) FM. = appropriate material cost fraction (%/100) 1 Representative 0.25-0.35, values for these variables are; FL 8 and = FL and FM 9 = 0.01-0.10. Labor manhours can also and; FM be estimated using manloading profiles based on previous programs. The design and builder's (D&B) margin is costed and included as part of basic construction on the assumption that the will be "used up" during the development of the design construction margin and in of the ship as awarded. The costing of the margin is done by applying the DB margin percentage to the total and material dollars manhours for groups 100 to 900; MHD& = FD& (MH1 + ... MH&B E F.D&BB ) + MH9 9 (3.4) MC where D&B( = F (MC D& 1 + + MC ) 9 F = D&B fraction (%/100) D&B The D&B margin is generally on the order of 12%. For calculating employed for Manufacturing labor manufacturing rates is and separate labor engineering are applied to labor associated weight groups 100-700, rate costs, 900 and the D&B margin. rates are operations. with SWBS The engineering applied to the labor required for SWBS group 800 work. For any given labor rate, the labor cost, 113 LC ($M), is given by the simple expression; LCi - MH i */HR where (3.5) $/HR = appropriate labor rate (dollars per hour) Overhead costs, OV ($M) are calculated as a percentage the labor costs associated with each of the SWBS groups of 100-900, such that; OV. - F 1 ovhd LC i where F = The cost ovhd margin, direct C labor overhead fraction (%/100) of construction for each SWBS weight ($M), is and overhead Ci The simply the addition labor costs, group of material plus cost and so that; = MCi + LCi + OVi (3.7) cost for each SWBS group can be summed to arrive at intermediate CC The (3.6) ship construction = C1 + C2 + ... - cost contractors for of the money cost cost, CCC ($M), where; C9 + CD&B (COM) is an (3.8) intended of providing to capital compensate for facility fraction of facility costs that contractors can treat as capital invested in investments. the costs Government marketplace. is referred standards specify the The rate of return allowed on these investment to as the imputed interest rate. The amount used for the COM is calculated by multiplying the sum of the estimated direct labor costs by an appropriate factor. 114 This factor is computed by multiplying the shipbuilder's net book value of assets times the imputed interest rate and divided by The base is set equal to the direct cost allocation base. labor a labor dollars expended in the shipyard for a particular year. The for the COM is as follows; equation COM = Fcm where F cam = (LC1 + ... the COM (3.9) LC9 + LCDB) factor (%/100) = (net book valua) (im_ ted interest rate) (allocation base) Cost of money is also referred to as facilities cost of money of the basic which can be abbreviated to FCM. Profit construction is the final element cost. Profit, percentage of the sum of all in the estimation C ($M) , is calculated SWBSgroup plus margin costs. as a It can be expressed as; Cprofit where and (3. 10) Fp CCC Fp = profit fraction (%/100) CCC is the construction cost estimated After- the profit dollars are calculated, costs, cost of money and (3.8) in Eqn. construction the profit are summed to arrive at a complete basic construction price, PBC ($M), where; PBC It is construction = CCC + Cprofit important price be that + (3. 11) COM all elements making up adjusted to a common dollar the basic base date. Shipbuilding contracts are generally costed to a given near- 115 term base date. reimburse The contracts include an escalation the shipbuilding shipbuilder for inflation to in the occurring industry over the life of the contract (as measured from the base date in the contract). is estimated , Ces c ($M), and clause The dollar requirement that reflects a specified building assumed labor outlay profile (e.g., see Fig. **). an Several of the end cost categories are typically calculated as a percentage of the basic construction price (i.e., Construction , plans change reserve categories are all Construction to period the orders and PM Eqn. 92). (program manager) examples of this type of methodology. plans refer to the nonrecurring costs related development of detailed construction drawings and other associated engineering tasks by the shipbuilder or design Associated computer tasks include programs, damage control books, lead ship related contractor engineering responsible calculIations, technical ships selected records, agent. manuals, and mock-ups. The normally carries the majority of the costs for this category. Historical data is reviewed to determine what percentage the construction similar plan costs were of the basic construction price new designs. Percentages developed in this then adjusted by judgement factors, obtain the cost of construction C CCP where F Fconstr constr such as ship complexity, plans, =acto a complexity factor (typically > 1) construction plan fraction (%/100) 116 are to CCp ($M), where; =FCfactor F F constr PBC r manner on (3 12) (3.12) A typical value for Fconstr expressed in terms of material, estimate is and overhead costs, COM The is 0.12. labor, final and profit. The change order category is simply an allowance of money to fund necessary changes after the shipbuilding is contract awarded. Some of the reasons for these changes are: - To include state-of-the-art improvements that come about during construction - To correct "fit-up" problems that surface due to incorrect drawings - To correct differences between contract drawings and ship specifications - To incorporate safety items that become evident during construction - To incorporate improvements that are generated by the operational forces afloat - To have the shipbuilder repair or modify GFM (government furnished material) - To change the contract ship delivery point or the contract date of delivery For the lead ship, change order costs , Ccord ($M), are estimated by the following expression; Ccord = 10 PBC (3.13) For follow ships, change order costs are given by; Ccord 0.05 (3.14) PBC 117 The 10 and 5% figures reflect new NAVSEA guidelines programmatic costs. the lead and of respectively, ships has been taken as basic construction price the reduce the cost of change orders for Historically, follow to 12 and 8%, (e.g., see the ASSET cost model description). Although the change order dollar amount is estimated in base year dollars, it Therefore, it is not inflated over the life of the contract. throughout represents a total amount to be spent the construction period. Government furnished material (GFM), including both hardware and software, installation Navy is by the provided aboard Navy to shipbuilders for period. The ships during the construction chooses to supply these selected equipments for any cost The GFM categories can be a significant savings and convenience. portion security, safety, including standardization, of reasons, number these The estimator must ensure that of the ship cost. costs are not duplicated in the basic construction category. electronics, are categorized (see Fig. CGF M ($M), GFM costs, Electronic items include electronics Electrical) and propulsion. production components, training and services, engineering and (Hull11, Mechanical H,M&E ordnance/air, 3.2) into support repair equipment, parts test associated and with installation. The ordnance/air systems, search radars, training support items include fire and missile control missile launching systems, gun systems, equipment, test and integration services, landing aids, and selected catapult components. H,M&E items consist of H,M&E 118 equipments, small boats, installation with Some equipment. H,M&E of training and repair parts H,M&E engineering services, support equipment, associated equipment, environmental protection special vehicles, "unofficial" estimates have calculated the cost of this category as 2% of the basic construction price. GFM usually involves nuclear propulsion systems. Propulsion Components responsibility generally conventionally powered ships are for the of the shipbuilder and are therefore included in the estimate for the basic construction price. estimates for each of the GFM categories are Cost These lists are reviewed using appropriate GFM "shopping lists". ship design compatibility and base year pricing. for prepared Historical data on similar purchases are used for comparison purposes. The shopping list approach for GFM cost estimation is broken into the following cost elements: - major possible it make for as the primary units defined hardware, the total system meet to the that mission requirement; - ancillary equipment, required to logistically support the such hardware major special tools, gauges as data/documentation, the data installation, equipment, and jigs; - technical documenting test special-purpose complete integration, package operation, and developing for and associated with maintenance of the hardware or system; - spares, of an required to ensure the operational readiness equipment or system until the normal Navy 119 supply system assumes support; - system engineering, ensure to engineering support required the integration of the various components that make up a major hardware item; - technical engineering services, contractor/vendor and services required to support efforts engineering government to attain system operational readiness; - other costs, including nonrecurring production startup, training, software, test and evaluation, and changes. there is the diverse nature of GFM equipments, to Due no standard procedure for estimating GFM costs. Delphi (e.g., vendor quotes), analogy, wherever they CERs, are or engineering methodologies are used the best deemed appropriate produce and results. Whatever method is used, material, labor, overhead, COM, and profit estimates are obtained for each GFM category. remaining The miscellaneous the include cost categories comprise end number a of G&A cost elements (programmatic in nature). These test and of categories instrumentation, other shore-based stock support, spares and program manager reserve. other The functions, costs, support in support engineering services, engineering services. previous a variety of G&A including but not limited to equipment transportation travel Other involves category support ship of ship commissioning costs, Cothe r acquisition programs, acquisition managers, acquisition, ceremonies, ($M), are and contract in-house estimated are supplied by the from ship or can be estimated as a percentage of the 120 basic construction price, so that; Cother where Fsup PBC (3.15) F sup = other support factor (%/100) value A typical for is 0.0C8. test and instrumentation category includes the cost The and instrumentation (T&I) related to routine or testing leading trials F to qualifying a ship for special service. active of The majority of these costs will be borne by the lead ship. Estimates for test and instrumentation costs, C (M), ship The obtained by analogy/comparison with previous programs. are acquisition program managers can provide necessary information on the number of trials and special tests that are costs can be adjusted to reflect the current must costs The be inflated to the requirements. proper time The period, is conducted before ship stock shore-based spares category includes procurement that most of the T&I effort remembering delivery also Fast required. and acceptance by the Navy. of back-up spares for stock ashore or aboard tender/repair ships. The stock spares funded in this category are limited to first-ofits-kind installations propellers, on anchor chains, the lead anchors, Examples ship. inc Lde turbine generators, diesel and gas turbine engines, and selected shafting. Items included in the stock spares cost, supplied will by the program manager. already assembled have priced C In most cases, the equipment from ($M), the estimator shopping lists or H,M&E for estimating the basic construction costs 121 are GFM. If this is not the case, marine vendor quotes can be obtained for the item. The Program Manager (PM) reserve category provides a source of funds to the project manager for unforeseen future problems or actions. This cost reserve is made up of the following elementsi - general cost reserve, for general risks in the estimating and acquisition process, equal to 1% of end cost (less contract escalation); - lead ship cost reserve, for cost uncertainties associated with introduction of the first ship of a new class, equal to 3% of end cost (less contract escalation); - follow ship cost reserve, for uncertainties associated with follow-on construction, equal to 2 and 1% of end cost (less contract escalation) for complex and non-complex ships, respectively; - cost reserve for less than budget quality (i.e., Class D and F), equal to 1% of end cost (less contract escalation) Complex craft, The and ships are defined as combatants, unique ships other ships with significantly complex GFM appropriate percentages to be applied to 122 systems. estimate dollar amount for PM growth can be found in Table 3.1. and the Budget Less Than Budget Quality Qual i ty Program Type Lead Ship - New/Modified Repeat 4% 5% - Complex 3% 4% 2% 3% Follow Ship - Not Complex Percentages to Calculate Program Manager Cost Reserve (Ref. 16) Table 3.1 The PM cost reserve, CpM ($M), is then estimated using the following expression; CpM = FPM (PBC + CC CGFM + + Ccord (3.16) CT&I where Cspares Cother Fp PM = program manager reserve cost fraction (%/100) (from Table 3.1) The total end costed price for a lead ship, Ptotal ($M), is estimated by summing the individual cost categories in Fig. 3.2; total CCp + + PBC Cesc + Ccord CGFM + (3.17) Cother + CT& I + Cspares +CpM When multiple ships are awarded for construction, 123. learning and benefits reduced costs are The anticipated. learning is highly dependent upon the acquisition degree of Another plan. important aspect of pricing follow ships is the exclusion of non- of non-recurring costs occur in the majority only. The ship borne by the lead are which costs, recurring stock shore-based test and instrumentation and construction plans end cost spares, categories. If learning will take place, appropriate learning rates must be (Eqns. applied to both manhour and material dollar estimates .1-3.2). These reductions reflected in a are basic reduced construction price, PBC (Eqn. 3.11). bid Historical data cumulative learning curves, Values for return cost that indicates data. A applied. and so these are generally from learning rates are estimated the learning labor typical prefer shipbuilders historical from rate an labor and Additional cost reductions for follow ship construction are "unofficial" estimate, applicable to direct both overhead, was 92%. realized on change order costs, manager reserves, change as Ccord (Eqn. 3.14), CpM (Table 3.1). Escalation costs and program Ces c a result of reduced manhour requirements and will varying construction periods. Provided that learning rates have been properly applied, all non-recurring costs have been eliminated, been Ptotal total adjusted, (M), the total can be end costed estimated 124 by and related costs have price of summing a follow the ship, following categories; Ptotal - PBC+ Cesc Ccord+ CGFM + (3.18) Cother To assist estimating, provide Navy CpM cost estimators involved include labor rates, shipbuilding pricing, ship POMs (program objective memorandum) are guidance on a range of cost issues. addressed in indices, ROM escalation. cost of money (rough order For example, of the issued Some of the shipyard profit, to topics material/labor (COM), overhead, magnitude) cost outyear estimates, and following percentage values are suggested for the following variables; Fp 10.% (see Eqn. 3.10) F com = 5.588% Life purposes. making cycle formulation) For example, period cost estimates are not required However, process, (see Eqn. 3.9). life cycle especially phase design costing enhances budgetary the decision during the early planning (concept of the acquisition trade-off can be evaluated for cycle (see studies conducted an a total cost basis Fig. 3.1). during as well as this on a performance/technical basis. NAVSEA (Visibility program cost and estimators Management use of ship data Operating and from the VAMOSC Support Costs) to assist in the preparation of the O&S portion of life- cycle costs. The VAMOSC program presents O&S data for Navy ships which in were active commissioned 125 status throughout the particular reporting year. the (Chjef CNO of The cost data are of a quality Naval Operations) has that approved the acceptability of VAMOSC data for decision-making usage. Operating sections for and support costs are presented in 121 cost elements. The first two separate section displays average costs for each of 21 combatant ship types (e.g., C, DDG, six FF, FF6, etc). The second section gives total 08S data for classifications of ships, warfare, patrol combatants, support. The explanation The CV, format by including warships, amphibious mine warfare, mobile logistics, and which these costs are of all the cost elements listed and an is found in Ref. 21. 121 data elements are grouped into the five major cost categories defined below: Direct Unit Costs - identifies the direct cost the associated operation and support of an with individual ship Direct Intermediate Maintenance expended by equivalent - cost of material a tender, ashore or and repair afloat labor ship, or Intermediate Maintenance Activity (IMA) in the repair and alteration of other vessels Direct Depot Maintenance - cost associated with depot level maintenance performed for the ship by public or Direct Recurring private facilities Investment - cost of Account Appropriations Purchase (APA) and Navy Stock Account repairable repair 126 parts consumed by (NSA) or procured for the ship Indirect Operating and Support - cost of those services and items (non-investment) that are required by the ship after commissioning and launching which are necessary to continue operations but not result Operations in and an expense do against Fleet Navy (O&MN) Maintenance, appropriations Table categories 3.2 indicates the five major categories and the category that are summed amounts. Successive in order to sub-categories indicated by further indentation. 127 calculate the in Table 3.2 submajor are Direct Unit Costs Personel Manpower TAD Material Ship POL Repair Parts Supp 1 i es Training Expendable Stores Purchased Services Printing and Reproduction ADP rental - contract services Rent and Utilities Communications Other Direct Intermediate Maintenance Afloat Maintenance Labor Labor Manhours Ashore Maintenance Labor Labor Manhours Material Afloat Repair Parts Ashore Repair Parts Direct Depot Maintenance Scheduled Ship Over ha ul1 Regular Overhaul Public Shipyard Private Shipyard Ship Repair Facility Selected Restricted Avail. VAMOSC-Ships Cost Categories (Ref. 21) Table 3.2 128 Direct Depot Maintenance (continued) Non-Scheduled Ship Repair Restricted Availability Public Shipyard Private Shipyard Ship Repair Facility Technical Availability Fleet Moderization Overhead Public Shipyard Ship Repair Facility Labor Funded Material Special Program Material Other Outfitting and Spares Other Depot Naval Air Rework Facility Field Change Installation Rework Design Services Allocation Direct Recurring Investment Exchanges Organizational Exchanges Depot Exchanges Organizational Issues Indirect Operating and Support Training Publications Engineering and Technical Services Ammunition Handling VAMOSC-Ships Cost Categories (Ref. 21) Table 3.2 (continued) 129 3.1.1.3 Input Information The following input information is required by NAVSEA Code 017's Unit Price Analysis (UPA) computer cost model for estimation in Table minimum ship. of 3.3 Navy ship acquisition costs. of design definition necessary to parameters below 1i sted inputs below are considered to be representative amount The The the are grouped into the of the describe the common driver classifications outlined in Table 1.5. TECHNOLOGY Ship type (e.g., destroyer, SWATH, etc.) Hull & Superstructure material Propulsion plant type Electrical plant type SHIP DESIGN Hull structure weight (SWBS group 100) Propulsion plant weight (SWBS group 20) Electric plant weight (SWBS group 300) Command & Surveillance systems weight (SWBS group 400) Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) Armament weight (SWBS group 700) Design & Builders margin PAYLOAD DESIGN Cost of payload GFE (includes armament and weapons portion of com. & surv.) NAVSEA Code 017 Ship Acquisition Cost Parameters Table 3.3 cost MANUFACTUR I NG Learning rate (labor & material) Labor rate (manufacturing & engineering) PROGRAMMATIC Cost of Money fraction Profit fraction Overhead fraction ECONOMICS Base year $ Base year for BLS data BLSmaterial indices NAVSEA Code 017 Ship Acquisition Cost Parameters Table 3.3 (continued) Output from the NAVSEAmodel gives cost lead and follow Table 3.4 ships. information for The following additional information in is used to escalate/discount the costs throughout construction period to a commonyear dollar value. the Inputted Costs Lead ship end cost Follow ship end costs PROGRAMMAT IC Contract award date Start of Construction Manpower profile (length of construction) Time between ships Number of ships required ECONOMICS Base year S Inflation rates NAVSEA Code 017 Fleet Escalation/Discounted Cost Parameters Table 3.4 35.11.4 Output Information The NAVSEA new ship costing estimating program gives a cost breakdown of lead and follow ship material, total acquisition (i.e., end) costs. cost information: one is a one digit SWBS group ummary information available. 132 overhead and There are two classes next is the so-called P-8 estimating format. the SWBS group labor, summary, of and the Table 3.5 indicates Cost Category Cost Variable (Eqn #) Lead Follow Ship Ship MC. (3.2) same (*) MC same Constructi on Material Cost SWBSGroup 100-700 800-900 D&B Margin 1 (3.3) MCD& B (3.4) D&E same MH same Labor Manhours SWBS Group 100-700 800-900 D&B Margin 1 (3. I:) MH. (3.3) MH D&b (3.4) (*) must include effects of learning, if applicable NAVSEA Code 017 SWBS Output Summary Table 3.5 133 same same Cost Variable (Eqn #) Cost Ctegory Lead Fol 1ow Ship Ship Labor Costs SWBS Group 100-900 LCi 1 (3. 5) same Overhead (3.6) OVi 1 same C.1 (3.7) same Total Const:;uction CCC same Cost of Money COM (3.9) same Profi t Cprofit (3. 10) same Construction Price PBC same SWBS Group 100-900 Material + Labor+ Overhead SWES Group 100-900 (3.8) (3. 11) NAVSEA Code 017 SWBS Output Table 3.5 (continued) 134 Summary Cost Category Cost Variable (Eqn #) Lead Ship Follow CCP (3. 12) NA NA (**) Ship Add-on Construction Plans Change orders cord cord GFM CGFM Other support Cother (3.13) Ccord (3.14) same (3. 15) Spares C Program Manager reserve CpM (3.16) Test & Instrumentation CT&I Escalation C End Costed (sai laway) Ptotal same spares same esc (3.17) (**) Not Applicable NAVSEA Code 017 SWBS Output Summary Table 3.5 (continued) 135 same same (3.18) For budget purposes, the P-8 format. so-called cost breakdown 3.2. A acquisition costs are documented using The P-8 format gives an using the and cost categories partial acquisition outlined listing of the categories used to in output costs is given below. MCC Category 100 Plan costs 200 Basic construction costs 300 Change orders 400 Electronics (GFM) 500 H,M&E (GFM) 800 Other costs 900 Ordnance (GFM) 951 Program manager growth 953 Escalation NAVSEA Code 017 P-8 Output Table 3.6 136 Summary Fig. ship 3.1.2 NCA 3.1.2.1 General for Cost Analysis) was Center (Naval NCA within the Department direct and strengthen cost aalysis guide, to established of the Navy and to ensure the preparation of credible of resources required to develop, estimates military procure and operate systems. Ship cost estimates are the responsibility of the in Their NCA-2. primary costing activity is to personnel independent cost analysis of each major ship acquisition program or considered by the Secretary of the Navy or the to, submitted an provide In other words, NCA-2 develops an independent cost check of CNO. NAVSEA Code 017 estimates. the requirement to Due personnel limited firm architecture the estimating NCA-2 resources, Gibbs of develop of cost a and check naval the contracted & Cox to construction basic cost for an independent method for future near-term frigates, destroyers and cruisers of the USN. Table 3.7 indicates the six ship classes used in the database. built at Bath Iron Works All the ships (BIW). To account for variations in design definition, were developed: were two models a one-digit cost model that utilizes weight data available at the SWBS one-digit level and a two-digit cost model that uses SWBS three-digit level weight data. These two levels of detail allow available at costs to be estimated from technical the NAVSEA planning phase up to the (i.e., including Class F and D estimates information butdget phase as shown in Fig. 3.1). Gibbs & Cox states that the goal of the models is to provide 137 feasibility vessels. level estimates for near-future (i.e., 1980's) The scope of the estimates is limited to shipyard costs only (material and direct labor portion of the basic construction cost) and does not include the cost of GFM for the command and surveillance and armament systems (i.e., SWBS groups 400 and 700, respectively). However, the shipyard's material and labor costs for GFM installation are included in the models. Ship Class DD 931 DDG 2 CG 16 CG 26 FFG 4 14 23 9 9 6 55-59 60-64 62-64 64-67 66-67 77-80 11/55 8/60 7/62 11/64 4/67 11/77 3960 4500 7800 7900 3426 3605 407 420 510 524 414 408 FFG 7 Number Built Year Comm. 8(*) BIW Deli very Date Ful 1 Disp. (LT) LP (ft) * as of 1980 NCA Cost Model Ship Database (Ref. 23) Table 3.7 138 3.1.2.2 Cost Estimatinq Relationships The cost estimating methodology outlined in this section is based upon the information available in Ref. developed for shipyard Additional costs, material such as GFM, costs overhead, Navy program support are not included. 