Analysis of the Production System at ABB Combustion Engineering Newington Operations by Rhonda L. Patton B.S., Mechanical Engineering (1999) Massachusetts Institute of Technology Submitted to the Department of Mechanical Engineering in Partial Fulfillment of the Requirements for the Degree of Master of Science in Mechanical Engineering at the Massachusetts Institute of Technology June 2000 0 2000 Rhonda L. Patton All rights reserved The author hereby grants to MIT permission to reproduce and to distribute publicly paper and electronic copies of this thesis document in whole or in part. Signature of A uthor............................................... Department of Mechanical Engineering May 5> 2000 C ertified by ........................................................ David S. Cochran Assistant Professor of Mechanical Engineering A ccepted by ......................................................... Am A. )omn Chairman, Committee on Graduate Students MASSACHUSETTS INSTITUTE OF TECHNOLOGY SEP 2 0 2000 LIBRARIES Analysis of the Production System at ABB Combustion Engineering Newington Operations by Rhonda L. Patton Submitted to the Department of Mechanical Engineering on May 5, 2000 in partial fulfillment of the requirements for the Degree of Master of Science in Mechanical Engineering ABSTRACT ABB Combustion Engineering Nuclear Power Newington Operations is a manufacturer of industrial and nuclear equipment located in Newington, New Hampshire. This thesis examines the current production system at ABB and applies the Manufacturing System Design Decomposition, developed by Professor David Cochran, Professor Paulo Lima, and the students of the Production System Design Laboratory at MIT, to begin planning the transition to a lean manufacturing system for the production of spent fuel dry storage canisters. Lean manufacturing is based on the philosophies of the Toyota Production System, developed by Taiichi Ohno. Justin-time and autonomation are the two main pillars of TPS. The ultimate goal of TPS is to eliminate all waste in the system, which is accomplished by setting up cells, which reduce travel distance, producing exactly the amount needed when needed, which minimizes inventory and prevents overproduction, and eliminates all non-value adding activities. The main obstacles that ABB must deal with in transitioning to a lean manufacturing system are resistance to change, the challenge of combining a cellular manufacturing system with a project shop manufacturing system, and working with the quality regulations set forth in the ASME Boiler and Pressure Vessel Code. ABB Newington has been producing industrial and nuclear equipment for over 40 years now. Many of the employees at ABB have been working there for a significant length of time. For these reasons, changing the philosophy of production is going to be difficult. Some of the components of the spent fuel canisters are extremely large and can't be moved easily. As a result, the production system at ABB will have to combine typical cellular manufacturing methods with project shop methods, where some of the components remain stationary and other parts come to them. Lastly, ABB must deal with the fact that the ASME Code prohibits inspection of parts by anyone that performed or directly supervised the work being inspected. Thus, self inspection as part of the cell work loop is impossible. ABB must be creative in dealing with this challenge and try to find ways to compromise between the stipulated inspection requirements and the ideals of TPS. Thesis Supervisor: David S. Cochran Title: Assistant Professor of Mechanical Engineering 3 4 TABLE OF CONTENTS TABLE OF CONTENTS .............................................................................. L IST O FIG URE S ...................................................................................... LIST O F T A B LE S ...................................................................................... ACKNOWLEDGEMENTS ............................................................................ 1.0 Introduction and General Background Information................................................9 1.1 ABB Combustion Engineering Nuclear Power Newington Operation.............. 1.2 Spent Fuel Dry Storage Canister Production.......................................... 1.3 O u tlin e ........................................................................................ 2.0 "Lean" Manufacturing.............................................................................. 2.1 Toyota Production System............................................................... 2.2 Manufacturing System Design Decomposition.......................................... 2.2.1 Axiom atic D esign............................................................................... 2.2.2 Manufacturing System Design Decomposition.............................................15 5 6 6 7 9 10 11 12 12 14 14 16 2 .3 In spection ................................................................................... 2.3.1 Statistical Process Control and Acceptable Quality Levels.................................17 2.3.2 Judgem ent Inspection...............................................................................22 . 22 2.3.3 Inform ative Inspection....................................................................... 3.0 Existing Conditions and Project Goals........................................................... 3.1 C urrent Plant L ayout........................................................................24 3.2 Flow of Parts and Information.............................................................26 3.3 Scrap, Non-conformances, and Corrective Action...................................28 3 .4 Inspection ................................................................................... 3.5 W orker Activities......................................................................... 3 .6 S chedulin g .................................................................................... 3.7 Project G oals.............................................................................. 4.0 MSD Decomposition Applied to ABB Newington.............................................. 4.1 Top Three Levels of PSD Decomposition............................................... 4 .2 Qu ality ........................................................................................ 4.3 Identifying and Resolving Problems.................................................... 4.4 Predictable Output.......................................................................42 4.5 D elay Reduction........................................................................... 4 .5 .1 T akt Tim e ............................................................................................ 24 29 30 32 33 34 34 37 40 45 47 4.5.2 F loor L ayout................................................................................... . .. 49 4.5.3 Sam ple M achining C ell........................................................................ 4 .5 .4 In spection ....................................................................................... 51 . . 55 4 .6 D irect L ab or................................................................................. 4 .7 Indirect L abor................................................................................59 5.0 Concluding Comments............................................................................. 5.1 S ummary .................................................................................... 5 .2 O b stacles.................................................................................... 5.3 T he N ext Steps.............................................................................. 5.4 F inal C om ment.............................................................................. R EFE R E N CE S .......................................................................................... A PP EN D IX A ............................................................................................. 5 57 60 60 60 61 63 65 66 LIST OF FIGURES Figure Figure Figure Figure Figure Figure Figure Figure Figure Figure 2-1: 2-2: 2-3: 2-4: 2-5: 3-1: 3-2: 3-3: 3-4: 3-5: O verall layout of the M SD D .............................................................. 16 Normal distribution curve with p = 0, a&= 1......................................... 18 Graphical representation of (x-error.................................................... 19 Graphical representation of B-error.................................................... 20 Confidence intervals of a standard normal distribution............................... 21 Current layout of the Light Manufacturing Building................................. 25 Current layout of the Heavy Manufacturing Building............................... 25 Histogram of inspection times........................................................... 30 Pareto chart of worker activities during a random 2-hour time slot...............31 Percentage of total worker hours spent on each operation/activity during a random 2-hour time slot............................................................. 31 Figure 3-6: Pie chart of value adding, non-value adding but necessary, and waste during a random 2-hour time slot...................................................... 32 Figure 4-1: Levels I, II, and III of the MSDD.........................................................35 Figure 4-2: "Quality" branch of the MSDD......................................................... 38 Figure 4-3: "Identifying and Resolving Problems" branch of the MSDD....................... 41 Figure 4-4: "Predictable Output" branch of the MSDD........................................... 43 Figure 4-5: "Delay Reduction" branch of the MSDD............................................. 46 Figure 4-6: Typical cellular manufacturing layout of the ship building industry................ 49 Figure 4-7: Possible linked-cell layout for production of canisters at ABB..................... 50 Figure 4-8: Machine-part matrix used to establish part families.................................. 52 Figure 4-9: Possible layout for the sample machining cell........................................ 54 Figure 4-10: "Direct Labor" branch of the MSDD................................................ 57 Figure 4-11: "Indirect Labor" branch of the MSDD................................................. 59 LIST OF TABLES Table 2-1: Table 3-1: Table 4-1: Table 4-2: Table 4-3: Type I and Type II errors of the Decision Making process............................ Sample travel distances of selected parts................................................. Part demand in sample machining cell................................................... Cycles times of each part at each machine in the sample cell......................... Improvements resulting from formation of sample machining cell.................. 6 20 28 52 53 54 ACKNOWLEDGEMENTS I would like to thank Professor David Cochran for providing guidance and inspiration for this thesis. I would also like to thank everyone at ABB Combustion Engineering in Newington, New Hampshire for their constant support and assistance. I certainly couldn't have done this thesis without their help. '7 8 1.0 INTRODUCTION AND GENERAL BACKGROUND INFORMATION This thesis presents a methodology that can be used as a guideline in the transformation of a traditional job shop plant to a lean manufacturing plant in the nuclear industry and is based on studies done during an internship at ABB Combustion Engineering Nuclear Power (ABBCENP), Newington Operations (Newington) in Newington, New Hampshire. The internship project was primarily a "feasibility study" to examine the major roadblocks that ABB would have to confront in developing a lean manufacturing system and devise a plan to deal with these major issues. While the details of the system pertain particularly to ABB-CENP Newington Operations, the general philosophies and methodologies can be applied to many other manufacturing plants, particularly those in the nuclear industry or other highly regulated industries. In particular, the issue of quality control and quality assurance is largely addressed in this thesis. The requirements for quality inspection imposed upon ABB (and the nuclear industry, in general) by the U.S. government are in direct conflict with the main principles of cellular manufacturing. The work done in this thesis examines that conflict and addresses possible compromise. 