831 REPORT To EXECUTIVE MAYOR 14 JUNE 2011 1 ITEM NUMBER: 2 2010/2011 ! CITY OF CAPE TOWN IISIXEKO SASEKAPA SUO UAPSTAD Me 41106111 THIRD QUARTER'S PROGRESS REPORT ON CORPORATE PERFORMANCE AND PERFORMANCE OF THE CITY'S ENTITIES INGXELO YEKOTA YESIBINI YONYAKA-MALI ENGENKQUBELA-PHAMBILI MALUNGA NENDLELA KWEZIKO NAMAQUMRHU AZIMELEYO ESIXEKO KA-2010/2011 YOKUSEBENZA EN VORDERINGSVERSLAG OOR KORPORATIEWE PRESTASIE PRESTASIE VAN DIE STAD SE ENTITEITE VIR DIE DERDE KWARTAAL VAN 2010/2011 3 RECOMMENDATIONS FROM ALL PORTFOLIO COMMITTEES: 03.05.2011; 05.05.2011 & 06.05.2011 RECOMMENDED that the 2010/2011 third quarter's progress report on Corporate performance and performance of the City's entities be approved. KUNDULULWE ukuba makuphunyezwe ingxelo yekota yesithathu yonyaka-mali ka-2010/2011 engenkqubela-phambili malunga nendlela yokusebenza kweziko namaqumrhu azimeleyo esixeko. AANBEVEEL dat die korporatiewe prestasie en prestasie van die Stad se entitieite vir die derde kwartaal van 2010/2011 goedgekeur word. UV\ 2o S S-=\- 832 REPORT To MAYCO REPORT To COUNCIL em DF CAPE TDWN iISIXEKD SASEKAPA ; SUD KAAPSTAD 1. ITEM NUMBER: 2. SUBJECT To be inserted by ExeculIve SuPpo/1 2010/2011 THIRD QUARTER'S PROGRESS REPORT ON CORPORATE PERFORMANCE AND PERFORMANCE OF THE CITY'S ENTITIES ISIHLOKO INGXELOYEKOTA YESITHATHU YONYAKA-MALI KA-2010/2011 ENGENKQUBELA-PHAMBILI MALUNGA NENDLELA YOKUSEBENZA KWEZIKO NAMAQUMRHU AZIMELEYO ESIXEKO ONDERWERP VORDERINGSVERSLAG OOR KORPORATIEWE PRESTASIE EN PRESTASIE VAN DIE STAD SE ENTITEITE VIR DIE DERDE KWARTAAL VAN 2010/2011 3. PURPOSE The purpose of the report is to enable Mayco to consider and Council to note: • the progress on the City's performance during the third quarter of the 09/10 financial year covering the period 1 July 2010 to 31 March 2011 (performance year to date), as required by legislation. 4. FOR DECISION BY Executive Mayor together with the members of the Mayoral Committee. System of delegations as amended by Council on 09 December 2010 - Section (3)(b) Evaluates progress against the key performance indicators (The Executive Mayor has delegated this power to all Mayoral Committee members, within the functional area of their relevant portfolios only) & section (3)(c) Reviews the performance of the municipality in order to improve(i) the economy, efficiency and effectiveness of the municipality; (ii) the efficiency of credit control and revenue and debt collection services; and the implementation of the municipality's by-laws. (iii) Cover letter to Mayea and Council.docx ISeptember 2009J Page 1 of 5 , 'Ir,.~/~/ Ji 833 5. EXECUTIVE SUMMARY The Municipal Systems Act and Municipal Planning and Performance Management Regulations require municipalities to submit regular reports on matters related to their performance. Accordingly, the City's corporate performance and performance of the City's entities for the period 1 July 2010 to 31 March 2011 which will be circulated separately as Annexure A, B & C. 6. RECOMMENDATIONS LSU4148 (reference number Language Services) "Delegated: for Decision by the Executive Mayor: Recommended that the report be considered and approved by Executive Mayor and Mayco, and noted by Council. AANBEVELINGS "Gedelegeer: vir besluit deur die uitvoerende burgemeester: Aanbeveel dat die uitvoerende burgemeester en die burgemeesterskomitee die vers/ag oorweeg en goedkeur en die Raad van die verslag kennis neem. IZINDULULO "Zigunyazisiwe: iSiggibo sesikaSodolophu weSiggeba: Kundululwe ukuba makuqatshelwe ingxelo nguSodolophu weSigqeba, yiKomiti yoLawulo (i-Mayco) neBhunga. 7. DISCUSSION/CONTENTS 7.1. Constitutional and Policy Implications The process of reporting on the City's performance and that of the City's entities is driven by legislation and the City's approved performance management policy. 