1.01 GENERAL

advertisement
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
SECTION 16010 – ELECTRICAL – BASIC REQUIREMENTS
PART 1 GENERAL
1.01
GENERAL
A. Provisions of the General Conditions, Supplementary Conditions and Division 1 - General
Requirements, and applicable provisions elsewhere in the Contract Documents apply to the work
of Division 16 - Electrical.
B. Articles contained in this section apply to all Division 16 Sections.
1.02
SUMMARY OF WORK
A. Work Included: Unless specified otherwise, provide all labor, materials and equipment necessary
for completely finished and operational systems. Provide all minor incidental items such as
offsets, fittings, etc. Required as part of the work even though not specified or indicated.
B. Description of Systems: The work of Division 16 includes but is not limited to:
1. Branch Circuit Power Distribution
C. Related Requirements:
1. General Requirements: Division 1 - All Sections
2. Division 16: All Sections
3.
Mechanical and Electrical Coordination: Division 15
D. Work Under Other Divisions:
1. Work Under Division 15
E. Examination: Examine work preceding or interfacing with the work of Division 16 Sections and
report any known or observed defects that affect the work to the General Contractor. Do not
proceed with the work until the defects are corrected. No waiver of responsibility for defective
work will be allowed due to failure to report unfavorable conditions affecting the work.
F. Existing Utilities: Existing Utilities are indicated as accurately as possible on the Drawings.
Work on utilities encountered and not indicated on the Drawings will be directed by change order
after being brought to the attention of the Architect. Close openings and repair damage in an
acceptable manner to utilities encountered.
1.03
COORDINATION
A. General: Coordinate and order the progress of Electrical work to conform to the progress of the
work of the other trades. Complete the entire installation as soon as the condition of the building
will permit.
ELECTRICAL – BASIC REQUIREMENTS
16010 - 1
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
B. Installation Procedures: Confer and cooperate with other trades and coordinate the work in proper
relation with theirs. Coordinate ceiling cavity space carefully with other trades.
C. Coordination with Mechanical Work: Division 15
D. Cutting and Patching: Section 16050.
E. Drawings and Specifications: The Drawings and Specifications are complementary; what is called
for in either of these is binding as though called for by both. The Electrical Drawings indicate the
general design and arrangement of lines, equipment, systems, etc. Information shown is
diagrammatic in character and does not necessarily indicate every required offset, fitting, etc. Do
not scale Drawings for dimensions. Take dimensions, locations, levels, etc. from Architectural
Drawings and equipment to be furnished. No extra compensation will be allowed on account of
differences between actual dimensions and those indicated on the Drawings.
F. Discrepancies:
1. Examine Drawings and Specifications for other parts of the work, and if any discrepancies
occur between the plans for the work of this Division and the plans for the work of others,
report such discrepancies to the General Contractor and obtain written instructions for any
changes necessary.
2. Make changes, at no additional cost to the Owner, to the work of Division 16 made
necessary by the failure or neglect to report such discrepancies. However, it is not the intent
of the Specifications that the Contractor be responsible for the correct design of the
electrical system.
G. Order of Precedence: The precedence of electrical construction documents is as follows:
1. Addenda and modifications to the Drawings and Specifications take precedence over the
original Drawings and Specifications.
2. Should there be a conflict within the Specifications or with Drawings of the same scale, the
more stringent or higher quality requirement shall apply.
3. In the Drawings, the precedence shall be Drawings of larger scale over those of smaller
scale, figured dimensions over scaled dimensions and noted material over graphic
indications.
4. Should a conflict arise between the Drawings and the Specifications, the Specifications shall
have precedence.
5. Should there be a conflict in the dimensions or locations between Electrical Drawings and
Architectural Drawings, the Architectural Drawings shall have precedence.
1.03
SUBMITTALS
A. Submit samples, shop drawings and product data as required by various sections of Division 16 in
accordance with Section 01300. Make submittals to Architect. Do not make submittals directly
to Engineer. Include one additional copy above the requirements of Section 01330.
ELECTRICAL – BASIC REQUIREMENTS
16010 - 2
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
1.04
QUALITY ASSURANCE
A. Preparation: Base final installation of materials and equipment on actual dimensions and
conditions at the project site. Field measure for materials or equipment requiring exact fit.
B. Workmanship: Perform work in accordance with good commercial practice. The good
appearance of finished work shall be of equal importance with its mechanical efficiency.
