Electricity Transmission in Deregulated Markets: Challenges, Opportunities, and Necessary R&D Agenda PRICING TRANSMISSION CONGESTION IN ELECTRIC POWER NETWORKS Chan S. Park, Jorge Valenzuela, Mark Halpin, Sevin Sozer, and Pinar Kaymaz Auburn University December 15-16, 2004 Outline I. Introduction II. Approaches to Transmission Congestion Pricing III. Pricing Congestion under System Stability Constraints IV. Analysis and Economic Interpretations V. Conclusion December 15-16, 2004 2 Introduction In the PJM and NYISO markets, the cost of moving power represents between 6 to 12% of total electric costs. Consider that the power traded in the US wholesale market was over 800 TW-h in 2000 and rapidly increasing. However, relatively little money has been put into the transmission system. December 15-16, 2004 3 Congestion Costs Statistics Total Congestion Cost as a Percent of the Total Electricity Cost $ Million Total Congestion Costs 2000 2001 2002 2003 700 600 500 400 300 200 100 0 PJM NYISO 14.0% 12.0% 10.0% 8.0% 6.0% 4.0% 2.0% 0.0% 2000 2001 2002 2003 PJM CAISO Sources: PJM State of the Market Report 2003, 2002 NYISO State of the Market Report 2003, 2002 CAISO Annual Report on Market Issues and Performance 2003, 2002 December 15-16, 2004 4 NYISO CAISO Research Issues Objective: To include system’s stability in the operation and economics of power systems How should the system’s stability be included in the optimal dispatch model? If modeled as a flowgate constraint, how should the additional cost created by the flowgate constraint be allocated? Which congestion pricing schemes send more appropriate economics signal for generation and transmission expansion that will assure system’s stability? December 15-16, 2004 5 Modeling System’s Stability Dynamic simulations suggest that proximity to a stability limit may be predicted using flowgates Some companies presently manage system’s stability using flowgates Flowgates can be related to generator outputs through Power Transfer Distribution Factors ⎞ ⎛ N k ⎜ PTDFi, j * Pk ⎟ ≤ Pflowgate, max ⎟ ⎜ ⎠ ⎝ k =1 ∑∑ i, j December 15-16, 2004 6 Congestion-Pricing Approaches Flat Rate Marginal Cost Market-based • Uniform price approach • Marginal cost pricing • Market finds its own equilibrium. • Used by preliberalized U.S. Markets • Used in restructured U.S. markets • Requires a wellestablished market structure • Based on full cost recovery and regulated return on investment • Based on optimum power flow models, nodal pricing, and flow-based pricing • Based on a coordinated multilateral trading model • No proper locational economic signals • Appropriate locational economic signals • Appropriate locational economic signals December 15-16, 2004 7 Security-Stability Constrained OPF: A Nodal Pricing Model N Min z = ∑ Minimize Total Generation Cost ck g k k =1 Subject to Subject to ∑S k ,ij × f ij + g k = Lk (λk ) Node balance equations for k = 1,…,N ij f ij − Yij * (θ i − θ j ) = 0 − f ijmax ≤ f ij ≤ f ijmax Voltage/flow equations on each line i-j (µ ij ) Thermal flow limits for all lines i-j g kmin ≤ g k ≤ g kmax Power capacities for each generator ∑ Security Constraint (Angular Stability ) ij∈FG fij ≤ FG max December 15-16, 2004 8 Security-Stability Constrained OPF A Flow-based Pricing Model N Min z = ∑c Minimize Total Generation Cost k gk k =1 Subject to Subject to N N ∑ g −∑ L k =1 k k k =1 N − f ijmax ≤ ∑ =0 (λ ) Total balance equation (µij ) PTDFijk (g k − Lk ) ≤ f ijmax Thermal flow limits for all lines i-j k =1 g kmin ≤ g k ≤ g kmax N ∑ ∑ PTDF ( g ij∈FG k =1 k ij k Power capacities for each generator − Lk ) ≤ FG max LMPs are calculated by ( µ FG ) Security Constraint (Angular Stability) LMPk = λ + ∑ ( PTDFijk × µij ) + ij December 15-16, 2004 9 ∑ ( PTDF ij∈FG k ij × µ FG ) Congestion Cost Calculation Nodal Pricing Model Total congestion cost Flow-based Pricing Model Total Congestion cost CR = ∑ ( LMPj − LMPi ) f ij ij CR = ∑ ( µij × f ij ) + µij × FG max ij