7.2. Environmental implications Does your report have any environmental implications: Cover letter to Mayea and Council.doGx ISeptember 20091 No~ Yes D Page 2 of 5 834 7.3. Legal Implications 7.3.1 Local Government: Municipal Finance Management Act (Act 56 of 2003). 7.3.2 Local Government: Municipal Systems Act (Act 32 of 2000) (Chapter 6), as read with the Local Government: Municipal Systems Amendment Act (Act 44 of 2003). 7.3.3 Local Government: Municipal Planning and Performance Management Regulations, 2001. In terms of Section 41 (1) (e) of the Systems Act and Regulation 7 (1) and (2) (e) of the Municipal Planning and Performance Management Regulations, the City (through the Integrated Development Planning and Organisational Performance Management Department) is required to submit quarterly corporate progress reports to the Council and its relevant Committees on matters connected with the City's performance. Therefore, this report deals with the monitoring of an existing, ongoing process that is prescribed by legislation. 7.3.4 System of delegations as amended by Council on 09 December 2010. (vi) Section (3)(b) Evaluates progress against the key performance indicators (The Executive Mayor has delegated this power to all Mayoral Committee members, within the functional area of their relevant portfolios only) & Section (3)(c) Reviews the performance of the municipality in order to improvethe economy, efficiency and effectiveness of the municipality; the efficiency of credit control and revenue and debt collection services; and the implementation of the municipality's by-laws. 7.4. Staff Implications (iv) (v) Does your report impact on staff resources, budget, grading, remuneration, allowances, designation, job description, location or your organisational structure? No I:8J Yes 0 (if yes, please indicate whether or not it is part of the approved staffing structure, whether the posts are budgeted for etc.) 7.5. Other Services Consulted All Directorates. Cover letter to Mayeo and Couneil.doex INovember 20091 Page 3 of 5 835 ANNEXURES Annexure A: 2010/2011 THIRD QUARTER'S CORPORATE PERFORMANCE PROGRESS REPORT ON Annexure B: 2010/2011 THIRD QUARTER'S PROGRESS CONVENCO'S PERFORMANCE (Municipal entity) REPORT ON Annexure C: 2010/2011 THIRD QUARTER'S KHYAYELITSHA COMMUNITY (Municipal entity) PROGRESS REPORT ON TRUST PERFORMANCE The annexures are not attached to the report, but it will be available at or before the Mayea meeting. FOR FURTHER DETAILS CONTACT: Cover letter to Mayeo and Couneil.doex INovember 2009J Page 4 of 5 FOR FURTHER DETAILS CONTACT: NAME Willem C/aassens CONTACT NUMBERS 021-40098231082341 9070 E-MAIL ADDRESS Willem. claassens@capetown.gov.za Office of the City Manager DIRECTORATE LEGAL C~ANCE TEL Cf\ l:::Y ~ 0 REPORT COMPLIANT WITH THE PROVI'eNS OF COUNCIL'S DELEGATIONS, POLICIES, BY-LAws AND ALL LEGISLATION RELATING TO THE MADER UNDER CONSIDERATION. 0 NON-COMPLIANT ~ NAME DATE ~ l:~~~ d! F Ii ~ ,\ 0'\ I c» I 2Dli Comment: . Certified as legal! Y compliant· Based . o e report. Comment: CITY MANAGER Achmat Ebrahim DATE I I I Cover letter to Mayco and Council.docx [November 2009J Page 5 of 5 ANNEXURE A 201012011 ONE YEAR CORPORATE SCORECARD (SDBIP) DRAFT 3rd QUARTER PROGRESS REPORT ON CORPORATE PERFORMANCE Rating Key: LINK TO LEAD DIRECTORATE ~ - Meets or exceeds target ; INDICATOR ANNUAL TARGET 2010/11 ~ - Currently does not meet target ; RATING TARGET QUARTER ENDING 31 MARCH 2011 ~ - Information not available or work on hold; ACTUAL QUARTER ENDING 31 MARCH 2011 REASON FOR VARIANCE "'e;J _ Original target to be amended .. 