SECTION 01310 PROJECT MEETINGS PART 1 1.01 GENERAL SECTION INCLUDES A. Pre-Construction Conference: A Pre-Construction Conference will be held after Notice of Award and before the Notice to Proceed; the date, time and location will be determined after Notice of Award. The conference shall be attended by: 1. 2. 3. 4. CONTRACTOR and CONTRACTOR’s Superintendent CONTRACTOR’s Surveyor and Subcontractors OWNER Others as requested by the CONTRACTOR or OWNER. Unless previously submitted to the OWNER, the CONTRACTOR shall bring to the conference a tentative schedule of the construction project, include in the schedule shop drawings and other submittals. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda will include: 1. 2. 3. 4. 5. 6. 7. 8. 9. B. CONTRACTOR’s tentative Schedule Permit applications and submittals, including Erosion and Sediment Control Plan, and Traffic Control Plan Transmittal, review and distribution of CONTRACTOR’s submittals Processing applications for payment Maintaining record documents Critical work sequencing Field decision and change orders Use of premises, office and storage areas, staging area, security, housekeeping, and OWNER’s needs CONTRACTOR’s assignment of safety and first aid Construction Progress Meetings: Progress meetings will be conducted weekly or at the discretion of the OWNER. These meetings shall be attended by the OWNER, the CONTRACTOR’s representative and any others invited by these people. The meeting will be conducted by the OWNER and the OWNER will arrange for keeping the minutes and distributing the minutes to all persons in attendance. The agenda of these project meetings will include construction progress, the status of submittal reviews, the status of information requests, critical work sequencing, review of strategies for connections into existing facilities, status of field orders and change orders, and any general business. Werner Elem. 01310-1 Project Meetings PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01310-2 Project Meetings