TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 SMOV4 Update: ACS Status David Golimowski (TIPS/JIM 16 Jul 2009) Outline • Summaries of Functional Test and Optimization Campaign • WFC and SBC Performance and Characteristics • Implications of SI C&DH Anomaly (HSTAR 11880) • Assessment of Day 174 Suspend (HSTAR 11895) • SMOV Status and Forward Plan TIPS/JIM 16 Jul 2009 1 ACS-R Functional Test and Optimization Campaign - 1 • ACS-R hardware successfully installed on 16 May 2009 during EVA-3 • WFC and SBC passed Aliveness and Functional Tests; HRC not recovered • Day 146 (26 May): WFC 12-hour anneal performed; pre- and post-anneal dark frames show little change indicating that 18 month hiatus at ambient -10° C was sufficient to anneal nearly all temporary hot pixels. • Day 148 (28 May): WFC Optimization Campaign commenced • Day 150 (30 May): SBC UV contamination check; BEA exit deemed safe • Optimization Campaign contained general WFC Performance Summary and multiple exploratory tests involving changes in bias and clock voltages and data transmission timing. Tests showed that all pre-failure settings remained valid for CEB-R operations and that no changes in default settings were warranted. TIPS/JIM 16 Jul 2009 2 WFC Bias and Dark Frames Superbias from Prop 11369 (SMOV CCD Functional Test) TIPS/JIM 16 Jul 2009 Superdark from Prop 11369 (SMOV CCD Functional Test) 3 WFC Linearity and Full Well Photon Transfer Test from Iteration 1 of O.C. (Amplifier D, Dual-Slope Integrator) TIPS/JIM 16 Jul 2009 4 WFC Performance Summary January 2007 (measured) May 2009* (projected) Problematic* Read noise (e-; gain = 2) C&S: 5.5 DSI: 4.0 10 DSI: 3.9-4.7 C&S: 4.4-5.7 Dark current (e-/pix/hr) 10.7 15 100 20-25 Hot pixels (%) 0.68 1.1 1.5 1.1 Full well depth (e-) 84,000 84,000 40,000 ~80,000 Non-linearity (%) < 0.1 < 0.1 0.5 < 0.2 Metric Post SM4 (measured) (exp time > 2 s) CTE (1620 e-) 0.999949 0.999921 0.9999 0.99989 Cross-talk 4x10-5 4x10-5 4x10-4 1x10-4 Bias shift** (%) 0.02 < 0.1 < 0.2 0.02-0.30 (before correction) * Projected and problematic values from Gilliland et al. 2008 (TIR ACS 2008-04) . **Residual bias shift after analytical correction of signal-dependent effect. TIPS/JIM 16 Jul 2009 5 ACS-R Functional Test and Optimization Campaign - 2 • Optimization Campaign truncated on 3 June 2009 after Iteration 2 Performance matched or exceeded projections and expectations VOD offsets of < -1 V produce anomalous behavior in amps C and D that mimic charge-injection but remain unexplained by Tiger Team HSTMO and Project elect to proceed with WFC default configuration and continue “off-line” investigation of VOD anomaly • Dual-Slope Integrator selected as default mode of ASIC pixel sampling • Low-frequency bias variations and signal dependent “bias shift” can be effectively removed during post-image processing • Bias striping pattern varies among quadrants and between frames; caused by 1/f noise (1 mHz to 1 Hz) generated with ASIC during setting of bias voltage offset. Striping appears constant across rows of CCD, so may be removable. TIPS/JIM 16 Jul 2009 6 VOD (Reset Drain) Anomaly VDD: +27V, VLG: -3V (defaults) Bias VOD: +14V (default is +15V) Illumination 1 Illumination 2 TIPS/JIM 16 Jul 2009 7 SBC UV Contamination F125LP Bright Earth photopolymerizes contaminants onto pickoff mirror Pre SM4 (short) Post SM4 (short & long) F150LP Delta Mag (Pre-Post SM4) F115LP = F125LP = F140LP = F150LP = F165LP = -0.034 +/- 0.017 -0.014 +/- 0.013 -0.019 +/- 0.015 0.002 +/- 0.015 0.008 +/- 0.015 TIPS/JIM 16 Jul 2009 8 SIC&DH Anomaly (HSTAR 11880) • HST safed on Day 166 (15 June) after failure of SIC&DH toggle test; all SI commanding lost; SIs remain in state at time of SIC&DH failure; SMS continues to execute; HST continues to slew • Tiger Teams assembled to investigate: Dangers to SI detectors (MAMA, CCD, IR) due to overexposure during Bright Earth crossings, SAA crossings, and slews across bright stars Potential polymerization of contaminants on optics in UV channels • Implications for ACS: No danger to CCDs; WFC science can continue unimpeded SBC MAMA vulnerable to catastrophic damage during BE crossings Impact of SAA on MAMA unknown because HV normally turned off ACS optics exposed to 100s of hrs of BE crossings with no ill-effects • SBC concerns resolved by 486 FSW revision that automatically shuts down MAMA HV after future (expected) SIC&DH anomalies TIPS/JIM 16 Jul 2009 9 Day 174 Suspend (HSTAR 11895) • ACS suspended on 23 June as result of 2 Error Status Buffer messages: ACS 955: CEB Command Max Retries Exceeded ACS 1002: NED ASIC Not Alive • Status at time of suspend: No observations executing or lost All monitored currents and voltages normal ASIC & FPGA properly initialized & functioning after SMS 173 reboot Error occurred during NED collection cycle (CS to ASIC comm broken) HST orbital position far from SAA • Tiger Team formed on 24 June and identified 2 possible causes: ASIC Status Line raised (informs FPGA of bit anomaly or comm error) FPGA reset in response to SEU of power regulator TIPS/JIM 16 Jul 2009 10 FPGA/ASIC Relationship TIPS/JIM 16 Jul 2009 11 Possible Causes of Day 174 Suspend • ASIC Status Line scenario not favored because it produces only ACS 955 ESB message and does not explain “ASIC Not Alive” failure • Radiation test reports now available show ambient heavy-ion flux sufficient to upset power regulator once every ~100 days SEU causes small voltage drop that triggers Power On Clear circuit FPGA and ASIC both reset; only FPGA reboots Scenario explains both ACS 955 and ACS 1002 ESB messages • Event will happen again, but signature of anomaly will depend on timing of SEU with phase of FPGA/ASIC/telemetry duty cycle • Tiger Team investigating FSW changes to inhibit suspend action in this particular instance of ACS 955 error message TIPS/JIM 16 Jul 2009 12 Status and Forward Plan • Both SBC and WFC have had successful and spectacular “first light” external observations. (No pretty pictures -- sorry!) • WFC focus is -2.5 µm off nominal. Other SIs will be made confocal with WFC and secondary mirror will be moved next week. • All SBC and WFC SMOV programs have been executed and data analysis is underway. Several SMOV programs (all HRC; WFC half-speed; coarse & fine corrector alignment) were unnecessary and dropped. • VOD anomaly and its possible beneficial use to mitigate CTE through chargeinjection will being investigated • Changes to FSW being considered to prevent suspend after SEU of CEB-R (expected every 100 days) • ACS cleared for GO Science!!! TIPS/JIM 16 Jul 2009 13 TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 TIPS COS Status: post-servicing --- Tony Keyes --16 July 2009 COS and NCS Pressure 5E-06 !COS (LVACPRES) !NCS (METPSPR) Pressure (Torr) 4E-06 SIC&DH Anomaly 3E-06 FUV HV Turn-on Complete 2E-06 1E-06 0E+00 5/22 5/26 5/30 6/3 6/7 6/11 6/15 6/19 2009 (UT) 6/23 6/27 7/1 7/5 7/9 7/13 COS NUV Temperature 30 NUV resume NUV ops / FUV turn-on NUV initial turn-on 25 FUV only Temperature (C) 20 15 COS suspend 10 5 !Charge Amps (LMCHAMPT) !MCE (LMMCETMP) !Electronics Box (LNELBOXT) !MAMA Tube (LNTUBET) !Front Bulkhead (LNUVFBT) SIC&DH Anomaly 0 -5 -10 5/22 5/26 5/30 6/3 6/7 6/11 6/15 6/19 2009 (UT) 6/23 6/27 7/1 7/5 7/9 7/13 COS MAMA Event Counter (LMEVENTS) 400 350 Events (counts) 300 250 200 150 100 50 0 5/22 5/26 5/30 6/3 6/7 6/11 6/15 6/19 2009 (UT) 6/23 6/27 7/1 7/5 7/9 7/13 COS Highlights NUV / FUV HV Turn-on complete NUV/FUV Functional Tests complete – – Darks: NUV ~70 counts/sec (10x less than STIS/NUV); FUV ~1 count/resel/3-hours OSM drift: few measures to