837 REMEDIAL ACTION Strategic Focus Area 1 : Shared Economic Growth and Development Corporate Objective: 1A. Create an enabling environment for the economy to grow and become globally competitive 1A.1 Capital budget spend R4bn ~ R2.28bn 51% R1,48bn 37% Reasons for variances and remedial action are provided per monthly Financial Monitoring Report (FMR) to Mayoral Committee and EMT 16000 0 10000 10965 Target exceeded Maintain the momentum 1A.3 % of Land Use applications finalised within statutory timeframes 80% 0 80% 83% Target exceeded Maintain the momentum 1A.4 % of Building plans finalised within statutory timeframes 70% ~ 70% 65% Staff capacity planning under pressure to meet the existing demand Ongoing monitoring 44 021 (Commercial) 585515 (Domestic) 629536 (Total) ~ 43466 (Commercial) 584 787 (Domestic) 628253 (Total) 576165 (Domestic) 31276 0 30776 31797 37 729 (Commercial) 585 082 (Domestic) 622811 (Total) 0 37 682 (Commercial) 584 354 (Domestic) 622 036 (Total) 585619 (Domestic) 11 574 0 11524 11546 157 378 (Commercial) 559206 (Domestic) 713584 (Total) 0 154 324 (Commercial) 557 595 (Domestic) 711919 (Total) 575 984 (Domestic) 6105 ~ 4440 1324 The electrification branch is undergoing a restructure in order to turn these numbers around (improve performance) Department to outsource the work while it is undergoing reengineering 2A.7 Number of formal domestic customers receiving a kerbside refuse collection service 571 327 0 602245 610799 T ar9et Exceeded Maintain the momentum 2A.B Number of informal settlement dwellings receiving a door-to-door refuse collection and area cleaning service 200722 t7 Bi-annual target Bi-annual target Bi-annual target Bi-annual target Finance Housing Strategy and Planning 1A.2 Number of EPWP job opportunities created EMT will monitor the spending on an ongoing basis Corporate Objective: 2A. Provide access to basic services 2A.1 Number of formal domestic customers receiving sewerage services 2A.2 Number of sanitation service points (toilets) installed for informal settlement customers 2A.3 Number of formal domestic customers receiving water services Utility Services 2A.4 Number of water service points (taps) installed for informal settlement customers 2A.& Number of electricity meters serving domestic customers 2A.6 Number of additional electricity subsidised connections installed Page 1 The original target inadvertently included commercial figures. The domestic customer figure is reflected separately for tracking Target exceeded The original target inadvertently included commercial figures. The domestic customer figure is reflected separately for tracking Target exceeded The original target inadvertently included commercial figures. The domestic customer figure is reflected separately for tracking Ongoing monitoring Maintain the momentum Maintain the momentum Maintain the momentum Maintain the momentum 3rd quarter 1011 New Corporate 5DBIP Performance ScorecardMavco(5).xIS ANNEXURE A 2010/2011 ONE YEAR CORPORATE SCORECARD (SDBIP) DRAFT 3rd QUARTER PROGRESS REPORT ON CORPORATE PERFORMANCE Rating Key: LINK TO LEAO DIRECTORATE ~ - Meets or exceeds target ; INDICATOR ~ - Currently does not meet target ; ~ -Information not available or work on hold; ~ - Original target to be amended ANNUAL TARGET 2010/11 RATING TARGET QUARTER ENDING 31 MARCH 2011 ACTUAL QUARTER ENOING 31 MARCH 2011 REASON FOR VARIANCE REMEDIAL ACTION 27% i:o 27% 27,4% Target achieved. Water Demand Management (WOM) measures appear to be having desired impact Maintain the momentum 9.95% i:o 9,65% 10,22% Target Exceeded Maintain the momentum R1.65 bn ~ Annual target Annual target Annual target Annual target <1.3 i:o <1,3 0,82 Target exceeded Maintain the momentum Completion of the Water Balance Improvement Strategy will reSult in mOre positive impact Corporate Objective: 28. Conserve natural