Lean Aircraft Initiative Plenary Workshop Cycle Time Reduction Using

advertisement
Lean Aircraft Initiative
Plenary Workshop
Cycle Time Reduction Using
Design Structure Matrices
October 8 -9, 1997
Presented By:
Tyson R. Browning
Product Development Focus Group
LEAN AIRCRAFT
INITIATIVE
Overview
l
Some cycle time reduction challenges
l
Task-based design structure matrices (DSMs)
l
How DSM method meets challenges
l
Part 2: David Grose on applications at Boeing
Perspective:
Process
Tyson R. Browning
Activity
PD100897-2 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
Some Cycle Time Reduction
Challenges
Inefficient personnel and resource distribution
– People
– Facilities & tools
– Information
l
l
l
l
l
l
l
l
Tyson R. Browning
Unstable requirements
Long and varied activity pipelines
Lack of activity coordination
Highly coupled activities
Delayed decisions
Rework
Schedule too ambitious to begin with
Hoped for solutions have adverse side effects
PD100897-3 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
l
l
l
Design Iterations
Account for many aspects of schedule overrun
Design rework, change, refinement
Difficult to plan for
Intentional iterations
– Improve design quality
– Reduce performance risk
l
Unintentional iterations caused by
–
–
–
–
l
Tyson R. Browning
Poor task sequencing quality
Poor communication and coordination quality
Design mistakes
Poor requirements quality, simplicity, stability
More difficult for complex system development
PD100897-4 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
Reducing Cycle Time
One approach: overlapping tasks
– Can cause iteration if tasks are coupled
l
True cycle time reduction requires
– Systems view
– Much information processing for complex relationships
l
Need for method
– to structure complex interactions
– to rework sequences of tasks
l
A better approach: Design Structure Matrix
– To manage task couplings and iterations
l
l
Tyson R. Browning
To reduce schedule overrun risk
To reduce cycle time
PD100897-5 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
Origins
–
–
–
–
l
Design Structure Matrices
Solving systems of equations (1960’s)
Network precedence diagrams (1960’s)
Matrix mathematics (1960’s and 1970’s; Warfield, et al.)
Similar to N2 diagrams in systems engineering
Formal definition
– Design processes (1981, Steward)
– Multiple applications in automotive, electronics, and
semiconductor industries (early 1990’s; Eppinger, et al.)
l
Compared with PERT
– Shows task precedence and coupling
– Explicit notation of iteration
– Simpler representation of complex process
Tyson R. Browning
PD100897-6 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
GET SOCKS
GET SHOES
PUT ON SOCKS
PUT ON SHOES
INSPECT SHOES
Introduction to Task-based or
Schedule DSMs
n
n
n
n
n
Diagrams adapted from Denker, Stephen. “ANew Way to Think
About Problems” Presentation to PMI, 6/19/97.
Tyson R. Browning
PD100897-7 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
GET SOCKS
GET SHOES
PUT ON SOCKS
PUT ON SHOES
INSPECT SHOES
Introduction to Task-based or
Schedule DSMs
n
n
n
n
n
Diagrams adapted from Denker, Stephen. “ANew Way to Think
About Problems” Presentation to PMI, 6/19/97.
Tyson R. Browning
PD100897-8 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
GET SOCKS
GET SHOES
PUT ON SOCKS
PUT ON SHOES
INSPECT SHOES
u
u
u
u
u
Introduction to Task-based or
Schedule DSMs
n
n
n
n
n
Precedence diagram: information
dependencies
Sequence tasks
First goal: reduce iterations and
their scope
Problem: coupled tasks
Identify parallel tasks
Diagrams adapted from Denker, Stephen. “ANew Way to Think
About Problems” Presentation to PMI, 6/19/97.
Tyson R. Browning
PD100897-9 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
GET SOCKS
GET SHOES
PUT ON SOCKS
PUT ON SHOES
INSPECT SHOES
u
u
u
u
u
Introduction to Task-based or
Schedule DSMs
n
n
n
n
n
Precedence diagram: information
dependencies
Sequence tasks
First goal: reduce iterations and
their scope
Problem: coupled tasks
Identify parallel tasks
GET SOCKS
GET SHOES
INSPECT SHOES
PUT ON SOCKS
PUT ON SHOES
n
n
n
n
n
Diagrams adapted from Denker, Stephen. “ANew Way to Think
About Problems” Presentation to PMI, 6/19/97.
Tyson R. Browning
PD100897-10 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
GET SOCKS
GET SHOES
PUT ON SOCKS
PUT ON SHOES
INSPECT SHOES
u
u
u
u
u
Introduction to Task-based or
Schedule DSMs
n
n
n
n
n
Precedence diagram: information
dependencies
Sequence tasks
First goal: reduce iterations and
their scope
Problem: coupled tasks
Identify parallel tasks
No interactions between
parallel tasks
GET SOCKS
GET SHOES
INSPECT SHOES
PUT ON SOCKS
PUT ON SHOES
n
n
n
n
n
Diagrams adapted from Denker, Stephen. “ANew Way to Think
About Problems” Presentation to PMI, 6/19/97.
