Telescope and Instrument Performance Summary (TIPS)

advertisement

Telescope and Instrument Performance

Summary (TIPS)

04 April 2002

AGENDA

1.

SMOV3B Update

2.

ACS Status

3.

NCS Status

4.

WFPC2 SMOV3B Results

Carl Biagetti

George Hartig

Larry Petro

Brad Whitmore

Next TIPS Meeting: 18 April 2002

SMOV3B

PROGRESS

As of 03Apr02

SMOV3B

SMOV3b PLAN

TIPS 04Apr02

Carl Biagetti

• MEASURE/MONITOR NEW SPACECRAFT BEHAVIOR

• POINTING, THERMAL, POWER

• RECOMMISSION EXISTING SIs

• STIS, WFPC2

• COMMISSION NEW SIs

• ACS

• Science/EROs in early April

• REVIVE NICMOS

• VIA NCS COOLDOWN

• Science/EROs in late April

Page 2

SMOV3B

TIPS 04Apr02

Carl Biagetti

BEA 9 - 21 March

ACS activated

• Temperature set point & CCD functional

STIS activated

• CCD functional, End-BEA Test, pre-NCS baseline tests, darks and biases

• All nominal

FGS

• Guiding functionality verified and pre-NCS baseline jitter tests

• All nominal

• BEA science

NCS

activated and

NICMOS

cooldown started (18 March)

• Late and slow

• FGS/FHST/STIS high voltages off during NICMOS cooldown

WFPC2

• in PROTECT DECON

Page 3

SMOV3B

TIPS 04Apr02

Carl Biagetti

Post-BEA period though today (14 days)

ACS

Coarse/fine alignment completed 2 April - Nominal

EROs commenced 1 April

STIS

- Recommissioned

SMOV calibrations mostly complete

CCD science enabled and has resumed

MAMA science enabled but usage still restricted due to NICMOS cooldown

WFPC2

- Recommissioned

Cooldown & UV Monitoring began and continues - nominal

GO science enabled and has resumed

All other SMOV complete

NICMOS

Cooling down but 2 –3 weeks behind schedule

NICMOS intentionally safed on 28 March to facilitate cooldown

FGS

- Recommissioned

Guiding and astrometry

Page 4

SMOV3B

TIPS 04Apr02

Carl Biagetti

Deviations, Problems, Issues

NICMOS

Cooldown is slower than expected (several weeks vs. 10-day predict)

End temperature is uncertain

NICMOS SMOV on hold until thermal behavior is stable

ACS

Achievement of fine alignment (2 Apr) occurred earlier than expected

• Allowed acceleration of EROs and GO/GTO science

Some calibrations have been moved earlier due to the small ACS/FGS alignment offsets => 3-week shortening of overall SMOV

ERO

• Visits 1-4 (UGC10214 & NGC4676) – pointing erroneously offset

• Visits 3 & 4 rescheduled for day 9 Apr => 1 week delay

• Visits 1 & 2 corrected with intercept SMS for 7 Apr => no delay

SBC (MAMA high-voltage) is restricted due to longer NICMOS cooldown

ACS/WFC Flat Field Stability (9018)

• TTRB approved the request for extra orbits for CR-splitting Page 5

SMOV3B

TIPS 04Apr02

Carl Biagetti

Deviations, Problems, Issues (cont’d)

STIS

MAMA usage (high-voltage) is restricted due to longer NICMOS cooldown period

• Impacted SMOV End-BEA Test and delayed SMOV Contamination

Monitor

• Has delayed NUV/FUV science

• May be re-enabled in week of April 15

FGS

SMOV Jitter Test failed on 25 March

• Improperly specified target proper motion

Page 6

SMOV3B

TIPS 04Apr02

Carl Biagetti

MAJOR SMOV MILESTONES

UPDATED AS OF 3 APRIL

Release 09 March

NICMOS Cooldown 18 Mar - tbd

STIS Basic GO Science

WFPC2 Cooldown

22 March

22 March

WFPC2 GO Science

ACS ALIGN

ACS EROs

ACS Basic GO/GTO Science (CCD)

26 March

22 March – 2 April

01-09 April

11 April

(delayed with uncertain endpoint)

(MAMA science delayed)

(5 days ahead of plan)

(~ 1 week ahead of plan)

(on schedule)

NICMOS Filter Wheel Test

NICMOS Alignment (PAM adjust)

NICMOS EROs

NICMOS Basic GO Science

SMOV Complete

Mid-late April

TBD late April

TBD May

TBD May

TBD Aug

(~ 3 week delay)

(~ 3 week delay)

(~ 3 week delay)

(~ 3 week delay)

(without fine aperture locations)

(ACS/NIC coronographs enabled)

Page 7

George Hartig

4 April 2002

TIPS Meeting

SMOV Status

• SMOV activities proceeding as expected since last report (TIPS) but proposals are being executed earlier than planned thanks to the already good pointing accuracy