date, but definitely present; TAGFLASH can remove COS-to-FGS Alignment established COS NUV (imaging) “first light” on 11 June – – F2V astrometric target in NGC-188 Counts ~30% higher than predicted > > within errors on model simulation NUV sensitivity quicklook observations upcoming COS Highlights (continued) COS NUV Optical Alignment established – Final verification visits in progress COS NUV (spectroscopy) “first light” on 14 July – FUV Sensitivity Quicklook > > Range: TV03 estimates +20% / -10% (nominal) Some system throughput to ~1000 Angstroms COS Upcoming Events FUV Optical Alignment (COS26 - 11484) – Mon-Sun 20-26 July: NUV Sensitivity Quicklook (COS34 -11479) – Tues 21 June NUV Internal Flat Fields (COS 22 - 11478) – First 18 (of 72) : Tues-Fri 21-25 July NUV Internal/External Wavecal (COS14 – 11474) Fri/Sat 24-25 July NUV Focus and Alignment Verification (COS18 – 11469) – – Completes 20 July COS SMOV4 NUV Sequence HST release COS-01 Recovery from SAFE COS-06 11467 NUV Internal Functionality & Operation Internal pressure <20 micro-Torr MAMA LV on COS-02 11353 Onboard Memory Check COS-03 11354 Science Data Buffer Check COS-04 11355 NUV Initial HV Turn-on/Ramp-up COS-07 11355 v5 NUV Fold Test COS-05 11466 NUV Dark Measure 24h data 24h data SCI REF COS-08 11468 OTA to FGS Alignment (NUV) Wavelength Ranges OK SIAF update available Uplink 24h data Alignment Not OK COS-10 11496 Internal NUV Wavelength Meas & Grating Eff. Vis 1, 3 – lamp 2 COS-09 11469 NUV Optical Alignment /Focus visit 1-6 24h data COS-17 11477 NUV Ext. Spectr. Perf. Part 2 Enable Wavecaldependent NUV Calibration and Science COS-15 11475 Wavelength Internal NUV Ranges Wavelength Not OK Verify 24h data REF Require Wavelength Scale Update COS-16 11476 NUV Ext. Spectr. Perf. Part 1 Internal pressure <10 micro-Torr BEA Complete ERO FUV SMOV sequence 24h data Uplink COS-19 11479 v2-n NUV Spectr. Sensitivity REF COS-20 11480 NUV Structural & Thermal Stability COS-21 11481 NUV High S/N Verification REF COS-14 11474 NUV Int/External Wavelength Scales Uplink IHB 24h data COS-09 11469 NUV Optical Alignment vis 7-12 External Observations 24h data COS-19 11479 v1 NUV Spectr. Sensitivity Quick Uplink 24h data COS-10 11470 Internal NUV Wavelength Meas May require wait 9 April 2009 SIAF update start Alignment OK Uplink Uplink COS-11 11471 NUV Imaging Acq Verify REF COS-12 11472 NUV Dispersed Acq Verify Uplink REF COS-18 11478 NUV Flat Fields COS-13 11473 NUV Imaging Performance Do NOT Require Wavelength Scale Update COS SMOV4 FUV Sequence Outgassing Concern? XDL at OPER Internal Pressure COS-01 HST COS-02 11353 release COS-03 11354 <100 microTorr NUV SMOV sequence COS-08 11468 NUV Optical Alignment /Focus Uplink SIAF update start May require wait COS-31 11489 FUV Ext. Spectr. Perf. Part 1 Wavelength Ranges OK REF COS-27 11496 Internal FUV Wavelength Meas Vis 2 – lamp 2 SIAF update available COS-30 11488 Wavelength Ranges Internal NUV Not OK Wavelength Verify 24h data Uplink Uplink 24h data COS-26 11484 FUV Optical Alignment /Focus visit 1-4 COS-27 11485 Internal FUV Wavelength Meas – Vis 1 COS-26 11484 FUV Optical Alignment /Focus Verif. – visit 5-6 Alignment OK COS-36 11494 FUV High S/N Verification Require Wavelength Scale Update 24h data COS-28 11486 FUV Dispersed Acq Verify Does NOT Require Wavelength Scale Update Enable FUV ERO No wavecal COS-32 11490 FUV Ext. Spectr. Perf. Part 2 Enable Wavecaldependent FUV Calibration and Science REF COS-29 11487 FUV Int/External Wavelength Scales 24h data Uplink External Observations COS-23 11356 FUV Initial HV Turn-on/Ramp-up Pressure Gauge OFF COS-25 11483 FUV Internal Functionality & Operation COS-34 11492 v1 FUV Spectr. Sensitivity - Quick 24h data Internal Pressure <10 microTorr BEA Complete uplink 24h data COS-09 11469 NUV Optical