Estimation of Ship Construction Costs by Aristides Miroyannis Naval Architecture and Marine Engineering B.S., (2005) Webb Institute, NY Submitted to the Department of Mechanical Engineering in Partial Fulfillment of the Requirements for the Degree of Master of Science in Mechanical Engineering at the MA SS OCH US Massachusetts Institute of Technology ETTSNsTrr TE June 2006 LIBRARIES @ 2006 Massachusetts Institute of Technology OARKER All rights reserved ............. Signature of Author ........... I Certified by .......... Ar Isides Miroyannis May 12, 2006 . . . . . . . ...--Henry S. Marcus Profes or of Marine Systems Thesis Supervisor Accepted by ........ Professor Lallit Anand Chairman Department Committee on Graduate Students MITLbraries Document Services Room 14-0551 77 Massachusetts Avenue Cambridge, MA 02139 Ph: 617.253.2800 Email: docs@mit.edu http://Iibraries.mit.edu/docs DISCLAIMER OF QUALITY Due to the condition of the original material, there are unavoidable flaws in this reproduction. We have made every effort possible to provide you with the best copy available. If you are dissatisfied with this product and find it unusable, please contact Document Services as soon as possible. Thank you. The images contained in this document are of the best quality available. OUTLINE Outline................................................................................................................................. 2 List of Figures..................................................................................................................... 3 A cknow ledgem ents:....................................................................................................... 5 Abstract ............................................................................................................................... 6 Introduction......................................................................................................................... 7 Chapter 1 - Overview of U S N avy:..................................................................................... 9 Reasons for Cost Overruns: .......................................................................................... 11 Chapter 2 - Cost Estimation:........................................................................................... 20 Chapter 3 - Design To Build Improvements/ build strategy:......................................... 34 Product W ork Breakdown Structure........................................................................... 34 Modular Construction:............................................................................................... 36 Learning Curves:........................................................................................................... 41 Benefits of Reduced Construction Time:.................................................................. 46 M ulti- Purpose V essels ............................................................................................. 51 Cost Estim ating Relationships:.................................................................................. 53 CHAPTER 4 - NAVSEA 017 Ship Cost Estimating System:................... 55 NAV SEA 's use of CER 's ......................................................................................... 64 Limitations of W eight Based System : ...................................................................... 68 CH APTER 5 - PODA C: ................................................................................................ 73 Use of Empirical CERs in the PODA C M odel......................................................... 76 Improving Empirical CERs: ...................................................................................... 81 Sam ple Representations of Empirical CERs: ........................................................... 83 Interim Products (IP).....................................................................................................86 Design Trade off Capabilities.................................................................................... 89 Risk Analysis................................................................................................................93 Life Cycle Costs............................................................................................................95 Problems......................................................................................................................97 CHA PTER 6 - M IT M ath Model.................................................................................. 98 CHA PTER 7 - Ship Cost Reduction Suggestions: ......................................................... 100 2 Conclusion ...................................................................................................................... 103 B ibliography ................................................................................................................... 105 LIST OF FIGURES Figure 1. Growth in Program Budget (4)...................................................................... 11 Figure 2. Shipyard Cost and Productivity (24)............................................................. 12 Figure 3. Typical Weapons Systems Production Times (4) .......................................... 13 Figure 4. Components of US Navy Cost Growth (4).................................................... 15 Figure 5. Reasons for Shipyard Labor Hours Growth (4) ............................................. 16 Figure 6. Growth in Material Costs (4)......................................................................... 18 Figure 7. Typical Project Timeline (1) .......................................................................... 20 Figure 8. Cost of Scope of Various Cost Estimations (1)............................................. 22 Figure 9. Cost of Design Change (1)............................................................................. 23 Figure 10. Comparison of Cost Estimates (25)............................................................. 27 Figure 12. Addition of Risk in CER's (1)....................................................................... 30 Figure 13. One Digit SWBS Breakdown (1)............................................................... 31 Figure 14. DDG-51 Design Issues (26) ........................................................................ 33 Figure 15. Efficiency of Group Technology (21)........................................................ 35 Figure 16. Modular and Zonal Construction (26)......................................................... 36 Figure 17. Converting to Re-Use Modules (25) .......................................................... 37 Figure 18. Using Modular Architecture in the Navy (26) ............................................. 39 Figure 19. Modular Construction of UK Destroyer (12)............................................... 40 Figure 20. Predicted Cost Savings (26) ........................................................................ 40 Figure 21. Effect of Learning on Cost (14).................................................................... 42 Figure 22. Typical Learning Rates (20)......................................................................... 43 Figure 23. Effect of Break in Production (1)............................................................... 45 Figure 24. Construction using PWBS (21).................................................................... 50 Figure 25. A Single or Multi Purpose Navy (19)........................................................... 53 Figure 26. Asset Model Output (20)............................................................................. 59 3 TABLE 1. NAVSEA SHIP COST ESTIMATE CLASSIFICATION SYSTEM.......... 60 Figure 27. Total Ship Cost Categories (18)................................................................... 63 Figure 28. Index of Estimated Shipbuilding Costs (16) ............................................... 71 Figure 29. System vs. Product WBS (16)......................................................................... 74 Figure 30. PODAC PWBS Sections (PODAC)............................................................. 75 Figure 31. CER Change with PWBS Hierarchy (14) ................................................... 76 Table 2. Sample Ship Type Factors for Empirical CERs ............................................ 78 Table 3. Empirical Preliminary CER Derivation........................................................... 79 Table 4. Empirical Contract Level CER Examples ...................................................... 80 Figure 32. Complexity Factor by Work Stage (15) ...................................................... 85 Figure 33. Complexity Factor by Work Area (23) ........................................................ 86 Figure 34. Examples of Work Packages (14)............................................................... 87 Figure 35. Example of Re-Useable Work Package (16)............................................... 88 Figure 36. Possible Outfitting Cost Savings (15) .......................................................... 89 Figure 37. Material Options with PODAC (16)............................................................. 90 Figure 38. Material Trade-off Analysis (16).................................................................. 91 Figure 39. Construction Cost Material Trade-off (16).................................................. 92 Figure 40. Cumulative Cost Distribution (14)............................................................... 94 Figure 41. Probability Cost does not Exceed Estimate (14).......................................... 95 4 ACKNOWLEDGEMENTS: I would thanks like my to to thesis continued help, MIT from my express sincere advisor, to acceptance Professor Henry Marcus. His throughout my tenure at and trust guidance, and many appreciation will graduation stay me with forever. I also would patiently and detailed inner benefits also that necessary associates to like Laurent thank helped painstakingly workings it presents to who me of the PODAC to ship cost mention from NAVSEA Deschamps John so ever gave and the and estimating. his their so the understand system Hootman readily who It is other time and effort to explain the ship procurement process of the Navy. Lastly the I would University like to thank of Michigan for Professor his Howard information Bunch about from PODAC and Professor Patrick Keenan from MIT for his help with the MIT Math Model. To Lindsey... 5 ABSTRACT Since the end of the Cold War naval procurement for the US Navy has seen a dramatic decrease. This decrease in defense spending has placed existing programs under more scrutiny than previous years. the taxpayers part of As a result there is and Congress for less tolerance on procurement cost growth. This Thesis attempts to examine the current method that the Navy conducts ship cost estimates and suggests the confidence level and changes in order to improve accuracy of the forecasts. An examination of how industry is conducting cost estimates was used as a comparison to the current Navy practices. Finally using only a weight based approach to ship cost estimating is insufficient. It is necessary to develop and use a model that incorporates other cost driving factors in order to develop estimates of sufficient quality at the preliminary design level. 6 INTRODUCTION Since the end of Navy has seen a dramatic decrease. spending has of part and taxpayers tolerance on is less cost procurement for Congress scrutiny more under As a result there than previous years. the This decrease in defense programs existing placed the US for the Cold War naval procurement growth. and especially the Navy have Government steps when determining whether they need a conservative their of evaluation to take known been practices. has estimating cost Ship re- evolved in industry to include new production processes and since developments the estimating the is Navy of the that are part being 80's. the at built a The higher not. ships of cost past during much Navy has As using a result processes were an era where vessels rate less with for need transparency and cost cutting. An ability ship cost to perform estimating effective, could finally detailed, create and a change way the Navy is able to negotiate its contracts. understanding lead to a of the decrease factors that drive in cost overruns for reliable costs two in the A greater can hopefully reasons: First 7 will be designers off trade with an and studies understanding of how designs affect better cost. Second, cost estimates the Navy will be level, preliminary their a develop therefore to perform reliable ability to quickly perform a better position in negotiate more to able at the favorable contract terms that could decrease costs. In past the estimate and the It costs. the has method reliable not Navy a used been shown driving based weight that this costs estimating for factor only has not is a this to good weight since Thus costs. model is thesis attempts to examine how the Navy conducts its estimates and Furthermore an the of examination practices could ship has improve cost determine and of limitations life the current been its current included suggesting current capabilities cycle ship industry estimating model its method. costs. models has and been ways that practices. examined in estimating Finally estimating cost some in the Navy The order MIT to ship construction suggestions for decreasing ship construction costs have been included. 