UCCS Construction Documents University Center AV Integration February 8, 2012 SECTION 27 00 50 QUALITY ASSURANCE PART 1 GENERAL 1.01 SUMMARY A. This Section defines processes and procedures for quality assurance applicable to Division 27. 1.02 GENERAL QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) A. Design Intent Meeting 1. The Contractor shall schedule and attend a meeting to review the design with the Engineer and Owner. The purpose of the meeting will be to ensure that the Contractor fully understands the design intent as detailed in the Contract Documents. The Contractor shall thoroughly review the Contract Documents prior to the meeting, and shall document questions, comments, and/or concerns to be discussed at the meeting. The meeting shall take place prior to Submittal preparation and submission. Attendees shall include: i. Communications Contractor(s) 1) ii. iii. iv. B. Electrical Contractor Engineer Owner Pre'installation Meeting 1. Prior to beginning work in a given area (or areas), the Contractor shall schedule and attend a pre'installation meeting to review and coordinate work within that area with the other trades. The purpose of the meeting will be to review the communications pathway/raceway layout and identify and resolve any potential conflicts, to have each trade verify that the pathway/raceway sizing is sufficient for the cabling to be installed within, to ensure a consistent installation for all cabling, to minimize interference with adjacent materials and equipment, and to ensure that communications cabling and equipment is accessible to the Owner for future modifications and maintenance. The meeting shall take place a minimum of 30 days prior to communications pathway/raceway rough'in. Attendees shall include: i. Communications Contractor(s) 1) ii. iii. iv. C. Audiovisual Audiovisual Electrical Contractor Engineer Owner Inspections 1. The Contractor shall schedule and coordinate all inspections of the work as required by the Governing Authorities. The Contractor shall be solely responsible for scheduling inspections by the Governing Authorities at times appropriate to the stage of construction and the work to be inspected. The Contractor shall provide all assistance as required by the inspector(s) during their inspection(s). QUALITY ASSURANCE 27 00 50 ' 1 UCCS Construction Documents i. ii. D. Should the Governing Authorities require remedial action on the Contractor’s part due to the failure of the Contractor to schedule inspections at appropriate times, such work shall be at no additional cost to the Owner. The Contractor is solely responsible for scheduling inspections such that, should the work fail inspection, enough time remains in the project schedule to take remedial action and re'inspect the installation. Observation of Work 1. 2. E. University Center AV Integration February 8, 2012 Work will be observed by the Engineer on a periodic basis. Work not found to be in compliance with the Construction Documents, or not in compliance with the intent of the Construction Documents, shall be brought into compliance at no additional cost to the Owner. The Contractor shall notify the Engineer at least one week in advance of the covering of concealed work so that the Engineer may schedule on'site observation of the work to be concealed. Work shall not be concealed until work has been tested (if applicable), observed by the Governing Authorities (if applicable), and at the Engineer’s discretion, observed by the Engineer. Should work be concealed prior to such testing and observation, it shall be uncovered, tested, observed, and restored by the Contractor to the finished condition at no additional cost to the Owner. Coordination 1. 2. The Contractor shall thoroughly examine the Construction Documents, for construction details and methods that are dependent upon or will affect the work of other trades. The Contractor is responsible for identifying coordination issues and dependencies, and for preparing Shop Drawings, work plans and schedules to accommodate or mitigate coordination issues and dependencies before they arise. Changes necessitated by the failure of the Contractor to coordinate with the work of other trades shall be at no additional cost to the Owner. The Contractor shall confer and cooperate with the other trades, throughout the entire construction process, in order to coordinate the work in the proper sequence. Typical coordination issues include but are not limited to: i. ii. iii. 3. 4. 5. 6. Electrical work, including but not limited to electrical receptacles, power panels, transformers, the telecommunications grounding system, and the installation of raceway, device boxes, conduits, cable tray, ladder racking and sleeves. Ceiling cavity spaces. Installation of acoustical ceiling tiles and similar finishes that may conceal the work. Verify that the physical dimensions of each item of equipment fit the available space, promptly notify the Engineer of any potential conflicts, and await the Engineer’s direction prior to purchase and rough'in of the equipment. Coordinate locations of devices with field conditions, unless such locations are specifically dimensioned or otherwise noted in the Construction Documents. If so noted, verify location with other affected trades and against existing field conditions, promptly notify the Engineer of any potential conflicts, and await the Engineer’s direction prior to purchase and rough'in of the equipment. Coordinate locations for