Alignment /Focus COS-22 FUV Detector Door Open COS-24 11482 FUV Dark Measure 24h data 24h data COS-33 11491 FUV Flat Fields REF COS-34 11492 v2-4 FUV Spectr. Sensitivity REF COS-35 11493 FUV Structural & Thermal Stability 24h data Rapid data turnaround required ERO Required to enable ERO SCI Required to enable science REF Analysis produces reference file IHB Results reported in IHB 9 April 2009 COS SMOV Timeline • • • • • • May 11: SM4 Launch May 16: COS installation (EVA3) May 22 – Jul 27: Beginning COS SMOV engineering and alignment activities – – – Engineering Check-out and Detector Turn-on (NUV: May 23 – June 4, FUV: June 5-15) Fast turnaround of turn-on visits Initial Detector verifications (NUV: June 4-8, FUV: June 16-20) Optical Alignments (June 11- Jul 27) Fast turnaround of each visit – – – – – – – – TA Verification (FUV: Aug 10, NUV: Aug 22-27) Imaging Verification (Aug 10) Wavelength Calibration (FUV: Jul 27 - Aug 9, NUV: Jul 22 – Aug 6) Flux Calibration (FUV: Aug 10-13, NUV: Aug 18-20 Internal and External Flat Fields (NUV: Jul 22 - Aug 16, FUV: Aug 24-25) High S/N Verification (FUV: Aug 30-31, NUV: Aug 28-29) Spectroscopic Performance (FUV: Aug 16-25, NUV: Aug 17-29) Thermal Stability (FUV: Sep 15, NUV: Aug 30 – Sep 5) ~Aug 30: COS science observations enabled Aug 3-9: COS EROs enabled Jul 22 – Sep 15: General Science Calibration Verification TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 STIS Status TIPS July 16, 2009 STIS Status • STIS MIE anomaly – What is known • STIS CCD status before the anomaly • STIS MAMA SMOV status STIS MIE Anomaly • • STIS currently suspended Original suspend (day 187) : Main STIS CS computer unable to get timecode update from MIE (MAMA Interface Electronics) that was needed to populate the header of a CCD exposure. – Originally suspected that single event upset had hung up the MIE 486. • 2nd suspend (day 190): Suspended while attempting to copy MIE memory to CS. Done before full reset in attempt to preserve MIE memory – Theorized that problem with MIE dump was caused by lack of full reset, and hoped a full reset would clear the problem. – About 1/2 of MIE memory was successfully copied. • 3rd suspend (191): Did full reset and successfully recovered STIS to operate, but suspended while attempting to copy MIE memory to CS. – MIE copy to CS seems to have succeeded, but still suspended – Recovery included successful queries of MIE for time code update (I.e., the original problem from day 187 did not recur). – Observed events suggest transient failure on MIE FIFO Flags interface between CS and MIE? STIS MIE Anomaly - cont • What we know: • • The three anomalies occurred during three different circumstances and have three different and - in some aspects - inconsistent signatures Observed events suggest transient failure on MIE FIFO Flags interface between CS and MIE • Investigation is continuing • Perhaps MIE dump problem is separate from original time code update problem? • STIS still suspended • Hope to allow resumption of CCD operations soon, while analysis continues. • • • See if original anomaly reoccurs. CCD observations could, in principle work around MIE problems Since anomalies are not yet understood, implications for MAMA observations are not yet known STIS CCD Read Noise • • STIS CCD read noise slightly increased from ~ 5.4 e- in 2004 to ~ 5.7 e- now Side 2 read-noise includes ~ 1 DN of semi-coherent 17 kHz pattern noise – This pattern noise appears to be unchanged after SM4 STIS CCD Dark Current • • • • CCD housing temperature (OCCDHT) surrogate for CCD chip T For comparison these plots scale darks to housing temperature of 18 C Dark rate increases by 7%/degree of housing temperature 2009 aft-shroud hotter than 2004 – – • When MAMAs on, OCCDHT 22-25 C With MAMAs off, OCCDHT 16-18 C RN