• CCD daily monitoring prog. confirms the CCDs are performing well

– read-out noise remains stable for both cameras

– dark current rate well below nominal values (WFC = 7 e/p/hr, HRC=10 e/px/hr; Sirianni)

– fluctuation of bias level of amplifier WFC-B reported previously is confirmed and found also in ground-based data

• Frequency of cosmic ray hits analyzed and found to agree with predictions based on WFPC2 data (Riess)

• Optical alignment program successfully completed on 3 April

• First annealing procedure executed on 29 March

– Pre and post anneal data used to derive the growth (& decline!) of hot px

• First installment of ERO images obtained, under processing by IDT

Page 1

George Hartig

4 April 2002

TIPS Meeting

T i t l e

Science data buffer check

CCD functional

CCD daily monitoring

I D

9 0 0 3

9 0 0 5

8 9 4 7

ACS CCD hot pixel annealing 9 0 3 1

ACS corrector alignment, fine 9 0 1 4

ACS ERO programme

ACS to FGS alignment

8 9 9 2

9 0 1 1

CCD geometric distorsion

CCD preflash test

ACS CTE test

SMOV contamination plan

9 0 2 8

9 0 3 2

8 9 4 8

9 0 1 0

HRC coronograph repeatibility 9 0 1 6

ACS sensitivity 9 0 2 0

SBC anomalous recovery test 9 0 0 8

WFC flat field stability 9 0 1 8

HRC flat field stability 9 0 1 9

SBC dark current measurement9 0 2 2

SBC PSF measurement 9 0 2 3

SBC flat field uniformity

SBC geometric distorsion

9 0 2 4

9 0 2 7

ACS ramp filter test 9 0 2 6

ACS grism/prism performance 9 0 2 9

HRC coronograph acquisition 9 0 1 2

ACS pointing stability 9 0 1 7

Scattered light in coron. obs. 9 0 2 5

S t a r t l o c a l d a t e t i m e

11.3.

E n d d a t e l o c a l t i m e

P I S u p e r v i s o r

7:12 11.3. 22:38 S T S c I C o x

12.3.

13.3.

5:35 12.3. 16:56 S T S c I C o x

1:50 14.3.

8:26 S T S c I C o x

14.3. 10:01 15.3. 19:58 I D T Clampin

17.3. 20:04 end of SMOV

22.3. 10:40 29.3.

6:23

I D T Clampin

I D T H a r t i g

28.3.

9:47 30.3. 15:45 S T S c I C o x

28.3. 18:11 2.4. 19:57 I D T H a r t i g

31.3. 20:33 7.4. 13:05 I D T F o r d

3.4.

0:13

5.4. 16:09

3.4.

2:45

5.4. 23:31

I D T H a r t i g

I D T H a r t i g

5.4.

1:42 5.4. 15:52

8.4. <---> 15.4.

S098

I D T M e u r e r

S T S c I C o x

8.4. <---> 15.4.

8.4. <--->

8.4. <--->

8.4. <--->

15.4. <--->

15.4.

14.4.

15.4.

21.4.

S098 I D T Clampin

S098

S098

I D T T r a n

I D T Golimowsk

S098 S T S c I De Marchi

S105 I D T Kimble

15.4. <---> 21.4.

15.4. <---> 21.4.

15.4. <---> 21.4.

29.4. <--->

29.4. <--->

29.4. <--->

29.4. <--->

5.5.

5.5.

5.5.

5.5.

S105 I D T Kimble

S105 S T S c I Bohlin

S105 S T S c I Bohlin

S119 I D T Kimble

S119 I D T H a r t i g

6.5. <--->

6.5. <--->

6.5. <--->

2.6. <--->

2.6. <--->

12.5.

12.5.

12.5.

9.6.

9.6.

S119 S T S c I Bohlin

S119 I D T M e u r e r

S126

S126

I D T T s v e t a n o v

I D T T s v e t a n o v

I D T Golimowsk S126

S154

S154

I D T H a r t i g

I D T Golimowsk

Page 2

George Hartig

4 April 2002

TIPS Meeting

On-orbit optical alignment

• First Light obtained on 22 March ‘02

– Both WFC and HRC images noticeably comatic, but well in range of the corrector mechanism adjustability

– Aperture location correct to within ~2-3 arcsec

– Throughput approximately as expected

– Filters with BG-40 blockers (F435W, F475W, F502N, F555W) appear OK

• Coarse alignment (prop 9013) achieved requirements

– 3 iterations of observation/corrector adjustment 22-27 March

– Phase retrieval analysis used to derive req’d tip/tilt and focus corrections

– Realtime commands sent to effect adjustments

• Fine alignment (prop 9014) refined image quality over field

– Focus and tip/tilt mechanism scans performed 29,31 March

– Encircled energy, sharpness, width and phase retrieval analyses used to trim corrector alignment