23. and CERs were only labor manhours. training, spares, and However, these additional costs would be available to NCA through the same channels as NAVSEA, and so NCA would be equally able to estimate for each of the end cost categories shown in Fig. 3.2. Various weight groupings (e.g., SWBS groups) were identified by Gibbs & Cox as the primary cost drivers for the development of the cost estimating relationships. Other significant cost drivers include shaft horsepower (SHF), kilowatts (KW), installed generating capacity in type of propulsion plant, and tubic number (CN). These variables are related to material costs and labor manhours for each cost group through simple cost algorithms. These algorithms regression small were developed using a linear technique. number of The linear squares least fit was used because of sample points and the Uncertainty of the future technological direction. The the costs of all the relevant groups are added basic shipyard costs associated with a lead costs and tabular ship's labor manhours are presented in lists of delivery; inflation) productivity) and three to ship. provide Material formats: costs and labor manhours at the time (2) graphs of material labor plotted manhours costs (adjusted for against a relevant of the (adjusted for BIW parameter, shipyard and; mathematical equations calculated from the graphs in (2). 139 (1) (3) - 1950 1960 1970 FFG-7 1.32 FFG-4 CG-26 CG-16 2.75 2.90 2.92 DDG-2 2.95 D0931 2.97 - Shipbuilding Inflation Factors for 1980 (Ref. 23) Figure 3.3 140 1960 BIW return cost data and material costs, MC ($), were adjusted for inflation from the delivery date (see Table 3.7) to a 1980 standard using the following relation: MC19 1980 MCDelivery Delivery ate Date (3.19) Inflation Factor where the Inflation Factor, shown in Fig. 3.3, was based upon the steel vessel index from the Statistical Quarterly (e.g., see Ref. 24). BIW by use total of labor manhours were adjusted to the productivity curve shown in 1960 Fig. standards 3.4 and the following simple expression. MH1980 = MH Delivery Date Productivity Variations workload Factor (3. 20) in the Productivity Factor were due to the effects of and management practises over the building period of interest. 3.1.2.2.1 One-D i git Model The one-digit level cost model relates one-digit SWBS weight group estimates, cubic number, KW, and SHP of a ship to material cost manhours graphically or through and labor simple linear equat i ons. Fig. 3.5 shows a representative SHP (shaft horsepower) for SWBS 200 points were obtained from the indicated as filled-in circles. by plot of material - Propulsion. ships in Table cost versus Actual 3.7 Starred (*) points were and data are derived BIW estimators based on return costs of similar systems. The solid line in Fig. 3.5 indicates the calculated algorithm for the actual data points. The dashed lines are projected algorithms for 141 PRODUCTIVITY MH/TON 600- 500- -0.83 I -I - FFG-7_ 0.90 400- AND PMHTO FACTOR PRODUCTIVITY AND FFG-4. 1. 18 CG-26 1.22 CG-I16-_ 1.17 DDG-2 DD931 300- I 17 l 1.01 200100Y , - - -. -- . 9 DELIVERY YEAR 1955 28 I I 960 C5 r -- . -1.25 v I I I - . a', -I B.I.W. I 1970 1965 DESTROYER TYPE VESSELS *. . - A . - - - - EXPERIENCE 23) Figure 3.4 142 I W N.. , 1980 1975 NO DESTROYER TYPE VESSELS Total Ship Labor Factors for 1980 BIW4 (Ref. . . m -I .33 50 40 aCo 30 nv la O C 20 .C oli 10 40 60 50 70 SHAFT HORSEPOWER (in thousands of SHP) One-Digit Propulsion Systems Material Cost (Ref. 23) Figure 3.5 143 80 90 actual or derived data points, Cost cost, algorithms were developed from the plots for material and labor manhours, MH, for each of the nine SWBS MC ($), groups (e.g., see Fig. *.*) according to the following equation: MH 1 or MC i1 = Slope i CD 1 + Intercept ' where (3.21) CD. = particular SWBS group cost driver Eqn. shows 3.21 and relationships intercepts for the functional form is not meant to imply cost and material of the identical labor estimating slopes and Table 3.8 manhours. indicates the cost drivers for material and labor for each of the SWSS groups. There are several SWBS groups where more than one is satisfactory for the generation of the variable independent cost algorithms. The cost and labor figures used in the model for design and engineering services (SWBS group 800) are applicable to USN ships built after 1970. They include costs from the fbllowing areas: Program Manager's Office Integrated Logistics Support Reliability, Maintainability, and Availability Data Management Producibility Management Test and Evaluation Integration Engineering Configuration Management The figures used for the lead ship should be reduced to 50% for the first follow ship and to 20-25% for succeeding ships of the same class. Construction length of delivery). time If the services were found to be proportional to vessel is the in the shipyard (from keel laying to the building time is unknown, 30 months can be 144 Cost Driver SWBS Group Material Labor Application - aluminumsuperstructure, cubic number 100 - 100 wt. 300 400 600 - steam, geared GT, electric GT - single & twin shaft SHP 200 KW 300 wt. - steam & diesel generators 400 wt. - early & current technology 500 wt. - steam constant values 900 months construction heat - pre & post 1965 habitability - early & current 700 wt. 800 electric - pre & post 1965 habitability length x beam 600 wt. 700 all hull steels aluminum superstructure, all hull steels One-Digit SWBS Group Cost Drivers (Ref. 23) Table 3.8 145 technology assumed for an FFG-7 type vessel. In orderto estimate the total material and labor for the lead ship, the individual SWBS group costs and labor manhours are summed. rate. this Labor costs are calculated using the appropriate labor The total direct labor plus material cost estimated using method not does Adjustments for curves shown in Figs. The include any design margin. builders and productivity are inflation one-digit & based on the 3.3 and 3.4. estimate presumes a subsystems within each SWBS group. given of combination The disadvantage of this type particular of estimate is its inability to differentiate between design features of a new ship and those of the baseline ship from which the algorithms The two-digit were derived. cost model attempts to overcome this limitation. 3.1.2.2.2 Two-DigSi t Model The two-digit of manhour CER. groups, of 22 cost by at least one material which is represented labor for level model consists cost each CER and a Table 3.9 indicates the cost group structure This structure was developed after the two-digit model. was recognized that the BIW shipyard data was not accumulated it in the identical manner that the USN used. The definition of each cost group in Table 3.9 is determined by its equipment content, breakdown. Appendix D as defined by the shows the SWBS contribute to each of the 22 cost groups. the two-digit SWBS weight groups The main advantage level model is that the increased groups are more specifically related to weight, 146 three-digit number of that of cost volume, or power Cost Cost Group - Group Title - - - - - - 1A - - - - - - - - Structural - - - - Group _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _- - Envelope/ Group Title _ _ _ _ _ _ _ _ _ _ _ - _- _ _ _ _ _ _ _ _ _._ _ _ 5A Environment System 58 Fluid System 5C Maneuvering System 5D Equipment Handling System 6A Hull Fittings 6B Non-Structural Subdivisi ons 18 Superstructure iC Foundations 1D Structural Attachmen ts I 2A Propulsion Energy Sy stem 2B Propulsion Train System 2C Propulsion Gases System 6C Preservation 2D Propulsion Service System 6D Facilities 3A Electrical Electrical Power Generaticn 6E Habitability Power 7 Ordnance 8 Design & Engineering Services 9 Construction Services 3B Subdivisions Di stri buti on 4A Vehicle Command 48 Weapon Command Two-Digit Cost Model Structure (Ref. 23) Table 3.9 147 Cost Driver Cost Group _ _ _ _ _ Material _ _ _- - _ . _ B1 _ _ _ _ _ Labor _ _ _ _ _ _-- _ _ _ Application _ _ _ _ _ _- _ _ _ _ _ _ _ _ _ _ _-- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ cubic number - all hull steels 1A wt. - all hull steels 1B wt. - aluminum, steel superstructure 1C 1C wt. 1D ID wt. - steam, gas turbine SHP - steam, geared GT, electric GT - single & twin shaft 2B SHF' - fixed, controllable pitch 2C SHP - steam, gas turbine 2D SHP 2D wt. - steam, gas turbine KW 3A wt. - steam & diesel generators 38B 3B wt. 4A 4A wt. - early & current technology 4B 4B wt. - early & current technology Two-Digit Cost Model Cost Drivers (Ref. 23) Table 3.10 148 Cost Driver Cost Group Material Labor Application 5A 5A wt. - steam & electric heat 5B 5B wt. - steam & gas turbine 5C length x draft 5D 5D wt. 6A length - early & current technology 6A wt. x beam 6B 1 ength - pre & post 1965 habitability x depth - pre & post 1965 habitability 6B wt. 6C 6D bE 700 - early & current technology length x beam complement - pre & post 1965 habitability 6D wt. - pre & post 1965 habitability 6E wt. - early & current technology 700 wt. 800 constant values 900 months construction Two-Digit Cost Model Cost Drivers (Ref. 23) Table 3. 10 (continued) 149 than are the more general seven cost groups of the one-digit model. Material and labor estimates are linearly related to various cost drivers in a manner identical to that described for the onedigit the model 22 according to Eqn. 3.21). The cost drivers cost groups are listed in Table 3.10. 3.8 Tables (i.e., two-digit A comparison for of and 3.10 shows that the cost drivers for the one- and models are similar. This is not surprising since the two models are closely related through the SWBS groupings. As noted previously, GFM, but does installation. the model does not include the cost of account for the costs associated Installation includes material with and shipyard labor for foundations, mounts, magazines and hoists, supporting hydraulics, cables, and electrical systems and their testing. Cost groups 4B and 7 are most affected The more by GFM considerations. detailed two-digit cost wherever there separate groups breakdown is warranted is sufficient technical data to distinguish listed in Table 3.9. When there is a lack the of weight data for a particular cost group, the weight amount can be estimated by use of a weight algorithm (see Ref. 235 Appendix B), or by comparing the known new ship weight percentage distribution with a baseline distributions ship. Table 5.11 lists the percentage of lightship weight for the six ships included in the Gibbs & Cox study (see Table 3.7) plus the average SWBS group weight distribution for 12 Navy combatant ships. 150 Cost Group DD 931 DDG 2 CG 26 CG 16 FFG 4 FFG 7 Avg _--______________________________________________________________ 28 28 37 38 37 B 3 3 3 3 3 4 C 4 4 3 3 4 5 D 2 2 2 3 3 2 36 37 46 47 46 46 2A 21 18 12 11 9 5 B 4 4 5 3 3 C I 1 1 1 1 1 D 4 3 2 2 2 1 30 26 18 17 15 10 2 2 2 2 2 2 2 2 2 4 4 4 4 4 4 7 4A 1 1 1 1 I 1 B 2 4 6 6 5 3 3 5 7 7 6 4 1A B Model Groups (Ref. 23) Table 3.11 151 16.9 4 Percentage Distribution of Lightship Weight for Two-Digit 45.9 4.8 5.7 Cost Group DD 931 DDG 2 CG 16 CG 26 FFG 4 FFG 7 5A 3 3 3 3 3 4 B 6 7 6 6 6 9 C 1 1 1 1 2 2 D 1 1 1 1 3 2 Avg _____---_______--____-----___-----____________________________ 11 12 11 11 14 17 6A 1 1 1 1 1 1 B 1 1 1 1 3 C 2 2 3 4 4 D 1 1 1 1 2 3 E 1 1 1 2 2 7 8 7 8 10 12 8.3 9 a 7 6 5 4 5.5 100 100 100 100 100 100 13.0 7 Total Percentage Distribution of Lightship Weight. for Two-Digit Model Groups (Ref. 23) Table 3.11 (continued) 152 100.0 3.1.2.3 Input Information The Gibbs & material ship. between digit following input information is required by the Cox ship cost models in order to estimate the inputs indicated in Table 3.12 do the model not the SWBS weight group data for the the Ship type (frigate, destroyer, or cruiser) Hull & Superstructure material Propulsion plant type Electrical plant type level of technology SHIP DESIGN Hull structure weight (SWBS group 100) Propulsion plant weight (SWBS group 200) Electric plant weight (SWBS group 300) Command & Surveillance systems weight (SWBS group 400) Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) (SWBS group 700) Armament weight Number of Propeller Shafts Length, Beam, Draft Steam or Electric Heating System Missile magazineflooding requirement Habitability Standards Cubic Number SHP Generator rating (KW) _______--_-------__----_________________________----------_---- NCA Lead Ship Shipyard Cost Parameters Table 3.12 153 two- one-digit TECHNOLOGY Early or Current lead differentiate more detailed weight inputs required for and - shipyard and direct labor costs (excluding margins) of the The NCA PAYLOAD DESIGN Cost of payload GFE (includes armament and weapons portion of com. & surv.) MANUFACTURING Labor rate (manufacturing & engineering) PROGRAMMATIC Length of Construction ECONOMICS Base year $ Base year for LS data BLS material indices NCA Lead Ship Shipyard Cost Parameters Table 3.12 (continued) model. The required parameters for base listed under the economic year calculations outside are category of the range indicated in Figs. 3.3 & 3.4. Calculation Fig. 3.2 for of the remaining end cost categories the shown lead and follow ships are carried out manner similar to that outlined for the NAVSEA Code 017 UFA model. 154 in in a cost 1.2.4 53. Output Output Information from the NCA - Gibbs & Cox cost model is limited shipyard material costs, for the major MC ($), SWBS groups and direct labor manhours, MH, (or a specified values are shown below in Table 3.13. labor costs estimated using this methodology can to within 20% of actual costs Material and direct be considered (Ref. 23). Cost Variable (Eqn #) Cost Category Lead Ship Construction Material subset). two-digit These accurate Cost MCi (3.21) 1 SWBS Group 100-900 Labor Manhours SWBS Group- 100-900 MHi NCA Lead Ship Output Summary Table 3.13 155 to (3.21) 3.1.3 ASSET 3.1.3.1 General ASSET, which Evaluation Tool, is an addresses acronym most for of Advanced the Surface major Ship technological of naval architecture that are relevant to the design of domains Navy warships (e.g., see Ref. 15). ASSET was developed by Boeing Company for the David Computer Services Research and Development Center (DTNSRDC). 3.6, and Naval Taylor As indicated in Fig. is intended to be used primarily in the ASSET Ship exploratory The feasibility phases of the ship design process. program has proven useful in assessing a variety of whole ship technology impacts in a consistent manner. Because it is essentially a synthesis model, ASSET also serves as a repository of current USN design practises. Technical information, formulae were principally ship data, algorithms and empirical supplied by the US Navy. versions of ASSET are available for a variety of ship the present time, ASSET can handle hydrofoils, Updated types. At monohull surface combatants and SWATH (Small Waterplane Area Twin Hull) ships. The ASSET program has been divided into initialization, synthesis and analysis. During the data entered completeness to define the current ship Next, and fatal errors. the data three sections: initialization, is checked is for synthesized until an integrated ship design is acheived, in that each element of data element analyses, that defines the ship is consistent with of ship data. such as Once the design cost, are 156 has carried every converged, out. The other various different 'I MISSION REQUIREMENTS ............. ~~~~~~~ I . -. I I I II I I I . . I - I EXPLORATORY STUDIES I I I I I ,. I I i I , I - I I FEASIBILITY STUDIES ii I I i i ii i I I -~~~~~~~ PRELIMINARY I I L DESIGN I . ,, _ I i I I I I -I · CONTRACT DESIGN I DETAIL I . ASSETApplicability Within the Ship Design Process (Ref. 60) Figure 3.6 157 DESIGN I INITIALIZATION INITIALIZATION START HULLGEOMETRY HULLSTRUCTURE RESISTANCE PROPELLER SYNTHESIS MACHINERY WEIGHT DESIGNSUMMARY CONVERGENCE YES END PERFORMANCE HYDROjTATICS SEAKEEPING COST SPACE MANNING ASSETCaomputational Addules (Ref. 1) Fiaure 3.7 158 ANALYSIS computational Fig. modules within each section are indicated in 3.7. The intent of the costing module in ASSET is to provide costs data which can be used to evaluate the relative life cycle of competing ship systems. major three investment research and considered cost in (R&D), development operations and support (O&S). theoretical basis of the ASSET cost analysis module The the and categories: Life cycle costs are evaluation program developed for the Advanced is Naval Vehicle Concept Evaluation (ANVCE) study. This study, done in the early used the latest available lead shipbuilding to mid 1970s, cost data on a variety vehicles to develop of surface, air and special CERs of future vessel types. purpose naval The ship sample for the ANVCE study and the resulting SWBS group CERs used have been placed in Appendix E. The ASSET cost development of module is shown in Table 3.14. The list of vessels indicates the wide range of vessel types (i.e., SWATH, the sample database used in the ship monohull, etc.) and accommodated. 159 displacements hydrofoil, that can ACV, be Base Year I 1960 1961 1964 1973 1957 1956 1958 1961 1973 1976 1959 1962 1968 1970 Contractor Both Iron Works a' a a . ' a a " . ' · · ' ' * ' · ' '* O " . Bethlehes Steel 0 a Newport News sh p Class DC 1037 DE 1040 DE 1053 PF 109 DD 2 DLO 12 DLG 16 DLG 0 26 SWATH DO SWATH CM DLGN 25 DLGN 35 DLGN 36 DLON 36 Cost Basis Total iMaximum Continuous shp BID ' . PROPOSAL BID ' STUDY 20,000 35,000 35,000 40,000 70,000 8· 5,000 2,654 3,331 4,066 3,561 4,562 5,786 85,000 85,000 60,000 7,645 7,839 3,710 3,441 8,514 8,947 10,056 10,497 40,000 PROPOSAL BID . PROPOSAL 60,000 70,000 70,000 70,000 6,140 15,600 25,850 1973 1967 1976 . Tacoma Peterson/Tao, U . CPIC PG 92 PGG 1 BID ' 1967 Grumann PGH I PROPOSAL .3,470 1967 Boeing PGH 2 ACTUAL 3,260 1961 1974 1964 1975 1974 1974 1974 1975 1974 * * ' . . Aerojet Bell a Rohr PCH 1 PHM 1 AGEH 1 ' DBH STUDY ARTIC SEV JEFF A JEFF B 2KSES () 2K1SE (R) ' BID a 491 ACTUAL 75i ACTUAL PROPOSAL ASSETCost bdule Ship Database (Ref. 1) Table 3.14 160 FLD (LT) 6,800 17,300 29,800 76 254 390 66 58 111 232 295 54,020 1,042 48,000 11,200 16,800 96,000 96,000 540 152 152 1,950 1,800 3.1.3.2 Cost Estimating Relationships calculative sequence employed by the ASSET cost The is a seven step process, step module as illlstrated in Figure 3.8. The first involves a complete review of all data input to the via the current model. invalid The input data are scanned Where appropriate, entries. module for missing or replaced missing data are with default values. The next step involves the calculation of miscellaneous ship data that are required as input to various CERs. These data include the following: NCi th = the i element of the number of crew aboard 2=petty officers, 3=enlisted ship (officers, men), PSum = the total power available from all of the ship's propulsion engines, NHH = the number of helicopters aboard ship, WL = the lightship weight, SWBS weight groups equal to the sum plus margins, the of and WMp = the weight of the ship's costed military payload, listed in Appendix Following lead and Construction acquisition the follow costs A. calculation of the miscellaneous ship ship acquisition costs are data, determined. are the first costs estimated for the total cost. For the lead ship, the cost of the ship elements or services within each of nine major SWBS groups, 161 plus the margin cost, is PROCESS INPUT DATA X CALCULATEMISCELLANEOUS SHIP DATA .I ~~ DETERMINELEAD SHIP ACQUISITIONCOSTS DETERMINEFOLLOWSHIP ACQUISITIONCOSTS DETERMINEFLEET LIFECYCLECOSTS I____ i- CALCULATETOTALSYSTEMSCOSTS (UNDISCOUNTED AND DISCOUNTED) - -- - - -- . .- GENERATEPRINTED OUTPUT ASSETCost Module Calculative (Ref. 1) Figure 3.8 162 Sequence to computed according C1 = 2 = C = 3 C = C = 4 5 C = 6 (33.95 (1.86 (75.05 HP )0.808 )(W ) KN2) (PuM) N3 300 0.910 617 KN4 )(W40) (108.57 N4 400 (94.87 KN5 )(W (98.59 KN )(W )C78 N6 600 (W / = (0.019 C9 = (0.385 *N 500 K )(W N7 W700 (WLS - equations; 772 100 )100 Ni K C (8.38 C8 KN1) (W C (1.86K = 7 CM = the following (3.22) 0782 0 987 W )) (CL1 + ... + CL7) KN8) (CL1 + KNg) ~N9 (CL LI + ... C +~C CL7 )1.099 LM ++C + C ) 0.839 CL7 + CLM where C 1 = the appropriate lead ship SWBS group cost, $K KNi - the technology factor for the i th SWBS group Wi = the appropriate SWBS group weight, LTON and subscript M refers to the D&B and growth weight margins. 163 The KN technology factors used for Eqn. based of (3.22) are selected upon the characteristics of the ship to be costed. KN values for various ship configurations Appendix B. are Tables included These tables were originally derived from the in cost evaluation program of the ANVCE study. Follow ship construction costs are principally a function of lead ship learning. costs and a factor that For the first follow ship, accounts for production this factor, F, is defined by the following equation; = 2.0 R LL - F (3.23) 1.0 where RL = learning rate The value ASSET equal rate (default of the average model uses a cumulative learning to 0.97) to account for the decrease cost per ship resulting from increased production. Ci Follow ship construction costs, ($K), are given by the following expressions; C j2 1,2, .. 7 = F CL =M 7,9,M L1,L2, .. L7,L9,LM (3.24) C 8 = (0.019 KN8) (CL1 + ... where = appropriate C + CL7 + CLM) lead ship SWBS group and Li from Eqn. (3.22). 164 margin costs The ship construction CCC ($K), cost, is the sum of weight group costs, such that; CcC = C 1 + C 2 + ... + C 9 + C Profit, C ($K), and of is assumed to equal a fraction P C ($K), construction cost and the price, cost plus (3.25) equals the construction profit. As a result; Cprofit FP CCC (3.26) + (3.27) PBC = CCC Cprofit where Fp = profit fraction (ASSET default value of 0.15) A series of miscellaneous program (G&A) costs must computedand added to the price to determine the acquisition of the ship. be cost These costs are described below: Ccord = cost of change orders, Cnsea = NAVSEA support $K costs, $K Cpdl = post delivery charges, Coutf = outfitting costs, $K K Chmeg = hull/mechanical/electric plus growth, $K They are estimated as a percentage of the acquisition price, F'BC, according to the values listed in Table 3.15 for lead and follow ship applications. 165 Cost Lead Ship El ement Percentage Follow Ship Percentage C 12 8 2.5 2.5 C cord nsea 5 Cpdel Coutf Chmeg 4 4 10 10 NAVSEAProgram Cost Percentages Table 3.15 The total ship acquisition cost, Cacq ($K), is given as; Cacq PBC 'cord Cpdel The "sailaway" C where C P S acq + Cnsea + + (3.28) Coutf + Chmeg cost of the ship, C S (WK), is given by; (3.29) p ship payload cost, 166 The value of C P by may be input or estimated the following equation; C where payload WMp) + (18.71 N H ) Vpayload = 0.373 = 0.326 The (3.30) ) 1000. for the lead ship for the follow ship in factor 18.7 approximates the cost (in millions) FY (fiscal year) 81 dollars of acquiring a helicopter. Payload costs are defined as the sum of ordnance and electronics costs. The next sequence in the ASSET cost module the estimation of fleet life-cycle costs, and categories. The these categories R&D cost of and investment, development, (see Fig. 3.8) is consisting of research operations and support major life cycle cost elements addressed under can be seen in Fig. 3.9. costs are calculated as the sum of two components: the test and design and development, and the cost of evaluation. Design and development costs are computed 167 as the sm of ship ASSETLife Cycle Cost Elements (Ref. 1) Figure 3.9 168 design and development CSD D cost, ($M), and other design and development cost, CODD ($M); = 0.0011 C (0.571 C SDD ) + C /F + 0.072 C Lp Facq TECH (3.31) CODD = 1.1 (0.06 CF where = CFacq I ) acquisition cost of the first follow ship, $K CLp = lead ship payload cost, $K (see Eqn. 3.30) = CTECH technical advancement cost, M (user supplied input) CFI = additional facilities cost, $M (user supplied input) The ship cost, life-cycle value of C Facq/F represents an adjusted lead or first and is probably the most important input to the ASSET cost model 1). This cost is intended (Ref. to capture the recurring production cost of the lead ship. The technical advancement cost is the cost of developing any technological advances that will be necessary before the ship can be bui It. The cost of additional facilities refers to the construction of facilities such as shipyards and piers that will be necessary for the support of the ship. Test ship and evaluation costs are computed as the sum of test and evaluation cost, the CSTE($M), the payload test and 169 evaluation cost, CpTTE ($M), and other test and evaluation costs, COTE ($M); C 0.0(012 ( 0.499 C STE CpTTE + C /F + 0.647 C Facq Lp ) OAS (35.2) 1.2 CPHTE COTE = 1.2 (0.02 CF I ) where CPHTE = payload hardwere test and evaluation cost, M (see Eqn 3.33) COS = total operations (see and support cost, $M Eqn. 3.49) The payload hardware test and evaluation cost may be input by the users or estimated by the following equation; CpHTE = 0.0646 (3.33) WMp The total research and development phase cost, CRD (*M), is given by the following equation; CRD = CSDD + CODD + CSTE + CTTE Investment support costs are equipment cost, spares and repair parts, underway replenishment). made up of + COTE prime cost of facilities, (3. 