chases, slots, sleeves, and openings in the building structure. For new concrete coordinate, locate and provide chases, slots, sleeves, and openings prior to the pouring of the concrete. Outages shall be coordinated and scheduled in advance with the Owner at a time and duration acceptable to the Owner. Outages scheduled at times other than the normal working hours shall not entitle the Contractor to additional compensation beyond the original amount bid. Outages without advance notice and prior approval by the Owner are not acceptable. QUALITY ASSURANCE 27 00 50 ' 2 UCCS Construction Documents 7. F. University Center AV Integration February 8, 2012 Furniture and Casework: Prior to procurement and installation of materials and equipment within furniture and casework, the Contractor shall coordinate with other trades and verify all locations, pathway requirements, etc. Materials and equipment installed in furniture and casework without prior coordination are solely at the Contractor’s risk, and as such, are subject to possible rejection by the Engineer. Rejected materials and equipment shall be replaced and modified furniture and casework shall be restored to its original condition at no additional cost to the Owner. Verification and Validation 1. Measurements i. 2. The Contractor shall physically verify and validate all measurements on site (i.e. actual measurements vs. those of the Drawings). Where discrepancies exist which could affect the Work or the Intent of the Construction Documents, the Contractor shall notify the Engineer and await the Engineer's direction, prior to procurement and installation of materials. Raceway/Pathway Sizes i. Prior to procurement and installation of raceway/pathway, the Contractor is responsible for verifying and validating raceway/pathway (conduit, sleeves, cable tray, surface raceway, etc.) sizes with any and all trades which will make use of them. 1) 2) 3. Equipment locations i. Prior to the installation of equipment, the Contractor shall coordinate with other trades and subsequently verify all equipment locations that mount on walls or within ceilings. This work shall include but shall not be limited to: 1) 2) 3) 4. G. The Contractor, in conjunction with the various trades, shall determine the quantity, types, and outside diameters of the cables to be installed within each raceway/pathway, and shall verify the cable fill ratios for each pathway based upon this information. The cable fill ratios shall include spare capacity as required elsewhere within these Specifications or on the Drawings. Where the calculated cable fill ratios exceed that recommended by the NEC and TIA/EIA 569, where the ratios indicate that the raceway/pathway is of insufficient size, and/or where discrepancies exist between the raceway/pathway sizes shown on the Drawings and the Contractor’s calculated sizes, the Contractor shall notify the Engineer and await the Engineer's direction prior to procurement and installation of the raceway/pathway or cable. Structural elements such as lighting devices, HVAC equipment, fire protection devices, and cable tray. Structural support elements for ceiling mounted devices such as but not limited to speakers, cameras, projectors and projection screens. Backing Board for wall mounted devices such as but not limited to equipment panels, equipment panels, power supplies, head'end equipment, flat panel displays, speakers, and equipment room devices. No additional compensation will be approved for additional work or materials required due to the Contractor’s failure to verify and validate the above. Examination QUALITY ASSURANCE 27 00 50 ' 3 UCCS Construction Documents 1. 2. 3. University Center AV Integration February 8, 2012 The Contractor shall carefully examine the project site and the Construction Documents and shall be responsible for identifying all utility, state, and local requirements that will affect the Work. The Contractor shall become familiar with the local conditions under which the work is to be performed and correlate those conditions with the requirements of the Construction Documents. No allowance will be made for claims of concealed conditions which the Contractor, exercising reasonable due diligence while examining the site, observed or should have observed. The Contractor shall be responsible for determining if the Work will affect the operation or code compliance of existing systems. Where this is the case, the Contractor shall notify the Engineer and await the Engineer's direction prior to procurement and installation. 1.03 SYSTEMS SPECIFIC QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) A. In addition to the quality assurance processes and procedures specified above, the Contractor shall provide the following for each system: 1. Audiovisual i. Equipment locations: Prior to the installation of equipment, the Contractor shall coordinate with other trades and subsequently verify all equipment locations that mount on walls or within ceilings. This work shall include but shall not be limited to: 1) 2) 3) Structural elements such as lighting devices, HVAC equipment, fire protection devices, and cable tray. Structural support elements for ceiling mounted devices such as projectors, projection screens, and speakers. Backing Board for wall mounted devices such as flat panel displays, speakers, and equipment room devices. PART 2 MATERIALS 2.01 THIS SECTION NOT USED PART 3 EXECUTION 3.01 THIS SECTION NOT USED END OF SECTION QUALITY ASSURANCE 27 00 50 ' 4