– Realtime commands sent to effect adjustments Page 3

George Hartig

4 April 2002

TIPS Meeting

On-orbit optical alignment

• Focus adjustment required to bring ACS into confocality with WFPC2 and STIS

– Two iterations of prop 9574 (PI Gilliland) obtained simultaneous images with all three SI’s on 29 Mar, 2 Apr

– Phase retrieval analysis by J. Krist used to determine optimal focus settings

– Apr 2 data indicate WFC & HRC in excellent agreement with WFPC2

• Aperture locations/orientation determined with prop

9011 images obtained on 3 Apr

– Data under analysis by C. Cox

– Astrometric field observed with guide stars from same catalog

– Locations ~ 3 arcsec from pre-launch estimates; orientation v. close

• Prop 9015 will further evaluate image quality over field through additional filters

– Scheduled for 5 Apr

Page 4

ACS Confocal with WFPC2 (Krist)

George Hartig

4 April 2002

TIPS Meeting

Page 5

George Hartig

4 April 2002

TIPS Meeting

On-orbit optical alignment complete

• ACS image quality, following alignment activities, is excellent

– Both WFC and HRC handily exceed encircled energy CEI requirements (75% EE in .25 arcsec diameter at 633 nm)

– HRC easily exceeds EE goal of 80%; WFC close to goal

– Other image quality measures (PSF peak fraction, width) are as predicted

– Phase retrieval results indicate expected low level of residual aberrations (small amounts of field-dependent coma, astigmatism, defocus)

– WFC focal plane well-matched to image surface: focus variations over field are minor

Page 6

George Hartig

4 April 2002

TIPS Meeting

First CCD Anneal Sequence

• ACS transitioned to ANNEAL mode on 29 March

– CCD temperatures rapidly rose from operating temps of –77 C

(WFC) and -80 C (HRC) as TECS were turned off and HRC window and ASCS interface plate heaters turned on

– Temperatures stabilized near expected levels: 19 C (WFC),

22 C (HRC)

• CCDs remained warm for ~24 h to permit annealing process

• Cooldown proceeded nominally with nominal operating temps achieved and TEC current stable in ~1.5 h on WFC

• Approximately 80% of hot pixels repaired; similar to STIS experience (Riess analysis)

Page 7

George Hartig

4 April 2002

TIPS Meeting

CCD Annealing Warm-up

Annealing Temperatures

30

20

10

0

-10

13:00 14:00 15:00 16:00 17:00 18:00

UT

19:00 20:00 21:00 22:00 23:00

WFC

HRC

Page 8

First HRC Anneal: 80% effective (Riess)

George Hartig

4 April 2002

TIPS Meeting

Page 9

NICMOS

Cooling System Status

Larry Petro

April 4, 2002

Summary

NICMOS continues to cool

NICMOS is safed in order to accelerate cooling

NCC not surging, increasing cooling

Occurred later than expected

NCS performance improvements under study

April 4, 2002

TIPS

2 / 10

Significant activities

Turboalternator speed increased 100 rps (3/24)

Cause unknown

Improved cooling of NICMOS

NICMOS safed (3/28)

Reduces heating in circulator loop by 0.1-0.2 W

NCC surging stopped (4/3)

Turboalternator inlet temperature 85 K (>90 K in ground tests)

Compressor speed limit (7090 rps) in effect until 80 K

April 4, 2002

TIPS

3 / 10

Cooldown continues

Actual NICMOS Cooldown, Compared to Model Prediction

280

260

240

220

200

180

160

140

120

100

80

60

8888 Detector

87007 Neon at N2 tank

MNPNCOLT (NICMOS Outlet Temp)

NDWTMP21 (Cold-Mask Temp, VCS front)

NDWTMP25 (VCS aft)

NFPA1TMP (Camera 1 FPA Temp)

MNPTAILT (TBA Inlet Temp)

0 1 2 3 4 5 6 7 8 9 10 11 12

Time since Compressor startup (Days since 2002 Day 78, 00:23.328 UT)

13

L. Bergeron

14 15 16

April 4, 2002

TIPS

4 / 10

NICMOS cooldown

NICMOS Inlet Temperature

110

105

100

95

90

85

80

75

7

135

130

125

120

115

MNRNCILT (NICMOS Inlet Temp)

MNPNCOLT (NICMOS Outlet Temp)

MNPLINTT (Comp/Circ Load Interface Temp)

8 9 10 11 12

Time since Compressor startup (Days since 2002 Day 78, 00:23.328 UT)

13

NFPA1TMP

NFPA2TMP

NFPA3TMP

14 15

L. Bergeron

16

April 4, 2002

TIPS

5 / 10

C. Long

Cooldown rate

April 4, 2002

TIPS

6 / 10

NCC surging stopped

• Compressor

• Surging

400 rps

NCC Speeds & Temperature

No surging

8000

7000

6000

5000

4000

3000

2000

1000

0

0:00:00

April 4, 2002

80

Compressor

TBA

TBA inlet temperature

NICMOS inlet temperatur

2:24:00 4:48:00

78

7:12:00 9:36:00 12:00:00

Time Day 093 (hr:min:

TIPS

14:24:00 16:48:00

76

19:12:00

84

82

92

90

88

Turboalternator

Inlet Temperature = 85K

86

7 / 10

Ultimate detector temperature?

