SECTION 01320
CONSTRUCTION SCHEDULES
PART 1
1.01
GENERAL
SECTION INCLUDES
A.
Prepare detailed schedule of all construction operations and procurements to be reviewed
by parties attending the preconstruction conference.
Schedule shall be approved by the OWNER prior to Notice to Proceed.
1.02
FORMAT AND SUBMISSIONS
A.
Prepare construction and procurement schedules in a graphic format suitable for
displaying scheduled and actual progress.
B.
Submit four (4) copies of each schedule to the OWNER for review.
The OWNER will return one copy to the CONTRACTOR with revisions suggested or
necessary for coordination of the Work with the needs of the OWNER or others.
1.03
CONTENT
A.
Construction Progress Schedule
1.
Show the complete work sequence of construction by activity and location.
2.
Show the dates for the beginning and completion of major task items. At a
minimum, show the following items for each phase of the project:







3.
B.
Werner Elem.
Removal of existing asphalt pavement and landscape materials;
Removal of existing concrete work (sidewalks, curb and gutter, and drain
pans);
Preparation of subgrade and grading;
Installation of new concrete work (driveway, entrance ramp, sidewalk,
curb and gutter, curb access ramp, drain pans, and bus canopy pavement);
Installation of new asphalt pavement;
Installation of bus canopy wheel stops; and,
Pavement markings.
Show projected percentage of completion for each item as of the first day of the
month.
Report of delivery of equipment and materials.
1.
Show delivery status of critical and major items of equipment and materials.
2.
Include a schedule which includes the critical path for Shop Drawings, tests, and
other submittal requirements for equipment and materials.
01320-1
Construction Schedules
1.04
PROGRESS REVISIONS
A.
Submit revised schedules and reports when changes are foreseen, when requested by
OWNER, and with each application for progress payment.
B.
Show changes occurring since previous submission.
1.
2.
C.
1.05
Actual progress of each item to date.
Revised projections of progress and completion.
Provide a narrative report as needed to define:
1.
Anticipated problems, recommended actions, and their effects on the schedule.
2.
The effect of changes on schedules of others.
OWNER'S RESPONSIBILITY
A.
OWNER's review is only for the purpose of checking conformity with the Contract
Documents and assisting CONTRACTOR in coordinating the Work with the needs of the
Project.
B.
It is not to be construed as relieving CONTRACTOR from any responsibility to
determine the means, methods, techniques, sequences and procedures of construction as
provided in the General Conditions.
PART 2
PRODUCTS (Not Applicable)
PART 3
EXECUTION (Not Applicable)
END OF SECTION