Safeguarding Power in the Shaky Islands With Haywards Substation, a key component of New Zealand’s transmission network, placed on a major seismic fault line, national grid operator Transpower confronted Siemens with the strictest seismic requirements ever implemented. The ­replacement of the HVDC Pole 3 and upgrade of Pole 2 challenged all partners to find unique solutions. Text: Garry Barker Photos: Guy Frederick A multitude of AC and DC lines come in and go out of Transpower’s terraced substation built on the lush green slope of Haywards Hill near Lower Hutt, some 20 kilometers from New Zealand’s capital Wellington. S Auckland Haywards Wellington Christchurch The HVDC Inter-Island link connects the grids of the North and the South Island of New Zealand since 1965. In 2012, Pole 1 was decommissioned and in 2013 the new Pole 3 was added, together with a control ­system upgrade for Pole 2. Illustration: Mariela Bontempi Benmore ome call New Zealand the “Shaky Isles,” recognition that its two long, narrow main is­ lands straddle major fault lines in the earth’s crust. The landscape is beauti­ ful, ranging from broad green pastures and sapphire blue lakes to steep rug­ ged snow-capped mountains and wide snow-fed crystal clear rivers. But be­ neath them lies the constant threat of major earthquake activity. Christchurch, a beautiful city, the larg­ est in the South Island, was nearly destroyed by a series of disastrous earthquakes since 2010. The first quake, of magnitude 7.1 on the Mercalli scale, struck in the early morning of Sep­ tember 4, 2010. Hundreds of after­ shocks followed until a catastrophic 6.3 magnitude quake struck at mid­ day on February 22, 2011. Major city buildings collapsed, killing 185 people and leaving thousands more injured. Since then more than 11,000 quakes have occurred, most small – magni­ tude 2 or 3 – almost all around Christ­ church but recently touching the ­national capital, Wellington, on the southern tip of the North Island. It was in this most challenging environ­ ment that Siemens, under contract to Transpower, the government-owned grid management company, de­ signed, built, tested, installed and commissioned a high-voltage direct current (HVDC) state-of-the-art thy­ ristor-based converter and intercon­ nector system, capable of withstand­ ing a one-in-2,500-years earthquake event. It has an installed capability of 1,400 megawatts, of which current­ ly 1,200 megawatts are used due to the limited capacity of the submarine ­cables. The buildings and the equipment now running in the valve hall, switchyard and transformer bays at Transpower’s Haywards site, 25 miles north of Wel­ lington, and at Benmore, the hydrosubstation in the far South Island, have been built to that incredible standard. The system is unique. Andrew Gard is Transpower’s project director for the HVDC Pole 3 project and juggled the installation and testing of the new equipment in a live environment. New Zealand’s HVDC Link The project involved replacing the original Pole 1, a 49-year-old mercury arc system with a new thyristor-based Pole 3 as well as refurbishing Pole 2, installed in 1992, with a new, state-ofthe-art control system. The original interconnection consisting only of Pole 1 was rated at 270 kilovolts, 540 megawatts but underwent a major upgrade between 1987 and 1992, producing a so-called hybrid link of two poles, the existing Pole 1 and Pole 2 rated 350 kilovolts, which add­ ed 700 megawatts with modern thy­ ristor valves. u Living Energy · No. 10 | May 2014 79 Reportage A Visit at the Energy Minister’s Office in Wellington “The HVDC project just completed will support New Zealand’s security of supply far into the future.” Hon Simon Bridges, Minister of Energy and Resources Hon Simon Bridges at his office at the Beehive, Wellington’s iconic ­parliament building. On the South Island, the HVDC link begins at Benmore substation, where the hydropower collected from the surrounding lakes is transformed to DC to travel north – or, in turn, North Island power is fed into the South Island AC grid. The new Pole 3, installed by Siemens, has a continuous rating of 700 mega­ watts in both directions and, as with Pole 2, is capable of operating in ­bipole and individually in monopole configurations. The bidirectional ­design is needed because, in winter when power demands are high for heating, water stocks in the dams feeding the hydroturbines can run low; rain becomes snow and snow does not melt until spring. Then, power from the North Island’s gener­ ators – geothermal, hydro, gas, wind and the sole New Zealand coal-fired station at Huntly – is needed to meet South Island needs. Similar standards and equipment up­ grades were built into the Benmore substation in southern Canterbury where hydro output is collected and converted to DC current for transmis­ sion at 350 kilovolts over 611 kilome­ ters north to the three submarine 80 Living Energy · No. 10 | May 2014 c­ ables that carry it across the turbu­ lent Cook Strait and then on overhead lines to Haywards. There it is converted to 220 kilovolt AC for the 700-plus kilometer journey through the North Island to Auckland and beyond. If Transpower’s new system is unique, so, too, were the formidable construc­ tion and electrical engineering prob­ lems that were solved. Firstly, Haywards is a mere 300 meters from a major fault line; hence the seis­ mic standard demanded. Secondly, 50 percent of the nation’s total power is supplied by hydro generating sta­ tions in the