1.1 ABB Combustion Engineering Nuclear Power Newington Operations ABB-CENP Newington Operations is a manufacturer of industrial and nuclear equipment. For more than 40 years, Newington has been manufacturing high precision stainless steel and high alloy components for the nuclear energy industry. Newington manufactures the reactor vessel internals (RVIs), which provide a support structure for the core and provide a flow path within the reactor vessel; the control element drive mechanisms (CEDMs), which are 9 electromechanical devices that insert and withdraw the control element assembly; and the reactor coolant pumps (RCPs), four pumps that circulate water through the reactor coolant system, each with a rated flow from 85,000 to 120,000 gallons per minutes at 8,000 to 12,000 horsepower. Newington Operations is part of Nuclear Systems, a division of ABB Combustion Engineering Nuclear Power, Inc.. Newington Operations employs 144 employees, 95 of which are hourly employees. The facilities in Newington consist of two large manufacturing warehouses, one known as the "light manufacturing" building and the other known as the "heavy manufacturing" building. The light manufacturing building runs two shifts, while the heavy manufacturing building runs three shifts. There is also a building that houses quality assurance, including all retained quality assurance records, and another building that houses design engineering, human resources, production control, and purchasing. 1.2 Spent Fuel Dry Storage Canister Production In December of 1998, ABB-CENP Nuclear Systems won a contract to build spent fuel dry storage canisters. This contract is the first of many contracts that ABB expects to win over the next few years. Newington Operations is simply the fabricator of these canisters. External firms did the design. There are three basic designs to the canisters that ABB may build over the next few years, that are all similar in basic structure but vary in the amount of machining, welding, and assembling involved. During this internship period, production of the first canister contract was underway. However, a major design problem was discovered partway through the internship period and 10 production of the canisters was halted. ABB then began assisting in an R&D effort to correct the problem. The projected restart is 2002, which is when rework on the partially constructed canisters will be done, as well as complete production of additional canisters for the contract. Fabrication of a second type of canister has already started at ABB, though no finished products are scheduled to ship until July 2000. Thus, this thesis focuses on the general state of the production system in Newington with examples taken from canister production. 1.3 Outline Chapter 2 gives a brief description of the Toyota Production System (TPS) and the Manufacturing System Design Decomposition (MSDD), which are used to analyze the production system at ABB and suggest improvements to the system. This chapter also details the inspection philosophies of mass production and TPS. The current state of the production system at ABB-CE Newington Operations is described in Chapter 3. The goals of this project are also laid out. Chapter 4 is the heart of this thesis. The MSDD is used as a tool to analyze the production system at ABB and determine feasible ways to improve the system. Certain sections of the MSDD are emphasized over others due to their pertinence to ABB's production system. Finally, in Chapter 5, comments are made regarding inspection at ABB and the regulations infringed upon the industry. Chapter 5 also includes a summary of the analysis presented in this thesis and recommends the next steps for ABB to take. 11 2.0 "LEAN" MANUFACTURING This chapter provides a brief history and overview of the Toyota Production System, as well as describes the Production System Design Decomposition Framework that was used to analyze the current production system at ABB. Finally, a detailed look at the inspection procedures and philosophies of mass versus "lean" production is presented. 2.1 Toyota Production System Lean manufacturing, the Toyota Production System (TPS), and Just-in-Time manufacturing are all synonyms for the production system developed by Taiichi Ohno. Following World War II, when Japan was in a state of rebuilding and resources were scarce, the President of the Toyota Motor Company, Kiichiro Toyoda, said, "Catch up with America in three years. Otherwise, the automobile industry of Japan will not survive" [Ohno, 1988]. Ohno, who worked for Toyota, looked at the mass production systems in existence in America at the time to try to find ways to keep his company in business. Ohno had once been told that the work force ratio between Japan and America was 1-to-9 [Ohno, 1988]. How could this be? Ohno knew that there was no way that American workers could actually exerted ten times more physical effort than Japanese workers. This was when he realized that there was simply too much waste in the Japanese system that was getting in the way of productivity. In Japan, demand for automobiles was not as high as in America and Toyota did not have as many resources as the American companies. As a result, Ohno created a system based on two pillars: just-in-time and autonomation (automation with a human touch). Just-in-time refers to the method of making only what is needed, when it is needed. This meant that Toyota could keep a minimal amount of inventory and work-in-process (WIP), which would reduce their costs. 12 Autonomation is the use of machines "with a human touch" [Ohno, 1988]. That is, machines that can detect defects autonomously. When a defect is detected, the machine stops and cannot continue until the source of the problem is corrected. The ultimate goal of TPS is to reduce the amount of time between when the customer's order is taken and when the company receives the cash for the product. This time reduction is accomplished by eliminating waste. The seven wastes as defined by TPS include [Ohno, 1988]: " " " " " * " waste of overproduction waste of time on hand (waiting on machines) waste in transportation waste of processing itself waste of stock on hand (inventory) waste of movement waste of making defective products Elimination of these wastes can improve system efficiency and reduce costs. The main working unit of TPS is the cell. In mass production systems, all machines of the same type are in one department, which requires parts to criss-cross through the shop from one operation to another. Ohno realized that if he set up a sequence of machines in the proper order of operations, the parts could quickly travel, one part at a time (referred to as single-piece flow), through the U-shaped or L-shaped cell, drastically reducing the distance that the parts had to travel. This layout also allowed workers to operate multiple machines at once. The worker could set-up a part in a particular machine, hit a switch to make the machine begin, and while that machine was running, move onto the next machine in the cell continuing in a similar manner. By creating these "work loops," production efficiency drastically improved over the "one operator, one process" methods of mass production. To keep inventory levels low and assure smooth flow of parts through the cells, balanced production and leveled production were implemented. In balanced production, all operations or 13 cells produce at the same cycle time, which is less than or equal to the takt time [Cochran, 1999, 2.82/2.812 class notes]. Takt time is the pace at which parts should be produced to meet customer demand, and is defined as the available time per shift divided by the average demand per shift. Leveled production means that all operations make the quantity and mix of products demanded by the final customer within a given time interval [Cochran, 1999, 2.82/2.812 class notes]. Thus, instead of producing long runs of the same type of parts, a variety of parts are produced in smaller runs. To achieve this objective, however, changeover times had to be drastically reduced, which was accomplished through single-minute exchange of dies (SMED) [Shingo, 1989]. Takt time and leveling of production should be recalculated and adjusted on a regular basis. This could be weekly, monthly, or annually, depending on the rate of change of customer demand. The method used to enforce just-in-time is called kanban, which is the Japanese word for "card." A kanban is typically a small card in a protective envelope that contains information about pickup, transfer, and production [Ohno, 1988]. The use of kanban prevents overproduction or production of the wrong parts. The bottom line of Ohno's system is constant improvement. In taking a look around the plant, small increments of progress can always be made to help get the product to the customer faster and reduce waste. The Japanese word used to describe this philosophy is "kaizen." 2.2 Manufacturing System Design Decomposition 2.2.1 Axiomatic Design Axiomatic Design provides a means to translate customer needs into specific design implementations through mapping the Functional Requirements (FRs) and Design Parameters 14 (DPs) [Suh, 1990]. The FRs, in the functional domain, are determined directly from the needs of the customer and detail specific requirements that the design must accomplish. The DPs are in the physical domain, and specify the physical implementations set forth by the FRs. Put simply, the FRs state what to accomplish and the DPs state how to accomplish it. A top-level functional requirement is established, with its corresponding design parameter. More functional requirements are derived from the top level DP, which each have their appropriate DPs. This breakdown continues until the bottom level DPs are feasible, implementable solutions to the desired goals. The mapping of FRs and DPs must follow two design axioms [Suh, 1990]: Axiomi: The IndependenceAxiom Maintain the independence of functional requirements (FRs). Axiom 2: The Information Axiom Minimize the information content. 2.2.2 Manufacturing System Design Decomposition Professor David Cochran, Professor Paulo Lima, and the students of the Production System Design Laboratory at MIT have developed a Design Decomposition, using the method of axiomatic design, for a production system. The Manufacturing System Design Decomposition (MSDD) can be used to closely examine "lean" production systems. A better understanding of what needs to be achieved in order to attain a "lean" production system and how to achieve it can be achieved by "zig-zagging" along the path mapped out by the FRs and DPs of the Decomposition. 15 The overall layout of the MSDD is shown in Figure 2-1. The MSD Decomposition can be divided into six sections: (1) Quality, (2) Identifying and Resolving Problems, (3) Predictable are detailed Output, (4) Delay Reduction, (5) Direct Labor, and (6) Indirect Labor. The sections in Chapter 4. Indirect Labor . . . . . .. ....... Quality Identifying and Resolving Problems Direct Labor Delay Reduction Predictable Output Figure 2-1: Overall layout of the MSD Decomposition with the six branches labeled. 2.3 Inspection Because this thesis emphasizes the problems with inspection found at ABB and in the methods nuclear industry, in general, we must first examine the differences between inspection Production at mass production plants and job shops versus the inspection methods in the Toyota System. 16 2.3.1 Statistical Process Control (SPC) and Acceptable Quality Levels (AQL) In the 1920s, at Bell Telephone Laboratories, statistical process control (SPC) began [DeVor et al., 1992]. SPC uses statistics and probability concepts to draw conclusions about a population after examining a small amount of data. These conclusions, however, cannot be stated with absolute certainty. The introduction of uncertainty into the picture causes some problems. Typically, sample inspection involves two particular monitoring tools, acceptance sampling and/or control charts. Sampling is done when it is either too costly, too difficult, or impossible to inspect all the parts. For example, the cost associated with the time needed to inspect every part may be too much, inspection of the parts may be destructive, or not all of the parts may yet to have been produced. In acceptance sampling, a maximum amount of defective parts is allowed to be produced for the lot to be considered satisfactory. This "acceptable quality level" (AQL) means that some defects are accepted in each lot sampled. In today's competitive world of high-quality, no defects are acceptable. Control charts are used to track the mean and variability of a process. Key characteristics of the parts produced are, again, sampled, and their mean value is plotted on an X-average chart, while their range or variability is plotted on an R chart or cy chart, respectively. These charts are known as Shewhart Control Charts, named after their founder, W.A. Shewhart, who worked at Bell Labs in the 1920's. Upper and lower control limits are set on each chart and the characteristics of each sample are plotted. The plot is examined for trends or "out-of-control" data points, which are then evaluated for their probable cause. The theory behind control charts is that there are two types of causes of variation. "Chance" causes are natural causes that are 17 inherent in the process. They are extremely difficult to isolate, and, frankly, are usually too small to really care about. Chance causes result from inherent variability in, for example, material properties and measurement error. Control charts are mainly used to detect the presence of "assignable" causes. Assignable causes are events that alter the accuracy and/or precision of the process. Examples of assignable causes are environmental