C. Supervision: Be responsible for and coordinate the work of all sub-contractors working under
Division 16.
D. Properly locate anchors chases, recesses and openings required for the proper installation of the
work. Arrange with the proper contractors for the building of anchors, etc. and for the leaving of
the required chases, recesses and openings.
E. Install equipment and material in accordance with manufacturer=s instructions unless specifically
indicated otherwise, or where local codes or regulations take precedence.
1.05
REGULATORY REQUIREMENTS
A. Pay for permit and inspection fee costs applicable to work of Division 16.
B. Comply with State and local requirements and ordinances. Comply with requirements of the
Utility Companies. Call for inspections required by local building inspection authority. Submit
certificate of occupancy or final acceptance by inspection authority.
C. Applicable Building Codes and Ordinances: Including but not limited to the following:
1. Governing Fire Department Requirements
2. State of Colorado Energy Standards
3. State Department of Labor Requirements
4. State Department of Health Requirements
5. National Fire Protection Association Standards
6. State and Federal Safety and Health Laws
7. NFPA 70 2008 Edition - National Electrical Code
8. NFPA 72 2008 Edition - National Fire Alarm Code
9. NFPA 90A Latest Edition - Fire Detection in Mechanical Systems
10. NFPA 101 Latest Edition - Life Safety Code
D. Discrepancies: If discrepancies occur between these Specifications, local codes, local Utility
requirements, etc., the most stringent requirements shall apply.
ELECTRICAL – BASIC REQUIREMENTS
16010 - 3
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
1.06
REFERENCE STANDARDS
A. References:
1. For products or workmanship specified by association, trade or Federal Standards, comply
with the requirements of the standard, except when more rigid requirements are specified or
are required by applicable codes.
2. The date of the standard is that in effect at the bid date, or date of Owner/Architect
Agreement when there are no bids, except when a specific date is specified.
3. When required by individual Specification Section, obtain copy of standard. Maintain copy
at job site during work until Substantial Completion.
1.07
DELIVERY, STORAGE AND HANDLING
A. General: Comply with Section 01600. Deliver and store materials and equipment in
manufacturer=s unopened containers fully identified with manufacturer=s name, trade name,
type, class, grade, size, and color.
B. Protection: Store materials and equipment off the ground and under cover, protected from
damage.
C. Acceptance: Check and sign for materials to be furnished by others for installations under
Division 16 upon delivery. Assume responsibility for the storage and safekeeping of such
material from time of delivery until final acceptance.
1.08
CLEANING
A. Cleaning: Comply with Section 01770. Clean exposed surfaces of conduit, hangers, lighting
fixtures, and other electrical equipment of grease, dirt, etc. Clean the inside of panelboard
enclosures prior to installing the front cover. Remove shipping labels. Carefully and thoroughly
clean all items of equipment. At completion of the work, remove rubbish and debris resulting
from the operations and leave equipment spaces clean and ready for use.
1.09
PROJECT RECORD DOCUMENTS
A. Job Site Documents: Maintain at job site, one record copy of the following:
1. Drawings
2. Specifications
3. Addenda
4. Reviewed Shop Drawings
5. Change Orders
B. Do not use record documents for construction purposes. Maintain documents in clean, dry,
legible condition, apart from documents used for construction.
ELECTRICAL – BASIC REQUIREMENTS
16010 - 4
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
C. Record Information: Label each document ARecord Document@. Mark information with
contrasting color using ink. Keep each record current. Do not permanently conceal any work
until required information is recorded.
D. Record the following Information on the Specifications:
1. Manufacturer, trade name, catalog number and supplier of each product or item of
equipment actually installed.
2. Changes by change order or field order.
3. Other matters not originally specified.
E. Record the following information on the Drawings:
1. Field changes of dimension and detail.
2. Changes by change order or field order.
3. Details not on original Contract Drawings.
F. Shop Drawings: Maintain Shop Drawings as record documents recording changes made after
review as specified for Drawings above.
G. Submittal: At completion of project, deliver Project Record Documents to General Contractor.
END OF SECTION
ELECTRICAL – BASIC REQUIREMENTS
16010 - 5
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
SECTION 16050 – ELECTRICAL – BASIC MATERIALS AND METHODS
PART I
1.01
GENERAL
SECTION INCLUDES
A. Conduit
B. Wires and Cables
C. Boxes
1.01
DESCRIPTION
A. Install wiring in complete raceway systems unless specifically indicated otherwise.
B. Provide galvanized rigid conduit throughout except as allowed below:
1. Electrical metallic tubing Athinwall@ may be installed concealed in furred ceilings
and walls or exposed at least 5 feet above the floor, provided such areas are dry.