8 CHAPTER 1 - OVERVIEW OF US NAVY: The which US Navy, is comprised currently 283 vessels, of is the most technologically advanced Navy in the world. The US assigns government year to The superiority. this maintain of amount a sizable its budget billion. projects Class of was 96% which the Arleigh Burke Class four classes: the carrier, aircraft 2007 will in the budget billion. be $4.4 the Navy devoted $7.6 billion to new ship In 2005, construction for increase The projected budget president's for the US Navy for the year 2006 amounted to $133 each allocated destroyer, the Nimitz Class amphibious Antonio San between transport dock ship, and the Virginia Class submarine. Procurement growth in cost construction programs naval has been a longstanding problem that has plagued Navy officials and Members Naval not Congress. of Operations outright (CNO), has expressed budgetary constraints on ship The 2006 defense authorization bill by the House Armed contains provisions Services Chief concern, strong (7). of if Combined the Navy is also facing with the rising procurement costs, reduced Clark, matter the about frustration Vernon Admiral procurement (H.R. 1815) Committee as reported (H.Rept. that establish procurement funding. 109-89) cost caps on 9 Navy several begin a developing lower in aimed part and create a Navy the order This funding. completion" appropriations had is $3 surpass the milestones. 12% to the Over billion by all time the estimates cost year "prior additional Congress in ship more currently vessels that assume efficiencies current maintain of construction contract. are and (7). billion increase that US complete. The total appropriations are expected to than 30% since vessels for to essentially already under for vessels requirements ship resort to appropriated funds to cover a $2.1 budget its in overruns has Navy the programs, cost fund to for efficiency cost effectiveness of the construction of Navy ships In to cost lower new program a improving at the direct destroyer, cost submarine, nuclear-powered shipyards programs, shipbuilding complete will shipyards meet and are all their This would correspond to a cost increase range 17% of past 5 the initial years, contract about 10% of price the 1). (Figure Navy's ship construction budget of $52 billion has paid for cost growth for cost ships funded in prior years. overruns budget for is that current it reduces construction The implication of these the buying power and reduces the of rate the of modernization of the Navy. 10 Table 3: Growth in Program Budgets for Case Study Ships Dollars in millions Initial and fiscal year 2005 President's budget Case study ship DDG 91 DDG 92 CVN 76 CVN 77 LPD 17 LPD 18 SSN 774 SSN 775 Total Initial' FY2005 $917 $997 925 4.476 4.975 954 762 3.260 2.192 18.461 979 4,600 Difference in budgets Difference due to Difference due to construction Navy-furnished costs equipment Total difference $37 $43 S80 62 (7) 55 252 (128:' 124 (51: 100 49 734 21 804 246 3 249 327 95 422 294 18 312 1.951 145 2.095 5,024 1,758 1,011 3,682 2,504 20.556 O ,prfrafildcsi. Gdai, S,:uron: New tudget submission for year of ship authorization. fiscal year 2005. through 'Includes all prior year requests in the scop of tie contract. to changes due Is 'Part of increased cost 'Negative reflects savings resulting from th. use of a more economical warfare system than was initially budgeted on the DDG 92. 'Negatlve reflects savings garnered from Navy-furnished reactor plant equipment. 'Negative reflects shifting of funds f rom the construction contract to Navy-fumished equipnent. 'Estimated cost from the President's Growth in Program Budget Figure 1. (4) Reasons for Cost Overruns: New production technologies in shipyards manhours/tonne have resulted over time. and in If organizational improvements a continuous time spent decreasing, then why is cost continuing to rise reduction in dock in is (Figure 2)? 11 MfianU Thms in per doddrhh tXOnn suma A reee~e n aswre WI-nk i ovd U69anig2 tea i m tes tw te tenies te s w e -yar Sa"flaC- Figure 2. Shipyard Cost and Productivity (24) 1. Types of Shipbuilding Contracts The nature of the shipping business in general lends itself to situations that place an difficulty excessive to effective cost estimation even to the most experienced ship cost estimator. it takes to be Ship contracting is 9-14 years for a new class developed from concept design still at a time where of surface combatants to delivery, when at the same time new technologies have a 3-5 year life cycle. It is therefore on technological production times imperative to design vessels with a focus convertibility. Figure 3 shows typical for various weapon systems. 12 Figure 1: Typical Production Tlmes for Various Weapon Sysrna AlrcnMt ow vIm GUbrneskM 4- -hun- -w, Ta* 1 2 5 4 * I 0 Vamminprocaiedn Figure 3. In most cases is this for ship without the upon estimate are formalize designs. ship buyer who construction being agreed are contracts cost detailed a with designs detailed reason The of detailed design. completion that very expensive and excessively time consuming. Shipyard work in to (4) Typical Weapons Systems Production Times and predict This might work of terms directly presents end very to detailed intricate from overpaying up seller who might have a difficult specification is for to both the vessel and the to the risk large a incur exorbitant costs due lack of clear definition of the work at hand. Two the types of contracts difficulty parties involved that in have naval the emerged that acquisitions transaction. The try to deal with to all present first is fixed 13 agreed the The additional costs of completing a vessel prove are used cost reimbursement contracts the class due to vessels in the if pay all Generally for the lead ship and following the for used are contracts price fixed that if the shipyard can unavoidable. were costs incurred the that to government the forces contract contracts. in reimbursement cost is method is second The costs. made additional all pay to agrees it surpasses, shipyard price ceiling a definite is there but cases some be can Adjustments parties. both by upon is pre-arranged and case the price In this contracts. price of uncertainty the large amount present in a lead ship acquisition. The defined. cost provisions They both have profit. and and shipbuilder These the are Navy called share attempt that the incentive savings when the price exceeds the if to control The fees. the final and they share the cost is less than the estimated target, cost clearly so not are however themselves contracts target. This process attempts to provide incentives for both parties to do their jobs efficiently. Either way, both contracts place an absolute emphasis on the need for a reliable cost estimate. Due to the methodology, absence the of contracts an effective that are being cost used estimating inherently 14 create case this (in buyer the force to ways Navy) the to incur the major cost of overruns. 2. Labor and Materials Cost is apparently which account It growth. surcharges breakdown the shows 4 Figure of clear 78% for the that overruns cost of leading cost burden that the US Navy has material and labor cost of components are the to manage. Figure 2: Components of Cost Growth 7< 5% 17% 40% Overhead rate and labor rate increases 38 . -e Material increases Labor hour increases Otu Percentage of cveral lot grwth due Percentage of ontraiccet r to shipbuilde construction costs th due bo cost of Navy-turnished equipment ct pcriudor ana~ dflS a; '.. 'anotonto. growth in constructic -costs is $3.2 billion. based on shipbuilders' esimte at Note: Tutal Figure For growth due billion. in 4. Components of US Navy Cost Growth vessels the to The Figure 5. completion. that were increased main The determined to be examined by GAO, labor hours reasons for repeated the the issue the totaled more cost growth causing the (4) total cost than $1.3 be seen can delays lack of maturity of the design was which directly led to rework. Examples of such issues include the LPD 17 where construction began as the design of the vessel 15 continued to increases and 92 the all of due vessels largest faced the has vessel The evolve. DDG The fact. this to suffered from severe reworking and delays due the of installation remote which system minehunting cost 91 to the was a technology not fully developed at the time. Table 6: Reasons Given by Shipbuilder for Labor Hours Cost Growth Reasons for increase . Inesperienced laborers - Design upgrades that reed Iin reowcrk . Intrcduclion of a new construction facelity, setfng workers back on the learning curve *karunds . Design upgrades that read tin reswk and -. * Strike increased number of hours needed to constfuct ship . Less-skilled workers due to demands ltr le;r on other Case study ship DD& 91 DDG 92 CV N 76 prcqraim at shipyard . Extensive use ot cverfi-m . Design changes resulting in rework . Late material delivery results in delays ard workarourds . Design chamnge resulting n rework . Inexpertenced subt.ontracted lab:.r . Design difficulties led to doing wck out of sequence and rework . &hedule delays * Bused workers to meet latr shortages . Increases in LPD 1 translated into more hours for LPD 1 CVN 77 LPD 1 LPD 18 SSN 774 . Late matenal delrvery . First in class design issues . Quality prblems and design changes . Incluskn of rcn-recurring labor hours SSN 775 sau Empiu~r ianasoa0nu Reasons for Shipyard Labor Hours Growth Figure 5. Overhead costs of operation the to chargeable majority of an include overhead costs significant decrease. costs ship The in this that benefits, growth labor in directly overwhelming The This leads to time there manhours don't construction if incurred not are related. time even cost costs contracts. reducing by increased are of which shipyard the particular understanding are wide variety a (4) relating to overhead case are attributed to the decreased workload 16 shipyards are that US facing which would absorb some of the operating costs. installed. of the significant (Figure from 4) . for recent budget total sector has reasons for cost The commonality scale of economies approach procuring equipment from creating an accounts typically equipment Such it that The in bulk. organized to beginning is Navy is trans-vessel however class 5% through affordability the to at benefits Navy the that is this of this low relatively 30% about for The growth vessels. remained due and has the Navy purchases equipment that and technologies for costs the to refers equipment furnished Navy when use still far commonality approach to its equipment acquisitions. 3. Underbudgeting and Price Increases and Underbudgeting increased the Antonio, was Nimitz, the most 6) . DDG levels of material and Virginia significant of Ingalls under Northrop Grumman. class component 91 had $22 million consolidation cost Shipyard growth. vessels, of cost in material dramatically have increases price cost with material cost growth (Figure savings due to Avondale Therefore materials the San For Shipyard were purchased 17 for four ships a price decrease time leading to one at due to economies of scale. Tab Is7: Growth in Material Costs Dollers in millions Ar"Oystased.:n data availelIe J ULy 2i4 Total dollars due to increased material costs Case study ship DDG 91 DDG 92 CVN 76 (S22) (3% 30 294 cVN 77 LPE 17 LPC 18 SSN 774 SSN 775 Total 20 43 34 13 0 iCG 39 43 56 38% 93 141 209 $1.210 UNSu : sM Material cost as a percent of total contract growth (40, 23 46 Percent increase 31 47 24 49 49 G1c ympe5 -te at -xipietion ic .dt-4fline total c>:inat Note W4 cicnpar-d WHOl target i6I b3 the uIrEnt . -. O .>>st grcK*Ih. 0:t jrvJP:th wj tb due to Navy chanrge6 I rlract so:p. nShOullde per ntcnCA unanicipabed oevnis. Figure 6. The reasons contracts are than budget of the materials formulated. The first materials submarines' actual that are Since budget the the way the Virginia class million lower $132 vendors and aircraft carriers, the received by class on heavily and four was that were the Nimitz For cost budget was based on an incomplete materials reason again Why? The list. cost quotes price subcontractors. materials rely cost the of quality increases these for (4) Growth in Material Costs negotiated shipyards know in change orders value specialized lies between the that they contracts or items, they in the types shipyards will price be of contract the and Navy. reimbursed increases underbudget for their for high cost 18 forecasts, win the contract to build and then simply pass on the higher cost back to the Navy. Price of increases component price of material increase levels. materials are more that that faced by the the are the not subsequent in suppliers growth. Factors than directly the ship submarines LPD since industry resulted and a just the end rate of of in a lack contracts increase single in that A for of a increases of Changes cold war due production lower competition in price. the the to has number of between Over Virginia source vendors. cost range of industry. ship of affect inflation price the consolidation. been from the display construction the significant national consequent increase material have 17, naval decreasing has subcontractors the do supplier base resulted of another Inflation itself is an average number products in cost is 75% class While on subcontractors accounted for 70% of the increase in material costs (4). 