changes (temperature fluctuations in the factory), tool wear, noise resulting from excessive machine vibrations, and intentional adjustments to the machine's settings. When assignable causes are detected, they must be evaluated and fixed to bring the process under control. Shewhart developed this method of charting the mean and variability of key characteristics of processes based on the fact that natural sample statistics will be "normally distributed" about its mean value. Figure 2-2 shows a normal distribution with the mean value at zero. The width of the curve is determined by the variability, c2. This figure also shows how the normal distribution curve, when still centered at a mean value of zero, "narrows" when 022 < 7 . The upper and lower control limits, in this case, set at +/-2o, are shown on the chart. LCL UCL 22 2 -4y -3c -27 -ic7 0 icy 2cy 3(y 4a x Figure 2-2: Normal distribution curve with p=O, 18 02=1. The region under the curve and outside the control limits is called the x-error, also known as a Type I error. A Type I error is defined as "viewing a process as bad, when it is actually not making defects." cx is known as the "significance of the test." See Figure 2-3. UCL LCL aY2 W2 -4a -3a -2a -la 0 la 2a 3a 4cy x Figure 2-3: The area under the normal curve and outside of the control limits is the x-error. The opposite kind of error that can be made is to "view a process as good, when it is actually making defects." This is known as a Type II error or P-error. The value (1-$) is known as the "power of the test." The value of P is determined from the area under the curve that is inside the original control limits when a shift in the mean value of the process has occurred. Figure 2-4 depicts the value of P for a process whose mean value has shifted over +3a. In a manufacturing setting, either ct-error or 1-error can be minimized, but not both. Minimizing one type of error compromises the other. Table 2-1 illustrates the decision-making (DM) process that results from control charts and Type I and Type II errors [Black, 1991]. 19 0 LC L -4a -3cy -2a -la 0 x L la 2a Enew 3a 4a Figure 2-4: The value of P is equal to the area under the curve of the shifted curve that is within the original control limits. The sample suggested to the DM that: The truth was that the process had not changed. The truth was that the process had changed. The process has not changed. DM takes no actions as nothing is wrong. DM takes no action, but process making more defects; Type II error. The process has changed. DM takes action, but nothing can be found to be wrong with the process; Type I error, DM embarrassed. DM takes action, finds problem with process. DM looks good! Table 2-1: Two types of errors can be made during the "Decision Making" process, Type I and Type II errors. This type of inspection is known as "judgement inspection." Improving judgement inspection increases the chances of detecting defects (minimizing a-error), but does not actually reduce the number of defects produced. 20 To illustrate Type I and Type II errors numerically, consider a standard normal distribution curve with control limits set at +/-3G from the mean value, which is a typical acceptance range. 99.7% of the measured values will fall inside this acceptance range. (See Figure 2-5.) Thus, the u-error, the probability that a part will be marked defective when it is actually a good part, is 0.3%. In other words, there is a 3/1000 chance that the inspector will think that the process is bad, when it has not changed at all. UCL LCL -4cy Ry 2y ICT 0 95.4% G ( Cr 4cy P 99.7% Figure 2-5: Confidence intervals of a standard normal distribution. Now suppose that the mean value shifts over one standard deviation. Instead of the mean value of the process being at zero, the mean value of the process is now at +1. For this shifted standard normal distribution, the area under the shifted curve but still inside the control limits is $ = 97.7%. There is a 97.7% chance that the part will be detected as good, when in reality, the process has shifted. Due to the fact that sample inspection is being used, instead of 100% inspection, this failure to detect the mean shift allows defective parts to be passed on to the customer (internal or external). 21 2.3.2 Judgement Inspection At many companies, inspection is simply defect detection. Improving judgement inspection increases the chances of finding defective parts, but does not actually decrease the number of defective parts. 2.3.3 Informative Inspection TPS used "informative inspection" methods to detect defects immediately after they are made, or, better yet, to detect defects at their source, before the defects are actually made. Preventative inspection reduces the amount of waste (defects) produced, which reduces overall costs. While production is often stopped (money lost) while the problem that caused the defect is being corrected, the cost associated with this production loss is less than the cost that would have incurred due to the production of defective parts (cost of scrap or rework). There are three basic types of informative inspection: self inspection and successive inspection, enhance self inspection, and source inspection. All three methods are used in TPS. In self inspection, each worker inspects his/her own work. A few problems can arise with this type of inspection, though. If the worker misunderstood the work orders, he/she may unintentionally pass along parts that should have been rejected. Another drawback is that the worker may compromise judgement and knowingly accept parts that are actually defective. To keep inspection within the cell but avoid these problems, the worker can pass along his/her parts to the next worker who inspects them. Successive inspection provides the immediate feedback that self inspection provides, but provides more objectivity. Another solution to address the conflict of interest that can arise in self inspection is to provide a "mistake-proofing" device, or poka-yoke, to assist in the inspection. Again, 22 production benefits from the immediate feedback provided by enhanced self-inspection, without the drawbacks of standard self inspection. The best inspection method is source inspection. By monitoring and controlling the conditions at the source of the operation, defects can be prevented rather than detected. Source inspection can trace the problems "vertically" through the process flow or "horizontally" within an operation. The most important aspect of the inspection philosophies of TPS is that every part is inspected. 100% inspection assures that defects are not passed to subsequent processes and certainly not to the final customer. All it takes is for one customer to buy one defective product and that company has lost that person's business forever. 23 3.0 EXISTING CONDITIONS AND PROJECT GOALS 3.1 Current Plant Layout Production of parts in Newington is split up into two categories: light and heavy manufacturing, which also (generally) corresponds to small and large components. These components are appropriately machined and sub-assembled in the respective light and heavy manufacturing buildings. The light manufacturing building is set up mainly in a departmental layout. It also houses a warehouse for the storage of raw stock, as well as partially machined parts and fully-machined parts that are awaiting assembly. A 2-ton boom crane in the light manufacturing building facilitates material handling. See Figure 3-1 for a schematic of the light manufacturing building. The heavy manufacturing building contains assembly areas, as well as machines needed to produce the large components that Newington makes. These machines are permanent fixtures in the building. The heavy manufacturing building is divided into two halves, one of which is served by a 30 ton crane with a height of 29 feet, while the other half is served by a 100 ton crane with a height of 70 feet. See Figure 3-2 for a schematic of the heavy manufacturing building. There are also three fork trucks that are used to move material around - small, medium, and large. In June, at the beginning of the internship, production of the canisters was already underway and plans for a new building (300 feet x 85 feet in area) dedicated to canister production were being developed. In the meantime, fabrication of the canisters occurred on the existing machines in the shops and wherever floor space could be found. 24 m == Celt RCP ASSEMBLY Assembly - storage of finished components awaiting assembly Classroom WAREHOUSE storage of finished receiving components awaiting assembly cut-off s Machine poison strip,.. assembly storage E wellsaj ! - bands 0C _torage tat es aw Lunch M"eNE ROOM TOOL & CUnER GRNINNG AREA -ai Crossee Assembly storage ___- 11~ grinders-- he ""*i deburrng Figure 3-1: Schematic of Light Manufacturing Building. (Note: Drawing not to scale.) SYS 80 CORE SHROUD The work in this area changes daily , CNC 6 G&L HBM CARLTON RADIAL DRILL LOW BAY (30 TON) SYS 80 FAB & FINAL ASSY RCP FINAL ASSY HIGH BAY (100 TON) ______ -CNC GAGE ROOM RCP ASSY FROREIP VBM VBM MAINT. CNC HBM GRAY ~7" TROOM INT ASSY DORRIES VEM TN STAND OFFICES TEST LOOP CRAVEN VBM POWER SUB-STATION BLAST/PAINT FACILITY Figure 3-2: Schematic of the Heavy Manufacturing Building. (Note: Drawing not to scale.) 25 3.2 Flow of Parts and Information Production begins when a project engineer creates a Manufacturing Process Sheet (MPS). The main body of an MPS contains manufacturing and inspection instructions set up in sequences of operations. The MPS also includes a list of parts/raw materials needed (called the "items checklist"), referenced drawings, weld procedures (which are added later), and inspection procedures. The last page of the MPS is an accounting document called a "J50", which is basically the engineer's best estimate of how long each sequence in the MPS should take, and is used to record the actual hours that each sequence takes. The MPS then moves to the weld engineer, who adds the specific welding instructions, if any are necessary. Next, the MPS goes to Quality Assurance (QA), who writes up any Dimensional Inspection Reports (DIR) if they are needed. Manufacturing services receives the MPS next and checks to make sure that all items listed in the items checklist are currently in the warehouse. If they are, then the MPS is ready to be released to the shop floor. At the same time that the MPS is travelling around getting all its necessary components, the project engineer orders the parts/raw stock needed. When the material arrives in Newington, it must go through the receiving department. Large items that will be machined in the heavy manufacturing building are delivered directly to that building. The parts are received at one of two doors, depending on the weight of the material. (Anything greater than 30 tons must be received at the back entrance, where there is a 100 ton overhead crane. The overhead crane at the front of the building is a 30 ton crane.) All other items are delivered to the light manufacturing building, which contains the warehouse. (Note: The warehouse only contains material that has been approved for use. Nothing can be kept in the warehouse until it has passed through receiving inspection.) The receiving department checks to make sure that what has been 26 delivered is truly what was ordered, and also checks to make sure that the material has all necessary certification documents with it. If everything checks out okay, the material is placed in the warehouse until needed. If receiving doesn't approve the shipment, a Non-Conformance Report (NCR) is written stating what the problem is, which then must be verified by QA. The material can either then be returned to the supplier, scrapped, or "repaired" if possible. At this point, manufacturing services releases the MPS to the shop floor. The items checklist is given to a material handler, who kits the parts and delivers them to the proper work station, which could be in either the light manufacturing building or the heavy manufacturing building. If the machining is happening in the heavy manufacturing building, the items checklist page is usually given to a material handler a day or so in advance of when the parts are actually needed. In the light manufacturing building, if the MPS is currently on the shop floor, it is common for the machinist to walk over to the warehouse, himself, and fill out a "material withdrawal request" to get the material that he needs, rather than go through the shop foreman again. The machinist then begins working. After the first part is machined, it must be inspected by Quality Control (QC). To do this, the machinist must go to his immediate supervisor (the shop foreman) and tell the foreman that he needs an inspector for a first piece inspection. The foreman then fills out an Inspection Service Request (ISR), which he usually then brings directly to a QC inspector. Inspection generally happens on a first come, first serve basis, so if an inspector is currently free, he performs the first piece inspection. Otherwise, the machinist must wait for a few minutes until an inspector is available. If QC approves the part, the machinist can then continue machining the remaining parts for that particular sequence of the MPS. Sometimes first piece inspection will happen after a few sequences of the MPS have been performed, which then allows the machinist 27 to perform all of those operations on the remaining pieces. Other times, first piece inspection happens after each individual sequence of the MPS. The project engineer that wrote the MPS determines which of the above procedures to follow. When the machinist has finished machining all the parts, a QC inspector is needed, again, for final inspection, which can be either 100% inspection or sample inspection, depending on the type and number of the parts. At this point, typically, the machinist will move on to another job, and the ISR will be dropped off in the QC "in-box" and tended to the next day or at the first convenience. If necessary, certain inspection requests can be prioritized over others if the job is in high demand. The above procedures hold true for assembly, also. Parts travel all over the shop in Newington. They also travel a good deal between the light manufacturing and heavy manufacturing buildings. Below is a table of a few selected canister parts and the distances that those parts traveled in the current production system at ABB. Part Name, Number Distance traveled (ft.) 5x2 tube steel arms, P05-001 580 Structural Ed, P04-001 2,196.5 Shield Lid, top plate, P03-001 1,293.6 Shield Lid, bottom plate, P03-003 1,293.6 3,009.6 Shield Lid, P03-001 welded to P03-003 Table 3-1: Sample travel distances of selected parts. 