WFC3 TIPS John W. MacKenty TIPS Presentation 29 November 2007 1 What a Difference a Year Makes! • This time last year: – SOFA was delivered to GSFC after filter ghosts and chips fixed • New IR Grisms were just installed – Circuit boards were all removed and retested • Still troubleshooting a MEB1 failure to start issue – IR2 (substrate on) was still the only complete IR detector • IR1 was just completing bypass surgery for a failed internal JFET – TV2 was scheduled to start 3/28/07 (Launch May 08) – Most of the new IR Detector Lot 4 wafers at Teledyne had failed • One part on a backup wafer (FPA150) would become IR3 – Randy & I were trying to “sell” a Lot 4C IR detector run Æ FPA165 • We did not see coming: – – – – Electrical short in UVIS1 Damage to TECs in UVIS1 and UVIS2 Thermal control problems with IR 6-stage TEC Failure of 3 (of 4) Tungsten bulbs in the internal calibration system John W. MacKenty TIPS Presentation 29 November 2007 2 WFC3 Status Today • • • • • The WFC3 team persevered through the successful 127 day T/V-2 campaign (with three chamber breaks) that verified most of the instrument’s performance. Completed first round of EMI/EMC testing (only one minor issue) Complete fit checks into HFMS and Crew Fam IR4 (Flight) and IR3 (Spare) Detectors at GSFC [IR4 about to be installed!] UVIS1’ (Flight) detector – – – – – • TEC replaced Flex leads coated with insulator after multiple metal particles found Glint discovered in TV2 fix within installed of baffle inside UVIS1’ package UVIS1’ partway through thermal cycling (and was vibed yesterday at Ball) Schedule to arrive at GSFC next week for immediate installation The replacement Tungsten Lamp assemblies for the Calibration Sub-System are assembled and aligned for drop-in replacement at GSFC. – Presently in test at Ball • • TV3 is schedule for 42 days starting early February 2008 Final WFC3 Delivery to HST I&T is holding at 3/30/08. John W. MacKenty TIPS Presentation 29 November 2007 3 WFC3 Schedule 8/08 Shuttle Launch 3/24 – 3/25/07 UVIS2 Detector Installation 10/24/05 – 4/5/07 4/5/07 – 8/12/07 Instrument Integration Pre-IR Detector Instrument Level Testing (Includes T/V test-2) 8/29/07– 9/17/07 T/V– 2B IR FPA Temp & Throughput Investigation 9/20/07– 10/13/07 T/V– 2D IR FPA Temp Control Verification 5/23/06 – 5/16/07 10/15/07 Build Flight IR1 Detector Assy 10/28 – 12/6/07 Delivery to HST I&T 10/1/06 – 8/27/07 Build Flight IR3 Det. Assembly 12/3/07 10/1/06 – 11/07 Prime and Spare Detector Designation Build Flight IR4 Det. Assembly 11/27 – 12/15/07 Flight detector installation(s) and final instrument closeout 3/2/07 – 12/07 UVIS1 Detector Reassembly and Test 4/1/07 – 2/29/08 Build Flight UVIS3 Det. Assembly John W. MacKenty Cal Subsystem & LVPS Rework 12/26 – 1/4/08 = NEW Acoustic -2 1/4 – 1/25/08 EMI / EMC -2 1/30/08 – 03/24/08 T/V test -3 NET 3/3/08 – 3/14/08 UVIS3 Installation? TIPS Presentation 29 November 2007 = CRITICAL PATH ITEM 12/21/07 – 3/27/08 T/V test -3 (Dedicated SES chamber time) 3/30/08 Final Delivery to HST I&T 4 WFC3 in SES (prior to installation of thermal shrouds) John W. MacKenty TIPS Presentation 29 November 2007 5 TV2 Summary • Statistics – 127 days in SES Chamber with 93 days of 24/7 operations – Over 15,000 images from >350 SMS runs – 25 STScI scientists and data analysts supported this effort • Validated many issues from prior testing – – – – – – – – Electronics and detector heatpipes worked well Detector crosstalk fixed in both channels UVIS optical filter ghosts resolved and SOFA working well Internal flat field illumination uniformity much improved IR grisms properly aligned (and IR backgrounds correct) Detector alignment transfers worked very well CCD charge injection working properly Line-of-sight stability looks much better (but still 2x specification) John W. MacKenty TIPS Presentation 29 November 2007 6 TV2 Issues • IR FPA temperature control – Spacecraft voltage variations due to orbital cycling produce FPA temperature fluctuations – detector has non-linear dark – Was ~1 degC in TV1; Initial fix for TV2 resulted in 1.7 degC – Led to decision to perform TV2-B,C,D with LVPS board mods – Significant coupling issues discovered and resolved – Current performance of 0.15 degC demonstrated (expect to improve) • Calibration Subsystem: – Tungsten lamps 2 & 4 failed early in TV2 (lamp3 declining by end) • New bulbs from alternate vendor procured – in test and looking good – D2 lamp turn-on delays (within tolerable range) • Significant glint discovered in UVIS detector package – Repaired in UVIS1 • IR throughput degradation/variation – Now believed to be an issue with ground calibration equipment!! John W. MacKenty TIPS Presentation 29 November 2007 7 UVIS Glint • Large area effected with up to 20% of energy into a 10,000 pixel glint feature • Present by design in both UVIS1&2 • Cause of flat field “flare” feature • Fixed by addition of mask behind outer window (UVIS vacuum enclosure) • UVIS2 (deep spare) not fixed John W. MacKenty TIPS Presentation 29 November 2007 8 Image Stability: Hot Case orbital slew orbital cycling orbital cycling This is data on the more demanding hot case (cold case behaves better). John W. MacKenty TIPS Presentation 29 November 2007 9 Image Stability (cont.) CEI Spec: UVIS <10mas, IR <20mas in 200 minutes (~2 orbits). Well within spec during 3 hours of stable orbital cycling. John W. MacKenty TIPS Presentation 29 November 2007 10 Image Stability (cont.) Spec exceeded for steepest rate of change after thermal simulation of a worst case pointing slew: 15-20 mas vs. spec of 10mas/200min in UVIS; slightly greater than spec of 20mas/200 min for IR. Still examining data, realism of slew (might have been too severe); but if no obvious “easily fixed cause” emerges, likely to have to waive this violation. Affects dithering precision, not single-exposure image quality. John W. MacKenty TIPS Presentation 29 November 2007 11 IR Thermal Background • IR thermal background results vs. filter modeled remarkably accurately by M. Robberto. • Extrapolation to in-flight performance with FPA165 (higher QE, longer wavelength cutoff) is well within spec and within the assumptions in our sensitivity calculations. John W. MacKenty TIPS Presentation 29 November 2007 12 SOFA Repeatability • • • Used tilt of G280 spectrum to measure repeatability of wheel #1 position over 26 moves, using 2 different homing methods Very repeatable: scatter of spectrum tilt angles corresponds to 0.01 wheel steps Negligible effect on spectral tilt of grism mode or on external flat field performance John W. MacKenty TIPS Presentation 29 November 2007 13 TV2 Analysis • TV2 data continues to be analyzed – ISR 2007-26: WFC3 TV2 Testing: UVIS-2 Dark Frames and Rates -- A. R. Martel 02 Nov 2007 – ISR 2007-25: WFC3 TV2 Testing: IR Channel Non-linearity Correction and Unstable Pixel Masking -- B. Hilbert 01 Nov 2007 – ISR 2007-24: WFC3 TV2 Testing: UVIS Filtered Throughput -- T. Brown 26 Oct 2007 – ISR 2007-23: WFC3 TV2 Testing: IR Channel Throughput -- T. Brown 23 Oct 2007 – ISR 2007-22: WFC3 TV2 Testing: UVIS-2 Amp B Anomaly -- S. Baggett, A. Waczynski 19 Oct 2007 – ISR 2007-21: WFC3 TV2 Testing: UVIS Channel Glint -- T. Brown 17 Oct 2007 – ISR 2007-20: WFC3 TV2 Testing: System Throughput on the UVIS Build 2 Detector -- T. Brown 11 Oct 2007 – ISR 2007-19: WFC3 TV2 Testing: UVIS-2 Gain Results -- S. Baggett 14 Sep 2007 – ISR 2007-18: WFC3 TV2 Testing: Image Stability -- T. Brown 28 Aug 2007 – ISR 2007-17: WFC3 TV2 Testing: UVIS Shutter Stability and Accuracy -- B. Hilbert 16 Aug 2007 – ISR 2007-16: WFC3 TV2 Testing: IR Channel Ghosts and Baffle Scatter -- T. Brown 15 Aug 2007 John W. MacKenty TIPS Presentation 29 November 2007 14 UVIS Detectors John W. MacKenty TIPS Presentation 29 November 2007 15 UVIS Throughput (cont.) John W. MacKenty TIPS Presentation 29 November 2007 16 UVIS Detector Status • UVIS1 (Prime flight detector) – – – – Used in TV#1 and has best science performance Developed short on AmpB due to metal particle on flex lead Re-assembled but TEC performance declined during re-testing at Ball TEC removed – column was cracked probably due to thermal stress • Continuing uncertainty between over-testing or anneal ramp methodology • Modification to MEB boards and operating procedures in instrument to soften ramp – TEC replaced, reassembled, disassembled to fix glint, found more particles – Proceeded to protect flex leads with “paint on” covering • UVIS2 (Spare flight detector) – Acceptance testing deferred in 2004 for cost reasons – TEC lost 10 degrees of cooling capability after acceptance testing – Used for TV2 but serious lien against TEC (probably cracked) • UVIS3 (Backup flight detector – new start) – Improved TEC and Flex Leads – Delivered CCDs to Ball with science performance between UVIS1 and UVIS2 – Current estimate is delivery of acceptance tested assembly to GSFC March 08 John W. MacKenty TIPS Presentation 29 November 2007 17 IR Detector Status • • • • IR2 (FPA 64) was used for TV1. This substrate ON detector has proton induced glow performance concern but is otherwise healthy. IR1 (FPA129) is now in WFC3 for TV2. This device has 10-12% hot pixels but good QE and could be flown. IR3 (FPA150) is assembled and has passed acceptance testing at Ball Aerospace. [Shown as right during assembly.] – FLIGHT SPARE IR4 (FPA165) is assembled and passed acceptance testing at Ball. The detector assembly will be installed into WFC3 in early December. –FLIGHT DETECTOR John W. MacKenty TIPS Presentation 29 November 2007 18 IR Detector QE John W. MacKenty TIPS Presentation 29 November 2007 19 IR Detector Dark Current John W. MacKenty TIPS Presentation 29 November 2007 20 Closing Remarks • CP is out next week – WFC3 Instrument Handbook is done – Kudo’s to Howard Bond, Jessica Kim Quijano and the entire team! • Onwards to TV3! John W. MacKenty TIPS Presentation 29 November 2007 21