19 CHAPTER 2 - The COST ESTIMATION: costs overhead costs. capital profit. Due industry shipbuilding between particular correct cost cost and estimations is any include will inflation, particular nature of necessity the the reasonably complexity The imperative. of and variation of degree high the projects, including financing, the to and a vessel of price final for allowances shipyard The construction the in involved materials labor the all of sum the is vessel a of cost and cost of detailed ship design and the length of time between preliminary design that determine the and the shipyard. definition of design is the change and the are completion factors leading flexibility of contract between the Navy This leading cause orders lack of the increasing number price escalation costs. for final and and flexibility inherent Figure 7 shows a typical project timeline. c:plete P..ans Cnt:jct Io) 7Cam r je r aci r-=t T lne ( I I, I n,t1 Figure 7. Typical Project Timeline (1) 20 designers Historically categorize such costs as hull electrical. type. sections of the developed hull machinery, hull piping, priced on weight systems segregate different according costs difficulty of section. priced to structure breakdown different the the vendor. outfit analysis and construction the for and Major Other parametric through data historical extrapolated able and develop generally are work directly priced from is equipment and More is been have outfit, Structure production the systems consistent structure, Hull material to by shipyards and installation of the system. Cost are estimates The development. required importance particularly at the early when all at of levels a of stages good of design cost can be It comparing different design proposals. design estimate crucial is very easy to manipulate early cost estimating programs that use basic parameters The as different into three basis types general Concept Design, Design. a 2) of and criteria cost for estimates groups relating to Preliminary Design, determining can be broken cost. down stage of design: 3) 1) Detailed Contract Figure 8 shows a comparative cost comparison as the breadth and scope of each stage of cost estimation changes. 21 BREADTH E /1 LEVEL SSESSMENT H <$IK LEVELI ASSESSMENT < $1OK of explanation detailed stage will be presented in shows how the enviable of applying (relative to project savings decrease with the design. of greatest innovations Incorporating design is relationship This introduction The as dramatically at new already of the the to effect Possible project is technologies from stages early committed is 9 in for cost defined is particularly applicable result technologies Figure stages maximum cost). advanced savings section. design early the position cost clearly. following the to according estimate cost each in analysis cost minimum more (1) Cost of Scope of Various Cost Estimations Figure 8. A LEVEL 9I ASSESSMENT <$IOOK at later a certain in ship the introduction of development. stages when technology the will result in increased labor costs and change orders. 22 CUMULATIVE SYSTEM PROGRAM COST COMMITMENT DECISIONS COST- POSSIBLE COSTa SAVINGS 10-95% of total Prograrn Less Then, 5% Program Figure 9. Cost of Design Change In Concept the estimate to create is cost estimate. are presented are broadly feasibility estimate is At this the and a very rough order on based (ROM) of magnitude stage basic ship type and parameters mission The defined. check cost the of purpose the stage, Design (1) the and cost operational estimate project. At as used stage extrapolated historically on this is requirements a cost the data and basic parametric analysis. The Preliminary stage. At Design this phase, stage is a very crucial design the methodology and validity of the cost estimate is imperative since it is at this point where the design will be evaluated against other options. It is 23 designer the for important therefore to understand his how decisions will affect cost since major tradeoff studies are This is a very powerful and exciting project will be made. that components capital initial at addressed must be cost for the of construction the operating costs and the net present value of the the are: stage this cost necessary two The choice. design each of implications the of understanding thorough and decisions careful requires that one also but process, design the of time the of future the about decisions major and performed vessel, discounted throughout the life of the vessel. The estimating cost on depends stage vessel is using new composite materials, of type the designed designs methodology radically used new that of the equipment, and difficulty are Parametric, The Analogy similar four main types of cost this stage: available 3) at Extrapolation, type systems. uses a 4) the past of making realistic and reliable estimate will be compounded. because If all from different the then underway. project technologies, preliminary this at a This is estimating methods 1) Analogy, 2) Expert Opinion. direct comparison It is used in early stages between two of design and 24 is inherently for new to labor in productibility due features and changes account inability to Its historically based. learning rate are its major flaws. Parametric parameters mathematical analyses use a parameter and cost regression Cost (i.e. analysis = know when an factor adjustment is cost The f*(weight)). estimator using this system must be through determined historically is that input between relationship Such etc. horsepower, weight, ship size, such as design on predictions their base estimates knowledgeable enough to and needed, to know what the factor should be. costs return for available be similar inflation). for (adjusting vessels only can methods Extrapolation there when used systems used prior in of accuracy The are the system is a function of the length of the extrapolation and the consistency the of factor being They extrapolated. should only be used if the project has progressed to such a level of definition. In the case of new technologies this type of methodology is difficult to assume. Expert also opinion be can prove misleading. to be Personal very effective involvement but in it can projects 25 carries with A follow. it Low interests are the by low estimates. shipyards, who are estimates high the want cost Committee when it turns out by persons to by persons not does some or the whose be and built. be In this case it who to could Examples vessel superiors his by scrutinized influences generated estimator wants subcontractors, served by high estimates. government person position generated designers, interest is be and each are vendors Similarly, that estimates served vessel material agenda occupation person's forecast. the the want whose could to be Congressional requires additional the project funds. The value of an experienced cost estimator is that he has a better understanding of which particular to each derived situation. factors, it most Since is include CER's necessary CER is have to applicable empirically them by used someone who appreciates and understands their implications. This is particularly important which technologies Furthermore, expert rational crosscheck general, computer therefore the not have opinion of is been very data the generated appropriate if the new design in used useful that equations combination the new past. in providing modern, produce. of uses the a complex, It is value of 26 relationships estimating A forecasts. that of the summary of effectiveness better in result can with conjunction in used expert the by provided judgment various types of cost estimates is shown in Figure 10. ABILITY ABILITY DATA WORK TO TO WITH REFLECT REFLECT BASE TYPE OF COST PRECISION COST TIME PROD'TN DESIGN COST PODAC ESTIMATE CHANGES CHANGES New Work Requires Factor Some Yes Large Yes Yes Some New Wok Requires Factor Requires Factor Some New Wouk Modeate Possibly Possibly Low Possible Quick Requires Possibly Some Unknown Yes Irp Yes Quick Low Parametric Fair Engineering High Analog (Comparison) Fair/Good Extrapolation Fair Low Quick Expert Opinion Fair-Low Low Requires Factor I Yes Req'd Slow Very II Large Medium Modente Requires Factor Req'd Red Unknown Performance Based __________ High Re-use/Module Low ___ ______ I__ Low- Factor Figure 10. final The design construction is the phase the costs. It on a stage _Startup before expensive "bottom up" used to this level is methodology accounting construct (25) moves stage. to used In the of the ship. required It is into this determine and tedious process the most accurate method available. at project the Detailed Contract Design is a timely, and materials . Comparison of Cost Estimates engineering detailed Yes Quick- Medium Moderate based work however, The costing information of design provides the fundamental basis for 27 the contract price rather than to create The analysis. the strong a that detailed to design. indications are There modularized a towards moving This design however is implemented is a method that that can structure production This will be discussed be into modules formulate and categorize the vessel elements. can of re-use modules. introduction requires technique final off a design trade that and re-use Navy the approach oriented further in the is following sections. The difficulty of assigning an assumed final cost to a product 3 to 7 years before its materialization is logical; however, it result could necessary is in cost to changes understand in order factors the to develop that better methods of analysis to deal with them: 1. Technology Change " New processes " New materials 2. Social, Economic, and Political Situation * Changing workforce * Economic downturn and unrest 3. Shipyard Backlog 0 Heavy backlog causes confusion 28 Few orders results in loss of learning 0 4. Labor Rates 0 Different for each shipyard 0 Unpredictable changes 5. Material Costs * Vendor base changes " Delayed shipments 6. Regulatory Structure 0 New rules 7. Inflation * Fluctuates unpredictably * Different rate for each item new are developing that cost will estimates. system analysis deal One are currently trying with of the (discussed in which will these most issues to incorporate that distort important Chapter assign will 5) a the Navy industry and that estimating systems The additions be certain the parameter to the new uncertainty probabilistic distribution to each parametric regression equation 11). factors (Figure This will provide cost estimates with a certain range of probable outcomes. In this way it will be easier for the 29 Navy to plan risk associated of level the and manage with each project. Addition of Risk in CER's Figure 12. Since the cost estimates which basic is based construction through determined, form These factors. that are Breakdown designer, design the use cost estimating level shipyard a of method and of as determined (CER's) relationships a of ship Ship Work analysis the common The directly historically uses of method weight. then is parametric (SWBS) Structure communicating the ship of a developed parameter: cost This costs. Navy US advance in required well common single provide to used construction varies a on the phase, design contract often are (1) means of technical definition between the cost estimator. Its definition in depth and breadth as a project moves through each phase. The main components that make up the one 30 SWBS digit system group are Figure in shown The 13. total weight of the ship is the sum of groups 100 through 700. Description SWBS Group 100 Hull Structure 200 Propulsion Plant 300 Electric PIlant 400 Command 500 Auxiliary SyStwms 600 Out4it & FarnishingS 700 Armament 800 Design & Cnqgn*rirnq Sev~iceu 900 construction Services the group level of design increases, within specification ance One Digit SWBS Breakdown Figure 13. As Sur vwi & the so system. (1) does For the level example, a of two digit weight group such as group 130 defines hull decks. On the like Engineers because it design level, digit three using group this is system based. and it lends itself 132 type could of be second classification deck. system It is good for early stages of to parametric extrapolation or reliance on analogy cost estimating methods. Such weight an approach as the which results in of costs surrogate a heavy can be deceiving. Experience has shown that there are cost drivers other than 31 weight cannot that be ignored. The from suffered DDG51 severe operational issues due to the use of a solely weight based decreasing beam the by 2ft would decrease construction difficulty factor however, level that the overall cost the costs. The increased to such a ship to the change issues arose due operational of that believed Designers method. estimate cost increased. Also since stretchers couldn't fit in the 2ft narrower corridors. issue Another system system ignores designs which arises when rather than whole. Figure height of available shows of access for 9ft and structural member penetration The runs. interference between design changes in the one aspect or of the and systems multiple was 6'5" to a deck is 2'7" congested due to deviation from space meant that the common systems. the installation lack of available as had only led that system vessel Since DDG51 This difficult costly issue increasing is friendly an is 11'2". systems. overheads, optimum pipe to personnel, distributive of effect the from DDG51 optimize production efficient 14 the try to it current The based. This costs. reduce designers for required would that is production of possibility the the classification production than rather based SWBS the with which This resulted in fueled change 32 and orders dramatically increased construction time and cost. Lnangener 80 -Pjaruwt 2. - PU.4 Umz 4,-, omoo, %te* CeCX Woo Fram* 641g M&cUnary Plaorm M PIZOam Figure 14. DDG-51 Design Issues (26) 33 - 3 CHAPTER DESIGN BUILD IMPROVEMENTS/ BUILD TO STRATEGY: Product Work Breakdown Structure system for The US Navy has been using a SWBS classification the past systems approach. products work that accordingly. convenient to as are savings and group products These because functional technology. and A the typical incorporate new rather than just a the is This the from sequenced process example of Work interim different benefit that are Product subdivides work order. the The classifies assembled at in subassemblies characteristics. (PWBS) Structure schedule to necessary Ships are built common by Breakdown is initial however, design; look at production methods features that grouped of stage it level detailed system that provides an is a an early at approximation more It 60 years. required cost into and a is referred its function is shown in Figure 15. 