April 4, 2002

230

220

210

200

190

180

170

160

150

140

130

120

110

100

90

80

78 80 82

T= a(0) * exp( (x+a(1)) * a(2) ) + a(3) ["NICMOS OFF" range] fit range

TBA speed increase

MNPNCOLT (NICMOS Outlet Temp Data)

MNPNCOLT (NICMOS Outlet Temp Fit)

a(0)=139.83409

a(1)=-79.407515

a(2)=-0.16725383

MNPTAILT (TBA Inlet Temp Data)

MNPTAILT (TBA Inlet Temp Fit)

a(3)=96.473789

a(0)=103.60486

a(1)=-77.500066

a(2)=-0.10552370

a(3)=68.224042

No surging

NICMOS safed

84 86 88 90 92

2002 Daynumber

94 96 98 100 102 104

L. Bergeron

TIPS

100 K in

2   weeks without further improvements

8 / 10

Possible improvements

Lower NCC heat rejection interface temperature

Lower CPL reservoir minimum temperature from -10   C to -12 C to -15 C

Increase NCC compressor speed

7300 rps present limit

7400 rps under consideration

Modify circulator loop

Increase speed & pressure

April 4, 2002

TIPS

9 / 10

NCS Status

NCS performing nominally

Cryovalve heater operating nominally

No leakage past o-rings

AS pressure declined from 1.2

× 10 -6 to 0.7

× 10 -6 torr

Occasional 3 × spikes (< 2 × 10 -6 torr)

Heater power cycle is nominal (40- 50 %)

60 - 70% occasionally

NICMOS cooling rate is slower than expected

April 4, 2002

TIPS

10 / 10

MEMORANDUM

TO: Distribution

DATE: April 4, 2002

SUBJECT: Questions and Answers from TIPS Meeting on 04 April 2002

SMOV3b Update

Presenter – Carl Biagetti

Q: What is the magnitude of the ACS/FGS alignment offset?

A: The ACS/FGS alignment offset is about 3 arc seconds.

ACS Status

Presenter – George Hartig

Q: Did the gravity release affect only the ACS optics and not the other components? Could the gravity release be part of the cause of the 3 arc seconds ACS/FGS alignment offset?

A: The gravity release would affect the whole system, and thus it can also contribute to the observed 3 arc second alignment offset.

Q: What are the values for the PSF peak fraction?

A: For the HRC, 86-87%. For the WFC, 80-81%.

Q: On the graph showing the encircled energy vs. radius, what do the solid line and dashed line represent?

A: The two lines are the same, except that the dashed line’s abscissa is stretched to bring out the details.

Q: The image distortions seen on plots, are those coma?

A: Those images have been corrected for coma effects. However, geometric corrections have not been applied to them, and thus the distortions.

Q: Can we apply what we have learned thus far from calibrating the ACS optics to WFC3?

A: The magnitude is too small for it to be of significance.

NCS Status

Presenter – Larry Petro

Q: Is the detector temperature expected to be slightly lower than the outlet temperature?

A: Yes, the detector temperature is expected to be between the inlet and outlet temperature, and in this case it is expected to be lower than the outlet temperature and above the inlet temperature.

Q: Are there other ways to reduce the head load?

A: Not at the moment. Once the system is stabilized, we will investigate other options. We will also be weighing the options against the amount of time they will take the telescope away from useful observing time.

1

Q: The heaters for the O-rings, can they be turned off or regulated so as to help with the cooling?

A: No, the heaters are needed for safety reasons.

Q: If the temperature of the detectors stabilized at 100K, what kind of science can we do?

A: We are currently looking into this.

Q: How is the attitude of the telescope affects cooling and how would that constrain observations?

A: When the Sun is at certain aspects relative to the telescope and when we have large Bright Earth exposure, these two situations can warm up the radiator. We will have to wait until the system stabilizes before we can separate out the various components.

Q: Any plans to correct the cooling model?

A: Yes, there is work in progress to correct the cooling model.

Q: Are the observed pressure spikes in the aft-shroud a concern for MAMA operations?

A: No, it should be fine.

WFPC2 SMOV3b Results

Presenter – Brad Whitmore

Q: How does the ripple compare to the read noise?

A: They are not measurable.

2

Download