between 0.009 and 0.013 e-/s, fluctuating with temperature TDS & CTE effects • • Standard monitor target AGK+81o266 (*’s) shows large scatter at low flux levels (right panel), even in 2004 - correlates with T Need to separate T dependence of CTE before deriving final throughput estimates • CTE extrapolated to zero background as a function of flux level • 2009 points are at colder T than older data – Expect reduced CTE losses at lower T MAMA SMOV Status • FUV MAMA – FUV MAMA HV ramped to full values – Fold test & flat look as expected – Dark current perhaps lower than expected • NUV MAMA – Initial steps of NUV MAMA HV recovery completed – Have not yet ramped NUV HV to level where tube generates real counts. • • Still need to do initial internal lamp exposures and external exposures with both MAMAs Once MAMAs cleared for operations, most SMOV activities for either or both could be completed in a week if time available. TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 WFC3 SMOV Report for TIPS 16 July 2009 John MacKenty This presentation contains material that is embargoed until after the SM4 ERO press conference. Images/spectra of external (astronomical) objects may not be altered, distributed, reproduced, published, displayed, or used in any other way without the consent of the STScI Director or the HST Project. WFC3 Activities • 11451 IR Zero Points – P330E and GD153 standard stars (Visits 11,21) – Series of short exposures of • White Dwarf standard star GD153 (hot source) • Solar analog P330E (cool source) • Both about V = 13.0 – All IR Filters exposed in RAPID plus narrow filters in SPARS10 – IRSUB128 used • Target was close (2.5”) to corner but OK – Two sets of exposures obtained • • – Preliminary conclusion: IR photometry is 10-15% better than expected 11452 UVIS Flat Field Uniformity – very nice dataset on Omega Cen 11427 UVIS Shutter Test – data being analyzed PRELIMINARY IR Throughput WFC3 SMOV Progress • • WFC3 has 43 distinct SMOV Activities following SM4 Three phases: – Engineering • Complete except for TEC setpoint verification ongoing • Instrument performance nominal – Optical Alignment • Both channel alignment/focus activities complete • Verification follows OTA move on Day 201 – Science performance and calibration verification • This week completing items for ERO and “EASY” science enable • Most WFC3 ERO’s on 201 and 208 SMSs (208 also first science!) • Except to complete SMOV in mid-late August Engineering Tests • • • • • • • • • Activation – repeat of FT and TEC cooldowns (11 June) Memory and Science Data Buffer Tests UVIS and IR Detector Functional Tests – Demonstrated expected readnoise and gain in both channels Channel Select Mechanism Test (aka First Light) – Beam is clear of obstructions and CSM repositions correctly UVIS SOFA and IR FSM tests – SOFA has shown 1 step offset in Wheel 10 – minor issue UVIS and IR Tungsten primary and spare lamp tests UVIS Contamination monitor UVIS Anneal UVIS and IR TEC performance – Still working thermal models to verify WFC3 can hold detector operating temperatures throughout Cycle 17: TECFIRE DB is close Optical Alignment • • • • • • UVIS – Initial and Fine Alignment activities completed – Four iterations of focus and tip/tilt adjustment – Lost (and repeated) on visit due to Guide Stars – UVIS focus mechanism shows some “wobble” – Final tip/tilt run has best image (minimize coma) in corner of box IR – Initial and Fine Alignment activities completed ( 5 iterations) – Best image quality and EE achieved WFC3 chief ray angle was off by about 1 arc min (expected 10-15”) Both focus mechanisms near center of range Intentional defocus of 2.5 microns to be confocal with ACS/WFC – Move to nominal focus on Day 201 with OTA move of 3 microns Detailed image characterization (EE and PSF