4) equipment cost, cost of initial and the cost of associated system (e.g. Investment acquisition costs of these equipments. has two distinct components, costs are primarily The prime equipment the cost the ship prime equipment cost, CSpE 1 70 ($M), and the payload prime equipment cost, CppE ($M), given by the following expression; 5PE ( (C SPE q/F) /1000o) ) N (ln(2RL )/ln(2)) Facq (3.35) CppE = ( CLp + (NS - where 1) CFp )/ 1000 RL = average learning rate NS = total number of ships to be acquired CLp = lead ship payload cost, $K CFp = follow ship payload cost, $K ln = natural logarithm An average of the ship cost, C avg ($K), is computed ship prime equipment investment for use by as a function other life- cycle cost algorithms; Cavg 10C)C)0 (CSp /NS E+Cpp E) The equipment C cost of support equipment is divided into ship cost, CSSE ($M), and payload support equipment (3.36 support cost, ($M), such that; CSSE = 0.05 CSPE (3. 37) CPSE = 2c CPp'E 171 The costs of initial spares for the ship, for the payload, C P CS ($M), S and ($M), are given by; 166SP C S S = 0.03 CSE (3.38) C IS P = 0. 13 C.FE SP 'E The final investment cost to be estimated is the associated systems investment cost, CIASOC ($M); C IASOC = 25 N S H (WS + . 1 Wp) x (3.:39) (CURU/UCAP) (L/30) where H = ship operating hour per year, HR/YR WS = ship fuel rate, LTON/YR Wp = payload CURU = cost fuel rate, LTON/YR of underway replenishment unit, $M (user supplied input) UCAP = underway replenishment unit fuel capacity, LTON/YR LS = ship service life, YRS The cost of underway replenishment is the acquisition of each underway replenishment ship. unit The underway cost replenishment fuel capacity is the weight of fuel that a typical underway replenishment associated ship can deliver per year to the ship systems cost accounts for the cost of fleet. The buying and operating UNREP ships over and above the support forces currently operated by the USN. 172 The total investment phase cost is given by the following sum: CINV = (CspE + CppE ) + (CSSE + CFSE) + CFI + (3.40) (CiS S + CS P ) + CiASOC Operations of seven maintenance spares, and support (O&S) costs are computed as the components: costs, personnel energy (fuel) costs, major support costs, data base costs, operations cost of costs, replenishment and associated systems costs. sed to estimate the operations, sum The maintenance and major support cost CERs can be seen in Table 3.16. Personnel CpAY costs are divided into pay and allowances costs, ($M), and temporary additional duty pay costs, CTAD ($M); CpAY = ( (26,184 NC1 ) + (11,510C(NC2+ NC )) ) x (NS L S / 106) C .65(40) ( (Nc1 + NC2 + N) Operations cost, COOS COpS (3.41) + (Nc1 + NC2 + NCS) - (0.4459 H/12) + (1000 CT) where )/106 ($M), is given by the following; NS L S (188 + 0.0013 C 2.232 (N L) (3.42) ) /1000 CAT C = annual cost of training ordnance, $M rn-cC 73 Maintenance (OOOs) Operations (OOOs) (SFY81) Ship Class fY81) CG26 C616 D0637 D00631 D0062 D00931 D00963 LST1179 LPD1 LSD28 LPD4 ULA113 LHA LSD36 LCC19 LPH2 AE26 4,689 1,212 4,770 3,888 5,661 5,592 1,212 4,139 858 934 715 AE22 AOEI AFS1 AOR1 ASR21 ATS1 FF67 FFG1 FF1052 FF1040 FF1037 CVS9 3,268 2,926 3,884 5,389 3,847 2,264 8,963 4,214 3,899 5,047 3,705 3,811 5,685 4,670 3,676 3,141 2,908 1,176 1,014 1,095 1,055 857 1,055 989 2,724 1,055 1,712 1,779 701 745 1,440 998 1,181 448 454 796 796 3,999 4,721 3,646 5,253 3,896 22,331 · 729 729 729 7,659 Major Support (000s) {SFY81) 3,184 3,089 3,105 2,819 3,271 2,733 2,492 1,707 2,839 2,743 2,894 1,703 6,425 2,547 4,652 4,192 2,460. 2,295 3,996 3,058 2,893 1,489 1,103 1,422 2,555 2,377 2,724 2,138 19,546 OOOs) $FY81) 1) Table 3.16 174 Ship Personnel 266,104 434 271,302 407 213,189 391 120,646 163,863 122,148 347 315 188,649 66,023 174,566 99,466 251 293 221 403 333 Hours Per Month 296 373 308 291 319 393 463 198 428 142,732 419 89,968 364,797 92,898 209 338 293 289 287 229 398 216,083 205,666 787 .381 641 115,437. 345 321 565 362 360 330 74,632 286,129 884 427 97,896 120,209 173,863 33,255 124,155 119,543 252 80,840100,008 68,977 1,071,799 2,781 Data for Selected USNShips Operations and Support (Ref. Steaml~ Ship Cost 420 181 101 201 270 261 204 457 356 371 188 325 404 316 316 236 364 425 The annual cost of training ordnance may be input by the user or estimated using the following expression: CATC = 0.0051 The as CFp /1000 (5.43) decrease in operations cost with ship operating shown in Eqn (.42), reflects the increased hours, operations cost associated with being in port. Maintenance costs, CMTC ($M), are estimated by the expression: MTC (NS L S ) (2967 + 0.0064 C + 4.814 (NC1 + NC2 + NC 3 ) - (3.44) (3.939 H/12) + (10 HDEF /168) ) /1000 where HDEF = deferred maintenance manhours, HRS The deferred maintenance manhours is the average number of additional maintenance manhours per ship that will have supplied each week by a shore based facility to perform to be required preventative and corrective procedures. A value of zero indicates that ship's crew can perform these tasks between overhaul periods. Eqn (3.44) indicates that maintenance costs decrease as ship operating expected hours to increase, whereas maintenance costs increase under such anomaly reflects minimal maintenance the fact that circumstances. historically, and therefore minimal 175 would This ships be apparent requ iring maintenance costs, were able to operate for longer The cost of energy (fuel), periods at sea. CEGY that used by ($M), includes the ship and helicopters, if any. The expression isi C (N S EGY L S ) (C FUEL /10 ) (2240 H/6.8) x (WS + O. 1 Wp) (3.45) where CFUEL = fuel cost per gallon, $/GAL The cost of replenishment CREP = ( (LS Values of CS expression the - ($M), is8 4) (CISS + CSP ) )/4.0 and CS S spares, CREP P (3.46) are calculated in Eqn. (3.38). This reflects the assumption that the initial spares cover first four years of ships operations and that replenishment spares are required at four year intervals thereafter. Major support costs, CMSP ($M), are calculated as follows: (NS L ) C MSP S S (698 + 0.00(:))22 Cavg + avg (3.47) 5.988 (NC 1 + NC + NC) ( 1.158 H/12) )/1000 The associated systems cost, COASOC COASO C = 0.25 NS L S H (WS + where CAS = ($M), is; . 1 Wp)(CAS/UA annual cost of operations and underway replenishment unit, input) 176 support (3.48) P of each $M (user supplied The total operations and support cost, COA S ($M), is given by the following expression: COA S = CA Y + CTAD + COF S + CTC + CMTC CREP + CMSP + COASOC + CEGY (5.49) Total systems costs are computedin the next step. The total systems costs equals the research and development, investment, and operations and support costs minus the residual value of platforms costs at are the end of their useful life. computed both in terms of the The total systems constant year dol 1 ars (undiscounted) and discounted dollars. The residual value of the platform, R ($M), is estimated using the double declining balance method (e.g., see Ref. 1): = CSpE This decline (1 - depreciation /L S (5.50) )L S method most closely approximates the in value of capital assets which are not worn out at the end of a nominal service life, but are capable of being restored, modernized and/or converted to other uses (Ref. The undiscounted life ships, CLIFE cycle total systems cost for the ($M), is given by the equation: CLIFE The 1). discounted CRD + CINV + (3.51) COAS - cost of a given phase is a function non-discounted cost and a discounted cost factor. 177 of the The discounted cost factor the is calculated cost phase, B, as a function of a beginning and an ending year, E. year The beginning of and ending years are assumed to be integers and are normalized to the base year. The discounted cost factor, Fd ' is given by the following equation: F - + 1) (-1) (E - (1/1.1) + (1/1.1) + ... + (1/1.1) E-1+ ( 1 /1. 1 )E ) (3.52) This expression assumes that the costs associated with particular phase (i.e., end of payment In each each R&D, investment, O&S) becomes due at the year that the program runs and that each yearly is equal to the average cost/yr over the program length. addition, Eqn (3.52) assumes a constant discount rate of 10% for all discounting calculations. The ending and development phase, beginning ERD and BRD, years for the research and respectively, are calculated as foll ows: ED = YI0C + 2 - YB RD (3.53) BRD where =ERD - LRD + YB = the base year (ASSET default value of 1981) LRD = length of research and development phase, YRS YIOC = year of initial operational The end capability of the R&D program is assumed to occur after the IOC date. 178 two years The C*RD discounted ($M), is given C where FdRD cost of the research and development phase, as: dRD = RD discounted development (3.54) cost factor for the research and phase using the beginning and ending years calculated in Eqn. (3.53) The beginning and ending years for the investment phase, BINV and EINV, respectively, are calculated belows ERD R + BINV (3.55) EIN V = BIN INY NYV + (N /Rd ) + 0.9999 where 1 Rd = ship production rate If the value of EIN V is a non-integer, the value is truncated to the next lower integer. The length of the investment phase is ships, the number of years required to construct all including the lead ship, at the given production of the rate. Also, no overlap between the R&D and investment phases is assumed. The ($M), discounted is calculated C where FdINV cost of the investment phase, from: NV = F C INV dINV INV = C* INV (3.56) discounted cost factor for the using in Eqn. investment the beginning and ending years (3.55) 179 phase calculated The beginning and ending years support phase, BOAS and ES, OAS E INV B for the operations and respectively, are given as: 1 (3.57) O&S EOAS BOAS + LS costs are not charged until all the constructed, and the operating period ships have been is set equal to the ship service life. The discounted C*OAS S ($M) support phase, is; S = Fdo S C 0 C FdOAS where cost of the operations and = (3.58) discounted support cost factor for phase the operations using the beginning and and ending years calculated in Eqn. (3.57) The discounted residual value of the platform, given R* ($M), is by: R* f R (1/1.1) (EAS + 1) (3.59) where R = the non-discounted residual value from Eqn. (3.50) The total discounted life-cycle systems cost, C*LIFE LIFE () is given by the following equation: C* Cost dollars of LIFE C* RD + C* INV + C OAS - R outputs from any year. (3.60) the module may be expressed in terms Because all 1 80 cost equations used by of the module reflect dollars of the year 1981, cost figures must be adjusted to account for inflation occurring between the base year and 1981. Table actual 3.17 indicates the calculated escalation indexes and convert projected to base inflation year rates from dollars, the 1977 1981 to dollar for 1996. To figure is multiplied by the appropriate base year index. The Costing and System Design Office at DTNSRDC has recently modified the life cycle portion of the ASSET cost module. improvements relaxation include a greater emphasis of some of the simplifying on assumptions These discounting, in the original discounting analysis, an ability to compute and display cash flow diagrams, and escalation of the ability to study the impact of relative particular cost categories such as energy cost or personnel. The in improvements are accomplished primarily through changes the structure of the calculations. For the most part, the original module's cost estimating relationships (as documented in this study) are retained. 181 -L - I INFLATIOI RATE S YEAR .6722 .7287 .8001 .8995 1981 11.30 1.0000 1982 1983 1984 1985 1986 8.50 8.90 7.50 7.60 7.60 1.0850 1.0816 1.2702 1.3667 1.4706 1987 7.60 1.5823 1988 1989 1990 1991 1992 1993 1994 1995 1996 7.60 7.60 7.60 7.60 7.60 7.60 7.60 7.60 7.60 1.7026 1.8320 1.9712 2.1210 2.2822 2.4557 2.6423 2.8431 3.0592 1) Table 3.17 182 -- I FACTOR 5.87 8.40 9.80 12.30 (Ref. ~ ~ ~ ~ II 1977 1978 1979 1980 ASSETUSNShip Construction Escalation Indices -~~~-- I··. · IR 3. 1 . 3 Ot5 Information Input information required by the ASSET cost module has been divided into ship acquisition plus payload cost parameters and life cycle cost parameters. These parameters are grouped into the common cost driver classifications outlined in Table acquisition plus payload costs are the costs for the lead and follow ships so-called 1.5. Ship "sai1away" (e.g., see Eqn. 3.29). TECHNOLOGY Ship type (i.e., SWATH, Hydrofoil, etc.) Hull & Superstructure material Propulsion plant type Electrical plant type Control systems complexity (*) Electronics complexity (*) Weapons complexity (*) SHIP DESIGN Weight limited considerations (i.e., SES vs Monohull) Amount of trials testing (**) Hull structure weight (SWBS group 100) Propulsion plant horsepower Propulsion plant weight (SWSS group 200) Electric plant weight (SWBS group 300) Command & Surveillance systems weight (SWBS group 400) Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) Armament weight (SWBS group 700) Margin weight (SWBS group MOO) (*) simple, modest, complex (**) limited, extensive ASSET Sailaway Ship Cost Parameters Table 3.18 185 - PAYLOAD DESIGN Number of helicopters Costed military payload weight MANUFACTUR ING Tooling complexity (*) Learning rate PROGRAMMAT IC Profit fraction ECONOMICS Base year $ ASSET Sailaway Ship Cost Parameters Table 3.18 (continued) 184 Inut ted Costs Lead ship acquisition cost Lead ship payload cost 1st follow ship acquisition cost Follow ship payload cost SHIP DESIGN Ship fuel rate Crew accommodations PAYLOAD DESIGN Costed military payload weight Payload fuel rate MANUFACTUR I NG Learning rate PROGRAMMATIC R & D program length Technological advancement costs Payload testing and evaluating costs IOC (initial operational capability) date Number of ships required Ship production rate ASSET Life Cycle Cost Parameters Table 3.19 185 ECONOMICS Base year $ Inflation rates OPERATIONS AND SUPPORT Additional facility costs Deferred manhours required Annual cost of training ordnance Underway replenishment ship operating and support costs per year Underway replenishment ship acquisition cost Underway replenishment ship fuel delivery capacity per year Annual operating hours Service life Fuel cost/gal ASSET Life Cycle Cost Parameters Table 3. 19 (continued) The inputted cost information required to estimate the fleet life cycle costs calculations for can be obtained from lead and first follow ship the previous construction ASSET plus payload costs. The ASSET cost module makes use of several default values or expressions to representative facilitate values to ease of operation the program. and to Table 3.20 lists cost parameters and their default values or expressions. 186 supply these ASSET Value ASSET Parameter or Expression Year $ Inflation 1981 Rate Table Production Rate 4 5 ships/year Learning Rate 0.97 Fuel Cost $1.20 /gallon (*) Payload Testing and Evaluation Cost $0.0 Lead Payload Cost Eqn. (12) Follow Payload Cost Eqn. (21) Annual Training Ordnance Cost $0.0 Payload Fuel Rate 0.334 LTON/hr/helo (*) in 1981 dollars ASSETParameter Default Values Table 3.20 187 ASSET Value or Express ion ASSET Parameter R&D Program Length 0 years Number of ship Acquired 25 Profit Fraction 0.15 Service Life 30 years Annual Operating Hours 2500 hours Technology Advancement Cost $0.0 Additional Facilities $0.0 Cost Deferred Manhours Required 0.0 UNREP Unit Capacity 258,585 LTON/year UNREP Unit Cost $120.209 Million (*) UNREP O&S Cost $14.656 Million (*) (*) in 1981 dollars ASSET Parameter Table Default Values 3.20 (continued) 188 5.1.3.4 Output Information Output breakdown information of lead from the ASSET cost and follow ship model acquisition includes costs, and a a breakdown of life cycle costs. The ship acquisition costs consists of the follow: ing output cost variables and their applicable equations. Cost Variable (Eqn #) Cost Category Lead Follow Ship Ship Construction SWBS Group 100-900 Ci Ci (3.22) C.152)C (3.24) Margins C (3.22) CM Total Construction CCC CC Profit Cprofit Construction Price Miscel 1aneous Change Orders NAVSEA SuoDort - r- - PBC C C same (3.25) (3. 26) (3.27) cord nsea same same same same ASSETShip Sailaway Output Summary Table 3.21 189 (. 24) Cost Category Cost Variable (Eqn #) Lead Ship Follow Ship Post Delivery Charges Cpdel same Outfitting CoLtf same H/M/E + Growth Chmeg same Total Acquisition C Payload C _--____________________________________________________________ Miscellaneous (continued) (3.28) same (3.30) same (3.29) same P Sailaway C ASSET Ship Sailaway Output Summary Table 3.21 (continued) 190(: For the life cycle costs the output, ollowing cost variables and their corresponding equations are listed below. Cost Category NonRecurring Cost Variable Ship Recurring (Eqn #) Payload Other R &D Design & Development CSDD CODD (3. 31) COTE (3.32) Test & Evaluation CSTE CPTTE CSF'E SF'E CPPE Investment Pri me Equi pment (3. 35) Support Equipment (3.37) CSSE Initial Spares ISS (3. 38) CIS ISF' Associated Systems CISOC IASiOC Facilities CFi ** user input value ASSET Life Cycle Cost Output Table 3.22 191 (**) (3. 39) NonRecurring Cost Category Cost Variable (Eqn #) Payload Ship Recurrng Other Operations& Spport Personnel Operations Maintenance Energy Replenishment Spares Major Support Associated Systems CFAY (3. 41) CTAD (3.41) COPS (3.42) CMTC (3. 44) CEGY (3. 45) CREP (3. 46) CMSPF (3. 47) C OASOC Residual Value R (3.50) ASSET Life Cycle Cost Output Table . 22 (continued) 192 (3.48) Cost Category Cost Variable (Eqn #) Total Systems UnDi scounted CLIFE LIE Discounted C*LIFE (3.51) (3.60) ASSET Life Cycle Cost Output Table 3.22 (continued) 193 USCt 3.1.4 3.1.4.1 General ship cost estimating in the US Coast Preliminary a from derived is to as referred which is generally procedure Guard "Flanagan's Method". This method is based upon an unpublished The in 1969 (see Ref. by Flanagan report written in this described methodology information found in Flanagan's report, study computer ship synthesis models. uipon personnel. has also been used in Method based is previous MIT theses, and from discussions with USCG cost estimating Flanagan's 12). Goodwin (Ref. conjunction with 7) first used the method to estimate conceptual and preliminary lead ship costs for and rescue and patrol type between 150 and 400 feet. program predicted full load displacements within 4% of Coast Guard cutter designs. Goodwin stated that lengths with cutters search USCG synthesis the existing There was no mention of the accuracy of the cost estimating procedure. A synthesis application to 150 for Coast Guard search and feet rescue for in patrol Since Flanagan's Method was developed for cutters, Tuttle boats. (CERs) from The CERs were also modified some of the cost estimating relationships existing cost updated to data for patrol-sized boats. reflect more recent Navy information on propulsion machinery, see Ref. changes in hull materials and overhead charges (e.g., 10). Flanagan's cost (Ref. 8) going boats between 50 and ocean especially length, was developed by Tuttle model Method is the basis for the current estimating methodology. USCG Changes have been incorporated 194 ship to account for accounting the addition of return methods cost data, and administrative changes and that different have been introduced since the late 1960's. The output from the present day cost model provides estimates ranging from concept decisions to budget submissions. 195 development 3. 1.4.2 Cost Estimating_Relationships Flanagan's Method is based upon the weights of If these weights are standard US Navy weight groups. seven the incorrect, the estimate will be correspondingly incorrect. Flanagan reasoned the average dispersion of bids for new that since vary by 20% about the mean bid, construction any technique that can come to within 10-20% of actual costs should be considered adequate. Estimates of the SWBS (Ship Work Breakdown Structure) weight groups are used to determine material costs weight groups include all government furnished equipment all including In Flanagan's report, weight manhours, agencies weight. the following MHi 1 were group weight a representative plot of material Fig. 3.10 presents versus developed (GFE), log-log plots of material cost versus manhours versus weight for each and presented. cost government supplied by other The manhours. US Navy). the (e.g., material and these From plots, CERs for material Goodwin cost, MC i (Ref. ($M), 7) and ($M); MH 10 l1og(W 1 C) FDG) MH 2 = 10 .752 + 2.973] 1og(W2 0 0 FDG ) 1.027 + 2.344] (3.61) MH = MH4 = 1Clog(Wc)00FDG ) 10 1.078 + 2.630) log(W4 0)0 FDG) 1.078 196 + 2.6303 0 0 Y= LOG 0 A COST X = LOG WEIGHT Y = A+ BX Basis of USCG Material Cost to Non-CostRelationshins (Ref. 64) Figure 3.10 197 0 MH5 = 10 FDG) .763 + 3.2373 Clog(W .974 + 2.7423 [ 6 MH 6 = 10 log(W )C)FDG MH 7 = 1 0 log(W700 MC 1 = 1lo1g(Wl 0 FDG) .752 + 2.9733 FDG) .954 + 2.790] (3.61) and MC2 = 10lC 0 (W2 0 1.019 + 3.634) 0( FDG) 1 MC 3 = 10 Elog(W 3 0 0 FDG) 1.073 + 3.6683 MC 4 = input 1 g ( W5 0 0 MC 5 =10 MC6 = log (W MC 7 = input where value (3. 62) FDG) .871 FDG) + 3.974] 1.068 + 3.60()4] value FDG = design and builders margin -factor (setequal to 1.02) F 1 = $0 for diesel = $1,500,000 W. for propulsion CODAG(combined diesel and gas) = the appropriate SWBS group weight, L.TON The design and builders margin of 2% is distributed among the seven weight groups that make up the lightship 198 even l y weight. As indicated in Fig. 3.10, the manhour and material cost versus weight curves are assumed linear when plotted on log-log paper. Since inflation years. all material costs curves are based on 1959 prices, indices must be used to correct prices to more These Statistics indices (BLS) data can be obtained (e.g., from see Ref. Bureau recent of Labor 11) for the shipbuilding industry. In cites order to account for different hull materials, data from the US Navy and Newport News indicates into that structure HY-SO Shipbuilding HY-80 requires 40% more man-hours than mild steel. In Flanagan to fabricate 1969, the material was 3.4 times that for mild steel. that cost of Ship estimates must be adjusted to reflect the percentage of structure which is made of high-strength steels (HSSs). For aluminum structures, US Navy and Maritime Administration (MARAD) data from aluminum structure times the However, cost has a total (material of the same weight Flanagan contracts June 1969 indicate that a notes of given weight + labor)cost 1.8-2.2 mild steel stru(Cture. that computations from WMEC and more recent Navy information on changes in hull Tuttle for WHEC ignored the presence of aluminum in their construction estimates -without introducing any significant additional From of found that the effects of all aluminum hull patrol boats could be accounted material costs only, by 2.192 (see Eqn. Material costs for by error. materials, construction multiplying the .64). for command and control equipment and for armament (SWBS weight groups 400 and 700, respectively) are input directly into the model. Better estimates are generally obtained 199 when there particularly exist good electronic, shopping lists for material armament and machinery using a shopping list in conjunction with Eqns weight used for the labor estimate weight group, particular item the equal to the total for the that used in must be reduced by the equipment calculation the remains (3.61) Although not to "double-bill". it is important (3.62) the year price, and weight. of purchase, When The hardware. minimum cost data required for any equipment is the and costs, cost material weight. The cost of is then added to the revised material cost calculated from Eqn (3.62). (3.61) and (3.62) were developed by Eqns from report. Flanagan's directly Tuttle modified some of these CERs order for the results to be more consistent in Goodwin the 50-150 foot length range. Eqns. with CG patrol in boats (3.63) and (3.64) show these adjusted relationships. For calculating manhours, only the equation for armament was so that: modified, MH 7 = 10 og(W70 material costs, For equipment propulsion FDG ) .954 + 2.7903 (3.63) structural the relationships for costs were updated using more recent and Navy data from Ref. 10: Mc = 10 log(W 1( FDG) 1.019 + 2.7903 F 1 2 (3.64) MC 2 = 10 Clog(W 2 0 .- FDG ) 1.019 + 3.634 F3 + F 3 4 where F 2 = 1.0 for steel construction = 2. 192 F3 = 1.0 for aluminum construction for diesel prime mover or CODAG = 1.57 F 4 = $0 for gas turbine prime mover for diesel and gas turbine = $1,500,00 PM for CODAG For calculating tne labor cost, the labor rate is assumedto be the same for all weight groups. Therefore, the labor cost, LC. ($M), is given by the simple expression: LCi - MH. $/HR 1 where (3.65) 1 MH 1 = estimated manhours from Eqn. (3.61) or (3.63) $/HR = labor rate (dollars per hour) , adjusted to the appropriate year of shipbuilding For the lead ship, the labor and material costs of and engineering services (i.e., SWBS weight group 800), design LC 8 and MC 8 ($M), respectively, are given by the following expressions: LC = (.114 LOA - 1.6)(LC + ... + LC 7 ) / 100 (3.66) MCe = (-.01 LOA + 7.5)(MC1 + ' where LOA = overall ship length + MC7) / 100 (ft) The percentage calculated in Eqn. (3.66) for the costs associated with design and engineering services assumes that contract design is available to the shipyard at 2( )1 the time the of construction. The services labor and material (i.e., SWBS costs for lead weight group 900), ship LC9 construction and MC9 (sM), respectively, are as follows: LC9 = (.014 LOA + 7.0)(LC1 + ... + LC 7 ) / 100 (3.67) MC, = (-.015 LOA + 6.5)(MC1 + ... For vessels under + MC7) / 100 approximately 160 ft in length, the material cost for SWES weight group 900 is estimated at 4% of the sum of the construction material costs. Overhead cost, OVi ($M), is calculated from the labor cost of each SWBS weight group by the simple relationship: OV. 1 where F ovhd LC (3.68) 1 F ovhd = labor overhead fraction The cost of construction ($M), is the sum of material, for each SWBS MC, weight group, C1 and labor, LC i, plus overhead, OV i , costs and can be written as: C. = MC + LC (3.69) + OVi The ship construction cost, CCC ($M), is given as the sum of the weight group costs, such that: CC Profit, C1 + C + C+ C9 profit ($M), is assumed to equal a fraction Cprofit (3.70) of the construction cost and the price or base estimate, PBC ($M), equals the construction cost plus profit. As a result: Cprofit and PBC = CCC Fp = profit where A series price (3.71) = Fp CCC + (3.72) Cprofit fraction (set equal to 0.15) nd added to the of add-on costs must be calculated the "sailaway" of the ship to determine cost of the ship. These costs are determined by the following expressions: = 0tf .02 PBC C Cretro = 0.04 PBC (.3. 