resources 28.1 Percentage reduction below unconstrained water demand Utility Services Finance 28.2 Percentage of waste diverted from Council Waste Management Facilities 2C.1 Amount spent on repairs and maintenance 2C.2 Average number of customer power interruptions experienced per annum 2C.3 Percentage unaccounted for water Utility Services 2C.4 Percentage drinking water compliance to SANS 241 22.5% i:o 23% 19,6% Progress on reducing uncertainties in various aspects of the water balance has been made, including bulk metering inaccuracies reduced. Metering of Informal Settlement consumption being extended to all settlements over time but with some still being estimated currently. Losses are being reduced through pro·active pipe replacement programme and pressure management schemes. 96% i:o 96% 98% Target Exceeded Maintain the momentum Bi·annual target Bi-annual target Strategic Focus Area 3: Energy Efficiency for a Sustainable Future Corporate Objective: 3A Develop, adopt and implement a comprehensive response to Cape Town's energy and climate change challenges Utility Services 3A.1 % reduction of electricity consumption below projected unconstrained electricity consumption 10% ~ Bi·annual target Bi·annual target Page 2 3rd quarter 1011 New Corporate SDBIP Performance ScorecardMayco(5).xlS 838 ANNEXURE A 2010/2011 ONE YEAR CORPORATE SCORECARD (SDBIP) DRAFT lrd QUARTER PROGRESS REPORT ON CORPORATE PERFORMANCE Rating Key: LINK TO LEAD DIRECTORATE ~ - Meets or exceeds target ; INDICATOR ANNUAL TARGET 2010/11 ~ - Currently does not meet target; RATING TARGET QUARTER ENDING 31 MARCH 2011 839 '6- -Information not available or work on hold; ACTUAL QUARTER ENDING 31 MARCH 2011 ~ - Original target to be amended REASON FOR VARIANCE REMEDIAL ACTION Strategic Focus Area 4: Public Transport Systems Corporate Objective: 4A. Improve public transport system and services (for e.g. the implementation of phase 1A of the integrated rapid transit programme) 4A.1 Form two Operating Companies to run IRT Form two Operating Companies for Phase laoflRT Transport, Roads & Major Projects ~ Annual target Annual target Annual target The following progress has been made to date to achieve annual target: 1. Concluded interim contract with TransPeninsula, an interim company formed by two of the Phase 1 A taxi associations. 2. Company B: association based companies formed. 3. Company A: new facilitator appointed to expedite finalisation of company formation and negotiation of contracts 4. Company C: Approved by Council in February 2011 Strategic Focus Area S: Integrated Human Settlements Corporate Objective:SA. Provide equitable community facilities and services across the City SA.1 Number of Community Parks maintained according to selected service standards SA.2 Number of libraTies open according to minimum planned open hours, including ad hoc Unforeseen Closing Hours SA.3 Number of fenced formal Sport fields compliant with the defined level grass cover standard Excessive littering in certain areas resulted in cleaning of only once a week instead of twice as per the standard. Mowing tender not approved yet. Received lots of appeals which Legal services department is working on. Mowing tender might only be approved in the new financial year. Increase litter picking to twice a week in certain areas. Extension of the current mowing contracts until the new mowing tender is approved. Submission of additional funding request to the Budget Steering Committee to improve the maintenance standard. Investigating a process to Consolidate all Public Open Spaces to determine Public Open Spaces that we can rationalize. 