3.3 Scrap, Non-conformances and Corrective Action To date, there is no numerical record of the level of scrap in Newington. As for nonconformances, ABB keeps a large database detailing the disposition of all non-conformance 28 reports (NCR). They track failures, defects, operator, and machine work center involved with each non-conformance, as well as all NCRs caused by suppliers. When an in-process defect is made, the machinist brings it to the attention of the foreman, who then fills out an NCR detailing the defect. In the NCR, the foreman will also describe any corrective action measures that could be taken to prevent such a defect from occurring in the future. The NCR then goes back to the project engineer, who writes another MPS to either repair the damaged parts or produce completely new ones. Hopefully, also, the project engineer uses the "corrective action" suggestion in the NCR and edits the old MPS so as to improve the instructions and prevent the same mistake from happening in the future. At the same time, the machinists usually take notes on the operations that they do and keep track, for themselves, of things that go wrong, why, and how to prevent them in the future. Unfortunately, the machinists do not always refer back to these notes and thus, repeat the same mistake. 3.4 Inspection As describe in the previous section, inspection happens many times during each MPS. The first sequence of most MPSs is "QI verify items checklist," which simply requires an inspector to verify that the material has been approved for use. QI is needed for first piece inspection, for verification of fit-ups and weld tacks, for dimensional inspection, as well as for inspection of welds. Inspection of parts can take anywhere from a few minutes to a few hours, depending on the type of inspection that is performed, the size of the part being inspected, and the complexity of the part being inspected. The following histogram shows the distribution of inspection times per part for 26 MPSs that were part of the first canister contract. The mean inspection time is 29 just over half an hour (33 minutes), though the range is from 6 seconds (for a quality inspector to verify the part number of 2816 parts in 3 hours) to 97.5 hours (for the first piece inspection of the 5x2 tube steel arm for the main cross assembly). Histogram 70 1 61 60 50 40 a) IL 30 20 13 10 1 0 0.001 0.751 1 .501 0 0 3.001 3.750 -- --- - - ------- 2.251 - 1 0 1 5.250 More -- --- 4.500 Inspection Time (hours) Figure 3-3: Histogram of inspection times per part for 26 MPSs of the initial canister contract. 3.5 Worker Activities ABB Newington is a union shop. Each worker has a specified role and never cross-trains between roles. There are machinists, assemblers, welders, material handlers, and quality inspectors. Machining and assembly in Newington is highly manual. There is very, very little automation in the plant. To document typical daily activities, a random 2-hour time slot was chosen and 9 workers were observed during this time slot. The following charts show a breakdown of the time spent on each activity per worker and the percentage of total time (9 workers x 125 minutes of 30 observation =1125 minutes) spent on each value adding and non-value adding but necessary operations. Pareto Chart of Activities 250 S200 S150 - - *~1000. 4) 50 0) C ) aCUC )C)U 0 0 C - Ra-)c r- a)0C a)~-- ) .C c .- 0 LL CU LU V> 0 -O 0 0) 00 Activity Figure 3-4: Pareto chart of worker activities during a random 2-hour time slot. Total Time Spent on Each Operation/Activity E 40%- P 35% * 30%,* 25%'1 20%15% S10% 0) :92 0) E -Y 0 ( C 0)0 - 7~ (D C. .0- 0)0. V~( Operation/Activity Figure 3-5: Percentage of total worker hours spent on each operation/activity during the same random 2-hour time slot. 31 tM 0 C W. ) .0= 0)> a) 4) .9 0@ E/ 0a 0 E . CL Sorting the above activities into value-adding, waste, and non-value adding but necessary, results in the following breakdown: Non-value adding but necessary 27% Value adding 37% Waste 36% Figure 3-6: Pie chart of value adding, non-value adding but necessary, and pure waste observed during the random 2-hour observation period. 3.6 Scheduling Initial scheduling put together for the bidding process is based on experience for up-front engineering span, long lead material spans, and rough estimates on duration (normally, the latter is a high level look), plus shipping added onto the end. Production scheduling is based on actual engineering/QA tasks scheduled in hours for 40 hours per week per person. Shop work is based on estimated duration for major operations at the sub-MPS level, but not quite at the operation level. A typical contract at ABB for the System 80 Power Plant components (described briefly in Section 1.1) takes three years to complete. There is a good amount of play in a 3-year schedule, so ABB doesn't necessarily have to adhere to the nitty-gritty details of their proposed 32 schedule. There is a lot of opportunity to "catch up" to the schedule and ship the final product(s) on time. For the canisters, however, ABB must adhere to a much stricter schedule. For example, production of one particular canister contract began in the beginning of March and the first finished canister is expected to ship in July, with another finished product following every two weeks thereafter. 3.7 Project Goals The purpose of this project is to determine to what extent a cellular manufacturing system is truly feasible at ABB-CENP Newington Operations. The intentions of creating a cellular manufacturing system are to improve the flow of parts through the shop, reduce the amount of inventory and work-in-process (WIP), reduce the amount of floor space taken up by production, and reduce the throughput time and manufacturing lead time. It is intended that, at the end of this project, ABB can use this thesis as a basis to begin making changes in their manufacturing system. The ideas set forth in this thesis will provide a starting point for ABB to work off of, as well as illustrate the improvements that can be made by making simple changes. Another goal of this thesis is to address the conflict that arises between the ideals of cellular manufacturing and the necessary "evils" of the nuclear power industry. Specifically, the issue of quality assurance is addressed, as well as the combination of cellular manufacturing and project-shop manufacturing that must take place for the production of these spent fuel canisters. Chapters 4 and 5 explore these issues deeper. 33 4.0 MSD DECOMPOSITION APPPLIED TO ABB NEWINGTON The main goal of this thesis is to analyze the current production system at ABB in order to systematically improve the system as a whole. In Chapter 3, the current situation at ABB was described. In this chapter, the MSD Decomposition will be detailed branch-by-branch and applied to the production system at ABB to determine the necessary path that ABB needs to take in order to transform their plant into a "lean" production system. Suggestions are made or examples are given wherever possible to illustrate potential improvements to ABB's system. As discussed in Chapter 2, the MSD Decomposition is based on axiomatic design and provides a comprehensive approach to designing a lean production system. The ideas of TPS are encapsulated in the structured MSDD. The MSDD is used in this thesis because it provides a systematic framework for analyzing a production system. 4.1 Top Three Levels of the MSD Decomposition Levels I, II, and III of the MSD Decomposition are detailed in Figure 4-1. "FR" states the functional requirement, "PM" details the performance measurement, and "DP" lists the corresponding design parameter. The functional requirements of these three levels outline the ultimate goals of the system. As a company, ABB wants to maximize the long-term return on investment, which means maximizing sales revenue, minimizing manufacturing costs, and minimizing investment over the production system lifecycle. To maximize sales revenue, a company must make sure it's producing quality parts, delivering products on time, and meeting the customers' expected lead time. Minimizing 34 Level I FR1I Maximize long-term return on Investment PM1 Return on investment over system lifecycle DP1 Manufacturing System Design FR11 Leve II Maximize sales revenue PM11 Sales revenue FR12 Minimize manufacturing costs FR13 Minimize investment over PM12 Manufacturing costs PM13 DP1 2 Elimination of non-value adding customer satisfaction Level Ill Investment over system lifecycle -I - - - - DP11 DP1 1 Production to maximize production system lifecycle sources of cost DP1 3 Investment based on a long term strategy I FR111 FR112 FR113 FR121 Manufacture products to target design specifications Deliver products on time FR122 Meet customer expected lead time Reduce waste in direct labor Reduce waste PM111 Process capability PM112 Percentage labor Difference between mean throughput time and PM121 Percentage of operators' time spent on wasted motions and customer's waiting PM113 on-time deliveries in indirect FR123 Minimize facilities cost PM123 PM122 Amount of required Facilities cost indirect labor expected lead timi DP-111 Production processes with minimal variation from the target Quality DP112 Throughput time variation reduction DP113 Mean throughput time reduction DP121 Elimination of non-value adding manual tasks DP122 Reduction of indirect labor tasks Identifying Predictable Delay Direct Indirect and Output Reduction Labor Labor DP123 Reduction of consumed floor space Resolving Problems Figure 4-1: Levels I, II, and III of the MSD Decomposition. 35 manufacturing costs involves reducing waste in both direct and indirect labor, as well as minimizing facilities cost. These functional requirements lead to design parameters that describe a cellular manufacturing system perfectly. The design parameters call for a system that produces with minimal variation from the target, works to reduce mean throughput time and throughput time variation, eliminates all non-value adding tasks, reduces indirect labor tasks, and reduces the necessary floor space. A linked-cell production system exemplifying the philosophies of the Toyota Production System is the best way to implement these design parameters. Before beginning a discussion on each Level IV branch of the MSDD, FR-123 "Minimize facilities cost" needs to be addressed. DP-123 calls for the "reduction of consumed floor space." ABB is currently constructing a new building to house the spent-fuel canister production. At the same time, approximately 30-40% of the already-existing Light Manufacturing Building is occupied by a warehouse. This warehouse contains a large amount of inventory. Much of this inventory is parts that are needed for upcoming contracts that may be received a few months to a few years in advance of when they are actually needed. There are also many smaller components that are ordered in bulk and stored in the warehouse for use whenever needed. If ABB would simply reduced the amount of inventory in the warehouse, they could cut the size of the warehouse drastically and use that added floor space for production. By employing the concept of "just-in-time," whereby parts are received when needed and in the amount needed, ABB can eliminate the need to store parts in the warehouse. To meet this objective, requires having confidence in suppliers to deliver quality products on time, which is an issue that will be addressed in section 4.2, and may not even be feasible. 