7) C C where = input value misc spare Cutf = .09 MC 2 + .08 MC + .25 MC + .10 MC 5 = initial outfit costs ($M) Cretro = retrofit costs (SM) Cmisc = miscellaneous and contingency costs (M) C spares = cost of spares Instead modifications accumulates of decided some construction period. this issuing (M) change upon during orders ship for design all construction, the CG throughout the Retrofit costs are the costs incurred when of these modifications work is done by CG shipyards immediately after the ship built. 2 C)3 is Miscellaneous design work automation, technical initial and studies, contingency costs include such items training specialized services. ship use training requirements, Other load mock-ups, of costs under this all fluids and the as of large-scale and additional category inclusion are of the cost margins. Administrative costs, Cad admin ($M), are estimated from the following equation: C + Cadmin =F Fadmin (P PBC Cretro + Coutf C Cmisc + C spares where Fadmi n = administrative POGA = cost cost fraction (including profit) P OGA ) (3.74) (set equal to 0.035) of material supplied by other government agencies Administrative personnel attached costs to Resident Inspector Offices (RIOs) and at other related expenses. claims, the office equipment purchases, on a particular project supplied are known, this portion of command and the into the estimate. by other government agencies (OGAs) the US Navy contributions to SWBS weight groups 700 weapons and When the size of the RIO and HO personnel cost can be input directly include salaries CG travel Equipments made up of the of headquarters, working are control portion of the 400 Included with these items are the spares supplied by OGAs. 204 and group. The "sailaway" cost of the ship, C ($M), is given by: Cs - PBC + Coutf + Cretro+ Cmisc + Cspares + Cadmin The (3 75) lead ship cost for the CG would be equal to Eqn. actual (3.75) minus POGA' the cost of material from other government from multi-ship agencies. For contracts follow ship for that costs, Flanagan found succeeding ships there was a reduction total labor manhours according to the schedule in Table 3.23. PERCENT DECREASE IN LABOR FROM SHIP # 1 PREVIOUS SHIP Eqns. (3.61)-(3.67) 2 10 3 5 4 2 5 2 6 2 7 1 8 1 > 8 same as 8th Follow Ship Reduction in Total Labor Manhours Table 3.23 20(5 in This delivered little reduction in labor accounts for learning. more than six (6) months apart, learning For ships Flanagan states occurs other than for design and tnat construction services. For design and engineering services on follow ships, the percentage of costs in Eqn. (3.66) becomesa LC = (.025 LOA) (LC1 + ' + LC7) / 100 (3.76) MC 8 = (-. 0(:02 LOA + 2) (MC+ Eqn. (3.76) accounts for + MC 7 ) / 1 : ... a substantial portion of the reduction in labor noted in Table 3.23. For construction services on follow ships, the percentage of costs in Eqn. (3.67) is modified to: LC9 = (.022 LOA + 1.5)(LC1 + ... + LC7 ) / 100 (3. 77) For material MC9 = (-.0125 LOA + 5.5)(MC + ... ) /1oC + MC7 vessels ft cost under approximately 200 of construction services in length, is estimated at 3.C)% the of the sum of the construction material costs. Regardless of the magnitude of the reduction in labor calculated using Eqns. (3.76) and (3.77), the total reduction in 1abor ship must be consi stent with for each follow the val Les found in Table 3.23. Apart from any differences associated contingency costs, with miscellaneous and Flanagan noted the following 22 -)6 adjustment to the cost of spares for follow ships: Cspares = .045 MC 2 + .07 MC + .23 MC 4 + .1 MC 5 (3.78) Administrative costs are estimated in an identical manner as for the lead ship, using Eqn. (3.74) with appropriate follow ship costs. cost of the follow ship, C The "sailaway" PBC is the price of the follow ship adjusted (3.75), where Eqn. the required reduction in manhours. for ($M), is given by ship cost for the CG would be equal to Eqn. follow POA, the As before, actual minus (3.75) the cost of material from other government agencies for the The cost of OGA material includes follow ship. portion of the cost of spares calculated in Eqn. relevant any (3.78). previous discussion was based entirely upon the The by written Flanagan in 1969. estimating personnel, USCG After discussion with the following changes and/or report cost explanations were noted as being applicable to the CG model as it now exists. The procedure for estimating the ship price or base estimate the variables used for -calculating material and labor costs may be different than those listed in Eqns (3.61)-(3.67). This is due mainly is essentially correct. The numerical values of to additional data becoming available in recent years. effects The related into learning on the to the rate of production. the between of learning curve, construction base This introduces so that learning starts estimate increases. For cost a time factor decreases as time periods of time greater than 2 years, learning is taken to be non-existent. 207 are Return data from recent multi-ship acquisitions indicate, that for CG vessels, it is more appropriate to apply the learning curve to the labor plus material costs. The categories under which costs are grouped have been changed from those reported by Flanagan to reflect differences in current cost accounting procedures. These categories are listed in Table 3.24. Categories Contract Award Contract Spares Contract PTD Escal ati on Related Costs Outfitting RIO Retrofit Ship & ICP Spares Self Insurance Training USCG Cost Model Categories Table 3.24 208 The costs categories of contract award and PTD and related require some explanation. The dollar amount of the contract award is PBC in Eqn to equal accounts and documentation technical, provisioning, to refers PTD (3.72). for of most the miscellaneous costs (e.g., Cmisc ) The related costs listed in Table 3.24 make up the rest the add-on costs (inventory similar listed control (3.74). Ship and ICP spares are calculated point) to that outlined (3.73) and in Eqns. in Eqns (3.73) and in a manner (3.78). RIO costs are Inspection the administrative costs associated with the Resident Offices at private shipyards. of The related costs are estimated to be some percentage of the contract award amount. A simple analysis risk has been incorporated into the present model by presenting a range of cost estimates. This range of values is economic (i.e., for inflation obtained by varying design forecast inflation) inputs. rates of %, forecast, (i.e., and Costs are estimated and 6% and SWBS weights of 10% below estimated, estimated, and 25%/.above. 209 weight) 3.1.4.3 Input Information following input information is required The Method for by the estimation of CG ship acquisition costs. These equal to the "sailaway" cost of the lead and follow costs are ships minus the cost of equipments supplied by other agencies into the Flanagan's (e.g., government The parameters below are the US Navy). common cost driver classifications outlined grouped in Table 1.5. TECHNOLOGY Ship type (e.g., cutter or patrol boat) Hull & Superstructure material Propulsion plant type SHIP DESIGN Hull structure weight (SWBS group 100) Propulsion plant weight (SWBS group 200) Electric plant weight (SWBS group 30) Command & Surveillance systems weight (SWB.Sgroup 400(:)( Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) Armament weight (SWBS group 7)(:)) Design & Builders margin Overall ship length PAYLOAD DESIGN Cost of payload material (includes armament and weapons portion of com. & surv.) USCGShip Acquisition Cost Parameters Table 3.25 21 MANUFACTURING Learning rate Labor rate PROGRAMMATIC Profit fraction Overhead fraction ECONOMICS Base year $ Base year for BLS data BLS material indices USCG Ship Acquisition Cost Parameters Table 3.25 (continued) 211 OuLtpt lead used from Flanagan's Method gives cost and follow ships. to information The following additional information escal ate/di scount the CG costs throughoLut for is the construction period to a common year dollar value. Iputted Costs Lead ship acquisition cost Lead ship payload cost (*) Follow ship acquisition costs Follow ship payload costs FROGRAMMATIC Contract award date Length of constrcttion Time between ships Number of ships required ECONOM ICS Base year $ Inflation rates (*) payload refers to material cost (plus profit) weapons portion 700 & 400) - of command and surveillence USCGFleet Escalation/Discounted Table 3.26 212 of armamentand (SWBS weight Cost Parameters groups 3.1.4.4 Outpt Output breakdown Information information from Fl anagan's of lead and follow ship material, Method includes labor, overhead a and total acquisition costs. Cost Category Cost Variable (Eqn #) Follow Lead Ship Ship Construction Material Cost SWBS Group 100-200C (*) (3.62 or 3.64) MCi 1 same 300-700 MC. (3.62) 1 800 MC 8 900 MC 9 (3. 67) MC 9 (3.77) MH (5.61) same MH 7 (. 61 or 3.63) same (3.66) same MC8 (3.76) Labor Manhours SWBS Group 100-600 .700 (*) all construction costs include the design and builders margin USCG Ship Output Table 3.27 213 Summary Cost Category Cost Variable (Eqn #) Lead Fol 1 ow Ship Ship Labor Costs SWBS Group 100-700 LC. (3.65) same 800 LC (3. 66) LC (3.76) 900 LC9 (3.67) LC 9 (3.77) 1 Overhead SWBS Group 100-900 OVi (3.68) same SWBS Group 100-900 Ci1 (3.69) same Total Construction CCC (3. 70) same Profit C same PBC (3.72) same Material + Labor + Overhead Total profit (3.71) Ship Price USCG Ship Output Summary Table 3.27 (continued) 214 Cost Category Cost Variable (Eqn #) Lead Ship Follow Ship Outf it Coutf (3.75) same Retrofit Cretro Mi scel 1 aneous Cmisc . (.73) same Spares Cspares (3.73) C Administrative Cdi admi same Add-on n Sail away C s; (3. 7.3) (3.74) (3. 75) USCGShip Output Summary Table 3.27 (continued) 215 spares same (3. 78) 3.1.5 RCA PRICE 3.1.5.1 General RCA cost PRICE has developed a family of automated, estimating models. for Costing parametric, PRICE (Programmed Review of Information and Evaluation) was originally developed for internal RCA use in the early 1960's. Commercial operations began in 1975, with applications to hardware development software design and implementation, maintenance and support costs. Fig. 3.11 gives an indication of modeling systems. For ship acquisition cost estimating, used extensively. the PRICE H model has The PRICE H model is applicable aspects of hardware acquisition, government furnished, be it development, to all production, or modification of existing equipment. The model estimates costs associated with design, management, production, microcircuits and associated the diversity of areas covered by PRICE been and drafting, project documentation, engineering, special tooling and test equipment, material, labor and overhead. Also, costs to integrate subassemblies into a system and to test the system for required operation can be estimated. A detailed explanation of the PRICE H model can be found PRICE H methods (.g., a in Ref. 20. is characteristic of traditional of estimating NAVSEA, NCA) in that it performs cost estimates on cost per pound basis. breakdown cost However, its output does not contain a material and labor costs. These figures must "backed" out using a post-processor (i.e., PRICE LABOR) or be some other method, as outlined in Section 3.1.5.4. There is strong resistance to the use of PRICE among traditional "material list and labor" ship cost estimators. There 216 HARDWARE COST ESTIMATING PRICE H PRICE HL PLANNING AND MANAGEMENT PRICE PM MICROCIRCUIT COST ESTIMATING PRICE M SOFTWARE COST ESTIMATING PRICE S PRICE SL SUPPORTING MODELS PRICE A PRICE D PRICE Parametric m3delina Systems (Ref. 20) Figure 3.11 217 are several reasons for this distrust, points: black (1) the model box; aerospace (2) is proprietary including the and must be operated was originally developed it applications; following for as avionic a and (3) the user must pay to use it, and; (4) it doesn't give material/labor figures. Despite these reservations, years PRICE has been used for several for early stage estimating of Navy weapons systems. Also, the Costing and Design Systems Office, Code 1204, at David Taylor Ship Research Naval the PRICE H and Development model useful for: (DTNSRDC) Center early-stage ship has found design cost assessment; advanced technology cost impacts; alternative systems cost analysis, and; RD PRICE Journal modeling of systems Parametrics International Refs. resource planning. 17-19). are extensively discussed and in the proceedings relating the of Society of Parametric Analysts (ISPA) Articles in the (e.g., see PRICE to ship costing can be found in Refs. 25-27. Cost estimates obtained using PRICE are generally intended for acquisition planning purposes and not for budget submissions. Even a so, PRICE can estimate costs at any level of detail, from The DCAA states the whole ship viewpoint down to individual equipments. (Defense Contract "parametric Audit estimating Agency) provides completeness of proposal coverage." 21.8 Audit an Manual excel lent cross-check on 3.1.5.2 Cost Estimating Relationships This section is intended to provide a brief overview of PRICE H model. discussion available information personnel The in that follows in the users manual is (Ref. the based upon 20)) and from the Costing and Design Systems Office at DTNSRDC. For additional clarification, PRICE offers users an intensive two week training program to familiarize users with the concepts and use of the model. and PRICE H model estimates costs for both development The the program. Table production elements of categories included under the development and 3.28 the lists production cost headings and a brief description of their make-up. Cost Category Development Production Description Engineering - drafting, design, systems engineering, project management and data Manufacturing - labor and material associated with prototype production - tooling & test equipment costs Engineering - non-recurring production costs such as drafting, design, project management and data Manufacturing - production costs - tooling & test equipment costs PRICE H Cost Output Categories Table 3.28 219 The is basis for the development of the PRICE proprietary CERs multiple result regression curve fitting of historical of this analysis is literally thousands of data. The mathematical equations relating the various input variables to cost. Input data physical, consists of 67 variables used to qualitative, programmatic, describe economic, engineering dependent and system dependent characteristics of the system. However, with minimal amount of hardware a input variable makes the the user model useful specification statistical Of all the information, since missing This feature generated. for cost estimating It is important in to realize of all the input variables uncertainty particular model has been designed to estimate costs values are internally stage of development. the the conceptual that the proper will reduce the of the model. inputs, the more fundamental parameters listed in Table 3.29. Description Number of production units built Learning curve Integration difficulty Schedules for development and production Weights Amount of new design required Operational environment Manufacturing complexity Technology improvement Fundamental Cost Drivers in the PRICE H Model Table 3.29 220 are Weight and cost drivers, manufacturing complexity are the most so that in its simplest powerful form; Cost = f (Weight x Manufacturing Complexity) where f( ) applications, is a nonlinear function. For (3.79) ship costing weights are based on SWBS. PRICE can be run at any level of detail (i.e., whole ship, one-, two- or three-digit SWBS levels) provided the necessary information exists. Separate manufacturing mechanical /str ctural applications are and almost complexities electronics are computed items. exclusively based Ship for costing estimated upon mechanical/structural complexities (MCFLXS). MCFLXS can manufacturing be thought processes engineering work. Typical Fig. and in terms of a cost/lb It exhibits a wide range of values the for and a cost/drawing or required effort for upon the technology required environment of for its fabrication, employment history values for a variety of non-ship of the operating the systems depending manufacturer. can be found in 3.12. An important trend to note from Fig. 3.12 is the increase in manufacturing complexities requirements. Fabricating standards for with severe more and specifications are more stringent for space applications ground assemblies. operating specification environment level The number associated with a is (FLTFM). referred to The variable as reliability than those particular platform WSCF is equal to the density of the structure in pounds per cubic foot. 2~ 1 the operating Equipments TypicalExamrnples WSCF 1.0 1.4 Ground Mobil 1.8 Airborne 2.0 Space 2.5 Manned Space Antennas Drive Assembliles Microwave Transmission Small,Spiral,Horn,Flush.Perabolic 4 4.75 5.39 Scanning Raedr10-40'Wide 8 5.3 5.4 Phased Arrays(Ll Redators) 6.8 5.9 6.2 Autornobile.00 to 400 H.P. 25-35 4.30 TurboJet(PrimePropulsion) 25-35 RocketMotors 14-15 ElectricMotors 75-100 4.47 5.0 MachinedParts,Gears. etc. 7-10 5.115.24 5.5 Mechanisnsw/Stamnpings (HiProd) 12 3.33-3.73 Wevu;de, IsolItors Couplers, 11-20 5.4-5.6 5.4-5.6 StriplneCrcuitry 9 5.7 5. Optics Good (Commercial) Engines & Motors 5.64 5.5 6.4 6.6-7.9 6.16.5 5.3 5. . 5.5-5.7 59 6.55-7.04 6.92-7.44 7.0 7.2 - 6.47.3 5.46.3 7.28. 5.46.3 - - 5.5-5.9 6.0 - 5.5-59 61 70-90 5.1 5.4 6.3 6.7 7 3. Ordnance Fuze Servo Tools Printed Excellent(Militery) Highest(Add 0.1per 10%YIeld) AutomatedProduction SmallProduction-Min. Tooling Maechrive &Coupliq Networks MachineTools PaperPhenolic CKT Cards GlassExpoxy, Double Sided 110 5.3 5.3 5.3 5.3 5.3 Cabling Add 0.1 for Platea.Thru Holes Multiconductor wiMS Connectors Same rv/ Hfwmtically Sealed Connectors 40 40 4.9 5.1 5.0 5.2 5.0 5.2 5.1 5.3 52 53 Nickel- Hydrogen NickelCadmium InertialPlatformTypo 80 75 79 5.39 6.01 5.83 6.56 6. 6.73 6.8 7.81 7.63 6.9-9.1 7.6 6.5 9.4 9.5 (BoardsOrdy) Battery Gyro Lr (Add0 2for3Layers&0.05forAddn'l) Module 70-90 5.4 5.8 7.3 7.8 8.0 70-90 5.9 6.8 8.0 8.3 85 14-20 4.3-4.65 4.3.465 14-20 5.11-5.33 5.11.5.33 6575 5.63 5.63-5.7 5.76 26 5.7-6.86 .7.6 86 25-30 4.45-4.52 83 4.14.3 4.14.3 4.14.3 4.14.3 4.14.3 Typical MCPLIXS Factors for Mechanical Assemblies (Ref. 20) Figure 3.12 222 8.55 8 38 7.0-9.4 9.5 Ships also experience a range of manufacturing complexities. Fig. 3.13 several illustrates USN the variation vessels. Note that of "whole ship" MCF'LXS for the cost per pound figure increases proportionately with MCPLXS. The platform specification level used in deriving these complexities was estimated at 1.4 for conventional ships and at PLTFM=1.6 for weight critical ships (i.e., hydrofoils, The affect complexity of technology on the value boats, technology manufacturing designs done at DTNSRDC (see Ref. 27). equal to 5.531 and 5.082 were estimated planing of is clearly shown in the comparative cost analysis alternative WPB MCPLXS SESs and ACVs). respectively. for the hydrofoil of Values of for hydrofoil and The result of the higher level of was a cost that was 70% more than the planing boat. The effects complexity on indicated costs vary with time in Figure 3.14. expected and according with time. indicates technology. manufacturing to and year As expected, of maturity for trends reductions manufacturing The year at which the curve the the The curves show the cost with improvements in design methods efficiency abscissa of the level of technology crosses the the particular lower technology matures earlier than high tech., but typically has less effect on costs. Scheduling effects production phases Penalties are on the costs of the can also be explored with assessed for accelerated schedules as shown in Figure 3.15. development the and PRICE and model. stretched-out ,P 0.5 _ a x I- 0DG993 6.0 w -a a. 5.5 _ LS041 · C. /A041 ~AS33 t 5.0 - Lid T-AOT177 O T-AOT168 Ce a. T-AFT166 *T-AFT166~~~~ I 10 20 45; 0 00963 j FFG7 SHIP TYPE S/LB. NICPLXS CG47 ODG993 FFG7 00963 CRUISER DESTROYER FRIGATE DESTROYER LS041 AD41 AS39 T-AOT177 T-AOT168 LANDING SHIP TENDER SUB-TENDER OILER OILER 54.0 42.9 32 3 28 6 138 13.7 111 9.6 86 T-AFT1E6 OCEAN TUG 6.29 6..12 5.82 5 73 5 36 5 30 5.19 5 08 4 96 4 53 20 40 COST PER POUND(S/LB) MCPLXS Factors for Selected USNVessels (Ref. 60) Figure 3.13 224 53 50 60 .HIGH TECHNOLOGY w J Q 4 z-a I 4) a 1970 1980 1990 Effect of Technology Inprovement on Costs (Ref. 64) Figure 3.14 225 . 2000 2010 $ $ $ DEV PROD TOTAL 190 6,887 7,077 190 7,133 7,323 190 7,841 8,031 DEVELOPMENT PRODUCTION DEVELOPMENT PRODUCTION -~~~~~~~~~~~~~~~~ DEVELOPMENT PRODUCTION Influence of Schedule on Costs (Ref. 64) Figure 3.15 226 The PRICE including: model incorporation production units; runs; a incorporates of a several learning other curve features, for multiple estimating the cost of multiple lot production factor to account for component integration difficulty; allowing design costs in proportion to existing discounting the through-put of vendor quotes to data, and; double prevent billing. PRICE also has a design-to-cost mode, to input a target cost, information. quantities which allows the user and level technology consists of design limits for weight. This Output analysis would be especially beneficial type of of during concept development and the early stages of feasibility design. One of widespread through Figure the use an main reasons that the model has is its adaptability to any hardware easy to use calibration process, found such application as illustrated in 3. 16. Basic inputs for calibration consist of cost and data plus the physical characteristics of the system. schedule The model then iterates on MCPLXS values until a complexity is calculated that matches the input data. calculated when the The empirical factors are now representative of the system and the supporting organization and data is ECIRPed (PRICE spelled can be used independently to estimate Once a user backwards) costs and schedules. has performed this process on a variety of related cost data, a pattern usually emerges for the complexities that can effectiveness be related of the to the system calibration 227 characteristics. is highly dependent on The the JO OM l l The PRICECalibration (Ref. 64) Figure 3.16 228 Process availability and accuracy of the cost data used. Fig. 3.17 (i.e., whole refers their shows ship) calibration. value data of PEND and respectively, month/year (e.g., 252 is Costs are given in British pounds. was obtained from an (Institute IDA were increase in 3.17, Defense a trend showing complexity with manufacturing production was developed and is shown in Fig. the complexity has been that for (e.g., see Ref. 44). study From the ship data contained in Fig. shows box by Cost and System Design Office personnel at DTNSRDC. performed the 1 1 box calibrations for selected US Navy ships Similar Analyses) production, given in terms is a The variables PSTART and the start and end of to February, 1952). The the information required to do 3.18. steadily start the The of figure with increasing time. The model with conjunction manufacturing. uncertainty of a incorporates the However, r i sk program in development and analysis cost estimates this analysis for is developed the PRICE algorithms and not of the input Understandably, the accuracy dependent upon the input data. indicates that of the model Bearing this in is mind, the PRICE model produces results within actual costs. 229 the using data. highly Ref. 20 10. of CLASS TYPE NAME COSTM STANDARDSCHEDULEDLENGTHHP (TOTAL) (ATPEND) OISP'T(WT) PSTART-PENO SALIS8URY 2170 SALISBURY 61 2170 LINCOLN 61 2300 LYNX LEOPARD 41 2380 BRIGHTON 12 WHITOY 2300 ASHANTI 81 ASHANTI 2450 LEANDER LEANDER 2500 .. ~ ARIADNE 5440 KENT COUNTY 5440 ANTRIM .. 6100 BRISTOL 82 BRISTOL 2750 AMAZON 21 AMAZON 2750 ANTELOPE 21 ". 2750 ARROW 21 .. SHEFFIELD 42() SHEFFIELD 3500 42(i) BIRMINGHAM 3500 42(I) GLOUCESTER 4000 42(II) EDINBURGH 4000 22(i) BROADSWORD3500 BROADSWORD 22(0) BATTLEAXE 3500 3800 22(n) BOXER ". 3800 22(0) BEAVER ". 450 MCMV WILTON TON 615 MCMV BRECON HUNT 32 MCMV (PROPOSAL) 120 HYMARINE 4000 SSN WARSPITE VALIANT SSN CONOUEROR 4000 .. SWIFTSURE SSN SWIFTSURE 4000 4000 SSN SUPERB . SSBN RESOLUTION 7500 RESOLUTION 7500 SSBN RENOWN . 7500 SSBN REPULSE " 7500 SSBN REVENGE .. PRICE H Ship Calibration (Ref. 25) Figure 3.17 230 3398 252-257 3398 655-660 3398 853-257 370 857-961 158-1161 360 372 459-363 1169-273 372 520 5 360863 266-770 520 5 1167-373 507 1169-574 384 384 471-775 1072-776 384 412 170-275 372-1176 412 1179-1283 463 463 980-1284 430 275-579 430 276-380 1179-1183' 471 471 680-684 1170-773 150 197 975-380 107 980-683' 1263-467 285 1257-1171 285 272 469-473 372-1176 272 264-1067 360 664-1168 360 360 365-968 565-1269 360 Data 14400 14400 14400 30000 20000 30000 30000 60000 60000 60000 64500 64500 64500 64500 64500 64500 64500 64500 64500 64500 64500 3000 3540 1000 NK NK 15000 15000 NK NK NK NK 33 33 32 3.6 5 22 4.7 70 13.8 168 27 144 144 20 2 23 2 309 78 5(1980) 850(1980) 68 6 69 2 125(1981) 130(1981) 23 30 135' 24 30 37 1 41 3 40 24 3995 375 386 77 7 Inl I r I - 1 Iq I I 1-1 ' 1 1 I I] FRIGATES& DESTROYERSMCPLXSvs PSTART r/I: 5.8 6I 5.,4 E ~~~~~BF~~~~~~~ T22(11. . I I T22()_ I _ 5;2 C. r 5 .4-142 :, . _/ ' T21II , T21T821 .121 ---1 II I _ . T . _.