3133 ~ 3133 2804 63 ~ 63 64 Target exceeded Maintain the momentum 450 ~ 450 466 Target exceeded Maintain the momentum A. Community Services SA.4 Number of halls maintained to speCified standard 181 ~ 169 181 Page 3 There is major Repairs and Maintenance in 4 of the department's halls, i.e. 1. Parkwood Community Centre - Closed 2. Ottery Sport & Recreation Centre - Closed 3. KhayeHtsha Resource Centre - Closed 4. Valhalla Community Centre - Closed B. There is also minor Repairs and Maintenance problems in 8 of the department's halls, i.e. 1. Goodwood Civic 2. Parow Civic 3. Leonsdale Civic 4. Parow North Community Centre 5. Nooitgedacht Hall 6. Edgemead Hall 7. Bothasig Hall 8. Bloekombos Hall All these halls are operational, but they scored below the required 16 pOints because of minor repairs and maintenance problems. A The department will monitor the contractors busy with major Repairs and Maintenance B. All the minor Repairs and Maintenance problems will be addressed within a month's time 3rd quarter 1011 New Corporate SDBIP Performance ScorecardMayco(5).xls ANNEXURE A 2010/2011 ONE YEAR CORPORATE SCORECARD (SDBIP) DRAFT 3rd QUARTER PROGRESS REPORT ON CORPORATE PERFORMANCE Rating Key: LINK TO LEAD DIRECTORATE ~ - Meets or exceeds target ; INDICATOR ANNUAL TARGET 2010/11 ~ - Currently does not meet target ; RATING TARGET QUARTER ENDING 31 MARCH 2011 ~ -Information not available or work on hold; <"Q;J - Original target to be amended ACTUAL QUARTER ENDING 31 MARCH 2011 REASON FOR VARIANCE REMEDIAL ACTION 4409 Target exceeded Maintain the momentum Michael Krauser in process to negotiate with the Khayaletsha Development Forum 840 Corporate Objective: 58. Deliver housing opportunities in accordance with the five year housing plan (reviewed annually) 58.1 Number of housing opportunities provided per year 8400 Housing 58.2 Implementation of informal settlement upgrade programme (UISP) and Emerging Housing Programme (EHP) 1 000 erven serviced ~ 4400 ~ 700 384 ervan serviced 4 Projects were suspended because of community dynamics (Monwabisi Site; Lookout Hill Site; Khaya Site & Ithemba Site) t7 Annual target Annual target Annual target Annual target ~ 3.75% 43% reduction from a baseline of 186 Target Exceeded Maintain the momentum Target Exceeded Maintain the momentum Strategic Focus Area 6: Safety and Security Corporate Objective: 6A. Foster a safe and secure environment 6A.1 Survey score on 5 point symmetric scale ~3 6A.2 % reduction in accident rate at high frequency locations 5% 176 accidents 179 108 Safety and Security 6A.3 % increase in arrests in drug related crimes 5% 1 002 ~ 3.75% 627 5.08% 1020 6A.4 % response times for fire and other emergency incidents within 14 minutes from call receipt up to arrival 80% ~ 80% 73% Page 4 Fire and Rescue services are not at full staffing capacity. This affects response times as resources are required to respond from outside the areas of operation of each fire station, thereby increasing response times to incidents. In addition, a system failure in March resulted in incidents having to be manually recovered. Recovery is not yet complete as there is some outstanding information. Once all incidents have been recovered, it may have an effect on the current result. Until such time as Fire and Rescue are at full capacity and continually respond to Medical and Trauma related incidents, response times will continuously be negatively affected. The departmentt is continuously engaging all avenues to secure funding for additional rescources. 