Tyson R. Browning
PD100897-11 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
l
l
DSMs Show Opportunities to
Reduce Cycle Time
DSM: a description of the current process
Modify DSM to achieve a prescription for a
process with reduced risk and cycle time
Capabilities
– More accurately manage schedule
– Systems view of many cycle time drivers
– Quickly examine potential task sequence changes
– Intelligently place tasks in parallel
– Deploy resources to reduce unintentional iterations
Tyson R. Browning
PD100897-12 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Another DSM Example
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
n
n
n
n
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-13 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Another DSM Example
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
Series
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
n
n
n
n
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-14 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Another DSM Example
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
7
8
9 10 11 12 13 14
1 2 n n
n
n n
2
4 n
n
n n
3
7 n n n n
4
7
n
5
5 n
n
n
Series
6
2 n n
7
5 n n n
n
Parallel
8
n 4 n
n n
9
n n 5 n
10
4
n
11
7 n n
Parallel
12
4
n
Parallel
13
2 n
14
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-15 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Another DSM Example
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
1 2 n n
n
2
4 n
n
3
7 n n
4
7
5
5
Series
6
7
Parallel
8
9
10
Coupled
11
12
13
14
6
7
n
n
n
8
9 10 11 12 13 14
n
n
n
n
n
n
n
2 n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
Parallel
4
n
Parallel
2 n
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-16 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Another DSM Example
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
1 2 n n
n
2
4 n
n
3
7 n n
4
7
5
5
Series
6
7
Parallel
8
9
10
Coupled
11
12
13
14
6
7
n
n
n
8
9 10 11 12 13 14
n
n
n
n
n
n
n
2 n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
Parallel
4
n
Parallel
2 n
2
“Toll Gates” for Review
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-17 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Project Duration
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
2
6
n
n
n
n
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-18 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Project Duration
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
2
6
13
n
n
n
n
20
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-19 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Project Duration
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
2
6
13
n
n
n
n
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
20
22
?
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-20 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
Project Duration
Kodak “Cheetah” Project
Task
Receive and accept specification
Concept generation/selection
Design beta cartridges
Produce beta cartridges
Develop testing program
Test beta cartridges
Design production cartridge
Design mold
Design assembly tooling
Purchase assembly equipment
Fabricate molds
Debug molds
Certify cartridge
Initial production run
1
2
3
4
5
6
1 2 n n
n
2
4 n
n
3
7 n n n
4
7
n
5
5 n
6
2
7
8
9
10
11
12
13
14
7
n
n
n
8
9 10 11 12 13 14
2
6
13
n
n
n
n
n n
5 n n n
n
n 4 n
n n
n n 5 n
4
n
7 n n
4
n
2 n
2
20
22
?
~9
31
38
42
44
Diagram adapted from Ulrich and Eppinger, Product
Design and Development, McGraw-Hill, 1995, p. 262
Tyson R. Browning
PD100897-21 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
l
DSM Provides Method to Meet
Cycle Time Reduction Challenges
Shows where resources must flow
Examine effects of changes
– Unstable requirements
– “Creeping elegance”
l
l
l
l
l
l
Tyson R. Browning
Exposes long and varied subprocess pipelines
Shows where to check for lack of task
coordination
Illuminates highly coupled activities
Shows schedule impacts of delayed decisions
Exhibits likely iterations and rework chains
Helps ensure schedule not too ambitious
PD100897-22 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
Applications
–
–
–
–
l
Applications and Next Steps
Process task/activity sequencing
Cycle time and schedule risk reduction
Process visualization, representation, and reengineering
David Grose: applications at Boeing
Next Steps
– Product Development Focus Group (tomorrow)
– Ongoing research to expand applications
Tyson R. Browning
PD100897-23 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
Risk Definitions
Schedule Risk
– Uncertainty in ability of program to develop a design that meets
desired quality levels by certain points in time
– … and the consequences thereof
l
Performance Risk
– Possibility that a new design will not meet desired quality
criteria within cost and/or schedule expectations
– … and the consequences thereof
l
Technology Risk
a subset of performance risk; the possibility that a technology will not provide anticipated
performance benefits within cost and/or schedule expectations and the consequences thereof
l
Development Cost Risk
the possibility that designing to desired specifications within schedule expectations will cost more
than anticipated and the consequences thereof
l
Market Risk
the possibility that the chosen “design to” specifications will not be of anticipated utility to the
market and the consequences thereof
Tyson R. Browning
PD100897-24 ©1997 Massachusetts Institute of Technology
LEAN AIRCRAFT
INITIATIVE
l
l
l
l
l
l
l
l
Tyson R. Browning
Overly optimistic schedule
Lack of personnel or other resources
to complete activities
Multiple refinements of analyses or
repetition of tasks required to improve
design performance relative to
specifications
Schedule rigidly dictated/constrained
by available budget profile
Subtask or subprocess duration is too
long
Subtask or subprocess duration is
unpredictable
Highly coupled activities must
coordinate repeated, bilateral
information exchange
Decisions take too long to get made
Representative
Schedule Risk Drivers
l
l
l
l
l
l
l
l
l
Information required to begin some
tasks is not available when task begins
Requirements change forces rework
Inadequate development cost budget
Design mistakes cause rework
Long lead time tasks force early
decisions
Task content or ramifications are
inadequately understood
Organization is inflexible regarding
adaptation to schedule modifications
Personnel and/or leadership turnover
causing delays
Task set or statement of work is
underestimated
PD100897-25 ©1997 Massachusetts Institute of Technology
Download