Construction Engineering 380 Contract Changes

advertisement

Construction Engineering 380

Contract Changes

Contract Changes

• Types of changes

– Cardinal change- drastic change, either single direction or accumulated change in scope

– Constructive change- proceed with work even though there is disagreement over price or justification

(usually document conflicts)

– Deduct change order- may not deduct to give the work to others without basis, and usually cannot reduce POH (except fed work)

– Minor (no cost CO) and tentative (wait for price)

Contract Changes

Construction contracts are unique because owner can make unilateral changes to contract (with consideration)

Contract Changes

• Changes in scope require change orders

• Changes in time require delay or acceleration claims

• Most claims are handled in change orders

• Change orders must be in writing and confirmed

• Contractor entitled to OHP

Contract Changes

• Document the changes in scope or time

• Estimate costs

• Estimate time

• Submit request for change order per contract

• Get approval (dual or three-way signature)

• Handouts of standard forms

Contract Changes

• Field changes are used when there is no time for prior approval

• Explain and document (notification clause)

• Architect issues change directive, then contractor submits claim (court or arbitrator)

• Constructive change for extra work caused by defective plans and specs or owner misrepresentation (MSP airport)

• Contractor not responsible for synthesis and coordination of plans and specs

Contract Changes

• Scope changes are different than constructive changes- owner adds work

• If scope change becomes excessive, original contract can be voided

• Contractor entitled to payment after new contract is agreed to

• Each party must give consideration (prevents holdings tactics

Contract Changes

• “evidence of writing” required for certain transactions

– Sale of goods over $500 (UCC)

– Scope of work exceeds one year

– Involves purchase, lease or mortgage of property

– Promises to pay debt of another

– Agency contracts

– Scope exceeds life of the entity

– Agreements on consideration of marriage

Contract Changes

• Owners entitled to change the contract

• Suppliers entitled to consideration, but

“pre-existing duty” takes precedence

• Promissory estoppel

– Party has given reason to believe payment is due

– Other party relied on that promise in conduct

– Other party performs work and incurs costs

Contract Changes

• Waiver- any party can agree to relinquish a right or ignore contract clauses

• Delays

– Inexcusable- contractor pays costs

– Excusable- each party absorbs costs-

• contract delays are usually spelled out in contract

• Law delays are granted by court or statute

– Compensatory- owner pays contractor for additional costs

Contract Changes

• Acceleration claims

– Speed up construction

– Increase rate of work

– Refusal to grant extension is same as acceleration claim

– Liquidated damages and no damages for delay clauses are very difficult to enforce

(exculpatory)

– Notice and documentation are critical

– Delays within schedule float are not qualified

(conveying system at MSP airport)

Download