36 4.2 Quality Figure 4-2 details Level IV of the Quality branch of the MSDD. The very first functional requirement is FR-Q 1: "Operate processes within control limits." As mentioned in Chapter 3, ABB does not currently monitor in-process production or provide immediate (or even moderate) feedback to the operator regarding the quality of the parts. After first-piece inspection, the parts are produced in large batches (usually the entire quantity needed for that particular contract) and are not inspected again until final/sample inspection. At which point, prevention of defects is impossible. It is recommended that ABB begin use of a control system to determine the characteristics of the parts being produced immediately after they are produced. A simple first step would be dimensional inspection, by the operator, of each part as it is produced. Run charts can then be used to alert the operator of the presence of assignable causes of variation. Should problems arise, an investigation must be done to determine the cause of variation and then action must be taken to eliminate the assignable causes of variation due to the machine, operator, method, and material (FR-Q1 1 through FR-Q 14). (For further reading on this subject, refer to Statistical Quality Design and Control: Contemporary Concepts and Methods, DeVor, Chang, and Sutherland, Prentice Hall, 1992.) It should be noted, however, that, as discussed in Chapter 2, sample inspection allows defects to be passed on through the system. 100% inspection is the only way to assure that no defects end up in the hands of the final customer. Taking a slightly deeper look into the elimination of operator assignable causes, FRQ122 states: "Ensure that operator consistently performs tasks correctly." The corresponding DP-Q122 is the use of "standard work methods." This is an area where ABB can make some significant improvements. As it currently stands, the Manufacturing Process Sheets (MPSs) 37 FR-Q1 Operate processes within control limits Level IV FR-Q2 Center process mean on the target FR-Q3 Reduce variation in process output PM-Q3 Variance of process output PM-Q1 Number of defects per n parts with an assignable cause PM-Q2 Difference between process mean and target I--------------------- DP-Q1 Elimination of assignable DP-Q3 Reduction of process noise DP-Q2 Process parameter adjustment causes of variation I FR-Q11 Eliminate machine FR-Q12 Eliminate operator FR-Q13 Eliminate method FR-Q14 Eliminate material FR-Q31 Reduce noise in FR-Q32 Reduce impact of assignable causes assignable causes assignable causes assignable causes process inputs input noise on process output PM-Q11 Number of defects PM-Q12 Number of defects PM-Q13 Number of defects PM-Q14 Number of defects PM-Q31 PM-Q32 per n parts assignable to equipment per n parts assignable to operators per n parts assignable to the process per n parts assignable to the quality of incoming material Variance of process inputs Output variance / input variance DP-Q11 Failure mode and DP-Q12 Stable output from DP-Q13 Process plan design DP-Q14 Supplier quality DP-Q31 Conversion of DP-Q32 Robust process effects analysis operators program common causes design into assignable causes FR-Q121 Ensure that operator has knowledge of required tasks PM-Q121 Number of defects per n parts caused by an operator's lack of understanding about methods DP-Q121 Training program' FR-Q122 Ensure that operator consistently performs tasks correctly FR-Q123 Ensure that operator human PM-Q122 Number of defects per n parts caused by non-standard methods PM-Q1123 Number of defects per n parts caused by human error DP-Q122 Standard work methods DP-Q123 errors do not translate to defects Mistake proof operations (Poka- Yoke) Figure 4-2: Level IV of the "Quality" branch of the MSD Decomposition. 38 written by the project engineers are intended to be the guidelines for outlining the proper operations that need to be done on a part. However, the instructions in the MPSs are not detailed enough to serve as step by step instructions. Thus, many times the machinists have to consult the foreman for exact procedures or decide on their own the best way to go about the process. As a result, multiple methods are employed to produce the same part over time and mistakes are often repeated on subsequent contracts. Though each machinist takes notes on each job for future reference, there's no guarantee that the same machinist will perform the same operations for the next contract. The new machinist may not know about the previous machinist's notes, which may result in the same mistakes being made twice. Therefore, MPSs need to be more detailed and contain specific operating procedures to assure that each worker is using standard work methods. FR-Q14 is another area that ABB needs to look closely at. This functional requirement calls for the elimination of material assignable causes. The corresponding design parameter is a "supplier quality program." As detailed in the performance measure, ABB needs to minimize "the number of defects per n parts assignable to the quality of incoming material." Between March 1999 and February 2000, there were a total of 232 non-conformance reports filed on incoming material. 22% of those Non-Conformance Reports (NCRs) were due to "document deficiency," which means that the material was delivered to ABB without the necessary paperwork stating exactly what the material is, the lot that the material came from, the fact that it meets specified standards, etc.. 9.1% were filed because the certifications on the material were illegible. These types of errors are not acceptable. During the 1999 calendar year, ABB had six suppliers that caused 10 or more NCRs each. One of the key aspects to creating a wellfunctioning production system is to have the same type of "lean" system occur upstream and 39 downstream. In ABB's instance, the quality aspect of a lean production system is not happening upstream, which is resulting in ABB's receipt of defects. As it stands right now, ABB must inspect all incoming material to make sure it meets all requirements and regulations. Ideally, however, ABB shouldn't have to inspect any incoming material at all. Perhaps the best approach that ABB could take to resolve this problem is to tally the NCRs caused by each supplier and note the types of defects that occur and how often each defect occurs from the same supplier. Then, ABB can approach the most troublesome suppliers about improving their quality and have specific aspects of the suppliers' system that need special attention. Creating this linked chain of improvement will benefit the entire production stream. 4.3 Identifying and Resolving Problems This branch of the MSD Decomposition addresses ways to minimize disruptions in production. Figure 4-3 shows the components of this particular branch. Because most operations at ABB are manual, detection of production disruptions is immediate. When a disruption occurs, the machinist/welder/assembler brings it to the attention of his/her supervisor. If possible, the problem is resolved at this point and production resumes. Sometimes, however, either the worker and/or the shop foreman will bring the disruption to the attention of the project engineer that issued the MPS under which the disruption occurred. Again, if the problem can be resolved at this level, then production begins again. Otherwise, management becomes involved, also. FR-R13 states: "Solve problems immediately." This functional requirement is not always fulfilled at ABB. A production disruption is most likely caused by the production of a 40 FR-R1 Respond rapidly to production Level IV disruptions PM-R1 Time between occurrence and resolution of disruptions DP-R1 Procedure for detection & response to production disruptions FR-R11 Rapidly recognize production disruptions FR-R12 FR-R13 Communicate problems to the Solve problems immediately PM-R11 PM-R12 Time between identification of what the disruption is and support resource understanding what the disruption is right people Time between occurrence of disruption and identification of what the disruption is -i171 - I DP-R11 Subsystem configuration to enable operator's detection of disruptions 71 DP-R12 Process for feedback of operation's state PM-R13 Time between support resource understanding what the disruption is and problem resolution Vl V1 - - DP-R13 Standard method to identify and eliminate root cause I FR-R111 Identify disruptions when they occur FR-R1 12 Identify disruptions where they occur PM-R111 Time between PM-R112 occurrence and identification of recognition that disruption occurred disruption and FR-R113 Identify what the disruption is FR-R1 21 Identify correct FR-R1i22 Minimize delay in support resources contacting correct support resources PM-R121 PM-R122 Time between identification and Time between identification of where the disruption PM-R113 Time between identification of where disruption occurred occurred and correct support resource DP-R112 Simplified material flow paths Minimize time for support resource to understand disruption Time between identification identification of what the disruption is and identification of the of what contact of correct support resource PM-R123 Time between contact of correct support resource and support resource understanding what the disruption is the disruption is DP-R111 Increased operator sampling rate of equipment status FR-R1i23 DP-R121 Specified support resources for each failure mode DP-R113 Context sensitive feedback DP-R122 Rapid support contact procedure DP-R123 System that conveys what the disruption is Figure 4-3: Level IV of the "Identifying and Resolving Problems" branch of the MSD Decomposition. defective part, which means that an NCR needs to be filed. As mentioned in Chapter 3, the physical piece of paper detailing the non-conformance travels to approximately 3-4 people, 41 depending on whether the Quality Assurance department is involved or not. It isn't until the project engineer gets the NCR and writes a "repair traveler" to either fix the defective parts or produce new parts, that action can be taken to solve the problem. Quite often, a few days or even weeks will pass before the new MPS is issued. This time delay needs to be eliminated so that production disruption delays are as short as possible. 4.4 Predictable Output Not only do disruptions need to be identified and corrected rapidly, but they need to be minimized, as well. Both the length of time and the frequency of the disruptions must be addressed. The "Predictable Output" branch of the MSDD is detailed in Figure 4-4. The spent fuel storage canisters are a new product for ABB. Construction is at an "experimental" level at this stage in production. One of the main causes for this is that the design of the canisters was completely separate from the manufacturing. Another firm designed the canisters and then "tossed the design over the wall" to ABB, who is fabricating the canisters. For this reason, the beginning of production of each new type of canisters is going to be filled with trial and error procedures until the best methods are found. Once the best methods are determined, ABB can then focus on the "Predictable Output" branch of the Decomposition. Functional requirements FR-P13 and FR-P14 and the subsequent lower level FRs will be key areas for ABB to focus on once they establish exact production methods. To "ensure predictable worker output" (FR-P13), ABB must have a "motivated work-force performing standard work" (DP-P13). Once again, this issue of standard work arises. Knowing exactly which operations were performed on a part makes it easy to pinpoint the source of error and correct it. If different procedures are used to make the same part, multiple reasons may arise 42 FR-P1 Minimize production disruptions Level IV PM-P1 Number of occurrence of disruptions & Amount of time lost to disruptions DP-P1 Predictable production resources (people, equipment, info) FR-P11h Ensure availability of relevant production information PM-Ph1 Number of occurrences of information disruptions, Amount of interruption time for information disruptions DP-P11 Capable and reliable information system FR-P121 Ensure that equipment is easily serviceable PM-P121 Amount of time required to service equipment DP-P121 Machines designed for serviceability FR-P122 Service equipment regularly PM-P122 Frequency of equipment servicing FR-P12 Ensure predictable equipment output PM-P12 Number of occurrences of unplanned equipment downtime, Amount of unplanned equipment downtime D DP-P13 Maintenance of equipment reliability FR-P131 Reduce variability of task completion time PM-P131 Variance in task completion time DP-P122 Regular preventative maintenance DP-P131 Standard work methods to provide program repeatable processing FR-P13 FR-P14 Ensure predictable worker output availability PM-P13 Number of disruptions due to operators, Amount Ensure material PM-P14 Number of disruptions of interruption time for operators due to material shortages, amount of interruption time for material shortages Motivated work-force performing standard work DP-P1 4 Standard material replenishment system FR-P132 Ensure availability of workers PM-P132 Number of occurrences of operator lateness, Amount of operator lateness DP-P132 Perfect Attendance Program FR-P133 Do not interrupt production for worker allowances FR-P141 Ensure that parts are available to the material handlers FR-P142 Ensure proper timing of part arrivals PM-P133 Number of disruptions due to operator allowances, amount of interruption time for worker allowances PM-P141 Number of occurrences of marketplace shortages PM-P142 Parts demanded parts delivered DP-P133 Mutual Relief System with cross-trained workers DP-P141 Standard work DP-P142 Parts moved in process between sub- to downstream operations systems according to pitch Figure 4-4: Level IV of the "Predictable Output" branch of the MSD Decomposition. 