Wings) on 208 SMS UVIS Science Performance and Calibration Verification • • • • • • • • Bias, Darks, CTE – nominal, early results show ACS trend of CTE Hot pixel trending unclear – first anneal proceeded by SI C&DH INT flats looking good – droplets unchanged since TV3 FGS SIAF update in work SAA passage test OK “bowtie” (i.e. QEH mitigation working well <0.5% residual) Upcoming events: – plate scale, L-flat verification – shutter timing and jitter tests – Pointing stability and D2 lamp tests Throughput results look good PRELIMINARY UVIS Throughput IR Science Performance and Calibration Verification • • • • • Darks – Discovered light leak when HST pointed at bright earth – Likely fix is to position CSM in UVIS position (being tested) – Base dark is very good FGS SIAF update in work SAA passage test OK Upcoming events: – plate scale, L-flat verification – Pointing stability – Grism verification Throughput results look good IR Dark as function of pointing PRELIMINARY IR Throughput TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 TIPS/JIM 16 July 2009 Status of focus and pointing during SMOV4 M. Lallo for TEL TIPS/JIM 16 July 2009 SMOV Focus & Plan 1.) Focus of ACS/WF channel determined by TEL Group indicates a defocus equivalent to –2.5 microns of HST Secondary Mirror despace. (Coarser SBC measurements consistent with this). 2.) WFC3 & COS focus and optical alignment activities carried out by Hartig. During this process, they were offset last week by the equivalent of this –2.5 micron amount. This move has left the two new SIs slightly off their best focus but achieves practical confocality with ACS. 3.) A movement of the HST Secondary Mirror of +2.5+0.5 = 3.0 microns will occur this Monday (July 20th) and should leave the three SIsʼ focii ~ +0.5 micron. • Restoration of optimal focus for WFC3 will precede WFC3 PSF specification tests, Early Release Science, and Cycle 17. • WFC3 wishes to maintain focus comfortably within 2 microns • Leaving the OTA focus at +0.5 microns should result in passing through best focus (0) in cycle 17, and not reaching –2 microns until mid-2012 • STIS slit focus should remain within typical ranges seen in the past since STIS was originally optimized with OTA at comparable focus values. TIPS/JIM 16 July 2009 Long-Term Trend of the HST OTA ·Phase retrieval focus results from WF/PC, WFPC2/PC, & ACS/HRC images since HST launch culled together, averaged per visit and put onto same frame (WFPC2/PC focus) ·Secondary mirror moves have been removed to present continuous curve. ·Curve shown is a fit double exponential: -5.04 + 56.26e–t/364.53 + 106.24e–t/2237.2 ·RMS residuals 2.7 microns ·Asymptote of -5 mic TIPS/JIM 16 July 2009 SMOV Pointing & Plan 1.) FGS2: has been aligned (for now) with solution good to ~ 90 mas 1 sigma. • Alignment found ~9” from pre-flight operational values. Not unexpected. • Updates to scale have also been made. • Higher order distortion currently assumed as ground-tested. Will be calibrated later. • Scale and Alignment calibrations have brought the total position error from max of ~22 arcsec to ~ 90 mas. Will change! • FGSs 1 & 3 believed to be remained calibrated with total position errors ~50 mas. 2.) SIs: Calibrating the alignment of the SIs to the FGSs determines their location in V2,V3. Solutions have been worked by TEL & SI teams: • WFC3: UVIS, Preliminary results indicate a shift of ~3”, with small orientation change (<0.1 deg TBD). Not unexpected based on past SIsʼ gravity release, latch uncertainty, and pre-flight model accuracy. IR, Currently being worked. Larger shift expected due to optical adjustment of channel. Updates to Ground Systems database on Aug 3 SMS (215) • COS: Aperture found within 1.8” of pre-flight estimate. Since then aperture has been intentionally moves