34 R A) CONVENTIONAL PROCESS METHOD IG M B) GROUP PROCESS METHOD KEY: Figure 15. This system expanded order from to efficient of grouping subassembly of D DRILL PRESS G -GRINDER Efficiency of Group Technology a (21) resources efficiently to to blocks productivity improve use L - LATHE M - MILLING MACHINE C - CUTTING MACHINE shipyard's and outfit result resources. be zones in a in Since system operates by creating interim products, can more the PWBS the vessel built according to zones and assembled at the final is stage. (Figure 16) 35 Types of Zone Ouftftinc Modular Construction Zone Constructionand COutfit P-ocess F~ow Lanes On-Slack Cuftfiln UiA On~ ~ Launcfl Asseffibly 7 Ouffitting Onn.acat (26) Figure 16. Modular and Zonal Construction A to ship have productivity, amount of production. that designs this in efficiently overlap of material maximize significant procurement, and This is therefore placing added pressure on the already difficult position of incorporate to a implies approach subdivided be to attempting In design, system needs sequence vessels allow way. PWBS the production this shipyard that uses and anticipate the designer who now has the method and sequence to of production. Modular Construction: The concept of modular construction due to the the US changes Navy's that are is becoming more viable occurring procurement in the strategy. framework The of Navy's 36 the example of attempts of thickness) . incorporated system. new a that module or are a logical existing system an If direct and the existing associated of database possible to define modules at any design any of level subassembly to hull erection. be existing module can be an of The interim can it the added the added to it will Eventually entirely almost be PWBS, cost of the module be will modules. extension can adaptation information sizes, pipe that within directly into the new cost estimate. components different pumps, priced and classified, described, then in an of components standard of modules Reuse The program reuse modules. common using as (such Designs Naval use of the number standardize to and plate of effective an is program (ATC) Commonality Through Affordability production be by reuse line from (Figure 17) Product A Design A Desin aProducl 0 Develqopmn Figure 17. Converting to Re-Use Modules (25) 37 the Using new can result time the determination the of on cost consequent impact the estimate cost engineering architects of the will a the better a of be will make the It reduced. that understanding that of the they The accuracy of of a cost detailed and give also cost make and its design incurred will comparative a change in approach study. decisions design to without estimate conduct to effects ship procurement. and cheaper taken methods organization production faster, in easier, Moreover, lost and design time naval implications ultimately and result in producing lower cost vessels. DDG51 vessels were they thereby were not limiting built modular construction with modular ship possible savings that designed the using architecture would from the advanced outfitting capabilities of the Figure can 18 but result shipyard. shows how modular architecture and reuse systems be incorporated, scaled, and used throughout different vessel classes. 38 Common Modular System Architecture OBJECTIVE: RILD3 SH4IPS COMPORPM A DJSTRIBUTED OF COMMON MODULtP - U----- - - - - - 4a - Figure 18. for modules similar Using be cannot process construction overlooked. or (26) reaped from pursuing such a that are organized and understated Fn t Using Modular Architecture in the Navy The economies of scale focused UL9DINn BLOCKS. AND -q- - SYSTEMS RCHMTECTURES and productivity different vessel types improves shipyard decreases costs. Other benefits arise through the equipment in bulk which again and of purchasing materials process attempted to incorporate an increasing number of subcontracting deals in in results order cost. costs. will construction also let that they Having shipyards are more multiple suppliers contractors which in the service, quality, has The Navy scale. competition between increase It of decrease to increases should economies and focus reduce on efficient turn acquisition the aspects of or proficient at 39 ...... .. ......... ...... . . ... This conducting. due to the The the with deal would inexperience of the overruns hour labor workforce shown in Figure 4. UK Royal Navy uses such an approach to build its Type 45 destroyer (Figure 19). *** .......... ........ Vosper Thomycroft BAE Marine Barrow BAE Marine Govan BLOCK E BLOCK D MEGA-BLOCK B+ C BLOCK A BLOCK F Modular Construction of UK Destro yer Figure 19. (12) The possible savings that can be realized by switching to a modular shows production the cost can process be expected for savings pronounced. DD-21 Figure due to the 20 new design initiatives. Mannours (K mnnrs) (using DOG CERs) 1.458 SWBS 100 1,018 1 Savings 30% SI more producole structure, tritcKer plate, less weld distortion 0% 300 145 289 400 199 145 289 135 500 557 394 29% 600 612 374 39% 200 Notes: Percent Mannours (using DGIAmpntb CERs) 0% 32% SMART decks, air lown fiber optics. modulanty increased deck heights, zonal systems. ATC 700 800&900 and margin Total 1 68 66 ] 2.336 5 b.662 1.700 | 1 4121 modules incresed deck heights. ATC mocuies 0% 27% 1 27% function of SWBS 100-700 Figure 20. Predicted Cost Savings (26) 40 Learning Curves: as cost construction decreases specialization increased and Modularity more produced. are vessels similar average is because ship construction labor costs decrease with This as experience outcome. efficient more vessel original have Therefore to be CER's take to a with efforts their the modified of learning as series the effects and production manufacturing coordinate management and strategy, strategy, build used into for the account of several vessels of the same class are constructed in sequence. The basic form of the learning curve is: Log(y) = Log(a)+b(Log(x)) where: y = Cost of x# of units a = Cost of 1 St unit b = Learning curve coefficient The slope for 2 of the units, x learning curve =2, and b(Log(x)) is the equal learning rate. So, of the to the log slope. Thus, b = Log (slope) / Log(2) For a 90% slope, b = Log (0.9) / Log (2) = -0.152 41 = Cost of Cost of Nth vessel The theory is built doubles, cost the for first the the the vessel third of cost effect equation, of will be first the different i.e. y = ships decreases by if Therefore cost the for a the second 90% of the cost of the first. 2^(-0.152) 3^(-0.152) = cost cost. the 1, is year vessel will be 10% less (Or using former the of of total quantity the construction the basic percentage constant *N^ (b) st time each that 1 ..... .. ..... ........ ... . . .... . . 0.846, = 21 Figure vessel. learning 0.9). = curves The or shows decreases cost of 84.6% of how costs the as output increases. Cost Learning Curves 0 1Z 0 15 0 25 Ship Number in Series Ship Construction Program Figure 21. Effect of Learning on Cost (14) 42 is Learning and including system following reduction in skill Low ship. levels low between learning the amount of of a certain task. have slopes close to region with can where highly Figure 22 learning makes improve how its because efficiency different increase it effects. is increase Production but substantial a This labor. skilled cost learning to shows not do machines decrease and attributed significantly tend to also experience. through efficiency necessarily since unity no repeated performance such as modulization and PWBS innovation processes shipyard labor with or little is each exhibit tend to processes there and of start Highly automated operations productivity their since of factors technology, and completion level of variety a manufacturing complexity, time construction on depending varies performed being is that process each for different is The not major difference skilled with manufacturing is labor experience. activities exhibit differences in learning rates. Typical Slope % Manufacturing Activity Electronics 90-95 Machining 90-95 Electrical 75-85 Welding 88-92 Figure 22. Typical Learning Rates (20) 43 ratio ratio 50:50, 25:75 is Typical is the in the vicinity slopes are learning in rate and manual 75% requires operation slopes automation, the an if Generally, common. of 80% are the 85% region. 90% the in is If If the region. run between shipbuilding learning slopes tend to 25% 80 and 85%. There are instances when using curve learning Such situations factors is not appropriate. correction include: " When ship construction is sporadic " When the types of functions performed are inconsistent (custom products) " When work is highly automated and production rate cannot increase further " When rules and regulations limit the production rate " When production quantities are small Sporadic production, either due to low levels of orders, results in breaks in labor issues such as extended strikes, production. The effects resumption of construction in cost upon resumption of of such can result or between gap a time in a stepped increase construction as shown in Figure 23. 44 Break Produr f.an RecurrIng Unit Pro.Iuction Cost Other where instances include of time accustomed become to requires labor the to cost a new occur can changes and facilities to since production processes in increases similar upgrades major (1) Effect of Break in Production Figure 23. certain to amount facilities and production methods. A typical example would be Philadelphia cost of increased the trained to changes and can uses for caution is the use in inherently ship since a upgrade major A equipment. new loss upgrades of facilities design of vessels a class since the Thus CER's that different. can to Significant learning cost estimating have they the to construction because workers were not technological result also process yard. Masa Kvaerner result in to production the be used with significant Navy extreme variations between actual and predicted costs. 45 has to due is number question and is it the US the Today, applicable use to could that benefits cost for 5 is therefore necessary to It whether factors correction annum. per vessels down to less than 6. re-evaluate current 17 about constructing cold war During the years. 10 of order the of cancellation the class Virginia the and 79 shipyards and Navy the between DDG of the past over vessels contention costs the been submarines was of point A major arise from improvements in learning. Benefits of Reduced Construction Time: shipyards Korean delivery time with a by pre-negotiating detailed work breakdown change outlawing essentially that proved has concept decrease shown design total to delivery by costs by 50% as much to possible was as time the decreasing by that and structure Analysis of construction decrease construction time by 30%. costs it orders, exact an it will 30% be (19) . taken from possible to Although it may be infeasible and undesirable to decrease costs by 50%, it is clear that the time value of money should play a much more important role in the decision making aspects of the 46 naval By process. procurement longer having the projects Navy incurs the following costs: 1. Interest on capital 2. Interest on material inventory labor and material 3. Extra factors cost due to escalation (inflation) 4. Opportunity of cost and usage facilities cost of occupancy of facilities 5. Increased overhead costs 6. Cost of built-in obsolescence 7. Cost of rescheduling and planning In as short, final as long acquisition to continue will cost held is vessel the cold war reduction in military spending decrease in historical of procurement decrease in the Jones Act the drydock, With rise. post and the consequent vessels naval in combined with fleet, shipyards a are not interested in decreasing manhours and/or project time. Since shipyards business, they expensive ships possible. Thus rely on work inherently with the as Navy procurement naval many has to slowly, extra to and change re-evaluate remain produce orders the in way as it 47 expects shipyards to operate if any benefits are to be made by using existence highly modern, a of PWBS efficient production of system existence since the late 1980's. that produce projects cost time carrier Figure was 24 built shows at has The been in In fact the same shipyards for naval overruns can build commercial time and cost. bulk and construction methods. vessels the in a fraction speed that Avondale construction shipyards a of the commercial by using a PWBS for vessel construction. 48 Z<. 1: -R now vi 1 60 49 ........ ............. .......... Fig, 3-64 Figure 24. Construction using PWBS The vessel shipyards was are still in experienced produce similar vessels is no reason that Far at days far very levels there 43 launched from East about the after same keel attaining yards, 50% US (21) laying! US production which generally of the time. However, yards cannot use the same production methods to build naval vessels. 