^ I -1 --l COUN'TY -- r ''- - IcIL-e I I I· LEANDER I II r, 1 D t- r A a: IE ] - AA -· 7 _ 4 ~E 54 .- l PJTV J I.1l I I 1-1 J 1- .I- ANDEi II l----· - l II II 58 , . - , - . r ._ _ - - _T I1 _ -- H-e __. & Destroyer MCP(XSvs PSTARTTrend 25) Figure 3.18 231 - . t l- |- __ lA _ 7 IE3 : E_ lEI 74_ 1960 62 64 66 68 1970 72 (Ref. _I I - x PSTART Frigates _ . I I fi -E 56 r . .j T81,~ , _/ I T61 T41 lk - - T12---I -W "T611 I' " 4 I 1 - 2 _ U) x t,/' F T42(i)- - - - _ 76 I = 7 _ J 78 1980 82 84 When life the output from PRICE H is coupled cycle costs can be estimated. as the cost of supplying with PRICE Life cycle costs are defined and maintaining a particular system. The model can discount future costs or present funding by The costs equipment; HL, year. estimated depend on the characteristics of the: employment/deployment; organization, and; maintenance concepts used. The model uses over 250 preset variables, each of which altered by the user, may be support environment. to describe the system's Input I__nformat i on 3.1.5.3 The minimum following data "reasonable" input required estimate information by of the is considered to PRICE H model development and the a costs A glossary the input variables and the data sheet used to input information The obtain manufacturing during the feasibility/preliminary design phase. all to be for system into the PRICE H program can be found in Appendix F. parameters below are grouped into the common cost classifications outlined in Table 1.5. TECHNOLOGY Manufacturing complexities Technology base year SHIP DESIGN Hull structure weight (SWBS group 100) Propulsion plant weight (SWBS group 200) Electric plant weight (SWSSgroup 300) Command& Surveillance systems weight (SWBSgroup 400) Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) Armament weight (SWBS group 700) Design & Builders margin Operating environment PRICE H Development & Production Cost Parameters Table 3.30 driver MANUFACTUR I NG Manufacturing complexities Learning rate PROGRAMMAT I C Scheduling Development start & end dates Production start & end dates Number of ships ECONOMICS Base year $ ______________________________________________________________--- PRICE H Development & Production Cost Parameters Table 3.30 (continued) Output .1. 5. 4 The Information PRICE H output production costs, cost data is in terms of development not the usual material/labor format seen "shipbuilding only" cost methods. Table 3.31 categories brief total. previously description and with shows the major cost indicated in Table 3.28, of the various elements that and contains make up a their ~~-----,~~-- Prropgram Cost~,;~+ Cost Element ---- ,~--- - -- - - -- Q~eRg_!ippt,i on - - -- - - -- - - -- - - -- - - -- - - Engineering Data Documentation costs for manuals, lists, reports, deliverable drawings, and other related items Design Cost of design and development engineering Drafting Cost of manufacturing drawings, data lists, specifications, and incorporation of engineering changes in drawings Project Management Cost of program management and control to include travel expenses, computer operation costs, in-house reports and the "ilities" Systems Cost of conversion of performance requirements into design speci i cations ManLtufacturi ng Producti on Manufacturing costs to include material, labor, st-up, overhead, and quality control Prototype Production costs for prototypes including material, labor, overhead, and qualification testing Tool -Test Cost of all special Equipment equipment to include their design and any refurbishment Description of PRICE H Cost Elements Table 3.31 tools and test The Costing and Design Systems Office at DTNSRDC has familiarity output with cost PRICE to correlate USN SWBS based accounting categories in order to obtain recognizable ASSET and NAVSEA formats. enough and PRICE the Table 3.32 indicates more the relationship for lead and follow ships between PRICE cost outputs and NAVSEA end cost respectively, construction plans (CP) and basic construction (BC) categories 211, (e.g., see MCCs 111/113 and in Fig. 3.2). PRICE Cost Category Development Production Drafting CF (lead) 0.0 Design CP (lead) 0.0 SWBS800 (lead) Not Applicable SWBS800 (lead) SWBS800 (lead & follow) SWBS800 (lead) SWBS800 (lead & follow) Engineering Systems Project Mgmt Data Manuf acturi ng Production SWBS1-7, margins, NA GFM (lead & follow) Prototype Tool-Test Eqmt. 0.0 0.0 NA SWBS900 (lead & follow) Total Cost = Development + Production Costs Relating PRICE and SWBS-based Ship Costs Table 3.32 236 The following PRICE sum is used to estimate the construction plans, CCp (see Eqn. Cp CP cost .12): (3.80) (Dev. Drafting) + (Dev. Design) The basic construction cost, of CCC (see Eqn. 3.8), is then estimated from the remaining PRICE cost elements, so that: C = FG& A ( (Total cost) - ( (Dev. Drafting) + (3..Desi1) (Dev. Design) ) ) where F G&A = 1.165 F a is factor that accounts for general and G&A administrative overhead not included in the FRICE cost algorithms. The nLlmerical value of this factor is the result of experience gained by DTNSRDC in comparing NAVSEA cost estimates with PRICE outputs (e.g., see Ref. 1ists are separately through-put by PFFRICE and from the total cost figure their in Eqn. Once the construction cost is obtained, categories indicated in Fig. in Section 26). GFM cost sum wi11 237 appear (3.81). the other end 3.2 can be calculated as 3. 1. 1. formatted cost described 3.1.6 Other Cost Models There are several cost models which have not been discussed in this study. In this section these models are broken into three groups: the FAST-E parametric model; models for merchant ships, and; contractor/shipyard models. 3.1.6.1 FAST-E FAST-E is - Equipment) (Freiman Analysis of Systems Technique a parametric cost model for estimating cycle costs of various equipments. acquisition and life- the model is very similar to the RCA PRICE model. This is not surprising, since Frank Freiman originally the RCA PRICE model back in the 1960s. FAST-E study developed model is explained in greater detail than found in Refs. This cost change express etc.) in this 18 and 37. model adjustable, The has which a feature of being is said to emulate designers' perceptions change unique (Ref. 18). from a known design to a new one using This allows (or descriptions and linearly managers' analysts shedule, to reliability, such as 25% less, 50% more, etc. Costs- are related to an overall complexity factor which itself related to a variety of general integration factors equipment technologies, and reliability & maintainability impacts. Complexities are calculated by calibrating the model using data. FAST complexity mechanical system factors unlike represent a those in PRICE is complete which input electrorepresent structural and electronic separately. This one feature variable makes of combining the two PRICE complexities it easier to calibrate FAST because into no of to be made as to the weight and density has assumption the various components. Only the total weight is required as input. An unpublished Navy report on the FAST-E model suggests that approximate total ship costs. it is a useful tool for obtaining To date no Navy personnel are actively pursuing the use of in Navy ship costing, model Costing System and although this the in several personnel taken FAST cost estimates are usually broken down into Design Office at DTNSRDC have training. 3.1.6.2 Merchant Ship Cost Models ship Merchant manhours cost material costs for three and These categories. are; categories (1) Steel (2) Outfit (3) Machinery Cost estimates are obtained in each area through the use cost engineering detailed for CERs weight/cost general estimating cost Conventional trends. for more field was procedures are employed design definitions. Perhaps developed at the most well-known cost model in this MARAD (Maritime Administration) (e.g., see Ref. 38). A description by 39). There are of the procedures several other references merchant ships in the open literature. under Refs. 40 - 43. 239 Fetchko J.A. available MARAD for estimating ship costs is given in a paper by (Ref. of at Landsburg to costing Some of these are of listed 3.1.6.3 Private Contractor Models Private costs contractors typically estimate construction ship using the conventional engineering method. Labor manhour to material costs are estimated on a system basis and sliummed and obtain a total ship cost. Generally, the work breakdown system by private contractors is not the SWBS system found in used the Navy. Private shipyard contractors experience rely heavily ulpon their (most have spent several years extensive working in shipyards). Their databases are considered highly proprietary and are closely guarded. the open literature, Because they seldom publish cost studies in methodologies is access to even their difficult. 240 3. 2 COST MODEL COMPARISONS This section is intended to provide a comparative study the NAVSEA Code 017, comprehensive examination studies, costs, cost of of NCA, ASSET, USCG and PRICE cost models. Any model comparison will input/output involve sensitivities, a detailed comparative cost the influence of design standards, treatment of program database requirements, plus a variety of other cost issues. The ability to perform such an analysis requires complete access to the models and data bases proprietary nature of costing in general, involved. Given this access is the seldom granted. The research above result of papers on costing in the open literature apply issues based this reluctance to share information is in a general way. is to the primarily pon data available in published journals and unclassified government documents, comparisons is also forced 3.2.1 Since this study that General the following discussion on cost model to be of a general nature. Model Characteristics The five cost models selected in this study present a fairly complete spectrum of methodologies used for new ship construction costing. These include the following categories; (1) conventional engineering (2) CER (3) parametric The NAVSEA Code 017 model is representative of conventional engineering or so-called bottoms-up approach, the ship is broken down into discrete blocks for which and labor costs are estimated. 241 The highest level the where material of detail for obtained this approach occurs when the estimator job. for the entire possession of a bill of material individual material and labor costs have been is Once in the they calculated, are summed for the total ship construction cost. The NCA USCG, and ASSET use models cost estimating relationships (CERs) to estimate costs. CERs employ a single nonto cost relationship to estimate ship cost can be developed down to any level CERs Although of costs. technical are usually applied on the 1 digit SWBS level they detail, construction and are referred to as a top-down approach. is representative The RCA PRICE model of end cost the parametrically. approaches, spectrum methodology Parametric intended estimates and at the other costs estimate also are top-down for use under conditions in which there is not a detailed breakdown of the ship. approach dffers of models the parametric Typically, from the use of CERs, in that it uses more than one non-cost variable in its regression. plus the models use weight as the main cost driver, All accouint for different method to include a multitude of influences, variations in materials, Technologies technologies. including but not limited to, propulsion, electrical power generation and distribution and electronics. invariably a are "high tech", Combat related systems, which to be input are generally intended using a shopping list. Technology differences are accounted for in the NAVSEA model through linear the extensive data base. The NCA model trend lines for the various technologies .242 has different represented in The ASSET and RCA PRICE models use technology its cost elements. to describe the variations in technology (although there factors is no relationship between each model's factors). The USCG model adjusts CER outputs directly using appropriate multipliers. Rangeof Appelicability 3.2.2 3.2.2.1 Vessel Range Type and Displacement for which each model is capable displacements and of producing Accurate model results are assumedfor ships "accurate" results. place them within the range of ship costing whosedesign features accurate information available in the database. In other words, are produced whencost information on similar results types of applicability refers to the variety of ship ship types has been incorporated into the model CERs. Table 3.33 indicates the vessels for which each model is was obtained intended and has in fact been used. This information model. from personnel using the specified The wide range of applicability for the NAVSEAcost model is of the existence and continual updating primarily due to database. The NCA checks the NAVSEAestimate for conventional monohull combatants using the model discussed in this study. vessels, other NCA Due to the Corporation. uses a model developed its the by For RAND classified nature of this model, it could not be documented. The it ASSET model indicates a wide range of vessels for which can be used. ASSET CERs It is important to note that the data is from the early to mid 1970's and so 243 is for the becoming Cost Range of Applicability Model Vessel Type Displacement (LT) NAVSEA Code 017 any new construction NCA frigates, destroyers, cruLi sers ASSET all monohulls, SWATH, hydrofoils, SES, CV 10 - 20,000 USCG all CG vessels (i.e, patrol boats to polar 69 - 12,000 2 - 100,000 5,000- 12,000 i cebreakers) RCA PRICE any new construction 2 - 100,000 Cost Model Vessel Applicability Table 3.33 dated. the In addition, several of the advanced vehicles included in ASSET database environment and are were built therefore in an aircraft not indicative of and/or a R&D production setting. The vehicles Coast Guard model has incorporated a wide range in its database. Due to limited construction of USCG in the CG, the database for each vessel type is typically small. However, it has been found to be representative of the indicated range. The RCA PRICE model ability has an all encompassing range due to its to be calibrated and the universality of its 244 complexity factors. vessel The flexibility of the complexity factors type ot be estimated, allows even if extrapolating outside any the range of the database. Cost analysts, a ship cost for by necessity, may be called upon to estimate a vessel type not included in the current database. For these situations, it is important to understand how each model can be perturbated (and by how much) to account for new design variations. As mentioned for the RCA PRICE model, the complexity factors allow for technology extrapolation factors in outside of the the model ASSET database do not range. The have any universality, in that a new technology factor cannot be estimated from a knowledge of the current database values, and the factors scale differently for each SWBS group. By the nature of their development, cost models are intended to be used to estimate ships similar to those in the database. If it becomes necessary to extrapolate outside of must be done so logically and this intelligently. range, Phrases it like, "relate existing data tempered with experience" become applicable (but certainly not helpful) and show the importance of knowledgeable personnel in the cost analysis process. 3.2.2.2 All provide Ship Desian Phase of some conceptual, the the models discussed in this study are intended weights in the to of ship cost estimates during the and on into the preliminary design phase. Typically, technical Due measure to definition available during these periods are - 2 digit SWBS level. its conventional engineering approach, 245 the NAVSEA Code 017 is applicable from model the provided appropriate level ROM to budget is definition technical of estimates, available. Although, any of the cost methodologies will produce a more accurate estimate (as related to its database) if there is uncertainty in the input data. less model was intended The ASSET cost for comparative cost of naval vehicles rather than specific point estimates. analyses Therefore, ASSET estimates may be the cost questionable most (i.e., uncertain) for specific ship design applications. Model _In_pt/Outtput 3.2.3 the Al1 estimation weight models Comparisons discuLssed in this technology construction costs. level are address the As previously mentioned, the main inputs for estimating of ship acquisition costs. and study Scheduling and programmatic costs are also important for calculating total acquisition costs. Only the ASSET cost model directly estimates the total lifecycle cost (LCC) associated with a ship. LCCs are most frequently for select comparative studies and require used operating equipment profile, analogy the personnel salaries, such as those obtained consumption, -spares and maintenance policies. Financial using fuel infor-mation on spreadsheet comparisons, USCG's CASHWHARS program (e.g., see Ref. 34), or direct comparisons with the USN's VAMOSC methods of doing these LCCstudies. 246 data, are popular 3.2.3.1 Minimum Ipt Requirements In this section, the cost parameters that are representative of the technical definition necessary to cost a ship during conceptual/preliminary design phase are presented. data required for each model, the The amount of or its definition, may differ from the inputs given below. The user NAVSEA model would require the most input data because of its conventional engineering approach. PFRICE model would require the least amount by the The RCA of data to obtain a reasonable estimate, provided it was calibrated initially. Table estimate listed 3.34 shows the representative input data required the construction cost of a lead ship. The in this table are the general cost driver Table 1.5 and were used previously to categories categories in to group the cost parameters associated with each model. Weight cost drivers in Table .34 are in the form of the 1- digit level SWBS groups and the margin weights. Cost influences from the appropriate levels of technology apply to manufacturing, materials, propulsion, electric power generation and electronics. Expensive shopping combat lists. systems Scheduling related effects components enter are affected through through the interaction of length of construction and the rate of inflation. Other parameters reflect the shipyard labor and material costs or provide a base date for technology effects and monetary conversions. 247 TECHNOLOGY Ship type (i.e., SWATH, Hydrofoil, etc.) Hull & Superstructure material Fropulsion plant type Electrical plant type Year of technology SHIP DESIGN Hull structure weight (SWBS group 100) Propulsion plant horsepower Propulsion plant weight (SWBS group 200) Electric plant weight (SWBS group 300) Command & Surveillance systems weight (SWBS group 400) Auxiliary systems weight (SWBS group 500) Outfit & Furnishing weight (SWBS group 600) Armament weight (SWBS group 700) Margin weights F'AYLOAD DESIGN Cost of payload material (includes armament& weaponsportion of cornm. & surv.) MANUFACTURING Labor rate Production technology PROGRAMMATIC Profit fraction Overhead fraction Construction start date Delivery date ECONOM ICS Inflation rates Base year $ BLSmaterial indices Base year for BLS data Representative Lead Ship Construction Table 248 .34 Cost Parmeters Table 3.35 shows the additional data required to estimate construction costs for a multi-ship procurement. Frimary inputted data include a labor and material cost breakdown for the lead ship, inflation rates, and profit and overhead fractions. Major from the inflation. influences on multi-ship construction relationships between learning, costs result scheduling and Drawn out scheduling can substantially increase costs due to inflation. Multiple production lots increase costs due to a reduction in production learning effects. Increased costs due to uneconomical scheduling or unforeseen inflation can easily result in a decrease in the number of ships that can be produced if there is only a fixed amount of money be spent. Inp!tte d Dat a Lead ship construction costs Inflation rates Profit fraction Overhead fraction Base year $ MANUFACTUR ING Learning rate (material and labor) PROGRAMMAT IC Number of ship required Construction start dates Delivery dates Representative Multi-Ship Construction Cost Table 3.35 249 armeters to LCCs discussed in this study deal mainly with and operations & support (O&S) costs. to the acquisition cquisition costs are equal construction price plus various program and G&A add-on costs. These add-on costs are generally estimated as a percentage of the construction price. Typically, the total program cost is 30-40% above the construction price. O&S costs include contributions from the areas of personnel, operations, maintenance, related to salaries, the time the fuel and spares. Personnel costs are benefits and training. Operations determine ship will be underway. Maintenance, fuel and equipment spares costs are self-explanatory. Table 3.56 indicates the additional information required to estimate LCCs. Inputted data consists of total ship acquisition (i.e., program) costs and the necessary economic data. Research incurred into the & development plus testing & evaluation costs to enable the introduction of high the ship design. construction or technology are systems The additional facilities costs relate to refurbishment of maintenance or docking facilities. The vessel ship's residual value refers to the scrap value of at the end of its service life. generally in the range of 25-30 years. 25 0) The service life the is Inputtted Data Total ship acquisition costs Ship delivery dates Inflation rates Interest rates Base year SHIP DESIGN Ship fuel rate Crew accommodations PAYLOAD DESIGN Payload fuel rate PROGRAMMAT I C R & D, OPERATIONS T & E costs AND SUPPORT Annual cost of training ordnance. Equipment spares Additional facilities Salaries,benefits costs and training Annual operating hours Ship residual value Service life Fuel cost/gal Representative Life-Cycle Cost Parameters Table 3.36 251 3.2..3.2 Cost Output Sensitivities In this section, to variations accomplished subsystem in the sensitivity of the cost model the input by examining cost data marginal are discussed. cost factors drivers) and total outputts This (i.e., acquisition is the major (program) cost sensitivities. There is no quantitative comparison between cost sensitivities of the different models reviewed in this study. To have done this would have required a detailed comparison of model outputs for various ship types. Unfortunately this was not feasible given that these results would have been considered of a proprietary nature. 3.2.3.2.1 Marginal Cost Factors Marginal determine cost the factors provide For convenient method effect of subsystem changes to ship costs see Ref. 5, 13 and 35). The marginal associated a cost is the change (e.g., (in cost) with a unit change of weight of a particular this study, to system. the subsystems are identified by their 1-digit SWBS designation. In found terms of this breakdown, that leverage the four cost analysts (4) SWBS groups with the have typically greatest cost are; (1) combat systems & related electronics (2) electric generation and distribution (3) propulsion systems (4) axiliary This subsystem machinery list is representative of the naval surface combatants cost percentage breakdowns noted in Ref. 36. The and electrics upon the systems cost/weight depending propulsion systems may be interchanged chosen for each. Table 3.37 lists the sensitivities calculated for the DD3 51 navy surface combatant. Note that the factors for combat systems and command & control groups do not include the cost of equipment. Marginal Cost* Factor ($/LT) SWBS Group 17,500 100 Structure 200 Pr opul s i on 110, 800 300 Electrics 180,200 400 Command 46,300 500 Auxi iary 80,800 600 Outfi t 78,500 700 Armament 16,000 * costs in FY 83 $ ** shipyard installation costs only, equipment procured separately Naval Surface Combatant Marginal Cost Factors (Ref. 5) Table 3.37 in Personnel DTNSRDC costing and the systems office at for the the cost/weight sensitivities that indicated design ASSET and RCA PRICE models were similar. 3. 2. 3.2.2 Program Cost Factors cost sensitivities examine the Program cost contributions in addition from a one resulting loaded labor (i.e., additional plus or reduction dollar direct program overhead) and material costs. Table shows that effect of the dollar NAVSEA format. dollar change in labor cost in results This example provides change of $2.73. cost program A in increase labor during construction on subsequent elements of loaded using 3.38 a direct a illustration of the importance of add-on costs to ship costing. Table The increase. lower 3.39 dollar shows a similar effect for a material smaller program cost is primarily the for percentages engineering and cost result of construction services material. 3.2. 