43 when trying to determine what caused a defect. In order to be able to predict the output, the same operations need to be performed in the same order each time the same part is made. Standardizing the work will also help in predicting how much time it will take to complete a task. Currently, production scheduling is done at the sub-MPS level, but not quite at the operation level. If standardized work was employed, scheduling could be done at the individual operation level, which would make scheduling more accurate and predictable. This practice will improve scheduling for bidding purposes and increase the chance of delivering the finished products on time to the customer. "Ensure material availability" is FR-P14, with its corresponding DP-P14 of "Standard material replenishment system." The next functional requirements are "Ensure that parts are available to the material handlers" (FR-P141) and "Ensure proper timing of part arrivals" (FRP142). Both of these bottom level FRs would drastically improve ABB's material handling system. The utilization of the computerized inventory system at ABB needs to be improved, as well as the overall philosophy regarding the level of inventory, in general, and the manner in which material is delivered to each work station. Currently, when material is received from a supplier, it is immediately entered into the computerized inventory system. The information entered into the system includes the part number, part description, quantity, location in the warehouse where the material will be stored, who ordered the material, and how much the material cost. Not everyone at ABB uses the same notation to designate, within the program, when a quantity of parts has been allotted to a specific job, which often causes confusion and occasionally either a shortage or an excess of parts. Even though many employees at ABB have been working there for quite some time, if ABB wants to 44 make this inventory system work properly, they need to have another training session and come to a consensus on proper notation and designation methods within the system. Regarding the level of inventory, in general, however, ABB shouldn't need a "warehouse" to store parts. A typical contract for System 80 power plant components takes three years to build. Many of the components arrive at ABB pre-machined, cast, sandblasted, etc.. Each project engineer must keep track of the parts that he will need a few years in advance and make sure that he places the order to the supplier far enough ahead of schedule so that the parts arrive in time for assembly. Quite often, however, parts will be ordered so far in advance that the parts sit in the warehouse for months or even years. This practice is an ineffective use of capital. As discussed in section 4.1, purchasing materials when needed and in the quantity needed will reduce the amount of money invested by the company and also free up space in the Light Manufacturing Building that can be used for production instead of storage. Standardizing the work throughout the system will also help to assure that the material handlers always have the proper quantity of parts that they need to deliver to the next work station at the proper time. When parts are produced on a regular schedule, the material handlers will always know how many parts will be produced in a certain amount of time and can use that fact to stick to a regular material delivery schedule. This notion of producing parts at regular intervals of time will be discussed in more detail in section 4.5 when the idea of "takt time" arises. 4.5 Delay Reduction As can be seen in Figure 4-5, the top design parameters of Level IV of the "Delay Reduction" branch of the MSDD call for single-piece flow, production to run at takt time, 45 Level IV FR-T1 FR-T2 Reduce lot delay FR-T3 Reduce process FR-T4 Reduce run size Reduce delay (caused by ra > r,) delay transportation delay FR-T5 Reduce systematic operational delays PM-T1 PM-T2 PM-T3 Inventory due to lot size delay PM-T4 Inventory due to process delay Inventory due to run size delay Inventory due to transportation delay PM-T5 Production time lost due to interferences among resources DP- T1 Reduction of transfer batch size (single-piece flow) DP-T2 Production designed for the takt time DP-T3 Production of the desired mix and quantity during each DP-T4 Material flow oriented layout design DP-T5 Subsystem design to avoid production interruptions demand interval FR-T21 Define takt time(s) FR-T22 Ensure that production FR-T23 Ensure that part arrival FR-T31 Provide knowledge of FR-T32 Produce in sufficiently cycle time FR-T51 Ensure that support rate is equal to demanded small run resources equals takt time service rate (ra=rs) product mix (part types sizes don't interfere with and quantities) PM-T21 Has takt time been defined? (Yes / No) PM-T22 Difference between production cycle time and PM-T23 Difference between arrival and service rates takt time PM-T31 Has this information been provided? PM-T32 Actual run size - target run size (Yes/No) FR-T52 Ensure that FR-T53 Ensure that production resources support resources production (people/autom ation) don't interfere with (people/autom ation) don't interfere with resources one another one another PM-T51 Production time lost due to support PM-T52 Production time lost due PM-T53 Production time lost due to production resources interferences to support resources interferences with one another with one another DP-T51 DP-T52 DP-T53 Subsystems Ensure Ensure and separation of production work patterns coordination and separation of support work patterns resources interferences with production resources DP-T21 Definition or grouping of DP-T22 Subsystem enabled to customers to DP-T23 Arrival of parts at downstream meet the operations achieve takt times within an ideal range desired takt time (design and operation) according to pitch DP-T31 Information flow from downstream DP-T32 Design quick changeover for material customer handling and and equipment configured to equipment separate support and production coordination access req'ts FR-T221 Ensure that automatic cycle time minimum takt time FR-T222 Ensure that FR-T223 Ensure level cycle time mix manual cycle time 5 takt time PM-T221 Has this been achieved? (Yes / No) DP- T221 Design of appropriate automatic work content at each station PM-T223 Is average cycle time less than PM-T222 Has this been achieved? (Yes / takt time in desire d time Nol interval? DP- T222 Design of appropriate operator work content/loops DP-T223 Stagger productio n of parts with different cycle tim es Figure 4-5: Level IV of the "Delay Reduction" branch of the MSD Decomposition. 46 balanced and level production, as well as minimum transport of material. All of these parameters are prime descriptors of a cellular manufacturing system. The first step in reducing delay is to create single-piece flow. When large batch sizes are used, parts end up sitting after being machined or assembled, waiting for the rest of the batch to go through the same operation. The parts don't move on to the next operation until that particular operation has been performed on every piece in the batch. This routine is one of the seven wastes as defined by the Toyota Production System. In a cellular manufacturing system, each part is passed on one at a time as each operation is completed. This allows for final products to be produced much sooner than in batch production and also reduces the quantity of work-in-process (WIP). The next functional requirement, FR-T2, is to "reduce process delay." This is accomplished by running production at "takt time," which is the available time per shift divided by the average demand per shift. At the time of this thesis project, ABB was working on its first canister contract. While this contract ended up being put on hold due to design problems, the cellular design suggested in this thesis is based on this initial contract. This thesis aims to set an example of how to design the cellular system, not necessarily detail the exact system that ABB should develop. Therefore, all numbers and details used to design the cellular system described in the remainder of this thesis are fictitious. 4.5.1 Takt Time FR-T21 says that takt time(s) need to be defined. At ABB, based on a working schedule of 6 hours and 45 minutes of work per shift (which results from subtracting breaks from the full 47 8-hour day), 2 shifts per day, and 22 working days per month, and assuming customer demand of 50 canisters per year, the takt time is: 405 minutes/shift (50 canisters/12 months)/(44 shifts/month) = 4276.8 minutes/canister = 71.28 hours/canister This calculation means that every 71.28 hours of operation, a finished product should be produced. The finished canister is made up of subassemblies, which are, in turn, made up of individual components. Each of these subassemblies will be made in separate cells, which will run at their own takt times, depending on the quantity of subassemblies needed per canister. For example, there is only one shell per canister. The shell arrives at ABB in four segments, which are welded together and then go through a series of machining operations. One shell should be produced every 71.28 hours to feed the final assembly cell. There are 32 main cross assemblies, however, which means that the main cross assembly cell should produce one complete product every 133 minutes. Continuing with the example of the main cross assemblies, we further break them down into individual components, which will come from machining cells. Each machining cell will produce at its own takt time, depending on the number of parts going through the cell and the level of demand. 48 4.5.2 Floor Layout One of the main ideas of a linked-cell system is to minimize the throughput time, to maximize workers' effectivity, to highlight problems, and to provide an environment for continuous improvement. As a result, cells are typically U-shaped and machining cells are physically located so that they feed easily into the subassembly cells, which, likewise, are set up to feed easily into the final assembly cell. The ship building industry uses a set-up similar to that shown in Figure 4-6 [Storch et al.]. Note, however, that the overall shape of this layout is a square. ABB's new building, however, in going to be 300 feet x 85 feet. Such a rectangle makes it difficult to surround final assembly with the subassembly cells, and impossible to place machining cells in a ring beyond that. Adequate pathways must be left between the cells to allow for passage of fork trucks and large parts moved by overhead cranes. Adjusting to this long, skinny rectangular shape, a possible layout for the canister production is shown in Figure 4-7. This possible layout pertains to a general form of a spent fuel canister with components Machining Cell ubcssemb y Subassembly aol components come from machining cells Machinir g Cells components purchased from outside vendor Fina ALAemhly LA Shipping/ Receiving Subassembly Subassembly Machining Cell all components purchased from outside vendor components come from machinig cLls Figure 4-6: A square layout, with the final assembly cell surrounded by a ring of subassembly cells, which are fed by machining cells, is typical of the ship building industry. 