50 of costs it While to relating project, assigning obsolescence attained by are there shown that been shorter a longer of built-in itself The elimination of change orders short in increase significant benefits construction term re- it has conversely, equipment; of upgrade and conversion of cost added the obsolescence an in result probably material Built-in harder. is a knife with two edges. would the to a value much is and capital labor, estimate to trivial relatively is construction longer with associated costs future periods. construction shorter a is necessary to conduct a present value analysis it period, of the value to understand In order that without times can be expensive, time consuming change orders. Multi- Purpose Vessels Navy mission requirements have become less focused and as a vessels result, the navy is more flexible at any capabilities. As a result, given By at time their performance penalties typical capital multipurpose that different requirements. under of the expense nature missions multiple with designed been have and operating costs. vessel are designs imposed It can be argued, perform only by incorporate their various that most vessels one main mission 51 of the With more focused crew size which and training of the requirements could (14). to possible is personnel dedicated would have specialization Furthermore, capability. mission each it missions 37% is and extra manning both reduce to need the emphasizes equipment. for surface-to-air modernization 13% and maintenance, 21% personnel, reduce other breakdown cost operating the ships naval This many but the capabilities were never used. warfare, In Most and anti-submarine as such functions bombardment. perform to manned and equipped were the primary use Gulf War, surface to surface was warships vessels during the example, For function. crew on primary and secondary mission improve operational proficiency and effectiveness. 25 Figure different purpose and Navy vessel is cost and 75% significantly require would A type value present by configurations a Clearly, operate. management. a performs fleet more mission. expensive specialized vessels increase of 35% three The multi and construct to mission better comprising oriented operations 60% type A could be procured and operated at: B vessels (0.6*1.113+0.75*1.032) more more of comparison = 1.442C. This is about 82.5% of the 52 7 - cost of procuring and operating a - -~ smaller fleet of multiple purpose vessels. Table I Comparative characteristics Multi-purposc shiw Displacement AAW capability ASW capability GSF capabilitv Screws# Speed (kn) D Primary Primary Good TFpe A Type R 0.4D 0.4C Pumarv Fair Fair Primary Good Poor 2 M Procu rement cost Endurance FuIe cvst. PV 20 vears* cost PV20 years Overhaui cos / 20 year Operating ;und! /PV 20 y. Same 0-0780C 0.067C 0.480C 0.11 4C 0.O IC 0.031C 0.040C 0.310C 0 00C 0.010C 0.022C 0.024C 1.746C 1.113C rs Re-air Oarts,. PV 20 yeas Commissr P\ '0 ears. Port costs and scervice PV 2ear viu 0.05iC 0.310C 0.067C 0.010(C 0.020( 0 024C 20 yeArs Total discounted comparative 20 year cost PV=pfes4,- 0.5M 0.iC Same 0.tC C Same Crew 1 X 2 X+2 OM X MaIning Figure 25. A Single purpot-e ships 1.032C Lot Single or Multi Purpose Navy (19) Cost Estimating Relationships: are CER's item's that formulas or physical also compare item or the group of relate the functional of cost an items. cost an of item They characteristics. item are They and parametric the to cost of historically analysis. Since to the can another derived CER's are through regression derived from physical how the data correlates to the problem that is being solved in particular each data, cost it is estimate. necessary CER's vary to in understand complexity 53 design provide the between and detail time and cost that would be the a detailed engineering analysis their reliable with estimators cost ship in lies detail and the stage design significance Their stage. concept ability to without results incurred through of a design. the use of There are five main types of CER's: " Manual - determined from external such information as vendors and subcontractors " - Calculated actual from derived and determined previous ship cost data. " - Predictive data multiple of vessels over manufacturing method that is " Empirical - determined regression though determined time, or from return a common from changing over time. through statistical regression analysis of particular shipyard processes. " Standard of the Interim PWBS. standard Products Existing common - CER's determined are grouped interim products and at level each together modules into called re-use packages. 54 NAVSEA 017 SHIP COST ESTIMATING SYSTEM: CHAPTER 4 - Sea Naval the to refers 017 NAVSEA The department of Cost Engineering and Industrial Analysis. prepares estimates cost ship Navy's the Office Command Systems initial the from design feasibility study phase through production award and extends submission for execution contract actual into to the annual Department of Defense's shipbuilding budget. The Shipbuilding total Navy's 10 approximately constitutes (18). conversions constructed authorized by Congress must be it This must cease. through the ship has that assures been that funds all reasonably expected construction. Exceptions to for ship major and fully funded or the work on "end costed" policy available always are the appropriation, item procurement SCN An of percent includes the procurement of ships newly be to craft 15 The annual procurement budget. as indicated by its name, and to percent (SCN) Appropriation Navy Conversion, and this costs policy include ship outfitting and post delivery costs. Also there are provisions costs to be due to that In inflation. considered for allow as a of shipyard cost estimate cost escalation order for potential a ship budget candidate the following conditions must be met: 55 OPNAV Written " cost and be must request feasibility in hand. * Formal technical design inputs must be available. * strategy acquisition An approved schedule must be available. * A of These estimates are submitted during each and the estimate reliability of on preparation. the estimates the Clearly, improve the at available data economic strategy, acquisition program system. Budgeting and Programming based definition technical of Planning, the phase and shipbuilding cognizant Program Manager must be involved. Cost estimates are to be prepared and time and confidence the level into four as of technical definition increases. In the design ship acquisition past, phases: Design Phase, Phase. For Feasibility Contract almost design all Design major was divided Study Phase Phase, Preliminary Detail and ship programs, new Design NAVSEA would develop a ship design up to and including Contract Design. The intent of Contract Design was to provide a ship design that was a sufficiently detailed and technically mature shipbuilder could use ultimately sign a build the ship. it to develop contract to develop Nowadays, NAVSEA that a cost proposal and the Detail Design and only develops rough 56 the DoD requests are met, turned be will design 05 NAVSEA of different If the specifications submitted. that are alternatives the by an analysis it to make allows This division. level design concept the at designs that then the development of the ship over latter The industry. to then performs feasibility, preliminary and contract designs. goal commitment will not to due SWBS to be required . furnished The "C" class by (exceptions is estimate also The system estimate is the process. A class Navy the The estimate material. classification estimate estimating Congress inflation) system. The cost ship the of 1. Table in shown cost ship NAVSEA The that being ultimate C additional escalation the based on is is a funds factors three-digit includes cost for government Estimating Relationships Cost (CERs) used to calculate the cost estimates are based on: " an accepted weight estimate using bid information " current weight estimate when using cost data contractor's * similar ship latest Cost Performance Report construction building yard(s) data of the from the (CPR) prospective where new designs are being costed. 57 modernizations, The estimate and is there are provisions occur with for of this the and and/or include: material of that a class a complete parts is to that requirements The conversion. that except C uncertainties with the deal that repair estimate equipment to comparable (SLEP). Programs Extension Life Ship conversions, ship with deal estimates D Class be list, weights and replaced, a proposed list of ship alterations. Class estimates F are prepared information using from single digit SWBS weights and only general guidance with respect to major electronics and feasibility studies based on weapons equipment. parametric The extrapolation cost of estimate a is previous example of such an ASSET model estimate in most ship cases design. a An is shown on Figure 26. 58 ] C A L I SW5 I 2 4 00 S 6 200 300 1 HULL5T UR _ _ 1PROPULSION PLANT ILECTRIC PLANT URV. r 9 f1 1_291 _._ 85 r 41000 94.3 LTONS HP LTONS 100.6 LONS LTN 98.1 IT.N. LTONS 400 500 4AUXSYST r1S 0 __UTFIT/F1JRNI3H1NG$ ARHARENT 700 8 INPUTS I________ ____ LI CRACUP _ 288.1 91.00 1 I1 RA9---r----VWM 1 2 900 13 OTA 15 ~ 201 21 1 233i 4701 *T*~ H - 1 1.00 r 3359 1 6771. 31057 6260 736 - 1 6204 8475 ItS 746 994 10?5 2996, 39901 43.16 227941 24654 1216'.: 17115 -- -- --- 22969 17261 9PIj16987Si I 24 2 4.. I 10V _PROFIT 0 I _i461 426 NTRUCTION COST 16 12331 23S 1.00 3.15 F _LEAD SHIP LEADSHIP, LEADSHIP $31 T (S903K) T .('92SK COT i SK = 1.04)-2 =3 8892 I.3 j 1CNSTRLRONSERYICES 14 17 94-5 0.5 E KN FACTORS 2486S5 252683f 2731_ li __ 22 Figure 26. Asset Model Output A applicable is It estimate R class is a for rough designs order when (20) of magnitude estimate. design the information that is being used is not of feasibility standards quality. limited is There estimate uses old information weight or generalized known adjustment cost the and Some factors. examples are: " a new design of an unconventional ship platform. * a ship platform that is initially designed to carry many unconventional or developmental equipments. * A a ship designed beyond the current state of the art. class X estimate is applied to situations where the design is: 59 * by developed not the Engineering and Engineering Cost Division or the NAVSEA Ship Design Industrial Analysis Integration NAVSEA and Engineering Office, through Directorate, estimating normal the Cost process " provided by other commands or agencies " directed by higher authority. TABLE 1. Class NAVSEA SHIP COST ESTIMATE CLASSIFICATION SYSTEM Use Basic Technical Input C Completed Preliminary Design Three Digit Weights D Scope of Work, Including Weights of Deletes & Adds Budget Phase (New Construction) Budget Phase (Conversion) SHIPALTS and Repairs F Feasibility Study One Digit Weights Planning/Programming Phase R Rough Order of Magnitude Planning Phase Less Than Feasibility Study A directed or modified X estimate - an estimate not developed through the normal NAVSEA estimating process. An estimate established external to NAVSEA. NAVSEA 05 uses a parametric ship design model called ASSET (Advanced Surface Ship Evaluation with an existing ship design, Tool). The or parent ship, model starts that is most 60 closely model analogous with iteratively that solution changes The estimator ASSET from which by the Navy. NAVSEA ship the parent design is the input adequate The program also has with the ACEIT program new accommodates requirements. estimates. the ship is a joint and factors, reach a of ship provided to the cost to develop Class "R" cost the capability to be linked Army/Air also to ASSET set Integrated Tools) force program includes learning supported order to conform with It is also SWBS based in but The desired (Automated Cost Estimating standards escalation concepts. costs, indirect curves. The system can also output total life cycle costs for the vessel. Once a design has been agreed upon, project is turned cost estimator of the contractors' cooperation due the of contractor the and in the communication, at Navy instrument estimates. and the arise differences of a validation interaction, contention to of role The models cost amount of between issues involvement industry. to then becomes that requires a large Several over the development of the This and Navy personnel. this level estimating of methods used by the Navy and all the different contractors that it uses. is As a provided result, in NAVSEA SWBS form generally requires in to order be that all effectively data and 61 efficiently NAVSEA 017 quality also analyzed still class C has 017. to develop ratings that requests by for This is cost necessary estimates to submission provide shipbuilders because of budget Congress. 017 return cost actual data in order to keep the system updated. The categories are show conform to in that Figure the plans, The (GFM), basic and end Major The can be portion, general construction, cost Category and accounting, categories shipbuilder groupings: material 27. collection, used by NAVSEA. total constitute separated government change shipyard profit which is about 10%) Codes review administrative. and for orders a ship (MCC) systems into three furnished Construction (including constitute the shipyard portion. 