3. Cost Otput Accuracy This section is an attempt to provide a quantitative measure of the accuracy that a user can expect with the cost models presented,' and a qualitative measure of cost estimating accuracy in general. The personnel using the five models in this study contacted and asked to provide a representative percentage figure that would given an indication of the uncertainty point estimate. For example, the value of the estimate - 10%. Some interesting points were brought Lip. .54 were error of a is $X + or Cost Factor Element Calculation No. Description 1 SWBS 100-700 2 Margins 12.5% 3 SWBS 800 4 - $ Amount 1.00 (1) .125 30% (1 + 2) .396 SWBS 900 27% (1 + 2) LR* .304 5 SWBS 100-900 1 + 2 + 3 + 4 6 Profit 10% (5) 7 FCM 5% 8 BCC 5 + 6 + 7 9 Change Orders 1)% (8) .205 10 Escalation 20% (5) .365 11 PM 12 Program Cost * ** Growth 5% (5) .183 OV (8 + 9) 8 + 9 + 10 + 11 LR = engineering/manufacturing labor rate ratio OV = engineering direct/burdened labor rate ratio Labor/Program Cost Sensitivity Table 3.38 1.825 .044 2.052 .113 2.735 Cost Factor Element Calculation $ Amount No. Description 1 SWBS 100-700 2 Margins 12.5% (1) .125 3 SWEBS800 1% (1 + 2) .011 4 SWBS 900 4% (1 + 2) .045 5 SWBS 100-90)( 1 + 2 + 3 + 4 6 Profit 10% (5) 7 FCM 8 BCC 5 + 6 9 Change Orders 10% (8) . 129 10 Escalation 20% .236 11 PM Growth 5% (8 + 9) 12 Program Cost 8 + 9 + 10 + 11 - (5) Material/Program Cost Sensitivity Table 3.39 256 1.00 1. 181 .118 1.299 .072 1.737 First of all, each person contacted was more than a little hesitant to give a representative figure. If nothing else, this demonstrates the uncertainty that pervades cost analysis. Figures that were given were typically in the range of plus or minus 15- 25% the for estimates during the conceptual phase and 7-15% at end of preliminary design. Such a percentage figure is strictly there is no uncertainty involved. estimate is percentage applicable if For instance, if a single cost compared to the return costs for that error only would completely define the vessel, accuracy the of the estimate. However, if the figure is given as a general measure of the accuracy, then in order for it to be statistically meaningful, it requires an indication of the analyst's confidence that any given estimate will fall within the specified range. estimates versus This point is illustrated in Section 2.3.1. Percentage error differences for return cost data vary significantly. to cost Differences can be expected decrease as input data becomes more accurate. accuracy is usually is a necessary requirement not similar costs accompanied by greaterdetail, for accuracy. Although more greater detail Ref. 26 shows percentage errors for ACVcost estimates versus return for input data ranging in detail from whole ship down to the 3-digit SWBS level. Current indicated to point be estimate double those of the reasons were given for this; uncertain database to errors for the other ASSET cost model were models. Two (1) the KN technology factors within 2(:%of their values due to the 15 year from which they were derived, 2.57 and; (2) the' model were old was initially intended for comparative studies. The relative cost percentage errors for the ASSET model be expected estimates. since to be significantly lower than those of This statement is true for any the comparative can point study, only selected baseline characteristics are prturbated create the variant. Because of this strong correlation the baseline and variant, to between there is less overall cost uncertainty (i.e., a smaller variance) and therefore reduced errors. It not a is important to note that in cost estimating, lot of confidence associated with any there one is estimate. Although this can easily be shown to be statistically true (e.g., see leve Section 2.3.1), it can also be seen at a bids received, characteristics bids practical 1. For any request for bids, the more there will be a wide variation in each reflecting the of the yard at the time. particular needs Because each of and these can be rationalized in relation to the yard submitting it, the bid is "accurate" for the assumptions and data used (provided that there are no blatant errors). The preceding discussion indicates that a comparison of the accuracy or requires a correctness of any cost methodology with another detailed examination of the assumptions used in the development of the model. These assumptions will impact the areas related to standards, management and scheduling, few. 258 to name but a CHAPTER 4 DEVELOPING A SHIP COST ESTIMATING CAPABILITY The design increased emphasis on the economic feasibility of (e.g., involvement and However, any within the constraints dictated by the perceived needs and resources of the visibility costing see Ref. from the cost capability must requires estimating be a greater community. developed to operate throughout the conceptual/preliminary design Even organization. 52), ship phase, these needs can vary from cost comparisons for feasibility studies trade-off ship a costing capability. require Fig. 4.1 groups these priorities may that Therefore, in addition associated also experience changes. is estimating capabilities should be view of current management to fLifilling these needs, quantifiable accuracy and available within a specified timeframe. require their sense. the important Accuracies to requirements. periodically direction. there must estimate Estimates for must be accurate in the range of 10-20% are be an must be trade-off relative accuracy between comparative estimates on the other hand, Budgetary It a priority shift can affect costing cost re-evaluated absolute that functions most organizations are continually evolving, Because studies specific to their applicability within the ship design process. according In for Table 4.1 lists a wide variety of functions designs. realize through to budgetary estimates designs. in an usually indicated for estimates in the early stages of design. The obvious time for an estimate to be available is whenever a decision point is reached in the design process. 259 During the conceptual/preliminary design phase, translates has into this requirement immediate availability. led to the development of cost interface with the otput This rapid Design-To-Cost Source Selection Froposal Review Trade-Off Studies Budgeting Cost Control Technology Impact Specification/Standards Impact Economics Effects Scheduling Effects Bid - No Bid Decisions Contract Negotiations Organizational Cost Estimating Functions (Ref. 58) Table 4.1 260 turnaround estimating models which will from design synthesis models. Contract generally * COST IMPACT * COSTDRIVERS * COST STANDARDS * ADV. VEHICLE * COST AS A DESIGNPARAMETER * IMPROVEDCOST ESTIMATINGTOOLS ABILITYTO ESTIMATERELATIVE COST CHANGEAS DESIGNADVANCES * IMPROVEDMETHODS TO ESTIMATE NON-HARDWARE COSTS * COST TRADEOFF ANALYSIS DATA BASE * R&D PROGRAMS FORCOST REDUCTION * ESTIMATE RELATIVE COST * IMPROVEDCOST DATA BANK * HIGH QUALITY COST ESTIMATES * COST IMPACT OF ACOUSTON POLCES * INCREASEDCOST DETAILS * EFFECTIVECOST ESTIMATING PARTICIPATION o INDEPENDENT COSTESTIMATE * ANALYZE CONTRACTOR COST ESTIMATE Cost Estimating Functions for the Ship Design Process (Ref. 59) Figure 4.1 261 * COST IMPACT OF CHANGES,DELAY. DISRUPTION.ETC. * ABILITY TO ADJUDICATE COST CHANGES * AWARENESSOF COSTDRIVERS 4.1 COST MODEL DEVELOPMENT This section deals with some of the factors to be considered for developing a parametric cost estimating model (of which CERs are assumed to be a subset). The primary motivations for using parametrics are to reduce the costs of estimating, and to provide consistent, primarily there (e.g., repeatable results. Although used as an independent check for parametrics contract proposals, is increasing interest in using them for contract see Ref. 57). A list of criteria for objective is given in Table 4.2. Cost-to-Noncost Estimating Relationships Must Be Logical Data Used For CERs Must Be Verifiable A Significant Statistical Relationship Must Exist Between The Variables CERs Must Predict Well Parametric Estimating Systems Have To Be Easy to Monitor Compliance To The Previous Criteria Must Be Verifiable Criteria for Parametric Contract Fricing (Ref. 57) Table 4.2 262 are pricing meeting this The first Chapter 2. within in Table 4.2 has been discussed Data verification will ensure that the estimates the database criteria database's range is kept current. of applicability In order to predict and well, that the in are the model must be sensitive to a multitude of factors, including technology improvements, design and manufacturing complexities, scheduling, programmatic considerations and the "ilities" reliability, etc.). should be criteria Ease of monitoring indicates that the CERs able to be easily updated and requires (maintainability, calibrated. that documentation sufficient to The last verify the previous requirements accompanies the estimate. Although cost relationships (e.g, particular and most models are based upon similar non-cost versus model chosen experience of the weight versus construction cost), is largely dependent upon the organization requirements of its customers. requirement for budget format and should For example, submissions the the interests reflect the labor/material makes the engineering costing method the only practical approach for NAVSEA (e.g., see Section 3.1.1). particular the group, of the but also the resources that were available to group during the model development. Before form Cost models not only reflect the needs of prospective benefits a parametric estimating system is cost/benefit analysis should be developed, some performed. The costs of a new system can then be weighed of potential savings in estimating against the effort and/or increased estimating accuracy. Most data parametric models require essentially the (e.g., see Section 3.2), 263 although they may same input weigh these parameters differently within the algorithms of the model. Also, since these models are trend indicators, they tend to reflect the projects in the database. 4.1.1 Data Gather ing The most difficult phases part of cost estimation in early program is that of finding the proper mix of cost model and model input data. properties The of model the shoul d system require inputs that are well based defined on and can the be established with a reasonable degree of certainty at the time the estimate is required (e.g., SWBS 1-digit weights during feasibility studies). Data gathering considered is just one of the factors for the development of the cost that database. must Fig. be 4.2 indicates six factors, including data acquisition, that determine the characteristics considerations are of the cost database. important for information of Data a access proprietary nature. Cost definitions and standards (e.g., sailaway costs, mil specs, etc.) specify the format in which the cost data will be found. The economic factors and definitions allow for consistency in the cost reported (e.g., see Section level of detail of the available database 1.5. 1). greatly The size and influences the choice of costing technique. If then there it is an abundance becomes much of data for a particular easier to develop representative cost estimating relationship. are system, accurate Whether these CERs developed within the organization or by outside agencies 264 aid is COST DATA BASE DATA ACQUISITION A BA! COST MODELS COST PREDICTION DESIGN / % za .,,~ ~ < Sunni nrtV I l[. MANUFACTURING TECHNOLOGY *'-U,) CcT DnlIrT Ul I I\LLJUL. I Tnl Factors Affecting the Cost Database and Cost Predictions (Ref. 60) Figure 4.2 265 i on dependent the monies and to available personnel the organization. The cost models at NAVSEA Code 017 and the USCG are examples of internally (i.e. in-house) the When undoubtably cost data resides with other proprietary of BIW NCA data source. it companies, easily is obtainable. contracted the naval architecture & Cox to develop a cost model using Gibbs proprietary not and therefore Due to limited resources, firm developed CERs. Gibbs & Cox in shipyard to supply cost information, turn an outside subcontracted nwilling which it was to supply of its own volition. such as When there is little data available for the design, for it becomes difficult to of existing CERs can lead to technology applications, advanced The extrapolation estimate costs. erroneous results. Models that have been developed to account for all ranges of technology include the RCA FRICE and FAST-E models. Fig. 4.2 also illustrates that a cost database can create a level of cost awareness sufficient to allow analysts to determine the cost impacts from changes specifications, technology and Data can design methods and operational capabilities. be collected from cost data (e.g., in shipyard data). individuals or from existing In either case, data gathering can be broken down into three steps; (1) find the right experts or cost data files (2) ask the right questions or retrieve necessary data (3) transform the responses or data into data compatible with the model input data The processing individuals biased involved is illustrated in retrieving cost data in Fig. 4.3. The data collected by the respondent's perception of the event in from may be question; it may be irretrievable based upon the respondent's understanding of the question, Once or; it may even be forgotten. access to cost data files is available, the main problem with existing data is the conversion of the data. Much of the effort in developing transformation of the shipyard NCA cost cost data model into involved SWBS the compatible groupings (see Ref. 23). The most important consideration for the maintenance of historical database is to have a process consistently collect data. to comprehensively an and If personnel other than cost analysts are required to document return costs, it is imperative that the forms used be simple and short. repeated personal contact Also, provides continuing reminders and gets the job done! 4.1.1.1 Establishingq User Needs Information methodologies on user needs can be (i.e., CER, Parametric) divided into and model features costing that are important to the analyst. Table 4.3 provides a partial listing of some his of these desirable features. own ranking for this list, Since each analyst a cost model can be will have developed which is cognizant of those priorities. In order requirements throughout to establish the cost within the USCG, various estimating a questionnaire departments at HQ in 267 and was Washington, modeling distributed D.C. The RESPONOENT'SINFORMATIONPROCESSING INTERVIEWER'SDESIGN OF OUESTIONS Behavioural Information Processing Model (Ref. 19) Figure 4.3 268 Input Data Availability Is the input data requi,-ed by the model available during the conceptual/feasibility design phase? Evaluation Capability DesLiagn Does the model consider factors appropriate for design trade-off studies? Ease of Use Is the model easy to use with minimal training? Ease of Calibration Can the model be calibrated to the stated situation with available data? Data Base Validi ty Is the model database relevant to and valid for the situation addressed? Currentness Is the model based on current information which reflects the latest technology? bi 1i ty Accessi Is the model easy to access at a low cost? A1i pP _Ralg?._of cabi i tey Is the model applicable to a wide variety of programs? Ease of Modification Can the model be easily modified to incorporate new data? Cost Model User Features (Ref. 19) Table 4.3 269 survey, Table 4.3, The in Appendix C, found as well as asking for specific costing intent different addresses all of the features of the survey was to develop an costing recommended cost model selection or requirements. awareness requirements thoughout the CG, in of the that any would be so selections responsive to these needs. Unfortunately, of the twenty surveys distributed at USCG HQ, one only was making returned, sampling representative it impossible to obtain There of the costing requirements. one reason that the information was not available for only study, and that was the lack of personal follow-up after a is this the questionnaires were distributed. A more effective procedure would been to meet personally on a one-on-one basis and let have answer the survey questions orally. In this manner, not have been intimidated by a lengthy survey, of their time would be lost, them they would a minimum and any misunderstandings amount arising could be settled immediately. 4.1.2 Resource Reqirements Personnel and monetary resources are closely related through the costs of salaries and training. have several individuals who have been estimating for several years. minimum pool number. ensures associated with cost Two people should be regarded as a A constant nucleus of people provides a stable which tends to increase the management's) confidence in their ability, and that new staff members receive extensive formal and on- of knowledge and experience, analysts' Most organizations generally (and the-job training. 2 7C) Monetary costs resources are not only required for the associated (e.g., with the development of a software, equipment purchases, viable manuals, front-end cost model training) , but also with recurring operations and support costs (e.g., salaries, training, model updates, resLilt from effects of equipment repair). Model updates can programmatic changes and/or CER changes due to new materials and fabrication processes the (e.g., robotics, zone-outfitting, etc.). 4.1.3 Organizational Considerations For cost estimating to function properly, must be (a) committed to maintaining the responsive to organization the results. As part of the organization capability, its and commitment, must allow the costing group to communicate (b) the within the organization as the need arises. Effective encountered for reporting. both can overcome 90%/of information tables) management. For can greatly example, popular affect financial problems and analysis the CASHWHARS (see Ref. text, receptivity spreadsheet programs because results can be obtained and immediately as inputs are changed. USCG gathering. the The presentation of estimating resilts (i.e., graphics, becoming communication of are displayed Thus, programs similar to the 34) give management fast feedback for program trade-offs. Historically, although costs risk analysis, probabilities have been presented as a point with its range of costs and (see Section 2.3), 271 defines costs val Lue, associated in a more (and statistically) intuitively illustrates correct costs can be presented how Fig. manner. 4.4 management's combining desire for "a" cost figure with risk analysis. Such presentations can overcome management bias and resistance and provide still all the necessary data for decision-making. can Management a its commitment to sustaining show the cost team Primarily, estimating capability in several ways. cost must be included in the early stages of design, where costing has on maximal impact reduces financial design. Early planning uncertainty cost of As in the project. resources the design progresses, cost analysts must be allowed to interact on a real- time with basis to design engineers relationships This will allow the costs and design engineering. between establish cost impacts of design changes to be known quickly. If the need for a cost estimating team has been established, management must support the development of a time-phased plan make it a viable, activities support for (e.g., see development, and model demonstrate training and ef. 58) . To gain management's confidence, to This involves prioritizing independent group. database to repeatably that the cost team must be able the estimates produced are reliable. Because this can only be done using actual return data, the rate that management trust is built-up is highly upon the product cycle. dependent For a very short cycle, this process may take only a few months. For shipbuilding in the USCG, the product cycle is several years, and so many of the makers have yet to go through a ship acquisition present billets. 272 current decision program in their PROBABILITY RESERVE IS SUFFICIENT 100 Nominal cost $330 million + 60 0 33 RESERVE (SM) 60 percent confidence that 10 percent reserve is sufficient Point Estimate with Cost Reserve Probability (Ref. 19) Figure 4.4 273 COST MODEL SELECTION 4.2 a cost model can be divided approach to selecting The into four basicsteps: (1) determining needs (2) selecting candidate models (3) choosing the best model(s) (4) reconsidering the choice The previous sections in this chapter have discussed some of needs that may require the development of a cost the and capability Chapter several existing models have been The choice 3. of the best model(s) discussed in both should consider accuracy) (i.e., (see Table 4.3) and quantitative qualitative estimating considerations. Most can support models limitations of the models a cost estimating are they understood, the if activity used are consistently, and are calibrated for the particular organization. From the various of limited information available on the accuracy costing techniques discLussedin Chapter 3, there is the no evidence to suggest that the existing USCG cost estimating model for new ship costing in the CG. However, it is is not appropriate generally recommended model be utilized: (e.g., see Ref. one as the primary 19), that more than one estimating resource and the (i.e., other(s) for comparison and validation of primary outputs an independent reasonableness check). CER and model development can be done in-house, to an outside source, to or purchased on a time-sharing contracted basis. the front-end resource requirements for in-house and Due outside source development, time-sharing models are becoming increasingly 274 The RCA PRICE parametric cost model is the most commonly It is primarily category. used model in the time-sharing a models. back-up as particularly attractive, used as (i.e., back-up model for validating bottoms-up cost estimates the NAVSEA Code 017 model) and generating internal cost targets attractive features of this model (see Section (Ref. 19). 3.1.5) The include it detail, is applicability. its ability to analyze systems at any easily However, calibrated, and as with any has unlimited costing system technique, and quantity accuracy is dependent upon the quality of level its of input data available. At the present time, the current USCG cost model (see Section 3.1.4), combined with the RCA PRICE parametric model as a back-up seems appropriate for ship estimating in the CG. However, as suggested reconsidered analyzed, any model choice in the four steps above, periodically organizational due to changes structure, experience. 275 in database, should be projects personnel being and CHAPTER 5 CONCLUSIONS AND RECOMMENDATIONS 5.1 CONCLUSIONS discusses some of the technical and study This that considerations can be capability are applicable ship ship new to design. The for the with the costing requirements overlap can techniques The any organization. within established during the feasibility phase of construction estimating must be examinedbefore a cost techniques estimating cost managerial conceptual/exploratory, as well as preliminary phases. of a mission profile translation The into the final ship design necessitates a ship optimization process. Synthesis models one method used to provide the alternative designs are to this produce optimization. Any method generally required the has following common elements; (1) selection of criteria, or measures of merit, that will indicate which alternative ship design is the opti mum (2) development of CERs (3) construction Measures of merit of LCC models can be rated according to military effectiveness, LCCs, or techical design characteristics. The CERs require the determination of ship design, operational factors total ship costs occur which have an effect from inception on costs. to retirement in three distinct phases; R&D, construction and/or LCCs are the and are assumed to investment or acquisition and O&S. This study is primarily concerned with so-called initial 276 investment costs associated with the delivery of the the owner. These include material, labor, for hull, outfit, auxiliary fabrication. n.achinery Economic and vessel to overhead and profit procurement and and production learning effects can have significant cost impacts on final vessel costs. The need for early design definition for new ships has put increased demands for greater costing accuracy at lower levels of design detail. The accuracy skill of the analyst, of any estimate is dependent upon the the quality and quantity of data available and the time available to make the estimate. Results seem to be independent of the costing technique used. 5. 