Congestion cost allocated to line ij ( CRij = LMPj − LMPi December 15-16, 2004 )f Congestion cost allocated to line ij CRij = µij × f ij ij CRFG = µij × FG max 10 Nodal vs. Flow-based Model Nodal Model Flow-based Model Generation Expansion Incentives Provides correct incentives. Provides correct incentives. Transmission Expansion Incentives Little incentive provided. Correct signals available for transmission investment. Market Experience PJM (1998) NY ISO (1999) ISO-NE (2003) CAISO (Zonal) ERCOT (proposed flowgatezonal) December 15-16, 2004 11 Numerical Example 55≤ g1≤110 300≤ g5≤600 $10/MWh Bus 1 $14/MWh Bus 5 L1 = 425MWh Bus 2 Bus 4 Bus 3 L3 = 425MWh December 15-16, 2004 100≤ g4≤200 130≤ g3≤520 $25/MWh $30/MWh 12 L2 = 425MWh Effects of the Stability Constraint Alone Assuming no flowgate and no thermal limits on the lines: Bus 1 $30/MWh Bus 5 $30/MWh Bus 4 $30/MWh December 15-16, 2004 Bus 3 $30/MWh 13 Bus 2 $30/MWh Effects of the Stability Constraint Alone Assuming no thermal limits on the lines: Flowgate Limit 670 MW $20/MWh Bus 5 $10/MWh Bus 4 $10/MWh December 15-16, 2004 Bus 3 $30/MWh 14 Bus 1 $30/MWh Bus 2 $30/MWh Effects of the Stability Constraint Alone Without FG Total Revenue to Gen $38,250 Total Production Cost $23,490 Net Income to Gen $14,760 Congestion Cost $0 Total Cost to Load $38,250 With FG $24,850 $24,590 $260 $13,400 $38,250 Redispacth Cost -$13,400 $1,100 $0 Revenue to generators decreases significantly. Total cost to load remains unchanged. Although redispatch cost for the production cost is $1,100, congestion cost is $13,400. December 15-16, 2004 15 Allocation of Congestion Costs Line 12 23 Flow-b. App Nodal App. $0 $0 $0 $0 54 43* $0 $5,300 $0 $0 41* $0 $2,550 51* $0 $5,550 FG $13,400 $0 Note that under the nodal congestion pricing scheme, no congestion cost is ever assigned directly to the flowgate constraint. December 15-16, 2004 16 Effects of the Flowgate Constraint Alone Partition of the Total Cost to Load in terms of total generation revenues and congestion costs when there are no thermal limits on the transmission lines. $45,000 $40,000 Cong. Cost G5 $35,000 $30,000 $25,000 $20,000 G4 $15,000 $10,000 G3 $5,000 G1 $0 650 670 700 725 750 775 800 825 850 875 900 Flowgate Limit (MWh) December 15-16, 2004 17 Effects of the Flowgate Constraint with Thermal Limits Flowgate Limit 670MW Bus 5 Bus 1 Limit 240 MW Bus 4 December 15-16, 2004 Bus 3 18 Bus 2 Allocating congestion costs $6,000 1 5 Congestion Cost $5,000 $4,000 4 3 2 $3,000 $2,000 $1,000 $0 Line -$1,000 12 23 43* 54 41* 51* FG Flow-b. App. $0.00 $0.00 $0.00 $5,208.5 $0.00 $0.00 $4,205.3 Nodal App. $97.78 -$444.77 $1,392.0 $3,600.0 $336.57 $4,432.2 December 15-16, 2004 19 $0.00 Allocating Congestion Costs to Transmission Lines PTDF-based Allocation Assumes equal flow sent from generators. Constant coefficients used every time. Flow-based Allocation The price of the flowgate is used to assign values by CRij = p FG × f ij (∀ij ∈ FG ) Flow-based Allocation PTDF-based Allocation Line Flow Cong. Cost ΣPTDFij Cong. Cost 43 278.40 $1,747.43 1.1177 $2,350.14 41 137.55 $863.37 0.3382 $711.12 51 254.04 670 $1,594.52 $4,205.32 0.5441 2.0000 $1,144.06 $4,205.32 Total December 15-16, 2004 20 Comparison of the Congestion Allocation Schemes $6,000.00 1 5 $5,000.00 Congestion Cost $4,000.00 4 3 $3,000.00 2 $2,000.00 $1,000.00 $0.00 -$1,000.00 Line 12 23 43* 54 41* 51* Flow-b. Alloc. $0.00 $0.00 $1,747.40 $5,208.51 $863.35 $1,594.51 PTDF-b. Alloc. $0.00 $0.00 $2,350.14 $5,208.51 $711.12 $1,144.06 Nodal App. $97.78 -$444.77 $1,392.02 $3,600.00 $336.57 $4,432.23 December 15-16, 2004 21 Comparison of Congestion Cost Allocation Schemes Nodal Approach Provides little incentive for transmission expansion. Prices can’t give you which constraints are binding. Assigns value to uncongested lines. Does not assign a direct cost to the flowgate Flow-based Approach Assigns costs to only congested lines. Assigns a cost to the flowgate. Flow-based