62 Construction Plans MCC 100 ESWBS Group 100 Hull Structure 200 Propulsion 300 Electric Plant 400 Command and Surveillance Change Orders MCC 300 500 Auxiliary Systems 600 Outfit and 700 Armament Contract Escalation MCC 291 Basic Construction MCC 200 GFM Electronics MCf 400 Furnishings GFM Ordnance/Air MCC 900 Integration/ 0aA Engineering GFM HM&E MCC 500 Ship Assembly and Support Services 900 GFM Propulsion MCC 521 Other Support MCC 800 Total Ship End Cost (Dollars) Total Ship Cost Categories Figure 27. Change orders long have been both the Navy and Congress. due commonly is to the a of region (18) for difficulty The existence of change orders initial award of looseness the contract. The methods that such a change can take place are indicated in the federal acquisition regulation "changes" clauses. The reasons for change orders are the following: 0 To include about ship, 0 during state-of-the-art the lengthy improvements construction that periods To correct discovered deficiencies in information furnished drawings or government come of a contract which is the responsibility of the government, 63 To * correct drawings contract between differences and ship specifications, * To incorporate construction, safety items 0 To incorporate improvements that forces afloat, operational during emerge that are generated by approved and the for implementation, * To have the shipbuilder repair or modify GFM, " the contract ship delivery To change contract date of delivery, or the method point, the of shipment or packing. are about year. The budgeted for interest as ships lead of the possible, cost 5% and 8000 to 3000 There for for orders change follow as shipyard to include is there see to present system already mentioned consequent increase especially for in lead a 1, costs ships. is For very the 10% is in the many it change their change a to orders under incentive in decrease Chapter in no currently amounts As ships. fiscal each orders change levels. orders and the As the significant number change orders DDG-51 accounted for over 17% of the total cost. NAVSEA's use of CER's Historically CER's were used to relate cost to SWBS weights under the following formula: 64 C = f * f Where a represents material per cost ton technical parameters anticipated. systems that These (SWBS weight) relationship functional labor and/or cost ton. Other also used when better results are are could include cost of cost relate per relating to power energy generating rating and weight. The following equation would be used: C = X (R/Rs)Kr (Km x W) where These Kr R = Rs Km W = = = = power rating (e.g., horsepower) consideration power rating of "standard" unit cost per unit of weight weight of unit equations in then cost factor based on unit power rating the generate discretion basic of the CER of unit under as estimator to what he is going to expand on or change the initial CER. are adjustments as costs well made as for an inflation It relationships. of incorporation labor of and a is extent Typical material historically acceptable level of risk. This process is far from an exact science and therefore judgment requires and experience. According to the level of detail of the data available from the contractor CER's according performed. The or to shipyard, the the class following of estimator estimate estimating has that to develop is relationships being are 65 by presented NAVSEA as the suggested group relationships for class F estimates: SWBS 100 - Hull Structure Item Labor CER Material CER GR 150, Deckhouse weight (Tons) X MH/Ton $/Tons (specific) (specific material) GR 100, Remaining weight (Tons) X MH/Ton (steel) X $/Ton (steel) Adjustments are made for different materials used: Mild Steel (Tons) High-Yield Steel (Tons) High-Strength, HighAlloy Steel (Tons) X MH/Ton X MH/Ton X MH/Ton X $/Ton X $/Ton X $/Ton X MH/Ton X $/Ton X MH/Ton X $/Ton For Submarines: Pressure Hull Weight (Tons) GR 100, Remaining weight (Tons) SWBS 200 - Propulsion Plant Item Labor CER GR 220, Energy Generation System Material CER MH/Unit, Rating, Ton, or Combination Marine Vendor Input GR 230, Propulsion MH/Unit, Rating, Ton, or Combination Marine Vendor Input GR 240, Transmission MH/Ton $/Ton MH/Ton $/Ton Propulsion Systems GR 200, All Other 66 SWBS 300 - Electric Plant Item Labor CER Material CER MH/Unit, Rating, Vendor Input Ton, GR 310, Electric Power Generation GR 320, Power Distribution Systems (Tons) GR 330, (Tons) Lighting System GR 300, All Other SWBS 400 - (Tons) GR 520, 530, GR 500, All Other(Tons) 540, 550, Since Painting the MH/To n $/Ton Material CER $/Ton Labor CER MH/Ton Material CER $/Ton* MH/Ton $/Ton* MH/Ton $/Ton* Outfit and Furnishings GR 600, Outfit and Furnishings (Tons) SWBS 700 - $/Ton Auxiliary Systems Climate Control GR 630, MH/To n Labor CER MH/Ton Item GR 510, SWBS 600 - $/Ton Command and Surveillance Item GR 400, Command and Surveillance SWBS 500 - MH/To n MH/Ton $/Ton MH/Ton MH/Cubic Number $/Ton Armament majority of armament is GFM, the items separately costed by the vendor or subcontractor. costs are for installation of the equipment. are Shipyard 67 Material CER Labor CER Item Guns MH/Unit $/Unit (Units) MH/Unit $/Unit MH/Unit $/Unit (Units) Missile Launchers Torpedo Tubes (Units) $/Ton MH/Ton GR 700, All Other (less weight of guns, etc.) (Tons) SWBS 800 and 900- Integration/Engineering and Ship Assembly and Support Services The manhours represented by these groups are type requirements, of shipyard is involved. dollars Group of of the percentage 800 sum of most historical 900 and for the work function of specification a and ship, The required dollars material and can significant, and material manhours be which expressed as a and material historical manhours dollars for Groups 100 through 700 of the same ship. Limitations of Weight Based System: " It cannot easily estimate cost differentials below gross levels of precludes studies the the of work breakdown method from designs, (WBS) . structure being materials, useful for and This trade-off manufacturing processes. " It cannot estimate cost differentials performed at different stages of outfit of construction: work on unit, 68 on and block thumb on that indicate Various board. these cost rules established can differentials of vary from 300% to 500% or more. * It cannot estimate cost configuration complexity, density HVAC (e.g. deckhouse) or differentials such as compartment installation system on board the location due engine room installation versus ship to or system in tight (e.g. confining easily accessible weather deck installation). * It cannot estimate cost differentials due to orientation of work (e.g. less productive work versus over head more productive down hand work). " It cannot estimate build of strategy, selected cost differentials due the including outsourcing components to more to changes in manufacturing productive, costly less vendors and suppliers. * Since it operates mostly at high levels of the WBS, it cannot easily translate or segment costs from one type of ship to another, particularly ship types and hull forms not yet developed and built. In typical government fashion, although it is clear that a Paleolithic cost estimating system is being used, being to done improve the current situation. little The is NAVSEA 69 guide for the ship although "weight has been shown the past the other in cost available weight if is cost the the most past parameters reference manual parameter and provide good estimates, in been encouraged to be are states this that used to results suggests commonly estimator has improved (18) estimator used with, or anticipated". fact, to explore in lieu Although cost estimates of the conducted by the Navy are still primarily weight based. How can when weight different completely gives be the single designs different can cost? have The estimates incorrect competing preliminary sensitive enough most cost the weight current same approach when especially designs when important because evaluating the the but inherently comparing system effects factor is of not subtle design changes. The weight based model does not reflect or incorporate the effects of productivity changes or the process by which the vessel is built. hullform by change An example reducing in insignificant relationships, actual in increasing amount the steel terms resulting is in of the parallel structure of no the change "shape" midbody. The may be weight cost in of a estimating estimated cost. 70 ............. However, result definitely product oriented cost module such as PODAC. that cost only not changes with size ship modules within increase cost a in block flat several eliminating a will modular Figure 28 shows but also with ship form. Average Structural Size Productivity Factors (Variable by Block Coefficient) 2.50 L.0 2.00 -+- U 1.50 - 0 0 ---0- C,, -J 040 -a- 0.50 1.00 0.60 0.70 0.80 0.90 i R 0.50 +- 4 0 4 + f I 100 200 300 400 600 500 LWL (M) i Figure 28. Index of Estimated Shipbuilding Costs The current estimating makes method consideration of life cycle costs. when making Operating trade costs off over studies the life allowance or This is major impediment between of no (16) a different vessel can designs. amount to 71 Thus a cost estimating over 75% of total life cycle costs. that system without focuses only for consideration It be to conduct trade design at that and early the mission are requirements is inherently of visibility the true be or problem issue program that met the in an a lack of In most cases to lead can and ineffective, unnecessary, of appropriation of ensure can and realistic and analysis stage leaders and cost effective manor. efficient costs benefit cost reliable offs development; mission cycle life cost acquisition initial is important and necessary that both designers flawed. able on operationally useless and/or expensive vessels. In all to fairness the Navy, NAVSEA faces in acquiring useful data from shipyards. costs are bid data. of distributed a unit production great difficulty In most cases the The data is also gathered on the basis system which rather forces the than on the basis Navy to use a SWBS of a cost breakdown. The next chapter its ship incorporate non evolved insight will give cost estimating weight based into how capabilities parameters industry has in order into to their forecasts. 72 CHAPTER 5 - The Product model was PODAC: Oriented conceived as that would employ (PWBS) by a Design and group joint and a means a product technology government, Construction of developing oriented (GT) . industry, (PODAC) a cost model work breakdown The system and cost was academia system developed consortium and the research funded by the Naval Surface Warfare Center (NSWC). The developing team was comprised of: " Avondale Industries " Bath Iron Works " Ingalls Shipbuilding * National Shipbuilding and Steel Company * Newport News Shipbuilding " University of Michigan " Designers and Planners " SPAR Associates * NAVSEA The new program issue was designed to address the long facing the traditional weight based models primarily linked incorporates to design algorithms features. that can The determine standing that were PODAC the system effects on cost of subtle design changes that have little or no impact on weight. It is a program that focuses on the production 73 provided generalizations 29 shows how rather product interim each of process by for from project changes the viewpoint of a PODAC Figure CER's. based weight broad on than a System based to a Product based approach. PRODUCT WBS SYSTEM WBS De:e & Eanrn $lp lLp Zone & -HullBkck iull Um: & C-ifit Modjle: S:ucStre 1i Machi:iaiElectxcal Hui1 Ouri: Askmb. Sub Assembly MPnXactSud Fa:- systenz C A, c =:2:odat-:: SLp-md Suppcr Seice Camnpc:entm I Figure 29. The in used successfully government been has program and System vs. Product WBS operational industry programs of specifications both been has and 1997 since range wide a (16) for both domestically and internationally. As already define to system previously costs. information: types of type. The hierarchical Figure defined 30. by At each their finished product. effects of design described, defined is work The system the classification breakdown stage or specific process, work using process, structure, product is PWBS a uses three work and shown on interim products are up the types that make In this way it is possible to assess the changes and innovations as well as to 74 analyze their on impact life total the cost cycle of a vessel. z me. .. b Naraska ho is wd-p r i a ftffl Piew 12 MM 1 WR wM . yes Fahne~r~ft het from meeapw 1.m11atfrmsst 1A4 L orr 1.4 1 IS 30.3.*4..VAS3 3 Sujlo Anon"m uve sp ~ LIM 32ns . WA S&radw*c Asmeft ,j%c321 y 03eve m. ani I11.411-1 1 1 -Pr~di.s iuoem Figure 30. e~nge.reem a PDAC PWBS Setin &1c4n .. KA (P2DAC 75 "1111 in Whereas generally defined are CER's system estimating cost SWBS a " ........... ~~nn nill I1'11" ~~~~~1111111 ~~...... through weight based relationships, in a PWBS system the definition of CER's changes with each level of definition. Examples of such evolution of CER definition is shown in Figure 31. Possible Levels of Cost Estimating Relationships -- Mhrs"EA Mhrs/To hlrs/Toni Nhrs/Ton CER Change with PWBS Hierarchy Figure 31. (14) Use of Empirical CERs in the PODAC Model Empirical the PODAC estimating CERs Cost are also Model Basic to the used in provide Construction a Parametric top-down Costs at Module approach the of for Concept, Preliminary, and Contract stages of design: * concept design level cost based on complexity factor (explained later in this report), displacement, and speed, 76 " preliminary design cost level based on complexity factor and system-based weight at the SWBS one-digit level, * contract factor design level cost weight system-based and based on the at complexity two- or used in SWBS three-digit level. A combination conjunction based of with complexity form CER's weight traditional factors, backbone the of based CER's and process, the product estimating PODAC system at every level of design. 1. Concept Design Level: Price = Complexity Factor x *where All Price the is Indirect Costs, [ 752 x DISPL0 sum of Labor .835 Cost, x SPEED' .2] Material Cost, and Profit Complexity Factor = Ship Type Factor x Size Factor Ship Type Factor from Table 2 Size Factor = 32.47 x DISPL 03 7 9 2 DISPL = full load displacement in long tons SPEED = maximum sustained speed in knots It is there important is elements no of to note ability price, that to such at the distinguish as labor Concept between and Design the material level, various costs. 