C. Circuits #6 and smaller are classified as branch circuits.
D. Conductors installed in high ambient conditions such as near boiler breeching, directly
under roofing, exposed on roof, etc., shall be rated 90 degrees C minimum.
1.02
REFERENCES
A. American National Standards Institute (ANSI)
1.
C-80.3
Electrical Metallic Tubing
B. Federal Specifications
1.
2.
W-S 896E
WW-C 563
Switch, Toggle, and Locks
Specification for Electrical Metallic Tubing
C. National Electrical Manufacturer=s Association (NEMA)
ELECTRICAL – BASIC MATERIALS AND METHODS
16050 - 1
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
D. Underwriters Laboratories, Inc. (UL)
1.
2.
PART 2
2.01
UL 514-79
UL 493-72
Outlet Boxes and Fittings
Ground Fault Circuit Interrupters
PRODUCTS
CONDUIT
A. Galvanized Rigid Conduit: Fed. Spec. WW-C581-d and ANSI c-80.1.
B. Electrical Metallic Tubing: Fed. Spec. WW-C563 and ANSI C-80.3.
C. EMT Fittings: Set screw or compression gland type only.
D. Conduit Bushings: Metal insulating type, including grounding bushings, on 1-1/4" and
larger; non-metallic insulating type, 1" and smaller. Metal insulating type bushing to
have molded phenolic insulation equivalent to OZ specification grade.
E. Liquid-tight Flexible Conduit: Constructed of a galvanized steel core with PVC cover;
Anaconda Sealtite or equivalent. Use fittings of same manufacturer as conduit.
2.02
WIRE AND CABLE
A. Branch Circuit Conductors: Copper, #12 minimum, THWN or THHN insulated only.
Pilot control (Class 2 Circuits) may be #14 AWG. Other class 1 control circuits may be
#16.
2.03
OUTLET, JUNCTION, AND PULLBOXES
A. Boxes Up to 150 Cubic Inches: Standard, one piece, zinc-coated, or cadmium plated
steel.
2.01
DEVICE PLATES
A. Surface Plates: Galvanized steel, 1.25 oz/sq.ft. minimum coating, pressure formed with
round corners for smooth edge and fit to box.
ELECTRICAL – BASIC MATERIALS AND METHODS
16050 - 2
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
PART 3
3.01
EXECUTION
PREPARATION
A. Supports:
1. Support raceways, boxes etc., in accordance with Section 16190, Supporting
Devices.
3.01
INSTALLATION
A. Conduits:
1.
2.
3.
4.
5.
6.
7.
B.
Cross expansion joints with expansion fittings and bonding conductor.
Space supports for exposed raceways not more than 7 feet on center.
Route exposed conduit parallel or perpendicular to walls and structural members,
with neat right angle bends or change direction with conduit fitting.
Install conduits at least 6 inches from parallel runs of flues, steam lines, or other
heated lines.
Effectively seal conduit penetrations through fire walls and floors through the use of
rated fittings such as OZ ACFSF@ series fittings or equivalent.
Provide double locknuts and bushings on all rigid conduit terminations.
Provide short extensions of flexible liquid-tight metallic conduit for makeup of
motor, transformer, or equipment connections.
Wire and Cable:
1.
2.
3.
Do not install wire in incomplete conduit runs.
Make branch circuit conductor terminations with insulated pressure type connectors
such as Ideal Industries AWing Nut@, 3M Company AScotchlok@, or Buchanan ABCap@.
Color code power and signal conductors. Sizes #6 and smaller, factory colored.
Sized larger than #6 may be color coded color taping of exposed ends.
120/208V
Phase A - Black
Phase C - Blue
Neutral - White
Ground - Green
5. Provide an insulated equipment grounding conductor in all power circuits. Size
conductor per the NEC unless indicated otherwise on the Contract Drawings.
ELECTRICAL – BASIC MATERIALS AND METHODS
16050 - 3
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
6. Provide insulating grommets as mfgr=d. By Arlington Industries or equivalent, in
steel stud openings when installing MC or NM cables through pre-punched or field
punched stud openings.
