TIPS-JIM Meeting 15 February 2007, 10am, Auditorium 1. ACS Status Update Marco Sirianni 2. Update on NICMOS flat-field monitoring Tomas Dahlen 3. Speckle Interferometer for Measurement Babak Saif of Large Optical Structures Next TIPS Meeting will be held on 15 March 2007. ACS Current Status M.Sirianni TIPS Feb 15, 2007 Agenda: • ACS Side-2 failure • SBC reactivation • ACS programs conversion Timeline: January 27, 2007 12:29:12 – ACS began WFC observation, shutter was closed because of a GSACQ failure 12:34:17 – Initial spike in HST structure current 12:34:21 – Begin a 7-second ramp-up of HST structure and load bus current 12:34:28 – ACS PDU-2 fuse blows, ACS telemetry goes to zeros 12:34:33 – ACS suspended because of invalid mode 12:34:37 – NCS pressure sensor detects a pressure burst, initiating HV protection and NCS safing 12:34:38 – ACS safed because of invalid mode 12:34:42 – HST enters Inertial Hold January 29 – ACS Hybrid LEI team given “go” to prepare for Side-1 switch pending ARB recommendation and HST Project approval January 31 – ACS Side-2 ARB Kickoff Meeting. Goal: “Assess the risks of recovering SBC Operations on ACS Side-1” February 5 – ARB Status Briefing #1 to HST Project February 9 - ACS heater zone B switched to Side-1 February 13 – ARB Status Briefing #2 to HST Project February 15 - Flight Readiness Review • HST was recovered from Inertial Hold Safemode DOY 028 – Health and Safety SMS intercept at 028/07:00 – HGA communications restored at 028:07:55 • Safing System is in its Nominal Operational Configuration – Neon Leak Safemode Test was re-enabled 028/17:45 UT • Battery performance is nominal – Battery temperatures are below 0degC since event and converged – System SOC increased 3-5 A-H • TPS reporting nominal pressures • FHSTs and FGSs powered back on – Temperature and performance are as usual • NCC was returned to its operate configuration on DOY 030/01:09 UT • NICMOS was recovered to SAA Operate on 032/15:48 UT – Subsequent filter wheel checkout was nominal – Resumed science observations - NGC 4639 • WFPC2 resumed nominal science operations – Calibration image of Omega Cen, a globular cluster What was observed: • Structure current elevated in two events separated by ~3.5s – First event persisted for ~1.5s and peaked at ~6A – Second event persisted for ~7s, increased gradually, was very noisy, peaked at ~18.6A, and ended abruptly • Main Bus current elevated during both events – First event approximately tracked structure current – Increase during second event peaked at ~37A • • • • PDU-2 current elevated only during second event, increase peaked at ~13.6A ACS input current monitor saturated at 12A during peak of second event and returned to zero when event ended ACS input voltage sagged by ~1.5V during peak of second event and dropped to zero when next sampled after drop in currents NCS/ESM Total Pressure Sensor measured peak pressure of 1.0E-4 torr – Pre-anomaly reading was 1.6E-7 • After the overcurrent event finished, the gas pressure decreased exponentially Possible origin of fault: 1. MEB1- LVPS2 (Side-2) 2. Auxiliary Power Box (APB) 3. Harnesses between LVPS2 and APB Most likely cause of the fault: Exploding/burning tantalium capacitor The ARB is still investigating ways to rule out origin of the fault. So far the primary goal of the ARB has been the assessment whether SBC can be safely operated under side-1. Current Situation 28V Spacecraft Input Power (PDU) 28V Spacecraft Input Power (PDU) ACS Hold Power 1 Powered Units Unpowered Units Previously Failed Unit Heater Power 1 Hold Circuits Side-1 Hold Circuits Side-2 Zone A1 Zone A2 Zone B1 Zone B2 TEC Power 1 Hold Power 2 Heater Power 2 TEC Power 2 TEC CEB Power 1 Anneal Power 1 CEB Power 2 Anneal Htrs Side-1 CEB Anneal Htrs Side-2 Anneal Power SBC Operate Power 1 Mechanism Power 1 MEB Side-1 Mechanisms Side-1 MEB Side-2 Mechanisms Side-2 Calibration Power 1 Operate Power 2 Mechanism Power 2 Calibration Power 2 Calibration Lamp Controller Side-1 powered on for SBC Operation 28V Spacecraft Input Power (PDU) 28V Spacecraft Input Power (PDU) ACS Hold Power 1 Powered Units Unpowered Units Previously Failed Unit Heater Power 1 Hold Circuits Side-1 Hold Circuits Side-2 Zone A1 Zone A2 Zone B1 Zone B2 TEC Power 1 Hold Power 2 Heater Power 