77 the Additionally, was approach first ship design for of and a estimate price Shipbuilding U.S. and class, engineering. did For using determined Programs, not include naval this for the the cost for it did not was ships, include the costs of weapons or Navy program management. LSHIP FACTOR TYPE Tanker Product Tanker Single Hull Chemical Tanker 0.80 1.13 1.25 Double Hull Tanker 0.90 Bulk Carrier Ore/Bulk/Ore Carrier Reefer 0.86 0.95 1.16 Containership Roll-On/Roll-Off 0.96 0.83 Car Carrier Liquid Petroleum Gas Carrier Liquid Natural Gas Carrier Ferry - Aluminum High Speed Ferry Ferry - Aluminum SWATH 0.61 1.14 1.12 0.15 1.25 0.70 Passenger Fishing 3.00 2.20 Harbor Tug 0.20 Naval Aircraft Carrier 6.00 Naval Combatant, Naval Combatant, Cruiser (Nuclear) Destroyer 9.00 8.00 Naval Combatant, Frigate 7.00 LHD/LHA 7.00 Amphibious, LSD/LPD Auxiliary, Oiler Auxiliary, Tender Research 5.00 2.25 4.50 1.25 Naval Amphibious, Naval Naval Naval Naval Naval Fleet Tug 1.00 US Coast Guard Icebreaker 4.50 US Coast Guard Buoy Tender 2.00 Table 2. Sample Ship Type Factors for Empirical CERs 78 Factor = Complexity (from table Ship Type Factor 2) x Size Factor 0 32.47 x DISPL- Size Factor = .3792 DISPL = full load displacement in long tons 2. Preliminary Design Level: At the CERs Preliminary Design level, for Domestic labor distinguish Complexity Factors and Size Factors as the Programs Shipbuilding from are material derived following weight-based as from can shown the Ship be in seen to Table 3. Type Factors shown before in Table 2. MATERIAL DOLLARS DESCRIPTION LABOR MANHOURS 100 Structure x CF WGT1 0 0 0.862 177 x 800 x WGT1 oo 200 Propulsion CF x WGT 200 0.704 365 x 15,000 WGT 2 0 0 300 Electrical 682 x WGT 30 0 1 .0 SWBS 400 Command Control 500 Auxiliary and Outfit Furnishings x 34.8 1.24 310 x WGT 6 00 .9 49 20,000 x 25,000 x WGT 30 0 1, 605 x WGT 40 0 .795 CF and 5 0 WGT50 600 2 + I I 40,000 x WGT 40 0 x 10,000 + 10,000 x U U WGT500 5, 0 0 U U + 10, 000 WGT 60 0 Table 3. Empirical Preliminary CER Derivation 79 x CF = Complexity Factor = Ship Type Factor x Size Factor 0 Size Factor = 32.47 x DISPL- .3792 DISPL = WGTxoo 3. full load displacement in long tons = weight of SWBS X00 in long tons Contract Design Level: At the Contract Domestic guish Design level, Shipbuilding Programs can also be labor from material, Complexity Factors are from the for seen to distin- as shown in Table derived CERs weight-based 4. Ship As before, Type Factors and Size Factors. SWBS DESCRIPTION LABOR MANHOURS 110 Hull Structure CF x 4 x WGT110' 150 Superstructure 0 384 CF x 5, 157 x WGT1 5 0 . 161 Structural Forgings Castings and CF x 314 321 x WGT 1 6 1 0. 62 3 95 Structural Closures 1 60 x WGT 1 67 / 8 169 Special Purpose Closures CF x 36 x WGT1 170 Masts and Towers 0 73 5 CF x 149 x WGT 1 7 0 ' 167/ -2 8 6 9 0. 96 9 Table 4. Empirical Contract Level CER Examples 80 CF = Complexity Factor = Ship Type Factor x Size Factor Size Factor 3 7 92 x DISPL-. = 32.47 DISPL = full load displacement in long tons WGTxyo = weight Similar of SWBS XYO Contract SWBS Groups 2 - Design in long tons Labor have CERs been derived for 6. Improving Empirical CERs: The suggested product-based CERs include the following, of detail. It is important and process-based Empirical at the Preliminary Design level to note that these Preliminary CERs are constructed by collecting data at the Contract and Detailed Design levels. * STRUCTURE structural at the weight, BLOCK number level, of with parts, known block surface area, and joint weld length: - manhours = f (number of parts) for preparation, - manhours = f (number of parts) for fabrication, - manhours = f (weight, surface area, weld length) for sub-assembly, 81 - manhours = f (weight, surface area, weld length) for assembly, - manhours = f (weight, surface area, weld length) for erection. * PIPING at the BLOCK level, with known block piping number of parts: - manhours = f (number of parts) for preparation, - manhours = f (number of parts) for fabrication, - manhours = f (number of parts) for sub-assembly, manhours = f (number of parts) for assembly. * OUTFIT at the BLOCK level, with known block outfit weight and number of parts: - manhours = f (weight, number of parts) for on-unit outfitting, - (weight, number of parts) for on-block manhours= f (weight, number of parts) for on-board manhours= f outfitting, - outfitting. 82 0 PAINTING at the BLOCK level, with known block surface area: - manhours = f (surface area) for block painting, - manhours = f (surface area) for final painting. Sample Representations of Empirical CERs: For Preliminary Design level CERs for LABOR in MANHOURS: STRUCTURE manhours: Preparation = f (Complexity Factor (CF), number of parts) Fabrication = f (CF, number of parts) Sub-Assembly = f (CF, weight, surface area, weld length) Assembly = f (CF, weight, surface area, weld length) Erection = f (CF, weight, surface area, weld length) PIPING manhours: Preparation = f (CF, number of parts) Fabrication = f (CF, number of parts) Sub-Assembly = f (CF, number of parts) Assembly = f (CF, number of parts) 83 OUTFITTING manhours: On-Unit Outfitting f = (CF, number of parts, weight) On-Block Outfitting = f (CF, number of parts, weight) On-Board Outfitting = f (CF, number of parts, weight) PAINTING manhours: Block Painting = f (CF, surface area requiring paint) Final Painting = f (CF, surface area requiring paint) = f SUPPORT manhours: (CF, displacement) Complexity Factors: There been are introduced Several have several of been types into these of the complexity PODAC empirically presented in the system factors that derived that adjust complexity previous section. have CER's. factors Complexity factors adjust CER equations according to each level of the hierarchy of the PWBS. conditions consuming, workshop become and to The increasingly expensive on reason for this is that working board as the more work installation. difficult, progresses Ideally from the time the most preferable place to do work would be: 0 Under Cover 84 .. m e.i in na. ienmi nu wimus ng ynsu min uumulys ... mmm "".. - ---- '1111111"'- m =111111..11.11............ -- * At an easily accessible area " Where less support services are required " Where tools and equipment are readily available Thus most the assemble the vessel is in the workshop. work location is to do the work when the blocks are not too large than workplaces convenient productivity on which and The least desirable On board. block work (under 500 tons) There onboard. are more is added if the blocks can be assembled under cover to eliminate the effects of weather conditions. work, construct to place efficient cost involves the assembly of Lastly on unit outfit modules, can produce cost savings since it is easier to access, assemble and outfit a unit on block rather than on board. Figure 32 assigned to different shows comparative complexity factors work sites. Addad Cost Factor 500% 400%300%200%- 100% 6 0% In Shop On Block On Board Figure 32. Complexity Factor by Work Stage (15) 85 work, by but type the work of location of the only by the factors differ not Complexity performed being at that For example down hand welding is much particular location. cheaper and more productive than overhead work at any stage of production. of the PWBS being However, conducted to due same for the 33 shows Figure workplace. be the cannot CER's being used at the the difficulty each level same type of work of access typical complexity to factors the that are assigned to different working sectors of a vessel. TABLE 10.1 Typical Added Complexity Of Ship Zone Work Ship Zone Added Cost Factor 0% On Weather Deck Oil Tanks 25% Engine Room 50% Superstructure 25% Pump Room 50% Holds 10% Double bottom 25% Figure 33. Complexity Factor by Work Area Interim Products The CER's system (IP) that are are there developed in series of pre-costed, to be conducted. (23) order and incorporated to subdivide the into the new vessel in a re-usable modules or packages of work Typical examples of standard work packages 86 are that are are categorized The combination estimator Cost can work or CERs of sections different organized and just like Standard work packages, developed for CERs system. 34. Figure in shown in then libraries the select packages the ship within the of appropriate pertaining to the particular project. Fi I It f11 ' ' I It IIN - Iidm I %sipand M.-imjt-mf-nk Edt Vie Ervrrnnert LbraP Dala Sytlem Repot ?ia- @ Window Het CPG A Z U De s cripfa n h ; Alummirm b-r, b[7e- as;-_-bl., i tk i bli., :%A -6-_ khu bL. a;Au b" 213 E &L IS i& Sh.' Alum mLLN r m bcn20 bk-% asiE--biv, i-ipe _ .: -ti bo::.:rr 33 -E - J -ottor AJUMm 4hA, EAL - F hp,: Ahimitm bowi-n b-1r ar-',, fbly. - pp' - de -.rall Package -~- -',. 6 E3, -E 3-~ !EA 3Kh Mi E rh~nttn-i de ':hvIl r344:JL-Y .. 734 Fird I -,I Im;I mr-nn- nn- ; '7P. -. nII bi: as;_biv, -at __ :he :, - IPr hn , ppw h I h21 bcI z. b : el:bv, m-pw. zde i l =I bw :-z M c, M Z:u i F i4-A-e .. Alumritmrri iy rkn uu' ;=~" :s . - r7, derr jN Au ee g Jn uas-ey 1P BA 1: &L IButto,-:.- AluM Cr w. :on ::C- r2 S~F, 11a: -ulu[ b.:.:11 4-.a-AL- (-:: O l2k Al Figure 34. :ne .:. Examples of Work Packages (14) Such reusable modules can be subdivided into reusable work that packages require amount a of consume standard money. A a amount typical standard amount of and work, example of cost such material, of a standard a process is shown on Figure 35. 87 ____ ---_ - ---- - -- - Re-Use Package CER: Welding Repairs:Cracks Labor CER Labor JoM I MHtFT 0.500 Drill Out MHIFT 0.250 Welding Repairs: MH/FT 0.250 Gen Labor: MH/FT 1.000 Total: Figure 35. Example of Re-Useable Work Package (16) In order implemented in shipyards presented by necessary that the strategy in mind. capability and to the outfitting, generic the the to the from the construction of the lack had shipyards the using modular vessel strategy build is organization build a such although construct to on block Experience that showed DDG-51 with it construction, modular technical design information sent tailored is shipyard to maximize cost savings in order outfitted, pre effectively be to system cost a such for of methods consideration design excessive in resulted the re- workings and a low level of productivity. SPAR Associates conducted a study to determine the possible cost savings that could occur by the use of built strategy savings Figure through 36 shows vessel the use that of attempted minimal on to a modular, PWBS maximize cost board a summary of the results. It outfitting. is important 88 to note the 16% cost savings realized by the implementation of such a generic build strategy. bkc k & 0ei Jn i OuIi it nq S-jvi,qs rrc-, lv si5 Mcde1: s I An Ssr ;:le S'im Drdjctic-. 20 130 2T T sikr S.-rrrary ir 'cw'd St'p Cos v 5:C,5 - C ti Ca Ra i&od ';c:I Cvi sad XR 5 . 1 S% 4 2X z%2 _C S 106 CC 5yJro; 7CC165CC % 57! 15275 Cri J Trt c.ck C=ni & O rI =e le X,13C 1% ,4C 2S 1.C 5 !1S4C 3 1.5 1I3 63 1&'n I j1' V _,2 Dcc C -aings taaid Grig mal 12 1E 312-1 37! 313 5 T, :)-ce S63 . 719 927 S 2522C.28 SXelCC'202C Possible Outfitting Cost Savings Figure 36. 1.5% (15) Design Trade off Capabilities An feature interesting incorporation trimarans new of into the the of hullforms database. The new such is the catamarans, and system PODAC as of development new CER's for different vessel classes and designs is very important as the Navy continues such configurations. libraries helps make to design and purchase Any added data into the the final ship cost vessels with system and CER estimation more 89 .. . Clearly realistic. cannot be used for variations of CER's that are Figure for used monohull steel composite trimarans. material be cannot CER's Similarly, vessels. class destroyer submarine ................................. CER's 37 shows the with the available new PODAC system. Composte (AH) HY -80 HSLA-80 HTS H -100 HSLA-100 -. 1 30 wanmAn (4:P Ti 5OAS Ti 130) Aurzanum (Sxx) Aiumknum r (2xn 7 Stanw*ss Steel itokpex Grscsj) De Structiral Materia Setections MMICode Stuctwal Mateial Selections: Ml Steel (A. 8. C, CS, D. Ei 2 3 Compoite 4 5 Comvoste Caffoste 6 Coposue 7 Compeoste Composie Compomite a 9 10 11 fo# each nudef W provided in StrwctprpfrAy eleit. saeH Comrs0e inclusion important design trade different choosing 3 14 Is 1_ data offs. materials has That for led is to the _ 17 1 19 20 21 22 AdvwnCed Metabc or Noin-metW CoffpoksOe Wor kshet. Advanced L9twett. 7?WT Capwcty SJ4 HTs 3 3A Ad Steel 1113 HTS. d2MW Sleel 26 such of 12 opte - E-Gfas & EpoxY LASCCR Meil Sand 23 24 25 Figure 37. Material Options with PODAC The Nanced FRPC-Aed Ponei - FRP Shf1ened Panel Section - FRP Stiffened - SCRW FRP Cored Pane - SCFAW FRP Stiffened Paei - SCRW FRP Stffened FUt Section - vARTM E-gtsitnyesteir -USection - Carbon Fer & Epoxy KevAw 3 Epoxy a (16) area new decision particular ship of between regions. The use of a re-use/ modular construction and design allows the designer or cost estimator to immediately determine the cost of for using different materials parts of it. Figure 38 shows for the the vessel or on weight of whole effect using different materials on a Trimaran hull. 90 -------------- ............... Trimaran Hull Materials 4,000 3.500 2,"1 3,000 2,500 2,000 1.500 1,000 500 Ftf # ~ , 1; < .0 40 Figre 8. ateia Trde-ff nalsi (16) As already stated rather repeatedly throughout this thesis, it is not enough to simply have a weight based analysis order costs, to determine DDG-51's resulted in process. In costs. deckhouse excessive was plate an effort built with thin distortion due to plate. the shows This welding This distortion made the assembly of blocks highly labor intensive requiring the use of hydraulic rams. 39 lower produce to in the clear benefit of using a non weight Figure based system to analyze ship construction costs. 