7. Bolt aluminum lugs to equipment with properly sized high strength aluminum bolt or
an assembly of plated steel bolt, flat washer, and plated Belleville washer.
B. Outlets and Boxes:
1.
2.
Install flush boxes plumb, within 1/8 inch of finished surface. Install exposed boxes
plumb, securely anchored to ceiling or wall.
Coordinate locations of junction boxes and pull boxes with other trades so that
boxes as accessible remain so.
E. Cabinets:
1.
2.
H.
Coordinate depth of flush cabinets with wall thickness prior to purchase.
Set enclosure at maximum 6 feet 3 inches above the floor.
Systems Identification:
1.
Identify junction and pull boxes with labels of embossed metal or plastic tape
affixed to their cover and side. Identify the electrical system it serves, i.e.,
Emergency Power, etc.
END OF SECTION
ELECTRICAL – BASIC MATERIALS AND METHODS
16050 - 4
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
SECTION 16060 – GROUNDING
PART 1
1.01
GENERAL
RELATED DOCUMENTS
A. Drawing and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 - General Requirements, apply to this Section.
B. Section 16010 - General Electrical Provisions applies to work of this Section.
1.02
SECTION INCLUDES
A. Raceways and Enclosures.
1.03
REFERENCES
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referred to in the text by the basic designation only.
B. Institute of Electrical and Electronics Engineers (IEEE):
1. ANSI/IEEE 142, 1982, ARecommended Practice for Grounding of Industrial and
Commercial Power Systems@ (copyrighted by IEEE, ANSI approved).
C. Underwriters Laboratories, Inc. (UL):
1. UL 467, 1984 (Revised 1986), AGrounding and Bonding Equipment@.
2. UL 486 A, 1908 (Revised 1989), AWired Connectors and Soldering Lugs for Use
with Copper Conductors, Seventh Edition@.
D. American Society for Testing Materials (ASTM):
1. ASTM B-3, 1981, AStandard Specification for Individual Conductors@.
2. ASTM B-33, 1981 (Revised 1985), AStandard Specification for Tinned Soft or
Annealed Copper Wire for Electrical Purposes@.
PART 2
2.01
PRODUCTS
CONDUCTORS
A. General: Grounding conductors shall be stranded, medium drawn copper or as shown on
the drawings or required by this specification.
ELECTRICAL – GROUNDING
16060 - 1
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
B. Conductivity: Copper conductors shall have a conductivity of not less than 98 percent at
20 degrees C. Conductor resistance values shall be in accordance with the value in
IPECEA S-68-516.
C. Stranded Conductors: Stranded conductors shall comply with the following requirements:
1. Individual Conductors: ASTM B-3.
2. Stranded Assembly: ASTM B-8.
D. Insulation: Provide insulation same as specified in section 16050.
2.02
BONDING JUMPERS
A. Flexible Bonding Cable: Provide flexible flat cable constructed of 480 strands of 30
gauge copper wires, 3/4 inch wide by 1/8 inch thick.
B. Flexible Bonding Strips: Provide flexible flat conductor, constructed of 480 strands of 30
gauge bare copper wires with bolt hole ends. Strap size shall be 3/4 inch wide by 10
inches long.
2.03
CONNECTORS
A. Ground Bushings:
1. Bushings shall be malleable iron, cadmium plated, insulated throat with screw type
wire connector.
2. Acceptable Manufacturer: OZ Gedney - Type IGB.
PART 3
3.01
EXECUTION
PREPARATION
A. Examine areas and conditions under which the work is to be installed, and notify the
Owner’s Representative in writing of any conditions detrimental to the proper and timely
completion of the work. Do not proceed with the work until unsatisfactory conditions
have been corrected.
3.02
COORDINATION
A. Coordinate with other work to ensure that installation is not vulnerable to physical
damage.
ELECTRICAL – GROUNDING
16060 - 2
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
3.03
SAFETY GROUNDING SYSTEM
A. Provide for a complete grounding system. Route grounding conductors to provide the
shortest and most direct path. Install grounding conductors in conduit.
B. Provide a separate grounding conductor, securely grounded, on each run of metallic
conduit and flexible conduits.
C. Provide a green or bare grounding jumper from the ground screw of outlet boxes to the
ground screw of wiring devices. Wiring devices UL tested and approved for use without
the jumper may be used in lieu of the jumper.
3.01
INSTALLATION
A. Comply with applicable requirements of UL 467, ANSI/IEEE 80, and applicable NEMA
standards, to ensure that products fulfill requirements.