49 consisting of a shell, a top lid with a ventilation system, a bottom lid, and some type of inner network that holds the fuel rods and keeps them separated within the canister. Material flow is shown by solid lines, while information flow is shown by dashed lines. ( \Machining KJjJHiH1H Celts FinaL s rb -0.A U L 0 Network Sub as sembly 10 ni -- V ti t Ventilati ni Ma system hini n Cel To U Lid- TpSubassemby osrk1y(H 1 material Top Lid and Bottom Lid machining occurs in Heavy Manufacturing Building Shell machining occurs in Heavy Manufacturing Building information Figure 4-7: Possible linked-cell layout for the production of canisters at ABB. Within this system, kanban would be used for final assembly to notify each subassembly cell when to produce another part, which, in turn, would signal the appropriate machining cells. Material handling loops would need to be established to provide the proper amount of material to the proper cells at a specified interval of time. For the machining cells, new machining centers will need to be purchased and/or machines currently in other buildings may need to be moved to the canister building. The current system of machining some parts in the Light Manufacturing Building and transporting them to the Heavy Manufacturing Building for final assembly is inefficient. The overall cost of purchasing new machines (such as a small lathe or milling machine) will be less than the cost associated with transporting parts back and forth between all three buildings over time. There is 50 a catch to this layout, however. The two lids and the shell require machining on the large (2-3 story high) machining centers that are located in the heavy manufacturing building, located adjacent to the canister building. These machines are extremely expensive and are, literally, part of the building. Purchasing multiples of these machines is simply not practical. The canister building will be build adjacent to the Heavy Manufacturing Building. Therefore, it is recommended that the current machines in the Heavy Manufacturing Building remain the machining centers used for these large canister components. However, it is important to try to minimize the distance that the parts need to travel. That is why, as can be seen in Figure 4-7, the subassembly areas for these large components of the canisters should be located as close as possible to one of the pathways between the buildings. It is also important to note that these pathways and doorways should be large enough to handle the passage of such components and that overhead cranes, if needed, should be installed appropriately. 4.5.3 Sample Machining Cell Functional requirements FR-T221, FR-T222, and FR-T223 all deal with the subsystems of the entire system, whereas the previous section dealt with the system as a whole. FR-T221 states, "Ensure that automatic cycle time minimum takt time." Most of the operations at ABB are manual, so this FR can't quite be dealt with yet. As ABB acquires more and more automated machinery (which is recommended if new machines are purchased for the machining cells), then this FR and corresponding DP can be addressed. FR-T222 states "Ensure that manual cycle time takt time." This FR is extremely important to a cellular system at ABB. DP-T222 calls for the "design of appropriate operator work content/loops." To illustrate what this FR and DP mean, a sample machining cell will be 51 discussed. To create this sample machining cell, various steps were taken. First, all parts of the canister were compared to determine which machining centers were used to make the part and in which order the machining centers were used. Each cluster of the machine-part matrix represents a part family that can be produced in a cell. The sample machining cell described in this thesis is shown by the shaded portion of the chart in Figure 4-8. Part Number Part# 1 TMM AJV X X Li X 2 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 X X X X I X X X XX X XX X X X X X X X X VM TMM2 WS BSW VH3 Pch CPM COS2 TMM3 SBE TMM4 X X X X X X X - _ X X X X X X X .X X x X X X X X X GHBM CRD FRP DOR 32 33 X HBM COS1 3 X X X X X X X X X X X X X X X X X X X X Figure 4-8: Machine-part matrix used to establish part families. To determine the takt time of the cell, the demand of the parts (quantity per canister x 50 canisters per year) must be determined. Part Number Quantity/Canister 17 64 18 128 19 16 20 12 21 12 22 32 23 4 Total # of Parts 268 Table 4-1: Part demand in sample machining cell. 52 Thus, the takt time of the cell is 15.96 minutes/part. This takt time means that the cycle time of each operation within the cell must be less than or equal to 15.96 minutes/part. Table 4-2 lists the cycle times at each machine for each part in the sample cell. VH3 Pch CPM 3.5 0.35 14.2 6.67 Part # COS TMM WS BSW 17 18 2.81 2 1.5 1.5 4.23 6.44 19 20 21 22 2 1.03 1.03 3.32 1.5 1.5 1.5 1.5 23 1.5 3.32 Table 4-2: Cycle times of each part at each machine in the sample cell. All times are in minutes. 1.8 4.05 SBE 6.67 3.2 3.2 Fortunately, the cycle times are all less than takt time already, so there is no need to divide any operations into multiple tasks. To achieve leveled production, there should be a proper mix of parts going through the cell. Before small run sizes of parts can be achieved, however, set-up times must be drastically reduced [Shingo, 1989]. Figure 4-9 shows a possible layout for this sample machining cell. This cell produces the main cross braces, as well, as the corner braces for the corner cell assemblies. Two of the standardized work combination sheets for two of the parts that go through this cell are in Appendix A. Similar charts were done for all parts in the cell. In this particular cell, not every part goes to every work station. The numbering system in the figure refers to the order in which the parts move to each machining center. Part number (P/N) 18 follows path a, P/N 19 follows path b, P/N 17 follows path c, and P/N 20 follows path d. P/N 22 and P/N 23 exit the cell after operation #3 and go to the sandblasting area. P/N 21 exits the cell and goes to the next subassembly cell after operation #3. Possible work loops are shown. 53 P/N 22, P/N 23 to sonoblost All drenslons ore a4,proxlnote. PN2 xt 1e t P/ ColM 7 '_8q T Punct4o sJ w Insa.eu hole Saw Horionta ext _ _cl __ _ _ __ J[~~J I a I~e7 NI _ __ __Q_ 6c- Fiure 4-9 osbelyu o h ahnigcl htpoue 9s ela hecre9el rcs the mancos rcs at o Tabe 43 sowstheimpoveent ofthesamle ellove th jo shp mtho.o prdcngtesmeprs.(l Istane anaieaeapoxmt. Floor space Throughput time Job Shop 3700 sq. ft. 4131 minutes (additional waiting Machining Cell 1250 sq. ft. 25 minutes % Improvement 66% reduction 99% reduction 2 (+occasional 50% reduction time possible) Number of workers minimum of 4 required Travel distance of inspector) 580 ft. 105 ft. 82% reduction parts Table 4-3: Improvements resulting from formation of sample machining cell. (All times and distances are approximate.) Similar machining cells can be formed for other part families. Assembly cells must be formed, also. Much of the assembly of the canisters is stationary. Because the canister components are so large when they are sub-assembled, and especially final assembled, moving 54 the assemblies from work station to work station would be inefficient and costly. This is where ABB's system must combine a traditional "project shop" atmosphere with the improvements of a cellular manufacturing system. 4.5.4 Inspection In the above sample machining cell, note that the inspection stations are integrated into the cell. The procedure of physically taking parts to a gauge room to inspect them is a waste of time and material handling. There is no need to relocate parts simply to inspect their dimensional features. In theory, there is also no need to call in special "inspectors" to do the job, either. Unfortunately, this is where ABB runs into a need to compromise the TPS ideals. ABB Newington must abide by the regulations set forth in "The American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section III, Division 1, Nuclear Power Plant Components" and/or "Section III, Division 3, Nuclear Power Plant Components (Containment Systems and Transport Packagings for Spent Nuclear Fuel and High Level of Radioactive Waste)." All components that fall into this category must be physically "Code Stamped" with either N, N-TP, NA, NPT, or NPT-TP ASMIE Code Stamps. As stated in the "Quality Assurance Program Requirements for Nuclear Facilities, ANSI/ASME NQA-1," Basic Requirement 10: Inspection: "Inspections required to verify conformance of an item or activity to specified requirements shall be planned and executed. Characteristics to be inspected and inspection methods to be employed shall be specified. Inspection results shall be documented. Inspectionfor acceptance shall be performed by persons other than those who performed or directly supervised the work being inspected." (emphasis added) 55 This requirement is in direct conflict with the philosophies of the Toyota Production System, where the ideal is to have 100% inspection performed by the workers, themselves. Changing this practice involves more politics and economics than technology. To change the code would require joining ASME, serving on the committee that forms the codes and standards, and working from the inside to change them. ABB would have to form a cell, knowing that using an external inspector is not the best way to go, and include the inspector in the work loop of the cell to allow the inspector to see the difference between the job shop way of inspection versus the lean way of inspection. To change the ASME Code would require the cooperation of a qualified inspector who understands lean manufacturing. A preliminary code would have to be drafted for inspection requirements in a lean manufacturing cell environment (Black, 2000). Another compromise between the TPS ideals and the ASME Code is possible. The regulations require specially-qualified personnel to perform the final inspection and sign off that the parts have been approved for use. The regulations also, however, allow for sample inspection to be done, rather than requiring 100% inspection. This difference is where ABB can take advantage of the regulations and create the compromise. 100% inspection can be performed in the cells by the workers as stipulated by TPS, while a "qualified inspector" can roam between a few cells to perform random sample inspection as required by the ASME regulations. Inspection sometimes calls for non-destructive examination. These tests require more time than simple dimensional inspection. Perhaps one or two of the inspectors on each shift could be specifically designated to do all NDE tests, which would require these inspectors to rotate between the cells that require such inspection. In any case, inspection should be performed as part of the cell loop. 56 4.6 Direct Labor The next branch of the MSDD is the "Direct Labor" branch and is show in Figure 4-10. Level IV FR-D1 Eliminate operators' waiting on machines FR-D2 Eliminate wasted motion of operators PM-D1 FR-D3 Eliminate operators' waiting on other operators PM-D3 Percentage of operators' time PM-D2 spent waiting on equipment Percentage of operators' time spent on wasted motions Percentage of operators' time spent waiting on other operators IZILIZ-7--i771 DP-D1 Human -Machine separation DP-D2 Design of workstations / work- loops to facilitate operator tasks FR-D11 Reduce time operators spend on FR-D12 Enable worker to operate more than non-value added tasks at each station one machine / station PM-D11 PM-D12 Percentage of operators' time Percentage of stations in a system spent on non valueadding tasks while that each worker can operate FR-D21 Minimize wasted DP-D3 Balanced work-loops FR-D22 FR-D23 motion of operators between stations Minimize wasted motion in operators' work preparation Minimize wasted motion in operators' PM-D21 PM-D22 PM-D23 Percentage of operators' time Percentage of operators' time spent on wasted motions during work Percentage of operators' time spent on wasted motions during work spent walking between stations work tasks prparti~n prepaationroltina waiting at a station DP-D11 DP-D12 DP-D21 Machines &stations designed to run autonomously DP-D22 Workers trained to operate multiple stations DP-D23 Machines / stations configured to reduce walking distance Standard tools / equipment located at each station (5S) Ergonomic interface between the worker, machine and fixture Figure 4-10: Level IV of the "Direct Labor" branch of the MSD Decomposition. FR-D1 requires elimination of "operators' waiting on machines," which is accomplished by "human-machine separation." Currently at ABB, most of the work is manual. Many of the simple lathes, milling machines, etc. that are used are not automated. This ties the workers to the machines for extended periods of time. If ABB could purchase automated machinery, operations could be performed at the push of a button and allow the worker to move on to the next operation 57 in the work loop. In order for this to be truly effective, though, the machines must also be "autonomous," meaning that the machines can detect when a defect has occurred, and shut themselves down until a worker can correct the source of the problem. The next functional requirement is an area where ABB can easily take large strides toward improving their system. FR-D2 states "Eliminate wasted motion of operators," which is further broken down into three FRs. The first of which, FR-D21, states: "Minimize wasted motion of operators between stations," which is accomplished by DP-D21: "Machines/stations configured to reduce walking distance." The development of a linked-cellular system will do exactly this. The walking distance to the next machine in the sequence will be 5 feet instead of 30 feet. FR-D22 calls for minimizing "wasted motion in operators' work preparation." Having all necessary tools/equipment at each workstation is the best way to accomplish this. As noted in Figure 3-6, 36% of the worker time observed during a random 2-hour period was waste. Much of this wasted time was due to the fact that workers had to walk across the shop to get the tools that they needed. This retrieval time is a waste of resources. Each work station should contain every tool and supply that the worker will need for the job. This could mean that there are "mobile" tools/supplies that move around to various stations depending on the type of work that is to occur at each station on that particular day. Such a system would mean that some tools that are only used occasionally could be traded between stations, rather than having to supply each station with every tool only to have some of them sit there, not being used, for extended periods of time. Any tools or supplies that are used regularly at a station should be kept there permanently so that the worker always has it on hand whenever he needs it. 58 The third FR in this sub-branch calls for minimizing "wasted motion in operators' work tasks." The corresponding DP is the "ergonomic interface between the worker, machine, and fixture." This means easy loading and unloading of parts and easy use of fixtures and jigs, which were common improvements already being made during this internship. The remaining segment of the Direct Labor branch requires "balanced work loops" as a way to "eliminate operators' waiting on other operators." This functional requirement is an issue that will have to be worked out in greater detail when the cells are actually formed. 