far south of the South I­sland, but 76 percent of the 4.5 mil­ lion population lives in the North ­Island, one third of it (about 1.12 mil­ lion) in Auckland. If Haywards failed or stopped for even a few hours, the consequences for the national econo­ my and well-being would be huge. Thirdly, the existing system could not New Zealand’s energetic Minister of Energy and Re­ sources, Hon Simon Bridges, says the major upgrade to Transpower’s high-voltage transmission and control system will secure New Zealand’s electricity system for the next 20 to 30 years. be shut down while the build proceed­ ed. Concrete was poured, footings were installed and equipment con­ nected while 350,000 volts surged above the engineers and workmen. Yet not one serious accident occurred in the four years. Built to Withstand the WorstCase Scenario Dr. Günther Wanninger, the electrical engineer who headed the Siemens team in New Zealand for the four years of the project, says the seismic challenge was “the biggest we ever had to face.” “We had to apply the highest seismic standards in the design for an inter­ connect that is a major part of the New Zealand infrastructure. Recently there was an earthquake in Welling­ ton, reasonably big – magnitude 6.7 – but with the design we have applied, there was no effect at Haywards.” Security and reliability of generation and supply are not sufficiently discussed by either Government or the public, he says. “We take it for granted and don’t de­ bate it enough, but we must be sure of supply in our challenging environment. The HVDC project just com­ pleted will support New Zealand in security of sup­ ply far into the future.” u It is the largest single com­ ponent of the NZ$5 billion investment the ­Government will make in the grid over the next eight years, he says. By increasing geo­ thermal and wind genera­ tion, the Government plans to raise ­renewable supply beyond 90 percent by 2025. Ultimately, the country’s only coal-fired power sta­ tion at Huntly in the North Island will be closed. 2011, we can see population and demand growing there, too. In Christchurch we have by some measures the biggest rebuilding project in the world going on, and as that progresses and business and industry re­ develop, demand for elec­ tricity there will also grow.” “I believe our system, with about 75 percent of total generation from renewable sources, is one of the best in the world. It gives us ­many advantages,” states Bridges. Efficiency in use of energy is constantly improving and New Zealand now has more than 1 million smart me­ ters, Bridges explains. “There is also scope to im­ prove the use of electricity in transport.” “Our population is growing, particularly north of Taupo (in the center of the North Island) but, as Christchurch rebuilds after its disastrous earthquakes in 2010 and “The HVDC upgrade is a great success in terms of knowledge and skills for New Zealand,” says Simon Bridges. “Return on this in­ vestment will be good.” Benmore also had seismic challenges, a little lower than Haywards, but the same standards were applied there. “It made commercial sense for us to have a single design. The buildings are identical,” Dr. Wanninger says. Aurecon, a New Zealand company with a worldwide reputation in seismic engineering, produced new designs for lead-rubber bearings, 600 milli­ meters in diameter, and sliders, to protect the long, deep piles on which the buildings and the equipment are mounted from both vertical and horizontal movement. Now the valve hall, for example, can move up to 700 millimeters horizontally without damage in an earthquake. Everything in the switchyard is similarly isolated from shocks. “Aurecon tells me there is no build­ ing in the world that has such high seismic standards as the valve halls we have built for Transpower,” Dr. Wanninger says. “We have built for high seismic re­ quirements in California, China and Chile, but those standards were not high enough for New Zealand,” he says. “So we had to design new equip­ ment, new damper solutions, and most had to be put on a shake table in­ to which we put earthquake data for the rigorous testing we carried out. But the transformers (300 tonnes each) were too big to do that, so in parallel we made computer models and ran those with several ‘design earthquakes’ to show the equipment could withstand such forces.” Further electrical performance tests were done on-site, but because of that single-backbone configuration of the grid, testing had to be done while the grid was live. Nothing could be isolat­ ed; again, a unique problem. Project director Andrew Gard explains the smoothing reactor’s special damping system in front of the camera. 82 Living Energy · No. 10 | May 2014 Live Market Conditions Siemens designed new damper solutions for each piece of equipment and built in extra cable loops. Electrical engineer Andrew Gard, Transpower’s project director, explains the problem: “New Zealand operates a market system determined by sup­ ply and demand, governing price and source of the power. Siemens at the fac­ “There is no building in the world that has such high seismic standards as the valve halls we have built for Transpower.” Dr. Günther Wanninger, Siemens tory in Germany tested every scenario – 1,500 tests over ten months testing the control system to its limits. We could not do that on the grid; it would take years. So we chose a representa­ tive sample to test the boundaries of those factory tests in the live environ­ ment – about 190 tests. “Test plans had to be written for each of those and submitted for approval from the Transpower grid manager. The plans went back and forth and a security analysis was done on the proposed test for the day, because grid conditions vary, day to day, hour to hour,” Mr. Gard says. u Living Energy · No. 10 | May 2014 83 Reliable power supply keeps the lights on in “the coolest little capital in the world.” Wellington is New Zealand’s political center, its second-largest city and an important hub for the country’s world-famous film industry. 