2 TEC Power 2 TEC CEB Power 1 Anneal Power 1 CEB Power 2 Anneal Htrs Side-1 CEB Anneal Htrs Side-2 Anneal Power SBC Operate Power 1 Mechanism Power 1 MEB Side-1 Mechanisms Side-1 MEB Side-2 Mechanisms Side-2 Calibration Power 1 Operate Power 2 Mechanism Power 2 Calibration Power 2 Calibration Lamp Controller ACS Side-1 Checkout Programs – Filter Wheel Check (#11094, 2 internal orbits, P.I. = C. Cox) • Commands the SBC filter wheel to each of its positions (in both directions) • Verifies proper motion of wheel through encoder readout • Test has been used previously (e.g., Side-2 switch) – SBC MAMA Recovery (#11048, 4 internal orbits, P.I. = C. Cox) • Initial MAMA turn-on and recovery from anomalous shutdown – SBC was off when ACS was safed, so this is a conservative procedure • Brings the MAMA back to operating condition while watching for possible problems – Signal processing check – Intermediate high voltage ramp-up – Full high voltage ramp-up • Fold analysis provides detailed performance information – Measures charge cloud size on anode and gain • Darks and flats obtained during test • Test has been used previously (e.g., Side-2 switch) – Three Stage Contamination Check/Monitor • Modification of Internal Flatfield Program (#11052, P.I. = R. Bohlin) – D2 flat for all 6 filters (6 orbits) – Subset of filters (2 orbits) each week to monitor until external (NGC6681) observation is obtained (maximum of three weeks) • Modification of SBC Flux Calibration Program (#11056, P.I. = J. Walsh) – Single orbit ASAP on white dwarf standard WD1657+343 (visible now) » F122M, F165LP, PR110L PR130L – Second orbit one week later • UV Contamination Monitor (#11050, P.I. = R. Gilliland) – – – – – Observation of NGC6681 (1 external orbit) NGC6681 becomes visible ~ February 28 Comparison against historical data Exposures in all 6 filters and 2 darks (in occultation period) Repeat up to 4 times Conversion of ACS programs SPD and HST MO have asked INS to review existing cycle15 ACS proposals to identify candidates for a conversion to WFPC2 or NICMOS ~ 120 programs are receiving a double technical review by INS. An internal Feasibility Review panel will asses science and time with guidance from the technical reviews. Most of the PIs will be notified in early March. (PI can/will appeal Review of phase-1s is coordinated by L.Smith. Phase-2s will be processed following the usual procedures (with limited reviews). Backup Slides WFPC2: Omega Cen - f814W (after anomaly event) APB Debris possible in LVPS2 and APB Side 2 Physical Isolation Hold Power presently active LVPS 2 LVPS 1 SBC Fuse Open Fuse OK CEBs Physical Isolation Only new powered state in vicinity of anomaly suspects is MEB1 CS/SES sections; Physical Isolation is provided MEB 1 MEB 2 STIS MEB ACS, Side-2 with panels removed APB is mounted to truss; here shown unsecured and resting in cavity WFC Dark Current WFC Hot Pixels The new the temperature setpoint brought dark Current and hot pixels back to the level after only 18 months on orbit. TIPS-JIM Meeting 15 February 2007, 10am, Auditorium 1. ACS Status Update Marco Sirianni 2. Update on NICMOS flat-field monitoring Tomas Dahlen 3. Speckle Interferometer for Measurement Babak Saif of Large Optical Structures Next TIPS Meeting will be held on 15 March 2007. Update on the NICMOS flat –field monitoring Tomas Dahlen & NICMOS team TIPS, Feb 15, 2007 - Tomas Dahlen 21 Update on the NICMOS flat –field monitoring • The current pipe-line flats are the “Post NCS On-Orbit Flat-fields” from 2002 • Flat-fields have been monitored every Post NCS cycle most frequently in F110W, F160W and F222M at least some flats have been taken in all available filters/grisms Q: have the flat-fields changed over time since 2002 in a way that would require an updated set to be constructed/distributed? To investigate this we create 1) “Single-date-flats” from each observing run 2) “Epoch-flats” from combining flats over time-spans ~1 yr TIPS, Feb 15, 2007 - Tomas Dahlen 22 Update on the NICMOS flat –field monitoring Dates when flats have been taken (2002-2007) Wave-length Red=cam 1 Green=cam 2 Blue=cam 3 TIPS, Feb 15, 2007 - Tomas Dahlen 23 Update on the NICMOS flat –field monitoring Changes in flat-fields: 1) Overall DQE changes 2) Spatial changes in normalized