significantly as optical alignment is performed. Total shift being determined by COS team. Values will be used to update Ground Systems database on Aug 3 SMS (215) • ACS: ACS shift was (–0.55,–0.41) arcsec V2V3. Early 2007 checks gave (–0.32,–0.36). Ground Systems database update planned for ~Aug 10 (SMS 222) • STIS: position determined (+0.233, –0.062). Ground Systems database update TBD. TIPS/JIM July 16, 2009 Agenda: ACS Status (David Golimowski) COS Status (Tony Keyes) STIS Status (Charles Proffitt) WFC3 Status (John MacKenty) HST Focus and Pointing (Matt Lallo) NICMOS Update (Anton Koekemoer) Next TIPS/JIM: August 20, 2009 TIPS 15 July 2009 NICMOS Status Update Anton Koekemoer NICMOS Status Update NCS/NCC restart: Goals: – Avoid a condition where mostiure can migrate into the Circulator Pump and freeze out (causing current limit violations) – Avoid a condition where the TurboAlternator operates near its lowrr thrust bearing speed limit for an extended period of time – Reproduce as closely as possible the conditions of the successful March 2002 cooldown Restart criteria: Temperatures within 275 - 278 K for > 12 hours for: – TurboAlternator inlet – Circulator housing – heat rejection interface274 Temperatures of TA inlet were 274.6 K as of this morning Aiming for a restart sometime early Friday morning NICMOS SMOV plan remains ready to execute NICMOS reprocessing: All pre-NCS data reprocessed, in HLA Next step is to continue post-NCS reprocessing 1 TIPS 15 July 2009 NICMOS Status Update Anton Koekemoer Recent NCS restart attempts With circulator problems: – 2008 Sep 11: Safed on Circulator speed limit 1396 rps after approximately 6 hours of operation. Circulator Housing Temp ~ 94 K. (NCC Only) – 2008 Sep 15: Circulator Housing Temp ~ 169 K. Safed at start-up on Circulator current limit of 130 mA. (NCC only) – 2008 Sep 16 (1): Circulator Current Limit raised to 150 mA. Safed at start-up on Circulator speed limit of 1396 rps. (NCC only) – 2008 Sep 16 (2): Circulator Upper Speed Limit was disabled. Circulator Housing Temp ~ 187.5 K. Safed shortly after start-up (~25 minutes) on Circulator current limit of 150 mA. (NCC only) – 2008 Nov 19: Circulator Housing temp ~ 274 K. Safed at start-up on Circulator current limit of 150 mA. (NCC Only): Successful circulator restart, but TA low speed problems: – 2008 Dec 20: Circulator Housing temp ~280 K. TA Inlet temp ~ 209K. Safed on TA Speed low limit of 1650 rps after 65 hours of compressor operations. (NCC Only) – 2009 Jan 15: Circulator Current Limit raised to 200mA. Circulator Housing Temp ~280K. Safed on TA speed low limit of 1650 rps 2 TIPS 15 July 2009 NICMOS Status Update Anton Koekemoer Other NICMOS News NICMOS Data Handbook V8.0 released (Thatte, Dahlen et al.) NICMOS Instrument Handvook v11.0 released (Viana, Wiklind et al.) Instrument Science Reports: – NICMOS ISR 2009-001 (E. A. Barker & T. Dahlen): "New Bad Pixel Mask Reference Files for the Post-NCS Era" – NICMOS ISR 2009-002 (T. Dahlen et al.): "Temperature Dependent Dark Reference Files: Linear Dark and Amplifier Glow Components" – NICMOS ISR 2009-003 (T. Dahlen, M. Sosey & E. Bergeron): "Updates to Calnica: Using Temperature Dependent Reference Files" – NICMOS ISR 2009-004 (A. C. Viana, R. S. de Jong & A. M. Koekemoer): "NICMOS Photometric Calibration Pipeline" – NICMOS ISR 2009-005 (D. Thatte & T. Dahlen): "NICMOS Temperature Dependent Flat-fields" – NICMOS ISR 2009-006 (N. Pirzkal, R. Bohlin & D. Thatte): "NICMOS Grism Wavelength Calibration" – NICMOS ISR 2009-007 (N. Pirzkal, D. Grumm & E. Bergeron): "CalTempFromBias:Implementation and Testing: – NICMOS ISR 2009-008 (T. Wiklind & D. Thatte): "NICMOS Breathing and Focus Field Variations" 3 TIPS 15 July 2009 NICMOS Status Update Anton Koekemoer Some NICMOS Reprocessed / HLA images 4