Capital Action Plan 2013-14 Name of Action Plan Capital Action Plan Task Due Date Responsible Continue to Implement Housing Renewal Plan: July 2014 Physical Plant University Housing McCalmont Hall Capital Action Plan Continue to Implement Housing Renewal Plan: North Hall design phase Capital Action Plan Manage major enumerated capital Project: Harvey Hall Phase II: Process Measures & Performance Indicators • June 2013: 35% design report • Aug/Sept 2013: Final design • Nov 2013: Bid process • January 2014: Construction phase • July 2016: Project Complete Construction Phase: • Jan 2017 – July 2018: Cubes A, B&C Physical Plant University Housing • Design Phase to begin July 2016 • Bids: Oct 2016 • Construction: o Jan 2017 • Completion: July 2018 July 2015 Physical Plant CAHSS • November 2013: Design phase • June 2014: Construction to start • July 2016: Project complete Progress as of 12/2013 Progress as of 5/2014 • Design report complete • Final design complete • Contracts awarded • • • • • Construction begins on January 20 • Completion date on schedule • UW-System postponed two years. • Final design complete • Construction scheduled to begin February Design report complete Final design complete Contracts awarded Construction began January20, 2014. Project on schedule. • Completion date planned for July 25, 2014. • Program approval delayed until January 2015 by UWSA and DFD. • A/E selection: January 2016 • Pre design report: July 2016 • SBC and BOR approvals: September 2016 • Start of construction: January 2017 • Substantial completion: July 2018 • October 2013 BOR and SBC approved for construction. • Pre Bid Tour: April 30, 2014 • Asbestos Bid date: May 8, 2014 • MEP Bid date: May 14, 2014 • General (Single Prime) Bid date: May 29, 2014 Capital Action Plan Manage Major Enumerated Capital Project: Bowman Hall Exterior Repair Delayed due to increasing scope and cost. Physical Plant • Design phase delayed due to increasing scope and cost. • A/E selected and has begun work on design. • Project moved from an all agency to a major enumerated project with a revised budget $8.4 million. Add doors and window replacement for the entire building. Moved to major project 15-17 biennium.