flats TIPS, Feb 15, 2007 - Tomas Dahlen 24 Update on the NICMOS flat –field monitoring Overall DQE changes Figures show change in counts/s (with mean normalized to unity). Total change 2002-2007 is typically a decrease by 1-2% TIPS, Feb 15, 2007 - Tomas Dahlen 25 Update on the NICMOS flat –field monitoring Could the decrease in DQE be due to change in detector temperature? Pre and Post NCS DQE Temperature variations Post NCS T=77K Pre NCS T=62K Decrease in detector temperature would lower DQE: ~2% per ΔK at F110 ~1.5% per ΔK at F160 ~1% per ΔK at F222 Gold points: Mounting cup temperature Rest of points: Temp-from-bias (Bergeron 05) (www.stsci.edu/hst/nicmos/documents/papers/2005_Calibration_Workshop) TIPS, Feb 15, 2007 - Tomas Dahlen 26 Update on the NICMOS flat –field monitoring Overall DQE changes Gray lines: predictions from temperature dependence of DQE CONCLUSION: Direction of DQE change is consistent with decrease in temp, but seems smaller than suggested by the change of temp-from-bias. If mounting cup temp reflects detector temp, then another explanation is needed to explain the decrease in DQE TIPS, Feb 15, 2007 - Tomas Dahlen 27 Update on the NICMOS flat –field monitoring DQE spatial changes As a measurement of spatial changes we define a “spatial ratio”: R(sp)=mean(abs[ratio-image – 1]), where: ratio-image=date-flat/pipe-line flat. Figures show change in R(sp) with time Strongest variations at short wave-lengths F110W: increase from 0.002 to 0.007 F160W: increase from 0.002 to 0.004 TIPS, Feb 15, 2007 - Tomas Dahlen 28 Update on the NICMOS flat –field monitoring Ratio images for cam 1+F110W 200 2 200 3 200 5 200 6 200 4 200 7 R(sp) increases from 0.002 (2002) to 0.008 (2007) (Stretch = +/- 2%) TIPS, Feb 15, 2007 - Tomas Dahlen 29 Update on the NICMOS flat –field monitoring Ratio images for cam 2+F110W 200 2 200 3 200 4 200 5 R(sp) increases from 0.002 (2002) to 0.005 (2005) TIPS, Feb 15, 2007 - Tomas Dahlen 30 Update on the NICMOS flat –field monitoring Ratio images for cam 3+F110W 200 2 200 3 200 5 200 6 200 4 200 7 R(sp) increases from 0.002 (2002) to 0.006 (2007) TIPS, Feb 15, 2007 - Tomas Dahlen 31 Update on the NICMOS flat –field monitoring What is the photometric uncertainty due to the spatial variations? To investigate this, we measure the ratios between the new flats and the pipe-line flats at random positions over the CCD. Cam 1 Cam 2 Cam 3 Figure plots the distribution for F110W. Cam1+F110W (2007) 34% probability of error >0.01 mag 1% probability of error >0.02 mag Cam 2+F1110W (2005) 3% probability of error >0.01 mag 0% probability of error >0.02 mag Cam3+F110W (2007) 14 % probability that error >0.01 mag 2 % probability that error >0.02 mag TIPS, Feb 15, 2007 - Tomas Dahlen 32 Update on the NICMOS flat –field monitoring Combining flats 1) Flats are divided into 5 epoch Example: cam1 + F160W IMAGE S/N t(bias) t(cup) N(image) date cam2_F160W_pipeline 596 cam2_F160W_ep1 836 76.49 77.11 24 ~2002 cam2_F160W_ep2 864 76.33 77.12 24 ~2003 cam2_F160W_ep3 706 76.13 77.19 16 ~2004 cam2_F160W_ep4 449 75.61 77.17 8 ~2005 cam2_F160W_ep5 700 74.99 77.15 14 ~2006 8? 2) Each flat has a ‘use after’ date 3) And an associated temperature 4) Typical S/N = 500-1000 TIPS, Feb 15, 2007 - Tomas Dahlen 33 Update on the NICMOS flat –field monitoring • • • • Conclusions (prel.) DQE has decreased 1-2% since 2002 Spatial changes up to 1% In total: ~0.03 mag photometric error (“worst case” F110W) “Epoch” flats soon ready for delivery TIPS, Feb 15, 2007 - Tomas Dahlen 34 TIPS-JIM Meeting 15 February 2007, 10am, Auditorium 1. ACS Status Update Marco Sirianni 2. Update on NICMOS flat-field monitoring Tomas Dahlen 3. Speckle Interferometer for Measurement Babak Saif of Large Optical Structures Next TIPS Meeting will be held on 15 March 2007. Presentation not available yet; awaiting ITAR clearance Speckle Interferometer for Measurement of Large Optical Structures TIPS February 15, 2007 Babak Saif, Bente Eegholm (SAI) Perry Greenfield, Warren Hack TIPS-JIM Meeting 15 February 2007, 10am, Auditorium 1. ACS Status Update Marco Sirianni 2. Update on NICMOS flat-field monitoring Tomas Dahlen 3. Speckle Interferometer for Measurement Babak Saif of Large Optical Structures Next TIPS Meeting will be held on 15 March 2007.