1 Fig. estimating as being supported by a pyramid structure. database design costing effort. transform of Cost Several applicability models cost provide the trends criteria into means cost current may be selected to necessary or any to projected determine single most important factor that determines the is experience. the observation skill Experience can be defined as the knowledge (skill) gained from a period of activity that The The of a cost model for any organization. the analyst training, cost and acquisition defines the foundation for historical estimates. The illustrates the development of high quality of practice, includes and personal participation. key ingredient of experience is allowing the time necessary to gain knowledge. Organizations can assist analysts in gaining this experience by ensuring continuity. This means supporting long-term planning which includes hiring full-time cost analysts, 277 providing lead-in Cost Estimating Building Blocks (Ref. 60) Figure 5.1 278 for new training of documentation additional training personnel, costing techniques and required, as allowing access to necessary documentation within the organization. a skilled cost analyst requires an extensive Even from and; re-calibrate reflect departures are made from large the the trends The more good any data On the other the more accurate the estimate will be. available, if CERs to the the additional information. by established hand, requires collect data; validate it; incorporate it into their ability to: database, Any costing group to base estimates. which database sized database, errors will increase substantially. involved with data collection is the proprietary The poblem for obtaining data from agencies true particularly If outside data is required, your own. this is outside of Of course, of the majority of the information. nature it typically must be paid for. Within organization, any in SWBS format). are way to get information Return content or they can be easily models Cost characterized by technical design estimating new used their data ship during rapid costs useful from individuals, and cost data forms may be intimidating in their surveys and/or gathering Generally, personal interviews to them (e.g., best data and in a form that is must be sent to the costing group, the of to inadequate communications. reduces typically the problem length "buried". studies feasibility turn around time and The five models requirements. construction since costs that were are limited for examined displayed important commonalities in two areas: SWBS weight group 279 incorporating the non-cost parameters for calculating costs, and on costs. It is important to influence of different technologies regardless of the technique used to that all estimates, realize calculate them, are extrapolations from experience. cost Different of view the various model of right or and design (e.g., assumptions can be to give feasibility cost estimates to within 10-20% of All standards). manufacturing expected cannot be regarded as any differences can be rationalized from the point since wrong, estimates the models examined of return costs. However, figures as high as 40% have been suggested 2). see Ref. (e.g., An the with 1ts structure, of adoption available parametric cost model is the commercially associated for consideration important commonality and language approach. Disadvantages include the proprietary nature of these models difficul ty the outputs. RCF The flexibility, of in getting FRICE management model appears terms of its ability have to estimate level of detail with a minimum of required and in their the most confidence to a costs at any data. Combat systems, electronics and machinery were found to have the These cost leverage for construction costs. highest are also very dependent upon the standards to which a ship is designed cost controllable scheduling. single and factor Costs by ship in any ship increase batch productions. influenced fabricated. Possibly dramatically for In addition, quantities and 280 time particular the acquisition costs biggest program multi-lot versus production learning between is is construction starts. There are a number of assumptions made in any cost estimates various being economic, the more managerial, obvious. scheduling, and technical The purpose of risk analysis quantify these effects to produce a range of possible opposed to ones is to costs, as the more traditional point or most likely estimate. Programmatic and schedule effects appear to have the largest cost uncertainty (i.e., risk). estimate costs, people In the final analysis, do, models don't and so there is a highly variable uncertainty associated with the cost analyst. For for a cost estimating group to be able to provide management operates decisions, be: must the committed organization to within maintaining guidance which its it expertise; responsive to its results, and; allow the group to operate within the organization as the need arises (e.g., receiving return cost data). The primary explainable design cost phase discarded; benefits of developing a estimating capability during are that it shows the: lost causes credible the and feasibility that need to be the winners that must be pursed more vigorously, and; the marginal cases requiring more careful examination. 5.2 RECOMMENDATIONS This study has examined a variety of cost models intended for use during the feasibility phase of ship design and some the factors that must be considered to incorporate technique into an organizational structure. found here address costing The recommendations issues of both a technical 281 any of and managerial nature 5.2.1 General Recommendations majority of tl:isstudy deals with the documentation The models now in use for new ship costing. cost instructive It would most investigate the sensitivities and accuracies to manner. models in a more systematic and quantitative these be primary difficulty of of The of this type would be dealing with an exercise with any proprietary model inputs and outputs. This inflation, study discussed the effects of scheduling, input uncertainty, technology, plus a variety of other issues in a rather general sense. examination of any A more exhaUsive and again, quantitative of the topics mentioned within would be enlightening to the cost estimating community. Weight is a primary cost driver for the majority of CERs. For the models considered here, SWBS weight groups are defined as elements with similar trends. cost fabricating techniques producibility methods) applicability of (i.e., on CER the effect of However, zone outfitting and development SWBS cost elements has yet to and other even be on a better the evaluated. Current shipyard accounting practises generally do not use Perhaps new procedure for grouping cost elements SWBS. can be found. Only cost estimating procedures used in the USN and the USCG were discussed here. It may prove extremely seful to look at how other Navies and Coast Guard equivalents have incorporated a cost estimating capability into their ship acquisition difficulty with this suggestion 282 would be the programs. high The travel expenses, since only by personal information be passed along. contact Typically, would any useful this contact would have to occur 3 or 4 times over a 4-6 month period to be effective for establishing a satisfactory working relationship between the persons involved. Because of the amount of information collected from sources and the number of individuals that were various contacted in regards to this work, it represents a "first cut" at establishing some degree of cooperation within the cost estimating community. Perhaps more dialogue work between towards in this area could establish some estimators for selected topics. developing a dialogue is to participate in A sort good of step professional organizations working in related areas of interest. Typically, a cost analysis requires inputs from economists, engineers, managers, important that accountants, analysts learn to plus other estimators. It is communicate with these individuals on a personal basis. Developing people skills will go a long way to enabling a cost analyst to obtain desired information properly prepared and establishing necessary credibility or through presentations (e.g., the use of graphics to explain and examine trends) and discussions. It is important that neither the cost analyst nor management regard cost estimating as a separate function. thought of in a systems integration Costing must approach, since be cost estimators interface with all the functional-type areas mentioned above and operate within the framework defined by the needs resources of their organization. 283 and 5.2.2 US Coast Guard Recommendations The cost survey (see Appendix C) distributed throughout USCG HQ was not successful in determining the cost estimating needs within the Coast Guard. A similar survey should be carried out on a personal interview basis before any further work in this is carried area out. USCG cost estimating operates in the Ship Building Branch of the Office of Engineering. estimating group (i.e., The limited one individual), size of this cost presents several long- term problems, some of which are addressed below. Experience capability be is estimating, impossible. With only continuity one within individual involved this for area in the can cost CG is The only solution to this problem is the addition of The actual needs and projected number can only resources the cost Augmenting personnel requires be documented, be determined by the future for cost estimating. estimating group with the development of a training end, it is recommended that the existing additional program. To this CG costing methodology perhaps in a similar manner to that found in NAVSEA Cost Estimating The estimating and continuity is the method by which experience maintained. personnel. an essential element of any cost Manual the (see Ref. 16). CERs used for costing in the CG are based on a limited database for a wide variety of vessel types. Currently within the CG, the CFPM (Critical Path Method) contractors Network program to supply material and labor cost data broken down by SWBSweight groups. This program should ndoubtably However, requires it would be extremely 284 useful for funding be continued. to be made available for various projects to expand and improve the database. Improvements major could functional include a detailed shopping components and high cost list equipments for such as electronics, which can be non-weight related. There could also be a formal the tracking VAMOSC general of CG operating system and support employed by the USN costs (see similar Ref. 21). Since and administrative (G&A) and shipyard support costs make up a substantial part of the acquistion costs, to can it would be advantageous that they be more accurately known. Feasibility applications should 7) and cost have proven (e.g., see Ref. 27). be models: studies capable model for of Patrol Boat model using vessel model synthesis 15), Goodwin's Cutter model (Ref. 8). In (Ref. addition, outputs should be available for life calculations CS The USCG cost estimating of interfacing with a variety the USN's ASSET (Ref. Tuttle's useful cycle the costing the CG developed CASHWHARS spreadsheet (see Ref. 34). Cost exists method. estimates a capability of cross-checking them using an The development many gain credibility and consistency there independent recommendation in this area is for the simultaneous of another cost model. The RCF PRICE model organizations as a means to provide analysts with a reasonableness check on cost estimates. uses if is used in and In fact, managers Ref. 27 the RCA PRICE model to investigate the cost of several USCG patrol boat quantifying concepts. the Also, for an cost impacts of various 285 increased design emphasis and on technical innovations, the RCA PRICE model may prove valuable (Ref. 46). Ideally, (1) fashions the would operate in the following PRICE model would be run simultaneously to obtain (the differences check knowledge pass CG cost model would be run to get first (including G&A and shipyard support functions); results RCA CG cost estimating should be easily cross- a explainable (3) the contractor of each model); (2) the with would have a expenditure program to enter the shipyard costs, cost and; (4) return from the shipyard would be tracked to obtain a history costs a of the expenditures and to re-calibrate or validate the cost models. This constant becomes an feedback integral is necessary part of construction project. 286 the to team ensure that managing any costing ship REFERENCES 1. Reeves, J.M.L., D.D. Findley and M.A. Logue, 1980. ASSET Theory Manual - Cost Analysis Module. David Taylor Naval Ship Research & Development Center, Technical Director's Technology Application Team, Technical Contribution No. 4, 111 pp. 2. Carstensen, R.V., 1975. Cost Considerations for Electrical/ Electronic System Installation Design. Marine Technology, 12, 378-389. 3. Anon., 1986. Building Canadian F'atrolFrigates, Marine Engineering/Log, 91(4), 33-40. 4. Anon., 1986. A New Approach to Warship Design, Marine Engineering/Log, 91(4), 52-59. 5. Hope, J.P. and Stortz, V.E., 1985. Warships and Cost Constraints. Naval Sea Systems Command. 26 pp. 6. Mills, J., Feasibility Studies and Ship Synthesis Models. Lectures 7,8,9. Unpublished lecture notes, Professional Summer at MassachuLsetts Institute of Technology. Cambridge, MA, 112 pp. M.J., 1975. Ship Synthesis Model for Coast Guard Cutters. Ocean Engineering Thesis, MIT, 278 pp. 7. Goodwin, 8. Tuttle, J.G., 1981. Synthesis Model for Ocean Going Boats between 5C) and 150 feet in Length. Ocean Engineering Thesis, 323 pp. 9. Maritime Administration (MARAD), 1986. Relative Cost of Shipbuilding, U.S. Department of Commerce, Washington D.C. 10. 11. International Maritime Associates, 1977. A Study of Ship Acquisition Cost Estimating in the Naval Sea Systems Command. Washington D.C., NTIS AD-A046 978. Shipbuilders Council of America, January 1986 Statistical Summary, 12. Flanagan, Washington D.B., D.C., 2 pp. 1969. A Cost Estimating Procedure Recommended for Coast Guard Cutters. Unpublished Report, Naval Engineering Division, Office of Engineering, US Coast Guard. 13. Turner, D.K., 1978. Marginal Cost Factors for High Performance Ships and their Impact on Subsystem Design. Ocean Engineering Thesis, MIT, 192 pp. 287 14. Brennan, A.J., J.D. Burroughs, D.H. Wacker, 1976. HANDE - A Tool for Integrating the Hydrofoil Preliminary Design Cycle, SNAME, Pacific Northwest Section, Salishan, Oregon. 15. Greenwood, R.W. and Fuller, of a A.L., 1986. Development Common Tool for Ship Design and Technology Evaluation. Presented at SNAME (New England) Symposium "Marine Computers 1986, Boston, MA, 24 pp. '86", 17-18 April 16. NAVSEA Ship Cos t Estimating. Entry-Level Shi Proceedings of A Reference Document for the p Cost Estimator. Naval Sea Systems Command, Washington, D.C ., 30 September 1986. 17. The International Society of Parametric Analysts (ISPA) , Fifth Annual Conference, St. Louis, Missouri, April 26-28, 1983. Vol. II, No. I, 502 pp. of The International Society of Parametric Analysts (ISPA), Sixth Annual Con ference, San Francisco, California May 15-17, 1984. Vol. III, No. I, 751. pp. 18. Proceedings 19. Proceedings of The International Society of Parametric Analysts (ISPA), Eighth Annual Conference, Kansas City, Missouri, May 12-15, 1986. Vol. V, No. I, 607 pp. 20. PRICE Systems User's Reference Manual, RCA PRICE Systems. 21. Visibility and Management of Operating and Support Costs Ships (VAMOSC - Ships), Total Support System Report, Fiscal year 1985, DD-I&L(A R)1422(SHIF'PS 5200), March, 1986. 22. Accelerating Utilization of New Materials. Prepared by The Committee on Accelerated Utilization of New Materials, National Materials Advisory Board, Division of Engineering National Research Council. Publication NMAB - 283, National Academy of Sciences, Washington, D.C., May 1971. 23. Cost Model U.S. Naval Vessels (Destroyer-type) Final Report. Prepared for Office of Naval Research, Contract No. N00014-80-C-0950. 1981. 24. Shipbuilders Prepared by Gibbs & Cox, Inc., August Council of America, Statistical Quarterly, Third Quarter, 1980. 25. Salmon, C.L. and A.J. Locke. The Application of PRICE to Ships and other Large Structures. J. of Parametrics, Vol. II, No. 3, Winter 1982-83, pp. 11-17. 26. Jones, R.R., D.L. Mayo, and D.J. Clark. the RCAPRICE Hardware Parametric Vehicles, 66-89. The Application of Cost Model to Air Cushion J. of Parametrics, Vol. 5, No. 2, June 1985, pp. 27. Jeffers, M.F., and R.R. Jones. A Comparative Cost Analysis of a Hybrid Ship Concept for the Coast Guard WPB Mission. Ship Systems Integration Department, Departmental Report, DTNSRDC/SSID/87/DRAFT, January 1987. 28. Walsh, S.P., 1985. An Improved Method of Risk Analysis for the Naval Ship Design Process, Ocean Engineering Thesis, MIT, 88 pp. 29. Hutchison, B.L., 1985. Application of Probabilistic Methods to Engineering Estimates of Speed, Power, Weight, and Cost. Marine Technology, 30. Vol. 22, No. 4, pp. 358-372. Byington, J.A., 1985. The Estimating and Administration of Commercial Shipbuilding Contracts. Marine Technology, Vol. 22, No. 3, pp. 286-292. 31. Black, R.L. and J.J. Wilder, 1984. Determining Cost Uncertainty In Bottoms-up Estimating. J. of Parametrics, Vol. 4, No. 2, pp. 51-64. 32. Black, R.L. and J.J. Wilder, 1982. Probabilistic Cost Approximation When the Inputs are Dependent. Parametrics, Vol. 2, No. 1, pp. 3-8. J. of 33. McNichols, G.R. (editor), 1984. Cost Analysis. Operation Research Society of America, Arlington, Virginia, 332 pp. 34. Sappern, A.S., S. Kimbrough, C. Pritchett and T. Coe, 1986. CASHWHARS - Wharton Cash Flow Analysis Model, Version , 1 July 1986, USCG R&D Center, Avery Point, Groton, CT, 44 pp. 35. Moy, J., J. Vail and S. Williams, 1973. Marginal Cost Analysis of Major Ship Design Parameters for DG Shipborne System Trade-Off Studies. Prepared for Naval Ship Systems Command, PMS 305, Report No. 6112-74-3. 36. Judge, S.D., 1985. Minimizing Ship O&S Cost. SNAME Hampton Roads Section Paper, December 5, 1985. 37. Mauro, C.V., 1985. The FAST-E Cost Estimating Model. J. of Parametrics, 38. Vol. 5, No. 1, 87-102. Fetchko, J.A., 1968. Methods of Estimating Investment Costs of Ships, Department of Naval Architecture and Marine Engineering, University of Michigan, Ann Arbor, Michigan, June 1968, 201 pp. ;9. Landsburg, A.C., 1982. Interactive Shipbuilding Cost Estimating and Other Cost Analysis Computer Applications. Presented at the IFIP/IFAC Conference "Computer Applications in the Automation of Shipyard Operation and Ship Design", US Naval Academy, Annapolis, MD, 7-10 June 1982. 289 40. Landsburg, A.C., A. Jenks, S. Lee and E.B. Schimler, 1986. Analysis of Japanese and Korean Shipbuilding Prices, SNAME Chesapeake Section, June 18, 1986. 41. Jenks, A. and J.E. Larner. A Tanker Owner's Perception of Newbuilding Costs and Prices in Japanese, North European, and United States Shipyards 1971 to 1981. Tanker Department, Exxon International Company, Florham Park, NJ. 42. Carreyette, J., 1978. Preliminary Ship Cost Estimation. Transactions of the Royal Institution of Naval Architects, Vol. 120, 235-246. 43. McNeal, J.K., 1969. A Method for Comparing Costs of Ships Due to Alternative Delivery Intervals and Multiple Quantities, SNAME Transactions, Vol. 77, 71-103. 44. Shafer, W.J.E., 1983. Cost Estimating Relationships for US Navy Ships. IDA Faper P-1732, Prepared for Office of the Under Secretary of Defense for Research and Engineering Special Ass tant for Assessment. 45. Leopold, R., O.P. Jons and J.T. Drewry, 1974. Design-to-Cost of Naval Ships. SNAME Transactions, Vol. 82, 211-237. 46. Spaulding, K.B., 1984. The CONFORM Program - An Update, Naval Engineering Journal, Vol. 96, No. 3, 94-110. 47. Rawson, K.J., 1973. Towards Economic Warship Acquisition and Ownership. Trans. Royal Institution of Naval Architects, Vol. 115, 43-56. 48. Keane, R.G., W.C. Sandberg, 1984. Naval Architecture for Combatants, A Technology Survey. Naval Engineers Journal, Vol. 96, No. 5, 47-64. 49. Kehoe, J.W., K.S. Brower, H.A. Meier, 1982. The Impact of Design Practices on Ship Size and Cost. Naval Engineering Journal, Vol. 94, No. 2, 68-86. 5C. Dart, C.E. 1970. Cost Estimating - Ship Design and Construction. University of Michigan. Department of Naval Architecture and Marine Engineering. No. 082, 61 pp. 51. Summers, L.S., 1973. The Prediction of Shipyard Costs. Marine Technology, Vol. 10, No. 1, 8-15. 290 52. Kazek, M.S., 1985. A Comparison of Offshore Patrol Vessels. Marine Technology, Vol. 22, No. 4, 351-357. 53. Whitlock, R.D., 1982. Estimates Curves. Journal of Parametrics, 54. Advanced Naval Vehicles Concept Evaluation (ANVCE) Final Report, CNO (P-96), December, 1979. 55. Daschbach, J.M., K.F. Matta and W. Frank, 1983. Regression in Parametrics: Estimation versus Prediction Errors. Journal of Parametrics, Vol. 2, No. 3, 3-8. 56. Moy J. and J. Vail, at Completion Using Beta Vol. 2, No. 2, 15-18. 1974. CV Ship Acquisition Cost Model, Final Technical Report. NAVSEC Report C-6113B3-75-15, October 1974. 57. Starrett, C.O., 1982. Parametric Cost Estimating - An Audit Perspective. Journal of Parametrics, Vol. 1, No. 4, 3-5. 58. Cost Analysis Capability at NUSC. Report of the Work Group Session 15-17 August, 1984. Encl (3) to MAT-01F41 memo 5050 Ser 01F41/410 59. Jeffers, M.F., The Costing and Design Systems Office at David Taylor Naval Ship Research & Development Center. PRICE Presentation to NAVSEA Cost Engineering Task Force, 21 August, 60. of 28 Sep 1984. 1986. Unpblished material. Costing and Design Systems Office, Code 1204, David Taylor Naval Ship Research and Development Center. 61. Gaffney, R., 1980. Avionics Software Parametrics, Vol. 1, No. , 26-30. 62. Unpublished material. Cost Estimating and Analysis Division, SEA 017, Naval Sea Systems Command. 63. Unpublished material. Ships Cost Analysis Division, NCA-2, Naval Center for Cost Analysis. 64. Breiling, R.W., 1984, Parametric Cost Estimating and the PRICE H Model. Presentation to Graduate Program in Technology Strategy and Policy. oston University, October 4, 1984. 291 Costing. Journal of APPENDIX A SWBSWeight Group Keys for Costed Military (Ref. 292 1) Payload SWBS Weight Group SWBS Group Name 410 Command and Control Systems 440 Exterior Communications 450 Surveillance Systems (surface) 460 Surveillance Systems (underwater) 470 Countermeasures 480 Fire Control Systems 490 Electronic Test, Checkout and Monitoring Equipment 498 Command Surveillance Operating Fl uids 710 Guns and Ammunition 720 Missiles and Rockets 750 Torpedoes 780 Aircraft Related Weapons 790 Special Purpose Systems F21 Ship Ammunition F22 Ordnance Delivery Systems (Ammo) F23 Ordnance Delivery Systems F24 Ordnance Repair Parts (Ships Ammo) F25 Ordnance Repair Parts (Ordnance Delivery Sys. Ammo) F26 Ordnance Delivery Systems Support Equipment F60 Cargo 293 B AFPENDIX ASSET KN Factors for SWBS Groups 100 - 900 (Ref. 294 1) KN VALUE _ 1.000 SUGGESTED APPLICABILITY IN ANVCE INTERPRETATION __ Mild/HT steel displacement FFG7 MCM VSS hull with aluminum deckhouse 1.570 Mild steel plus 25% HY-80 monohull with aluminum deckhouse SWACVN 2.191 Conventional aluminum hull CPICX LCPC PCI SWA4 ACVI HYD7 LSES SESCV ACV3 HYD2 HOC LCAC PHM SES3 SESCVN 5.586 DATA BASE CASES USED FOR KN HT aluminum hull MONO3 DE 1040 SWATH DE DEI 0S3 PF 109 DDG 2 DLGN 35 DLG 12 DLGN 36 DLGN 25 DLGN 38 CPIC PGG I(P) PG 92 PGG PGH I DBH PCH I 2K SES(R) AGEH I 2K SES(B) DE 1037 (T) CASES NOT USED DLG 16 SWATH MCM JEFF A HULL STRUCTURE (SWBS 100) GROUP KN VALUES 295 DLG 26 PGH 2 JEFF B PG 93 PHM I ARCTIC SEV KN VALUE INTERPRETATION -- ---------1.000 CODOG/CODAG power plant, SUGGESTED APPLICABILITY IN ANVCE CPICX LCPC ACV3 HOC PHM HYD2 LSES SES3 DATA BASE CASES USED FOR KN CPIC PG 92 PGG (T) PGH I PHM I 2K SES (B) PGH 2 DBH PCH I 2K SES (R) DDG 2 DLG 12 DLG 16 MONO3 PF 109 SWATH MCM SWATH DE SESCV JEFF A DLGN 35 DLGN 36 high speed marine propulsors and straight drive train 1.502 GT/CODAG power plant, high speed marine propulsors and right angled drive train 1.979 Steam turbine power plant, low speed CP propeller and long shafts 2.345 GT power plant, low speed CP propeller and reduction gears, with special arrange- HYD7 PCI - FFG7 VSS MCM SWA4 ments as in SWATH 3.280 GT power plant with complex drives ACVCI LCAC SESCVN 3.436 Nuclear steam pressurized water reactor power plant, low speed FP propellers, straight drive train SWACVN DLGN 25 DLGN 38 CASES NOT USED DE 1037 DLG 26 AGEH I PROPULSION (SWBS 200) GROUP KN VALUES 296 DE 1040 PG 93 JEFF B DE 1053 PGG (P) ARCTIC SEV KN VALUE SUGGESTED APPLICABILITY IN ANVCE INTERPRETATION 2.036 3.719 __ __ -_ 1.000 DATA BASE CASES USED FOR KN Conventional 60 HZ power, steam or diesel generator drive CPIC FFG7 MON03 SWACVN Conventional 60 HZ power, light diesel or GT generator drive HYD7 HOC LCPC PCI Very low 60 HZ or mixed SES3 SWA4 ACVI PHM MCM LCAC SESCV DE 1037 PF 109 DLG 16 PG 92 DLGN 25 DLGN 38 DE 1040 DDG 2 DLG 26 PGG (T) DLGN 35 SWATH MCM CPIC PGG I(P) PGH I AGEH I PGH 2 DBH PCH I 2K SES (R. PHM I JEFF B SESCVN VSS 60/400 HZ, GT generator drive 12.684 All 400 HZ, GT generator drive CASES NOT USED PG 93 ELECTRIC PLANT (SWBS 300) GROUP KN FACTORS 297 JEFF A DE 1053 DLG 12 DLGN 36 SWATH DE KN VALUE INTERPRETATION SUGGESTED APPLICABILITY IN ANVCE 1.000 Simple control systems, minimal electronics CPICX 3.153 Modest control systems, sophisticated electronics FFG7 SWA4 6.906 Complex control systems, sophisticated electronics weight critical ships ACVI ACV3 HYD2 HYD7 HOC LCAC LSES PHM SES3 SESCV SESCVN LCPC PCI MCM MONO3 SWACVN VSS DATA BASE CASES USED FOR KN DE 1037 DLG 12 CPIC DE 1040 DLG 16 PG 92 DE 1053 DLG 26 PG 93 PF 109 DLGN 35 SWATH MCM PGG (P) DLGN 36 SWATH DE DLGN 25 DLGN 38 PGH I PHM I JEFF A PGH 2 AGEH I JEFF B PCH I DBH ARCTIC SEV CASES NOT USED DDG 2 2K SES(B) COMMAND AND SURVEILLANCE 298 (SWBS 400) GROUP KN FACTORS PGG I(T) 2K SES(R) KN VALUE SUGGESTED APPLICABILITY IN ANVCE INTERPRETATION 1.000 Steam propelled displacement ship 1.528 GT propelled displacement 4.161 5.370 DATA BASE CASES USED FOR KN DE 1037 DG 2 DLG 26 DE 1040 DLG 12 DE 1053 DLG 16 CPICX FFG7 LCPC MCM MONO3 PCI SWA4 WACVN VSS PF 109 PG 92 DLGN 25 CPIC PGG (T) DLGN 35 PG 93 PGG (P) DLGN 36 Fully submerged hydrofoils HYD2 HYD7 HOC PCH I AGEH I DBH Air cushion vehicles ACVI LSES ACV3 SES3 LCAC SESCV JEFF A 2KSES(B) ship ARCTIC SEV 2K SES(R) CASES NOT USED PGH I JEFF B AUXILIARY SYSTEMS (SWBS 500) GROUP KN FACTORS 299 PGH 2 PHM I KN VALUE INTERPRETATION 1.000 Conventional displacement ship 1.857 Weight critical ship DATA BASE CASES USED FOR KN SUGGESTED APPLCABILITY IN ANVCE CPICX MCM SWA4 LCPC FFG7 MONO3 PCI SWACVN VSS ACVI HYD7 LSES SESCV HYD2 ACV3 LCAC HOC SES3 PHM SESCVN DE 1037 PF 109 DLG 16 PGG (T) DOGN 35 SWATH DE DE 1040 DDG 2 DLG 26 PGG (P) DLGN 36 PGH I PHM I 2K SES(R) PGH 2 AGEH I 2KSES(B) DE 1053 DLG 12 CPIC DLGN 25 DLGN 38 PCH ARCTIC SEV CASES NOT USED PG 93 DBH OUTFIT AND FURNISHINGS (SWBS 600) GROUP KN FACTORS 300 PG 92 JEFF A SWATH MCM JEFF B KN VALUE 1.000 3.401 SUGGESTED APPLCABILITY IN ANVCE INTERPRETATION Conventional Weight critical armament displacement ship, light ship CPIC MCM SWA4 ACVI HYD7 LSES SESCV FFG7 LCPC MONO3 PCI SWACVN VSS ACVC3 HYD2 HOC LCAC PHM SES3 SESCVN DATA BASE CASES USED FOR KN DE 1037 DDG 2 DLG 26 PGG I(T) DE 1053 DLG 12 CPIC DLGN 35 PF 109 DLG 16 PG 92 DLGN SWATH .MCM PGH 2 DBH SWATH DE PCH I 2KSES(B) PGH I PHM I 38 CASES NOT USED DE 1040 DLGN 25 JEFF A 2K SES(R) ARMAMENT (SWBS 700) GROUP K N FACTORS 301 PG 93 DLGN 36 JEFF B PGG (P) AGEH 1 ARCTIC SEV KN VALUE -- INTERPRETATION SUGGESTED APPLICABILITY IN ANVCE DA'rA BASE CASES USED FOR KN ;-- __ 1.000 Foliow ship before 2.881 Follow ship, 1970 and after 12.888 Lead ship, unsophisticated weapons CPICX MCM LCAC 26.064 Lead ship, sophisticated weapons ACVI HYD2 LESES PHM SESCVN VSG ACV3 HYD7 MONO3 SES3 SWA4 DE 1037 DODG2 PG 93 SWATH MCM DE 1040 DLG 12 PG 92 DE 1053 DLG 16 DLGN 25 LCPC PGG I(T) PGH I AGEH I JEFF B 2D SES(B) PGG (P) PGH 2 DBH ARCTIC SEV SWATH DE PCH I JEFF A 2K SES(R) FFG7 PF 109 PHM 1 1970 HOC PCI SESCV SWACVN CASES NOT USED DLG 26 DLGN 38 INTEGRATION/ENGINEERING 302 (SWBS 800) GROUP KN FACTORS CPIC DLGN 35 KN VALUE 1.000 4.254 INTERPRETATION Simple tooling, limited trials Complex tooling, extensive trials SUGGESTED APPLICABILITY IN ANVCE CPICX LCPC ACVCI ACVC3 HYD2 HYD7 LCAC LSES MONO3 PCI SES3 SESCV SWA4 SWACVN DE 1037 FFG7 HOC MCM PHM SESCVN VSS DATA BASE CASES USED FOR KN DE 2040 DDG 2 DLG 12 CPIC PGG (P) DLG 16 PG 93 AGEH 1 DLG 26 PGG 1(T) PF 109 DLGN 36 PHM I JEFF B DLGN 25 DLGN 38 DBH 2K SES(B) DLGN 35 SWATH DE JEFF A CASES NOT USED DE 1053 PGH I ARCTIC SEV PG 92 PGH 2 2K SES (R) SHIP ASSEMBLY AND SUPPORT SERVICES (SWBS 900) GROUP KN FACTORS 303 SWATH MCM PCH I APPF'FENDIX C COST ESTIMATING SURVEY The survey is designed to examine the perceived needs of any individual who must answer the question; "How much will this cost?" This is meant to include all levels of management involved in any type of ship acquisition program, from concept design through to production, and into operations and support, as well as official cost estimators. I hope to accomplish two tasks with this survey. The first is to develop an awareness of the different cost estimating needs that occur throughout the various phases of a ship's life. The second is to attempt to match these needs with the characteristics of different cost estimating techniques. In other words, to improve the responsiveness of cost estimating models to user expressed needs. questionnaire The hand column costing have is divided into two columns. is for any individual who perceives information and the le-t hand column is for used any sort of cost estimating 3 (I 5 The right a need for technique. people ship who NEW SHIP COST ESTIMATING SURVEY NAME .......................... ... RANK ......... PHONE .............. POSITION ............................ DEPARTMENT ............................. PLACE OF EMPLOYMENT ....................... · · · · · COST MODE[L PERFORMAN CE YOUR FUNCTION ................... ~~~~~~~~U·ff··l··ll ~ · · · ~ · l ll··1·····l···l· USER I MPORTANCE Name of cost model (e.g., ASSET, II RCA PRICE,...) Under the following headings indicatethe cost-related informat ion that is incorporated into your cost model and how this is done. Under the following headings, 1indicate the cost-related information you feel should be incorporated into a cost model and any ideas of how this can be accomplished. Technology (e.g. ,technology available, state-of-the-art desi gn . . . · · · · · . . . · · · · ·. · · · · mwll·wll·.mmmmm····!·~a.#··mm··!· ·m.m. m··m····l··w··laam···l·m···m·l·m·····~·· influences, . . . . . .m...mmm..· . . . . . . . m.m....m... . . . . . Design ship configuration, (e.g., weight, margins, design standards & practices, component/suLbsystemselections,...) IM····w·mlmmmmmmmm·&C Manufacturing (e.g., construction method, degree of automation, too learni ng,. i ng, . . . .. . . . . . . . . . .. ... . . . . ..... ... .. . . .···m· . . . Programmatic (e.g., type of a......... ........ .......... · · ·· · · · · i· · ·· · · · · ··· ··· · · · ,· · · · i · m·· · · ·J··,,·· ,·w· · m·mm ng j . . .. . orders I contract, competitions, scheduling, cost of change ..................................... ................. .. . . .. . . . .. ·m · · . . . . . . . · · · . . . . . . . i/imii . . .. . · iili·i . . .. . COST MODEL PERFORMANCE USER IMPORTANCE Economic (e ?.g., escalation, inflation rates, discc)unting,... . . . .. . . . .. . . . . .. . . .............. . . . .. . . . .. . . . . .. . . .. · · ·........ · · · · ·.. · Cost Breakdown (e.g., nonrecurring, direct,... ) . . . .. . . . .. . . . . . .. . . . .. . . . . . . ................. . . ................. Operations & Support (e.g., maintenance scheduling, reliability, m odu lari ty,...) . . . .. . ................ ... . . . .. . ·... . .... ·· mmm·. · . ................. Other I ..................................... I ....................................... I I I For the following features, use performance ratings from 1 to 10 (1 for total disagreement; 10 for For the following features, use importance ratings from 1 to 10 (1 for "nice to have"; 10 for extremely extremely important) I mportant) ........ Minimal training is required to use the model .............. ..... ...... The model can be calibrated using return data ..........I..... ..... . The model is based on data reflecting the latest technology ....... . : The model is able to ..... .............. (a) generate internal cost targets ................... .....t........... (b) prepare planning/budgetary estimates ................ ..................... (c) perform trade-off studies ....................... ..... .............. (d) validate outside industry bids ................... The model is able to provide estimates starting in the .... I................... conceptual design phase .................... ..... ... The model is easily accessible at reasonable cost ........... ft....... ..... .. The model is developed in-house and can be easily modified ....... I The model gives an accurate estimate of I .(a. ................... (a) construction costs .......................... . ................... .... (b) programmatic costs ..................... I..... .. . ...................... (c) life cycle costs ........................ I The model is available to agencies/individuals I i..................... with a need to know .......................... 1 Other f · · · · · ·· · · · · · ·. · · · · · · · · · · · · · · · · ft · ___ USER IMPORTANCE COST MODEL PERFORMANCE Indicate an approximate accuracy (as a percentage) for your cost model during concept/preliminary design for construction costs (a) life cycle costs other (c) (d) .. Is (a) construction costs ...... (b) programmatic costs ...... ...... (c) life cycle costs programmatic costs (b) t Indicate your required accuracy (as a percentage) during concept/ perliminary design for (d) other ......... :here an area where the model wel 1? perf orms especially ................... .............. ................... .............. Is there an area of cost estimating parti cular that you feel needs attention? ........ 0. ... ....e , .... ............ ............ What is your definition of well? ..... ................... Is t here perf orms ............ .............. an area where the model poorly? Whatis the reason(s) that this is so important? .............. .............. What is your definition For what phase(s) acqu isition appl icable? ................... . . . . of a of poorly? For what phase(s) of a ship acquisition program are you most ship is this model program interested in receiving costs for? .................................... · · m· mlmwmm.·e .................................... ................... ................... .............. 3(-)8 . APPENDIX D SWBS GROUP BREAKDOWN FOR THE NCA TWO-DIGIT COST MODEL (Ref. 1) Cc6T GUUOP: Sd S N. IA DESCRI PION I - --111 1 113 SHELL PLATING, SURF. SHIP AND SUBMARINE PRFSS. HULL ILNNERBO1 SHELL APPENDAGES STANCHIONS I'T. FRAMING, SURF. SHIP AND SL4ARINE LI T 114 115 116 PRESS. IlI.L 117 121 122 123 124 131 132 133 134 135 141 142 14 3 144 145 149 166 TRANSV. FWAMING, SURF. SHIP AND SMARINE HUI.L LfCI'IJUDINAL SI'HUK'UM1AI,HULIIH'ADt TRANSVERSE STRULXRAL BUIIHEALk 'TRuNKS ND ECIOSURES SYS'I'TE BLULKIIEADSIN 'IORPEllU tlI'EC'I'IN MAIN LECK 2NL DECK 3RD EC'K 1 4'1i ACK 5' 11t DECK AND L*.CKb L-L w I 1S' PLA'FtrU)t ND PIATFI 31)WPLA'I'tU 4''11 PIA'rt'O1 PIA'I'CF@ 15i I ILA'S S1t s C'OSTGRfJUP: _ N.)S _ _ IF-(:RI l'I(N I '1n) Fi{Rr 151 DECKHOUSESTRU'IJ 152 lSF 153 2ND DECKHOUSE EVEL 154 155 156 157 158 159 164 3RD DECKHOUSE LEVEL 4'TH Lt;CKHUSE LEVEL 'LEAVEL 5'THlCKHUSE b'IT DCKHOUSE LEVEL 7Trl UECKHOUSELVEL, MTtH DECKHOUSELEVEL AND AOVE LAI.ISTIC I'IAT{M(; [ECKOUSE EVEL 310 [LVE[, PRESS. cOST GRmUP: !( . ND. SWS - -- -L-- _ _ _ _ _ I--- _ _ _ _ Mt2SCRIrli I------1 1 182 PROPULSION PLANT FOINTIONS 183 ELECTRIC PANT -r IIDATIONS 184 CMAM 185 AUXILIARY SYS'I'ItS 186 OUIFI r AN 1 187 CUS GROUP: S N Nt. -I f I 1 FDATICS F'lNISIINGS RrATI4S AJmwwrFUNT ID I' 'l(IN EtlIV. A FOImN;S, STRUL'iRAL CASrNrG, WEI 1EMS STACKS AND MKS (MBINED STAC'KAND)MAS') SEA CSTS 16,' 165 .JNDATIONS t I*-' I 162 AN) SURVEILIANCE FOUNDATIONS 1 S(AR LX1)E I 167 168 169 1 IULL SI1UCTIAL CLL6URES C)SlUES DECKUSE bSTrHULI'IJHAL SPECIAL PURI4SE CLlUHkES A) sL,''RWnJi;S 171 1MASTS, lOWERS, 1VrRAOw 172 KINGWSIS AND sUP*r 311 FWVtES ca'r GFUP: E. -bS 2A _ _ I I r I*.SCHI I _ I PR[PULSION BOILERS CAS CENERATIDRS MAIN PROPULSION BATTERIES MAIN PRPULSION FUEL CELLS PRPULS ION SEAM JB~ [NES PROPULSION STEAM ENGINES PKPULSION II'ERNAL CBI3ULSTICNENGINES PROPULSION GAS TURINJES 221 222 223 224 231 232 233 234 235 236 237 241 242 ElICTRIC PPUI SIC1J 1 1 1 POUISION SEIF--CCWNTAINED 1 253 254 255 ! PIUPULSION CWLI'IES AND CUPLI NGS MAIN STEAM PIPING SYS'" JLz'IDRS C(NDENSFRS AND AI FEE) AND LCD0*NSA'I'ESYS'IlT -Sc-). ---- ------ c~zcr GI&JP: A3 SWS N) - I*.SC'RIPION 243 PFDPULS ION SAFrING 244 PRPULSIO 245 PIRPUISORS 1 246 CT' GI4_IP: S4US NJ. _ 251 259 _ SYSTEMS AUXILIARYPULSITON LVICES PIOlUIS (IN RFIXI'I(N CARS SHAFT BEARINS PROPULISORSIfOU AND FIKIIS 2C DESC' I I'ION I I 7 1 1 I CBLUSTIOI; AIR SYSTEM UI'AKES (INNER CASING) 312 C6' GINUP: 2D ). SWBS DESCRIPIrILON 252 256 258 261 262 264 ! C6T Cl EIP: SYSTFPI PIROPLISIOCNOIR')L CIC(JIATING AND C(XtiNG SEA WAI'FR SYS1EM H.. I sP. I DRAIN SYSTEM P'JEL SERVICE SYSTlEIS MAIN PRORII.SION 11JUE OIL SYSTE]U 1BE Oi)1. FllI., TANSPER, A%%)RHIFICATI(ON A SWi3SN. IESC'RIPFr(N I 311 SHIP SERVICE K)WER NERA'rON 312 3 14 FMF; I(M'Y }$' LRA 6H [A4Eu (ONVEIk'IN WI1[[ 34 341 ssr 111fBE0II. [ED ESEI:. SUtlq)!el' SYSTE'MS 342 34 1 TIRDBINE :;bl'l")I'r 711' .'YS'I'.IIS Cor GWPP: AI-SI3S ). | Fl:RPI'(N 313 321 I 1 3ATIERIES A SERVICE FACl, I''IrS SHIP SERVICEt iWEtH CAbk 322 323 324 I IME Y CAS:AIrY 9./I'CHEA PowE.R CABIE SYSr iJH CABLE SYSIAW AND PANUE5S 331 IUlTING DIS'TRIBUION 332 I,IGHTING FIJUES I 313 COiT GIP: S 4A N. .. I [ESCRIPrN -I _______ I 421 422 423 424 426 427 . 1 j 428 NAVICATION QaNfL P 431 SWITH0AR3S 432 TELEPHONE SYSTet4S 4 33 4 34 / FO IIT0RING I.C. SYSTEMS IUAO ING SYSTEMS E24lTERtAII#METAD TRAINING SYSTEMS 4 35 4 36 O)ICE 'IUBES AND MESSAG PASSING SYS['EMS ALARI, SAFETY, AND 'ANING SYSTIS 4 37 INDICATING, ORDER, AN) METERING SYSI'S 438 INIT'ATED (XTKUL SYSTEMS 4 39 443 47 3 474 475 RECODING; AND TE'lVISION SYSTEMS VISUAL AND AU)DIBLESYSrEMS 'IOPEDO DECOYS DECOYS((mTER) L)XAL SI;NG j 476 491 492 491 494 495 MINE OITE EASURES EILECRNIC TESr, clECKrI., AND MWIITKRING UrEN I FtIITXr fIL AND NSTRLN4r [LAN)ING SYSTEMS IJN C3BAT IIATA PECXESSIt; SYS"IS METIEX* G(AI, SYS]S SPECIAL, FPRI~JH E INEILLI[(;Ei'E SYSTEMS I I (-D''GRUP: S4WtS ). _ _ _ _._ I IESCRIPrI(N 412 i 1 413 414 415 417 441 !)IGIAL UATAWI'1tHCI 1 NII'EHFACEtJIiIN IGTrAI. IATA lMINICA'rI(*; 1 (A.MN) A I rl)a). ANAL-X; .'14I'1 HA)IO SYS'r24S 411 LATA DISPLAY (JP ArA PX'FSSING c1P 1 442 UNuLwUA'rESYS:rS 444 445 446 451 452 4533 454 TEIM4T1UY 7 SYSI'11; 'I1Y AN) FSIMILE SYSTE4S StUH IrY EIU I1wT SYSl'EMS SUfA(': SEAI' HAIt AIR StAA'II UiAR (21)) AIR SFARCH FADAR (JD) AIRCHAIT' CINI L APPIACII FIIR 455 456 459 461 462 463 464 465 471 472 481 482 483 484 489 . NoEL-EW ICAI/ELTELMNIC NAVIGATION AIS ELECTRICAL VIGATION AIDS (INkL NAVIG. L(;rrS) EIlXTR IC NAVIGATIONSYSrt-S, ADIO ELETNIONIC VIGATION SYSTEMS, UCIurlCAL EIEC'ICAL NAVICATIO SYSTEMS INERIrAL VIGA'ION SYSTmS 1 g 1 II*NIrIlA'IIlJN SYSI.S M IRSi (IFF) MUL'I'IPLE MI: RAIAR SPACE VEIItL'IE EL1tIIC TRACKING AL'i VE R PASSIVE SINAR !MULTIPLE MODE CLASSIt'CA'I'l(IN 9UNAR BA'THI'HEWOAPH ACriVE L (INCI. C}MINATION ICIVEPASSIVE) PASSIVE; EL GUN FIRE OIWrDL SYSTEMS MISSILE FIRE XOtCN~LSYSTEMS UNElWATEH FIRE 'll SYSTEMS fInX;Ai'rE) FIRE aWlUL L SYSrtMS WEAF)N SY:.ruS 11'ICIti 314 OaTG CGRUP: 5A 1 e3S W). --- - I --- -- _7- ITESTRIPrl(N 511 CEATIG SY I 511 Ct"lIPARWIT/ 512 ITING SYSIEM VENTILATION SYSTW 513 514 MACIINERY SPACE V2TIIATI'N 516 SYSiTE: AIR CTrITlDIlING REt RIGl-ATI'N SYSTrEM ILERS AND CMIER HEAT AUXII,IAHY 1 517 Cwr GiirJP: SYSTEI J'KHES 58 --- SS I). I DECRIPrl(N 521 522 AND FUISIIING (SEA WATER) SYSTEM FIRiA[N SPR I NKLER SYbSl'E 52 3 WASIfUX) 524 526 AUXILIAHY SEA WATER SYS'I:M SCUPPERSAND IXK LIAINS 527 528 529 FIEMAIN _YiIATED SERVICES - (HE PIJMBI NG DRAINAGE I)HAINA(E AO 3AIJAS'ItNG SYSTE4 5 31 5 32 PIANT I)ISTIIJING XCI).ING WA'IEH 533 534 5 35 536 541 542 F frA8LE. WATER AUX. SEA AllD IRAINS WITlHIN MACHINERYBOX AUX. STF Am1 RAINS OUISIDc MACHINERYBOX AUXII,IARY t'ThSH WA'rR cXof.lNK SYSTE SIIIP lEl, ANM)FtJEL (XI1'TSArING fW24E FUELS AVIATION AN{)(t,NIAI. 1 1 543 SYb'ti AVIA'l(iN A u-ER AL PuHH6E I HI(A'rPING OILL, 544 545 549 551 LIQUID CAFUD TANK HEATING SPECIAL FELL AND)LLURICANIS, 10N)ILING A) CTIPRSSED AIR SYSlEMS 552 S53 (CIPRESSEL GASES 0o2N SYST:1 554 IP 8BU 'IE 555 556 557 558 565 593 594 SInVA.R EXTXrIN;ISiiINL; SYSTIES IIYIJRAULIC FWII) SYSTI LIQUID GASES, CAlML SPECIAL PIPING SYSIEWS AND IEEL SYSTE4S (SURFACE SHIPS) 'IN . NVIKOEJrAL R)UA'ION (XNrR)L SYSTEIS ISUUIINE ESCUE, SALVAGE, A) 315 SURVIVAL SYSTEMS --I----GaEJP: CT 4SNO1C. 5C' *CIr I 561 562 568 1 SiTERING AND DIVING (fl", RII)ER MANEUVEING SYSTIMS CLIT GItUP: 50 57 IF RE 9-- -571 --A I SYSTiMS YS I-c;CRREPLENISlIt4MI'-Al-SEA 1 i (N -PrIl SYSr-M, I 572 SIilP SIORES AN ElUIE 573 574 581 CAW) IDte)LINGSYSliS 582 WXDRIN, AND lING r HIANLING SYST'EIS VhlrICAI. REPLkNISIEMEF_ SYSTIIS A'IWIf hiA.IN; AND SITJW_ SYS'TMS (WATr, fAT 584 SYSI4MS WHAI)I,IJG ANI) S'lWAC SYI'rIMS ] OR, GATE, RAMP, MFUHANICAI, (YPERATED TItkNrAI3E SYS'I'Im tlEVATING A) HwRACrING (AR AIRCAIF lA?,I.IN;, .SEHVICING AND SLM ~85 MISCEIJANE'XlS M'IANICAL HA ,IING SYSEIMS uMIHuMJAND IVt SUP1J~' Am P'rr(7'1C SYS-ErmS AND HAN)LING tH LIIRIcIATE '11111I;, LAI,'lIN S YS'iNS IIANI)1.IN; SYS'2S tIXJ DIVER AN SMESIBIL 589 592 595 596 S9 I SALVAG S4JPIHT SYS1TIS 316 COST GIlJP: 6A S ND. PSCRIPFrIIN A- _-----605 1o[' ---- _----- - F Ad) VEtfIN P'ING b611 HJU. FTrtNS 612 IAIIS, H 61 3 RIC(IN; 625 AIR)HR PR'IS,FIXtl) SrANCHIcNS, A) L'IFELINES AND CANV7S R(ILIGHM'S, A) crlsr CR tip: Sis N). I £SqrR Prl N I - 621 b22 Nl9-STHLUC URAL BIJULHEALE FILJR PArfI A) (ATINGS I 623 [AIdRS 624 t]N-STRL'VURAI. 637 51IF'AliI N(; C0T GlUP: CIJ{H S 6c N). Di3S I IJFSHIP'I(IN 602 603 604 631 IILL ESIGNATING A) MARKING L*AFT MARKS DCKS, KEYS, A TAGS PAlmrING 632 ZINC OTING 6 33 CAT1OiOIC PlIEX'TION 634 6 35 D)CK NVERING IIIIIL INSUIATION 6 36 639 HUILL DWMPING HADIATI(IN SiEIING 317 WNXkS CFT GaCUP: SWBS N). I 654 655 56 b64 1 1 I 1 671 672 i C~T6fT CRP: 638 641 642 643 644 645 iESCRIPrFIC SPACES L'ILI'Y LALURY SPACES TRASH DISR.3AL SPACES STATI(NS AUE (ITl)L 'TESAREAS (INCU)ING ORKSHOPS, LABS, I'X)LS, EUyI NI'r) 665 B3S ND. 6D RF(:AB.LE LXKErI AND SPECIAL SWA.C I.MS IC;UUIMS AND ISSUE 6E IPrl(N !IFXR I PE:FHIGERATEDSPACES E)MESSING SPAC'ES OFI'CER BRTING MJNCCIMISSI.Nl(EDOFFICER bLERHING A) MESSING [ SPACES I AN) MESSING SPACES ENILISTED PERSCONEL BtEING SPAC'ES AND FIXJitS .SANITAHY SPA('ES LEISUR4EAN) (lCMITY 1 I 651 CMIISSAY SPACES 652 65 3 661 662 MEDICAI, SPAC(S L*NrAL SPAC'b OFFICES MACFIINERYCINT)., 663 ELECrJICS 318 CEEIRTS F-URISIIMS Cl)IfM L CEIrERS FURNISHINGS : C6Tr GIXS: SawS N). GCNERALARRANCE4 701 7 11 712 713 721 722 - WEAPONRYSYSrE IAN)II NG ITIN AMMNL All' I l N $~ITAGE IAtICHING; IVI1CEtS (MISSILES AN) RHCKETS) 723 724 72) 72b 728 7 29 731 72 733 741 742 743 751 752 753 754 761 762 DRESCPrIcN I I 1 I 1 I I I E CAPSUlt MISSIIE, IU'KET, ANLi(UIL' ItAN)lING M1ISSILE MISSIIE MISSI MISSILE SYSTI E AND K('Kbl' Sn'&IMAC IiYIMAULIC.S MISS.L II.H LALN 'rNG (1IIIt'SATIKH UI tK)L ItPLHATlHE (JINIWLL MISSI1 E tIEA'rIl , (CX),lIN[;, rD Am(2MI TESr MISSIllE K1I'I!m[NG, MINE IAL'lIIlNG Il:VICES ,I1A LINGK MINE MINE SIRtWL IUEMIIIClIWCE LAL 'HING DILVICES IEfll CHARGE YAN)LING; DEPI C1HAE SIfML; 'IORPEDOI3ES 'TIRPEDO IANDLING 1r>PEDO SIi 7#A(Z SiIA~ INE TIRHPEJO EJETI(N U1ALI, AIMS AND PYROTECHNIC [AILMNClNG EVICES MALU,ARMS AND PYRfIECHN IC HANDLING 9AI1, AI4S ANDPYFIYIEIJNIC SIrdE CA.) MIINTI(fIi CAR) MUNITI(IN5 IiANDL[N 'AGE CAR ) MUNI''I()NS S 7631 770 772 773 HAM.,INI 782 Altl'IW-I' iLA';i) WNJS 783 AIRClAIT RELATED WEAPNIS SWAGE SPECIAL WEAI 5 IMIANLING SPECIAL WEAPM STOMGE MISCEIANLU.S (I4U1AtCE SPACiS 792 793 797 I 319 APPENDIX ANVCE SHIP E AND SWBS GROUP CERS SAMPLE (Ref. 532C) 54) Vehicle ACV 1 ACV 3 A'L(N) AVP VhcI Definition I _ _ Noaunal 1000-tonne ACV Nouinal 3000-tonneACV Air loiter aircraft Nuclear-powered,air loiter aircraft Advancedpatrol aircraft CPIC OLX Coastal patrol interdiction FAB FMI 7 Pully air-buoyant LTAvehicle HYD 7 HYD 2 HOC Naounal, 700-tonne, LCAC LCPC LSES Landing craft, Landingcraft, RMNO3 Nomnal, 3000-tonne, advanced-technology monohull Long-range cargo aircraft IANVCE Proi- BaselineIEx'stina ect Design .,.sDesign Des xcn X X X X I X X craft X (USAF) X x X PER-class, guided-mussilefrigate X high-speed hydrofoil X X Nounal, 2000-tonne hydrofoil Hydrofoil, ocean cortatant X air cushion vehicle planrng craft X X x Large SES X x x PC I PiM Nmtunal, 1000-tonne planlrq SAB SES 3 SES CV SES CVN Semlair-buoyant LTAvehicle Ncounal, 3000-t ne SES S/L(L) Large, sea loiter aircraft S/L(S) S/L(V) S 4 Small, sea loiter aircraft Ship-based,V/STOL, sea loiteraircraft Nonunal,4000-tonneS9 frigate MNir-ceountrmre asure STH shiD Nuclear-powered, SH carrier i craft X Guided-missile, patrol hydrofoil SWA SI x M CVN vS WIG(H) WIG(O) I wJl~rc ZI X ZPG X SES carrier Nuclear-pcwered SES carrier X X X X X X X X X X V/S$L, support ship x Hard-ernd-plate WIG vehicle Out-of-round-effect,WIG vehicle ChFed~rrllat Patrol,,., i Patrol, vei;l L. Lnr. vehicle 321 . ls X X I I x I I I ! - l :. --- - - - l - I - " . I Special-I I Air Vehicle Groups Surface Vehicle Groups Purpose I I Small, Multi-I ILarge, I I1I 13000-Torne I 1000-TonnelAircraftIMission Air-I ASW I Vehicles I IAircraftl craft ICarriersl I Class I Class I I S/L(S)I I S/L(v) l SWA I S/L(L) I AVP I WIG(H) I WIG(O) I I I I HYD SES 2 3 I i HYD 7 PC 1 ISES SWA 4 I I WIG(S) MONO 3 I FAB I ACV 322 I I I A/L(N) CVN ISWA CVN I I I I SAB A/L 3 1 I I I I I ISES CV ACV LCAC LCPC I MC I IU Z 650 U) 0. 40 030 I.- 0 10 10 100 1,000 GROUP 1 WEIGHT (TONNES) 323 10,000 NONNUCLEAR PROPULSION 140) 1200 X 2 400 200 1.000 10 000 100.000 GROUP2 POWER(MHPI 1.0.000 NUCLEAR PROPULSION ZXI O 0 z i \K\ i o NOTE COWNICO COST OLI DOES NOT mCLuOt COST O rLiC'OR 0*! I Tr41S O. O". S*S' TO theE _uCL U 'I 0 100 I !ELAtEO --- 1.000 10.000 GROUP2 WEIGHT (TONNES) 324 100,000 a600 zz 0 D500 o,) zc00 I.- w2 0 0 0. I- 0 u 100 1 10 GROUP 3 WEIGHT 325 100 ITONNES) 1000 I - tCA4 7m F- - - -- .wI'sI - -- I- - - - :n 1~~~~~~~ cn _ . i - KEY ~- - X SIMPE CONtRa SYSTEMS ItNIMAL ELECTRONICS 2 MOOEST CONTROL SYSlftS SOPHISTICATED ELECTRONICS 3 COMPLtE CONTROI SSTEMS SOPHISTICATED ELECTARONICS WIFICRITICAL SHIPS 3 - 0 I0 z (u, O0 I w Z z z 0 )- IVn) 0 U I 100 - £C ..... 0 1 _IIY~iS 'MY0 H -C LCPC i . 10 GROUP 4 WEIGHT(TONNES) 326 2 St S I - w%} iIJEJ S^4 . _ 100 _ r -CV b 1S CVN - - - S.. -- C.. SWACffi , 1000 a; zz O I- 0 a w 0 z o w. I- (t u- 1 10 100 GROUP5 WEIGHT (TONNESI 327 1,00 10.000 z oz u) 1 a z4 u) 0 z a 0I- U 00 GROUP6 WEIGHT ITONNES) 328 KEY 1. CONVENTIONALDISPLACEMENTSHIP 2. WEIGHT-CRITICALSHIP, LIGHT ARMAMENT Z F --- LCAC |Y- WIGISISS CV. - CVN (fl 0o O I z0 WA 4 16 -- JMCM 1 L Cpc SWA CVN 10 100 GROUP 7 WEIGHT 329 (TONNES) 1000 10( ca z co 0 f0 1 e Li 0.1 _01 1 1000 100 10 SUMMATION OF GROUPS 1 THROUGH 7 COSTS ($ MILLIONS) 330 o lO1 -J 2j a 0g1) . L) (0 C' 0 cc 0 1 o ,IAl 1 SUMMATION 10 100 1000 OF GROUPS 1 THROUGH 7 COSTS ($ MILLIONS) 331 APPENDIX F PRICE H INPUT GLOSSARY AND DATA SHEET (Ref. 20) GLOSSARY OF PRICE H VARIABLES BASICINPUTS AUCOST CATGRY CMPID COST CPF DCOST DESRPE DESRPS DFPRO DLPRO DSTART DTCOST ECMPLX EREL INTEGE INTEGS MCPLXE MCPLXS MECID MODE MREL NEWEL NEWST PCOST PEND PFAD PLTFM PRCOST PROSUP PROTOS PSTART PTCOST QTY QTYNHA RATOOL TARCST TCOST Average recu.ringunit productioncost (Historical Data). Thru-put cost category. Equipmentelectronicclassification. PurchasedItem cost. Two,three, or five digit code for the manufacturing process used in production. Thru-put developmentcost. Decimal fraction of electronicdesign repetition. Decimal fraction of structuraldesign repetition. Month/Yearof completionof first prototype(Not to Includefield tests). Month/Yearof completionof development. Month/Yearof start of development. Total developrn-nt cost (HistoricalData). Engineeringcomplexityfactor. Electronic reliabilityadjustmentfactor. Level of integrationand test requirements applicable o electronics. Level of integrationarn lest requirements applicableto structuraLmechanical areas. Empiricalinput of the electronicsmanufacturing complexity. Empiricalinput of the structural'mechanical manufacturingcomplexity. Equipmentsmechanicalstructuralclassification. Numericaldesignationof PRICE input mode. Mechanicalreliabilityadjustmentfactor. Decimalequivalentof uniquenew electronicdesign required. Decimalequivalentof unique new mechanical/ structural design required. Thru-put productioncost. MonthtYearof completionof production. Month/Yearof productionfirst article completion (Does not include field testing). Equipmentsdesignedoperatingenvironment (SpecificationLevel). Prototypemanufacturingcost, to includespecial tooling and test equipment(HistoricalData). Prototypesupport empiricalfactor. Number of prototypesto be developedfrom DSTARTto DLPRO. Month/Yearof release to production start of productioncycle. Total productioncost (HistoricalData). Number of productionunits to be built from PSTART to PEND. Numberof equipmentsrequiredfor integrationto the next higher assemblylevel (System). Average monthlyproductionrate for which tooling is to be costed. Target design-to-unit-production-cost (Amortized over all productionelements). Total thru-pIt cost. 333 Proportionof an equipmentsvolumeoccupiedby the electronicspackage. Envelopevolumeof an equipment (Cubicfeel). Electronicpackagingdensity(Weighlof electronics per cubicfoot). Weight of mechanicatlstructuralelements (Pounds). MechancaVstructural density (Weightof structure per cubicfool). Weight of equipment(Pounds). Economicbase year. Technologicalbase year. USEVOL VOL WECF WS WSCF wr YRECON YRTECH GLOBALINPUTS COSTU DDATA DESIGN DMULT DPROJ DRAFT DTECIM DTLGTS ECNE ECNS ESC NFACS NSHIFT PDATA PMULT PPROJ PSF PTECIM PTLGTS RSRCE SYSTEM TECDEL Units for cost measurements(e.g.dollars, thousands of dollars,etc.). Level of data requirementsfor the development phase. Empiricalfactorcontrollingthe levelof engineering design. Developmentcost multiplier (tor additionsto manufacturingcost level). Level of projectmanagementfor thedevelopment phase. Empiricalfactor controllingthe level of drafting. Level of technologicalimprovementfor developmentprograms. Level of specialtools and lest equipmentrequired for prototypemanufacturing. Levelof productionengineeringchangeactivityfor electronicssections. Level of productionengineeringchangeactivityfor structuralsections. Escalationcontrolvariable. Numberof productionfacilities (Lines)to build QTY equipment. Numberof productionshifts used to build OTY equipment. Level of data/documentation requirementsduring the productionphase. Productioncost multiplier(For additionsto manufacturingcost level). Multiplierof productionprojectmanagementcosts. Prototypeschedulefactor (Definesthe sequenbal manner in which the prototypeswll be manufactured). Level of technologicalImprovementfor production programs. Multiplierof specialproductiontools and equipment costs. Indicatorof resourcesthat are availablefor production. Multiplierof systemsengineeringcosts in the developmentphase. Numberof years of technological delay (Lag). ILTJE Input Data Worksheet m Filename: Shemt_ of Basic Modes t: Title: Fdu4tm snt'w Genral A GeneralB Mechanical/ oad v- OaTY PoToG WT VOL MODE. HSMNT O-mvi/lit NHin AmMV NM EItrotu FrMm Swctwel S cd0tmna Lew Yaw tie.0l Ya l Tectmn orYNNA INTo I TES PLYTFM YRECON YRTECH Sru gtwS Mi Dht U Rpil S RMa.dltr Swlql Iftioe" fDqur CovplI-t tt I d NW/ISW FestyvPft -~ Volm _ ItA If g CPL5 Swuctu NW,. hmufiduiMIWI Comeilbl E1V.sOfI Dsq I ROa Ectf RaI·LJ.ilV NEWEL DESIAE EEL W.S "V Structurl IVelu NE rC Ft/ Flrtuu Ebctronics Development WECF I USEVOLMFLXsE OIo_.0et Son In lotoYp C omlte Oiwlopmnw opem C E.iwarw C.t Tol & Tyt Eq.s ty etowlp Atyr OST^RT OFPRO OLPRO ECMPLX OTLGTS FROSUP hobcto ComfeN PRICElmprovemnt Tooll T to E5M I, Rau/Mont Tre Ftor PIF FTLGS RATOOL Fdoect.u S1/t F.r AItcil Dhlr Y Production FSTAT PF^D Actual A-la Urm Cost Data AUCOST EN PhodguiLt D To*t hosr PTCOST PRCOST :.o leopmm oTCOST (Mode7 only) Notes: _ _~~~~- . I ELECTRONIC ITEM 2 MECHANICAL ITEM S MODIFIEDITEM 7 ECIRF - GC 1613 1/85 o( 1985RCACorporation - [CE0I 334