3rd quarter 1011 New Corporate SDBIP Performance ScorecardMayco(5).xIS ANNEXURE A 2010/2011 ONE YEAR CORPORATE SCORECARD (SDBIP) DRAFT 3rd QUARTER PROGRESS REPORT ON CORPORATE PERFORMANCE Rating Key: LINK TO LEAD DIRECTORATE ~ 'l - Currently does not meet target ; ~ - Information not available or work on hold; - Meets or exceeds target; INDICATOR ANNUAL TARGET 2010/11 RATING TARGET QUARTER ENDING 31 MARCH 2011 ~ - Original target to be amended ACTUAL QUARTER ENDING 31 MARCH 2011 REASON FOR VARIANCE REMEDIAL ACTION 841 Strategic Focus Area 7: Health, social and community development Corporate Objective: 7A. Facilitate the development of a healthy and socially inclusive society Economic & Social Development, Tourism Health 7 A.1 Number of targeted development programmes 7A.2 Number of days when air pollution exceeds WHO guidelines 20 ~ 15 27 Target exceeded Maintain the momentum 135 ~ 101 64 Target achieved Data provisional and needs to be verified. Bi-ennial target Bi-ennia! target Bi-enniaJ target Bi-ennial target Strategic Focus Area 8: Good Governance and Regulatory Refonn Corporate Objective: SA. Ensure enhanced service delivery with efficient institutional arrangements BA.1 % 'truly loyal' employees as measured by the employee culture I climate survey 34% Corporate Services BA.2 % improvement in time to finalise complaints 12% ~ ~ 9% 34% decline in improvement Decline from 9.01 days to close to 13.86 days. 34% decline in improvement. More detail analysis underway to detennine reason for underperformance Ongoing monitoring Corporate Objective: BB. Manage key financial and governance areas such as income control, cash flow, indigent support, alternative income opportunities, asset and risk management BB.2 Opinion of Auditor Genera! Unqualified audit ~ Unqualified Audit Report Audit concluded and unqualified audit opinion received Target achieved Maintain the momentum High investment rating ~ High investment rating High investment rating of Aa2.za was reconfinned during July 2010 and is still valid Target achieved Maintain the momentum ~ Annual target Annual target Annual target Annual target Finance B8.3 Opinion of independent rating agency Corporate Objective: BC. Establish effective community engagement channels Strategy and Planning BC.1 Community satisfaction (Score 1-5) 3 Page 5 3rd quarter 1011 New Corporate SDBIP Performance ScorecarclMaYCO(5).xIS ANNEXURE 8 Third Quarter Convenco Performance Assessment Report for 10111 -1 June 2010 to 31 March 2011 t, No - Meets or exceeds target; ~ . Currently does not meet target; ~ -Information not available or work on hold Indicator Annual Target 30 June 2011 Target Performance 31 March 2011 Actual performance 31 March 2011 '"c Reason for variance Remedial action ~ Target Achieved Maintain the momentum "0:• Strategic Focus Area 1 . Shared Economic Growth and Development Corporate Objective: 1A. Create an enabling environment for the economy to grow and become globally competitive. Revenue 83% Expenditure 78 % 1 % Spend Operational Budget 98% 74% 2 % Spend of Capital Budget 80% 60% 71% ~ Tarrget exceeded Maintain the momentum 3 Contribution to Gross Domestic Product R2.3 billion per annum NfA NfA f!- Annual Target Annual Target 4 International Delegate Days 200000 NfA NfA f!- Annual Target Annual Target 5 Number of jobs created 9000 NfA NfA f!- Annual Target Annual Target 6 Number of events 500 375 387 ~ Target Achieved Maintain the momentum NfA NfA f!- Annual Target Annual Target Customer Centricity and Service Excellance 7 a 9 10 75% of minimum aggragate score for all GTICG intemal departments and external suppliers Reduction of water and energy consumption 5% saving on water and energy compared to 08/09 NfA NfA f!- Annual Target Annual Target Supply Ghain Procurement from BEE suppliers measured ito of BEE Act Percentage spend not lower that 50% NfA NfA f!- Annual Target Annual Target All training costs spent on the current permanent and temporary staff Minimum 5% as a percentage of salary cost NfA NfA f!