allocation uses flowgate price to assign congestion due to stability to the lines. PTDF-based allocation uses fixed coefficients to assign congestion to flowgate lines but assumes equal dispatched flows from generators. December 15-16, 2004 22 Conclusion This paper examined transmission congestion pricing on power networks with flowgate-based stability constraints. The difference of these pricing models is the allocation of the total congestion costs to the lines on the network. Effects of the stability constraint on the total cost of generator dispatch, total cost to load, and total congestion cost were analyzed. December 15-16, 2004 23 Thank you! Corresponding authors: Chan S. Park (park@eng.auburn.edu) Jorge Valenzuela (jvalenz@eng.auburn.edu) December 15-16, 2004 24 Congestion Costs Reported from ISOs Transmission congestions and investment have become an emergent problem. 600 517 500 430 391 400 $ Million 525 310 271 300 200 100 0 132 99 120 107 53 99 00 01 02 42 00 01 00 01 02 PJM ISO-NE Source: Lesieutre and Eto 2004 December 15-16, 2004 25 CAISO 00 01 02 NYISO Optimum Dispatch Without any Congestion Optimum dispatch without the stability constraint and without transmission thermal limits No Flowgate limit 1 2 3 4 5 LMP $30 $30 $30 $30 $30 Generation (MW) 110 0 365 200 600 1275 Total Production Cost $1,540 $0 $10,950 $5,000 $6,000 $23,490 Total Revenue to Gen $3,300 $0 $10,950 $6,000 $18,000 $38,250 Net Income to Gen $1,760 $0 $0 $1,000 $12,000 $14,760 425 425 425 0 0 1275 $12,750 $12,750 $38,250 MW $0 Gen Redisp. $0 FGR Price $12,750 Tot FG Cong. Cong. Cost $0 0 $0 $0 $0 Load (MW) Total Cost to Load December 15-16, 2004 26 Total Optimum Dispatch with Stability Constraint Optimum dispatch with the stability constraint and without transmission thermal limits Flowgate limit 670 1 2 3 4 5 LMP $30 $30 $30 $10 Generation (MW) 110 0 495 $10 (1) 100 570 1275 Total Production Cost $1,540 $0 $14,850 $2,500 $5,700 $24,590 Total Revenue to Gen $3,300 $0 $14,850 $5,700 $24,850 Net Income to Gen $1,760 $0 $0 $1,000 (1) -$1,500 $0 $260 425 425 425 0 0 1275 $12,750 $12,750 $38,250 MW $0 Gen Redisp. $0 FGR Price $12,750 Tot FG Cong. Cong. Cost $20 670 $13,400 $1,100 $13,400 Load (MW) Total Cost to Load (1) Minimum generation for generator 4 is 100MW. December 15-16, 2004 27 Total Allocating congestion costs due to stability constraint Allocation of congestion costs under flow-based and nodal approaches in the case of optimum dispatch with thermal limit on line 54 (= 240MW) and with flowgate limit (= 670MW) Flow-based Approach Nodal Approach Line Flow FGR 12 76.60 $0.00 $0.00 $1.28 $97.78 23 -348.40 $0.00 $0.00 $1.28 -$444.77 * 278.40 $0.00 $0.00 $5.00 $1,392.02 240.00 $21.70 $5,208.51 $15.00 $3,600.00 * 137.55 $0.00 $0.00 $2.45 $336.57 * 254.04 $0.00 $0.00 $17.45 $4,432.23 670.00 $6.28 $4,205.32 $0.00 $0.00 43 54 41 51 FG Total Cong. CostLMPj-LMP Cong. Cost $9,413.83 $9,413.83 Significant differences exist in allocating the congestion costs. December 15-16, 2004 28 Total Production Cost $27,000 Total Generation Cost $26,500 $26,000 $25,500 $25,000 $24,500 $24,000 $23,500 $23,000 650 700 750 800 850 Flowgate (M W) No limit December 15-16, 2004 Limit on 54 Limit on 51 29 Limit on 12 900 Total Congestion Cost $16,000 $14,000 Congestion Cost $12,000 $10,000 $8,000 $6,000 $4,000 $2,000 $0 650 700 Nolimit December 15-16, 2004 750 800 Flowgate (M W) Limit on 54 Limit on 51 30 850 Limit on12 900 Total Dispatch Cost $40,000 $38,000 Total Dispatch Cost $36,000 $34,000 $32,000 $30,000 $28,000 $26,000 $24,000 $22,000 650 700 750 800 850 Flowgate Limit (MW) Nolimit December 15-16, 2004 Limit on 54 31 Limit on 51 Limit on 12 900 Changes in LMPs with Different Transmission Thermal Limits Limit on 54 No limit $35 LMP LMP $35 $25 $15 $5 Node 1 2 3 4 $25 $15 $5 Node 1 5 Limit on 51 LMP LMP 4 5 4 5 $35 $25 $15 2 3 4 $25 $15 $5 Node 1 5 Flowgate Limit 670MW December 15-16, 2004 3 Limit on 12 $35 $5 Node 1 2 32 2 3