84 Living Energy · No. 10 | May 2014 But it was not just a matter of starting a test. Electricity flows had to be jug­ gled within the market. A test might require 500 megawatts to go south for an hour or two, but the market might want to send 800 megawatts north. “So we set up our own market trading team,” Mr. Gard says. Flow on the grid changes as market traders do deals minute by minute to get best prices and meet demand. So, the test team’s traders had to pay to control and, in effect, distort the market and get the flows needed for some of the testing. They had to check that no maintenance was in train and no AC transmission con­ straint that might block the flow. “You are just juggling everything – maintenance, generator situation, and so on – two or three hours before the test,” he says. “Some tests took a few minutes, but the average dura­ tion was half an hour to an hour.” Transpower’s chief executive Patrick Strange monitored the tests and the cost. “We probably spent NZ$20 mil­ lion to achieve the flows we wanted,” he says. “It was a world first. We were nervous about doing it, but we couldn’t see any other way, and it was successful. It was a new experience for Siemens, too, but they came to the party and between us we achieved the results we wanted.” u “We set up our own ­market trading team.” Andrew Gard, Project Director HVDC Pole 3 Living Energy · No. 10 | May 2014 85 Reportage Reportage Engineered for Highest ­Seismic Requirements New Zealand Facts and Figures The HVDC Inter-Island Link From Benmore substation on the South Island the HVDC line travels 534 km overland to Fighting Bay in the Marlborough Sounds area. 3 x 350 kV/500 MW submarine cables of 40 km length bridge the Cook Strait from Fighting Bay to Oteranga Bay on the southern tip of the North Island. Further 37 km of HVDC line continue from Oteranga Bay to Haywards substation near Lower Hutt. The upgrade increased the HVDC link capacity by more than 70% from 700 MW to currently 1,200 MW. The technology is future-proofed to boost capacity to 1,400 MW. New Zealand’s electricity generation by fuel type (2011) New Zealand’s electricity demand by region (2011) North Island (Auckland and Northland) Other Thermal 0.1 % Bioenergy 1.3 % 28 % Auckland North Island (Other) Hamilton Tauranga Wind 4.5 % 34 % Coal 4.7 % Geothermal 13.4 % Wellington Gas 18.4 % Hydro 57.6 % Christchurch Dunedin South Island 37 % Source: Energy Data File, 2011 Calendar Year Edition Award-winning filmmaker Gerard Smyth takes you on a visually stunning journey along the backbone of New Zealand’s transmission system as raindrops feed rivers on the South Island, lakes generate power and HVDC travels over land and sea to the North Island. siemens.com/living-energy/pole3 Living Energy at 86 Living Energy · No. 10 | May 2014 Minister of Energy and Resources Hon Simon Bridges says that New Zealand aims to push renewable out­ put above 90 percent of national needs, raising geothermal output from the current 14 percent to above 20 percent and doubling wind gener­ ation, now at 4.5 percent, over the next decade to 15 years. “And it is all based on strong market principles, not supported by government subsi­ dies,” he says. New Zealand’s HVDC project was a huge challenge for everyone involved, from the Siemens and Transpower engineers and site technicians to the construction and transport teams and the principals who took responsi­ bility for the venture’s success. “This is the first of its kind and some­ thing nobody has done before,” Dr. Wanninger says. “So now, we have equipment certified to these extreme­ ly high levels. We will see if anyone will ever ask again for such high re­ quirements. Maybe Japan in the fu­ ture after their recent earthquakes. We are now building on a platform in the North Sea and that also is very challenging. Siemens is prepared to take up any challenge and we never give up. When we commit to a project we will finish it, whatever the chal­ lenges, and that is good for me as an engineer.” Transpower CEO Patrick Strange, who oversaw the four-year project, has the last word: “We chose Siemens because we know the quality of their work. They don’t know how to build bad products. They build to very high standards and take great pride in their engineering. We were confident Siemens would build very high-quali­ ty equipment and systems and we were right. Transpower and Siemens can be very pleased and satisfied with what has been achieved.” p Patrick Strange was CEO of Transpower until end of January 2014 and can look back on the successful completion of one of the largest infrastructure projects in New Zealand’s recent history. “Transpower and Siemens can be very pleased and satisfied with what has been achieved.” Patrick Strange, Transpower CEO from 2007 to 2014 Garry Barker is a technology editor at The Age newspaper in Melbourne, and has worked as a foreign correspondent in over 50 countries. Living Energy · No. 10 | May 2014 87