- Annual Target Annual Target ANNEXURE C Khayelitsha Community Trust Third Quarter Performance Assessment Report for 10111 • 1 July 2010 to 31 March 2011 t. No Indicator - Meets or exceeds target; Annual Target 'l .Currently does not meet target; ~ -Information not available or work on hold Target 31 March 2011 Actual performance 31 March 2011 ;'" c Reason for variance Remedial action 0: Strategic Focus Area 1 : Shared Economic Growth and Development Corporate Objective: 1A. Create an enabling environment for the economy to grow and become globally competitive. 1 % Spend Operational Budget 98% 74% 76.0% ~ Target achieved Maintain the momentum % Spend of Capital Budget 95% 72% 51% ~ Supply chain process completed with approvals however transfer of ownership not completed by end March. Procurement to be completed by end April 2011 To maintain good corporate governance 8 Trustee Meetings, 4 Audit Committee Meetings. AFS and Annual Report issued in accordance with legislated deadlines. 6 Trustee Meetings. 3 Audit Committee meeting 6 Trustee meetings; 3 Audit committee meetings ~ Target achieved Maintain the momentum Funding sourced. Business plan for Phase 1 completed. Workshop has been conducted with all stakeholders in the project incl. City of Cape Town & potential financiers. t} Funding approval delayed by the bank (RMB) which will allow for commencement with the installation of civil services. Partnership with other service providers like Cape Town Community Housing Partnership is being explored to ensure that we expedite the delivery of other subsequent phases through funding from an alternative source. 2 3 To facilitate affordable Alternative funding sourced residential development in for Housing Project by 31 KBD December 2010 4 2011105/05 ANNEXURE C Khayelitsha Community Trust Third Quarter Performance Assessment ReDort for 10/11 -1 Julv 2010 to 31 March 2011 ~ No 5 6 Indicator - Meets or exceeds target; Annual Target 'l -Currently does not meet target; ~ -Information not available or work on hold Target 31 March 2011 KCT Human and Capacitation Plan reviewed, appoint CEO & Project Manager, replace Directors Management Company as required, manage financial reporting of Investment Companies Legally compliant set of structures for KCT and its investment companies To update development and opreational and decision- making framework for KBD (initiate develpoment of retail and office space) Approve updated development plan Updated Development Plan approved Secure alternative sources of funding. Secure alternative sources of Not applicable - anuual funds for KCT, corporate target compliance requirements and Phase 2 developments by 30 June 2011 To implement a legally compliant set of structures for KeT and its investment companies 7 2011105105 Actual performance 31 March 2011 '" c ~ Reason for variance Remedial action 0: t} Amended Trust Deed to be lodged with the Master of the High Court and SARS by end April 2011 in order for all necessary registrations to be done by 30 June 2011. Amendments to the development plan were presented to the Trustees at the workshop held on 26 January 2011. Outcomes from negotiations with PRASA were still outstanding at end March 2011 t} Rescheduling of meetings by PRASA caused delay in finalising negotiations affecting KCT development plan. Meeting between KCT, the professional team and PRASA now scheduled for 11 April 2011 to finalise outstanding information on the development framework. The updated development plan that includes information from PRASA will be tabled at the Board meeting of 20 April for approval by the Trustees. Not applicable - anuual target t} Not applicable - anuual target Not applicable - anuual target Amended Trust Deed to be tabled at the 20 April 2011 Board meeting for approval by Trustees. implemented 2