1. Lump-sum and unit-price estimates are forms of fixed-price estimates.
A = True B = False
2. The “bidding climate” refers to the anticipated weather conditions during the duration of a project.
A = True B = False
3. An employee of a contractor pays $450 per month for his/her portion of the medical insurance. This is an example of a contractor’s indirect labor costs.
A = True B = False
Construction Engineering 221 2
1. Lump-sum and unit-price estimates are forms of fixed-price estimates.
A = True B = False
The correct answer is A = True
Construction Engineering 221 3
2. The “bidding climate” refers to the anticipated weather conditions during the duration of a project.
A = True B = False
The correct answer is B = False
Construction Engineering 221 4
3. An employee of a contractor pays $450 per month for his/her portion of the medical insurance. This is an example of a contractor’s indirect labor costs.
A = True B = False
The correct answer is B = False
Construction Engineering 221 5
Construction Engineering 221 6
Accurate quantity takeoff of material
Accurate quantity takeoff of labor
Determine general and project overhead
What equipment will be needed and when
Construction Engineering 221 7
Begin the formation of a project schedule
Determine how project will be managed
Develop a list of questions (get answers)
Begin a relationship with owner/AE
Construction Engineering 221 8
In the arena of competitive bidding for a contractor to stay in business?
AND
In the arena of negotiated bidding what must happen in order to continue to attract clients to the negotiated process?
Construction Engineering 221 9
In the competitive arena
Need to be low bidder on sufficient number of projects to maintain a revenue base
And realize a reasonable profit to stay in business.
In the negotiated arena
Reliable advanced cost information that will become the “project cost”
Construction Engineering 221 10
Lump-Sum Estimates
Building construction
Nature of work and quantities will defined
Great for owner – financing and risk
Unit-Price Estimates
What type of construction is normally bid using unitprice estimates?
Nature of work is still well defined
Quantities of material or work items not precise
Who first determines quantities of work items?
Quantities shown for each work item.
Construction Engineering 221 11
What is the term use to describe a complete listing of all the materials and items of work that will be required for a project? (foundation to a good estimate)
Quantity survey or quantity take-off
Construction Engineering 221 12
Private – procedures (rules and regulations) normally established by owner and AE
Public – procedures follow various procurement statutes developed by federal, state, county and municipal governments
Construction Engineering 221 13
Public bidding statutes are designed to protect the public interest, not that of the contractor or AE. Their essential purpose is to protect public funds; prevent fraud, collusion, and favoritism; and obtain quality construction at reasonable and fair prices.
Construction Engineering 221 14
The decision to bid by the contractor depends on the bidding climate.
What is meant by “Bidding Climate”?
The bidding climate is the affected by:
1. Bonding capacity considerations
2. Location of project
3. Severity of contractual terms (contractor responsibilities and liabilities)
4. Owner and their financial status
5. Who is the architect/engineer
6. Nature and size of project as it relates to company experience and equipment
7. Labor conditions and supply
8. Completion date
Construction Engineering 221 15
Why is a reasonable bidding period important?
1. An accurate bid requires adequate time
2. Too little time to bid results in contractors either not bidding or bidding too high
3. Result of “rushed” or “quick” bids is NOT a lower price
4. When unsure, contractors add
CONTINGENCY $$$$$$$ to their bid
Construction Engineering 221 16
Preliminary Considerations
Become familiar with
Instruction to bidders
Proposal form
Alternates
General and supplementary/special conditions
Drawing and specifications (addenda)
Form of the contract
Prebid meeting (in-house)
Prebid meeting (with owner)
Construction Engineering 221 17
Jobsite visit
Observe job site specific conditions that must be covered in the bid (site access, logistics…)
Bid invitations
Quantity surveys (take-offs)
Unit-price project (AE’s #’s vs contractors)
Experience needed to do quantity surveys?
General contractor’s cost estimate of own work
Construction Engineering 221 18
Material Costs – anything that becomes a part of the finished structure
Material Allowance – What is it? Example?
Direct Labor costs
Basic wage rates of the labor categories
Production rate that applies to the work type
The largest areas of uncertainty
Where is the most reliable labor productivity information to found?
HISTORICAL COST DATA
Construction Engineering 221 19