4.7 Indirect Labor Figure 4-11 shows the "Indirect Labor" branch of the MSDD. Both FRs and DPs of this branch deal with decreasing the amount of indirect labor involved in running the production system. This branch of the tree is a basic goal of any company and should always be improved upon whenever possible. Level IV FR-11 Improve effectiveness of production managers FR-12 Eliminate information disruptions PM-11 Amount of indirect labor required to manage system PM-12 Amount of indirect labor required to schedule system DP-11 Self directed work teams (horizontal organization) DP-12 Seamless information flow (visual factory) Figure 4-11: Level IV of the "Indirect Labor" branch of the MSD Decomposition. 59 5.0 CONCLUDING COMMENTS 5.1 Summary By making the transition from job shop to lean manufacturing, ABB will see significant improvements in their production system. If the improvements suggested in this thesis are implemented, ABB will see a reduction in the floor space consumed, reduced scrap and re-work levels, decreased production costs, decreased throughput time, and increased quality. The production system will become more structured and systematic, which will provide a better atmosphere for making continuous improvements. 5.2 Obstacles The major obstacles that ABB will encounter in making the transition to the "lean" system design are resistance to change, the challenge of mixing cellular manufacturing with project shop manufacturing, and the quality regulations set forth in the ASME Code. The first two obstacles can be dealt with over time and with some patience and persistence. The key to overcoming resistance to change is to make sure that all change is a team effort. The transition cannot be made by one or two extremely motivated individuals. Everyone, from upper management on through the machine operators, must be involved with making decisions and implementing change. Hopefully, as changes are made, people will see the results and be encouraged to continue. Dealing with the mix of cellular and project shop manufacturing will be a challenge because there aren't many examples in existence to learn from. Much of the literature on "lean" manufacturing and implementation of the Toyota Production System describe fast-paced, high volume production, such as the automobile industry, where parts are in continuous motion. This 60 is obviously not the case at ABB. Fortunately, some companies in the aerospace and ship building industries have begun implementing cellular manufacturing systems that require some parts/assemblies to remain stationary. Working the ASME code regulations into a cellular manufacturing system, however, is going to be very difficult. The Code prohibits self inspection and successive inspection since inspection cannot be done by anyone involved in making the part, which means that separate inspectors must be involved. Quality in the nuclear industry takes on a slightly different meaning than most other industries. Even the smallest defects can have devastating effects. Thus, it is understandable that the nuclear industry is extra cautious about inspection. However, being cautious does not mean that there must be specially designated inspectors. Dimensional inspection can be done just as well by a worker in the cell as it can be done by a special inspector. If there is concern that a worker may compromise judgement while inspecting parts that he, personally, made, then successive inspection should be used. Of course, this means that the workers will have to be properly trained to know exactly how to use the measuring devices, as well as how to read drawings properly and understand tolerances. When it comes to inspecting welds and performing NDE tests, however, specially trained inspectors may still be needed. To train each worker to perform each NDE test would be more time consuming and costly than employing a few specially trained inspectors. 5.3 The Next Steps The very first step in a lean implementation process is forming a team of people, ranging from top-level management, to engineers, to shop workers, who will be the heart and soul of the 61 changing process. At ABB-CE Newington Operations, that team would involve a wide variety of people including the general manager, project manager, plant manager, union steward, manufacturing engineer(s), design engineer, maintenance foreman, quality engineering, NDE level III supervisor, production control, and shop workers. Because Newington is so tight-staffed, it would be most beneficial if this team designated a few people as the core of the group, the central cluster that would dedicate much of their time to making this cellular implementation work and constantly working to improve the current system. The rest of the larger team must also be involved in terms of keeping up to date on the progress being made, giving their input whenever something new is implemented or whenever they have an idea for improvement, and as support for the central core. Without the support and backing of the entire team, the cellular implementation will not be successful. Another step that needs to be taken early on is to improve the accounting system at ABB. Having an accurate count of exactly how much time each operation takes is vital to making improvements. Without this information, ABB won't know which operations are holding up production and delaying throughput time. First of all, the MPSs need to be more detailed and each process needs to be distinctly separated. Currently, multiples tasks are included in the same "sequence" on the MPS, which means that the times to perform each separate task are lumped into one total amount on the accounting sheet. Another problem is that times for each sequence of the MPS often get jumbled. For example, suppose a worker spends 6 hours of his day on one particular sequence but then works on the next sequence for the last 45 minutes of his shift. Usually, the worker will simply put all 6 hours 45 minutes down as the first sequence, rather than distinctly separating the last 45 minutes. This results in inaccurate records of time requirements. Also, if a machine 62 breaks down, the downtime is recorded as time for the sequence that was currently being worked on at the time of the breakdown. Thus, something that only takes 4 hours to complete, may actually say that it took 8 hours to complete, when 4 hours of that time was spent repairing a machine. Similarly, time spent retrieving tools and supplies is recorded as time spent on the particular machining/welding/assembly sequence. All of the above misrepresentations of time snowball into one large time chunk for each sequence that no one can completely explain. As a result, the accounting records are of no use to anyone in the future. The records can't be used to improve time estimates for bidding purposes, or as a means to pinpoint true critical paths and improve processes. In order for a truly smooth cellular manufacturing system to be designed and worked out, the accounting system (time recording system) needs to be revamped. Accurate time logging needs to be done for each sequence of each MPS, where each sequence consists of one operation. Activities such as machine breakdowns, tool searching, lunch breaks need to be clearly differentiated from actual production. As mentioned in Chapter 4, ABB also needs to begin keeping track of the amount of scrap produced, the amount of work-in-process, the amount of inventory, and the amount of rework done. These performance measures will help provide motivation for making changes and will also help gauge the level of improvement over time. 5.4 Final Comments The main point of this thesis was to show how the MSD Decomposition, based on the philosophies of the Toyota Production System, can be applied to the current production system at ABB in order to make improvements to the system as a whole, while coping with the constraints 63 and speed bumps of the nuclear industry. The recommendations put forth in this thesis are only starting points. Continuous improvement efforts must be made through kaizen teams. This thesis has discussed each branch of the MSD Decomposition separately as related to the production system at ABB. Certain FRs and DPs were emphasized over others because of their relevance to the current system at ABB, though every single one is important to the system as a whole. Making the transition to lean isn't easy or cheap, but is worth the investment in the end when the money that the new system is saving over the old system begins to add up and customers are more satisfied because they're receiving better quality products faster than before. 64 REFERENCES American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section III, Division 1, Nuclear Power Plant Components. American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section III, Division 3, Nuclear Power Plant Components (Containment Systems and Transport Packagings for Spent Nuclear Fuel and High Level of Radioactive Waste. Black, J.T., The Design of the Factory with a Future. McGraw-Hill, Inc., New York, NY, 1991. Cochran, David S., "2.82/2.812 Design and Control of Manufacturing Systems Course Notes", Massachusetts Institute of Technology, Cambridge, MA, 1999. Cochran, David S. and Paulo C. Lima, "Manufacturing System Design Decomposition, version 5.1". Production System Design Laboratory, Massachusetts Institute of Technology, 2000. DeVor, Richard, Tsong-how Chang, and John W. Sutherland, Statistical Quality Design and Control: Contemporary Concepts and Methods. Prentice Hall, Upper Saddle River, NJ, 1992. Interviews with Richard Brillon, Gerry Dopp, Ken Fortin, Dave Kelley, Richard Talbot, Robert Thompson, Scott Vallimont, and Carl Waterhouse, all of ABB Combustion Engineering Nuclear Power Newington Operations. Interview (via telephone) with Dr. J.T. Black, June 2, 2000. Ohno, Taiichi, Toyota Production System: Beyond Large-Scale Production. Productivity Press, Cambridge, MA, 1988. Shingo, Shigeo, A Study of the Toyota Production System From an Industrial Engineering Viewpoint. Productivity Press, Portland, OR, 1989. Storch, Richard Lee, Cohn P. Hammon, Howard M. Bunch, and Richard C. Moore, Ship Production, Second Edition. The Society of Naval Architects and Marine Engineers, Jersey City, NJ, 1995. Suh, Nam P., The Principles of Design. Oxford University Press, New York, NY, 1990. 65 Appendix A The following standardized work combination sheets are for the tube steel arms in the sample machining cell presented in Chapter 4. Similar sheets were done for all parts going through the cell. All operations are completely manual. Page Standard Operations Work sequence 02 5x2 Tube Steel Arm Cell # Work content Machine 120s 3s 90s 2s 04 Inspect length 30s 06 Mark P/N, S/N 20s 08 Deburr & clean ID 60s 10 Punch holes 10s 12 Inspect holes 60s 5s 20 Deburr all edges (after milling) 360s 4s 14 Mill chamfers 30s 120s 16 Mill weld preps 30s 240s 18 Inspect chamfers & weld preps 240s 850s 5 Walk I0s Takt Time: 15.96 min. 10 15 - - 4s 16s 3s 3s 2s 586s pages - Walking Operations Time (minutes) Cut to length on cut off saw TOTAL Main Cross Assy Time (seconds) Manual 1 Machine Processing - - - - - - Routine Sheet Part name of Manual operation Date: 17 Part no. 1 26s Takt lime 1462s (24.4 min) 66 20 25 Page 19 Part no. Standard Operations Work content Work sequence Cut to length on cut off saw 02 I0s Machine 120s 5 Walk 3s Takt Time: 15 10 - 30s Inspect length 06 Mark P/N, S/N 08 Deburr & clean ID 60s 2s 10 Mill holes 20s 3s 2O0s 12 Inspect 60s 5s 20 Deburr all edges (after milling) 360s 4s 14 Mill chamfers 30s 120s 16 Mill weld preps 30s 240s 18 Inspect chamfers & weld preps 240s TOTAL 15.96 min. 860s 3s 2s 670s Walking Operations Time (minutes) Time (seconds) 04 holes Main Cross Assy Cell # Manual 24s 1554s k2j.9 11n.) 1 ~CA. ~ 67 pages Processing- - --- ______________________Machine 2x2 Tube Steel Arm 1 of Manual operation Date: Routine Sheet Part name 1 A ...... T kdt Ti, a me, 20 25 -