91 Structural Hull Materials e.s 0 .0 $20,000 $18,000 4,5 $16.000 C. $14,000 $12,000 $10,000 $8,000 $6,000 $4,000 $2,00 Ir E) C5Z wo 7@ U) (D LCs 4: a" )< < < co Cs X (16) Figure 39. Construction Cost Material Trade-off Although Aluminium is the in Figure The it 38, welding suffers process labor. strength than steel structure to support results in more This PODAC system has from Aluminium also a has and thus capability with costs. requires and lower tensile requires stronger and armament. equipment, hull, structure the expensive, therefore and the installation higher difficult, is trained highly least cost solution as presented higher costs. its The comprehensive CER's to incorporate the build complexity and difficulty of production into its predictions. Other trade-off studies that can be conducted by the new system include: 92 Changes " e.g. in equipment and related AZIPOD propulsion versus auxiliary geared diesel systems and rudder propulsion. * Changes in subcontractors e.g. subcontracting the vessel pipe work. " Changes in general arrangement or mission requirement. Such trade-off immediate design of the of understanding decisions designer to as procurement. why An the the cost vessel designers implication on understanding costs in should It the changes. or change paradigmatic allow capabilities is increase thought their the part fundamental process result definitely a of an of ship cheaper in and faster vessel construction. Risk Analysis An important capability of the PODAC that it presents possible high costs risk. the for The cost estimator items greater or system is the ability to specify a range of processes the risk, that the are considered greater the probability that the cost estimate is not realistic. Since type it of is impossible probability to exactly determine beforehand distribution that can be applied the to 93 the maximum and presents a series program functions data combined complex cumulative a into different the essentially probability probability then is data The the and distribution Risk. using Monte Carlo analyzed is This cost. expected an of triangular probability distributions. single, one input the life real of variability of combines then into the value minimum of to requires program issues, The due CER or process each distribution of costs. Figure 40 shows an example of such a distribution. CO :4_1 1r 0m1 41: I Siandard N rmal Distribution, Z-Values Figure 40. The of existence Cumulative Cost Distribution a probability distribution (14) the allows estimator to develop a sense of confidence in the data that is produced, wrong, the and what probability the range of that the possible estimate cost will will be be about the expected prediction. The probability that cost does not 94 most estimators the exceed cost likely is estimate presented in Figure 41. w~UrE ~AR ~WTE mA~.OMIAI~ AP~94 PC7 79 f 1, S22L> _______________ 21.: (1)"n, --- Figure 41. Probability Cost does not Exceed Estimate (14) Life Cycle Costs Life cycle costs can be essentially divided into four main stages: In to order necessary have the The final correctly been SPAR Associates' ship owners an reason bottom with cost is line of area that concern ship of profit shipyard design a project and evaluate cost each and stage. are return it ship interested on is Such costs commercial for owners disposal. and operation, a prediction for to make always owners. acquisition, conception, in investment. estimating program provides trade-offs that pertain to life 95 maintenance several times estimating program allows to immediately determine the to have time the Thus period. and ship owner The the (ROI) design order over a certain be can analysis trade-off cost designer required freight rate in certain return on investment a has been costs) in previous sections. the and operational cycle (about 75% of life costs already stated of significance The costs. cycle expressed in terms of life cycle costs. overlooked by have a added naval Although ROI components of them. for necessary life cycle The Navy the costs acquisitions they requirement, not should feature Navy and currently to do not cost. possible how it has several a It the understand is be satisfy must least possible security commitment at the therefore reduce the Navy. particular national is this of importance The to reporting systems such as the Ownership Architecture Retrieval System (OARS) for which are breakdown. they are maintenance part all These not COMET issues, of systems integrated a with between personnel life cycle themselves costs, Cost Ownership Total deal for in (TOC) costs order but to provide direct answers to design trade off questions at the design, costing, and acquisition decision level. 96 Problems: Several issues have arisen due between the Navy, building ships and Designers subcontractors. for the US Navy are using system based cost which estimates shipyards, to the lack of coordination do design. Shipyards product based not are focus costing and while approach; the on the producibility vessels building Navy is of with a its conducting own cost operation using cost data provided by the shipyard in a product based format! A cost estimate supporting the collected in by estimating probably have is as only if estimate... ways that modular a good relatively can high modular be imperative that shipyards of (14) organize costs in cannot block difficult degree accuracy and validity of the estimate. information costs historical identify blocks the as costs, and risk be in will the It is therefore ways that can directly benefit the cost estimating process. 97 CHAPTER 6 - The MIT MIT MATH MODEL Math while serving Naval Construction Hamley. for their Navy the as the 13A in 1975 students with conjunction ship projects. design and of Naval Frigates". to designed and sophistication, and be a and It student It process the Model for revised and Math 1990. is in excel simplicity, between relatively it is compatible R. from adapted was is of tool in order to model balance generality. and use and understand The 1988, 1986, 1984, in updated was It Professor estimating cost Graham Clark 13A "Simplified called Model Design ship the with by Associate course Synthesis format in developed It was developed as an educational 13A assist was Model with all easy to personal computers. of Users the limitations. Naval It Frigates, The 8500 tons. and assumes have model is designed in order to be with a range of displacements model analyzes standard USN only design its understand however, to; applicable from 2500 to conventional practices. to The monohulls system is limited to single screw vessels with diesel generator sets. The hull options materials for considered aluminium or mild are mild steel steel hull superstructure. with The 98 empirically The weights. its purpose that, flexibility much without scope has at this be still historical methods level successful. use of data that from submitting they construction. preliminary design the model the weight (Chapter 5) . far to NAVSEA for for Even parametric are said shipyards detailed engineering designs Thus nore Congress, from appropriations limited ship design. naval is a teaching tool for a Having change. for for therefore are students are not presenting their designs The to CER's derived The model therefore based. primarily weight system breakdown weight SWBS USN the uses system to most based modern system industry systems CER's empirical Thus MIT's standard (PODAC) appears is practice from not using at this level of design. 99 CHAPTER 7 - 1. SHIP COST REDUCTION SUGGESTIONS: Improve quality of Cost Estimates * Improve Navy current the is cost estimating incorporating using method improvements that the discussed throughout this thesis. 0 Conduct independent support, and cost comparison in estimates of predictions Navy the addition, to assure accuracy. * work cost estimates independent Conduct is that suggested by of any change shipyards in order order to determine accuracy and reliability. 2. Improve contract award process 0 Negotiate prices for construction of the lead ship separately from the pricing of detail design work. * Separate ships. 3. the pricing of lead ships from follow on (4) Improve management of programs Require shipyards reports in order to to submit monthly allow project cost leaders performance to quickly become aware of cost driving factors. 100 4. Design Cheaper Vessels vessels Cheaper simpler, can be designed built and and faster methods by using the in cheaper, following general guidelines: " Maximum use of standard plate and stiffener sizes. * Avoid using thin plate to avoid distortions * Do not carry hull into curvature the structure inside of the hull plating " Run strakes in the same direction as primary framing * Design for maximum of high with the use productivity tools such as automatic welding " Design bilge strakes same thickness as bottom plates * Design to facilitate structural units, assembly machinery units, and erection and piping units " Make port and starboard units similar " Eliminate camber and sheer " Eliminate cruiser sterns and cambered transoms * Maximize use of flat panels, with straight frames, and reduce plate curvature * Locate knuckles and chins at unit breaks * Run chins parallel to keel (as much as possible) 101 Simplify bow and stern shape by removing unnecessary 0 curvature 0 Allow for large deckspace to outfitting facilitate (9) It is necessary however to be able to balance producibility with life perform cycle design and early costs and trade-offs stages of particularly design, established rather firmly, performance. where The at decisions ability the are to conceptual generally should be a top priority. 102 CONCLUSION Introducing paradigmatic difficult. introduction for teams product business is government. The between the from concept together a ensure any harder even co-operating can delivery is integrated of industry and the to so Doing in change Navy design for consideration better acquisition and total life cycle costs. Naval cost ship change the since outdated models is and any cost ship inability significant estimated still based weight assumptions whose seen not Cost 1980's. inaccurate and has estimating to using estimating reflect subtle the issues design changes result in cost overruns. The cost PODAC model the Navy funded the facing essentially using the because LPD-17, new systems. the projects. attempts deal today. project, with many of Although cost not been the government estimations To a large extent have results this clear are not is probably in similar It probably does not help that the design of the which ended up being many PODAC principles. be to effective and grossly overpriced, included Also in order for the new program to produce realistic estimates, it is 103 for necessary operating will in some a eventually time and industry thinking and take faith both in to this get product based happen for new Navy and Navy I but as practice to different and accustomed approach the the begin believe it has way. It to have it will happened effectively abroad. The MIT purpose Its Model Math it that estimates limitations of is serves are not a it useful is probably a expected the model. engineering to be It should be tool. For the reasonable method. realistic given examined whether the it would be possible to acquire a cost estimating program such as the one developed by SPAR Associates in order to improve the accuracy of the cost estimates conducted at MIT. 104 BIBLIOGRAPHY 1. "An Approach Estimating for Methodology a Developing for USCG Preliminary Vessels", Mark Gray, Cost MIT, June 1987 2. Cost Assessment in Ship Production, The Naval Architect, March 2005 3. Design and Cost Estimating Metrics, 4. Defense Acquisitions, GAO, 5. Characterization of NASSCO, April 2000 February 2005 Performance NASSCO, Requirements, February 1999 6. "A Practical Estimating", 7. Navy 8. Acquisitions: Ronald O'Rourke, "Portfolio of Ship Thomas Schiller et al, 9. Ship Options Construction Cost Combatant for Lower-Cost Ship June 2005 Designs: Early-Stage Design Tools", Marine Technology, April 2001 Impact of Producibility "The Naval for Jonathan Ross Ship Designs, Approach Design", on Cost and Performance Capt. Alan Brown et al, in SNAME, November 1996 10. "Navy Develops Product Oriented Design and Construction Cost Model", 11. Parametric "A Costs Scott Truver, of Cost Conventional US February 2001 Model for Navy Estimating Surface Ships", Acquisition Kirk Loftus, Naval Postgraduate School, September 1999 "A Producibility Corvette Bruno and and an Review Alternative Thomas Lamb, of the Contingency Producibility University of Producible Design", Michigan, Corey Report # 12. 9050-03-C5 13. Department of Admiral Stan Bozin, the Navy: 2007 President's Budget, February 2006 105 14. Shipyard Cost Estimating, 15. Cost Cost Manual, SPAR Associates Inc., New Estimating SPAR Associates Inc., 18. NAVSEA Ship Cost Estimating: NAVSEA, "In of Pursuit a versions: The Institute of Marine Engineers, 20. Short Course MIT, summer 1996 21. Ship SNAME, on Modern Ship Welding Prof. Navy", Richard David Watson, Mechanization and Worldwide, Richard Boekholt, Product Model 2002 1992, Frankel, Production and Ship Repair, Storch al, et Oriented Development, Automation in SNAME, 2003 Shipbuilding 1996 Design Howard 1998 Thomas Lamb, 23. Ship Design and Construction, 25. the 1995 22. Practical Ship Design, 24. User September 1994 Second Edition, Production, Repair Referance Manual for A Effective Cost 1998 Ship & & Other January 2003 MIT Math Model User Manual Ship Cost Estimator, August Construction 17. 19. Inc. Savings Using Modular Construction Methods Common Sense, 16. SPAR Associates and Bunch, Construction University (PODAC) of Cost Michigan, May 1995 Cost Estimate: Program Office, June 1997 26. DD-21 Cost Approach Methodology, SC 21 106 27. "Evolution of US Naval Acquisition Policies", Transactions, 2004 Surface John Combatant Hootman et Design al, and SNAME 107