B. Bonding Jumpers: Bonding jumper shall be installed where continuity of piping of metal
must be maintained or as required by the NEC.
END OF SECTION
ELECTRICAL – GROUNDING
16060 - 3
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
SECTION 16190 – SUPPORTING DEVICES
PART 1
1.01
GENERAL
SECTION INCLUDES
A. Conduit Supports.
B. Anchors.
PART 2
2.01
PRODUCTS
CONDUIT SUPPORTS
A. Single Runs: Galvanized one hole or two straps, lay-in adjustable hangers, clevis
hangers, or bolted split stamped galvanized steel hangers.
B. Multiple Runs: Rack on channel supports.
C. Vertical Runs: Channel support.
2.03
ANCHORS
A. Hollow Masonry: Toggle bolts or spider type expansion anchors.
B. Solid Masonry: Lead expansion anchors or preset inserts.
C. Metal Surfaces: Machine screws, bolts or welded studs.
D. Concrete Surfaces: Self-drilling anchors or powder driven studs.
PART 3
3.01
EXECUTION
PREPARATION
A. Obtain permission from the Architect before using powder actuated anchors or drilling
structural members.
ELECTRICAL – SUPPORTING DEVICES
16190 - 1
University of Colorado – Colorado Springs – University Hall
Boiler Replacement
B. Lay out to maintain headroom, neat mechanical appearance, and to support equipment
loads required.
3.02
INSTALLATION
A. Support exposed metallic conduits and metallic conduits installed above accessible
ceilings not more than 7 feet on center. Support conduits from building roof or floor
structure. Do not support from ceiling suspension support systems, refer to Art. 300-11
of the NEC for exceptions that may apply.
B. Support boxes independent of conduit unless a cast box is connected to galvanized rigid
conduits where conduit is supported within 12 inches of box.
END OF SECTION
ELECTRICAL – SUPPORTING DEVICES
16190 - 2
University of Colorado – Colorado Springs – University Hall
Rooftop Unit Replacement
SECTION 16195 – ELECTRICAL IDENTIFICATION
PART 1
1.01
GENERAL
SECTION INCLUDES
A. Directory Cards.
B. Engraved Nameplates.
C. Tape Labels.
PART 2
2.01
PRODUCTS
MATERIALS
A. Adhesive Tape Labels: Black imprinted letters on a clear tape as made by a tape
imprinting machine such as the Brother AP-Touch@ or approved equivalent. Install on
each junction box to clearly indicated circuit or circuits within.
B. Directory Cards: Modify existing as indicated on the Contract Drawings.
PART 3
3.01
EXECUTION
PREPARATION
A. No temporary markings which are visible on equipment are permitted.
B. Thoroughly clean surface to which pressure sensitive type tape labels are applied to
assure adherence of label.
3.02
INSTALLATION
A. Do not use abbreviations in labeling without specific permission.
B. Label panel boards as designated on electrical drawings.
C. Directory cards, nameplates, and labels shall indicate the general area and type of
electrical load served by each circuit.
ELECTRICAL – ELECTRICAL IDENTIFICATION
16195 - 1
University of Colorado – Colorado Springs – University Hall
Rooftop Unit Replacement
3.03
SCHEDULE OF LABELS
A. Provide 2 inch minimum height letters engraved in plastic laminate nameplates to
identify the equipment item for:
1. Branch and distribution panel boards.
B. Provide 1/4 inch minimum height letters engraved in plastic laminate nameplates, or
adhesive labels to identify circuits, switches, or circuit breakers in:
1. Switchboard or panel board (service equipment).
2. Distribution panels.
3. Separately mounted motor starters.
4. Disconnect switches.
C. Provide 1/8 inch minimum height laser etched or engraved device plates identifying
function or equipment controlled for:
1. Exhaust fans.
2. Light switches controlling lights that are out of sight.
D. Provide 1/8 inch minimum height lettering identifying panel and circuit number laser
etched on the front surface of plastic or nylon plates and adhesive labeled to the front of
device plates.
E. Provide neatly typed directories or identification labels. Use 12 or 15 pitch type as
appropriate to assure adequate information is included in small spaces. Use on:
1. Branch circuit panel board directories.
2. Terminal strips.
END OF SECTION
ELECTRICAL – ELECTRICAL IDENTIFICATION
16195 - 2
Download